SlideShare ist ein Scribd-Unternehmen logo
1 von 27
INDUSTRIAL TRAINING 
SEMINAR 
Seminar Coordinator:- 
Mr. Abhishek Dubey 
Presented by:- 
Suraj Kumar Talreja 
Branch :-Electrical & Electronics 
Roll No: 0832EX111057
Contents 
 Outline 
 About MPPKVVCL Co. Ltd Indore
Outline 
 15 days Summer Training at MPPKVV Co. Ltd, 
Indore . 
 From 12/06/2014 to 30/06/2014 at 33/11 KV. 
 It was a good experience. I got to see what are 
the processes that to be followed for 
transformer repairing and saw the testing of 
Low Tension Meter and High Tension Meter. 
And I also saw how electricity get transmitted 
from Substation to feeders.
About MPKVVCL Co. Ltd Indore 
Introduction 
 The Government of Madhya Pradesh vide 
order dated 1st July, 2002 has incorporated 
Madhya Pradesh Paschim Kshetra Vidyut 
Vitaran Company Limited as a wholly 
owned Government of Madhya Pradesh 
Corporations under the Companies Act, 1956 
to undertake activities of distribution and retail 
supply for and on behalf of Madhya Pradesh 
State Electricity Board in the areas covered by 
the Commissionaires of Indore and Ujjain.
MPPKVVCL Objectives 
 The main objectives are to achieving efficiency 
gains and making necessary changes to make 
the Company commercially viable, 
progressively self sustainable and less 
government dependent and at the same time, 
balancing the interest of the consumers in 
regard to quality of service and economical 
tariff.
 The Government of Madhya Pradesh had 
restructured the functions and undertakings of 
Generation,Transmission, Distribution and 
Retail Supply of electricity earlier carried out 
by 
 The Madhya Pradesh State Electricity Board 
(‘MPSEB’ or ‘Board’) and transferred the same 
to five Companies to function independently. 
The five Companies are as under: -
 (1) M.P. Power Generating Company Ltd., Jabalpur 
(MPPGCL) (GENCO) 
 (2) M.P. Power Transmission Company Ltd., Jabalpur 
(MPPTCL) 
(TRANSCO) 
 (3) M.P. Poorv Kshetra Vidyut Vitaran Company Ltd., 
Jabalpur (MPPKVVCL) 
(EAST DISCOM) 
 (4) M.P. Madhya Kshetra Vidyut Vitaran Company Ltd. Bhopal 
(MPMKVVCL) 
(CENTRAL DISCOM) 
 (5) M.P. Paschim Kshetra Vidyut Vitaran Company Ltd., 
Indore (MPPKVVCL) 
(WEST DISCOM)
About Training 
Whole Training is divided into Four Sections:- 
 MTRU(Main Transformers Repairing Unit) – 4 
Days 
 LTMT Lab(Low Transmission Meter Testing 
Lab) – 4 Days 
 HTMT(High Transmission Meter Testing Lab) – 
3 Days 
 33/11 KV Substation. – 4 Days
MTRU(MAIN TRANSFORMER 
REPAIRING UNIT) 
 In this Section four days training were taken 
place. 
 Here, we had found how transformer got repaired 
and the processes which are to be followed for 
repairing. 
 The faulty transformer is brought on a vehicle to 
the MTRU, from where it is placed on a suitable 
place with the help of a manually operated crane. 
 Firstly, the Transformer is opened and 
Transformer oil is removed 
 Then the Transformer is heated in Electric heater 
at 80ºC for 8 – 10 Days to remove the Moisture.
 Then the Transformer is heated in Electric 
heater at 80ºC for 8 – 10 Days to remove the 
Moisture. 
Then After this Transformer is taken out from 
Heater 
and Transformer Test is performed: 
 Double Frequency Double Test: 
The object of this test is to secure that the 
insulation between the phase windings, turn, 
coils, tapping leads and terminals withstand 
the temporary over voltages to which the 
transformer may be subjected during it’s 
lifetime.
 Transformer Winding Resistance Test: 
Transformer winding resistance measurement is 
carried out to calculate the I2R losses and to 
calculate winding temperature to check loose 
connections, broken strands of conductor, high 
contact resistance in tap changers. 
 Turn Ratio Test:- 
The performance of a transformer largely 
depends upon perfection of specific turns 
or voltage ratio of transformer.
We just apply three phase 415 V supply to HV 
winding, with keeping LV winding open. The 
we measure the induced voltages at HV and 
LV terminals of transformer to find out 
actual voltage ratio of transformer. 
 OIL TEST 
In this test high voltage is applied across the 
oil to determine it’s dielectric strength i.e break 
down voltage.
 SHORT CIRCUIT TEST 
Short circuit voltage and copper loss calculated 
during this test determine the performance of 
the transformer
LTMT(Low tension Meter 
Testing) 
 In this Section Low Tension Meter Testing 
carried out, Low Tension Meter(Digital Meter) 
Stands for the meter which is generally used 
for Domestic and Industries purpose which is 
under the range of 220-400 V. 
 Instrument which is used for testing is 
Phantom Loading. 
 Some of the test is performed for LT Meters 
are:
 Creep Test: 
This test is done by energizing only the pressure 
coil by supplying rated 220V whereas no 
current flows through the current coil. In this 
case the indicating LED should not blink. 
Main Aim of this Test is to find out whether the 
Meter is operating or not operating in No load 
condition.
 STARTING CURRENT TEST: 
In this test the current coil is energized by 0.5% 
of the base current to check whether the meter 
is working or not.
HTMT(High Tension Meter 
Testing) 
 Instead of only energy meter, energy meter is 
used along with Metering unit ( A CT& PT 
combination).It is generally used when the 
supply ranges between 22kv and 66 Kv. 
 This Metering unit provides 110v, 5A at the 
secondary Side.
Metering Unit
The tests which are carried out here are: 
 Oil Test: 
In this Test High Voltage is applied at the Oil to 
find out the Dielectric Strength of the Oil. 
 Voltage Ratio Test: 
In this test High Voltage is applies at the Primary 
side and at the Secondary Side Voltage is 
measured and Voltage Ratio is calculated.
 Ct Ratio Test: 
In this Test a high current is applied through 
Current Injector at the Low Voltage Side and 
current is measured at the High Voltage side. 
 Meter Test:
33/11 KV Substation 
 In this station, high transmission is step down 
to lower voltage which is suitable for domestic 
and commercial purposes. 
 In this substation 33kv voltage is stepped 
down to 11 kv. 
 In substation generally more than one 
transmission line is used to increase the 
reliability. So that in case of fault in one line 
other is operate.
 Similarly, here two transmission lines are used 
from Chambal Hydro Electric Power Station. 
 This transmission line are fed to the metering 
unit for determining the electric I/P power. 
 Then this Lines are fed to the step down 
transformer via Protection unit, which consists 
of Circuit Breaker and Relays. 
 Output from the step down transformer is fed 
to the different feeders.
 The Controlling of each feeder is done in 
Control Unit.

Weitere ähnliche Inhalte

Was ist angesagt?

Speed control of dc motor
Speed control of dc motorSpeed control of dc motor
Speed control of dc motormpsrekha83
 
Open circuit and Short circuit test on transformer
Open circuit and Short circuit test on transformerOpen circuit and Short circuit test on transformer
Open circuit and Short circuit test on transformerHarshit Khandelwal
 
PPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclPPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclVISHAL VERMA
 
Switchyard design overview
Switchyard design overviewSwitchyard design overview
Switchyard design overviewMilind Punj
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substationIshank Ranjan
 
Module 4 power generation & Economics - Substation vtu syllabus
Module 4 power generation & Economics - Substation vtu syllabusModule 4 power generation & Economics - Substation vtu syllabus
Module 4 power generation & Economics - Substation vtu syllabusDrCVMOHAN
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.Hemendra Kumar Rajput
 
Resonant Inverters
Resonant InvertersResonant Inverters
Resonant Invertersraviarmugam
 
Commutation in DC Machines
Commutation in DC Machines Commutation in DC Machines
Commutation in DC Machines Dinesh Sharma
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrushmichaeljmack
 
Summer traning on Power Transformer Construction
Summer traning on Power Transformer ConstructionSummer traning on Power Transformer Construction
Summer traning on Power Transformer ConstructionStudent
 
industrial training ppt from 33 kv substation UPCL
industrial training ppt from 33 kv substation UPCLindustrial training ppt from 33 kv substation UPCL
industrial training ppt from 33 kv substation UPCLsurendra rawat
 
substation internship report
substation internship report substation internship report
substation internship report Arun Thapa
 
Summer internship Railway Electrical.pdf
Summer internship Railway Electrical.pdfSummer internship Railway Electrical.pdf
Summer internship Railway Electrical.pdfAbhisheksamal22
 
Basics of ups seminar presentation
Basics of ups   seminar presentationBasics of ups   seminar presentation
Basics of ups seminar presentationMurali Krishnan
 

Was ist angesagt? (20)

Speed control of dc motor
Speed control of dc motorSpeed control of dc motor
Speed control of dc motor
 
Open circuit and Short circuit test on transformer
Open circuit and Short circuit test on transformerOpen circuit and Short circuit test on transformer
Open circuit and Short circuit test on transformer
 
Inverter
InverterInverter
Inverter
 
PPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclPPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppcl
 
Switchyard design overview
Switchyard design overviewSwitchyard design overview
Switchyard design overview
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
 
Module 4 power generation & Economics - Substation vtu syllabus
Module 4 power generation & Economics - Substation vtu syllabusModule 4 power generation & Economics - Substation vtu syllabus
Module 4 power generation & Economics - Substation vtu syllabus
 
Buchholz relay
Buchholz relayBuchholz relay
Buchholz relay
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
 
Resonant Inverters
Resonant InvertersResonant Inverters
Resonant Inverters
 
132kV GSS ppt
132kV GSS ppt132kV GSS ppt
132kV GSS ppt
 
Commutation in DC Machines
Commutation in DC Machines Commutation in DC Machines
Commutation in DC Machines
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
 
Summer traning on Power Transformer Construction
Summer traning on Power Transformer ConstructionSummer traning on Power Transformer Construction
Summer traning on Power Transformer Construction
 
industrial training ppt from 33 kv substation UPCL
industrial training ppt from 33 kv substation UPCLindustrial training ppt from 33 kv substation UPCL
industrial training ppt from 33 kv substation UPCL
 
substation internship report
substation internship report substation internship report
substation internship report
 
Summer internship Railway Electrical.pdf
Summer internship Railway Electrical.pdfSummer internship Railway Electrical.pdf
Summer internship Railway Electrical.pdf
 
Basics of ups seminar presentation
Basics of ups   seminar presentationBasics of ups   seminar presentation
Basics of ups seminar presentation
 
132 33kv substation
132 33kv substation132 33kv substation
132 33kv substation
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
 

Andere mochten auch

Training report of 33/11kv substation Mohamdabad, Tundla
Training report of 33/11kv substation Mohamdabad, TundlaTraining report of 33/11kv substation Mohamdabad, Tundla
Training report of 33/11kv substation Mohamdabad, Tundlashashanksltor
 
NTPC SUMMER INTERNSHIP MBA FINANCE
NTPC SUMMER INTERNSHIP MBA FINANCENTPC SUMMER INTERNSHIP MBA FINANCE
NTPC SUMMER INTERNSHIP MBA FINANCENEHA GAUTAM
 
33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)Prateek Agarwal
 
Sanwariya Packaging Private Limited, Indore, Aluminium Foils & Packaging Mate...
Sanwariya Packaging Private Limited, Indore, Aluminium Foils & Packaging Mate...Sanwariya Packaging Private Limited, Indore, Aluminium Foils & Packaging Mate...
Sanwariya Packaging Private Limited, Indore, Aluminium Foils & Packaging Mate...IndiaMART InterMESH Limited
 
comparative analysis on ntpc and nhpc
comparative analysis on ntpc and nhpccomparative analysis on ntpc and nhpc
comparative analysis on ntpc and nhpcAhMed Ŝĥãbÿ
 
CFA Challenge - Tata Power
CFA Challenge - Tata PowerCFA Challenge - Tata Power
CFA Challenge - Tata PowerPurav Sheth
 
Industrial safety.
Industrial safety.Industrial safety.
Industrial safety.psc2015
 
Mba internship formats
Mba internship formatsMba internship formats
Mba internship formatsShankaran Rd
 
A SUMMER INTERNSHIP PROJECT REPORT ON “CONSUMER BEHAVIOR” AT IDBI FEDERAL LIF...
A SUMMER INTERNSHIP PROJECT REPORT ON “CONSUMER BEHAVIOR” AT IDBI FEDERAL LIF...A SUMMER INTERNSHIP PROJECT REPORT ON “CONSUMER BEHAVIOR” AT IDBI FEDERAL LIF...
A SUMMER INTERNSHIP PROJECT REPORT ON “CONSUMER BEHAVIOR” AT IDBI FEDERAL LIF...Gaurav Mehta
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
 
National thermal power corporation ppt
National thermal power corporation pptNational thermal power corporation ppt
National thermal power corporation pptShalini Krishna
 
Ntpc badarpur training ppt
Ntpc badarpur training pptNtpc badarpur training ppt
Ntpc badarpur training pptanuj_kumar57
 
Uttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training reportUttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training report19saurabh89
 
Pid controllers
Pid controllersPid controllers
Pid controllersmilind1076
 
NTPC BADARPUR PROJECT REPORT
NTPC BADARPUR PROJECT REPORTNTPC BADARPUR PROJECT REPORT
NTPC BADARPUR PROJECT REPORTARVIND NEGI
 
IOCL summer internship report
IOCL summer internship reportIOCL summer internship report
IOCL summer internship reportsagarmehra
 
Industrial health and safety seminar
Industrial health and safety seminarIndustrial health and safety seminar
Industrial health and safety seminarFahad Shaikh
 

Andere mochten auch (20)

Training report of 33/11kv substation Mohamdabad, Tundla
Training report of 33/11kv substation Mohamdabad, TundlaTraining report of 33/11kv substation Mohamdabad, Tundla
Training report of 33/11kv substation Mohamdabad, Tundla
 
NTPC SUMMER INTERNSHIP MBA FINANCE
NTPC SUMMER INTERNSHIP MBA FINANCENTPC SUMMER INTERNSHIP MBA FINANCE
NTPC SUMMER INTERNSHIP MBA FINANCE
 
33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)
 
Sanwariya Packaging Private Limited, Indore, Aluminium Foils & Packaging Mate...
Sanwariya Packaging Private Limited, Indore, Aluminium Foils & Packaging Mate...Sanwariya Packaging Private Limited, Indore, Aluminium Foils & Packaging Mate...
Sanwariya Packaging Private Limited, Indore, Aluminium Foils & Packaging Mate...
 
comparative analysis on ntpc and nhpc
comparative analysis on ntpc and nhpccomparative analysis on ntpc and nhpc
comparative analysis on ntpc and nhpc
 
CFA Challenge - Tata Power
CFA Challenge - Tata PowerCFA Challenge - Tata Power
CFA Challenge - Tata Power
 
Ntpc
NtpcNtpc
Ntpc
 
Industrial safety.
Industrial safety.Industrial safety.
Industrial safety.
 
Mba internship formats
Mba internship formatsMba internship formats
Mba internship formats
 
A SUMMER INTERNSHIP PROJECT REPORT ON “CONSUMER BEHAVIOR” AT IDBI FEDERAL LIF...
A SUMMER INTERNSHIP PROJECT REPORT ON “CONSUMER BEHAVIOR” AT IDBI FEDERAL LIF...A SUMMER INTERNSHIP PROJECT REPORT ON “CONSUMER BEHAVIOR” AT IDBI FEDERAL LIF...
A SUMMER INTERNSHIP PROJECT REPORT ON “CONSUMER BEHAVIOR” AT IDBI FEDERAL LIF...
 
Study of Finance in Taj
Study of Finance in Taj Study of Finance in Taj
Study of Finance in Taj
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
National thermal power corporation ppt
National thermal power corporation pptNational thermal power corporation ppt
National thermal power corporation ppt
 
Ntpc badarpur training ppt
Ntpc badarpur training pptNtpc badarpur training ppt
Ntpc badarpur training ppt
 
Uttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training reportUttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training report
 
Pid controllers
Pid controllersPid controllers
Pid controllers
 
NTPC BADARPUR PROJECT REPORT
NTPC BADARPUR PROJECT REPORTNTPC BADARPUR PROJECT REPORT
NTPC BADARPUR PROJECT REPORT
 
IOCL summer internship report
IOCL summer internship reportIOCL summer internship report
IOCL summer internship report
 
Industrial health and safety seminar
Industrial health and safety seminarIndustrial health and safety seminar
Industrial health and safety seminar
 
NFI - Industrial Pneumatics
NFI - Industrial PneumaticsNFI - Industrial Pneumatics
NFI - Industrial Pneumatics
 

Ähnlich wie MPEB, MPPKVVCL Indore 15 days Training Seminar

summer internship report on erection, commissioning and pre-comissioning of50...
summer internship report on erection, commissioning and pre-comissioning of50...summer internship report on erection, commissioning and pre-comissioning of50...
summer internship report on erection, commissioning and pre-comissioning of50...Rahul Akinapelli
 
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL Rahul Akinapelli
 
Vocational training
Vocational trainingVocational training
Vocational trainingSuraj prasad
 
INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)Asafak Husain
 
yogesh Barvadiya (3)
yogesh Barvadiya (3)yogesh Barvadiya (3)
yogesh Barvadiya (3)YOGESH PATEL
 
Mppkvv company ltd
Mppkvv company ltdMppkvv company ltd
Mppkvv company ltdDEEPAK PATEL
 
Transformer Repair Workshop Report [EEE]
Transformer Repair Workshop Report [EEE] Transformer Repair Workshop Report [EEE]
Transformer Repair Workshop Report [EEE] Nik Sharma
 
Kanti Thermal Power Station
Kanti Thermal Power StationKanti Thermal Power Station
Kanti Thermal Power Stationneeraj prasad
 
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...Rishabhlko
 
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622
ELECHTRICAL   COMMISSIONING  TECHNICIAN   2201622ELECHTRICAL   COMMISSIONING  TECHNICIAN   2201622
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622MOHAMMAD KHALID MUSTAFA
 
REPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTREPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTRAJPRASAD RS
 
Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protectionRakesh Joshi
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHShankar Singh
 
ae-1.pptx
ae-1.pptxae-1.pptx
ae-1.pptxxGeNoSx
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV Girish Gupta
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjarMukesh gurjar
 
APFC project presentation
APFC project presentationAPFC project presentation
APFC project presentationkartickmp613
 

Ähnlich wie MPEB, MPPKVVCL Indore 15 days Training Seminar (20)

summer internship report on erection, commissioning and pre-comissioning of50...
summer internship report on erection, commissioning and pre-comissioning of50...summer internship report on erection, commissioning and pre-comissioning of50...
summer internship report on erection, commissioning and pre-comissioning of50...
 
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
INSTALLATION OF 500MVA TRANSFORMER AT PGCIL
 
Vocational training
Vocational trainingVocational training
Vocational training
 
INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)INTERNSHIP REPORT-ORIGINAL (Autosaved)
INTERNSHIP REPORT-ORIGINAL (Autosaved)
 
yogesh Barvadiya (3)
yogesh Barvadiya (3)yogesh Barvadiya (3)
yogesh Barvadiya (3)
 
finalseminar.docx
finalseminar.docxfinalseminar.docx
finalseminar.docx
 
Mppkvv company ltd
Mppkvv company ltdMppkvv company ltd
Mppkvv company ltd
 
ntpc
ntpcntpc
ntpc
 
Transformer Repair Workshop Report [EEE]
Transformer Repair Workshop Report [EEE] Transformer Repair Workshop Report [EEE]
Transformer Repair Workshop Report [EEE]
 
Kanti Thermal Power Station
Kanti Thermal Power StationKanti Thermal Power Station
Kanti Thermal Power Station
 
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
 
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622
ELECHTRICAL   COMMISSIONING  TECHNICIAN   2201622ELECHTRICAL   COMMISSIONING  TECHNICIAN   2201622
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622
 
REPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTREPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANT
 
Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protection
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
 
ae-1.pptx
ae-1.pptxae-1.pptx
ae-1.pptx
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjar
 
Ntpc barh (bstpp)
Ntpc barh (bstpp)Ntpc barh (bstpp)
Ntpc barh (bstpp)
 
APFC project presentation
APFC project presentationAPFC project presentation
APFC project presentation
 

Kürzlich hochgeladen

Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 

Kürzlich hochgeladen (20)

Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 

MPEB, MPPKVVCL Indore 15 days Training Seminar

  • 1. INDUSTRIAL TRAINING SEMINAR Seminar Coordinator:- Mr. Abhishek Dubey Presented by:- Suraj Kumar Talreja Branch :-Electrical & Electronics Roll No: 0832EX111057
  • 2. Contents  Outline  About MPPKVVCL Co. Ltd Indore
  • 3. Outline  15 days Summer Training at MPPKVV Co. Ltd, Indore .  From 12/06/2014 to 30/06/2014 at 33/11 KV.  It was a good experience. I got to see what are the processes that to be followed for transformer repairing and saw the testing of Low Tension Meter and High Tension Meter. And I also saw how electricity get transmitted from Substation to feeders.
  • 4. About MPKVVCL Co. Ltd Indore Introduction  The Government of Madhya Pradesh vide order dated 1st July, 2002 has incorporated Madhya Pradesh Paschim Kshetra Vidyut Vitaran Company Limited as a wholly owned Government of Madhya Pradesh Corporations under the Companies Act, 1956 to undertake activities of distribution and retail supply for and on behalf of Madhya Pradesh State Electricity Board in the areas covered by the Commissionaires of Indore and Ujjain.
  • 5. MPPKVVCL Objectives  The main objectives are to achieving efficiency gains and making necessary changes to make the Company commercially viable, progressively self sustainable and less government dependent and at the same time, balancing the interest of the consumers in regard to quality of service and economical tariff.
  • 6.  The Government of Madhya Pradesh had restructured the functions and undertakings of Generation,Transmission, Distribution and Retail Supply of electricity earlier carried out by  The Madhya Pradesh State Electricity Board (‘MPSEB’ or ‘Board’) and transferred the same to five Companies to function independently. The five Companies are as under: -
  • 7.  (1) M.P. Power Generating Company Ltd., Jabalpur (MPPGCL) (GENCO)  (2) M.P. Power Transmission Company Ltd., Jabalpur (MPPTCL) (TRANSCO)  (3) M.P. Poorv Kshetra Vidyut Vitaran Company Ltd., Jabalpur (MPPKVVCL) (EAST DISCOM)  (4) M.P. Madhya Kshetra Vidyut Vitaran Company Ltd. Bhopal (MPMKVVCL) (CENTRAL DISCOM)  (5) M.P. Paschim Kshetra Vidyut Vitaran Company Ltd., Indore (MPPKVVCL) (WEST DISCOM)
  • 8. About Training Whole Training is divided into Four Sections:-  MTRU(Main Transformers Repairing Unit) – 4 Days  LTMT Lab(Low Transmission Meter Testing Lab) – 4 Days  HTMT(High Transmission Meter Testing Lab) – 3 Days  33/11 KV Substation. – 4 Days
  • 9. MTRU(MAIN TRANSFORMER REPAIRING UNIT)  In this Section four days training were taken place.  Here, we had found how transformer got repaired and the processes which are to be followed for repairing.  The faulty transformer is brought on a vehicle to the MTRU, from where it is placed on a suitable place with the help of a manually operated crane.  Firstly, the Transformer is opened and Transformer oil is removed  Then the Transformer is heated in Electric heater at 80ºC for 8 – 10 Days to remove the Moisture.
  • 10.
  • 11.  Then the Transformer is heated in Electric heater at 80ºC for 8 – 10 Days to remove the Moisture. Then After this Transformer is taken out from Heater and Transformer Test is performed:  Double Frequency Double Test: The object of this test is to secure that the insulation between the phase windings, turn, coils, tapping leads and terminals withstand the temporary over voltages to which the transformer may be subjected during it’s lifetime.
  • 12.
  • 13.  Transformer Winding Resistance Test: Transformer winding resistance measurement is carried out to calculate the I2R losses and to calculate winding temperature to check loose connections, broken strands of conductor, high contact resistance in tap changers.  Turn Ratio Test:- The performance of a transformer largely depends upon perfection of specific turns or voltage ratio of transformer.
  • 14. We just apply three phase 415 V supply to HV winding, with keeping LV winding open. The we measure the induced voltages at HV and LV terminals of transformer to find out actual voltage ratio of transformer.  OIL TEST In this test high voltage is applied across the oil to determine it’s dielectric strength i.e break down voltage.
  • 15.  SHORT CIRCUIT TEST Short circuit voltage and copper loss calculated during this test determine the performance of the transformer
  • 16.
  • 17. LTMT(Low tension Meter Testing)  In this Section Low Tension Meter Testing carried out, Low Tension Meter(Digital Meter) Stands for the meter which is generally used for Domestic and Industries purpose which is under the range of 220-400 V.  Instrument which is used for testing is Phantom Loading.  Some of the test is performed for LT Meters are:
  • 18.  Creep Test: This test is done by energizing only the pressure coil by supplying rated 220V whereas no current flows through the current coil. In this case the indicating LED should not blink. Main Aim of this Test is to find out whether the Meter is operating or not operating in No load condition.
  • 19.  STARTING CURRENT TEST: In this test the current coil is energized by 0.5% of the base current to check whether the meter is working or not.
  • 20. HTMT(High Tension Meter Testing)  Instead of only energy meter, energy meter is used along with Metering unit ( A CT& PT combination).It is generally used when the supply ranges between 22kv and 66 Kv.  This Metering unit provides 110v, 5A at the secondary Side.
  • 22. The tests which are carried out here are:  Oil Test: In this Test High Voltage is applied at the Oil to find out the Dielectric Strength of the Oil.  Voltage Ratio Test: In this test High Voltage is applies at the Primary side and at the Secondary Side Voltage is measured and Voltage Ratio is calculated.
  • 23.  Ct Ratio Test: In this Test a high current is applied through Current Injector at the Low Voltage Side and current is measured at the High Voltage side.  Meter Test:
  • 24. 33/11 KV Substation  In this station, high transmission is step down to lower voltage which is suitable for domestic and commercial purposes.  In this substation 33kv voltage is stepped down to 11 kv.  In substation generally more than one transmission line is used to increase the reliability. So that in case of fault in one line other is operate.
  • 25.
  • 26.  Similarly, here two transmission lines are used from Chambal Hydro Electric Power Station.  This transmission line are fed to the metering unit for determining the electric I/P power.  Then this Lines are fed to the step down transformer via Protection unit, which consists of Circuit Breaker and Relays.  Output from the step down transformer is fed to the different feeders.
  • 27.  The Controlling of each feeder is done in Control Unit.