31. Palm Jumeirah Monorail
Guideway Beam
Production & Stitching
Precasting of 428 beams
each beam is 28m long x 1m wide x 2m high and weighs 80 tons
Joining of beams to columns at site
beams are “stitched” to other beams and columns by concrete
Contract Amount: AED 11.3 Million
DMCI GLOBAL, LTD
32. Palm Jumeirah Monorail
Atlantis Station
3 floors
2100 sq m
Contract Amount (Structural): AED 3.6 Million
Contract Amount (Finishing): AED 11.0 Million
DMCI GLOBAL, LTD
33. Palm Jumeirah Monorail
Village Center Station
5 floors
2200 sq m
Contract Amount (Structural): AED 3.9 Million
Contract Amount (Finishing): AED 7.9 Million
DMCI GLOBAL, LTD
34. Palm Jumeirah Monorail
Trump Tower Station
3 floors
1700 sq m
Contract Amount (Structural): AED 2.6 Million
Contract Amount (Finishing): AED 9.5 Million
DMCI GLOBAL, LTD
35. Project Features
Monorail Guideway Beams
32 cu m concrete per beam (typical)
80 tons beam weight (typical)
2 beams per day average production
Hollow section
Pre-stressed, post-tensioned
Vertically & horizontally curved and canted beams
Curved soffit
Monorail Stations
Structural:
Concrete: 5900 cu m
Rebar: 1160 tons
Finishes:
(1) Custom glass and aluminum external envelope
(2) Spray tile finish to exterior concrete surfaces
(3) Granite interior walls and floors
(4) Perforated aluminum ceiling finish
DMCI GLOBAL, LTD
36. Benefits Derived :
Profit realized
Retention of human resource
Capability enhancement – through this
experience the company was able to win
two more projects in the Philippines.