2. • Ministry of Power sanctioned following PMDP distribution projects in Nov 2016:
• Subsequently, additional funds were sanctioned in Jun 21/ Aug 21 for completion of balance sanctioned work:
PMDP-2015- Introduction
Project Initial Sanction amount ( Rs in Cr)
Urban Distribution Strengthening Projects Rs.1144.59 Crore
Rural Distribution Strengthening Projects Rs.1157.75 Crore
New Technology Projects Rs. 267.80 Crores
Total Cost Rs 2570.14 Crores
Project Additional Sanction amount
Urban Distribution Strengthening Projects Rs.486.81 Crore
Rural Distribution Strengthening Projects Rs.565.87 Crore
New Technology works PIA charges Rs. 15.72 Crore
Total Cost of Additional works Rs 1068.40 Crores
3. S N Action Point Responsibility Action Taken
1
PIAs to expedite the works for
additionally sanctioned projects and
advised that the material for the
projects may be mobilized by PIAs on
the identified land for which the land
allotment has not been done formally by
the UT of J&K.
All PIAs
KPDCL:
• Major material like poles conductor, cable DTs are available and erection works are going
on. At present, KPDCL has achieved progress of around 6 % and It is expected that
substantial progress shall be achieved in October and November 2022. 90% Pole errection
has been completed
• Further Civil works are in full swing at 3 Nos 33/11kV Receiving Stations being
constructed by KPDCL. Expected completion by Dec-22
RECPDCL:
• 30-40% of the material has been mobilized for PMDP(U) – Addl. Scheme including Power
Transformers for the allotted lands.
• 2 Nos. of lands out of 5 Nos. of lands for construction of New 33/11 KV S/s has been
handed over in Jammu circle. Further, JPDCL has instructed to augment the capacity of Ex.
33/11 kV S/s instead of construction of the balance 3 Nos. of New 33/11 kV S/s.
• 3 Nos. lands out of 4 Nos. lands for construction of New 33/11 kV S/s is allotted in
Srinagar circle. 1 No. Land is under Court stay.
POWERGRID:
• Work under progress at all 9 new substations & 12/16 Augmentation substations. 8335
poles have been erected and 36kM stringing done in 185 villages. DT installation and
LT/HT stringing under progress in villages. Materials being delivered and erected.
• Issue raised by PGCIL : JPDCL has informed that it will not bear the state share of 3.5% PIA
charges. No PIA charges has been received for Addl PMDP works till date. CEA has already
sent letter dated 28.07.2022 to J&K and Ladakh for the release of PIA state share charges
JPDCL response is still awaited.
2
PS (Energy, J&K) to expedite the pending
land allotment of 5 substations to PIAs
including the sub-station of Roopnagar
in Jammu region.
J&K J&K to respond
Action taken from Last meeting- 18.08.2022
4. S
N
Action Point Responsibility Action Taken
3
PS (energy), J&K to expedite the release of state share of
around Rs.4 Cr pending against ongoing New Technology
(smart metering) projects to RECPDCL so that the
matching central share can be released by MoP.
J&K
The State Share of Rs. 3.25 Cr. is approved by UT of J&K and is under
remittance against the ongoing New Technology (Smart Metering)
projects to RECPDCL.
4
CEO (RECPDCL) to provide the data regarding details of
billing and collection efficiency of installed meters in J&K
to MoP
RECPDCL
Billing & collection efficiency increased to ~31% (Jammu) and
~13% (Kashmir) for billing months of July-2022 vs. July-2021 for
No. of consumers 18,302 (Jammu) & 11,828 (Srinagar)
5
CEO (RECPDCL) to prioritize the smart meter installation of
Lot A meters (3 lakh) in Kashmir region before November
2022, owing to the upcoming winter season.
RECPDCL
Smart Meters supply will be increased from Sept-22 in Kashmir
region as compared to Jammu region to expedite installation of
Smart Meters in Kashmir.
6
Development of prepaid functionality for the installed
meters and integration with the new MDM system and
necessary testing to be completed by 30th of Aug-22.
RECPDCL
1) System Integration Testing (SIT) between CCB & MDM systems
is in progress and expected to be completed by 30.09.2022.
2) After successful completion of SIT, the deployment and
integrations will be shifted to UAT. Further, UAT will be conducted
between 01.10.2022 to 07.10.2022.
7
LPDD and RECPDCL to expedite wildlife board clearance for
construction of 220kV Nubra and Zanskar transmission line
in Ladakh
LPDD and
RECPDCL
LPDD and RECPDCL to respond
Action taken from Last meeting- 18.08.2022
5. PMDP projects Summary- ongoing projects
Projects UT No of sub-
projects
sanctioned
No of sub-
projects
awarded
No of sub-
projects
completed
Status of balance works Timelines
Distribution
strengthening
J&K 158 158 133 Balance 25 sub-projects in
progress.
All projects awarded
from Feb18 to Nov 18.
On the basis of
extension requests
from PIAs, the date of
completion is
between Sept 22 to
Dec 22
Ladakh 36 34 32 2 sub-projects (meter testing
lab) dropped.
2 sub-projects in progress.
New
Technology
J&K 3 2 - 2 sub-projects are in progress
and
1 project (smart grid project) is
dropped
Ladakh 2 0 - 2 Smart grid projects dropped
Ongoing Total 199 194 165 5 Sub projects dropped
Detailed progress
On-going projects issues
6. Additional sanctioned projects summary
Additional projects progress
Projects UT No of sub-
projects
sanctioned
No of sub-
projects
awarded
No of sub-
projects
completed
Status of balance
works
Timelines
Additional
projects
J&K 37 37 - All the additional
sub-projects are
under progress.
All the additional sub-
projects have been
awarded during Nov-
Dec 2021 and
scheduled to be
completed by Dec 22
Ladakh 3 3 -
Additional Total 40 40 -
Grand Total
(Ongoing + additional)
239 234 165 5 no of Ongoing Sub Projects have been
dropped
Sub projects – to be completed
Ongoing – 29 Additional -40
Additional projects issues Detailed progress
7. Ongoing projects- Financial Progress-1/2 As on 30th September 2022
Work
Package
Area PIA
Eligible
Cost***
Eligible
Central
Share
Central share
received by
PIAs*
State
Share
State
released
% Central
Share
Released
% State
Share
Released
Ongoing Rural JPDCL 376.85 313.30 256.8 63.55 54.71 82% 86%
KPDCL 329.20 273.68 181.67 55.52 65.83 66% 119%
LPDD 9.58 7.97 6.19 1.62 1.43 78% 88%
PGCIL 226.14 188.00 156.94 38.14 29.54 83% 77%
Rural Total 941.78 782.96 601.6 158.83 151.50 77% 95%
Urban JPDCL 169.81 152.83 126.57 16.98 15.15 83% 89%
JPDCL/KPDCL** 16.8 15.12 0.00 1.68 0.00 0% 0%
KPDCL 223.74 201.36 183.52 22.37 30.30 91% 135%
LPDD$$ 0.00 0.00 0.00 0.00 0 0% 0%
RECPDCL 637.98 574.18 436.68 63.80 57.16 76% 90%
Urban Total 1048.33 943.50 746.77 104.83 102.61 79% 98%
New Technology PGCIL$
0.00 0.00
0
0.00 0.00
0%
0%
RECPDCL 125.77 113.19 64.03 12.58 8.49 57% 68%
New Technology Total 125.77 113.19 64.03 12.58 8.49 57% 68%
Ongoing Total
2115.88 1839.65 1412.40 276.24 262.60
77%
95%
a. *Adjustment of state share on receipt of Central Share of Rs 122.07crore & Rs. 80.07 crore(already processed by MoP in Dec21) – KPDCL already released 100% share, proposed to adjust
the balance share in Additional works.. b. RECPDCL has reported reduction of state share from 12.58 crore to 8.49 crore for new technology project as balance share of 4.08 crore & Rs. 6.55
Cr. under Ongoing Infra projects yet to be released by JPDCL c. **Meter Testing Lab d. *** eligible cost (Minimum of Sanctioned and Surveyed & Approved Cost) e. $ Corresponds to
Smart Grid Project worth Rs 140.5 Crore which has been dropped f. $$ Corresponds to Meter Test Lab worth Rs 2.43 Crore which has been surrendered.
8. Additional projects -Financial Progress-2/2 As on 30th September 2022
Work Package Area PIA
Eligible
Cost
Eligible
Central
Share
Central
share
received
by PIAs
State
Share
State
released
% Central
Share
Released
% State
Share
Released
Additional Rural JPDCL 133.45 110.95 33.29 22.51 0.00 30% 0%
KPDCL 82.49 68.58 30.57 13.91 0.00 44.57% 0%
PGCIL 175.46 145.87 37.18 29.59 0.00 25.48% 0%
Rural Total 391.41 325.40 101.04 66.01 0.00 31.05% 0%
Urban JPDCL 70.63 63.57 0 7.06 0.00 0% 0%
KPDCL 33.50 30.15 0 3.35 0.00 0% 0%
RECPDCL 207.99 187.19 72.32 20.80 0.00 38.63% 0%
Urban Total 312.12 280.91 72.32 31.21 0.00 25.74% 0%
Additional Total
703.53 606.31 173.36 97.22 0.00 28.59% 0%
Re-appropriation-
PMDP(R+U)
New
Technology
RECPDCL 180 162 0 18 0.00 0% 0%
Grand Total 2999.41 2607.96 1585.76 391.46 262.60
Note: Recently, Rs. 125.18 cr was released by MoP on 28.07.2022 as 1st and 2nd tranche to JPDCL, KPDCL and RECPDCL towards additional distribution projects.
9. Town Name
Nos. of meters
sanctioned/ Awarded
Nos. of meters
installed
Nos. of meter
charged
Nos. of meters
communicating
a b c d e (w.r.t. 'd')
Jammu 57,750 57,750 56,563 53,654
Srinagar 57,750 57,750 51,224 43,395
Total 1,15,500 1,15,500 1,07,787 97,049
Overall % of works 100% 93% 84%
Status of 1.15 Lakh Smart Meters in UT of J&K as on 29.09.2022
Note- Till Aug-2022, billing done for 88,336 no. of smart meters in J&K (47,015 nos. in Jammu and 41,321 nos. in Srinagar)
10. Status of 6 Lakh Smart Meters in UT of J&K as on 29.09.2022
Lot A (3 lakh)
Lot B (3 lakh)
a. Technical Bid(s) submitted by Various PEA(s) has been opened on 20.09.2022.
b. PoC demonstration has been completed on 28.09.2022 & 29.09.2022.
c. Financial Bid(s) are expected to be opened on 07.10.2022.
Town(s)/ Discom(s) Scope
Meters
Delivered
Meters under
PDI/Transit
Meters
Installed
Meters Charged
1 2 3 4 5 (w.r.t. 3) 6(w.r.t. 5)
Jammu/ JPDCL 1,43,813 2,500 2,500 536 483
Srinagar/ KPDCL 1,43,813 2,200 2,800 542 542
Total 2,87,626
4,700 5,300
1,078 1,025
10,000
11. Ongoing Physical Progress- 1/4 As on 30th September 2022
Project
Description
Area Region PIA
Sub-Projects
Sanctioned
Sub-Projects
Awarded
Sub-
Projects Yet
to be
awarded
Sub-
Projects
Completed
% Physical
Progress
DoC
(Schedule/L
ikely)
Distribution
Strengthening
Rural
JAMMU
JPDCL 7 7 0 1 88%
Mar’22/
Sept’22
PGCIL 3 3 0 3 100% Apr’22-
Comp
All Works completed.
KASHMIR
KPDCL 6 6 0 0 69%
Oct-22/
Nov-’22
• Poor progress of work by M/s Shalaka Infra.
PGCIL 3 3 0 3 100% Mar’22-
Comp
All works completed.
LADAKH
PGCIL 2 2 0 1 85%
Nov-21/
Nov’22
• Balance: 5 nos villages (4 nos under Wild life) and 1 no 33/11 kV Pinchmik Substation.
Work under progress in all balance 5 nos villages and 1 nos substation. Target- Nov’22
• Reason of Delay: LPDD gave clearance for resumption of overhead work only on 18th
July'22.
Return
13. Ongoing Physical Progress- 3/4
Project
Description
Area Region PIA
Sub-Projects
Sactioned
Sub-
Projects
Awarded
Sub-Projects
Yet to be
awarded
Sub-
Projects
Completed
% Physical
Progress
Date of
Completio
n
RoBW
Rural Part B JAMMU JPDCL 37 37 0 37 100% Completed
KASHMIR KPDCL 46 46 0 46 100% Completed
LADAKH LPDD 4 4 0 4 100% Completed
UGC
Rural Part B JAMMU JPDCL 1 1 0 1 100% Completed
KASHMIR KPDCL 1 1 0 1 100% Completed
SS @ IA Rural Part B
JAMMU JPDCL 16 16 0 16 100% Completed
KASHMIR KPDCL 4 4 0 1 92%
Oct-
22/Nov-22
Shrine Works Rural Part B
JAMMU JPDCL 12 12 0 10 91% Sep-22
KASHMIR KPDCL 10 10 0 8 99% Sept-22
LADAKH LPDD 27 27 0 27 100% Completed
Return
14. Ongoing Physical Progress- 4/4
Project
Description
Area Region PIA
Sub-Projects
Sactioned
Sub-
Projects
Awarded
Sub-Projects
Yet to be
awarded
Sub-
Projects
Completed
% Physical
Progress
Date of
Completio
n
Smart Metering
(1.15 Lakh)
New Technology JAMMU RECPDCL 1 1 0 1 100% Completed
KASHMIR RECPDCL 1 1 0 1 100% Completed
Smart Grid New Technology J&K PGCIL 1 0 1 0
Dropped
LADAKH PGCIL 2 0 2 0
Grand Total 199 194 5* 165
* 05 sub projects (yet to be awarded)have been dropped, reducing the Total sub projects to 194.
15. Additional Physical Progress (1/3) As on 30th September 2022
Project
Des. Area Region PIA
Sub-
Projects
Sanctioned
Sub-Projects
Awarded
Sub-
Projects
Yet to be
awarded
Sub-
Projects
Completed
% Physical
Progress
Date of
Completi
on
Equipment
ordered
Distributi
on
Strength
ening
Rural
JAMMU JPDCL
7 7 0
0 3% Dec-22
DTs-147 ,
Conductors- 38
kms,Poles- 2726
PGCIL
3 3 0
0 3% Dec-22
All equipment
ordered
KASHMIR KPDCL
6 6 0
0 6% Dec-22
DTs-216, Poles-
2500,
Conductors- 302
kms
PGCIL
3 3 0
0 8% Dec-22
All equipment
ordered
LADAKH PGCIL
2 2 0
0 2% Dec-22
All equipment
ordered
16. Additional Physical Progress (2/3) As on 30th September 2022
Distribution
Strengthenin
g
Urban
JAMMU JPDCL
4 4 0
0 3% Dec-22
PTR-3,Power cables,Poles-
1159, DTs-303,Conductors-
400 kms
RECPDCL
1 1 0
0 15% Dec-22
PTR, VCBs,C&R
Panels,Poles-1368,DTs-
361,Conductors-102 kms
KASHMIR KPDCL
3 3 0
0 6% Dec-22
Poles-740,Conductors-92
kms
RECPDCL
3 3 0
0 1% Dec-22
PTR-3,DTs-308,Conductors-
35 kms
LADAKH RECPDCL 1 1 0 0 0% Dec-22 DTs-50,Poles-
540,Conductors-73 kms
Project Des. Area Region PIA
Sub-
Projects
Sanctio
ned
Sub-
Projects
Awarde
d
Sub-
Projects
Yet to be
awarded
Sub-
Projects
Complete
d
% Physical
Progress
Date of
Completi
on
Equipment ordered
17. UGC Rural
Part B JAMMU JPDCL
3 3 0
0 0 Dec-22
KASHMIR KPDCL
2 2 0
0 0 Dec-22
SS @ IA
JAMMU JPDCL
1 1 0
0 0 Dec-22
KASHMIR KPDCL
1 1 0
0 0 Dec-22
Additional Total
40 40 0
0
Project Des. Area Region PIA
Sub-
Projects
Sanctio
ned
Sub-
Projects
Awarde
d
Sub-
Projects
Yet to be
awarded
Sub-
Projects
Complete
d
% Physical
Progress
Date of
Completi
on
Equipment ordered
Additional Physical Progress (2/3) As on 30th September 2022
18. Project
Description
Area Region PIA Issues/ Reasons for delay
Distribution
Strengthening
Rural
JAMMU
JPDCL
DTs, 11 kV & LT Lines: Slow pace of work of execution by M/s Shalakha
Infratech Pvt.Ltd in Doda & Kishtwar districts. (same shall be completed
by Sept'22)
PGCIL All works completed.
KASHMIR
KPDCL • Poor progress of work by M/s Shalaka Infra.
PGCIL • All works completed.
LADAKH PGCIL
• Balance: 5 nos villages (4 nos under Wild life) & 1no 33kV Pinchmik S/s
• Work under progress in all balance 5 nos villages and 1 no Pinchmik S/s
• Reason of Delay: LPDD gave clearance for resumption of overhead work
only on 18th July'22. Target- Nov'22
Ongoing projects- issues(1/2)
19. Distribution
Strengthenin
g
Urban
JAMMU
JPDCL
33/11 kV S/s: Delay in land allotment.
33 kV Lines: Due to restricted availability of shutdowns
RECPDCL
33 kV Line : Shutdown related issue and RoW issues
11 kV Line: Limited Hours shutdown and RoW issues.
KASHMIR
KPDCL
Delay in allotment of land at one receiving station in Budgam due to
litigation which finally got dismissed in Aug-21 post which work was
started. Station Stand Test charged on 2nd October 2022
RECPDCL
33/11 kV S/s: Delay in allotment of Land
33 kV Line Shutdown related issue
HT Line & LT Line: Shutdowns and RoW issues
LADAKH RECPDCL 66/11 kV S/s and 66 kV line: limited working season.
Ongoing projects issues(2/2)
Project
Description
Area Region PIA Issues/ Reasons for delay
SS @ IA Rural
Part B
KASHMIR KPDCL
Delay due to allotment of land by Industrial department within
Industrial estates, Covid Restrictions and lock downs resulting in de-
mobilization by contractors.
Shrine Works JAMMU JPDCL Delay on the part of TKC due to some payment issue.
20. Additional Project implementation issues
Project
Description
Area Region PIA Remarks/ Reasons for delay
Distribution
Strengthening
Rural JAMMU PGCIL
Advance @ 30% (Rs 11.32 Cr) not received from REC for central share of
Ladakh UT.
Advance @ 30% (Rs 10.12 Cr) for State share not received from J&K UT
(7.83 Cr) and Ladakh UT (2.29 Cr).
Urban
JAMMU RECPDCL
Out of the proposed 5 New substations in Jammu Circle under PMDP(U),
where RECPDCL is PIA, all 5 Lands have been identified. Further, out of 5
Nos. identified lands, 02 Nos. Land at Arnia & Talab Tillo are handed
over to RECPDCL. Remaining 3 No. Land at RS Pura(Barnota), Roopnagar
& Bhatindi(Sunjwan) are yet to be handed over.
KASHMIR RECPDCL
Land has been identified for all proposed 4 New substations in Srinagar
Circle under PMDP(U) where RECPDCL is PIA. Further, KPDCL has
instructed to take up the works at 4 Nos. identified locations for new
33/11 kV S/s. However, 1 land at Tengpora is under Court stay ( District
court ).
Issued highlighted by PGCIL & RECPDCL in regard to land acquisition for additional projects
23. Comparison table of state share release(1/2)
Region PIA
December 2021 September 2022
State Share
State share
released
% State
Released
State Share
State share
released
% State
Released
Rural
JPDCL 65.32 67.21 103% 63.55 54.71 86%
KPDCL 56.04 78.82 141% 55.52 65.83 119%
LPDD 1.62 1.43 88% 1.62 1.43 88%
PGCIL 38.14 13.05 34% 38.14 29.54 77%
Total 161.11 160.51 100% 158.83 151.50 95%
Urban
JPDCL 16.88 25.54 151% 16.98 15.15 89%
JPDCL/KPDCL 3.76 0.00 0% 1.68 0.00 0%
KPDCL 22.65 58.23 257% 22.37 30.30 135%
LPDD 0.24 0.00 0% 0 0 0%
RECPDCL 63.72 27.29 43% 63.80 57.16 90%
Total 107.26 111.06 104% 104.83 102.61 98%
New Tech
PGCIL 14.06 0.00 0% 0 0 0%
RECPDCL 12.51 0.00 0% 12.58 8.49 68%
Total 26.57 0.00 0% 12.58 8.49 68%
Grand Total 294.94 271.57 92% 276.24 262.60 95%
Return
24. Comparison of state share release(2/2)
As can be seen from above table of Fund Status for the Month of Dec-21 and September-22
a. State-share released amount for PGCIL has gone up from Rs. 13.05 cr (34%) in Dec-21 to Rs. 29.54 cr (77%) in
July 2022. However, there is no change in the month of September 2022.
b. State-share released amount for RECPDCL has gone up from Rs. 0 cr (0%) in Dec-21 to Rs. 8.49 (68%) in July 22
for PMDP (New Technology). However, there is no change in the month of September 2022.
Return
25. PIA Charges
Work Package Area PIA
PIA Charges
Sanctioned
PIA Charges
Eligible
PIA charges
Released
Ongoing Rural PGCIL 16.38 13.34 9.92
Urban RECPDCL 37.64 37.64 27.74
New Technology PGCIL 8.29 0.00 0.00
RECPDCL 7.43 7.42 0.00
Ongoing Total 69.74 58.40 37.66
Additional Rural PGCIL 12.07 10.35 0.00
Urban RECPDCL 17.11 12.27 0.00
Additional Total 29.17 22.62 0.00
Re-appropriation-
PMDP (R) AND
PMDP(U) New Technology RECPDCL
7.22+3.62 0+3.62 0.00
Grand Total 109.75 84.64 37.66
Note: (a) PIA charges includes for Ongoing and Additional Works as Additional Fund.
(b) In addition to PIA charges payable to POWERGRID by MOP for ongoing PMDP, State PIA charges of Rs 2.6 Cr (J&K UT- 2.24 Cr &
Ladakh UT- 0.36 Cr) is also pending from DISCOMs.
(c) For Additional PMDP Works, advance payment of PIA charges of Rs 1.95 Cr (J&K UT- 1.62 Cr & Ladakh UT- Rs 0.33 Cr) is also
pending from DISCOMs to PGCIL
Return
27. Work Package Area PIA PMA
PMA Charges
Sanctioned
PMA Charges
Eligible
PMA charges
Released
Additional
Rural
JPDCL RECPDCL 0.94 0.67 0.00
KPDCL RECPDCL 0.68 0.41 0.00
PGCIL RECPDCL 1.02 0.88 0.00
Rural Total 2.64 1.96 0.00
Urban
JPDCL RECPDCL 0.43 0.35 0.00
KPDCL RECPDCL 0.26 0.16 0.00
RECPDCL Voyant solution 1.45 1.04 0.00
Urban Total 2.13 1.56 0.00
Additional Total 4.77 3.51 0.00
Re-appropriation-
PMDP(R+U)
New
Technology
RECPDCL* 0.90 0.90 0.00
Grand Total 17.50 14.99 2.90
PMA Charges-2/2
a. $ Corresponds to Smart Grid Project worth Rs 140.5 Crore which has been dropped.
b. $$ Corresponds to Meter Test Lab worth Rs 2.43 Crore which has been surrendered.
Return
28. Region PIA
66/11,33/11KV Sub-Stations 66KV & 33KV Lines
Sanctio
ned
Nos
Awarde
d Nos
Surve
yed
Approv
ed
Equipment
ordered, Nos
Status of
Land
Acquisition
Sanctione
d Scope
(CKm)
awarded
,Ckm
Survey
ed
Approv
ed
Conductor
and Poles
ordered
ROW
issues if
any
Jammu
JPDCL 4 4 4 4
PowerCables,PT
R-3
Acquired -4 91 91 93 93 200 nos. Nil
RECPDCL 5 5 2 2
PTR, 33kV VCBs,
11kV VCB
panels, C&R
Panels,
Capacitor banks
and associated
equipments.
Acquired - 2,
Identified -3
169.68 169.68 103.35 103.35
71.5
Ckms/850
nos.
Nil
Kashmir
KPDCL 2 2 2 2 Acquired-2 30.5 30.5 9 9
30
ckms/310
nos.
Nil
RECPDCL 7 7 7 7
PTR-3
Acquired-6,
Under Court
stay-1
24 18 24.4 24.4 5 kms Nil
Ladakh RECPDCL 0 0 0 0 0 0 0 0 0 0 Nil
Additional Projects status Urban(Sub-stations and HT LT lines) 1/4
Return
Sub-station Land acquisition status in Urban area:
Out of 18 awarded substations , Land Acquired for 14 SS, Land for 01 SS are under court stay and land for 03 nos SS has been identified.
30. Regio
n
PIA
66/11,33/11KV Sub-Stations 66KV & 33KV Lines
Sanctio
ned
Nos
Awarde
d Nos
Surveyed Approved
Equipment
ordered, Nos
Status of
Land
Acquisition
Sanctione
d Scope
(CKm)
awarded,
Ckm
Surveye
d
Approved
Conductor
and Poles
ordered
ROW
issues if
any
Jammu
JPDCL 25 25 24 24
Materials in
pipeline
Acquired-24 78 78 43 43 226 nos. Nil
PGCIL 9 6 6
6
(restricted within
sanctioned fund)
Engineering.
Completed & Eqp
ordered.
Acquired-6 42 42 22
22
(restricted within
sanctioned fund)
All ordered Nil
Kashmi
r
KPDCL 1 1 1 1 Acquired-1 141.76 137.6 140.5 140.5
54 kms/384
nos.
Nil
PGCIL 19 19 19
16
(restricted within
sanctioned fund)
Engineering.
Completed & Eqp
ordered.
Acquired-16 98 48 18.1
18.1
(restricted within
sanctioned fund)
All ordered Nil
Ladakh PGCIL 3 3 3 3
Engineering.
Completed & Eqp
ordered.
Acquired-3 111 111 109
109
(restricted within
sanctioned fund)
All ordered Nil
Additional Projects status Rural (Sub-stations and HT LT lines) 3/4
Return
Sub-station Land acquisition status in Rural
Out of 53 awarded substations , Land Acquired for all 53 SS
31. Region PIA
DTs installation, Nos 11KV Feeders,CKm
Sanction
ed (DTs)
awarded
Surveye
d
Approved
DTs
ordered,
Nos
Sanction
ed (11 KV
line
awarde
d
Survey
ed
Approved
Conductor
and Poles
ordered,
kms/Nos
ROW
issues if
any
Jammu
JPDCL 460 460 292 292 147 424.21 424.21 293.4 293.4
38 kms/2500
nos
Nil
PGCIL 183 147 139 139 (restricted within
sanctioned fund)
139 198.88 179.9 177.9 177.9 (restricted within
sanctioned fund)
All ordered Nil
Kashmir
KPDCL 422 422 321 321 216 500.4 469.1 418 418
248 kms/2115
nos.
Nil
PGCIL 388 265 214 214 (restricted within
sanctioned fund)
214 102.51 74.6 62.5 62.5(restricted within
sanctioned fund)
All ordered Nil
Ladakh PGCIL 3 3 3 3 3 42.81 42.81 20.81 20.81(restricted within
sanctioned fund)
All ordered Nil
Additional Projects status Rural (DTs, HT/LT Feeders) 4/4
Return
Region PIA
LT Feeders, CKM
Sanctioned (LT
line )
awarded Surveyed Approved
Conductor and Poles
ordered, kms/Nos
ROW issues if
any
Jammu
JPDCL 618.4 618.4 470.8 470.8 140 kms/2380 nos Nil
PGCIL 302.65 227.2 364.17 364.17(due to site requirement) All ordered. Nil
Kashmir
KPDCL 659.6 602.2 641.9 641.9 441.9 kms/6288 nos. Nil
PGCIL 386.95 233.5 188.3 188.3(restricted within sanctioned fund) All ordered Nil
Ladakh PGCIL 4 4 0.5 0.5(restricted within sanctioned fund) All ordered Nil