Summary
 SAP Functional Consultant – Project Systems, Plant and Maintenance and Document
Management System Consultant
 Over 4 years of strong industry experience in Projects and 2.8 year of SAP reimplementation,
system study and end to end implementation projects.
 Expertise in SAP (PS Module) ,PM and DMS entailing business process analysis & design, GAP
Analysis, integration with other modules and training, A starter with PM module handling basic
configuration, UAT , end user trainings and master data creation.
 A Document Management consultant working with data management required as per business
which includes data upload, approvals and object links.
Visa Information
Country Visa Type Valid Till
INDIA NA NA
Technical Expertise
Technology /
Classification
ERP
Primary Skills
Experienc
e
(Months)
Secondary Skills
Experienc
e
(Months)
Utkarsh Saxena
SAP PS 32+
PS Domain 48+
Additional Skills
Education
Degree Qualification
College / University /
Institution
Year of
Passing
Bachelors
B. Tech ( Electronics
&Instrumentation)
Hindustan College Of Science &
Technology
2009
Professional Activities, Certifications & Training attended
Course / Certification
Name
Institution Year Duration
Attended Tri Robotics
workshop conducted by IIT
Mumbai
TRI 2010
Attended the NATIONAL
CONFERENCE on ‘’
HOUSEHOLD WATER
TREATMENT
TECHNOLOGIES’’ & also
presented a paper titled ‘’
ROLE OF ELECTRONICS IN
WATER TREATMENT’’
SGI 2010
Engagement Overview
Project Name Project Sath Sath
Start
Date
May 2015
Client India Today Group End Till Date
Page 2
Utkarsh Saxena
Date
Project
Location
Noida, India
Team Size handled (If
applicable)
Project Description:
Implementation of Plant & Maintenance & Document Management System
Role / Responsibilities
Consultant (Plant & Maintenance & Document Management
System
 As a PM consultant I have done following activities :
• Business Process Study
• Training to the Key Users and Integration testing Team Members
• Conducting Pre UAT training and testing the system fitment as per client requirement.
• Analyzing and Mapping the gaps between Business blue print document and System
Configuration.
• Testing of Z-Developments and standard Sap Process.
 As a DMS consultant I have done following activities :
• Gathering Business Requirements.
• Designing & Mapping of DMS System as per client’s requirements.
• Configuration of DMS which includes Document types, Status, Object Links, Storing Documents
using Archive Link, Identification of Business Objects for establishing Archive link etc.
• Training to the Key Users and Integration testing Team Members
• Conducting Pre UAT training and testing the system fitment as per client requirement.
• Creating a document for the control, security and authorization of various documents
Project Name Trinity Touch
Start
Date
July2015
Client Trinity Touch
End
Date
Till Date
Project
Location
Delhi, India
Team Size handled (If
applicable)
Project Description:
• Implementation of Project Systems
Role / Responsibilities Project Systems Consultant
Page 3
Utkarsh Saxena
Contribution:
• Business Process Study
• Preparation of the Business Blue Print document and analyzing the gaps.
Project Name Jindal Steels
Start
Date
Nov 2014
Client Jindal Steels
End
Date
Dec 2014
Project
Location
Delhi,India
Team Size handled (If
applicable)
Project Description:
The project vision was to analyze existing sap system and to provide solution for the betterment.
Role / Responsibilities SAP PS – Consultant.
Contribution:
• Studied the complete system of Sap.
• Preparation of document and analyzing the gaps.
• Study and analyze the integration aspects of PS with other modules.
• Provided post Go Live support for PS modules
Project Name Project Amal
Start
Date
Sep 2013
Client Value Infra
End
Date
July 2014
Project
Location
Noida, India
Team Size handled (If
applicable)
The project vision was to achieve process integration to the maximum possible extent and provide
the business a single integrated information platform spanning across multiple geographies. This
was expected to provide the business leaders a strong enabler to fulfill their business vision and
mission.
Role / Responsibilities Sap PS and DMS Consultant
Contribution:
Page 4
Utkarsh Saxena
 As a PS consultant I have done following activities :
• Business Process Study
• Preparation of the Business Blue Print document and analyzing the gaps.
• Analyzing the business of client and requirements analysis so as to design solutions to streamline
client business processes.
• Study and analyze the integration aspects of PS with other modules
• Preparation of Business Blue Print Document
• Training to the Key Users and Integration testing Team Members
• Preparation of Functional Specification documents for Z developments and Z reports
• Used Project Builder to create and edit WBS and networks in an integrated environment &
individually. Also designed & implemented various views (detail/overviews), graphics & project board
planning for quick & efficient planning and decision making.
Worked on Project costing
• Defined various user statuses in the status profile in Customizing – Project Definition, WBS element,
Network Header & Network Activity for various task’s processing stage like Task outstanding, Take
released, Task completed or Task Successful.
• Worked on Budgeting, Planning, and availability control for Investment and customer project
• Worked on PS budgeting, carry forward budget release and transfer budget.
• .Planned and monitored material requirements and costs to regulate and schedule the flow of
materials.
Executed Budgeting and Availability Control for Project.
• Maintained dates in Project System relating to basic or forecast dates, actual dates, scheduled
dates, earliest & latest dates and constraints.
• Integration with Production Planning for creating production related scenarios.
• Integration with SD for billing of projects.
• Post Go Live Support.
• User Training, user manual preparation and Onsite and Offshore Post Go-Live Support.
 As a DMS consultant I have done following activities :
• Gathering Business Requirements.
• Designing & Mapping of DMS System as per client’s requirements.
• Configuration of DMS which includes Document types, Status, Object Links etc.
• Training to the Key Users and Integration testing Team Members
• Conducting Pre UAT training and testing the system fitment as per client requirement.
• Creating a document for the control, security and authorization of various documents
Project Name PCI
Start
Date
August
2013
Client PCI
End
Date
Sep 2013
Project
Location
Gurgaon, India
Team Size handled (If
applicable)
Page 5
Utkarsh Saxena
Project Description:
Project Systems Implementation Project.
Role / Responsibilities SAP PS Consultant
Contribution:
• Analyzing the business of client and requirements analysis so as to design solutions to streamline
client business processes
• Study and analyze the integration aspects of PS with other modules.
• Configured and mapped the business process.
• Preparation of Business Blue Print Document
Project Name Acme Tele Power
Start
Date
May 2013
Client Acme Tele Power
End
Date
June 2013
Project
Location
Gurgaon,India
Team Size handled (If
applicable)
Project Description:
Reimplementation of SAP all Modules
Role / Responsibilities SAP Project Systems Consultant
Contributions
• Providing training to users
• Testing of Z-Developments and standard Sap Process
Project Name -
Start
Date
April 2013
Client Sakha Engineers Pvt Ltd
End
Date
June 2012
Project
Location
Gurgaon- India
Team Size handled (If
applicable)
Role / Responsibilities Assistant Manager Planning and Marketing
Contribution:
• Responsible for the preparation of plans and schedules, designing that are required to manage the
project (LPG ,CNG and PNG Reticulated System) and attain target dates.
Page 6
Utkarsh Saxena
• Micro planning of each activity approved in budget, suggestion to Q.S. to increase billing of client,
finalization of materials in time as per micro plan& advance forecasting of machinery & material.
• Checking time cycle of various activities to cut down execution cost, planning regarding delayed
works, establishing root cause for slip & providing solutions.
• Planning of all three Ms i.e. Machinery, Manpower and Material as per ISO standards.
• Guiding planning engineer’s preliminary, pre-final, final construction schedule & Master schedule
which includes cad drawings.
• Identifying variation & extra scope of work and communicate the same to
client/consultant/execution team.
• Preparing Schedules, Monitoring & Tracking of construction schedule & highlighting anticipated
delays.
• Compare actual progress of work with all parameters i.e. physical, financial, time wise & contract
wise and analyze the data for identification of prospective claims
• Elaborate and revise Project scheduling procedures and documents in close co-operation with the
Project Manager, Tender/contract preparation, and correspondence as per standards
Project Name
Start &
End
Date
June 2009
to Aug
2010 &
Aug 2011
to June
2012
Client Goyal MG Gases Pvt Ltd
Project
Location
New Delhi,India
Team Size handled (If
applicable)
Role / Responsibilities Assistant Manager Planning and Maintenance
Contributions
• Planning:-
• Develop, update and maintain schedule data to ensure project consistency and Optimization.
• Ensure contractors provide resource loaded schedules at determined intervals to make sure
construction is being completed on time and within budget.
• Create and maintain project capital and non-capital spending plan as per BOQ..
• Create and maintaining project plan, Analyzes variances in cost and schedule performance against
the plan, and communicates the reasons for the issuance of variance.
• Maintenance:-
• Planning and Procurement of wind mill spares for periodic preventive maintenance.
• Progress Reporting, Contracts Enforcement and Material Tracking.
• Planning for Annual/Half yearly/Monthly preventive maintenance and Procurement of spares.
• Strategic vendor classification and scheduling.
• Forecast of requirements and creation of database of vendors.
• Evaluation of offers and Cost Estimation as per the technical competence.
Page 7
Utkarsh Saxena
• Planning and executing maintenance practices along with routine maintenance.
• Custodian of Generation tables, MSDs, etc for all sites in State (current + future sites).
• Coordination with CTO & Projects Installation.
• Develop & maintain MIS for Wind & Land data
• Co-ordination with TNEB for shut downs and monthly invoice submission.
Project Name -
Start
Date
Aug 2010
Client A2Z Maintenance and Engineering Services
End
Date
July 2011
Project
Location
Gurgaon- India
Team Size handled (If
applicable)
Role / Responsibilities Engineer Planning
Contribution:
• Maintains the established project cost/schedule program and prepares schedule/cost status reports
• Checking contractor bills and also all the statutory requirements in consultation with Project
Manager and other Site Engineers.
• Monitor and track the progress of the project against planned and establish progress status,
planned vs actual with deviation and what if analysis.
Foreign Languages Known
English
Page 8

Weitere ähnliche Inhalte

Was ist angesagt?

Dani Wang Resume_CBAP_PMP_SCJP_PM_Updated_1
Dani Wang Resume_CBAP_PMP_SCJP_PM_Updated_1Dani Wang Resume_CBAP_PMP_SCJP_PM_Updated_1
Dani Wang Resume_CBAP_PMP_SCJP_PM_Updated_1
Dani Wang
 
Arber Laura Resume June 2012
Arber Laura Resume June 2012Arber Laura Resume June 2012
Arber Laura Resume June 2012
Laura Arber, PMP
 
Dinesh_Deshpande_9Yrs_Exp_Informatica
Dinesh_Deshpande_9Yrs_Exp_InformaticaDinesh_Deshpande_9Yrs_Exp_Informatica
Dinesh_Deshpande_9Yrs_Exp_Informatica
Dinesh Deshpande
 
Patricia R. Smogor_v6
Patricia R. Smogor_v6Patricia R. Smogor_v6
Patricia R. Smogor_v6
Patti Smogor
 
Usharani R - CV
Usharani R - CVUsharani R - CV
Usharani R - CV
Usha Rani
 
Rich Bendis Resume1
Rich Bendis Resume1Rich Bendis Resume1
Rich Bendis Resume1
Rich Bendis
 
CMAD Group Workbook 3.2 Op Model Enable
CMAD Group Workbook 3.2 Op Model EnableCMAD Group Workbook 3.2 Op Model Enable
CMAD Group Workbook 3.2 Op Model Enable
Alexander Doré
 

Was ist angesagt? (18)

2013-03-14 Professional Services Seminar
2013-03-14 Professional Services Seminar2013-03-14 Professional Services Seminar
2013-03-14 Professional Services Seminar
 
Geetha 6 yrs cv_july-2016
Geetha 6 yrs cv_july-2016Geetha 6 yrs cv_july-2016
Geetha 6 yrs cv_july-2016
 
Services and Tools, DutchSoft
Services and Tools, DutchSoftServices and Tools, DutchSoft
Services and Tools, DutchSoft
 
Dani Wang Resume_CBAP_PMP_SCJP_PM_Updated_1
Dani Wang Resume_CBAP_PMP_SCJP_PM_Updated_1Dani Wang Resume_CBAP_PMP_SCJP_PM_Updated_1
Dani Wang Resume_CBAP_PMP_SCJP_PM_Updated_1
 
Arber Laura Resume June 2012
Arber Laura Resume June 2012Arber Laura Resume June 2012
Arber Laura Resume June 2012
 
Dinesh_Deshpande_9Yrs_Exp_Informatica
Dinesh_Deshpande_9Yrs_Exp_InformaticaDinesh_Deshpande_9Yrs_Exp_Informatica
Dinesh_Deshpande_9Yrs_Exp_Informatica
 
Tanushree
TanushreeTanushree
Tanushree
 
Want More Out of your SharePoint Environment? Extend your SharePoint Environm...
Want More Out of your SharePoint Environment? Extend your SharePoint Environm...Want More Out of your SharePoint Environment? Extend your SharePoint Environm...
Want More Out of your SharePoint Environment? Extend your SharePoint Environm...
 
Patricia R. Smogor_v6
Patricia R. Smogor_v6Patricia R. Smogor_v6
Patricia R. Smogor_v6
 
Ramakrishna_Profile
Ramakrishna_ProfileRamakrishna_Profile
Ramakrishna_Profile
 
Usharani R - CV
Usharani R - CVUsharani R - CV
Usharani R - CV
 
Sap bi consultant_ajay
Sap bi consultant_ajaySap bi consultant_ajay
Sap bi consultant_ajay
 
Noor-Res
Noor-ResNoor-Res
Noor-Res
 
Bi methodology
Bi methodologyBi methodology
Bi methodology
 
Resume abhishek deloitte_informatica
Resume abhishek deloitte_informaticaResume abhishek deloitte_informatica
Resume abhishek deloitte_informatica
 
Rich Bendis Resume1
Rich Bendis Resume1Rich Bendis Resume1
Rich Bendis Resume1
 
What's new in BABoK 3.0?
What's new in BABoK 3.0?What's new in BABoK 3.0?
What's new in BABoK 3.0?
 
CMAD Group Workbook 3.2 Op Model Enable
CMAD Group Workbook 3.2 Op Model EnableCMAD Group Workbook 3.2 Op Model Enable
CMAD Group Workbook 3.2 Op Model Enable
 

Ähnlich wie PS_PM_DMS_Utkarsh

Jigna Ganatra Resume
Jigna Ganatra ResumeJigna Ganatra Resume
Jigna Ganatra Resume
Jigna Ganatra
 
Cover letter _CV (1)
Cover letter _CV (1)Cover letter _CV (1)
Cover letter _CV (1)
Deepa Prabhu
 

Ähnlich wie PS_PM_DMS_Utkarsh (20)

Hrishikesh_Resume
Hrishikesh_ResumeHrishikesh_Resume
Hrishikesh_Resume
 
Experience of 8 yrs in IT Infrastructure Operation as lead
Experience of 8 yrs in IT Infrastructure Operation as leadExperience of 8 yrs in IT Infrastructure Operation as lead
Experience of 8 yrs in IT Infrastructure Operation as lead
 
Yuvraj singh CV
Yuvraj singh CVYuvraj singh CV
Yuvraj singh CV
 
Jigna Ganatra Resume
Jigna Ganatra ResumeJigna Ganatra Resume
Jigna Ganatra Resume
 
Bridget Milton Resume
Bridget Milton ResumeBridget Milton Resume
Bridget Milton Resume
 
resume_Biswajit1
resume_Biswajit1resume_Biswajit1
resume_Biswajit1
 
Trusha_Kanani_CV
Trusha_Kanani_CVTrusha_Kanani_CV
Trusha_Kanani_CV
 
Jai Dinesh Babu_Resume
Jai Dinesh Babu_ResumeJai Dinesh Babu_Resume
Jai Dinesh Babu_Resume
 
Business analyst / CV
Business analyst / CVBusiness analyst / CV
Business analyst / CV
 
Profile Sumana_Sen
Profile Sumana_SenProfile Sumana_Sen
Profile Sumana_Sen
 
Kajari_Resume
Kajari_ResumeKajari_Resume
Kajari_Resume
 
Sayyed Shahood Resume
Sayyed Shahood ResumeSayyed Shahood Resume
Sayyed Shahood Resume
 
Jitendra pattnaik
Jitendra pattnaikJitendra pattnaik
Jitendra pattnaik
 
Joginder Singh_SL
Joginder Singh_SLJoginder Singh_SL
Joginder Singh_SL
 
ShaileshKumarPM
ShaileshKumarPMShaileshKumarPM
ShaileshKumarPM
 
DPTripathy_Profile
DPTripathy_ProfileDPTripathy_Profile
DPTripathy_Profile
 
Resume
ResumeResume
Resume
 
Technical Webinar: By the (Play) Book: The Agile Practice at OutSystems
Technical Webinar: By the (Play) Book: The Agile Practice at OutSystemsTechnical Webinar: By the (Play) Book: The Agile Practice at OutSystems
Technical Webinar: By the (Play) Book: The Agile Practice at OutSystems
 
Cover letter _CV (1)
Cover letter _CV (1)Cover letter _CV (1)
Cover letter _CV (1)
 
JC_Gabuya_Resume
JC_Gabuya_ResumeJC_Gabuya_Resume
JC_Gabuya_Resume
 

PS_PM_DMS_Utkarsh

  • 1. Utkarsh Saxena Email:-jobs.utkarsh@yahoo.in Contact:-+919871449801 Candidate Name Utkarsh Saxena Emp ID S0036 Summary  SAP Functional Consultant – Project Systems, Plant and Maintenance and Document Management System Consultant  Over 4 years of strong industry experience in Projects and 2.8 year of SAP reimplementation, system study and end to end implementation projects.  Expertise in SAP (PS Module) ,PM and DMS entailing business process analysis & design, GAP Analysis, integration with other modules and training, A starter with PM module handling basic configuration, UAT , end user trainings and master data creation.  A Document Management consultant working with data management required as per business which includes data upload, approvals and object links. Visa Information Country Visa Type Valid Till INDIA NA NA Technical Expertise Technology / Classification ERP Primary Skills Experienc e (Months) Secondary Skills Experienc e (Months)
  • 2. Utkarsh Saxena SAP PS 32+ PS Domain 48+ Additional Skills Education Degree Qualification College / University / Institution Year of Passing Bachelors B. Tech ( Electronics &Instrumentation) Hindustan College Of Science & Technology 2009 Professional Activities, Certifications & Training attended Course / Certification Name Institution Year Duration Attended Tri Robotics workshop conducted by IIT Mumbai TRI 2010 Attended the NATIONAL CONFERENCE on ‘’ HOUSEHOLD WATER TREATMENT TECHNOLOGIES’’ & also presented a paper titled ‘’ ROLE OF ELECTRONICS IN WATER TREATMENT’’ SGI 2010 Engagement Overview Project Name Project Sath Sath Start Date May 2015 Client India Today Group End Till Date Page 2
  • 3. Utkarsh Saxena Date Project Location Noida, India Team Size handled (If applicable) Project Description: Implementation of Plant & Maintenance & Document Management System Role / Responsibilities Consultant (Plant & Maintenance & Document Management System  As a PM consultant I have done following activities : • Business Process Study • Training to the Key Users and Integration testing Team Members • Conducting Pre UAT training and testing the system fitment as per client requirement. • Analyzing and Mapping the gaps between Business blue print document and System Configuration. • Testing of Z-Developments and standard Sap Process.  As a DMS consultant I have done following activities : • Gathering Business Requirements. • Designing & Mapping of DMS System as per client’s requirements. • Configuration of DMS which includes Document types, Status, Object Links, Storing Documents using Archive Link, Identification of Business Objects for establishing Archive link etc. • Training to the Key Users and Integration testing Team Members • Conducting Pre UAT training and testing the system fitment as per client requirement. • Creating a document for the control, security and authorization of various documents Project Name Trinity Touch Start Date July2015 Client Trinity Touch End Date Till Date Project Location Delhi, India Team Size handled (If applicable) Project Description: • Implementation of Project Systems Role / Responsibilities Project Systems Consultant Page 3
  • 4. Utkarsh Saxena Contribution: • Business Process Study • Preparation of the Business Blue Print document and analyzing the gaps. Project Name Jindal Steels Start Date Nov 2014 Client Jindal Steels End Date Dec 2014 Project Location Delhi,India Team Size handled (If applicable) Project Description: The project vision was to analyze existing sap system and to provide solution for the betterment. Role / Responsibilities SAP PS – Consultant. Contribution: • Studied the complete system of Sap. • Preparation of document and analyzing the gaps. • Study and analyze the integration aspects of PS with other modules. • Provided post Go Live support for PS modules Project Name Project Amal Start Date Sep 2013 Client Value Infra End Date July 2014 Project Location Noida, India Team Size handled (If applicable) The project vision was to achieve process integration to the maximum possible extent and provide the business a single integrated information platform spanning across multiple geographies. This was expected to provide the business leaders a strong enabler to fulfill their business vision and mission. Role / Responsibilities Sap PS and DMS Consultant Contribution: Page 4
  • 5. Utkarsh Saxena  As a PS consultant I have done following activities : • Business Process Study • Preparation of the Business Blue Print document and analyzing the gaps. • Analyzing the business of client and requirements analysis so as to design solutions to streamline client business processes. • Study and analyze the integration aspects of PS with other modules • Preparation of Business Blue Print Document • Training to the Key Users and Integration testing Team Members • Preparation of Functional Specification documents for Z developments and Z reports • Used Project Builder to create and edit WBS and networks in an integrated environment & individually. Also designed & implemented various views (detail/overviews), graphics & project board planning for quick & efficient planning and decision making. Worked on Project costing • Defined various user statuses in the status profile in Customizing – Project Definition, WBS element, Network Header & Network Activity for various task’s processing stage like Task outstanding, Take released, Task completed or Task Successful. • Worked on Budgeting, Planning, and availability control for Investment and customer project • Worked on PS budgeting, carry forward budget release and transfer budget. • .Planned and monitored material requirements and costs to regulate and schedule the flow of materials. Executed Budgeting and Availability Control for Project. • Maintained dates in Project System relating to basic or forecast dates, actual dates, scheduled dates, earliest & latest dates and constraints. • Integration with Production Planning for creating production related scenarios. • Integration with SD for billing of projects. • Post Go Live Support. • User Training, user manual preparation and Onsite and Offshore Post Go-Live Support.  As a DMS consultant I have done following activities : • Gathering Business Requirements. • Designing & Mapping of DMS System as per client’s requirements. • Configuration of DMS which includes Document types, Status, Object Links etc. • Training to the Key Users and Integration testing Team Members • Conducting Pre UAT training and testing the system fitment as per client requirement. • Creating a document for the control, security and authorization of various documents Project Name PCI Start Date August 2013 Client PCI End Date Sep 2013 Project Location Gurgaon, India Team Size handled (If applicable) Page 5
  • 6. Utkarsh Saxena Project Description: Project Systems Implementation Project. Role / Responsibilities SAP PS Consultant Contribution: • Analyzing the business of client and requirements analysis so as to design solutions to streamline client business processes • Study and analyze the integration aspects of PS with other modules. • Configured and mapped the business process. • Preparation of Business Blue Print Document Project Name Acme Tele Power Start Date May 2013 Client Acme Tele Power End Date June 2013 Project Location Gurgaon,India Team Size handled (If applicable) Project Description: Reimplementation of SAP all Modules Role / Responsibilities SAP Project Systems Consultant Contributions • Providing training to users • Testing of Z-Developments and standard Sap Process Project Name - Start Date April 2013 Client Sakha Engineers Pvt Ltd End Date June 2012 Project Location Gurgaon- India Team Size handled (If applicable) Role / Responsibilities Assistant Manager Planning and Marketing Contribution: • Responsible for the preparation of plans and schedules, designing that are required to manage the project (LPG ,CNG and PNG Reticulated System) and attain target dates. Page 6
  • 7. Utkarsh Saxena • Micro planning of each activity approved in budget, suggestion to Q.S. to increase billing of client, finalization of materials in time as per micro plan& advance forecasting of machinery & material. • Checking time cycle of various activities to cut down execution cost, planning regarding delayed works, establishing root cause for slip & providing solutions. • Planning of all three Ms i.e. Machinery, Manpower and Material as per ISO standards. • Guiding planning engineer’s preliminary, pre-final, final construction schedule & Master schedule which includes cad drawings. • Identifying variation & extra scope of work and communicate the same to client/consultant/execution team. • Preparing Schedules, Monitoring & Tracking of construction schedule & highlighting anticipated delays. • Compare actual progress of work with all parameters i.e. physical, financial, time wise & contract wise and analyze the data for identification of prospective claims • Elaborate and revise Project scheduling procedures and documents in close co-operation with the Project Manager, Tender/contract preparation, and correspondence as per standards Project Name Start & End Date June 2009 to Aug 2010 & Aug 2011 to June 2012 Client Goyal MG Gases Pvt Ltd Project Location New Delhi,India Team Size handled (If applicable) Role / Responsibilities Assistant Manager Planning and Maintenance Contributions • Planning:- • Develop, update and maintain schedule data to ensure project consistency and Optimization. • Ensure contractors provide resource loaded schedules at determined intervals to make sure construction is being completed on time and within budget. • Create and maintain project capital and non-capital spending plan as per BOQ.. • Create and maintaining project plan, Analyzes variances in cost and schedule performance against the plan, and communicates the reasons for the issuance of variance. • Maintenance:- • Planning and Procurement of wind mill spares for periodic preventive maintenance. • Progress Reporting, Contracts Enforcement and Material Tracking. • Planning for Annual/Half yearly/Monthly preventive maintenance and Procurement of spares. • Strategic vendor classification and scheduling. • Forecast of requirements and creation of database of vendors. • Evaluation of offers and Cost Estimation as per the technical competence. Page 7
  • 8. Utkarsh Saxena • Planning and executing maintenance practices along with routine maintenance. • Custodian of Generation tables, MSDs, etc for all sites in State (current + future sites). • Coordination with CTO & Projects Installation. • Develop & maintain MIS for Wind & Land data • Co-ordination with TNEB for shut downs and monthly invoice submission. Project Name - Start Date Aug 2010 Client A2Z Maintenance and Engineering Services End Date July 2011 Project Location Gurgaon- India Team Size handled (If applicable) Role / Responsibilities Engineer Planning Contribution: • Maintains the established project cost/schedule program and prepares schedule/cost status reports • Checking contractor bills and also all the statutory requirements in consultation with Project Manager and other Site Engineers. • Monitor and track the progress of the project against planned and establish progress status, planned vs actual with deviation and what if analysis. Foreign Languages Known English Page 8