Setting Up Resources
Objectives  Set up basic resource information for the people who work on projects. Enter basic resource information for the equipment that will be used in projects. Enter resource information for the materials that will be consumed as the project progresses. Enter cost resource information for financial tracking. Set up cost information for work resources. Change a resource’s availability for work. Record additional information about a resource in a note.
Resources include the people and equipment needed to complete the tasks in a project Microsoft Office Project 2007 focuses on two aspects of resources Availability Costs Availability determines when specific resources can work on tasks and how much work they can perform costs refer to how much money will be required to pay for those resources
Setting Up People Resources Project works with three types of resources: Work Material Cost  Work resources are the people and equipment that do the work of the project
Cont>> Some examples of work resources
Cont>> How to set up resource information for several people resources On the View menu, click Resource Sheet In the Resource Sheet view, click the cell directly below the Resource Name column heading Type Jonathan Mollerup, and press Enter On the next empty rows in the Resource Name column, enter the following names: Jon Ganio Garrett R.Vargas John Rodman
Cont>> In the Resource Name field below the last resource, type Electrician, and then press TAB In the Type field, make sure that Work is selected, and then press TABseveral times to move to the Max. Unitsfield The Max. Units field represents the maximum capacity of a resource to accomplish any task The Max. Units field represents the maximum capacity of a resource to accomplish any task ENTER Click the Max. Units field for Jon Ganio, type or select 50%, and then press
Setting Up Equipment Resources In Project, you set up people and equipment resources in exactly the same way because people and equipment are both examples of work resources However, you should be aware of important differences people resources might be flexible in the tasks they can perform, but equipment resources tend to be more specialized
Cont>> you might want to set up equipment resources when Multiple teams or people might need a piece of equipment to accomplish different tasks simultaneously, and the equipment might be overbooked. You want to plan and track costs associated with the equipment.
Enter information about equipment resources In the Resource Sheet, click the next empty cell in the Resource Namecolumn On the Standard toolbar, click the Resource Information button OR double-click a resource name Click the General tab if it is not already displayed In the Resource name field, type Mini-DV Camcorder In the Type field, click Work.  In the Max. Units field for the Mini-DV Camcorder, type or click the arrows until the value shown is 300% and press ENTER
Cont>> Enter the following information about equipment resources directly in the Resource Sheet or in the Resource Information dialog box, whichever you prefer. In either case, make sure Work is selected in the Type field.
Setting Up Material Resources Material resources are consumables that you use up as the project proceeds On a construction project, material resources might include nails, lumber, and concrete You work with material resources in Project mainly to track the rate of consumption and the associated cost
Cont>> How to enter information about a material resource In the Resource Sheet, click the next empty cell in the Resource Namecolumn Type Video Tape and press TAB In the Type field, click the down arrow, select Material, and press TAB In the Material Label field, type 30-min. cassette and press ENTER Note that you cannot enter a Max. Units value for a material resource. Since a material resource is a consumable item and not a person or piece of equipment that performs work, the Max. Units value doesn’t apply
Setting Up Cost Resources The third and final type of resource that you can use in Project is the cost resource You can use a cost resource to represent a financial cost associated with a task in a project Common types of cost resources might include categories of expenses you’d want to track on a project for accounting purposes such as travel, entertainment, or training Like material resources, cost resources do no work and have no effect on the scheduling of a task
Cont>> However, after you assign a cost resource to a task and specify the cost amount per task, you can then see the cumulative costs for that type of cost resource In the Resource Sheet, click the next empty cell in the Resource Name column. 2. Type Travel and press TAB. 3. In the Type field, click the down arrow, select Cost, and press ENTER.
Entering Resource Pay Rates Almost all projects have some financial aspect, and cost limits drive the scope of many projects. Tracking and managing cost information allows the project manager to answer such important questions as What is the expected total cost of the project based on our task duration and resource estimates? Are we using expensive resources to do work that less expensive resources could do? How much money will a specific type of resource or task cost over the life of the project? How have we allocated a particular type of expense, such as travel, in a project? Are we spending money at a rate that we can sustain for the planned duration of the project
Cont>> How to enter cost information for each work resource In the Resource Sheet, click the Std. Rate field for Jonathan Mollerup Type 10 and press  ENTER In the Std. Rate field for Jon Ganio, type 15.50 and press ENTER Enter the following standard pay rates for the given resources
Cont>>
Adjusting Working Time for Individual Resources Project uses different types of calendars for different purposes A resource calendar controls the working and nonworking times of a resource Project uses resource calendars to determine when work for a specific resource can be scheduled Resource calendars apply only to work resources (people and equipment) and not to material or cost resources
Cont>> When you initially create resources in a project plan, Project creates a resource calendar for each work resource. The initial working time settings for resource calendars exactly match those of the Standard base calendar, chances are that some of your resources will need exceptions to the working time in the Standard base calendar-such as A flex-time work schedule Vacation time Other times when a resource is not available to work on the project, such as time spent training or attending a conference
Cont>> How to specify the working and nonworking times for individual work resources On the Tools menu, click Change Working Time. The Change Working Time dialog box appears. In the For calendar box, click Garrett R.Vargas. Garrett R.Vargas’s resource calendar appears in the Change Working Time dialog box. Garrett has told you he will not be available to work on Thursday and Friday, January 10 and 11, because he plans to attend a film festival. On the Exceptions tab in the Change Working Time dialog box, click in the first row directly below the Name column heading and type Garrett attending West Coast Film Festival
Cont>> Click in the Start field and type or select 1/10/2008. Click in the Finish field, type or select 1/11/2008, and then press ENTER

Weitere ähnliche Inhalte

Andere mochten auch (6)

Azuron - Jean-Marc Barthe
Azuron - Jean-Marc Barthe Azuron - Jean-Marc Barthe
Azuron - Jean-Marc Barthe
 
The place where you live
The place where you liveThe place where you live
The place where you live
 
Esc guidelines for guidelines update 2010
Esc guidelines for guidelines update 2010Esc guidelines for guidelines update 2010
Esc guidelines for guidelines update 2010
 
Hul
HulHul
Hul
 
So esitys kort
So esitys kortSo esitys kort
So esitys kort
 
Investments by institutions in primary agriculture in Russia, Ukraine and Kaz...
Investments by institutions in primary agriculture in Russia, Ukraine and Kaz...Investments by institutions in primary agriculture in Russia, Ukraine and Kaz...
Investments by institutions in primary agriculture in Russia, Ukraine and Kaz...
 

Ähnlich wie Setting up resources

MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docxMS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
rosemarybdodson23141
 
Course ProjectObjective Guidelines Milestones De.docx
Course ProjectObjective  Guidelines  Milestones  De.docxCourse ProjectObjective  Guidelines  Milestones  De.docx
Course ProjectObjective Guidelines Milestones De.docx
marilucorr
 
For this project you may choose one that is of interest to you or .docx
For this project you may choose one that is of interest to you or .docxFor this project you may choose one that is of interest to you or .docx
For this project you may choose one that is of interest to you or .docx
budbarber38650
 

Ähnlich wie Setting up resources (20)

03 Setting-up resources
03  Setting-up resources  03  Setting-up resources
03 Setting-up resources
 
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docxMS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
 
Yom Institute Presentation project management course
Yom Institute Presentation project management courseYom Institute Presentation project management course
Yom Institute Presentation project management course
 
08 Fine-Tuning Resource Details
08 Fine-Tuning Resource Details08 Fine-Tuning Resource Details
08 Fine-Tuning Resource Details
 
Ppsi pertemuan-3
Ppsi pertemuan-3Ppsi pertemuan-3
Ppsi pertemuan-3
 
Project Management Quick Reference Guide
Project Management Quick Reference GuideProject Management Quick Reference Guide
Project Management Quick Reference Guide
 
Project Management Quick Reference Guide For Microsoft Project 2007
Project Management Quick Reference Guide For Microsoft Project 2007Project Management Quick Reference Guide For Microsoft Project 2007
Project Management Quick Reference Guide For Microsoft Project 2007
 
Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007
 
Project management software
Project management softwareProject management software
Project management software
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
 
Project Web Access Quick Reference Guide For Team Members
Project Web Access Quick Reference Guide For Team MembersProject Web Access Quick Reference Guide For Team Members
Project Web Access Quick Reference Guide For Team Members
 
Devry proj 586 week 3 project guidelines microsoft project new
Devry proj 586 week 3 project guidelines microsoft project newDevry proj 586 week 3 project guidelines microsoft project new
Devry proj 586 week 3 project guidelines microsoft project new
 
Course ProjectObjective Guidelines Milestones De.docx
Course ProjectObjective  Guidelines  Milestones  De.docxCourse ProjectObjective  Guidelines  Milestones  De.docx
Course ProjectObjective Guidelines Milestones De.docx
 
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013
 
Create a new work order in Ibm Maximo
Create a new work order in Ibm MaximoCreate a new work order in Ibm Maximo
Create a new work order in Ibm Maximo
 
SAP HR: Training & event management
SAP HR: Training & event managementSAP HR: Training & event management
SAP HR: Training & event management
 
Lesson 13 primavera.pptx..........................
Lesson 13 primavera.pptx..........................Lesson 13 primavera.pptx..........................
Lesson 13 primavera.pptx..........................
 
For this project you may choose one that is of interest to you or .docx
For this project you may choose one that is of interest to you or .docxFor this project you may choose one that is of interest to you or .docx
For this project you may choose one that is of interest to you or .docx
 

Kürzlich hochgeladen

Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Victor Rentea
 

Kürzlich hochgeladen (20)

ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistan
 
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with Milvus
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectors
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
 

Setting up resources

  • 2. Objectives Set up basic resource information for the people who work on projects. Enter basic resource information for the equipment that will be used in projects. Enter resource information for the materials that will be consumed as the project progresses. Enter cost resource information for financial tracking. Set up cost information for work resources. Change a resource’s availability for work. Record additional information about a resource in a note.
  • 3. Resources include the people and equipment needed to complete the tasks in a project Microsoft Office Project 2007 focuses on two aspects of resources Availability Costs Availability determines when specific resources can work on tasks and how much work they can perform costs refer to how much money will be required to pay for those resources
  • 4. Setting Up People Resources Project works with three types of resources: Work Material Cost Work resources are the people and equipment that do the work of the project
  • 5. Cont>> Some examples of work resources
  • 6. Cont>> How to set up resource information for several people resources On the View menu, click Resource Sheet In the Resource Sheet view, click the cell directly below the Resource Name column heading Type Jonathan Mollerup, and press Enter On the next empty rows in the Resource Name column, enter the following names: Jon Ganio Garrett R.Vargas John Rodman
  • 7. Cont>> In the Resource Name field below the last resource, type Electrician, and then press TAB In the Type field, make sure that Work is selected, and then press TABseveral times to move to the Max. Unitsfield The Max. Units field represents the maximum capacity of a resource to accomplish any task The Max. Units field represents the maximum capacity of a resource to accomplish any task ENTER Click the Max. Units field for Jon Ganio, type or select 50%, and then press
  • 8. Setting Up Equipment Resources In Project, you set up people and equipment resources in exactly the same way because people and equipment are both examples of work resources However, you should be aware of important differences people resources might be flexible in the tasks they can perform, but equipment resources tend to be more specialized
  • 9. Cont>> you might want to set up equipment resources when Multiple teams or people might need a piece of equipment to accomplish different tasks simultaneously, and the equipment might be overbooked. You want to plan and track costs associated with the equipment.
  • 10. Enter information about equipment resources In the Resource Sheet, click the next empty cell in the Resource Namecolumn On the Standard toolbar, click the Resource Information button OR double-click a resource name Click the General tab if it is not already displayed In the Resource name field, type Mini-DV Camcorder In the Type field, click Work. In the Max. Units field for the Mini-DV Camcorder, type or click the arrows until the value shown is 300% and press ENTER
  • 11. Cont>> Enter the following information about equipment resources directly in the Resource Sheet or in the Resource Information dialog box, whichever you prefer. In either case, make sure Work is selected in the Type field.
  • 12. Setting Up Material Resources Material resources are consumables that you use up as the project proceeds On a construction project, material resources might include nails, lumber, and concrete You work with material resources in Project mainly to track the rate of consumption and the associated cost
  • 13. Cont>> How to enter information about a material resource In the Resource Sheet, click the next empty cell in the Resource Namecolumn Type Video Tape and press TAB In the Type field, click the down arrow, select Material, and press TAB In the Material Label field, type 30-min. cassette and press ENTER Note that you cannot enter a Max. Units value for a material resource. Since a material resource is a consumable item and not a person or piece of equipment that performs work, the Max. Units value doesn’t apply
  • 14. Setting Up Cost Resources The third and final type of resource that you can use in Project is the cost resource You can use a cost resource to represent a financial cost associated with a task in a project Common types of cost resources might include categories of expenses you’d want to track on a project for accounting purposes such as travel, entertainment, or training Like material resources, cost resources do no work and have no effect on the scheduling of a task
  • 15. Cont>> However, after you assign a cost resource to a task and specify the cost amount per task, you can then see the cumulative costs for that type of cost resource In the Resource Sheet, click the next empty cell in the Resource Name column. 2. Type Travel and press TAB. 3. In the Type field, click the down arrow, select Cost, and press ENTER.
  • 16. Entering Resource Pay Rates Almost all projects have some financial aspect, and cost limits drive the scope of many projects. Tracking and managing cost information allows the project manager to answer such important questions as What is the expected total cost of the project based on our task duration and resource estimates? Are we using expensive resources to do work that less expensive resources could do? How much money will a specific type of resource or task cost over the life of the project? How have we allocated a particular type of expense, such as travel, in a project? Are we spending money at a rate that we can sustain for the planned duration of the project
  • 17. Cont>> How to enter cost information for each work resource In the Resource Sheet, click the Std. Rate field for Jonathan Mollerup Type 10 and press ENTER In the Std. Rate field for Jon Ganio, type 15.50 and press ENTER Enter the following standard pay rates for the given resources
  • 19. Adjusting Working Time for Individual Resources Project uses different types of calendars for different purposes A resource calendar controls the working and nonworking times of a resource Project uses resource calendars to determine when work for a specific resource can be scheduled Resource calendars apply only to work resources (people and equipment) and not to material or cost resources
  • 20. Cont>> When you initially create resources in a project plan, Project creates a resource calendar for each work resource. The initial working time settings for resource calendars exactly match those of the Standard base calendar, chances are that some of your resources will need exceptions to the working time in the Standard base calendar-such as A flex-time work schedule Vacation time Other times when a resource is not available to work on the project, such as time spent training or attending a conference
  • 21. Cont>> How to specify the working and nonworking times for individual work resources On the Tools menu, click Change Working Time. The Change Working Time dialog box appears. In the For calendar box, click Garrett R.Vargas. Garrett R.Vargas’s resource calendar appears in the Change Working Time dialog box. Garrett has told you he will not be available to work on Thursday and Friday, January 10 and 11, because he plans to attend a film festival. On the Exceptions tab in the Change Working Time dialog box, click in the first row directly below the Name column heading and type Garrett attending West Coast Film Festival
  • 22. Cont>> Click in the Start field and type or select 1/10/2008. Click in the Finish field, type or select 1/11/2008, and then press ENTER