Bathurst Station Preliminary Design




                                        Bathurst Station
                                      Preliminary Design
                                               Open House #1
                                           November 28, 2011


                                                     11/28/2011
Bathurst Station Preliminary Design




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   2
Bathurst Station Preliminary Design




   Open House Overview
        Part 1
        • Introduction
        • Crosstown Update
        • Station Design 101 - Design Principles

        Part 2
        •Bathurst Station Preliminary Design

        *Our partners in City Planning are here if you have questions
        about existing development requirements in the Bathurst area
        or the future Land Use Study around Crosstown Stations

                                      11/28/2011   Bathurst Station - Preliminary Design Overview   3
                                                                                                    3
Bathurst Station Preliminary Design




  •
                  The Purpose of Tonight’s Open House
      Provide a brief Crosstown project update
  •   Present the Crosstown station design philosophy
  •   Explain the anatomy of the station components and challenges
  •   Display the preliminary design of Bathurst Station
  Most importantly:
  *Get your input on the Preliminary Design early in this process.

  • The architectural design will be prepared for Open House #2 in
    Spring 2012. Significant outreach will follow on construction.
  • Walls at the future station box are scheduled to begin at Bathurst in
    2013 as part of the tunnelling process.
  • Bathurst Station construction is scheduled to begin in 2014.

                                      11/28/2011   Bathurst Station - Preliminary Design Overview   4
Bathurst Station Preliminary Design




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   5
Bathurst Station Preliminary Design




   Format for Feedback
• Please speak with the project team at the displays, we’re here to answer your
  questions

• There are tables to write comments and for group discussions

• Please submit a feedback form tonight if possible , or send us comments
  via e-mail, mail, or online at www.thecrosstown.ca by December 12, 2011

• A consultation report to inform the designers will be posted online at:
www.thecrosstown.ca




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   6
Bathurst Station Preliminary Design




                                      * Final number and location of stations subject to review




                                                     11/28/2011   Bathurst Station - Preliminary Design Overview   7
Bathurst Station Preliminary Design




   The billion transit investment from the Province of Ontario through Metrolinx
   • $8.4 Eglinton-Scarborough Crosstown Plan

    • 25 km east-west transit corridor between Black Creek Drive and Scarborough
      Centre

    • 60% faster than bus service today (e.g. only 15 minutes from Keele to Yonge)

    • 19 km underground tunnel (Black Creek Drive to Kennedy Station)*

    • 6km seamless service will replace the SRT from Kennedy Station to Scarborough
      Centre

    • Up to 26 stations

    *Exact alignment west of Keele Street and east of Laird Drive TBD

                                              11/28/2011   Bathurst Station - Preliminary Design Overview   8
Bathurst Station Preliminary Design




    First Construction Contract at
     • Tunnel launch site preparation is underway
            Keelesdale Park (between Black Creek Drive and Keele Street)

      •     Tunnelling will start in summer 2012 and head east




                                             11/28/2011   Bathurst Station - Preliminary Design Overview   9
Bathurst Station Preliminary Design




     Crosstown Construction Update




     Crosstown tunnel preparation work at Black Creek and Eglinton in Keelesdale Park
     Piling rigs are building concrete support walls for the future tunnel launch shaft
     The shaft will enable tunnelling eastward in summer 2012
     Soil testing for the tunnel and stations continues from Keele Street to Kennedy Station in Scarborough


                                                  11/28/2011   Bathurst Station - Preliminary Design Overview   10
Bathurst Station Preliminary Design




    Conceptual Design of a Crosstown Station




Urban Design and Architectural Guidelines
have been developed:

•    ensure positive change along the
     corridor
•    guide individual station designs and
     achieve consistency
•    guide configuration of surface
     elements
•    integrate surface elements with
     existing and future development


                                            11/28/2011   Bathurst Station - Preliminary Design Overview   11
Bathurst Station Preliminary Design




      Stations 101
      What’s needed to make a Station Work?
      •   Main Entrance
      •   Secondary Entrance
      •   Passenger Transportation (elevators, escalators)
      •   Mechanical and Electrical Systems
      •   Ventilation Shafts and Ventilation Fan Rooms
      •   Traction Power Substations

      Guiding Principle:
      Consolidate Surface Elements to enhance design & minimize impacts

      •Reduce construction impacts (traffic, staging area, noise, dust )
      •Preserve public space and development potential
      •Save $



                                             11/28/2011   Bathurst Station - Preliminary Design Overview   12
Bathurst Station Preliminary Design




  Design Philosophy
  • Integrate with surrounding neighbourhood

  • Safe and enjoyable user experience

  • Full accessibility
                                                 Accessibility for all users
  • Preserve space for future re-development

  • Enhance the local “sense of place”

  • Long-term sustainability

  • Reduce Construction Footprint & Impacts

  • Reduce Costs
                                                 Compatible scale


                                         11/28/2011   Bathurst Station - Preliminary Design Overview   13
                                                                                                       13
Bathurst Station Preliminary Design




    Accessibility Principles & Features
     • Access for persons with all levels of mobility

     • Elevators

     • Escalators

     • Low-Floor Access




                                            11/28/2011   Bathurst Station - Preliminary Design Overview   14
                                                                                                          14
Bathurst Station Preliminary Design




  Safety and Security Features
     • Monitored CCTV Security Cameras

     • Urban Braille

     • High Quality Lighting




                                         11/28/2011   Bathurst Station - Preliminary Design Overview   15
                                                                                                       15
Bathurst Station Preliminary Design




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   16
Bathurst Station Preliminary Design




   Architectural Design Approach
   •    Excellence in architectural/urban
        design treatments
   •    Cost effective and maintainable
        structures
   •    Standard station box configurations
   •    Creative use of materials, color,
        textures, artwork, light
   •    Brand identification with graphics
   •    Use standard elements whenever
        possible




                                              11/28/2011   Bathurst Station - Preliminary Design Overview   17
Bathurst Station Preliminary Design




 Surface Elements – Guiding Principles
                                                                    •     Surface elements are
                                                                          most visible to public
                                                                    •     Integrate into local
                                                                          community
                                                                    •     Minimize property
                                                                          implications
                                                                    •     High quality design
                                                                    •     Major focus on
                                                                          consolidating:
                                                                            – Entrances
                                                                            – Vent Shafts
                                                                            – Substations




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   18
Bathurst Station Preliminary Design




           The Approach to Guide
           Detailed Design




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   19
Bathurst Station Preliminary Design




 Integrated Artwork

 • Any architectural finish can contain
   integrated artwork, including:

              •   walls
              •   floors
              •   ceilings
              •   glazing




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   20
Bathurst Station Preliminary Design




           Cross-Section




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   21
Bathurst Station Preliminary Design




     Station Entrances
•   Public spaces which fit into the
    community
•   Main & Secondary Entrance
•   Main Entrance is fully accessible

•   Use of height/massing to create
    unique structure
•   Highly visible, transparent,
    sophisticated
•   Promote Transit-Oriented
    Development

•   Maximize daylight opportunities
•   Well lit at night
•   Connect with Buses on street




                                        11/28/2011   Bathurst Station - Preliminary Design Overview   22
Bathurst Station Preliminary Design




 Traction Power Substations
 What and Why?
   •      Required to provide power to the station system
   •      Every two kilometres, at stations
   •      Many different configurations
   •      Above ground, surface, below-ground
   •      Guidelines to integrate substations




                                            11/28/2011   Bathurst Station - Preliminary Design Overview   23
Bathurst Station Preliminary Design




                                      Presentation
                                      Part 2:
                                      Bathurst Station




                                             11/28/2011   Bathurst Station - Preliminary Design Overview   24
                                                                                                           24
Bathurst Station Preliminary Design




            Bathurst Station Preliminary Design

       Preliminary Design by:

       Crosstown Consortium
       IBI Group
       LEA Consulting
       SNC Lavalin




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   25
Bathurst Station Preliminary Design



        Local Context
        Population Density within a 10 minute walk to Bathurst Station




                                       11/28/2011   Bathurst Station - Preliminary Design Overview   26
Bathurst Station Preliminary Design




 Bathurst Station – Existing Uses &
 Proposed Development




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   27
Bathurst Station Preliminary Design




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   28
Bathurst Station Preliminary Design




   Bathurst Station – Local Context
   Upper Village Business Improvement Area (BIA)
   •www.uppervillagetoronto.ca

   •Represents merchants, venues and services from Allen Road to Bathurst Street

   •Wide selection of shops, restaurants & services




                                          11/28/2011   Bathurst Station - Preliminary Design Overview   29
Bathurst Station Preliminary Design



Bathurst Station – EA (2010)
(add property numbers)




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   30
Bathurst Station Preliminary Design




          Generic
          Rendering Only
          Architecture
          Concept TBD




                                              Potential Future
                                              Secondary Entrance




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   31
Bathurst Station Preliminary Design




          Key Advantages of New Consolidated Design

          Reduces construction footprint, cost & impacts
           (roadway construction reduced by 21.5 metres)


          Improves look and feel from street for community


          Reduces number of properties affected


          Preserves potential for investment and development with
           more public space




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   32
Bathurst Station Preliminary Design




      NORTH/EAST CORNER OF
      BATHURST AND EGLINTON



                                      11/28/2011   Bathurst Station - Preliminary Design Overview   33
Bathurst Station Preliminary Design




      NORTH/EAST CORNER OF
      BATHURST AND EGLINTON


                                      11/28/2011   Bathurst Station - Preliminary Design Overview   34
Bathurst Station Preliminary Design




         Rear Laneway


                                      11/28/2011   Bathurst Station - Preliminary Design Overview   35
Bathurst Station Preliminary Design




                                                                     • Setbacks TBD


                                      11/28/2011   Bathurst Station - Preliminary Design Overview   36
Bathurst Station Preliminary Design




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   37
Bathurst Station Preliminary Design




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   38
Bathurst Station Preliminary Design




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   39
Bathurst Station Preliminary Design




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   40
Bathurst Station Preliminary Design




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   41
Bathurst Station Preliminary Design




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   42
Bathurst Station Preliminary Design




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   43
Bathurst Station Preliminary Design




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   44
Bathurst Station Preliminary Design




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   45
Bathurst Station Preliminary Design




            Passenger Circulation




                                                                                        ISOMETRIC


                                      11/28/2011   Bathurst Station - Preliminary Design Overview   46
Bathurst Station Preliminary Design




       Architectural Concept:
       Preliminary
       Representation
       •subject to change




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   47
Bathurst Station Preliminary Design




        Preliminary
        Representation
        •subject to change




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   48
Bathurst Station Preliminary Design




        Preliminary
        Representation
        •subject to change




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   49
Bathurst Station Preliminary Design




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   50
Bathurst Station Preliminary Design




                                      11/28/2011   Bathurst Station - Preliminary Design Overview   51

Weitere ähnliche Inhalte

Was ist angesagt?

Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
Crosstown TO
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open House
Crosstown TO
 
Mount pleasant station open house
Mount pleasant station open house  Mount pleasant station open house
Mount pleasant station open house
Crosstown TO
 
Forest Hill station open house
Forest Hill station open houseForest Hill station open house
Forest Hill station open house
Crosstown TO
 
Link And Place A Guide To Street Planning And Design By Prof Peter Jones
Link And Place   A Guide To Street Planning And Design By Prof Peter JonesLink And Place   A Guide To Street Planning And Design By Prof Peter Jones
Link And Place A Guide To Street Planning And Design By Prof Peter Jones
gueste0b5fe
 
Eastern market metro park project community meeting 07-22-2020
Eastern market metro park project community meeting  07-22-2020Eastern market metro park project community meeting  07-22-2020
Eastern market metro park project community meeting 07-22-2020
RamaChilamkurthy
 
Big Challenge, Big Success
Big Challenge, Big SuccessBig Challenge, Big Success
Big Challenge, Big Success
mecocca5
 
Forest hill station open house
Forest hill station open house Forest hill station open house
Forest hill station open house
Crosstown TO
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
Crosstown TO
 

Was ist angesagt? (20)

Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open House
 
Chaplin Station: Preliminary Design Consultation
Chaplin Station: Preliminary Design ConsultationChaplin Station: Preliminary Design Consultation
Chaplin Station: Preliminary Design Consultation
 
Mount pleasant station open house
Mount pleasant station open house  Mount pleasant station open house
Mount pleasant station open house
 
Forest Hill station open house
Forest Hill station open houseForest Hill station open house
Forest Hill station open house
 
Springfield Community Business Center Commuter Parking Garage
Springfield Community Business Center Commuter Parking GarageSpringfield Community Business Center Commuter Parking Garage
Springfield Community Business Center Commuter Parking Garage
 
Link And Place A Guide To Street Planning And Design By Prof Peter Jones
Link And Place   A Guide To Street Planning And Design By Prof Peter JonesLink And Place   A Guide To Street Planning And Design By Prof Peter Jones
Link And Place A Guide To Street Planning And Design By Prof Peter Jones
 
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...
 
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...
Online Consultation: Western Alignment and Vehicle Maintenance and Storage Fa...
 
Improving Street Design Through 'Link and Place'
Improving Street Design Through 'Link and Place'Improving Street Design Through 'Link and Place'
Improving Street Design Through 'Link and Place'
 
Balboa Avenue Station Presentation
Balboa Avenue Station PresentationBalboa Avenue Station Presentation
Balboa Avenue Station Presentation
 
Springfield Community Business Center Commuter Parking Garage Slugging Commun...
Springfield Community Business Center Commuter Parking Garage Slugging Commun...Springfield Community Business Center Commuter Parking Garage Slugging Commun...
Springfield Community Business Center Commuter Parking Garage Slugging Commun...
 
Clairemont CPG ad hoc subcommittee presentation 1/18/18
Clairemont CPG ad hoc subcommittee presentation 1/18/18Clairemont CPG ad hoc subcommittee presentation 1/18/18
Clairemont CPG ad hoc subcommittee presentation 1/18/18
 
Eastern market metro park project community meeting 07-22-2020
Eastern market metro park project community meeting  07-22-2020Eastern market metro park project community meeting  07-22-2020
Eastern market metro park project community meeting 07-22-2020
 
Laird Drive to Don Valley Parkway: Environmental Project Report Addendum Onli...
Laird Drive to Don Valley Parkway: Environmental Project Report Addendum Onli...Laird Drive to Don Valley Parkway: Environmental Project Report Addendum Onli...
Laird Drive to Don Valley Parkway: Environmental Project Report Addendum Onli...
 
Pb Community Planning Group May 24
Pb Community Planning Group May 24Pb Community Planning Group May 24
Pb Community Planning Group May 24
 
Big Challenge, Big Success
Big Challenge, Big SuccessBig Challenge, Big Success
Big Challenge, Big Success
 
Pacific Beach ad hoc subcommittee presentation 11/3/16
Pacific Beach ad hoc subcommittee presentation 11/3/16Pacific Beach ad hoc subcommittee presentation 11/3/16
Pacific Beach ad hoc subcommittee presentation 11/3/16
 
Forest hill station open house
Forest hill station open house Forest hill station open house
Forest hill station open house
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
 

Ähnlich wie Bathurst Station Preliminary Design Consultation

rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgrade
Robert Lee - CEng, MICE, PMP
 
Capitol Hill Cc 12110
Capitol Hill Cc 12110Capitol Hill Cc 12110
Capitol Hill Cc 12110
jseattle
 
Portfolio (Sunil Basnet )
Portfolio (Sunil Basnet )Portfolio (Sunil Basnet )
Portfolio (Sunil Basnet )
tensab_linus419
 

Ähnlich wie Bathurst Station Preliminary Design Consultation (20)

Allen Road - Eglinton West Station: Preliminary Design Consultation
Allen Road - Eglinton West Station: Preliminary Design ConsultationAllen Road - Eglinton West Station: Preliminary Design Consultation
Allen Road - Eglinton West Station: Preliminary Design Consultation
 
Open House: Bathurst Station Consultation
Open House: Bathurst Station ConsultationOpen House: Bathurst Station Consultation
Open House: Bathurst Station Consultation
 
West Station Reference Concept Design Online Consultation
West Station Reference Concept Design Online ConsultationWest Station Reference Concept Design Online Consultation
West Station Reference Concept Design Online Consultation
 
Central Station Reference Concept Design Online Consultation
Central Station Reference Concept Design Online ConsultationCentral Station Reference Concept Design Online Consultation
Central Station Reference Concept Design Online Consultation
 
Caledonia Station: Preliminary Design Consultation
Caledonia Station: Preliminary Design ConsultationCaledonia Station: Preliminary Design Consultation
Caledonia Station: Preliminary Design Consultation
 
2015 0617 workshop_presentation_outfall_draft_brm
2015 0617 workshop_presentation_outfall_draft_brm2015 0617 workshop_presentation_outfall_draft_brm
2015 0617 workshop_presentation_outfall_draft_brm
 
SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)
 
London Underground - Redesigning White-chapel Station
London Underground - Redesigning White-chapel Station London Underground - Redesigning White-chapel Station
London Underground - Redesigning White-chapel Station
 
Oak Harbor Design Open House
Oak Harbor Design Open HouseOak Harbor Design Open House
Oak Harbor Design Open House
 
Jumayliah Public Realm Design Report
Jumayliah Public Realm Design ReportJumayliah Public Realm Design Report
Jumayliah Public Realm Design Report
 
rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgrade
 
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectCommunity Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
 
Capitol Hill Cc 12110
Capitol Hill Cc 12110Capitol Hill Cc 12110
Capitol Hill Cc 12110
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
 
Armtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design ReviewArmtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design Review
 
TRB Managed Lane Design Build
TRB Managed Lane Design BuildTRB Managed Lane Design Build
TRB Managed Lane Design Build
 
West district library presentation
West district library presentationWest district library presentation
West district library presentation
 
Assarpour_Amir
Assarpour_AmirAssarpour_Amir
Assarpour_Amir
 
Architecture presentation 3
Architecture presentation 3Architecture presentation 3
Architecture presentation 3
 
Portfolio (Sunil Basnet )
Portfolio (Sunil Basnet )Portfolio (Sunil Basnet )
Portfolio (Sunil Basnet )
 

Kürzlich hochgeladen

Kürzlich hochgeladen (20)

Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 

Bathurst Station Preliminary Design Consultation

  • 1. Bathurst Station Preliminary Design Bathurst Station Preliminary Design Open House #1 November 28, 2011 11/28/2011
  • 2. Bathurst Station Preliminary Design 11/28/2011 Bathurst Station - Preliminary Design Overview 2
  • 3. Bathurst Station Preliminary Design Open House Overview Part 1 • Introduction • Crosstown Update • Station Design 101 - Design Principles Part 2 •Bathurst Station Preliminary Design *Our partners in City Planning are here if you have questions about existing development requirements in the Bathurst area or the future Land Use Study around Crosstown Stations 11/28/2011 Bathurst Station - Preliminary Design Overview 3 3
  • 4. Bathurst Station Preliminary Design • The Purpose of Tonight’s Open House Provide a brief Crosstown project update • Present the Crosstown station design philosophy • Explain the anatomy of the station components and challenges • Display the preliminary design of Bathurst Station Most importantly: *Get your input on the Preliminary Design early in this process. • The architectural design will be prepared for Open House #2 in Spring 2012. Significant outreach will follow on construction. • Walls at the future station box are scheduled to begin at Bathurst in 2013 as part of the tunnelling process. • Bathurst Station construction is scheduled to begin in 2014. 11/28/2011 Bathurst Station - Preliminary Design Overview 4
  • 5. Bathurst Station Preliminary Design 11/28/2011 Bathurst Station - Preliminary Design Overview 5
  • 6. Bathurst Station Preliminary Design Format for Feedback • Please speak with the project team at the displays, we’re here to answer your questions • There are tables to write comments and for group discussions • Please submit a feedback form tonight if possible , or send us comments via e-mail, mail, or online at www.thecrosstown.ca by December 12, 2011 • A consultation report to inform the designers will be posted online at: www.thecrosstown.ca 11/28/2011 Bathurst Station - Preliminary Design Overview 6
  • 7. Bathurst Station Preliminary Design * Final number and location of stations subject to review 11/28/2011 Bathurst Station - Preliminary Design Overview 7
  • 8. Bathurst Station Preliminary Design The billion transit investment from the Province of Ontario through Metrolinx • $8.4 Eglinton-Scarborough Crosstown Plan • 25 km east-west transit corridor between Black Creek Drive and Scarborough Centre • 60% faster than bus service today (e.g. only 15 minutes from Keele to Yonge) • 19 km underground tunnel (Black Creek Drive to Kennedy Station)* • 6km seamless service will replace the SRT from Kennedy Station to Scarborough Centre • Up to 26 stations *Exact alignment west of Keele Street and east of Laird Drive TBD 11/28/2011 Bathurst Station - Preliminary Design Overview 8
  • 9. Bathurst Station Preliminary Design First Construction Contract at • Tunnel launch site preparation is underway Keelesdale Park (between Black Creek Drive and Keele Street) • Tunnelling will start in summer 2012 and head east 11/28/2011 Bathurst Station - Preliminary Design Overview 9
  • 10. Bathurst Station Preliminary Design Crosstown Construction Update  Crosstown tunnel preparation work at Black Creek and Eglinton in Keelesdale Park  Piling rigs are building concrete support walls for the future tunnel launch shaft  The shaft will enable tunnelling eastward in summer 2012  Soil testing for the tunnel and stations continues from Keele Street to Kennedy Station in Scarborough 11/28/2011 Bathurst Station - Preliminary Design Overview 10
  • 11. Bathurst Station Preliminary Design Conceptual Design of a Crosstown Station Urban Design and Architectural Guidelines have been developed: • ensure positive change along the corridor • guide individual station designs and achieve consistency • guide configuration of surface elements • integrate surface elements with existing and future development 11/28/2011 Bathurst Station - Preliminary Design Overview 11
  • 12. Bathurst Station Preliminary Design Stations 101 What’s needed to make a Station Work? • Main Entrance • Secondary Entrance • Passenger Transportation (elevators, escalators) • Mechanical and Electrical Systems • Ventilation Shafts and Ventilation Fan Rooms • Traction Power Substations Guiding Principle: Consolidate Surface Elements to enhance design & minimize impacts •Reduce construction impacts (traffic, staging area, noise, dust ) •Preserve public space and development potential •Save $ 11/28/2011 Bathurst Station - Preliminary Design Overview 12
  • 13. Bathurst Station Preliminary Design Design Philosophy • Integrate with surrounding neighbourhood • Safe and enjoyable user experience • Full accessibility Accessibility for all users • Preserve space for future re-development • Enhance the local “sense of place” • Long-term sustainability • Reduce Construction Footprint & Impacts • Reduce Costs Compatible scale 11/28/2011 Bathurst Station - Preliminary Design Overview 13 13
  • 14. Bathurst Station Preliminary Design Accessibility Principles & Features • Access for persons with all levels of mobility • Elevators • Escalators • Low-Floor Access 11/28/2011 Bathurst Station - Preliminary Design Overview 14 14
  • 15. Bathurst Station Preliminary Design Safety and Security Features • Monitored CCTV Security Cameras • Urban Braille • High Quality Lighting 11/28/2011 Bathurst Station - Preliminary Design Overview 15 15
  • 16. Bathurst Station Preliminary Design 11/28/2011 Bathurst Station - Preliminary Design Overview 16
  • 17. Bathurst Station Preliminary Design Architectural Design Approach • Excellence in architectural/urban design treatments • Cost effective and maintainable structures • Standard station box configurations • Creative use of materials, color, textures, artwork, light • Brand identification with graphics • Use standard elements whenever possible 11/28/2011 Bathurst Station - Preliminary Design Overview 17
  • 18. Bathurst Station Preliminary Design Surface Elements – Guiding Principles • Surface elements are most visible to public • Integrate into local community • Minimize property implications • High quality design • Major focus on consolidating: – Entrances – Vent Shafts – Substations 11/28/2011 Bathurst Station - Preliminary Design Overview 18
  • 19. Bathurst Station Preliminary Design The Approach to Guide Detailed Design 11/28/2011 Bathurst Station - Preliminary Design Overview 19
  • 20. Bathurst Station Preliminary Design Integrated Artwork • Any architectural finish can contain integrated artwork, including: • walls • floors • ceilings • glazing 11/28/2011 Bathurst Station - Preliminary Design Overview 20
  • 21. Bathurst Station Preliminary Design Cross-Section 11/28/2011 Bathurst Station - Preliminary Design Overview 21
  • 22. Bathurst Station Preliminary Design Station Entrances • Public spaces which fit into the community • Main & Secondary Entrance • Main Entrance is fully accessible • Use of height/massing to create unique structure • Highly visible, transparent, sophisticated • Promote Transit-Oriented Development • Maximize daylight opportunities • Well lit at night • Connect with Buses on street 11/28/2011 Bathurst Station - Preliminary Design Overview 22
  • 23. Bathurst Station Preliminary Design Traction Power Substations What and Why? • Required to provide power to the station system • Every two kilometres, at stations • Many different configurations • Above ground, surface, below-ground • Guidelines to integrate substations 11/28/2011 Bathurst Station - Preliminary Design Overview 23
  • 24. Bathurst Station Preliminary Design Presentation Part 2: Bathurst Station 11/28/2011 Bathurst Station - Preliminary Design Overview 24 24
  • 25. Bathurst Station Preliminary Design Bathurst Station Preliminary Design Preliminary Design by: Crosstown Consortium IBI Group LEA Consulting SNC Lavalin 11/28/2011 Bathurst Station - Preliminary Design Overview 25
  • 26. Bathurst Station Preliminary Design Local Context Population Density within a 10 minute walk to Bathurst Station 11/28/2011 Bathurst Station - Preliminary Design Overview 26
  • 27. Bathurst Station Preliminary Design Bathurst Station – Existing Uses & Proposed Development 11/28/2011 Bathurst Station - Preliminary Design Overview 27
  • 28. Bathurst Station Preliminary Design 11/28/2011 Bathurst Station - Preliminary Design Overview 28
  • 29. Bathurst Station Preliminary Design Bathurst Station – Local Context Upper Village Business Improvement Area (BIA) •www.uppervillagetoronto.ca •Represents merchants, venues and services from Allen Road to Bathurst Street •Wide selection of shops, restaurants & services 11/28/2011 Bathurst Station - Preliminary Design Overview 29
  • 30. Bathurst Station Preliminary Design Bathurst Station – EA (2010) (add property numbers) 11/28/2011 Bathurst Station - Preliminary Design Overview 30
  • 31. Bathurst Station Preliminary Design Generic Rendering Only Architecture Concept TBD Potential Future Secondary Entrance 11/28/2011 Bathurst Station - Preliminary Design Overview 31
  • 32. Bathurst Station Preliminary Design Key Advantages of New Consolidated Design Reduces construction footprint, cost & impacts (roadway construction reduced by 21.5 metres) Improves look and feel from street for community Reduces number of properties affected Preserves potential for investment and development with more public space 11/28/2011 Bathurst Station - Preliminary Design Overview 32
  • 33. Bathurst Station Preliminary Design NORTH/EAST CORNER OF BATHURST AND EGLINTON 11/28/2011 Bathurst Station - Preliminary Design Overview 33
  • 34. Bathurst Station Preliminary Design NORTH/EAST CORNER OF BATHURST AND EGLINTON 11/28/2011 Bathurst Station - Preliminary Design Overview 34
  • 35. Bathurst Station Preliminary Design Rear Laneway 11/28/2011 Bathurst Station - Preliminary Design Overview 35
  • 36. Bathurst Station Preliminary Design • Setbacks TBD 11/28/2011 Bathurst Station - Preliminary Design Overview 36
  • 37. Bathurst Station Preliminary Design 11/28/2011 Bathurst Station - Preliminary Design Overview 37
  • 38. Bathurst Station Preliminary Design 11/28/2011 Bathurst Station - Preliminary Design Overview 38
  • 39. Bathurst Station Preliminary Design 11/28/2011 Bathurst Station - Preliminary Design Overview 39
  • 40. Bathurst Station Preliminary Design 11/28/2011 Bathurst Station - Preliminary Design Overview 40
  • 41. Bathurst Station Preliminary Design 11/28/2011 Bathurst Station - Preliminary Design Overview 41
  • 42. Bathurst Station Preliminary Design 11/28/2011 Bathurst Station - Preliminary Design Overview 42
  • 43. Bathurst Station Preliminary Design 11/28/2011 Bathurst Station - Preliminary Design Overview 43
  • 44. Bathurst Station Preliminary Design 11/28/2011 Bathurst Station - Preliminary Design Overview 44
  • 45. Bathurst Station Preliminary Design 11/28/2011 Bathurst Station - Preliminary Design Overview 45
  • 46. Bathurst Station Preliminary Design Passenger Circulation ISOMETRIC 11/28/2011 Bathurst Station - Preliminary Design Overview 46
  • 47. Bathurst Station Preliminary Design Architectural Concept: Preliminary Representation •subject to change 11/28/2011 Bathurst Station - Preliminary Design Overview 47
  • 48. Bathurst Station Preliminary Design Preliminary Representation •subject to change 11/28/2011 Bathurst Station - Preliminary Design Overview 48
  • 49. Bathurst Station Preliminary Design Preliminary Representation •subject to change 11/28/2011 Bathurst Station - Preliminary Design Overview 49
  • 50. Bathurst Station Preliminary Design 11/28/2011 Bathurst Station - Preliminary Design Overview 50
  • 51. Bathurst Station Preliminary Design 11/28/2011 Bathurst Station - Preliminary Design Overview 51