GDAS PM Professions:
PMP Study Group
                                           Session #10: Risk Management




Monique Howard
January 8, 2009

© 2005 Hewlett-Packard Development Company, L.P.
The information contained herein is subject to change without notice
1.   In your project, you can use all the following tools and techniques for risk response
     planning EXCEPT:

1.   Strategies for negative risks or threats
2.   Contingent response planning
3.   Strategy for threat and opportunities
4.   Strategy for residual risks
1.   In your project, you can use all the following tools and techniques for risk response
     planning EXCEPT:

1.   Strategies for negative risks or threats
2.   Contingent response planning
3.   Strategy for threat and opportunities
4.   Strategy for residual risks




Correct Choice: 4

Justification:   Figure 11-14

Reference: PMBOK Third Edition, Page Number: 260
2. You are the project manager in an automobile manufacturing company. A vendor was
    sending you the machine parts required in your manufacturing process,but the parts did
    not reach in time because of heavy rains. You had anticipated this risk and planned for it in
    your risk response plan. So, as per your risk response plan, you started using machine
    parts which had been supplied one year ago and were not utilized at that time. However,
    this has subjected your project to a new risk - that the machine parts which were not used
    for one year might be having higher level of defects.

This new risk can also be called:
1. Unidentifiable Risk
2. Unmanageable Risk
3. Secondary Risk
4. Residual Risk
2. You are the project manager in an automobile manufacturing company. A vendor was
    sending you the machine parts required in your manufacturing process,but the parts did
    not reach in time because of heavy rains. You had anticipated this risk and planned for it in
    your risk response plan. So, as per your risk response plan, you started using machine
    parts which had been supplied one year ago and were not utilized at that time. However,
    this has subjected your project to a new risk - that the machine parts which were not used
    for one year might be having higher level of defects.

This new risk can also be called:
1. Unidentifiable Risk
2. Unmanageable Risk
3. Secondary Risk
4. Residual Risk



Correct Choice: 3

Justification:   Secondary risks that arise as a direct outcome of implementing a risk response.

Reference: PMBOK Third Edition, Page Number: 264
3. In your project, you have identified important risks, and planned appropriate responses to the
       risks. Some risks e.g. possibility of natural disasters have been documented and accepted
       in your risk management plan. If there are risks that remain after you have taken these
       steps, then such risks are called:

1.   Unidentifiable Risks
2.   Residual Risks
3.   Secondary Risks
4.   Accepted Risks
4. Risk Management Planning is the process of deciding how to approach and plan the risk
    management activities for a project. It is important to plan for the risk management
    processes that follow to ensure that the level, type, and visibility of risk management are
    commensurate with both the risk and importance of the project to the organization. The
    output of Risk Management Planning is:

1.   Risks
2.   Risk Management Plan
3.   Risk Ranking of the Project
4.   Planning Meetings
3. In your project, you have identified important risks, and planned appropriate responses to the
       risks. Some risks e.g. possibility of natural disasters have been documented and accepted
       in your risk management plan. If there are risks that remain after you have taken these
       steps, then such risks are called:

1.    Unidentifiable Risks
2.    Residual Risks
3.    Secondary Risks
4.    Accepted Risks




Correct Choice: 2

Justification: Residual risks that are expected to remain after planned responses have been taken, as well as those which have
been deliberately accepted.

Reference: PMBOK Third Edition, Page Number: 264
4. Risk Management Planning is the process of deciding how to approach and plan the risk
    management activities for a project. It is important to plan for the risk management
    processes that follow to ensure that the level, type, and visibility of risk management are
    commensurate with both the risk and importance of the project to the organization. The
    output of Risk Management Planning is:

1.   Risks
2.   Risk Management Plan
3.   Risk Ranking of the Project
4.   Planning Meetings



Correct Choice: 2

Justification:   Figure 11-3

Reference: PMBOK Third Edition, Page Number: 242
5. In your project, you have identified a list of identified risks, a list of potential responses
     and root causes of risks. You should document this information in the :

1.   Risk Management Plan
2.   Risk Database
3.   Project Plan
4.   Risk Register
5. In your project, you have identified a list of identified risks, a list of potential responses
     and root causes of risks. You should document this information in the :

1.   Risk Management Plan
2.   Risk Database
3.   Project Plan
4.   Risk Register




 Correct Choice:      4

 Justification:    The risk register includes a list of identified risks, a list of potential responses, root causes of risk, and updated risk
 categories.

 Reference: PMBOK Third Edition, Page Number: 249
6. Risk management helps in maximizing the probability and consequences of positive
    events and minimizing the probability and consequences of adverse events to project
    objectives. Risk Response Planning helps in this context because it:

1.   helps in deciding how to approach and plan the risk management activities.
2.   develops procedures and techniques to enhance opportunities and reduce threats to project
     objectives.
3.   determines which risks might affect the project and documents their characteristics.
4.   monitors residual risks, identifies new risks and executes risk reduction plans.
6. Risk management helps in maximizing the probability and consequences of positive
    events and minimizing the probability and consequences of adverse events to project
    objectives. Risk Response Planning helps in this context because it:

1.   helps in deciding how to approach and plan the risk management activities.
2.   develops procedures and techniques to enhance opportunities and reduce threats to project
     objectives.
3.   determines which risks might affect the project and documents their characteristics.
4.   monitors residual risks, identifies new risks and executes risk reduction plans.



Correct Choice:     2

Justification:    Risk response planning - developing options and actions to enhance opportunities, and reducing threats to project
objectives.

Reference: PMBOK Third Edition, Page Number: 237

pmstudy.com comments:
* Option 1: This is Risk Management Planning
* Option 3: This is Risk Identification
* Option 4: This is Risk Monitoring and Control
7. Utility function is a commonly used technique to find out the tolerance of a project manager
    towards risk. Some project managers are more averse to risk than others. All of the
    following are different classifications of tolerance for risk EXCEPT:

1.   Risk Averter
2.   Risk Seeker
3.   Risk Mitigator
4.   Risk Neutral
7. Utility function is a commonly used technique to find out the tolerance of a project manager
    towards risk. Some project managers are more averse to risk than others. All of the
    following are different classifications of tolerance for risk EXCEPT:

1.   Risk Averter
2.   Risk Seeker
3.   Risk Mitigator
4.   Risk Neutral




 Correct Choice: 3

 Justification:




 Reference: Project Management - A Systems Approach to Planning, Scheduling and Controlling, Page Number: 906
8. As part of the Risk Management Process, you just created an overall risk ranking of the
    project and a list of prioritized risks, identified which risks need additional analysis and
    determined trends in risk analysis results. What should you do next?

1.   Analyze the effect of risk events and assign a numerical rating to those risks.
2.   Create a list of identified risks.
3.   Determine the fundamental conditions or events that may give rise to identified risk (root causes of
     risk).
4.   Make a list of potential responses to the risks.
8. As part of the Risk Management Process, you just created an overall risk ranking of the
    project and a list of prioritized risks, identified which risks need additional analysis and
    determined trends in risk analysis results. What should you do next?

1.   Analyze the effect of risk events and assign a numerical rating to those risks.
2.   Create a list of identified risks.
3.   Determine the fundamental conditions or events that may give rise to identified risk (root causes of
     risk).
4.   Make a list of potential responses to the risks.


Correct Choice: 1

Justification: Tasks like creating an overall risk ranking of the project, which includes a list of prioritized risks, identifying which
risks need additional analysis and determining trends in risk analysis results - are all outputs of Qualitative Risk Analysis (PMBOK
Page 253). So, the next step is to perform Quantitative Risk Analysis (i.e. analyze the effect of risk events and assign a numerical
rating to those risks) - (PMBOK Page 254)

Please note that Option 2, Option 3 and Option 4 refer to outputs from Risk Identification Phase which has already been completed
(PMBOK Page 249)

Reference: pmstudy.com notes as mentioned above
9. You are in the process of developing options, and determining actions to enhance
    opportunities and reduce threats to the project`s objectives. What should you be
    doing next?

1.   Determining which risks might affect the project and documenting their
     characteristics.
2.   Identifying, analyzing and planning for newly arising risks.
3.   Deciding how to approach and conduct risk management activities for the project.
4.   Assessing the priority of identified risks using their probability of occurring.
9. You are in the process of developing options, and determining actions to enhance
    opportunities and reduce threats to the project`s objectives. What should you be
    doing next?

1.   Determining which risks might affect the project and documenting their
     characteristics.
2.   Identifying, analyzing and planning for newly arising risks.
3.   Deciding how to approach and conduct risk management activities for the project.
4.   Assessing the priority of identified risks using their probability of occurring.


 Correct Choice: 2

 Justification:
 "Developing options, and determining actions to enhance opportunities and reduce threats to the project`s objectives" - this is Risk
 Response Planning; PMBOK Page 260

 "Identifying, analyzing and planning for newly arising risks" - this is Risk Monitoring and Control - PMBOK Page 264. Please note that
 this happens after Risk Response Planning and is the correct answer

 The other options happen before Risk Response Planning:

 Determining which risks might affect the project and documenting their characteristics (Risk Identification, PMBOK Page 246)
 Deciding how to approach and conduct risk management activities for the project (Risk Management Planning - PMBOK Page 242)
 Assessing the priority of identified risks using their probability of occurring (Qualitative Risk Analysis - PMBOK Page 249)


 Reference: pmstudy.com notes as mentioned above
10. You are in the build phase of the project. But it has run into several unanticipated
    problems. Several risks have surfaced which you had not anticipated earlier. The project
    is over-budget and behind schedule. What should you do?

1.   Create updates to risk response plan
2.   Create a revised project plan
3.   Perform risk response audits
4.   Perform updated risk identification and analysis
10. You are in the build phase of the project. But it has run into several unanticipated
    problems. Several risks have surfaced which you had not anticipated earlier. The project
    is over-budget and behind schedule. What should you do?

1.   Create updates to risk response plan
2.   Create a revised project plan
3.   Perform risk response audits
4.   Perform updated risk identification and analysis




Correct Choice: 4

Justification: Results from an earned value analysis may indicate potential deviation of the project at completion from cost and
schedule targets. When a project deviates significantly from the baseline, updated risk identification and analysis should be
performed.

Reference: pmstudy.com notes as mentioned above
11. In your project, there is:

    * 50% probability of $ 40,000 profit
    * 50% probability of $ 25,000 loss

What is the expected profit in your project?
1. $ 32,500
2. $ 25,000
3. $ 7,500
4. - $ 7,500 (i.e. loss of $ 7,500)
11. In your project, there is:

     * 50% probability of $ 40,000 profit
     * 50% probability of $ 25,000 loss

What is the expected profit in your project?
1. $ 32,500
2. $ 25,000
3. $ 7,500
4. - $ 7,500 (i.e. loss of $ 7,500)



Correct Choice: 3

Justification:
Expected Profit = Sum of (Probability X Profit) (for each alternative)
= (0.50 x $ 40,000) + (0.50 x - $ 25,000)
= $ 20,000 - $ 12,500
= $ 7,500 profit

Reference: pmstudy.com notes as mentioned above
12. In risk response planning, you are in the process of developing options, and determining
      actions to reduce threats to your project`s objectives. When you show the results of your
      risk response planning to your project sponsor, she is not comfortable with the risks in
      the project and she suggests that the project scope should be decreased. This is an
      example of :


1.   Inappropriate risk management because it is having a direct impact on your project scope
2.   Risk Avoidance
3.   Risk Mitigation
4.   Risk Transfer
12. In risk response planning, you are in the process of developing options, and determining
      actions to reduce threats to your project`s objectives. When you show the results of your
      risk response planning to your project sponsor, she is not comfortable with the risks in
      the project and she suggests that the project scope should be decreased. This is an
      example of :


1.    Inappropriate risk management because it is having a direct impact on your project scope
2.    Risk Avoidance
3.    Risk Mitigation
4.    Risk Transfer


Correct Choice: 2

Justification: Risk avoidance involves changing the project management plan to elimiate the threat posed by an adverse risk.... or
to relax the objective that is in jeopardy, such as extending the schedule or reducing scope.

Reference: PMBOK Third Edition, Page Number: 261
13. In your project, you just conducted a risk data quality analysis to evaluate the degree to which
      the data about risks is useful for risk management. What could be a potential next
      step?

1.   Perform a structured review of project plans and assumptions, both at the total project and detailed
     scope levels
2.   Develop checklists for identifying risks based on historical information and knowledge that has
     been accumulated from previous similar projects
3.   Conduct planning meetings to develop the risk management plan
4.   Conduct interviews to quantify the probability and consequences of risks on project activities
13. In your project, you just conducted a risk data quality analysis to evaluate the degree to which
      the data about risks is useful for risk management. What could be a potential next
      step?

1.     Perform a structured review of project plans and assumptions, both at the total project and detailed
       scope levels
2.     Develop checklists for identifying risks based on historical information and knowledge that has
       been accumulated from previous similar projects
3.     Conduct planning meetings to develop the risk management plan
4.     Conduct interviews to quantify the probability and consequences of risks on project activities



Correct Choice: 4

Justification:    Risk data quality analysis is a tool for Qualitative Risk Analysis.

* Option 4 refers to "Interviewing" which is a tool and technique for Quantitative Risk Analysis. Quantitative Risk Analysis is conducted
after Qualitatitive Risk Analysis
* Option 1 refers to "Documentation Reviews" which is a tool and technique for Risk Identification. Risk Identification is conducted
before Qualitatitive Risk Analysis
* Option 2 refers to "Checklists" which is a tool and technique for Risk Identification. Risk Identification is conducted before Qualitatitive
Risk Analysis
* Option 3 refers to "Planning Meetings" which is a tool and technique for Risk Management Planning. Risk Management Planning is
conducted before Qualitatitive Risk Analysis


Reference: pmstudy.com notes as mentioned above
14. You are the project manager of a project which involves oil-exploration in the ocean. Since
     you cannot plan for all eventualities, you establish a contingency reserve, including
     amounts of time, money or resources to handle known or unknown risks. This is an
     example of :


1.   Risk Avoidance
2.   Risk Transfer
3.   Active Risk Acceptance
4.   Improper Risk Planning since all risks should be identified and accounted for
14. You are the project manager of a project which involves oil-exploration in the ocean. Since
     you cannot plan for all eventualities, you establish a contingency reserve, including
     amounts of time, money or resources to handle known or unknown risks. This is an
     example of :


1.    Risk Avoidance
2.    Risk Transfer
3.    Active Risk Acceptance
4.    Improper Risk Planning since all risks should be identified and accounted for


Correct Choice: 3

Justification: The most common active acceptance strategy is to establish a contingency reserve, including amounts of time,
money or resources, to handle known-or even sometimes potential, unknown - threats or opportunities.

Reference: PMBOK Third Edition, Page Number: 263
15. Please refer to this Decision Tree which shows the analysis of profit/loss for the two
      alternatives (i.e. to build or buy).




What is the opportunity cost if the project manager decides to build instead of buy?
1.   $ 1,500        
2.   $ 3,500        
3.   $ 1,500        
4.   $ 5,000
Correct Choice: 2
Justification: Please refer to the diagram:




Profit of Build : $ 5,000
Profit of Buy : $ 3,500
Opportunity cost of Build = Profit you give up if you do not buy = $ 3,500


Reference: pmstudy.com notes as mentioned above
Wrap Up
     Conference#: 702-696-4520 or 866-409-2889
     Participant – 370670831

11     Procurement Management and Tips    January 22   2:00pm    Presenter:       https://
           & Tricks (PMBOK Chapters 12)                    EST
                                                                    www.rooms.hp.com/attend/default.aspx?key
                                                                    =EHHP87PUR6
                                                                 Participant:     https://
                                                                    www.rooms.hp.com/attend/default.aspx?key
                                                                    =EPFBPLUR8X

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (19)

Risk 9-pm study project risk management-test
Risk 9-pm study project risk management-testRisk 9-pm study project risk management-test
Risk 9-pm study project risk management-test
 
Risk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbazRisk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbaz
 
Risk 8- pm study question risk management
Risk 8- pm study question risk managementRisk 8- pm study question risk management
Risk 8- pm study question risk management
 
Risk 6 questions - 170
Risk 6 questions - 170Risk 6 questions - 170
Risk 6 questions - 170
 
Risk 5 simplelearn-exam4-ans
Risk 5 simplelearn-exam4-ansRisk 5 simplelearn-exam4-ans
Risk 5 simplelearn-exam4-ans
 
Pmp test 03
Pmp test 03Pmp test 03
Pmp test 03
 
PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360
 
Pmp test 04
Pmp test 04Pmp test 04
Pmp test 04
 
Pmstudy exam_1
Pmstudy exam_1Pmstudy exam_1
Pmstudy exam_1
 
Pmstudy exam 2
Pmstudy exam 2Pmstudy exam 2
Pmstudy exam 2
 
Risk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansRisk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ans
 
Self test engine PSP-PMI-SP
Self test engine PSP-PMI-SPSelf test engine PSP-PMI-SP
Self test engine PSP-PMI-SP
 
Pmp test 01
Pmp test 01Pmp test 01
Pmp test 01
 
Risk 4 simplelearn-exam3-ans
Risk 4 simplelearn-exam3-ansRisk 4 simplelearn-exam3-ans
Risk 4 simplelearn-exam3-ans
 
Pmi rmp
Pmi rmpPmi rmp
Pmi rmp
 
11 pmp risk management exam
11 pmp risk management exam11 pmp risk management exam
11 pmp risk management exam
 
Pmstudy exam 4
Pmstudy exam 4Pmstudy exam 4
Pmstudy exam 4
 
Pmp test 02
Pmp test 02Pmp test 02
Pmp test 02
 
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) exam
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) examRanga's 51 hot topics to remember for Risk Management Professional (RMP) exam
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) exam
 

Andere mochten auch

Andere mochten auch (20)

Session 7 gdas pmp study group presentation
Session 7   gdas pmp study group presentationSession 7   gdas pmp study group presentation
Session 7 gdas pmp study group presentation
 
4.contracting
4.contracting4.contracting
4.contracting
 
01 project management framework
01 project management framework01 project management framework
01 project management framework
 
Pmp scope chapter 5
Pmp scope chapter 5Pmp scope chapter 5
Pmp scope chapter 5
 
Pmp communication chapter 10
Pmp communication chapter 10Pmp communication chapter 10
Pmp communication chapter 10
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Pmp time chapter 6
Pmp time chapter 6Pmp time chapter 6
Pmp time chapter 6
 
Pmp integration chapter 4
Pmp integration chapter 4Pmp integration chapter 4
Pmp integration chapter 4
 
Pmp quality chapter 8
Pmp quality chapter 8Pmp quality chapter 8
Pmp quality chapter 8
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Pmp risk chapter 11
Pmp risk chapter 11Pmp risk chapter 11
Pmp risk chapter 11
 
PMP / Framework 1 2-3
PMP / Framework 1 2-3PMP / Framework 1 2-3
PMP / Framework 1 2-3
 
Pmp stakeholder chapter 13
Pmp stakeholder chapter 13Pmp stakeholder chapter 13
Pmp stakeholder chapter 13
 
Pmp hr chapter 9
Pmp hr chapter 9Pmp hr chapter 9
Pmp hr chapter 9
 
Pmp procurement chapter 12
Pmp procurement chapter 12Pmp procurement chapter 12
Pmp procurement chapter 12
 
Pmbok 4th edition chapter 12 - Project Procurement Management
Pmbok 4th edition   chapter 12 - Project Procurement ManagementPmbok 4th edition   chapter 12 - Project Procurement Management
Pmbok 4th edition chapter 12 - Project Procurement Management
 
Kpi for product manager
Kpi for product managerKpi for product manager
Kpi for product manager
 
2015 Upload Campaigns Calendar - SlideShare
2015 Upload Campaigns Calendar - SlideShare2015 Upload Campaigns Calendar - SlideShare
2015 Upload Campaigns Calendar - SlideShare
 
What to Upload to SlideShare
What to Upload to SlideShareWhat to Upload to SlideShare
What to Upload to SlideShare
 
Getting Started With SlideShare
Getting Started With SlideShareGetting Started With SlideShare
Getting Started With SlideShare
 

Ähnlich wie Session 10 gdas pmp study group presentation

MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
aryan532920
 
D.Q1Information System and Enterprise Systems· Identify.docx
D.Q1Information System and Enterprise Systems· Identify.docxD.Q1Information System and Enterprise Systems· Identify.docx
D.Q1Information System and Enterprise Systems· Identify.docx
theodorelove43763
 
Software Project Risks Management (1).pdf
Software Project Risks Management (1).pdfSoftware Project Risks Management (1).pdf
Software Project Risks Management (1).pdf
ShivareddyGangam
 
Project Management C7 -risk_management
Project Management C7  -risk_managementProject Management C7  -risk_management
Project Management C7 -risk_management
Izah Asmadi
 
Risk management plan loren schwappach
Risk management plan   loren schwappachRisk management plan   loren schwappach
Risk management plan loren schwappach
Loren Schwappach
 

Ähnlich wie Session 10 gdas pmp study group presentation (20)

Risk management Chapter 2 for project monument course for MSC students
Risk management Chapter 2 for project monument course for MSC studentsRisk management Chapter 2 for project monument course for MSC students
Risk management Chapter 2 for project monument course for MSC students
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Project risk management
Project risk managementProject risk management
Project risk management
 
OOSE-PRESENTATION.pptx
OOSE-PRESENTATION.pptxOOSE-PRESENTATION.pptx
OOSE-PRESENTATION.pptx
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentation
 
NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 
D.Q1Information System and Enterprise Systems· Identify.docx
D.Q1Information System and Enterprise Systems· Identify.docxD.Q1Information System and Enterprise Systems· Identify.docx
D.Q1Information System and Enterprise Systems· Identify.docx
 
Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk management
 
Software Project Risks Management (1).pdf
Software Project Risks Management (1).pdfSoftware Project Risks Management (1).pdf
Software Project Risks Management (1).pdf
 
BUS 519 Education Organization -- snaptutorial.com
BUS 519   Education Organization -- snaptutorial.comBUS 519   Education Organization -- snaptutorial.com
BUS 519 Education Organization -- snaptutorial.com
 
Project Planning and Management.pptx
Project Planning and Management.pptxProject Planning and Management.pptx
Project Planning and Management.pptx
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
A Guide to Risk Management
A Guide to Risk ManagementA Guide to Risk Management
A Guide to Risk Management
 
SPM RISK PLANNING.pdfddddddddddddddddddddddddddddddddddddddddddddddd
SPM RISK PLANNING.pdfdddddddddddddddddddddddddddddddddddddddddddddddSPM RISK PLANNING.pdfddddddddddddddddddddddddddddddddddddddddddddddd
SPM RISK PLANNING.pdfddddddddddddddddddddddddddddddddddddddddddddddd
 
Project Management C7 -risk_management
Project Management C7  -risk_managementProject Management C7  -risk_management
Project Management C7 -risk_management
 
riskanalysis-120305101118-phpapp02.pdf
riskanalysis-120305101118-phpapp02.pdfriskanalysis-120305101118-phpapp02.pdf
riskanalysis-120305101118-phpapp02.pdf
 
Risk management plan loren schwappach
Risk management plan   loren schwappachRisk management plan   loren schwappach
Risk management plan loren schwappach
 
Project managment 10
Project managment  10Project managment  10
Project managment 10
 

Mehr von Tu Nguyen, PMP®,PMI-RMP® (20)

3.estimating
3.estimating3.estimating
3.estimating
 
2.tendering
2.tendering2.tendering
2.tendering
 
1.introduction
1.introduction1.introduction
1.introduction
 
Node
NodeNode
Node
 
Contract
ContractContract
Contract
 
Cash flow
Cash flowCash flow
Cash flow
 
Bar chart
Bar chartBar chart
Bar chart
 
Arrow computation
Arrow computationArrow computation
Arrow computation
 
Arrow
ArrowArrow
Arrow
 
Administration
AdministrationAdministration
Administration
 
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
 
Time cost-control
Time cost-controlTime cost-control
Time cost-control
 
Resources
ResourcesResources
Resources
 
Pert
PertPert
Pert
 
Organization
OrganizationOrganization
Organization
 
Ch 6 construction progress control
Ch 6 construction progress controlCh 6 construction progress control
Ch 6 construction progress control
 
Ch 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisalCh 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisal
 
Ch 3 contract strategy
Ch 3 contract strategyCh 3 contract strategy
Ch 3 contract strategy
 
Ch 2 planning and scheduling
Ch 2 planning and schedulingCh 2 planning and scheduling
Ch 2 planning and scheduling
 
Ch 1 organization of construction projects
Ch 1 organization of construction projectsCh 1 organization of construction projects
Ch 1 organization of construction projects
 

Session 10 gdas pmp study group presentation

  • 1. GDAS PM Professions: PMP Study Group Session #10: Risk Management Monique Howard January 8, 2009 © 2005 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice
  • 2. 1. In your project, you can use all the following tools and techniques for risk response planning EXCEPT: 1. Strategies for negative risks or threats 2. Contingent response planning 3. Strategy for threat and opportunities 4. Strategy for residual risks
  • 3. 1. In your project, you can use all the following tools and techniques for risk response planning EXCEPT: 1. Strategies for negative risks or threats 2. Contingent response planning 3. Strategy for threat and opportunities 4. Strategy for residual risks Correct Choice: 4 Justification: Figure 11-14 Reference: PMBOK Third Edition, Page Number: 260
  • 4. 2. You are the project manager in an automobile manufacturing company. A vendor was sending you the machine parts required in your manufacturing process,but the parts did not reach in time because of heavy rains. You had anticipated this risk and planned for it in your risk response plan. So, as per your risk response plan, you started using machine parts which had been supplied one year ago and were not utilized at that time. However, this has subjected your project to a new risk - that the machine parts which were not used for one year might be having higher level of defects. This new risk can also be called: 1. Unidentifiable Risk 2. Unmanageable Risk 3. Secondary Risk 4. Residual Risk
  • 5. 2. You are the project manager in an automobile manufacturing company. A vendor was sending you the machine parts required in your manufacturing process,but the parts did not reach in time because of heavy rains. You had anticipated this risk and planned for it in your risk response plan. So, as per your risk response plan, you started using machine parts which had been supplied one year ago and were not utilized at that time. However, this has subjected your project to a new risk - that the machine parts which were not used for one year might be having higher level of defects. This new risk can also be called: 1. Unidentifiable Risk 2. Unmanageable Risk 3. Secondary Risk 4. Residual Risk Correct Choice: 3 Justification: Secondary risks that arise as a direct outcome of implementing a risk response. Reference: PMBOK Third Edition, Page Number: 264
  • 6. 3. In your project, you have identified important risks, and planned appropriate responses to the risks. Some risks e.g. possibility of natural disasters have been documented and accepted in your risk management plan. If there are risks that remain after you have taken these steps, then such risks are called: 1. Unidentifiable Risks 2. Residual Risks 3. Secondary Risks 4. Accepted Risks
  • 7. 4. Risk Management Planning is the process of deciding how to approach and plan the risk management activities for a project. It is important to plan for the risk management processes that follow to ensure that the level, type, and visibility of risk management are commensurate with both the risk and importance of the project to the organization. The output of Risk Management Planning is: 1. Risks 2. Risk Management Plan 3. Risk Ranking of the Project 4. Planning Meetings
  • 8. 3. In your project, you have identified important risks, and planned appropriate responses to the risks. Some risks e.g. possibility of natural disasters have been documented and accepted in your risk management plan. If there are risks that remain after you have taken these steps, then such risks are called: 1. Unidentifiable Risks 2. Residual Risks 3. Secondary Risks 4. Accepted Risks Correct Choice: 2 Justification: Residual risks that are expected to remain after planned responses have been taken, as well as those which have been deliberately accepted. Reference: PMBOK Third Edition, Page Number: 264
  • 9. 4. Risk Management Planning is the process of deciding how to approach and plan the risk management activities for a project. It is important to plan for the risk management processes that follow to ensure that the level, type, and visibility of risk management are commensurate with both the risk and importance of the project to the organization. The output of Risk Management Planning is: 1. Risks 2. Risk Management Plan 3. Risk Ranking of the Project 4. Planning Meetings Correct Choice: 2 Justification: Figure 11-3 Reference: PMBOK Third Edition, Page Number: 242
  • 10. 5. In your project, you have identified a list of identified risks, a list of potential responses and root causes of risks. You should document this information in the : 1. Risk Management Plan 2. Risk Database 3. Project Plan 4. Risk Register
  • 11. 5. In your project, you have identified a list of identified risks, a list of potential responses and root causes of risks. You should document this information in the : 1. Risk Management Plan 2. Risk Database 3. Project Plan 4. Risk Register Correct Choice: 4 Justification: The risk register includes a list of identified risks, a list of potential responses, root causes of risk, and updated risk categories. Reference: PMBOK Third Edition, Page Number: 249
  • 12. 6. Risk management helps in maximizing the probability and consequences of positive events and minimizing the probability and consequences of adverse events to project objectives. Risk Response Planning helps in this context because it: 1. helps in deciding how to approach and plan the risk management activities. 2. develops procedures and techniques to enhance opportunities and reduce threats to project objectives. 3. determines which risks might affect the project and documents their characteristics. 4. monitors residual risks, identifies new risks and executes risk reduction plans.
  • 13. 6. Risk management helps in maximizing the probability and consequences of positive events and minimizing the probability and consequences of adverse events to project objectives. Risk Response Planning helps in this context because it: 1. helps in deciding how to approach and plan the risk management activities. 2. develops procedures and techniques to enhance opportunities and reduce threats to project objectives. 3. determines which risks might affect the project and documents their characteristics. 4. monitors residual risks, identifies new risks and executes risk reduction plans. Correct Choice: 2 Justification: Risk response planning - developing options and actions to enhance opportunities, and reducing threats to project objectives. Reference: PMBOK Third Edition, Page Number: 237 pmstudy.com comments: * Option 1: This is Risk Management Planning * Option 3: This is Risk Identification * Option 4: This is Risk Monitoring and Control
  • 14. 7. Utility function is a commonly used technique to find out the tolerance of a project manager towards risk. Some project managers are more averse to risk than others. All of the following are different classifications of tolerance for risk EXCEPT: 1. Risk Averter 2. Risk Seeker 3. Risk Mitigator 4. Risk Neutral
  • 15. 7. Utility function is a commonly used technique to find out the tolerance of a project manager towards risk. Some project managers are more averse to risk than others. All of the following are different classifications of tolerance for risk EXCEPT: 1. Risk Averter 2. Risk Seeker 3. Risk Mitigator 4. Risk Neutral Correct Choice: 3 Justification: Reference: Project Management - A Systems Approach to Planning, Scheduling and Controlling, Page Number: 906
  • 16. 8. As part of the Risk Management Process, you just created an overall risk ranking of the project and a list of prioritized risks, identified which risks need additional analysis and determined trends in risk analysis results. What should you do next? 1. Analyze the effect of risk events and assign a numerical rating to those risks. 2. Create a list of identified risks. 3. Determine the fundamental conditions or events that may give rise to identified risk (root causes of risk). 4. Make a list of potential responses to the risks.
  • 17. 8. As part of the Risk Management Process, you just created an overall risk ranking of the project and a list of prioritized risks, identified which risks need additional analysis and determined trends in risk analysis results. What should you do next? 1. Analyze the effect of risk events and assign a numerical rating to those risks. 2. Create a list of identified risks. 3. Determine the fundamental conditions or events that may give rise to identified risk (root causes of risk). 4. Make a list of potential responses to the risks. Correct Choice: 1 Justification: Tasks like creating an overall risk ranking of the project, which includes a list of prioritized risks, identifying which risks need additional analysis and determining trends in risk analysis results - are all outputs of Qualitative Risk Analysis (PMBOK Page 253). So, the next step is to perform Quantitative Risk Analysis (i.e. analyze the effect of risk events and assign a numerical rating to those risks) - (PMBOK Page 254) Please note that Option 2, Option 3 and Option 4 refer to outputs from Risk Identification Phase which has already been completed (PMBOK Page 249) Reference: pmstudy.com notes as mentioned above
  • 18. 9. You are in the process of developing options, and determining actions to enhance opportunities and reduce threats to the project`s objectives. What should you be doing next? 1. Determining which risks might affect the project and documenting their characteristics. 2. Identifying, analyzing and planning for newly arising risks. 3. Deciding how to approach and conduct risk management activities for the project. 4. Assessing the priority of identified risks using their probability of occurring.
  • 19. 9. You are in the process of developing options, and determining actions to enhance opportunities and reduce threats to the project`s objectives. What should you be doing next? 1. Determining which risks might affect the project and documenting their characteristics. 2. Identifying, analyzing and planning for newly arising risks. 3. Deciding how to approach and conduct risk management activities for the project. 4. Assessing the priority of identified risks using their probability of occurring. Correct Choice: 2 Justification: "Developing options, and determining actions to enhance opportunities and reduce threats to the project`s objectives" - this is Risk Response Planning; PMBOK Page 260 "Identifying, analyzing and planning for newly arising risks" - this is Risk Monitoring and Control - PMBOK Page 264. Please note that this happens after Risk Response Planning and is the correct answer The other options happen before Risk Response Planning: Determining which risks might affect the project and documenting their characteristics (Risk Identification, PMBOK Page 246) Deciding how to approach and conduct risk management activities for the project (Risk Management Planning - PMBOK Page 242) Assessing the priority of identified risks using their probability of occurring (Qualitative Risk Analysis - PMBOK Page 249) Reference: pmstudy.com notes as mentioned above
  • 20. 10. You are in the build phase of the project. But it has run into several unanticipated problems. Several risks have surfaced which you had not anticipated earlier. The project is over-budget and behind schedule. What should you do? 1. Create updates to risk response plan 2. Create a revised project plan 3. Perform risk response audits 4. Perform updated risk identification and analysis
  • 21. 10. You are in the build phase of the project. But it has run into several unanticipated problems. Several risks have surfaced which you had not anticipated earlier. The project is over-budget and behind schedule. What should you do? 1. Create updates to risk response plan 2. Create a revised project plan 3. Perform risk response audits 4. Perform updated risk identification and analysis Correct Choice: 4 Justification: Results from an earned value analysis may indicate potential deviation of the project at completion from cost and schedule targets. When a project deviates significantly from the baseline, updated risk identification and analysis should be performed. Reference: pmstudy.com notes as mentioned above
  • 22. 11. In your project, there is: * 50% probability of $ 40,000 profit * 50% probability of $ 25,000 loss What is the expected profit in your project? 1. $ 32,500 2. $ 25,000 3. $ 7,500 4. - $ 7,500 (i.e. loss of $ 7,500)
  • 23. 11. In your project, there is: * 50% probability of $ 40,000 profit * 50% probability of $ 25,000 loss What is the expected profit in your project? 1. $ 32,500 2. $ 25,000 3. $ 7,500 4. - $ 7,500 (i.e. loss of $ 7,500) Correct Choice: 3 Justification: Expected Profit = Sum of (Probability X Profit) (for each alternative) = (0.50 x $ 40,000) + (0.50 x - $ 25,000) = $ 20,000 - $ 12,500 = $ 7,500 profit Reference: pmstudy.com notes as mentioned above
  • 24. 12. In risk response planning, you are in the process of developing options, and determining actions to reduce threats to your project`s objectives. When you show the results of your risk response planning to your project sponsor, she is not comfortable with the risks in the project and she suggests that the project scope should be decreased. This is an example of : 1. Inappropriate risk management because it is having a direct impact on your project scope 2. Risk Avoidance 3. Risk Mitigation 4. Risk Transfer
  • 25. 12. In risk response planning, you are in the process of developing options, and determining actions to reduce threats to your project`s objectives. When you show the results of your risk response planning to your project sponsor, she is not comfortable with the risks in the project and she suggests that the project scope should be decreased. This is an example of : 1. Inappropriate risk management because it is having a direct impact on your project scope 2. Risk Avoidance 3. Risk Mitigation 4. Risk Transfer Correct Choice: 2 Justification: Risk avoidance involves changing the project management plan to elimiate the threat posed by an adverse risk.... or to relax the objective that is in jeopardy, such as extending the schedule or reducing scope. Reference: PMBOK Third Edition, Page Number: 261
  • 26. 13. In your project, you just conducted a risk data quality analysis to evaluate the degree to which the data about risks is useful for risk management. What could be a potential next step? 1. Perform a structured review of project plans and assumptions, both at the total project and detailed scope levels 2. Develop checklists for identifying risks based on historical information and knowledge that has been accumulated from previous similar projects 3. Conduct planning meetings to develop the risk management plan 4. Conduct interviews to quantify the probability and consequences of risks on project activities
  • 27. 13. In your project, you just conducted a risk data quality analysis to evaluate the degree to which the data about risks is useful for risk management. What could be a potential next step? 1. Perform a structured review of project plans and assumptions, both at the total project and detailed scope levels 2. Develop checklists for identifying risks based on historical information and knowledge that has been accumulated from previous similar projects 3. Conduct planning meetings to develop the risk management plan 4. Conduct interviews to quantify the probability and consequences of risks on project activities Correct Choice: 4 Justification: Risk data quality analysis is a tool for Qualitative Risk Analysis. * Option 4 refers to "Interviewing" which is a tool and technique for Quantitative Risk Analysis. Quantitative Risk Analysis is conducted after Qualitatitive Risk Analysis * Option 1 refers to "Documentation Reviews" which is a tool and technique for Risk Identification. Risk Identification is conducted before Qualitatitive Risk Analysis * Option 2 refers to "Checklists" which is a tool and technique for Risk Identification. Risk Identification is conducted before Qualitatitive Risk Analysis * Option 3 refers to "Planning Meetings" which is a tool and technique for Risk Management Planning. Risk Management Planning is conducted before Qualitatitive Risk Analysis Reference: pmstudy.com notes as mentioned above
  • 28. 14. You are the project manager of a project which involves oil-exploration in the ocean. Since you cannot plan for all eventualities, you establish a contingency reserve, including amounts of time, money or resources to handle known or unknown risks. This is an example of : 1. Risk Avoidance 2. Risk Transfer 3. Active Risk Acceptance 4. Improper Risk Planning since all risks should be identified and accounted for
  • 29. 14. You are the project manager of a project which involves oil-exploration in the ocean. Since you cannot plan for all eventualities, you establish a contingency reserve, including amounts of time, money or resources to handle known or unknown risks. This is an example of : 1. Risk Avoidance 2. Risk Transfer 3. Active Risk Acceptance 4. Improper Risk Planning since all risks should be identified and accounted for Correct Choice: 3 Justification: The most common active acceptance strategy is to establish a contingency reserve, including amounts of time, money or resources, to handle known-or even sometimes potential, unknown - threats or opportunities. Reference: PMBOK Third Edition, Page Number: 263
  • 30. 15. Please refer to this Decision Tree which shows the analysis of profit/loss for the two alternatives (i.e. to build or buy). What is the opportunity cost if the project manager decides to build instead of buy? 1. $ 1,500         2. $ 3,500         3. $ 1,500         4. $ 5,000
  • 31. Correct Choice: 2 Justification: Please refer to the diagram: Profit of Build : $ 5,000 Profit of Buy : $ 3,500 Opportunity cost of Build = Profit you give up if you do not buy = $ 3,500 Reference: pmstudy.com notes as mentioned above
  • 32. Wrap Up Conference#: 702-696-4520 or 866-409-2889 Participant – 370670831 11 Procurement Management and Tips January 22 2:00pm Presenter: https:// & Tricks (PMBOK Chapters 12) EST www.rooms.hp.com/attend/default.aspx?key =EHHP87PUR6 Participant: https:// www.rooms.hp.com/attend/default.aspx?key =EPFBPLUR8X