SlideShare ist ein Scribd-Unternehmen logo
1 von 26
tanzeem772@gmail.com 1
Overall Equipment Effectiveness
Md. Shafiul Alam Chowdhury
tanzeem772@gmail.com
tanzeem772@gmail.com 2
What is OEE ?
Overall Equipment Effectiveness (OEE) is a total measure
of performance that relates the availability of the process
to the productivity and quality.
tanzeem772@gmail.com 3
Why is OEE so important ?
• If you were told that your department was running flat out you might
reasonably assume that the equipment was running efficiently and
effectively.
• What if the equipment only ran for 75% of the time?
• What if when it ran it ran at 80% of its speed ?
• What if only 90% of the parts it made are good?
• Individually these performance measures seem to indicate an OK piece of
equipment, but is it a true picture?
• What’s impacting on these performance figures?
tanzeem772@gmail.com 4
How to measure OEE?
OEE =AVAILABILITY x PRODUCTIVITY x QUALITY
tanzeem772@gmail.com 5
OEE and Six Big Losses
Equipment Six Big Losses
Available time
Available operating time
Actual operating
time
Effective
operating
time
Breakdowns1
Setup / adjustment2
Idling / minor
stoppages3
Speed4
Defects in process
and rework5
Start up losses6
Total Available time
Planned Downtime
tanzeem772@gmail.com 6
Availability
“The percentage of time equipment is actually running when we need it”
AVAILABILITY= AVAILABLE TIME – UNPLANNED DOWNTIME x 100%
AVAILABLE TIME
Where:-
Available Time = Total Available Time – Planned Downtime*
Available time
Available operating time
Breakdowns1
Setup / adjustment2
*Note :- Planned Downtime could be PM, no scheduled work, breaks, etc.
tanzeem772@gmail.com 7
Planned v Unplanned Downtime
• Planned
– Excess capacity.
– Planned breaks.
– Planned Maintenance.
– Communications briefs / team meetings.
• Unplanned (Losses)
– Breakdowns.
– Set Ups and Adjustments.
– Late deliveries (material).
– Operator availability.
Note :
Planned time such as breaks, meetings and maintenance can be considered as losses (useful for
encouraging ideas on how to minimise their disruption) as long as a consistent approach is
taken.
tanzeem772@gmail.com 8
Productivity
“The difference between the potential output and actual output, when the equipment was
available”
PRODUCTIVITY = IDEAL CYCLE TIME x ACTUAL OUTPUT* x 100%
AVAILABLE OPERATING TIME
Available operating time
Actual operating
time
Idling / minor
stoppages3
Speed4
*Note :- Actual Output is the Quantity of good & bad parts
tanzeem772@gmail.com 9
Operating Speed v Productivity
• Operating Speed Rate
– The % of actual cycle time against ideal cycle time.
• Productivity
– The Operating Speed Rate factored with interruptions to constant
processing, i.e. idling and minor stoppages.
tanzeem772@gmail.com 10
Quality
“The total good parts produced expressed as a % of the total parts produced”
QUALITY= PARTS MADE – DEFECT QUANTITY x 100%
PARTS MADE
Actual operating
time
Effective
operating
time
Defects in process
and rework
5
Start up losses6
tanzeem772@gmail.com 11
Processed v Defect Quantity
• Parts Made
– The total quantity of parts produced in the available time.
• Defect Quantity
– The quantity of parts that did not meet the required standard (including
rework) in the available time.
Defect
Good
tanzeem772@gmail.com 12
OEE and the Six Big Losses
Equipment
Available time
Available operating time
Actual operating
time
Effective
operating
time
Six Big Losses
Breakdowns1
Setup / adjustment2
Idling / minor
stoppages3
Speed4
Defects in process
and rework5
Start up losses6
tanzeem772@gmail.com 13
Six Big Losses - What Are They ?
The time lost due to key
equipment breaking down or
deterioration which causes the
production to be stopped for
more than 10 min.
Six Big LossesSix Big Losses
Breakdowns1
Setup / adjustment2
Idling / minor
stoppages3
Speed4
Defects in process
and rework
5
Start up losses6
tanzeem772@gmail.com 14
Six Big Losses - What Are They ?
The time lost through “product
change over and adjustment ” to
the point where the production
of the new product is completely
satisfactory.
Breakdowns1
Setup / adjustment2
Idling / minor
stoppages3
Speed4
Defects in process
and rework
5
Start up losses6
Six Big LossesSix Big Losses
tanzeem772@gmail.com 15
Six Big Losses - What Are They ?
The time lost through key
equipment being stopped for
less than 10 min.
Time lost during the standard
cycle when the equipment is
not adding value.
Breakdowns1
Setup / adjustment2
Idling / minor
stoppages3
Speed4
Defects in process
and rework
5
Start up losses6
Six Big LossesSix Big Losses
tanzeem772@gmail.com 16
Six Big Losses - What Are They ?
The time lost through key
equipment not producing parts
at its optimum rate.
Breakdowns1
Setup / adjustment2
Idling / minor
stoppages3
Speed4
Defects in process
and rework
5
Start up losses6
Six Big LossesSix Big Losses
tanzeem772@gmail.com 17
Six Big Losses - What Are They ?
The time lost through key
equipment not producing parts
that meet the specified quality
standard.
The time lost through key
equipment being utilised to
rework sub-standard parts.
Breakdowns1
Setup / adjustment2
Idling / minor
stoppages3
Speed4
Defects in process
and rework
5
Start up losses6
Six Big LossesSix Big Losses
tanzeem772@gmail.com 18
Six Big Losses - What Are They ?
The time lost through key
equipment not producing parts
to the specified quality
standard, following start up
and before the equipment
achieves controllable
production conditions.
Breakdowns1
Setup / adjustment2
Idling / minor
stoppages3
Speed4
Defects in process
and rework
5
Start up losses6
Six Big LossesSix Big Losses
tanzeem772@gmail.com 19
Data Collection for OEE
• Key Points
– OEE is a measure of the equipment or process, not the operators productivity.
– Keep it simple.
– Ensure the process of measuring and applying OEE involves the people who use the
equipment.
– Make data collection second nature not a hindrance.
– Understand the process.
– Obtain the data on fixed frequency.
– Snap shot v continuous.
– Units of time (1 min, 10 mins, 30 mins, etc.).
– Automatic or manual data collection.
– Ownership.
– Partnership – those completing sheets and those collecting/collating.
– Regular communication of results.
– Response to trends, peaks and troughs.
tanzeem772@gmail.com 20
Data Collection for OEE
tanzeem772@gmail.com 21
Data Collection for OEE
tanzeem772@gmail.com 22
AVAILABILITY
Gross Time (in minutes) A
Planned Down Time (in minutes) B
Net Available Time (in minutes) C=A-B
Non planned stoppages (in minutes) D
Operating Time (in minutes) E=C-D
AVAILABILITY F = E/C
PRODUCTIVITY
Output G
Standard Cycle time (mins/ unit) H
PRODUCTIVITY I= (HxG)/E
QUALITY
Defect Quantity J
QUALITY K = (G-J)/G
Data Collection for OEE
tanzeem772@gmail.com 23
How to Eliminate Losses ?
tanzeem772@gmail.com 24
How Do We Use OEE?
• OEE is only a measure, its benefits will be lost if the
shortfalls it identifies are not acted upon.
• OEE is a total measure of performance but the data used to
produce it must be used to prioritise improvement tasks.
• The purpose of measurement is to identify losses, remove
waste and drive improvement.
• OEE should be used to support the Total Productive
Maintenance (TPM) approach and the tools it supplies.
tanzeem772@gmail.com 25
What are the benefits of OEE?
• FOCUS
– Highlight priorities for change.
• SIMPLICITY
– Even complex processes can be measured.
• FEEDBACK
– Before and after change.
• BENCHMARKING
– Objective comparisons.
• TARGET SETTING
– Setting achievable goals.
tanzeem772@gmail.com 26
OEE
OEE
Solving Problems
OEE
Weekly
Production
MRP
Daily
APS Meeting
Support NC OPS
Log. Maintenance
Quality
Customer protection
Counter measure
Equip. uptime
Improve Quality
Improve Performance
2
Weeks
24
Hours
OEE
X Hours

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (20)

TPM the effective maintenance with Autonomous Maintenance
TPM the effective maintenance with Autonomous MaintenanceTPM the effective maintenance with Autonomous Maintenance
TPM the effective maintenance with Autonomous Maintenance
 
[Partial Preview:] Overall Equipment Effectiveness (OEE)
[Partial Preview:] Overall Equipment Effectiveness (OEE)[Partial Preview:] Overall Equipment Effectiveness (OEE)
[Partial Preview:] Overall Equipment Effectiveness (OEE)
 
Autonomous maintenance Jishu Hozen
Autonomous maintenance Jishu HozenAutonomous maintenance Jishu Hozen
Autonomous maintenance Jishu Hozen
 
Overall Equipment Effectiveness
Overall Equipment EffectivenessOverall Equipment Effectiveness
Overall Equipment Effectiveness
 
Overall equipment effectiveness
Overall equipment effectivenessOverall equipment effectiveness
Overall equipment effectiveness
 
20141209_AM Pillar_Introduction
20141209_AM Pillar_Introduction20141209_AM Pillar_Introduction
20141209_AM Pillar_Introduction
 
tpm presentation
tpm presentationtpm presentation
tpm presentation
 
Tpm basic
Tpm basicTpm basic
Tpm basic
 
Mistake proofing for web1
Mistake proofing for web1Mistake proofing for web1
Mistake proofing for web1
 
Oee (overall equipment effectifness)
Oee (overall equipment effectifness)Oee (overall equipment effectifness)
Oee (overall equipment effectifness)
 
16 major losses tng
16 major losses tng16 major losses tng
16 major losses tng
 
Autonomous maintenance ppt
Autonomous maintenance pptAutonomous maintenance ppt
Autonomous maintenance ppt
 
Tools of lean mfg
Tools of lean mfgTools of lean mfg
Tools of lean mfg
 
Jishu hozen
Jishu  hozenJishu  hozen
Jishu hozen
 
Tpm
TpmTpm
Tpm
 
Lean Tools
Lean ToolsLean Tools
Lean Tools
 
Ch 7 qm
Ch 7 qmCh 7 qm
Ch 7 qm
 
OEE-Practical-1.pptx
OEE-Practical-1.pptxOEE-Practical-1.pptx
OEE-Practical-1.pptx
 
TPM - tech talk
TPM - tech talk TPM - tech talk
TPM - tech talk
 
Autonomous maintenance training
Autonomous maintenance trainingAutonomous maintenance training
Autonomous maintenance training
 

Andere mochten auch (17)

Oee guide
Oee guideOee guide
Oee guide
 
The 7 deadly sins of Overall Equipment Effectiveness (OEE)
The 7 deadly sins of Overall Equipment Effectiveness (OEE)The 7 deadly sins of Overall Equipment Effectiveness (OEE)
The 7 deadly sins of Overall Equipment Effectiveness (OEE)
 
OEE
OEEOEE
OEE
 
6 OEE overview
6 OEE overview6 OEE overview
6 OEE overview
 
NG BB 17 Takt Time
NG BB 17 Takt TimeNG BB 17 Takt Time
NG BB 17 Takt Time
 
The Six Big Losses of OEE
The Six Big Losses of OEEThe Six Big Losses of OEE
The Six Big Losses of OEE
 
NG BB 18 Theory of Constraints
NG BB 18 Theory of ConstraintsNG BB 18 Theory of Constraints
NG BB 18 Theory of Constraints
 
Total Productive Maintenance - TPM
Total Productive Maintenance - TPM Total Productive Maintenance - TPM
Total Productive Maintenance - TPM
 
Tpm Presentation
Tpm PresentationTpm Presentation
Tpm Presentation
 
TPM. DR. K. BARANIDHARAN
TPM. DR. K. BARANIDHARANTPM. DR. K. BARANIDHARAN
TPM. DR. K. BARANIDHARAN
 
Presentation on Total Productive Maintenance
Presentation on Total Productive MaintenancePresentation on Total Productive Maintenance
Presentation on Total Productive Maintenance
 
Total Productive Maintenance
Total Productive MaintenanceTotal Productive Maintenance
Total Productive Maintenance
 
Value Stream Mapping: Case Studies
Value Stream Mapping: Case StudiesValue Stream Mapping: Case Studies
Value Stream Mapping: Case Studies
 
Value Stream Mapping Process
Value Stream Mapping ProcessValue Stream Mapping Process
Value Stream Mapping Process
 
Value stream mapping ppt
Value stream mapping pptValue stream mapping ppt
Value stream mapping ppt
 
Takt Time, Cycle Time & Line Balancing
Takt Time, Cycle Time & Line BalancingTakt Time, Cycle Time & Line Balancing
Takt Time, Cycle Time & Line Balancing
 
Value stream mapping training
Value stream mapping trainingValue stream mapping training
Value stream mapping training
 

Ähnlich wie OEE

Top OEE & Lean Manufacturing Terms Explained
Top OEE & Lean Manufacturing Terms ExplainedTop OEE & Lean Manufacturing Terms Explained
Top OEE & Lean Manufacturing Terms ExplainedJon Addison
 
Generic Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S DesrocherGeneric Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S DesrocherAlan Desrocher
 
Ask the Expert: Lean Leadership - Can We Talk About OEE?
Ask the Expert: Lean Leadership - Can We Talk About OEE?Ask the Expert: Lean Leadership - Can We Talk About OEE?
Ask the Expert: Lean Leadership - Can We Talk About OEE?MileyJames
 
Equipment reliability l1
Equipment reliability l1Equipment reliability l1
Equipment reliability l1Matthew Clemens
 
SMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction ProcessSMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction ProcessW3 Group Canada Inc.
 
Productivity related Vital Measures through simulations
Productivity related Vital Measures through simulationsProductivity related Vital Measures through simulations
Productivity related Vital Measures through simulationsSameer Kumar
 
Lean manufacturing presentation in pharmaceuticals industry
Lean manufacturing presentation in pharmaceuticals industryLean manufacturing presentation in pharmaceuticals industry
Lean manufacturing presentation in pharmaceuticals industrypraaditya2020
 
Total productivity maintenance
Total productivity maintenanceTotal productivity maintenance
Total productivity maintenanceFELIX JONATHAN
 
Design For OEE (DFOEE)
Design For OEE (DFOEE)Design For OEE (DFOEE)
Design For OEE (DFOEE)Lean Teams USA
 

Ähnlich wie OEE (20)

OEE CALCULATION PPT
OEE CALCULATION PPTOEE CALCULATION PPT
OEE CALCULATION PPT
 
Top OEE & Lean Manufacturing Terms Explained
Top OEE & Lean Manufacturing Terms ExplainedTop OEE & Lean Manufacturing Terms Explained
Top OEE & Lean Manufacturing Terms Explained
 
Generic Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S DesrocherGeneric Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S Desrocher
 
Oee part 2
Oee part  2 Oee part  2
Oee part 2
 
om
omom
om
 
OEE Webinar
OEE WebinarOEE Webinar
OEE Webinar
 
Ask the Expert: Lean Leadership - Can We Talk About OEE?
Ask the Expert: Lean Leadership - Can We Talk About OEE?Ask the Expert: Lean Leadership - Can We Talk About OEE?
Ask the Expert: Lean Leadership - Can We Talk About OEE?
 
OEE vs TEEP.pdf
OEE vs TEEP.pdfOEE vs TEEP.pdf
OEE vs TEEP.pdf
 
The mystery of OEE
The mystery of OEEThe mystery of OEE
The mystery of OEE
 
OEE.pptx
OEE.pptxOEE.pptx
OEE.pptx
 
Office_Lean_sample
Office_Lean_sampleOffice_Lean_sample
Office_Lean_sample
 
Office Lean Sample
Office Lean SampleOffice Lean Sample
Office Lean Sample
 
Equipment reliability l1
Equipment reliability l1Equipment reliability l1
Equipment reliability l1
 
SMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction ProcessSMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction Process
 
Productivity related Vital Measures through simulations
Productivity related Vital Measures through simulationsProductivity related Vital Measures through simulations
Productivity related Vital Measures through simulations
 
Lean manufacturing presentation in pharmaceuticals industry
Lean manufacturing presentation in pharmaceuticals industryLean manufacturing presentation in pharmaceuticals industry
Lean manufacturing presentation in pharmaceuticals industry
 
Tools of lean mfg
Tools of lean mfgTools of lean mfg
Tools of lean mfg
 
Total productivity maintenance
Total productivity maintenanceTotal productivity maintenance
Total productivity maintenance
 
Overall Equipment Efficiency
Overall Equipment EfficiencyOverall Equipment Efficiency
Overall Equipment Efficiency
 
Design For OEE (DFOEE)
Design For OEE (DFOEE)Design For OEE (DFOEE)
Design For OEE (DFOEE)
 

OEE

  • 1. tanzeem772@gmail.com 1 Overall Equipment Effectiveness Md. Shafiul Alam Chowdhury tanzeem772@gmail.com
  • 2. tanzeem772@gmail.com 2 What is OEE ? Overall Equipment Effectiveness (OEE) is a total measure of performance that relates the availability of the process to the productivity and quality.
  • 3. tanzeem772@gmail.com 3 Why is OEE so important ? • If you were told that your department was running flat out you might reasonably assume that the equipment was running efficiently and effectively. • What if the equipment only ran for 75% of the time? • What if when it ran it ran at 80% of its speed ? • What if only 90% of the parts it made are good? • Individually these performance measures seem to indicate an OK piece of equipment, but is it a true picture? • What’s impacting on these performance figures?
  • 4. tanzeem772@gmail.com 4 How to measure OEE? OEE =AVAILABILITY x PRODUCTIVITY x QUALITY
  • 5. tanzeem772@gmail.com 5 OEE and Six Big Losses Equipment Six Big Losses Available time Available operating time Actual operating time Effective operating time Breakdowns1 Setup / adjustment2 Idling / minor stoppages3 Speed4 Defects in process and rework5 Start up losses6 Total Available time Planned Downtime
  • 6. tanzeem772@gmail.com 6 Availability “The percentage of time equipment is actually running when we need it” AVAILABILITY= AVAILABLE TIME – UNPLANNED DOWNTIME x 100% AVAILABLE TIME Where:- Available Time = Total Available Time – Planned Downtime* Available time Available operating time Breakdowns1 Setup / adjustment2 *Note :- Planned Downtime could be PM, no scheduled work, breaks, etc.
  • 7. tanzeem772@gmail.com 7 Planned v Unplanned Downtime • Planned – Excess capacity. – Planned breaks. – Planned Maintenance. – Communications briefs / team meetings. • Unplanned (Losses) – Breakdowns. – Set Ups and Adjustments. – Late deliveries (material). – Operator availability. Note : Planned time such as breaks, meetings and maintenance can be considered as losses (useful for encouraging ideas on how to minimise their disruption) as long as a consistent approach is taken.
  • 8. tanzeem772@gmail.com 8 Productivity “The difference between the potential output and actual output, when the equipment was available” PRODUCTIVITY = IDEAL CYCLE TIME x ACTUAL OUTPUT* x 100% AVAILABLE OPERATING TIME Available operating time Actual operating time Idling / minor stoppages3 Speed4 *Note :- Actual Output is the Quantity of good & bad parts
  • 9. tanzeem772@gmail.com 9 Operating Speed v Productivity • Operating Speed Rate – The % of actual cycle time against ideal cycle time. • Productivity – The Operating Speed Rate factored with interruptions to constant processing, i.e. idling and minor stoppages.
  • 10. tanzeem772@gmail.com 10 Quality “The total good parts produced expressed as a % of the total parts produced” QUALITY= PARTS MADE – DEFECT QUANTITY x 100% PARTS MADE Actual operating time Effective operating time Defects in process and rework 5 Start up losses6
  • 11. tanzeem772@gmail.com 11 Processed v Defect Quantity • Parts Made – The total quantity of parts produced in the available time. • Defect Quantity – The quantity of parts that did not meet the required standard (including rework) in the available time. Defect Good
  • 12. tanzeem772@gmail.com 12 OEE and the Six Big Losses Equipment Available time Available operating time Actual operating time Effective operating time Six Big Losses Breakdowns1 Setup / adjustment2 Idling / minor stoppages3 Speed4 Defects in process and rework5 Start up losses6
  • 13. tanzeem772@gmail.com 13 Six Big Losses - What Are They ? The time lost due to key equipment breaking down or deterioration which causes the production to be stopped for more than 10 min. Six Big LossesSix Big Losses Breakdowns1 Setup / adjustment2 Idling / minor stoppages3 Speed4 Defects in process and rework 5 Start up losses6
  • 14. tanzeem772@gmail.com 14 Six Big Losses - What Are They ? The time lost through “product change over and adjustment ” to the point where the production of the new product is completely satisfactory. Breakdowns1 Setup / adjustment2 Idling / minor stoppages3 Speed4 Defects in process and rework 5 Start up losses6 Six Big LossesSix Big Losses
  • 15. tanzeem772@gmail.com 15 Six Big Losses - What Are They ? The time lost through key equipment being stopped for less than 10 min. Time lost during the standard cycle when the equipment is not adding value. Breakdowns1 Setup / adjustment2 Idling / minor stoppages3 Speed4 Defects in process and rework 5 Start up losses6 Six Big LossesSix Big Losses
  • 16. tanzeem772@gmail.com 16 Six Big Losses - What Are They ? The time lost through key equipment not producing parts at its optimum rate. Breakdowns1 Setup / adjustment2 Idling / minor stoppages3 Speed4 Defects in process and rework 5 Start up losses6 Six Big LossesSix Big Losses
  • 17. tanzeem772@gmail.com 17 Six Big Losses - What Are They ? The time lost through key equipment not producing parts that meet the specified quality standard. The time lost through key equipment being utilised to rework sub-standard parts. Breakdowns1 Setup / adjustment2 Idling / minor stoppages3 Speed4 Defects in process and rework 5 Start up losses6 Six Big LossesSix Big Losses
  • 18. tanzeem772@gmail.com 18 Six Big Losses - What Are They ? The time lost through key equipment not producing parts to the specified quality standard, following start up and before the equipment achieves controllable production conditions. Breakdowns1 Setup / adjustment2 Idling / minor stoppages3 Speed4 Defects in process and rework 5 Start up losses6 Six Big LossesSix Big Losses
  • 19. tanzeem772@gmail.com 19 Data Collection for OEE • Key Points – OEE is a measure of the equipment or process, not the operators productivity. – Keep it simple. – Ensure the process of measuring and applying OEE involves the people who use the equipment. – Make data collection second nature not a hindrance. – Understand the process. – Obtain the data on fixed frequency. – Snap shot v continuous. – Units of time (1 min, 10 mins, 30 mins, etc.). – Automatic or manual data collection. – Ownership. – Partnership – those completing sheets and those collecting/collating. – Regular communication of results. – Response to trends, peaks and troughs.
  • 22. tanzeem772@gmail.com 22 AVAILABILITY Gross Time (in minutes) A Planned Down Time (in minutes) B Net Available Time (in minutes) C=A-B Non planned stoppages (in minutes) D Operating Time (in minutes) E=C-D AVAILABILITY F = E/C PRODUCTIVITY Output G Standard Cycle time (mins/ unit) H PRODUCTIVITY I= (HxG)/E QUALITY Defect Quantity J QUALITY K = (G-J)/G Data Collection for OEE
  • 23. tanzeem772@gmail.com 23 How to Eliminate Losses ?
  • 24. tanzeem772@gmail.com 24 How Do We Use OEE? • OEE is only a measure, its benefits will be lost if the shortfalls it identifies are not acted upon. • OEE is a total measure of performance but the data used to produce it must be used to prioritise improvement tasks. • The purpose of measurement is to identify losses, remove waste and drive improvement. • OEE should be used to support the Total Productive Maintenance (TPM) approach and the tools it supplies.
  • 25. tanzeem772@gmail.com 25 What are the benefits of OEE? • FOCUS – Highlight priorities for change. • SIMPLICITY – Even complex processes can be measured. • FEEDBACK – Before and after change. • BENCHMARKING – Objective comparisons. • TARGET SETTING – Setting achievable goals.
  • 26. tanzeem772@gmail.com 26 OEE OEE Solving Problems OEE Weekly Production MRP Daily APS Meeting Support NC OPS Log. Maintenance Quality Customer protection Counter measure Equip. uptime Improve Quality Improve Performance 2 Weeks 24 Hours OEE X Hours

Hinweis der Redaktion

  1. 1st Animation - If you were told……. 2nd Animation - What if the equipment….. 3rd Animation - What if when it ran…….. 4th Animation - What if only ……. 5th Animation - Individually these ……. 6th Animation - What’s impacting ……..
  2. OEE is simply a combination of three other measures - availability, productivity and quality, which by themselves do not tell the full story.
  3. Animation - Activate randomly as you talk through. An ideal manufacturing environment means that equipment will be available to use when you want to use it! Typically the “Effective Operating Time” is limited by a number of key reasons. From the “Total Available Time” first take the “Planned Downtime”, such as breaks, planned maintenance, no scheduled work, etc. Waste restricts the “Available Time” even further Collectively these key waste elements which effect Availability, Productivity and Quality, are known as the “6 Big Losses”. These losses effect the “Available Time” in the following manner.
  4. Introduce the equation in basic terms. 1st Animation - Available time Starting with the Total Available time (this could be for a fixed time period (3 hrs), the full shift, 24 hours, etc.), less the time that you don’t wish to be considered, such as planned breaks, meetings and maintenance. To give you the Available time. 2nd Animation - Available operating time The Available operating time is, therefore, the Available time less Breakdowns and Setup / Adjustment. Prior to next slide ask for examples of Planned v Unplanned Downtime.
  5. Reasons for classifying breaks, meetings, etc. as losses can be when trying to encourage creative thinking around necessary activities, e.g. staggered break times, more efficient meetings, etc.
  6. Introduce the equation in basic terms. 1st Animation - Available operating time After the losses that effect Availability have been accounted for this leaves Available operating time. 2nd Animation - Actual operating time Further losses occur which effect productivity and leave Actual operating time. Those key losses includeIdling / minor stoppages and Speed.
  7. Ask for reasons why the operating speed might not be equal to the ideal cycle:- Hidden machine problems (electrical/mechanical) The Standard is not known The Standard has not been communicated In short, a lack of focus on it
  8. Introduce the equation in basic terms. 1st Animation - Actual operating time After the losses that effect Availability and Productivity have been accounted for this leaves Actual operating time. 2nd Animation - Effective operating time Further losses occur which effect Quality and leave Effective operating time. Those key losses includeDefects in process and rework and Start up losses
  9. The biggest loss to production is often the time required to re-work a component to the required quality standard. This can often be longer than the original process time.
  10. So we’ve seen how the effective operating time for a piece of equipment can be reduced due to ineffective working practices and conditions. What are the “6 Big Losses”? These 6 types of losses should give you a start point for the data to be collected and the areas to be targeted as part of the OEE study.
  11. More than 10 mins from the point the machine stopped adding value to the component to the point which it starts again.
  12. The time from the last complete component (operation) to the start of the first new component (operation), under stable conditions, i.e. the equipment must be capable of repeatable performance.
  13. Minor stoppages to the process. Examples :-Change a drill bit Top up lubrication Adjust the speeds and feeds Check the quality
  14. It is vital that the standards are known and adhered. This measure is often able to be generated automatically by the equipment.
  15. The biggest loss to production is often the time required to re-work a component to the required quality standard. This can often be longer than the original process time.
  16. It is often the case that equipment, particularly older equipment, will not run to a consistent quality until it has “warmed up sufficiently, i.e. after prolonged stoppages when the hydraulic systems have been “cold” for some time”. There may also be losses at start up which effect speed and breakdowns, i.e. machines may not get to full operating speed immediately and a high % of breakdowns occur when machines are “cold”.
  17. Stress the need for the team approach and that the people operating pieces of equipment are best placed to identify their problems (using their 5 senses) and potential solutions. Operators must be involved in how the data will be collected and the counter measures that arise from them.
  18. Remember that the method for collecting OEE is determined by the equipment you are monitoring, i.e. the level and detail required will be determined by how much is already known of the equipment and how far along the process you are, i.e. start with broad categories of losses and bring in more detail as more is learnt. Picking a suitable period for measurement and scale of measurement is also key, too much detail can lead to too much wasted time by operators in completing the data sheets, swiftly leading to a lack of belief in the process.
  19. Remember that the method for collecting OEE is determined by the equipment you are monitoring, i.e. the level and detail required will be determined by how much is already known of the equipment and how far along the process you are, i.e. start with broad categories of losses and bring in more detail as more is learnt. Picking a suitable period for measurement and scale of measurement is also key, too much detail can lead to too much wasted time by operators in completing the data sheets, swiftly leading to a lack of belief in the process.
  20. Set up the number crunching in as simple a format as possible, if only a limited number of machines are being monitored, keep the process manual. If there is a significant level of detail and/or a large number of pieces of equipment being monitored, then a spreadsheet to do the hard work would be recommended.
  21. Many of the common tools within the umbrella of Lean will be important when addressing the losses identified as part of the OEE data collection. These examples are not the whole picture but together with other methodologies now included within the APS, all the issues identified can be tackled in a systematic manner.
  22. OEE is a measure it will do nothing by itself! OEE must be used as part of a total approach to equipment effectiveness. Track the losses and draw a pareto chart to identify the biggest losses. Problem solve the biggest losses to identify root cause and implement permanent corrective actions.
  23. In summary, the benefits of using OEE are:- FOCUS:Identifies what the largest losses are SIMPLICITY:One measure to express a machines performance FEEDBACK:How do you judge an improvement unless you can measure it.You must be able to measure before and after. BENCHMARKING :How do you know how effective your process or equipment is, unless you have an objective measure to compare with other businesses, departments, etc. TARGET SETTING :You need to be able to set goals and targets in order to measure the effectiveness of the counter measures.
  24. Explain the schematic to the delegates in detail. Emphasise the fact that data is drawn from the machines BY the operator, and fed into an OEE chart, this then gives us valuable information that we can base improvements on. (such as performance, quality and equipment uptime improvements!!!) This valuable information is also fed into a number of review sessions (such as the APS Meeting review)