SlideShare ist ein Scribd-Unternehmen logo
1 von 45
Downloaden Sie, um offline zu lesen
1
PUBLIC PRIVATE PARTNERSHIP
INITIATIVES IN TAMIL NADU
Vikram Kapur, IAS
MD & CEO
TN Urban Infrastructure Financial Services Ltd
Chennai
2
BACKGROUND
• TN - most urbanized state in India
• 43% population lives in urban areas
• Rate of growth of urbanization is 5%
• 6 Corporations and 152 Municipalities
• Present urban infrastructure not sufficient to provide
quality services to the citizens
• Urban areas contribute more than 70% of GDP in TN
• Organic linkage between economic growth and
infrastructure development
3
PPP – BENEFITS TO GOVT
• Leveraging scarce budgetary resources of Govt
• Ownership of underlying public assets to continue to vest
with Govt
• Channelizing innovative and modern management
practices from private sector in
Project development and structuring
Resource mobilization
Asset management and preservation
• Project up-sides to be shared by Govt, while capping its
liabilities
• Preferred mechanism for outsourcing operations and
maintenance of viable public assets
4
PPP – BENEFITS TO PRIVATE
PARTNER
• Policy level and statutory support by Govt
• Handholding by Govt to resolve bottlenecks as in land
acquisition, R&R, clearances and approvals
• Limited financial assistance by Govt for ensuring viability
• Govt participation to enhance lender confidence, enabling
mobilization of cheaper funds
• Continuing policy and O&M support from Govt
throughout project concession period
5
SECTORS IDENTIFIED FOR PPP
• Water supply and sewerage
• Road infrastructure (roads, bridges and flyovers)
• Improvement of urban infrastructure
• Port infrastructure
• Computer literacy in school education
6
PPP ORGANIZATIONS FORMED
IN TAMIL NADU
• Tamil Nadu Water Investment Company (TWIC)
– Promoted by GoTN and IL&FS to develop water projects
– Established New Tirupur Area Development Corporation Ltd
(NTADCL) as SPV for supply of industrial and drinking water under
Tirupur Water and Sanitation Project
• Tamil Nadu Road Development Company (TNRDC)
– JV of TIDCO and IL&FS (50:50) to develop road projects
– East Coast Road (ECR) Project
• Tamil Nadu Urban Development Fund (TNUDF)
– Formed with Fis like ICICI, IL&FS and HDFC
– Implementing World Bank assisted TN Urban Development Project
• Ennore Port SEZ
7
TIRUPUR WATER & SANITATION
PROJECT
8
Genesis
• Despite international recognition as a major export centre for knitwear,
Tirupur lacks quality infrastructure
– Domestic water supply is limited to a few hours on alternate days
– Industries do not have access to piped supply
– Depleted ground water in the region
• Investment in infrastructure is critical for a future Tirupur
• A comprehensive program (TADP) was formulated to address the
infrastructure needs of the town
• Lack of budgetary resources prompted local industry to spearhead
implementation of TADP on a commercial format
• New Tirupur Area Development Corporation Limited (NTADCL) was
formed as the company to implement the TADP
9
Summary Terms of Concession Agreement
• Concession Model : Build-Own-Operate-Transfer (BOOT)
• Concession Period : 30 years
• Concession Grantor : GoTN and Tirupur Municipality
• Concessionaire Co. : New Tirupur Area Development
• Recovery mechanism : Composite water and sewerage charges
• Tariff revision : Annual revision linked to indexation;
Unusual increases to be approved by
Price Review Committee
• Transfer of Water Assets : At the end of the concession period
• Base Project Return : 20% pa on 185 Mld project cost
• Franchise Protection : Exclusive rights for service
10
Concession Agreement - Investment Matrix
NTADCL
Value Added Franchise
Backbone
Investment
Productivity Investments to
increase supply by 65 MLD
Waste Water Recycling
Bottled Water Supply
Water Supply
Sanitation
11
Scope
• Water Supply 185 Mld (250 Mld)
• Urban Population 3,46,551 (2001 Census Figure)
• Rural/Semi Urban Population 4,00,266 (2001 Census Figure)
• Industry 730 Units
• Sanitation Coverage 60% of Households of Tirupur
• Low Cost Sanitation for Slums
12
Schematic of Water Supply Scheme
Netaji App. Uthukali Perundurai Kanchikoil
Park (3.9 Mld) Chennimalai (2.7 Mld) 185 Mld
(1.0 mld) (8.4 Mld)
56 km Steel Pumping Main from WTP to MBR (1400 & 1200 mm dia)
Booster Water Intake at
PS Treatment Cauvery
Plant
LEGEND
PS Pumping Station
FM-I to TM MBR Master Balancing Reservoir
(9 DS) FM Feeder Main
TM Tirupur Municipality
FM-II to FM-III to DS Distribution Station
TLPA TLPA TLPA Tirupur Local Planning Area
(17 DS) (9 DS)
MBR
(23 Ml)
13
Project Structure
IL&FS
Project Sponsor
GoTN
- Project Sponsor
- Land and Right of Way
- Grant of Concession
Equity Investors
TWICL
Contractor
Consortium
Pvt Equity Funds
NTADCL
-Execution of the Project
- O&M of the Project
- Beneficiary of Concession
Terms
USERS
Lenders
Consortium led by
IDBI and SBI
Water
Charges
EPC CONTRACTOR
(WSA,, M&M, L&T, HCC)
O&M CONTRACTOR
(M&M & United Utilities)
Service
Concession Agreement
14
Project Implementation & Monitoring
Structure
• Concessionnaire : NTADCL
• Project Sponsors : TWICL (GOTN and IL&FS)
• Construction Contractors
– Advance Engineering : Bechtel Enterprises, USA
– EPC 1 Contractors : Hindustan Construction Co. Ltd.
– EPC 2 Contractors : Mahindra & Mahindra and Larsen & Toubro Ltd
• Operation & Maintenance: United Utilities, U.K and Mahindra & Mahindra
• Project Managers : Wilbur Smith Associates, USA
• Lenders Engineer : Pell Frischmann Water, U.K.
• Owners Engineer : GKW Consult, Germany and CES, New Delhi
• Independent Auditor : SB Billimoria, Chartered Accountants
15
Components of the Tirupur Project
• EPC1
River Intake Well and Pumping station
Water Treatment Plant & Booster Pumping Station
Transmission Main – 56 kms
Master Balancing Reservoir ( 23 Mn Ltrs)
• EPC 2
Feeder Mains 1, 2 and 3 – 93 kms
Water Distribution Stations – 36 Nos.
Distribution Network – 219 kms
Distribution Network to Wayside Villages
Sewerage System – 124 kms
Low Cost Sanitation
16
Total Landed Cost and Means of Finance
Rs Crores
• EPC Cost 650
• Owners Cost 127
• Contingency 93
• Interest During Construction 142
• Initial Working Capital 11
Total 1023
• The project cost of Rs 1023 cr is proposed to be financed through a
debt : equity ratio of 1.5 : 1
Equity 322.70
Subordinate Debt 86.50
Debt 613.80
17
Equity Structure
Equity Sub debt
GOTN 30 25
Equity Sub debt
IL&FS 35 15
TWICL
Equity 65 Sub debt 40
Total 105
AIDEC Fund 90 LIC 20
GIC 15 Contractors 45
Tirupur 10 Others 37.7
Industry
NTADCL
TWICL 105
Others 217.7
TOTAL 322.7
18
Allocation of Risks
• Government of
Tamil Nadu
– Political Force
Majeure
– Water Source
– Power
– Permissions
– Change in tax /
law
• NTADCL
– Commercial
– Construction
– Operations
– Insurable Force
Majeure
19
Innovative Financial Structuring
• Non recourse financing
• Issuance of a 30 year bond in the US Capital Market:
• Guarantee under the FIRE program
• Support of USAID in timing of issuance enhanced credibility of the
Project
•
• Fund for DSR using a contingent recourse structure
• Project financing with capped contingent liabilities on GoTN
• Risk Participation Agreements
• Sharing of upsides with consumers in the form of price relief
• Formulation of risk allocation matrix to allow for re-pricing
20
Value of Project to Tirupur
• Industry would collapse without it, and prosper with it
• Project strength: commercial viability and Social dimensions
• Pro-poor image
• Social Benefits - Health
• Environment
21
Value of NTADCL to Tirupur
• Facilitate industrial growth
• Effluent Treatment
• Apparel Park
• IIUS
– Exhibition & Convention Center
– Working Women’s Hostels
– R & D Center
– Roads
– Traffic De-congestion
• Social Forestry – Avenue & Schools
• Recreation Parks
• Social Study
22
PPP Strengths and Effectiveness - I
• Robust and Dynamic structure
• Arm’s length from the Govt.
• Government ownership high
• Governance structure ensures :
– Allaying of private sector concerns
– Social issues are addressed comprehensively
– consumer interests are safeguarded
• Commercial interest protected
23
PPP Strengths and Effectiveness - II
• PPP model domiciles risk to parties that are well equipped to
deal with them
• Transparent and well-conceived contracts
• Documentation recognizes rights and responsibilities of all
project related parties
• Concerns of all stakeholders addressed
• Examples of contracts :
– Concession Agreement
– Bulk Water Supply Agreement
– Shareholders’ Agreement
– Common Loan Agreement
– EPC and O&M Contracts
24
PPP Strengths and Effectiveness – III
• The PPP model is an effective format for implementing infrastructure
projects
• But it has its own challenges which need to be recognized
• PPP format involves the participation of a large number of Institutions:
– Government, Politicians, Banks, Financial Institutions, Investors, Contractors,
Consumers, NGO’s, etc.
– Each of these entities recognize the benefits of the project.
• But as the project develops, they exert pulls and pressures to enhance and
further their own narrow institutional interests
• The project development exercise requires addressing each of these
issues without losing the integrity of the project concept
25
What This Project Has Established
• As a pioneer project it has established:
– Demand-driven projects are inherently strong.
– Commercial formatting of projects is possible
– Private participation in the sector is viable
– Returns can be commensurate with risks
– Willingness to pay for efficient services
– Internal cross subsidy to reach the poor
– Healthy precedent to ease learning curves
26
Current Status of Project
• Construction commenced October 28, 2002
• Water supply already commenced
• Sewerage component to be completed shortly
27
TAMIL NADU ROAD
DEVELOPMENT COMPANY
• TNRDC a 50:50 JV between TIDCO & IL&FS which
have contributed Rs.5 crore each as share capital
• East Coast Road (ECR) project
– Initial improvement works (Rs.61 crore) and maintenance during
Concession Period of 30 years
– Recovery of initial investment, O&M and returns (capped at 20%)
by levy of nominal tolls; surpluses to be reinvested in road sector
– Project funding
• Equity: Rs.10 crore
• Sub Debt: Rs.10 crore
• Senior Non Convertible Debenture: Rs.41 crore
28
TAMIL NADU URBAN
DEVELOPMENT FUND (TNUDF)
• A non-guaranteed fund managed by a private AMC
• Established in November 1996 as a Trust
• GoTN (Rs.143 cr), ICICI (23 cr), HDFC (Rs.17 cr), IL&FS (Rs.17 cr)
• Policies and procedures by TNUITCL (FIs – 51% & GoTN – 49%)
• Managed by TNUIFSL (FIs – 51% & GoTN – 49%)
• Private Public Partnership arrangement to channelize private capital in
municipal infrastructure
• Object is to raise resources and to provide long term finance to ULBs
• Resources - Unit Capital and Line of Credit by IBRD through GoTN
• Flow of funds
– World Bank to GoI by Project’s Special A/c
– GoI to GoTN - pass through arrangement
– GoTN to TNUDF / CMA / Grant Fund
– TNUDF / Grant Fund to ULB
29
INITIATIVES UNDER TNUDF
• Rs.30 crore mobilized from first Revenue Bond for
Madurai Inner Ring Road
• First toll bridge on BOT model costing Rs.15 crore (Karur)
• First sewerage treatment plant (STP) on BOT model
costing Rs.6.63 crore (Alandur municipality)
• Rs.110 crore mobilized from domestic capital market for
municipal infrastructure
• Rs.51 crore mobilized by way of equity participation
• Rs.30 crore mobilized through pooled finance on lines of
US Bond Bank model (Water & Sanitation Pooled Fund)
TNUDP III
• Is a follow up project of TNUDP II
• Project launched on 19th October 2005
• Project Size : US $ 434 m
– World Bank : US $ 300 m
– GoTN : US $ 84 m
– Others : US $ 50 m
GoTN
• IDC to CMA : US $ 10 m
• Capital Grants to ULB : US $ 48 m
• Grants to CMA : US $ 26 m
Others
• ULB : US $ 10 m
• Market Borrowing by TNUDF : US $ 40 m
TNUDP-III
• Loan & Project Agreement - effective on 19th October,
2005
• Project period : 5 years
• Objectives
– Develop TNUDF as a financial intermediary to provide finance
for infrastructure in ULBs on a sustainable basis
– Strength urban reforms and consolidate the achievements under
TNUDP II
– Institutional strengthening and capacity building
– Provide grant to CMDA for traffic and transportation.
COMPONENTS
• Institutional Development component (IDC)
– World Bank : 15 US $ m
– GoTN : 10 US $ m
• Urban Investment component (UIC)
– World Bank : 146.5 US $ m
(Loan 110, Grant 46.50, PDA 3)
– GoTN : 48 US $ m
• Grant to CMDA
– World Bank : 124 US $ m
– GoTN : 26 US $ m
Funding Pattern – Break UpUS $ M
434.00134.00300.00TOTAL PROJECT COST
1.501.50Front End Fee
150.0026.00124.00Grants to CMDA - by TNUIFSL
257.5098.00159.50Total
3.003.00Project Development Advisory
94.5048.0046.50Capital grants to ULBs
160.0050.00110.00Loans to ULBs
UIC - by TNUDF
25.0010.0015.00IDC - by CMA
Total CostGoTN
Finance
Bank
Finance
Component
Pipeline of Projects
• Water supply Project : 11 projects; Sanctioned Loan of
Rs.90 crs and Grant of Rs. 36 crs for 10 projects.
• UGD Projects : 16 projects: Sanctioned Loan of Rs.272
crs and Grant of Rs. 80 crs for 11 projects.
• Road and SWM Projects: Sanctioned Loan of Rs.75 crs
and grant of Rs 33 crs sanctioned.
• Total - Loan of Rs. 437 crs, and grant of Rs.149 crores
sanction (Rs. 586 crs).
• Amount disbursed : Rs.14.90 crs
35
TNUDF’s Portfolio in Urban
Infrastructure
TNUDF's Sector Wise Portfolio (Sanctions)
Bus Statio ns and
Markets
4%
Sewerage &Sanitatio n
38%
Water Supply
17%
Stro m Water Drains
1%
Others
1%
Bridges and Ro ads
39%
Bridges and Ro ads
Bus Statio ns and Markets
Sewerage &Sanitatio n
Water Supply
Stro m Water Drains
Others
36
TNUDF - Innovative Financing
1. Karur Bridge –
Facilitated first toll bridge contracted by an
ULB in India – cost Rs.16 crores
Predictable cash flow
TN State Toll Act amended to facilitate ULB
to enter into BoT contract – stable regulatory
framework
37
KARUR TOLL BRIDGE
38
Contd…
2. Alandur Underground Drainage – Rs.34 crores
Initial tariff Rs.150 per house per month –
very high
TNUDF organised people’s participation @
Rs.5000 per household and generated Rs.14
crores
STP on BOT arrangement
With this, tariff rates reduced to Rs.75 per
household per month.
39
ALANDUR UNDERGROUND DRAINAGE
40
Contd…
3. Madurai Bye-Pass
• Included two-lane of 27 Kms, 2 RoBs and 1 high
level bridge.
• Project cost of Rs.44.35 crores funded @
15.50% interest rate (Rs.30 crores loan, 14 crores
grant)
• The vehicles toll collection efficiency within 31/2
years found to be 54 %
Based on toll tax collection efficiency, TNUDF
facilitated first revenue bond in the country.
Cost saving of 3% on interest rate.
41
Innovative Financing under TNUDP
MADURAI BYEPASS
MAP
42
Contd…
4. Compost Plant on BOT in Tiruppur -
• Conversion of Municipal Solid Waste into Organic
Manure (50 tpd plant)
• Supply or Pay contract between ULB and Private
Sector operator at Rs.3.50 pt + lease rentals
• Pressure / Incentive for the ULB to keep the streets
clean.
43
Innovative Financing (Contd..)
COMPOST PLANT
44
PPP POLICY FRAMEWORK FOR TN
• WB suggested consultancy for preparing policy framework
• GoTN engaged Economic Consulting Associates, IL&FS
and J.Sagar Associates
• Key issues identified by consultants:
– Is cross sectoral law required?
– Is cross sectoral agency required?
– Provide financial support to PPPs?
– What project development modes?
– How to manage unsolicited bids?
– How to manage contracts?
– How to resolve disputes?
– Role of independent regulation?
45

Weitere ähnliche Inhalte

Was ist angesagt?

Energy Choices - Sept 17 2014
Energy Choices - Sept 17 2014Energy Choices - Sept 17 2014
Energy Choices - Sept 17 2014annphancock
 
Aashish Misra India Urban Presentation at LSE 2010
Aashish Misra India Urban Presentation at LSE 2010Aashish Misra India Urban Presentation at LSE 2010
Aashish Misra India Urban Presentation at LSE 2010ashmishra
 
Financing water in_the_arab_countries_beirut89_3_2010
Financing water in_the_arab_countries_beirut89_3_2010Financing water in_the_arab_countries_beirut89_3_2010
Financing water in_the_arab_countries_beirut89_3_2010Parti Djibouti
 
National Slum Development Program (NSDP)
National Slum Development Program (NSDP) National Slum Development Program (NSDP)
National Slum Development Program (NSDP) Sumit Ranjan
 
Changes in Environmental Laws and Regulations
Changes in Environmental Laws and RegulationsChanges in Environmental Laws and Regulations
Changes in Environmental Laws and RegulationsCharlotte Chamber
 
Melamchi water supply project (mwsp)
Melamchi water supply project (mwsp)Melamchi water supply project (mwsp)
Melamchi water supply project (mwsp)Shisam Neupane
 
Executive Summary of Cook County Sustainability Advisory Report, 060513
Executive Summary of Cook County Sustainability Advisory Report, 060513Executive Summary of Cook County Sustainability Advisory Report, 060513
Executive Summary of Cook County Sustainability Advisory Report, 060513cookcountyblog
 

Was ist angesagt? (8)

What planners need to know
What planners need to knowWhat planners need to know
What planners need to know
 
Energy Choices - Sept 17 2014
Energy Choices - Sept 17 2014Energy Choices - Sept 17 2014
Energy Choices - Sept 17 2014
 
Aashish Misra India Urban Presentation at LSE 2010
Aashish Misra India Urban Presentation at LSE 2010Aashish Misra India Urban Presentation at LSE 2010
Aashish Misra India Urban Presentation at LSE 2010
 
Financing water in_the_arab_countries_beirut89_3_2010
Financing water in_the_arab_countries_beirut89_3_2010Financing water in_the_arab_countries_beirut89_3_2010
Financing water in_the_arab_countries_beirut89_3_2010
 
National Slum Development Program (NSDP)
National Slum Development Program (NSDP) National Slum Development Program (NSDP)
National Slum Development Program (NSDP)
 
Changes in Environmental Laws and Regulations
Changes in Environmental Laws and RegulationsChanges in Environmental Laws and Regulations
Changes in Environmental Laws and Regulations
 
Melamchi water supply project (mwsp)
Melamchi water supply project (mwsp)Melamchi water supply project (mwsp)
Melamchi water supply project (mwsp)
 
Executive Summary of Cook County Sustainability Advisory Report, 060513
Executive Summary of Cook County Sustainability Advisory Report, 060513Executive Summary of Cook County Sustainability Advisory Report, 060513
Executive Summary of Cook County Sustainability Advisory Report, 060513
 

Ähnlich wie Tn presentation.pdf2

P3 presentation - CCA.PPTX
P3 presentation - CCA.PPTXP3 presentation - CCA.PPTX
P3 presentation - CCA.PPTXMatt Meaker
 
Custom o105c399f97286
Custom o105c399f97286Custom o105c399f97286
Custom o105c399f97286venvetty
 
Equity Markets II.pptx
Equity Markets II.pptxEquity Markets II.pptx
Equity Markets II.pptxbfmsies
 
IWRM in Karnataka, India. Crafting a New Future
IWRM in Karnataka, India. Crafting a New FutureIWRM in Karnataka, India. Crafting a New Future
IWRM in Karnataka, India. Crafting a New FutureOswar Mungkasa
 
NJ Future Redevelopment Forum 2020 - Agid
NJ Future Redevelopment Forum 2020 - AgidNJ Future Redevelopment Forum 2020 - Agid
NJ Future Redevelopment Forum 2020 - AgidNew Jersey Future
 
Sustainable development model for American Cities
Sustainable development model for American CitiesSustainable development model for American Cities
Sustainable development model for American CitiesRushabh shah
 
Public private partnership_(sanitation)[1]
Public private partnership_(sanitation)[1]Public private partnership_(sanitation)[1]
Public private partnership_(sanitation)[1]Shraddha Kulkarni
 
IWRM in Karnataka India. Crafting a New Future
IWRM in Karnataka India. Crafting a New FutureIWRM in Karnataka India. Crafting a New Future
IWRM in Karnataka India. Crafting a New FutureOswar Mungkasa
 
Hall2C Wednesday 09h00 - Tony Nkuna
Hall2C Wednesday 09h00 - Tony NkunaHall2C Wednesday 09h00 - Tony Nkuna
Hall2C Wednesday 09h00 - Tony Nkuna7391456
 
Wednesday, 22 July 2015, Hall 2C, 09:00 - Tony Nkuna
Wednesday, 22 July 2015, Hall 2C, 09:00 - Tony NkunaWednesday, 22 July 2015, Hall 2C, 09:00 - Tony Nkuna
Wednesday, 22 July 2015, Hall 2C, 09:00 - Tony Nkuna7391456
 
Presentation project miel_ii
Presentation project miel_iiPresentation project miel_ii
Presentation project miel_iiProColombia
 
Bokamoso ba rona-agri-briefing-presentation
Bokamoso ba rona-agri-briefing-presentationBokamoso ba rona-agri-briefing-presentation
Bokamoso ba rona-agri-briefing-presentationMokaraneMorganMotsep
 
Alandur sewerage treatment plant project ppp model
Alandur sewerage treatment plant project   ppp modelAlandur sewerage treatment plant project   ppp model
Alandur sewerage treatment plant project ppp modelAr.Apurva Sinkar
 
SMART Seminar Series: Public Infrastructure Investment in the 2000s: Lessons ...
SMART Seminar Series: Public Infrastructure Investment in the 2000s: Lessons ...SMART Seminar Series: Public Infrastructure Investment in the 2000s: Lessons ...
SMART Seminar Series: Public Infrastructure Investment in the 2000s: Lessons ...SMART Infrastructure Facility
 
Community Infrastructure Levy- Helen Martin, RTPI West Midlands CPD
Community Infrastructure Levy- Helen Martin, RTPI West Midlands CPDCommunity Infrastructure Levy- Helen Martin, RTPI West Midlands CPD
Community Infrastructure Levy- Helen Martin, RTPI West Midlands CPDDesign South East
 
Hydro Priyank jain
Hydro Priyank jain Hydro Priyank jain
Hydro Priyank jain PRIYANK JAIN
 
Public-Private Partnerships - Business & Legal Issues
Public-Private Partnerships - Business & Legal IssuesPublic-Private Partnerships - Business & Legal Issues
Public-Private Partnerships - Business & Legal IssuesLou Milrad
 

Ähnlich wie Tn presentation.pdf2 (20)

P3 presentation - CCA.PPTX
P3 presentation - CCA.PPTXP3 presentation - CCA.PPTX
P3 presentation - CCA.PPTX
 
Pura presentation
Pura presentationPura presentation
Pura presentation
 
Custom o105c399f97286
Custom o105c399f97286Custom o105c399f97286
Custom o105c399f97286
 
Equity Markets II.pptx
Equity Markets II.pptxEquity Markets II.pptx
Equity Markets II.pptx
 
IWRM in Karnataka, India. Crafting a New Future
IWRM in Karnataka, India. Crafting a New FutureIWRM in Karnataka, India. Crafting a New Future
IWRM in Karnataka, India. Crafting a New Future
 
NJ Future Redevelopment Forum 2020 - Agid
NJ Future Redevelopment Forum 2020 - AgidNJ Future Redevelopment Forum 2020 - Agid
NJ Future Redevelopment Forum 2020 - Agid
 
Sustainable development model for American Cities
Sustainable development model for American CitiesSustainable development model for American Cities
Sustainable development model for American Cities
 
Public private partnership_(sanitation)[1]
Public private partnership_(sanitation)[1]Public private partnership_(sanitation)[1]
Public private partnership_(sanitation)[1]
 
IWRM in Karnataka India. Crafting a New Future
IWRM in Karnataka India. Crafting a New FutureIWRM in Karnataka India. Crafting a New Future
IWRM in Karnataka India. Crafting a New Future
 
Hall2C Wednesday 09h00 - Tony Nkuna
Hall2C Wednesday 09h00 - Tony NkunaHall2C Wednesday 09h00 - Tony Nkuna
Hall2C Wednesday 09h00 - Tony Nkuna
 
Wednesday, 22 July 2015, Hall 2C, 09:00 - Tony Nkuna
Wednesday, 22 July 2015, Hall 2C, 09:00 - Tony NkunaWednesday, 22 July 2015, Hall 2C, 09:00 - Tony Nkuna
Wednesday, 22 July 2015, Hall 2C, 09:00 - Tony Nkuna
 
Presentation project miel_ii
Presentation project miel_iiPresentation project miel_ii
Presentation project miel_ii
 
Bokamoso ba rona-agri-briefing-presentation
Bokamoso ba rona-agri-briefing-presentationBokamoso ba rona-agri-briefing-presentation
Bokamoso ba rona-agri-briefing-presentation
 
Alandur sewerage treatment plant project ppp model
Alandur sewerage treatment plant project   ppp modelAlandur sewerage treatment plant project   ppp model
Alandur sewerage treatment plant project ppp model
 
SMART Seminar Series: Public Infrastructure Investment in the 2000s: Lessons ...
SMART Seminar Series: Public Infrastructure Investment in the 2000s: Lessons ...SMART Seminar Series: Public Infrastructure Investment in the 2000s: Lessons ...
SMART Seminar Series: Public Infrastructure Investment in the 2000s: Lessons ...
 
Community Infrastructure Levy- Helen Martin, RTPI West Midlands CPD
Community Infrastructure Levy- Helen Martin, RTPI West Midlands CPDCommunity Infrastructure Levy- Helen Martin, RTPI West Midlands CPD
Community Infrastructure Levy- Helen Martin, RTPI West Midlands CPD
 
Hydro Priyank jain
Hydro Priyank jain Hydro Priyank jain
Hydro Priyank jain
 
Pioneer333
Pioneer333Pioneer333
Pioneer333
 
Project finance ppt final
Project finance ppt finalProject finance ppt final
Project finance ppt final
 
Public-Private Partnerships - Business & Legal Issues
Public-Private Partnerships - Business & Legal IssuesPublic-Private Partnerships - Business & Legal Issues
Public-Private Partnerships - Business & Legal Issues
 

Kürzlich hochgeladen

Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 

Kürzlich hochgeladen (20)

Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 

Tn presentation.pdf2

  • 1. 1 PUBLIC PRIVATE PARTNERSHIP INITIATIVES IN TAMIL NADU Vikram Kapur, IAS MD & CEO TN Urban Infrastructure Financial Services Ltd Chennai
  • 2. 2 BACKGROUND • TN - most urbanized state in India • 43% population lives in urban areas • Rate of growth of urbanization is 5% • 6 Corporations and 152 Municipalities • Present urban infrastructure not sufficient to provide quality services to the citizens • Urban areas contribute more than 70% of GDP in TN • Organic linkage between economic growth and infrastructure development
  • 3. 3 PPP – BENEFITS TO GOVT • Leveraging scarce budgetary resources of Govt • Ownership of underlying public assets to continue to vest with Govt • Channelizing innovative and modern management practices from private sector in Project development and structuring Resource mobilization Asset management and preservation • Project up-sides to be shared by Govt, while capping its liabilities • Preferred mechanism for outsourcing operations and maintenance of viable public assets
  • 4. 4 PPP – BENEFITS TO PRIVATE PARTNER • Policy level and statutory support by Govt • Handholding by Govt to resolve bottlenecks as in land acquisition, R&R, clearances and approvals • Limited financial assistance by Govt for ensuring viability • Govt participation to enhance lender confidence, enabling mobilization of cheaper funds • Continuing policy and O&M support from Govt throughout project concession period
  • 5. 5 SECTORS IDENTIFIED FOR PPP • Water supply and sewerage • Road infrastructure (roads, bridges and flyovers) • Improvement of urban infrastructure • Port infrastructure • Computer literacy in school education
  • 6. 6 PPP ORGANIZATIONS FORMED IN TAMIL NADU • Tamil Nadu Water Investment Company (TWIC) – Promoted by GoTN and IL&FS to develop water projects – Established New Tirupur Area Development Corporation Ltd (NTADCL) as SPV for supply of industrial and drinking water under Tirupur Water and Sanitation Project • Tamil Nadu Road Development Company (TNRDC) – JV of TIDCO and IL&FS (50:50) to develop road projects – East Coast Road (ECR) Project • Tamil Nadu Urban Development Fund (TNUDF) – Formed with Fis like ICICI, IL&FS and HDFC – Implementing World Bank assisted TN Urban Development Project • Ennore Port SEZ
  • 7. 7 TIRUPUR WATER & SANITATION PROJECT
  • 8. 8 Genesis • Despite international recognition as a major export centre for knitwear, Tirupur lacks quality infrastructure – Domestic water supply is limited to a few hours on alternate days – Industries do not have access to piped supply – Depleted ground water in the region • Investment in infrastructure is critical for a future Tirupur • A comprehensive program (TADP) was formulated to address the infrastructure needs of the town • Lack of budgetary resources prompted local industry to spearhead implementation of TADP on a commercial format • New Tirupur Area Development Corporation Limited (NTADCL) was formed as the company to implement the TADP
  • 9. 9 Summary Terms of Concession Agreement • Concession Model : Build-Own-Operate-Transfer (BOOT) • Concession Period : 30 years • Concession Grantor : GoTN and Tirupur Municipality • Concessionaire Co. : New Tirupur Area Development • Recovery mechanism : Composite water and sewerage charges • Tariff revision : Annual revision linked to indexation; Unusual increases to be approved by Price Review Committee • Transfer of Water Assets : At the end of the concession period • Base Project Return : 20% pa on 185 Mld project cost • Franchise Protection : Exclusive rights for service
  • 10. 10 Concession Agreement - Investment Matrix NTADCL Value Added Franchise Backbone Investment Productivity Investments to increase supply by 65 MLD Waste Water Recycling Bottled Water Supply Water Supply Sanitation
  • 11. 11 Scope • Water Supply 185 Mld (250 Mld) • Urban Population 3,46,551 (2001 Census Figure) • Rural/Semi Urban Population 4,00,266 (2001 Census Figure) • Industry 730 Units • Sanitation Coverage 60% of Households of Tirupur • Low Cost Sanitation for Slums
  • 12. 12 Schematic of Water Supply Scheme Netaji App. Uthukali Perundurai Kanchikoil Park (3.9 Mld) Chennimalai (2.7 Mld) 185 Mld (1.0 mld) (8.4 Mld) 56 km Steel Pumping Main from WTP to MBR (1400 & 1200 mm dia) Booster Water Intake at PS Treatment Cauvery Plant LEGEND PS Pumping Station FM-I to TM MBR Master Balancing Reservoir (9 DS) FM Feeder Main TM Tirupur Municipality FM-II to FM-III to DS Distribution Station TLPA TLPA TLPA Tirupur Local Planning Area (17 DS) (9 DS) MBR (23 Ml)
  • 13. 13 Project Structure IL&FS Project Sponsor GoTN - Project Sponsor - Land and Right of Way - Grant of Concession Equity Investors TWICL Contractor Consortium Pvt Equity Funds NTADCL -Execution of the Project - O&M of the Project - Beneficiary of Concession Terms USERS Lenders Consortium led by IDBI and SBI Water Charges EPC CONTRACTOR (WSA,, M&M, L&T, HCC) O&M CONTRACTOR (M&M & United Utilities) Service Concession Agreement
  • 14. 14 Project Implementation & Monitoring Structure • Concessionnaire : NTADCL • Project Sponsors : TWICL (GOTN and IL&FS) • Construction Contractors – Advance Engineering : Bechtel Enterprises, USA – EPC 1 Contractors : Hindustan Construction Co. Ltd. – EPC 2 Contractors : Mahindra & Mahindra and Larsen & Toubro Ltd • Operation & Maintenance: United Utilities, U.K and Mahindra & Mahindra • Project Managers : Wilbur Smith Associates, USA • Lenders Engineer : Pell Frischmann Water, U.K. • Owners Engineer : GKW Consult, Germany and CES, New Delhi • Independent Auditor : SB Billimoria, Chartered Accountants
  • 15. 15 Components of the Tirupur Project • EPC1 River Intake Well and Pumping station Water Treatment Plant & Booster Pumping Station Transmission Main – 56 kms Master Balancing Reservoir ( 23 Mn Ltrs) • EPC 2 Feeder Mains 1, 2 and 3 – 93 kms Water Distribution Stations – 36 Nos. Distribution Network – 219 kms Distribution Network to Wayside Villages Sewerage System – 124 kms Low Cost Sanitation
  • 16. 16 Total Landed Cost and Means of Finance Rs Crores • EPC Cost 650 • Owners Cost 127 • Contingency 93 • Interest During Construction 142 • Initial Working Capital 11 Total 1023 • The project cost of Rs 1023 cr is proposed to be financed through a debt : equity ratio of 1.5 : 1 Equity 322.70 Subordinate Debt 86.50 Debt 613.80
  • 17. 17 Equity Structure Equity Sub debt GOTN 30 25 Equity Sub debt IL&FS 35 15 TWICL Equity 65 Sub debt 40 Total 105 AIDEC Fund 90 LIC 20 GIC 15 Contractors 45 Tirupur 10 Others 37.7 Industry NTADCL TWICL 105 Others 217.7 TOTAL 322.7
  • 18. 18 Allocation of Risks • Government of Tamil Nadu – Political Force Majeure – Water Source – Power – Permissions – Change in tax / law • NTADCL – Commercial – Construction – Operations – Insurable Force Majeure
  • 19. 19 Innovative Financial Structuring • Non recourse financing • Issuance of a 30 year bond in the US Capital Market: • Guarantee under the FIRE program • Support of USAID in timing of issuance enhanced credibility of the Project • • Fund for DSR using a contingent recourse structure • Project financing with capped contingent liabilities on GoTN • Risk Participation Agreements • Sharing of upsides with consumers in the form of price relief • Formulation of risk allocation matrix to allow for re-pricing
  • 20. 20 Value of Project to Tirupur • Industry would collapse without it, and prosper with it • Project strength: commercial viability and Social dimensions • Pro-poor image • Social Benefits - Health • Environment
  • 21. 21 Value of NTADCL to Tirupur • Facilitate industrial growth • Effluent Treatment • Apparel Park • IIUS – Exhibition & Convention Center – Working Women’s Hostels – R & D Center – Roads – Traffic De-congestion • Social Forestry – Avenue & Schools • Recreation Parks • Social Study
  • 22. 22 PPP Strengths and Effectiveness - I • Robust and Dynamic structure • Arm’s length from the Govt. • Government ownership high • Governance structure ensures : – Allaying of private sector concerns – Social issues are addressed comprehensively – consumer interests are safeguarded • Commercial interest protected
  • 23. 23 PPP Strengths and Effectiveness - II • PPP model domiciles risk to parties that are well equipped to deal with them • Transparent and well-conceived contracts • Documentation recognizes rights and responsibilities of all project related parties • Concerns of all stakeholders addressed • Examples of contracts : – Concession Agreement – Bulk Water Supply Agreement – Shareholders’ Agreement – Common Loan Agreement – EPC and O&M Contracts
  • 24. 24 PPP Strengths and Effectiveness – III • The PPP model is an effective format for implementing infrastructure projects • But it has its own challenges which need to be recognized • PPP format involves the participation of a large number of Institutions: – Government, Politicians, Banks, Financial Institutions, Investors, Contractors, Consumers, NGO’s, etc. – Each of these entities recognize the benefits of the project. • But as the project develops, they exert pulls and pressures to enhance and further their own narrow institutional interests • The project development exercise requires addressing each of these issues without losing the integrity of the project concept
  • 25. 25 What This Project Has Established • As a pioneer project it has established: – Demand-driven projects are inherently strong. – Commercial formatting of projects is possible – Private participation in the sector is viable – Returns can be commensurate with risks – Willingness to pay for efficient services – Internal cross subsidy to reach the poor – Healthy precedent to ease learning curves
  • 26. 26 Current Status of Project • Construction commenced October 28, 2002 • Water supply already commenced • Sewerage component to be completed shortly
  • 27. 27 TAMIL NADU ROAD DEVELOPMENT COMPANY • TNRDC a 50:50 JV between TIDCO & IL&FS which have contributed Rs.5 crore each as share capital • East Coast Road (ECR) project – Initial improvement works (Rs.61 crore) and maintenance during Concession Period of 30 years – Recovery of initial investment, O&M and returns (capped at 20%) by levy of nominal tolls; surpluses to be reinvested in road sector – Project funding • Equity: Rs.10 crore • Sub Debt: Rs.10 crore • Senior Non Convertible Debenture: Rs.41 crore
  • 28. 28 TAMIL NADU URBAN DEVELOPMENT FUND (TNUDF) • A non-guaranteed fund managed by a private AMC • Established in November 1996 as a Trust • GoTN (Rs.143 cr), ICICI (23 cr), HDFC (Rs.17 cr), IL&FS (Rs.17 cr) • Policies and procedures by TNUITCL (FIs – 51% & GoTN – 49%) • Managed by TNUIFSL (FIs – 51% & GoTN – 49%) • Private Public Partnership arrangement to channelize private capital in municipal infrastructure • Object is to raise resources and to provide long term finance to ULBs • Resources - Unit Capital and Line of Credit by IBRD through GoTN • Flow of funds – World Bank to GoI by Project’s Special A/c – GoI to GoTN - pass through arrangement – GoTN to TNUDF / CMA / Grant Fund – TNUDF / Grant Fund to ULB
  • 29. 29 INITIATIVES UNDER TNUDF • Rs.30 crore mobilized from first Revenue Bond for Madurai Inner Ring Road • First toll bridge on BOT model costing Rs.15 crore (Karur) • First sewerage treatment plant (STP) on BOT model costing Rs.6.63 crore (Alandur municipality) • Rs.110 crore mobilized from domestic capital market for municipal infrastructure • Rs.51 crore mobilized by way of equity participation • Rs.30 crore mobilized through pooled finance on lines of US Bond Bank model (Water & Sanitation Pooled Fund)
  • 30. TNUDP III • Is a follow up project of TNUDP II • Project launched on 19th October 2005 • Project Size : US $ 434 m – World Bank : US $ 300 m – GoTN : US $ 84 m – Others : US $ 50 m GoTN • IDC to CMA : US $ 10 m • Capital Grants to ULB : US $ 48 m • Grants to CMA : US $ 26 m Others • ULB : US $ 10 m • Market Borrowing by TNUDF : US $ 40 m
  • 31. TNUDP-III • Loan & Project Agreement - effective on 19th October, 2005 • Project period : 5 years • Objectives – Develop TNUDF as a financial intermediary to provide finance for infrastructure in ULBs on a sustainable basis – Strength urban reforms and consolidate the achievements under TNUDP II – Institutional strengthening and capacity building – Provide grant to CMDA for traffic and transportation.
  • 32. COMPONENTS • Institutional Development component (IDC) – World Bank : 15 US $ m – GoTN : 10 US $ m • Urban Investment component (UIC) – World Bank : 146.5 US $ m (Loan 110, Grant 46.50, PDA 3) – GoTN : 48 US $ m • Grant to CMDA – World Bank : 124 US $ m – GoTN : 26 US $ m
  • 33. Funding Pattern – Break UpUS $ M 434.00134.00300.00TOTAL PROJECT COST 1.501.50Front End Fee 150.0026.00124.00Grants to CMDA - by TNUIFSL 257.5098.00159.50Total 3.003.00Project Development Advisory 94.5048.0046.50Capital grants to ULBs 160.0050.00110.00Loans to ULBs UIC - by TNUDF 25.0010.0015.00IDC - by CMA Total CostGoTN Finance Bank Finance Component
  • 34. Pipeline of Projects • Water supply Project : 11 projects; Sanctioned Loan of Rs.90 crs and Grant of Rs. 36 crs for 10 projects. • UGD Projects : 16 projects: Sanctioned Loan of Rs.272 crs and Grant of Rs. 80 crs for 11 projects. • Road and SWM Projects: Sanctioned Loan of Rs.75 crs and grant of Rs 33 crs sanctioned. • Total - Loan of Rs. 437 crs, and grant of Rs.149 crores sanction (Rs. 586 crs). • Amount disbursed : Rs.14.90 crs
  • 35. 35 TNUDF’s Portfolio in Urban Infrastructure TNUDF's Sector Wise Portfolio (Sanctions) Bus Statio ns and Markets 4% Sewerage &Sanitatio n 38% Water Supply 17% Stro m Water Drains 1% Others 1% Bridges and Ro ads 39% Bridges and Ro ads Bus Statio ns and Markets Sewerage &Sanitatio n Water Supply Stro m Water Drains Others
  • 36. 36 TNUDF - Innovative Financing 1. Karur Bridge – Facilitated first toll bridge contracted by an ULB in India – cost Rs.16 crores Predictable cash flow TN State Toll Act amended to facilitate ULB to enter into BoT contract – stable regulatory framework
  • 38. 38 Contd… 2. Alandur Underground Drainage – Rs.34 crores Initial tariff Rs.150 per house per month – very high TNUDF organised people’s participation @ Rs.5000 per household and generated Rs.14 crores STP on BOT arrangement With this, tariff rates reduced to Rs.75 per household per month.
  • 40. 40 Contd… 3. Madurai Bye-Pass • Included two-lane of 27 Kms, 2 RoBs and 1 high level bridge. • Project cost of Rs.44.35 crores funded @ 15.50% interest rate (Rs.30 crores loan, 14 crores grant) • The vehicles toll collection efficiency within 31/2 years found to be 54 % Based on toll tax collection efficiency, TNUDF facilitated first revenue bond in the country. Cost saving of 3% on interest rate.
  • 41. 41 Innovative Financing under TNUDP MADURAI BYEPASS MAP
  • 42. 42 Contd… 4. Compost Plant on BOT in Tiruppur - • Conversion of Municipal Solid Waste into Organic Manure (50 tpd plant) • Supply or Pay contract between ULB and Private Sector operator at Rs.3.50 pt + lease rentals • Pressure / Incentive for the ULB to keep the streets clean.
  • 44. 44 PPP POLICY FRAMEWORK FOR TN • WB suggested consultancy for preparing policy framework • GoTN engaged Economic Consulting Associates, IL&FS and J.Sagar Associates • Key issues identified by consultants: – Is cross sectoral law required? – Is cross sectoral agency required? – Provide financial support to PPPs? – What project development modes? – How to manage unsolicited bids? – How to manage contracts? – How to resolve disputes? – Role of independent regulation?
  • 45. 45