SlideShare ist ein Scribd-Unternehmen logo
1 von 19
or
So you want to add hydro-electric!
Melvin Swoboda
March 5, 2014
Identify what type of facility you will
have:
◦ Stand Alone
◦ Tied to an existing structure
◦ Tied to an existing water release
 Water Quality
 Terrestrial
 Cultural
 Land Management
 Threaten and Endangered Species
 Your key staff
◦ Manager
◦ Public Affairs
◦ Biologist and Engineers
 Licensing Process consultant (Hydro
experience)
 Legal firm (FERC Hydro experience)
 State –TCEQ, TWDB, TPWD, GLO, THC
 Federal – USFS, USFWS, NOAA (NMFS), NPS
 NGOs
 Local and state groups
 Adjacent landowners
 Tribes, federally recognized
 FERC
 ILP
 TLP
 PAD
 DLA
 FLA
 SD1
 SD2
 HPMP
 SMP
 RMP
 PM&E
 TCP
 SHPO
 THPO
 NAGPRA
 NHPA
 4e
 10j
What are the choices?
◦ Integrated License Process (ILP) 5- 7
years
◦ Traditional License Process (TLP)
(timing uncertain)
 Designed to move through the licensing
process in a defined manner
 Limits studies for study sake
 Places time constraints on EVERYONE
involved
 Designed to support the settlement of
issues
 Pre Application Document
 Study Phase
 Draft License Application
 Final License Application
 Environmental Impact Statement or
Environmental Analysis
◦ Draft
◦ Final
 401 Water Quality Certification
Contains existing information relevant to
the project proposal that is in the
potential applicant’s possession or that
the potential applicant can obtain with the
exercise of due diligence.
 Geology and Soils
 Water resources
 Fish and aquatic
resources
 Wildlife and botanical
resources
 Rare, threatened and
endangered species
 Recreation and land
use
 Aesthetic resources
 Cultural resources
 Social-economic
Resources
 Tribal resources
 River basin
descriptions
 Preliminary issues
and studies list
 Two year period
 Designed to allow for completion of
studies that fill gaps that are:
◦ Identified in the PAD
◦ Identified by agencies and the public
 Study requests must meet a strict set
of criteria
 Describes Goals & Objectives
 Provides relevant resource management
goals to agencies
 Supports the need for additional
information
 Shows a nexus between project
operations and effects
 Considers level of effort and cost
 Designed to include PAD and information
from studies
 Applicant’s analysis of the project effects
on the environment
 Opportunity for applicant to propose
PM&E measures
 Period to consider settlements for parties
 Initially issued in draft for public
comments (includes proposed PM&E’s)
 Final EIS or EA - FERC Staff’s
recommendation on the license
application and includes:
◦ PM&E’s and Draft License Articles
◦ 4e Articles if Federal lands are involved
◦ 10j Fish Prescriptions if needed
 Articles to include operations of the facilities
 Potential 4e articles if appropriate
 Fish prescriptions (10j)
 Shoreline Management Plan
 Recreation Management Plan
 Historical Properties Management Plan
 New federal requirements for Dam Safety
 6 – 7 years for a license of 30 – 50 years
◦ Length of license depends on the cost of the
project using FERC-anomics
 Currently FERC has launched an initiative
for small Hydro Projects with compressed
process time (2-3 years completion)
More information on re-licensing of
Toledo Bend www.tbpjo.org
Questions?

Weitere ähnliche Inhalte

Was ist angesagt?

Shauna Fitzsimmons: Managing to the DFC, TWCA Fall Conference 2015
Shauna Fitzsimmons: Managing to the DFC, TWCA Fall Conference 2015Shauna Fitzsimmons: Managing to the DFC, TWCA Fall Conference 2015
Shauna Fitzsimmons: Managing to the DFC, TWCA Fall Conference 2015
TWCA
 
Howard Slobodin: Agency Rulemaking Update, TWCA Fall Conference 2015
Howard Slobodin: Agency Rulemaking Update, TWCA Fall Conference 2015Howard Slobodin: Agency Rulemaking Update, TWCA Fall Conference 2015
Howard Slobodin: Agency Rulemaking Update, TWCA Fall Conference 2015
TWCA
 
Hope Wells: GCD Permitting and Changing Conditions, TWCA Fall 2015 Conference
Hope Wells: GCD Permitting and Changing Conditions, TWCA Fall 2015 ConferenceHope Wells: GCD Permitting and Changing Conditions, TWCA Fall 2015 Conference
Hope Wells: GCD Permitting and Changing Conditions, TWCA Fall 2015 Conference
TWCA
 
NIAP - EIA Guidelines- Transboundary Pipelines
NIAP - EIA Guidelines- Transboundary PipelinesNIAP - EIA Guidelines- Transboundary Pipelines
NIAP - EIA Guidelines- Transboundary Pipelines
Muhammad Aqib Uddin
 

Was ist angesagt? (20)

Texas Water Infrastructure Coordination Committee
Texas Water Infrastructure Coordination CommitteeTexas Water Infrastructure Coordination Committee
Texas Water Infrastructure Coordination Committee
 
Delta Policy Principles - Feb. 23, 2012
Delta Policy Principles - Feb. 23, 2012Delta Policy Principles - Feb. 23, 2012
Delta Policy Principles - Feb. 23, 2012
 
Evaluating the Relative Cost of Service from Publicly Funded vs. Privately Fi...
Evaluating the Relative Cost of Service from Publicly Funded vs. Privately Fi...Evaluating the Relative Cost of Service from Publicly Funded vs. Privately Fi...
Evaluating the Relative Cost of Service from Publicly Funded vs. Privately Fi...
 
Bay-Delta Conservation Plan: Governance - Feb. 13, 2014
Bay-Delta Conservation Plan: Governance - Feb. 13, 2014Bay-Delta Conservation Plan: Governance - Feb. 13, 2014
Bay-Delta Conservation Plan: Governance - Feb. 13, 2014
 
1_Swaim_WaterPlan
1_Swaim_WaterPlan1_Swaim_WaterPlan
1_Swaim_WaterPlan
 
Vassar et al., EPA/USGS Aquatic Life Report
Vassar et al., EPA/USGS Aquatic Life ReportVassar et al., EPA/USGS Aquatic Life Report
Vassar et al., EPA/USGS Aquatic Life Report
 
Shauna Fitzsimmons: Managing to the DFC, TWCA Fall Conference 2015
Shauna Fitzsimmons: Managing to the DFC, TWCA Fall Conference 2015Shauna Fitzsimmons: Managing to the DFC, TWCA Fall Conference 2015
Shauna Fitzsimmons: Managing to the DFC, TWCA Fall Conference 2015
 
Howard Slobodin: Agency Rulemaking Update, TWCA Fall Conference 2015
Howard Slobodin: Agency Rulemaking Update, TWCA Fall Conference 2015Howard Slobodin: Agency Rulemaking Update, TWCA Fall Conference 2015
Howard Slobodin: Agency Rulemaking Update, TWCA Fall Conference 2015
 
Bay-Delta Quarterly Update, July 26, 2012
Bay-Delta Quarterly Update, July 26, 2012Bay-Delta Quarterly Update, July 26, 2012
Bay-Delta Quarterly Update, July 26, 2012
 
National Floodplain Policy: FFRMS
National Floodplain Policy: FFRMSNational Floodplain Policy: FFRMS
National Floodplain Policy: FFRMS
 
Summary of Shale Gas Roundtable's August 2013 Report
Summary of Shale Gas Roundtable's August 2013 ReportSummary of Shale Gas Roundtable's August 2013 Report
Summary of Shale Gas Roundtable's August 2013 Report
 
Master ppt whole project report 2021
Master ppt whole project report 2021Master ppt whole project report 2021
Master ppt whole project report 2021
 
Key challenges and the Status of Water Reforms
Key challenges and the Status of Water ReformsKey challenges and the Status of Water Reforms
Key challenges and the Status of Water Reforms
 
Crunch IWI Presentation : David Baize
Crunch IWI Presentation : David BaizeCrunch IWI Presentation : David Baize
Crunch IWI Presentation : David Baize
 
TWCA Speech – Rep. James Frank
TWCA Speech – Rep. James FrankTWCA Speech – Rep. James Frank
TWCA Speech – Rep. James Frank
 
Hope Wells: GCD Permitting and Changing Conditions, TWCA Fall 2015 Conference
Hope Wells: GCD Permitting and Changing Conditions, TWCA Fall 2015 ConferenceHope Wells: GCD Permitting and Changing Conditions, TWCA Fall 2015 Conference
Hope Wells: GCD Permitting and Changing Conditions, TWCA Fall 2015 Conference
 
Nepa streamlining icf_rw_041818
Nepa streamlining icf_rw_041818Nepa streamlining icf_rw_041818
Nepa streamlining icf_rw_041818
 
2010 02 The Marine Management Organisation and the Role of Partnerships – Ste...
2010 02 The Marine Management Organisation and the Role of Partnerships – Ste...2010 02 The Marine Management Organisation and the Role of Partnerships – Ste...
2010 02 The Marine Management Organisation and the Role of Partnerships – Ste...
 
8 Integrating Land Use Planning with River Basin Management. Kevin Lynch
8 Integrating Land Use Planning with River Basin Management. Kevin Lynch8 Integrating Land Use Planning with River Basin Management. Kevin Lynch
8 Integrating Land Use Planning with River Basin Management. Kevin Lynch
 
NIAP - EIA Guidelines- Transboundary Pipelines
NIAP - EIA Guidelines- Transboundary PipelinesNIAP - EIA Guidelines- Transboundary Pipelines
NIAP - EIA Guidelines- Transboundary Pipelines
 

Ähnlich wie The Toledo Bend FERC licensing process - So you want to add hydo-electric!

REGULATORY COMPLIANCE A RESUME_Romalie_Valdes1
REGULATORY COMPLIANCE A RESUME_Romalie_Valdes1REGULATORY COMPLIANCE A RESUME_Romalie_Valdes1
REGULATORY COMPLIANCE A RESUME_Romalie_Valdes1
Romalie Valdes
 
Ocean SAMP research agenda
Ocean SAMP research agendaOcean SAMP research agenda
Ocean SAMP research agenda
riseagrant
 
The TCE Revolution and Its Permanent Impact on Environmental Due Diligence
The TCE Revolution and Its Permanent Impact on Environmental Due DiligenceThe TCE Revolution and Its Permanent Impact on Environmental Due Diligence
The TCE Revolution and Its Permanent Impact on Environmental Due Diligence
EDR
 
DOI - Framework for a Solution
DOI - Framework for a SolutionDOI - Framework for a Solution
DOI - Framework for a Solution
en3pro
 

Ähnlich wie The Toledo Bend FERC licensing process - So you want to add hydo-electric! (20)

Best Practices for NEPA Compliance and Related Permitting for EOR Projects
Best Practices for NEPA Compliance and Related Permitting for EOR ProjectsBest Practices for NEPA Compliance and Related Permitting for EOR Projects
Best Practices for NEPA Compliance and Related Permitting for EOR Projects
 
FERC 101, continued - Robert Deibel - USDA Forest Service and Matt Rice, Amer...
FERC 101, continued - Robert Deibel - USDA Forest Service and Matt Rice, Amer...FERC 101, continued - Robert Deibel - USDA Forest Service and Matt Rice, Amer...
FERC 101, continued - Robert Deibel - USDA Forest Service and Matt Rice, Amer...
 
Best Practices for NEPA Compliance and Related Permitting for Projects on In...
Best Practices for NEPA Compliance and Related Permitting for  Projects on In...Best Practices for NEPA Compliance and Related Permitting for  Projects on In...
Best Practices for NEPA Compliance and Related Permitting for Projects on In...
 
Regulatory readiness key issues, Craig Hart, Peoples University of China
Regulatory readiness key issues, Craig Hart, Peoples University of ChinaRegulatory readiness key issues, Craig Hart, Peoples University of China
Regulatory readiness key issues, Craig Hart, Peoples University of China
 
REGULATORY COMPLIANCE A RESUME_Romalie_Valdes1
REGULATORY COMPLIANCE A RESUME_Romalie_Valdes1REGULATORY COMPLIANCE A RESUME_Romalie_Valdes1
REGULATORY COMPLIANCE A RESUME_Romalie_Valdes1
 
Scoping meeting presentation 4 29-13
Scoping meeting presentation 4 29-13Scoping meeting presentation 4 29-13
Scoping meeting presentation 4 29-13
 
Sullivan, Sarah Toevs, Stinson Leonard Street, Vapor Intrusion Update and Ove...
Sullivan, Sarah Toevs, Stinson Leonard Street, Vapor Intrusion Update and Ove...Sullivan, Sarah Toevs, Stinson Leonard Street, Vapor Intrusion Update and Ove...
Sullivan, Sarah Toevs, Stinson Leonard Street, Vapor Intrusion Update and Ove...
 
Ocean SAMP research agenda
Ocean SAMP research agendaOcean SAMP research agenda
Ocean SAMP research agenda
 
The TCE Revolution and Its Permanent Impact on Environmental Due Diligence
The TCE Revolution and Its Permanent Impact on Environmental Due DiligenceThe TCE Revolution and Its Permanent Impact on Environmental Due Diligence
The TCE Revolution and Its Permanent Impact on Environmental Due Diligence
 
New TxDOT ENV Processes To Reduce Time to Deliver Projects by 50%
New TxDOT ENV Processes To Reduce Time to Deliver Projects by 50%New TxDOT ENV Processes To Reduce Time to Deliver Projects by 50%
New TxDOT ENV Processes To Reduce Time to Deliver Projects by 50%
 
Adam_Reed_Resume
Adam_Reed_ResumeAdam_Reed_Resume
Adam_Reed_Resume
 
Streamlined Permitting for Renewable Energy Transmission
Streamlined Permitting for Renewable Energy TransmissionStreamlined Permitting for Renewable Energy Transmission
Streamlined Permitting for Renewable Energy Transmission
 
Master Plan Public Hearing Presentation - January 9, 2014
Master Plan Public Hearing Presentation - January 9, 2014Master Plan Public Hearing Presentation - January 9, 2014
Master Plan Public Hearing Presentation - January 9, 2014
 
ppt watertech-1
ppt watertech-1ppt watertech-1
ppt watertech-1
 
BDCP: Water Authority Board Review Process July 25, 2013
BDCP: Water Authority Board Review Process July 25, 2013BDCP: Water Authority Board Review Process July 25, 2013
BDCP: Water Authority Board Review Process July 25, 2013
 
Code Blue Implementation
Code Blue ImplementationCode Blue Implementation
Code Blue Implementation
 
Raising the Bar North of the Border: The Ins and Outs of Canada’s New Evaluat...
Raising the Bar North of the Border: The Ins and Outs of Canada’s New Evaluat...Raising the Bar North of the Border: The Ins and Outs of Canada’s New Evaluat...
Raising the Bar North of the Border: The Ins and Outs of Canada’s New Evaluat...
 
DOI - Framework for a Solution
DOI - Framework for a SolutionDOI - Framework for a Solution
DOI - Framework for a Solution
 
Hydro 101 - A primer on the hydropower relicensing process - Allyson Conner, ...
Hydro 101 - A primer on the hydropower relicensing process - Allyson Conner, ...Hydro 101 - A primer on the hydropower relicensing process - Allyson Conner, ...
Hydro 101 - A primer on the hydropower relicensing process - Allyson Conner, ...
 
Permitting Geothermal Exploration And Development Projects On Public And Trib...
Permitting Geothermal Exploration And Development Projects On Public And Trib...Permitting Geothermal Exploration And Development Projects On Public And Trib...
Permitting Geothermal Exploration And Development Projects On Public And Trib...
 

Mehr von The Texas Network, LLC

Mehr von The Texas Network, LLC (20)

WHCRWA MUD directors' outreach workshop June 8, 2017
WHCRWA MUD directors' outreach workshop June 8, 2017WHCRWA MUD directors' outreach workshop June 8, 2017
WHCRWA MUD directors' outreach workshop June 8, 2017
 
WHCRWA APWA Presentation on CIP
WHCRWA APWA Presentation on CIPWHCRWA APWA Presentation on CIP
WHCRWA APWA Presentation on CIP
 
WHCRWA Town Hall and Open House 2015
WHCRWA Town Hall and Open House 2015WHCRWA Town Hall and Open House 2015
WHCRWA Town Hall and Open House 2015
 
TWCA Webinar - New “Waters of the United States” Rule
TWCA Webinar - New “Waters of the United States” RuleTWCA Webinar - New “Waters of the United States” Rule
TWCA Webinar - New “Waters of the United States” Rule
 
Pass the Salt: Desalination Brine Disposal Challenges
Pass the Salt: Desalination Brine Disposal ChallengesPass the Salt: Desalination Brine Disposal Challenges
Pass the Salt: Desalination Brine Disposal Challenges
 
Texas Water Development Board Update
Texas Water Development Board UpdateTexas Water Development Board Update
Texas Water Development Board Update
 
Professional Ethics
Professional EthicsProfessional Ethics
Professional Ethics
 
Groundwater Management GMA/GCD Panel
Groundwater Management GMA/GCD PanelGroundwater Management GMA/GCD Panel
Groundwater Management GMA/GCD Panel
 
Methods to promote freshwater inflow to East Matagorda Bay
Methods to promote freshwater inflow to East Matagorda BayMethods to promote freshwater inflow to East Matagorda Bay
Methods to promote freshwater inflow to East Matagorda Bay
 
The Economic Power of Water - GE’s Focus on Reuse
The Economic Power of Water - GE’s Focus on ReuseThe Economic Power of Water - GE’s Focus on Reuse
The Economic Power of Water - GE’s Focus on Reuse
 
Texas Drought Over? (But then again…)
Texas Drought Over?  (But then again…)Texas Drought Over?  (But then again…)
Texas Drought Over? (But then again…)
 
SURFACE WATER ISSUES IN THE GMA 7 JPINT PLANNING PROCESS
SURFACE WATER ISSUES IN THE GMA 7 JPINT PLANNING PROCESSSURFACE WATER ISSUES IN THE GMA 7 JPINT PLANNING PROCESS
SURFACE WATER ISSUES IN THE GMA 7 JPINT PLANNING PROCESS
 
RESPONDING TO A WATER SUPPLY CONTAMINATION EVENT
RESPONDING TO A WATER SUPPLY CONTAMINATION EVENT RESPONDING TO A WATER SUPPLY CONTAMINATION EVENT
RESPONDING TO A WATER SUPPLY CONTAMINATION EVENT
 
Individual liability for Water Authority Board Members
Individual liability for Water Authority Board MembersIndividual liability for Water Authority Board Members
Individual liability for Water Authority Board Members
 
From Projectile to Pump Station
From Projectile to Pump StationFrom Projectile to Pump Station
From Projectile to Pump Station
 
The Future is Now: The Rapidly Evolving Landscape of ASR in Texas
The Future is Now: The Rapidly Evolving Landscape of ASR in TexasThe Future is Now: The Rapidly Evolving Landscape of ASR in Texas
The Future is Now: The Rapidly Evolving Landscape of ASR in Texas
 
Pecos/Devils River Watershed Projects Part II
Pecos/Devils River Watershed Projects Part IIPecos/Devils River Watershed Projects Part II
Pecos/Devils River Watershed Projects Part II
 
Update on ERCOT Activities
Update on ERCOT ActivitiesUpdate on ERCOT Activities
Update on ERCOT Activities
 
San Antonio Vista Ridge Project
San Antonio Vista Ridge ProjectSan Antonio Vista Ridge Project
San Antonio Vista Ridge Project
 
Finding Balance Between Regulation, Management and Property Rights in the Cen...
Finding Balance Between Regulation, Management and Property Rights in the Cen...Finding Balance Between Regulation, Management and Property Rights in the Cen...
Finding Balance Between Regulation, Management and Property Rights in the Cen...
 

The Toledo Bend FERC licensing process - So you want to add hydo-electric!

  • 1. or So you want to add hydro-electric! Melvin Swoboda March 5, 2014
  • 2. Identify what type of facility you will have: ◦ Stand Alone ◦ Tied to an existing structure ◦ Tied to an existing water release
  • 3.  Water Quality  Terrestrial  Cultural  Land Management  Threaten and Endangered Species
  • 4.  Your key staff ◦ Manager ◦ Public Affairs ◦ Biologist and Engineers  Licensing Process consultant (Hydro experience)  Legal firm (FERC Hydro experience)
  • 5.  State –TCEQ, TWDB, TPWD, GLO, THC  Federal – USFS, USFWS, NOAA (NMFS), NPS  NGOs  Local and state groups  Adjacent landowners  Tribes, federally recognized
  • 6.  FERC  ILP  TLP  PAD  DLA  FLA  SD1  SD2  HPMP  SMP  RMP  PM&E  TCP  SHPO  THPO  NAGPRA  NHPA  4e  10j
  • 7. What are the choices? ◦ Integrated License Process (ILP) 5- 7 years ◦ Traditional License Process (TLP) (timing uncertain)
  • 8.  Designed to move through the licensing process in a defined manner  Limits studies for study sake  Places time constraints on EVERYONE involved  Designed to support the settlement of issues
  • 9.
  • 10.  Pre Application Document  Study Phase  Draft License Application  Final License Application  Environmental Impact Statement or Environmental Analysis ◦ Draft ◦ Final  401 Water Quality Certification
  • 11. Contains existing information relevant to the project proposal that is in the potential applicant’s possession or that the potential applicant can obtain with the exercise of due diligence.
  • 12.  Geology and Soils  Water resources  Fish and aquatic resources  Wildlife and botanical resources  Rare, threatened and endangered species  Recreation and land use  Aesthetic resources  Cultural resources  Social-economic Resources  Tribal resources  River basin descriptions  Preliminary issues and studies list
  • 13.  Two year period  Designed to allow for completion of studies that fill gaps that are: ◦ Identified in the PAD ◦ Identified by agencies and the public  Study requests must meet a strict set of criteria
  • 14.  Describes Goals & Objectives  Provides relevant resource management goals to agencies  Supports the need for additional information  Shows a nexus between project operations and effects  Considers level of effort and cost
  • 15.  Designed to include PAD and information from studies  Applicant’s analysis of the project effects on the environment  Opportunity for applicant to propose PM&E measures  Period to consider settlements for parties
  • 16.  Initially issued in draft for public comments (includes proposed PM&E’s)  Final EIS or EA - FERC Staff’s recommendation on the license application and includes: ◦ PM&E’s and Draft License Articles ◦ 4e Articles if Federal lands are involved ◦ 10j Fish Prescriptions if needed
  • 17.  Articles to include operations of the facilities  Potential 4e articles if appropriate  Fish prescriptions (10j)  Shoreline Management Plan  Recreation Management Plan  Historical Properties Management Plan  New federal requirements for Dam Safety
  • 18.  6 – 7 years for a license of 30 – 50 years ◦ Length of license depends on the cost of the project using FERC-anomics  Currently FERC has launched an initiative for small Hydro Projects with compressed process time (2-3 years completion)
  • 19. More information on re-licensing of Toledo Bend www.tbpjo.org Questions?

Hinweis der Redaktion

  1. Includes geology and Soils, water resources, Fish and aquatic resources, wildlife and botanical resources, Rare, threatened and endagered species, recreation and land use, aesthetic resources, cultural