Progress of Distribution Projects under PMDP
(J&K and Ladakh)
10.10.2022
• Ministry of Power sanctioned following PMDP distribution projects in Nov 2016:
• Subsequently, additional funds were sanctioned in Jun 21/ Aug 21 for completion of balance sanctioned work:
PMDP-2015- Introduction
Project Initial Sanction amount ( Rs in Cr)
Urban Distribution Strengthening Projects Rs.1144.59 Crore
Rural Distribution Strengthening Projects Rs.1157.75 Crore
New Technology Projects Rs. 267.80 Crores
Total Cost Rs 2570.14 Crores
Project Additional Sanction amount
Urban Distribution Strengthening Projects Rs.486.81 Crore
Rural Distribution Strengthening Projects Rs.565.87 Crore
New Technology works PIA charges Rs. 15.72 Crore
Total Cost of Additional works Rs 1068.40 Crores
S N Action Point Responsibility Action Taken
1
PIAs to expedite the works for
additionally sanctioned projects and
advised that the material for the
projects may be mobilized by PIAs on
the identified land for which the land
allotment has not been done formally by
the UT of J&K.
All PIAs
KPDCL:
• Major material like poles conductor, cable DTs are available and erection works are going
on. At present, KPDCL has achieved progress of around 6 % and It is expected that
substantial progress shall be achieved in October and November 2022. 90% Pole errection
has been completed
• Further Civil works are in full swing at 3 Nos 33/11kV Receiving Stations being
constructed by KPDCL. Expected completion by Dec-22
RECPDCL:
• 30-40% of the material has been mobilized for PMDP(U) – Addl. Scheme including Power
Transformers for the allotted lands.
• 2 Nos. of lands out of 5 Nos. of lands for construction of New 33/11 KV S/s has been
handed over in Jammu circle. Further, JPDCL has instructed to augment the capacity of Ex.
33/11 kV S/s instead of construction of the balance 3 Nos. of New 33/11 kV S/s.
• 3 Nos. lands out of 4 Nos. lands for construction of New 33/11 kV S/s is allotted in
Srinagar circle. 1 No. Land is under Court stay.
POWERGRID:
• Work under progress at all 9 new substations & 12/16 Augmentation substations. 8335
poles have been erected and 36kM stringing done in 185 villages. DT installation and
LT/HT stringing under progress in villages. Materials being delivered and erected.
• Issue raised by PGCIL : JPDCL has informed that it will not bear the state share of 3.5% PIA
charges. No PIA charges has been received for Addl PMDP works till date. CEA has already
sent letter dated 28.07.2022 to J&K and Ladakh for the release of PIA state share charges
JPDCL response is still awaited.
2
PS (Energy, J&K) to expedite the pending
land allotment of 5 substations to PIAs
including the sub-station of Roopnagar
in Jammu region.
J&K J&K to respond
Action taken from Last meeting- 18.08.2022
S
N
Action Point Responsibility Action Taken
3
PS (energy), J&K to expedite the release of state share of
around Rs.4 Cr pending against ongoing New Technology
(smart metering) projects to RECPDCL so that the
matching central share can be released by MoP.
J&K
The State Share of Rs. 3.25 Cr. is approved by UT of J&K and is under
remittance against the ongoing New Technology (Smart Metering)
projects to RECPDCL.
4
CEO (RECPDCL) to provide the data regarding details of
billing and collection efficiency of installed meters in J&K
to MoP
RECPDCL
Billing & collection efficiency increased to ~31% (Jammu) and
~13% (Kashmir) for billing months of July-2022 vs. July-2021 for
No. of consumers 18,302 (Jammu) & 11,828 (Srinagar)
5
CEO (RECPDCL) to prioritize the smart meter installation of
Lot A meters (3 lakh) in Kashmir region before November
2022, owing to the upcoming winter season.
RECPDCL
Smart Meters supply will be increased from Sept-22 in Kashmir
region as compared to Jammu region to expedite installation of
Smart Meters in Kashmir.
6
Development of prepaid functionality for the installed
meters and integration with the new MDM system and
necessary testing to be completed by 30th of Aug-22.
RECPDCL
1) System Integration Testing (SIT) between CCB & MDM systems
is in progress and expected to be completed by 30.09.2022.
2) After successful completion of SIT, the deployment and
integrations will be shifted to UAT. Further, UAT will be conducted
between 01.10.2022 to 07.10.2022.
7
LPDD and RECPDCL to expedite wildlife board clearance for
construction of 220kV Nubra and Zanskar transmission line
in Ladakh
LPDD and
RECPDCL
LPDD and RECPDCL to respond
Action taken from Last meeting- 18.08.2022
PMDP projects Summary- ongoing projects
Projects UT No of sub-
projects
sanctioned
No of sub-
projects
awarded
No of sub-
projects
completed
Status of balance works Timelines
Distribution
strengthening
J&K 158 158 133 Balance 25 sub-projects in
progress.
All projects awarded
from Feb18 to Nov 18.
On the basis of
extension requests
from PIAs, the date of
completion is
between Sept 22 to
Dec 22
Ladakh 36 34 32 2 sub-projects (meter testing
lab) dropped.
2 sub-projects in progress.
New
Technology
J&K 3 2 - 2 sub-projects are in progress
and
1 project (smart grid project) is
dropped
Ladakh 2 0 - 2 Smart grid projects dropped
Ongoing Total 199 194 165 5 Sub projects dropped
Detailed progress
On-going projects issues
Additional sanctioned projects summary
Additional projects progress
Projects UT No of sub-
projects
sanctioned
No of sub-
projects
awarded
No of sub-
projects
completed
Status of balance
works
Timelines
Additional
projects
J&K 37 37 - All the additional
sub-projects are
under progress.
All the additional sub-
projects have been
awarded during Nov-
Dec 2021 and
scheduled to be
completed by Dec 22
Ladakh 3 3 -
Additional Total 40 40 -
Grand Total
(Ongoing + additional)
239 234 165 5 no of Ongoing Sub Projects have been
dropped
Sub projects – to be completed
Ongoing – 29 Additional -40
Additional projects issues Detailed progress
Ongoing projects- Financial Progress-1/2 As on 30th September 2022
Work
Package
Area PIA
Eligible
Cost***
Eligible
Central
Share
Central share
received by
PIAs*
State
Share
State
released
% Central
Share
Released
% State
Share
Released
Ongoing Rural JPDCL 376.85 313.30 256.8 63.55 54.71 82% 86%
KPDCL 329.20 273.68 181.67 55.52 65.83 66% 119%
LPDD 9.58 7.97 6.19 1.62 1.43 78% 88%
PGCIL 226.14 188.00 156.94 38.14 29.54 83% 77%
Rural Total 941.78 782.96 601.6 158.83 151.50 77% 95%
Urban JPDCL 169.81 152.83 126.57 16.98 15.15 83% 89%
JPDCL/KPDCL** 16.8 15.12 0.00 1.68 0.00 0% 0%
KPDCL 223.74 201.36 183.52 22.37 30.30 91% 135%
LPDD$$ 0.00 0.00 0.00 0.00 0 0% 0%
RECPDCL 637.98 574.18 436.68 63.80 57.16 76% 90%
Urban Total 1048.33 943.50 746.77 104.83 102.61 79% 98%
New Technology PGCIL$
0.00 0.00
0
0.00 0.00
0%
0%
RECPDCL 125.77 113.19 64.03 12.58 8.49 57% 68%
New Technology Total 125.77 113.19 64.03 12.58 8.49 57% 68%
Ongoing Total
2115.88 1839.65 1412.40 276.24 262.60
77%
95%
a. *Adjustment of state share on receipt of Central Share of Rs 122.07crore & Rs. 80.07 crore(already processed by MoP in Dec21) – KPDCL already released 100% share, proposed to adjust
the balance share in Additional works.. b. RECPDCL has reported reduction of state share from 12.58 crore to 8.49 crore for new technology project as balance share of 4.08 crore & Rs. 6.55
Cr. under Ongoing Infra projects yet to be released by JPDCL c. **Meter Testing Lab d. *** eligible cost (Minimum of Sanctioned and Surveyed & Approved Cost) e. $ Corresponds to
Smart Grid Project worth Rs 140.5 Crore which has been dropped f. $$ Corresponds to Meter Test Lab worth Rs 2.43 Crore which has been surrendered.
Additional projects -Financial Progress-2/2 As on 30th September 2022
Work Package Area PIA
Eligible
Cost
Eligible
Central
Share
Central
share
received
by PIAs
State
Share
State
released
% Central
Share
Released
% State
Share
Released
Additional Rural JPDCL 133.45 110.95 33.29 22.51 0.00 30% 0%
KPDCL 82.49 68.58 30.57 13.91 0.00 44.57% 0%
PGCIL 175.46 145.87 37.18 29.59 0.00 25.48% 0%
Rural Total 391.41 325.40 101.04 66.01 0.00 31.05% 0%
Urban JPDCL 70.63 63.57 0 7.06 0.00 0% 0%
KPDCL 33.50 30.15 0 3.35 0.00 0% 0%
RECPDCL 207.99 187.19 72.32 20.80 0.00 38.63% 0%
Urban Total 312.12 280.91 72.32 31.21 0.00 25.74% 0%
Additional Total
703.53 606.31 173.36 97.22 0.00 28.59% 0%
Re-appropriation-
PMDP(R+U)
New
Technology
RECPDCL 180 162 0 18 0.00 0% 0%
Grand Total 2999.41 2607.96 1585.76 391.46 262.60
Note: Recently, Rs. 125.18 cr was released by MoP on 28.07.2022 as 1st and 2nd tranche to JPDCL, KPDCL and RECPDCL towards additional distribution projects.
Town Name
Nos. of meters
sanctioned/ Awarded
Nos. of meters
installed
Nos. of meter
charged
Nos. of meters
communicating
a b c d e (w.r.t. 'd')
Jammu 57,750 57,750 56,563 53,654
Srinagar 57,750 57,750 51,224 43,395
Total 1,15,500 1,15,500 1,07,787 97,049
Overall % of works 100% 93% 84%
Status of 1.15 Lakh Smart Meters in UT of J&K as on 29.09.2022
Note- Till Aug-2022, billing done for 88,336 no. of smart meters in J&K (47,015 nos. in Jammu and 41,321 nos. in Srinagar)
Status of 6 Lakh Smart Meters in UT of J&K as on 29.09.2022
Lot A (3 lakh)
Lot B (3 lakh)
a. Technical Bid(s) submitted by Various PEA(s) has been opened on 20.09.2022.
b. PoC demonstration has been completed on 28.09.2022 & 29.09.2022.
c. Financial Bid(s) are expected to be opened on 07.10.2022.
Town(s)/ Discom(s) Scope
Meters
Delivered
Meters under
PDI/Transit
Meters
Installed
Meters Charged
1 2 3 4 5 (w.r.t. 3) 6(w.r.t. 5)
Jammu/ JPDCL 1,43,813 2,500 2,500 536 483
Srinagar/ KPDCL 1,43,813 2,200 2,800 542 542
Total 2,87,626
4,700 5,300
1,078 1,025
10,000
Ongoing Physical Progress- 1/4 As on 30th September 2022
Project
Description
Area Region PIA
Sub-Projects
Sanctioned
Sub-Projects
Awarded
Sub-
Projects Yet
to be
awarded
Sub-
Projects
Completed
% Physical
Progress
DoC
(Schedule/L
ikely)
Distribution
Strengthening
Rural
JAMMU
JPDCL 7 7 0 1 88%
Mar’22/
Sept’22
PGCIL 3 3 0 3 100% Apr’22-
Comp
All Works completed.
KASHMIR
KPDCL 6 6 0 0 69%
Oct-22/
Nov-’22
• Poor progress of work by M/s Shalaka Infra.
PGCIL 3 3 0 3 100% Mar’22-
Comp
All works completed.
LADAKH
PGCIL 2 2 0 1 85%
Nov-21/
Nov’22
• Balance: 5 nos villages (4 nos under Wild life) and 1 no 33/11 kV Pinchmik Substation.
Work under progress in all balance 5 nos villages and 1 nos substation. Target- Nov’22
• Reason of Delay: LPDD gave clearance for resumption of overhead work only on 18th
July'22.
Return
Ongoing Physical Progress- 2/4
Project
Description
Area Region PIA
Sub-
Projects
Sanctioned
Sub-Projects
Awarded
Sub-
Projects
Yet to be
awarded
Sub-
Projects
Completed
% Physical
Progress
DoC
(Schedul
e/Likely)
Distribution
Strengthening
Urban
JAMMU
JPDCL 4 4 0 0 89%
Dec’21/
Sept’22
RECPDCL 1 1 0 0 91%
Dec’21/
Sept’22
KASHMIR
KPDCL 3 3 0 2 99%
Dec’21/
Oct’22
RECPDCL 3 3 0 2 87%
Dec’21/
Dec’22
LADAKH RECPDCL 1 1 0 0 94%
Dec’21/
Sep’22
Meter Test Lab Urban
J&K J/KPDCL 1 1 0 0 8% Awarded
LADAKH LPDD 2 0 2 0 0% Dropped
Ongoing Physical Progress- 3/4
Project
Description
Area Region PIA
Sub-Projects
Sactioned
Sub-
Projects
Awarded
Sub-Projects
Yet to be
awarded
Sub-
Projects
Completed
% Physical
Progress
Date of
Completio
n
RoBW
Rural Part B JAMMU JPDCL 37 37 0 37 100% Completed
KASHMIR KPDCL 46 46 0 46 100% Completed
LADAKH LPDD 4 4 0 4 100% Completed
UGC
Rural Part B JAMMU JPDCL 1 1 0 1 100% Completed
KASHMIR KPDCL 1 1 0 1 100% Completed
SS @ IA Rural Part B
JAMMU JPDCL 16 16 0 16 100% Completed
KASHMIR KPDCL 4 4 0 1 92%
Oct-
22/Nov-22
Shrine Works Rural Part B
JAMMU JPDCL 12 12 0 10 91% Sep-22
KASHMIR KPDCL 10 10 0 8 99% Sept-22
LADAKH LPDD 27 27 0 27 100% Completed
Return
Ongoing Physical Progress- 4/4
Project
Description
Area Region PIA
Sub-Projects
Sactioned
Sub-
Projects
Awarded
Sub-Projects
Yet to be
awarded
Sub-
Projects
Completed
% Physical
Progress
Date of
Completio
n
Smart Metering
(1.15 Lakh)
New Technology JAMMU RECPDCL 1 1 0 1 100% Completed
KASHMIR RECPDCL 1 1 0 1 100% Completed
Smart Grid New Technology J&K PGCIL 1 0 1 0
Dropped
LADAKH PGCIL 2 0 2 0
Grand Total 199 194 5* 165
* 05 sub projects (yet to be awarded)have been dropped, reducing the Total sub projects to 194.
Additional Physical Progress (1/3) As on 30th September 2022
Project
Des. Area Region PIA
Sub-
Projects
Sanctioned
Sub-Projects
Awarded
Sub-
Projects
Yet to be
awarded
Sub-
Projects
Completed
% Physical
Progress
Date of
Completi
on
Equipment
ordered
Distributi
on
Strength
ening
Rural
JAMMU JPDCL
7 7 0
0 3% Dec-22
DTs-147 ,
Conductors- 38
kms,Poles- 2726
PGCIL
3 3 0
0 3% Dec-22
All equipment
ordered
KASHMIR KPDCL
6 6 0
0 6% Dec-22
DTs-216, Poles-
2500,
Conductors- 302
kms
PGCIL
3 3 0
0 8% Dec-22
All equipment
ordered
LADAKH PGCIL
2 2 0
0 2% Dec-22
All equipment
ordered
Additional Physical Progress (2/3) As on 30th September 2022
Distribution
Strengthenin
g
Urban
JAMMU JPDCL
4 4 0
0 3% Dec-22
PTR-3,Power cables,Poles-
1159, DTs-303,Conductors-
400 kms
RECPDCL
1 1 0
0 15% Dec-22
PTR, VCBs,C&R
Panels,Poles-1368,DTs-
361,Conductors-102 kms
KASHMIR KPDCL
3 3 0
0 6% Dec-22
Poles-740,Conductors-92
kms
RECPDCL
3 3 0
0 1% Dec-22
PTR-3,DTs-308,Conductors-
35 kms
LADAKH RECPDCL 1 1 0 0 0% Dec-22 DTs-50,Poles-
540,Conductors-73 kms
Project Des. Area Region PIA
Sub-
Projects
Sanctio
ned
Sub-
Projects
Awarde
d
Sub-
Projects
Yet to be
awarded
Sub-
Projects
Complete
d
% Physical
Progress
Date of
Completi
on
Equipment ordered
UGC Rural
Part B JAMMU JPDCL
3 3 0
0 0 Dec-22
KASHMIR KPDCL
2 2 0
0 0 Dec-22
SS @ IA
JAMMU JPDCL
1 1 0
0 0 Dec-22
KASHMIR KPDCL
1 1 0
0 0 Dec-22
Additional Total
40 40 0
0
Project Des. Area Region PIA
Sub-
Projects
Sanctio
ned
Sub-
Projects
Awarde
d
Sub-
Projects
Yet to be
awarded
Sub-
Projects
Complete
d
% Physical
Progress
Date of
Completi
on
Equipment ordered
Additional Physical Progress (2/3) As on 30th September 2022
Project
Description
Area Region PIA Issues/ Reasons for delay
Distribution
Strengthening
Rural
JAMMU
JPDCL
 DTs, 11 kV & LT Lines: Slow pace of work of execution by M/s Shalakha
Infratech Pvt.Ltd in Doda & Kishtwar districts. (same shall be completed
by Sept'22)
PGCIL  All works completed.
KASHMIR
KPDCL • Poor progress of work by M/s Shalaka Infra.
PGCIL • All works completed.
LADAKH PGCIL
• Balance: 5 nos villages (4 nos under Wild life) & 1no 33kV Pinchmik S/s
• Work under progress in all balance 5 nos villages and 1 no Pinchmik S/s
• Reason of Delay: LPDD gave clearance for resumption of overhead work
only on 18th July'22. Target- Nov'22
Ongoing projects- issues(1/2)
Distribution
Strengthenin
g
Urban
JAMMU
JPDCL
 33/11 kV S/s: Delay in land allotment.
 33 kV Lines: Due to restricted availability of shutdowns
RECPDCL
 33 kV Line : Shutdown related issue and RoW issues
 11 kV Line: Limited Hours shutdown and RoW issues.
KASHMIR
KPDCL
 Delay in allotment of land at one receiving station in Budgam due to
litigation which finally got dismissed in Aug-21 post which work was
started. Station Stand Test charged on 2nd October 2022
RECPDCL
 33/11 kV S/s: Delay in allotment of Land
 33 kV Line Shutdown related issue
 HT Line & LT Line: Shutdowns and RoW issues
LADAKH RECPDCL  66/11 kV S/s and 66 kV line: limited working season.
Ongoing projects issues(2/2)
Project
Description
Area Region PIA Issues/ Reasons for delay
SS @ IA Rural
Part B
KASHMIR KPDCL
 Delay due to allotment of land by Industrial department within
Industrial estates, Covid Restrictions and lock downs resulting in de-
mobilization by contractors.
Shrine Works JAMMU JPDCL  Delay on the part of TKC due to some payment issue.
Additional Project implementation issues
Project
Description
Area Region PIA Remarks/ Reasons for delay
Distribution
Strengthening
Rural JAMMU PGCIL
 Advance @ 30% (Rs 11.32 Cr) not received from REC for central share of
Ladakh UT.
 Advance @ 30% (Rs 10.12 Cr) for State share not received from J&K UT
(7.83 Cr) and Ladakh UT (2.29 Cr).
Urban
JAMMU RECPDCL
 Out of the proposed 5 New substations in Jammu Circle under PMDP(U),
where RECPDCL is PIA, all 5 Lands have been identified. Further, out of 5
Nos. identified lands, 02 Nos. Land at Arnia & Talab Tillo are handed
over to RECPDCL. Remaining 3 No. Land at RS Pura(Barnota), Roopnagar
& Bhatindi(Sunjwan) are yet to be handed over.
KASHMIR RECPDCL
 Land has been identified for all proposed 4 New substations in Srinagar
Circle under PMDP(U) where RECPDCL is PIA. Further, KPDCL has
instructed to take up the works at 4 Nos. identified locations for new
33/11 kV S/s. However, 1 land at Tengpora is under Court stay ( District
court ).
Issued highlighted by PGCIL & RECPDCL in regard to land acquisition for additional projects
THANK YOU
LINKED SLIDES
Comparison table of state share release(1/2)
Region PIA
December 2021 September 2022
State Share
State share
released
% State
Released
State Share
State share
released
% State
Released
Rural
JPDCL 65.32 67.21 103% 63.55 54.71 86%
KPDCL 56.04 78.82 141% 55.52 65.83 119%
LPDD 1.62 1.43 88% 1.62 1.43 88%
PGCIL 38.14 13.05 34% 38.14 29.54 77%
Total 161.11 160.51 100% 158.83 151.50 95%
Urban
JPDCL 16.88 25.54 151% 16.98 15.15 89%
JPDCL/KPDCL 3.76 0.00 0% 1.68 0.00 0%
KPDCL 22.65 58.23 257% 22.37 30.30 135%
LPDD 0.24 0.00 0% 0 0 0%
RECPDCL 63.72 27.29 43% 63.80 57.16 90%
Total 107.26 111.06 104% 104.83 102.61 98%
New Tech
PGCIL 14.06 0.00 0% 0 0 0%
RECPDCL 12.51 0.00 0% 12.58 8.49 68%
Total 26.57 0.00 0% 12.58 8.49 68%
Grand Total 294.94 271.57 92% 276.24 262.60 95%
Return
Comparison of state share release(2/2)
As can be seen from above table of Fund Status for the Month of Dec-21 and September-22
a. State-share released amount for PGCIL has gone up from Rs. 13.05 cr (34%) in Dec-21 to Rs. 29.54 cr (77%) in
July 2022. However, there is no change in the month of September 2022.
b. State-share released amount for RECPDCL has gone up from Rs. 0 cr (0%) in Dec-21 to Rs. 8.49 (68%) in July 22
for PMDP (New Technology). However, there is no change in the month of September 2022.
Return
PIA Charges
Work Package Area PIA
PIA Charges
Sanctioned
PIA Charges
Eligible
PIA charges
Released
Ongoing Rural PGCIL 16.38 13.34 9.92
Urban RECPDCL 37.64 37.64 27.74
New Technology PGCIL 8.29 0.00 0.00
RECPDCL 7.43 7.42 0.00
Ongoing Total 69.74 58.40 37.66
Additional Rural PGCIL 12.07 10.35 0.00
Urban RECPDCL 17.11 12.27 0.00
Additional Total 29.17 22.62 0.00
Re-appropriation-
PMDP (R) AND
PMDP(U) New Technology RECPDCL
7.22+3.62 0+3.62 0.00
Grand Total 109.75 84.64 37.66
Note: (a) PIA charges includes for Ongoing and Additional Works as Additional Fund.
(b) In addition to PIA charges payable to POWERGRID by MOP for ongoing PMDP, State PIA charges of Rs 2.6 Cr (J&K UT- 2.24 Cr &
Ladakh UT- 0.36 Cr) is also pending from DISCOMs.
(c) For Additional PMDP Works, advance payment of PIA charges of Rs 1.95 Cr (J&K UT- 1.62 Cr & Ladakh UT- Rs 0.33 Cr) is also
pending from DISCOMs to PGCIL
Return
Work Package Area PIA PMA
PMA Charges
Sanctioned
PMA Charges
Eligible
PMA charges
Released
Ongoing
Rural
JPDCL RECPDCL 2.02 1.88 1.25
KPDCL RECPDCL 1.69 1.65 0.58
LPDD RECPDCL 0.05 0.05 0.00
PGCIL RECPDCL 1.39 1.13 0.86
Rural Total 5.15 4.71 2.69
Urban
JPDCL RECPDCL 0.86 0.85 0.06
JPDCL/KPDCL* 0.19 0.08 0.00
KPDCL RECPDCL 1.14 1.12 0.16
LPDD $ Wapcos 0.01 0.00 0.00
RECPDCL Voyant solution 3.19 3.19 0.00
Urban Total 5.39 5.24 0.22
New
Technology
PGCIL $ 0.70 0.00 0.00
RECPDCL JPDCL & KPDCL 0.63 0.63 0.00
New Technology Total 1.33 0.63 0.00
Ongoing Total 11.83 10.58 2.90
PMA Charges-1/2
Return
Work Package Area PIA PMA
PMA Charges
Sanctioned
PMA Charges
Eligible
PMA charges
Released
Additional
Rural
JPDCL RECPDCL 0.94 0.67 0.00
KPDCL RECPDCL 0.68 0.41 0.00
PGCIL RECPDCL 1.02 0.88 0.00
Rural Total 2.64 1.96 0.00
Urban
JPDCL RECPDCL 0.43 0.35 0.00
KPDCL RECPDCL 0.26 0.16 0.00
RECPDCL Voyant solution 1.45 1.04 0.00
Urban Total 2.13 1.56 0.00
Additional Total 4.77 3.51 0.00
Re-appropriation-
PMDP(R+U)
New
Technology
RECPDCL* 0.90 0.90 0.00
Grand Total 17.50 14.99 2.90
PMA Charges-2/2
a. $ Corresponds to Smart Grid Project worth Rs 140.5 Crore which has been dropped.
b. $$ Corresponds to Meter Test Lab worth Rs 2.43 Crore which has been surrendered.
Return
Region PIA
66/11,33/11KV Sub-Stations 66KV & 33KV Lines
Sanctio
ned
Nos
Awarde
d Nos
Surve
yed
Approv
ed
Equipment
ordered, Nos
Status of
Land
Acquisition
Sanctione
d Scope
(CKm)
awarded
,Ckm
Survey
ed
Approv
ed
Conductor
and Poles
ordered
ROW
issues if
any
Jammu
JPDCL 4 4 4 4
PowerCables,PT
R-3
Acquired -4 91 91 93 93 200 nos. Nil
RECPDCL 5 5 2 2
PTR, 33kV VCBs,
11kV VCB
panels, C&R
Panels,
Capacitor banks
and associated
equipments.
Acquired - 2,
Identified -3
169.68 169.68 103.35 103.35
71.5
Ckms/850
nos.
Nil
Kashmir
KPDCL 2 2 2 2 Acquired-2 30.5 30.5 9 9
30
ckms/310
nos.
Nil
RECPDCL 7 7 7 7
PTR-3
Acquired-6,
Under Court
stay-1
24 18 24.4 24.4 5 kms Nil
Ladakh RECPDCL 0 0 0 0 0 0 0 0 0 0 Nil
Additional Projects status Urban(Sub-stations and HT LT lines) 1/4
Return
Sub-station Land acquisition status in Urban area:
Out of 18 awarded substations , Land Acquired for 14 SS, Land for 01 SS are under court stay and land for 03 nos SS has been identified.
Region PIA
DTs installation, Nos 11KV Feeders,CKm
Sanctioned
(DTs)
awarded Surveyed Approved
DTs
ordered
Nos
Sanctioned
11 KV line
awarded Surveyed Approved
Conductor and
Poles ordered,
kms/Nos
ROW
issues if
any
Jammu
JPDCL 383 383 354 354 303 147 147 99 99
400.5 kms / 959
nos.
Nil
RECPDCL 1258 1258 435 435 361 120 120 77.3 77.3 30 Ckms/518 nos. Nil
Kashmir
KPDCL 202 202 201 201 0 86.5 86.5 45.31 45.31 61 ckms/426 nos. Nil
RECPDCL 4825 2482 685 685 308 228.5 166.5 109.4 109.4 30 Ckms Nil
Ladakh RECPDCL 231 102 50 50 50 123 123 35.61 35.61 73 ms/540 nos. Nil
Additional Projects status Urban(DTs, HT/LT Feeders) 2/4
Return
Region PIA
LT Feeders, CKM
Sanctioned
(LT line )
awarded Surveyed Approved
Conductor and Poles ordered,
kms/Nos
ROW issues if any
Jammu
JPDCL 221 221 171 171 52.5 kms / 1413 nos. Nil
RECPDCL 44.7 44.7 44.7 44.7 27 kms/412 Nos. Nil
Kashmir
KPDCL 315.88 316.13 260.24 225 133 kms/1600 nos. Nil
RECPDCL 219 219 219 219 68 kms Nil
Ladakh RECPDCL 108 40 106 106 5 kms/650 nos. Nil
Regio
n
PIA
66/11,33/11KV Sub-Stations 66KV & 33KV Lines
Sanctio
ned
Nos
Awarde
d Nos
Surveyed Approved
Equipment
ordered, Nos
Status of
Land
Acquisition
Sanctione
d Scope
(CKm)
awarded,
Ckm
Surveye
d
Approved
Conductor
and Poles
ordered
ROW
issues if
any
Jammu
JPDCL 25 25 24 24
Materials in
pipeline
Acquired-24 78 78 43 43 226 nos. Nil
PGCIL 9 6 6
6
(restricted within
sanctioned fund)
Engineering.
Completed & Eqp
ordered.
Acquired-6 42 42 22
22
(restricted within
sanctioned fund)
All ordered Nil
Kashmi
r
KPDCL 1 1 1 1 Acquired-1 141.76 137.6 140.5 140.5
54 kms/384
nos.
Nil
PGCIL 19 19 19
16
(restricted within
sanctioned fund)
Engineering.
Completed & Eqp
ordered.
Acquired-16 98 48 18.1
18.1
(restricted within
sanctioned fund)
All ordered Nil
Ladakh PGCIL 3 3 3 3
Engineering.
Completed & Eqp
ordered.
Acquired-3 111 111 109
109
(restricted within
sanctioned fund)
All ordered Nil
Additional Projects status Rural (Sub-stations and HT LT lines) 3/4
Return
Sub-station Land acquisition status in Rural
Out of 53 awarded substations , Land Acquired for all 53 SS
Region PIA
DTs installation, Nos 11KV Feeders,CKm
Sanction
ed (DTs)
awarded
Surveye
d
Approved
DTs
ordered,
Nos
Sanction
ed (11 KV
line
awarde
d
Survey
ed
Approved
Conductor
and Poles
ordered,
kms/Nos
ROW
issues if
any
Jammu
JPDCL 460 460 292 292 147 424.21 424.21 293.4 293.4
38 kms/2500
nos
Nil
PGCIL 183 147 139 139 (restricted within
sanctioned fund)
139 198.88 179.9 177.9 177.9 (restricted within
sanctioned fund)
All ordered Nil
Kashmir
KPDCL 422 422 321 321 216 500.4 469.1 418 418
248 kms/2115
nos.
Nil
PGCIL 388 265 214 214 (restricted within
sanctioned fund)
214 102.51 74.6 62.5 62.5(restricted within
sanctioned fund)
All ordered Nil
Ladakh PGCIL 3 3 3 3 3 42.81 42.81 20.81 20.81(restricted within
sanctioned fund)
All ordered Nil
Additional Projects status Rural (DTs, HT/LT Feeders) 4/4
Return
Region PIA
LT Feeders, CKM
Sanctioned (LT
line )
awarded Surveyed Approved
Conductor and Poles
ordered, kms/Nos
ROW issues if
any
Jammu
JPDCL 618.4 618.4 470.8 470.8 140 kms/2380 nos Nil
PGCIL 302.65 227.2 364.17 364.17(due to site requirement) All ordered. Nil
Kashmir
KPDCL 659.6 602.2 641.9 641.9 441.9 kms/6288 nos. Nil
PGCIL 386.95 233.5 188.3 188.3(restricted within sanctioned fund) All ordered Nil
Ladakh PGCIL 4 4 0.5 0.5(restricted within sanctioned fund) All ordered Nil

Weitere ähnliche Inhalte

Ähnlich wie PMDP Presentation Sep-22_Final dt 27.10.2022.pptx

Power transmission sector
Power transmission sectorPower transmission sector
Power transmission sector
Rahul Gupta
 
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxFinal Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
IESGATEWiz
 
PPT_for_states_reforms scheme which is very important aspect.pdf
PPT_for_states_reforms scheme which is very important aspect.pdfPPT_for_states_reforms scheme which is very important aspect.pdf
PPT_for_states_reforms scheme which is very important aspect.pdf
Rajneesh40
 
Telecom MIS Dec-Jan 2022 Final.pptx
Telecom MIS Dec-Jan 2022 Final.pptxTelecom MIS Dec-Jan 2022 Final.pptx
Telecom MIS Dec-Jan 2022 Final.pptx
aman477909
 
RAPDRP-Karnataka
RAPDRP-KarnatakaRAPDRP-Karnataka
RAPDRP-Karnataka
Aman Bharti
 

Ähnlich wie PMDP Presentation Sep-22_Final dt 27.10.2022.pptx (20)

Review of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptxReview of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptx
 
Power transmission sector
Power transmission sectorPower transmission sector
Power transmission sector
 
Departmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptxDepartmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptx
 
MNRE_Conclave-CP-ppt-Final.pptx
MNRE_Conclave-CP-ppt-Final.pptxMNRE_Conclave-CP-ppt-Final.pptx
MNRE_Conclave-CP-ppt-Final.pptx
 
MNRE_Conclave-CP-presentation-solar.pptx
MNRE_Conclave-CP-presentation-solar.pptxMNRE_Conclave-CP-presentation-solar.pptx
MNRE_Conclave-CP-presentation-solar.pptx
 
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptxFinal Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
 
Overview of solar power generation in india
Overview of solar power generation in indiaOverview of solar power generation in india
Overview of solar power generation in india
 
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxFinal Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
 
updated Presentation for NCC-FFP Meeting -Keyal HPP.pptx
updated Presentation  for NCC-FFP Meeting -Keyal HPP.pptxupdated Presentation  for NCC-FFP Meeting -Keyal HPP.pptx
updated Presentation for NCC-FFP Meeting -Keyal HPP.pptx
 
PPT_for_states_reforms scheme which is very important aspect.pdf
PPT_for_states_reforms scheme which is very important aspect.pdfPPT_for_states_reforms scheme which is very important aspect.pdf
PPT_for_states_reforms scheme which is very important aspect.pdf
 
New normal and beyond –RVNL Perspective dt 27.10.21
New normal and beyond –RVNL Perspective dt 27.10.21New normal and beyond –RVNL Perspective dt 27.10.21
New normal and beyond –RVNL Perspective dt 27.10.21
 
Performance Audit of GBPWD.pptx
Performance Audit of GBPWD.pptxPerformance Audit of GBPWD.pptx
Performance Audit of GBPWD.pptx
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
 
Power industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistanPower industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistan
 
Telecom MIS Dec-Jan 2022 Final.pptx
Telecom MIS Dec-Jan 2022 Final.pptxTelecom MIS Dec-Jan 2022 Final.pptx
Telecom MIS Dec-Jan 2022 Final.pptx
 
Design Status.pptx
Design Status.pptxDesign Status.pptx
Design Status.pptx
 
Rice husk based cogeneration power plant for finance, subsidy & project rel...
Rice husk based cogeneration power plant   for finance, subsidy & project rel...Rice husk based cogeneration power plant   for finance, subsidy & project rel...
Rice husk based cogeneration power plant for finance, subsidy & project rel...
 
Rice husk power plant information for finance, subsidy & project related su...
Rice husk power plant information   for finance, subsidy & project related su...Rice husk power plant information   for finance, subsidy & project related su...
Rice husk power plant information for finance, subsidy & project related su...
 
MAR,23.pptx
MAR,23.pptxMAR,23.pptx
MAR,23.pptx
 
RAPDRP-Karnataka
RAPDRP-KarnatakaRAPDRP-Karnataka
RAPDRP-Karnataka
 

Kürzlich hochgeladen

VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
dharasingh5698
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 

Kürzlich hochgeladen (20)

Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdf
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 

PMDP Presentation Sep-22_Final dt 27.10.2022.pptx

  • 1. Progress of Distribution Projects under PMDP (J&K and Ladakh) 10.10.2022
  • 2. • Ministry of Power sanctioned following PMDP distribution projects in Nov 2016: • Subsequently, additional funds were sanctioned in Jun 21/ Aug 21 for completion of balance sanctioned work: PMDP-2015- Introduction Project Initial Sanction amount ( Rs in Cr) Urban Distribution Strengthening Projects Rs.1144.59 Crore Rural Distribution Strengthening Projects Rs.1157.75 Crore New Technology Projects Rs. 267.80 Crores Total Cost Rs 2570.14 Crores Project Additional Sanction amount Urban Distribution Strengthening Projects Rs.486.81 Crore Rural Distribution Strengthening Projects Rs.565.87 Crore New Technology works PIA charges Rs. 15.72 Crore Total Cost of Additional works Rs 1068.40 Crores
  • 3. S N Action Point Responsibility Action Taken 1 PIAs to expedite the works for additionally sanctioned projects and advised that the material for the projects may be mobilized by PIAs on the identified land for which the land allotment has not been done formally by the UT of J&K. All PIAs KPDCL: • Major material like poles conductor, cable DTs are available and erection works are going on. At present, KPDCL has achieved progress of around 6 % and It is expected that substantial progress shall be achieved in October and November 2022. 90% Pole errection has been completed • Further Civil works are in full swing at 3 Nos 33/11kV Receiving Stations being constructed by KPDCL. Expected completion by Dec-22 RECPDCL: • 30-40% of the material has been mobilized for PMDP(U) – Addl. Scheme including Power Transformers for the allotted lands. • 2 Nos. of lands out of 5 Nos. of lands for construction of New 33/11 KV S/s has been handed over in Jammu circle. Further, JPDCL has instructed to augment the capacity of Ex. 33/11 kV S/s instead of construction of the balance 3 Nos. of New 33/11 kV S/s. • 3 Nos. lands out of 4 Nos. lands for construction of New 33/11 kV S/s is allotted in Srinagar circle. 1 No. Land is under Court stay. POWERGRID: • Work under progress at all 9 new substations & 12/16 Augmentation substations. 8335 poles have been erected and 36kM stringing done in 185 villages. DT installation and LT/HT stringing under progress in villages. Materials being delivered and erected. • Issue raised by PGCIL : JPDCL has informed that it will not bear the state share of 3.5% PIA charges. No PIA charges has been received for Addl PMDP works till date. CEA has already sent letter dated 28.07.2022 to J&K and Ladakh for the release of PIA state share charges JPDCL response is still awaited. 2 PS (Energy, J&K) to expedite the pending land allotment of 5 substations to PIAs including the sub-station of Roopnagar in Jammu region. J&K J&K to respond Action taken from Last meeting- 18.08.2022
  • 4. S N Action Point Responsibility Action Taken 3 PS (energy), J&K to expedite the release of state share of around Rs.4 Cr pending against ongoing New Technology (smart metering) projects to RECPDCL so that the matching central share can be released by MoP. J&K The State Share of Rs. 3.25 Cr. is approved by UT of J&K and is under remittance against the ongoing New Technology (Smart Metering) projects to RECPDCL. 4 CEO (RECPDCL) to provide the data regarding details of billing and collection efficiency of installed meters in J&K to MoP RECPDCL Billing & collection efficiency increased to ~31% (Jammu) and ~13% (Kashmir) for billing months of July-2022 vs. July-2021 for No. of consumers 18,302 (Jammu) & 11,828 (Srinagar) 5 CEO (RECPDCL) to prioritize the smart meter installation of Lot A meters (3 lakh) in Kashmir region before November 2022, owing to the upcoming winter season. RECPDCL Smart Meters supply will be increased from Sept-22 in Kashmir region as compared to Jammu region to expedite installation of Smart Meters in Kashmir. 6 Development of prepaid functionality for the installed meters and integration with the new MDM system and necessary testing to be completed by 30th of Aug-22. RECPDCL 1) System Integration Testing (SIT) between CCB & MDM systems is in progress and expected to be completed by 30.09.2022. 2) After successful completion of SIT, the deployment and integrations will be shifted to UAT. Further, UAT will be conducted between 01.10.2022 to 07.10.2022. 7 LPDD and RECPDCL to expedite wildlife board clearance for construction of 220kV Nubra and Zanskar transmission line in Ladakh LPDD and RECPDCL LPDD and RECPDCL to respond Action taken from Last meeting- 18.08.2022
  • 5. PMDP projects Summary- ongoing projects Projects UT No of sub- projects sanctioned No of sub- projects awarded No of sub- projects completed Status of balance works Timelines Distribution strengthening J&K 158 158 133 Balance 25 sub-projects in progress. All projects awarded from Feb18 to Nov 18. On the basis of extension requests from PIAs, the date of completion is between Sept 22 to Dec 22 Ladakh 36 34 32 2 sub-projects (meter testing lab) dropped. 2 sub-projects in progress. New Technology J&K 3 2 - 2 sub-projects are in progress and 1 project (smart grid project) is dropped Ladakh 2 0 - 2 Smart grid projects dropped Ongoing Total 199 194 165 5 Sub projects dropped Detailed progress On-going projects issues
  • 6. Additional sanctioned projects summary Additional projects progress Projects UT No of sub- projects sanctioned No of sub- projects awarded No of sub- projects completed Status of balance works Timelines Additional projects J&K 37 37 - All the additional sub-projects are under progress. All the additional sub- projects have been awarded during Nov- Dec 2021 and scheduled to be completed by Dec 22 Ladakh 3 3 - Additional Total 40 40 - Grand Total (Ongoing + additional) 239 234 165 5 no of Ongoing Sub Projects have been dropped Sub projects – to be completed Ongoing – 29 Additional -40 Additional projects issues Detailed progress
  • 7. Ongoing projects- Financial Progress-1/2 As on 30th September 2022 Work Package Area PIA Eligible Cost*** Eligible Central Share Central share received by PIAs* State Share State released % Central Share Released % State Share Released Ongoing Rural JPDCL 376.85 313.30 256.8 63.55 54.71 82% 86% KPDCL 329.20 273.68 181.67 55.52 65.83 66% 119% LPDD 9.58 7.97 6.19 1.62 1.43 78% 88% PGCIL 226.14 188.00 156.94 38.14 29.54 83% 77% Rural Total 941.78 782.96 601.6 158.83 151.50 77% 95% Urban JPDCL 169.81 152.83 126.57 16.98 15.15 83% 89% JPDCL/KPDCL** 16.8 15.12 0.00 1.68 0.00 0% 0% KPDCL 223.74 201.36 183.52 22.37 30.30 91% 135% LPDD$$ 0.00 0.00 0.00 0.00 0 0% 0% RECPDCL 637.98 574.18 436.68 63.80 57.16 76% 90% Urban Total 1048.33 943.50 746.77 104.83 102.61 79% 98% New Technology PGCIL$ 0.00 0.00 0 0.00 0.00 0% 0% RECPDCL 125.77 113.19 64.03 12.58 8.49 57% 68% New Technology Total 125.77 113.19 64.03 12.58 8.49 57% 68% Ongoing Total 2115.88 1839.65 1412.40 276.24 262.60 77% 95% a. *Adjustment of state share on receipt of Central Share of Rs 122.07crore & Rs. 80.07 crore(already processed by MoP in Dec21) – KPDCL already released 100% share, proposed to adjust the balance share in Additional works.. b. RECPDCL has reported reduction of state share from 12.58 crore to 8.49 crore for new technology project as balance share of 4.08 crore & Rs. 6.55 Cr. under Ongoing Infra projects yet to be released by JPDCL c. **Meter Testing Lab d. *** eligible cost (Minimum of Sanctioned and Surveyed & Approved Cost) e. $ Corresponds to Smart Grid Project worth Rs 140.5 Crore which has been dropped f. $$ Corresponds to Meter Test Lab worth Rs 2.43 Crore which has been surrendered.
  • 8. Additional projects -Financial Progress-2/2 As on 30th September 2022 Work Package Area PIA Eligible Cost Eligible Central Share Central share received by PIAs State Share State released % Central Share Released % State Share Released Additional Rural JPDCL 133.45 110.95 33.29 22.51 0.00 30% 0% KPDCL 82.49 68.58 30.57 13.91 0.00 44.57% 0% PGCIL 175.46 145.87 37.18 29.59 0.00 25.48% 0% Rural Total 391.41 325.40 101.04 66.01 0.00 31.05% 0% Urban JPDCL 70.63 63.57 0 7.06 0.00 0% 0% KPDCL 33.50 30.15 0 3.35 0.00 0% 0% RECPDCL 207.99 187.19 72.32 20.80 0.00 38.63% 0% Urban Total 312.12 280.91 72.32 31.21 0.00 25.74% 0% Additional Total 703.53 606.31 173.36 97.22 0.00 28.59% 0% Re-appropriation- PMDP(R+U) New Technology RECPDCL 180 162 0 18 0.00 0% 0% Grand Total 2999.41 2607.96 1585.76 391.46 262.60 Note: Recently, Rs. 125.18 cr was released by MoP on 28.07.2022 as 1st and 2nd tranche to JPDCL, KPDCL and RECPDCL towards additional distribution projects.
  • 9. Town Name Nos. of meters sanctioned/ Awarded Nos. of meters installed Nos. of meter charged Nos. of meters communicating a b c d e (w.r.t. 'd') Jammu 57,750 57,750 56,563 53,654 Srinagar 57,750 57,750 51,224 43,395 Total 1,15,500 1,15,500 1,07,787 97,049 Overall % of works 100% 93% 84% Status of 1.15 Lakh Smart Meters in UT of J&K as on 29.09.2022 Note- Till Aug-2022, billing done for 88,336 no. of smart meters in J&K (47,015 nos. in Jammu and 41,321 nos. in Srinagar)
  • 10. Status of 6 Lakh Smart Meters in UT of J&K as on 29.09.2022 Lot A (3 lakh) Lot B (3 lakh) a. Technical Bid(s) submitted by Various PEA(s) has been opened on 20.09.2022. b. PoC demonstration has been completed on 28.09.2022 & 29.09.2022. c. Financial Bid(s) are expected to be opened on 07.10.2022. Town(s)/ Discom(s) Scope Meters Delivered Meters under PDI/Transit Meters Installed Meters Charged 1 2 3 4 5 (w.r.t. 3) 6(w.r.t. 5) Jammu/ JPDCL 1,43,813 2,500 2,500 536 483 Srinagar/ KPDCL 1,43,813 2,200 2,800 542 542 Total 2,87,626 4,700 5,300 1,078 1,025 10,000
  • 11. Ongoing Physical Progress- 1/4 As on 30th September 2022 Project Description Area Region PIA Sub-Projects Sanctioned Sub-Projects Awarded Sub- Projects Yet to be awarded Sub- Projects Completed % Physical Progress DoC (Schedule/L ikely) Distribution Strengthening Rural JAMMU JPDCL 7 7 0 1 88% Mar’22/ Sept’22 PGCIL 3 3 0 3 100% Apr’22- Comp All Works completed. KASHMIR KPDCL 6 6 0 0 69% Oct-22/ Nov-’22 • Poor progress of work by M/s Shalaka Infra. PGCIL 3 3 0 3 100% Mar’22- Comp All works completed. LADAKH PGCIL 2 2 0 1 85% Nov-21/ Nov’22 • Balance: 5 nos villages (4 nos under Wild life) and 1 no 33/11 kV Pinchmik Substation. Work under progress in all balance 5 nos villages and 1 nos substation. Target- Nov’22 • Reason of Delay: LPDD gave clearance for resumption of overhead work only on 18th July'22. Return
  • 12. Ongoing Physical Progress- 2/4 Project Description Area Region PIA Sub- Projects Sanctioned Sub-Projects Awarded Sub- Projects Yet to be awarded Sub- Projects Completed % Physical Progress DoC (Schedul e/Likely) Distribution Strengthening Urban JAMMU JPDCL 4 4 0 0 89% Dec’21/ Sept’22 RECPDCL 1 1 0 0 91% Dec’21/ Sept’22 KASHMIR KPDCL 3 3 0 2 99% Dec’21/ Oct’22 RECPDCL 3 3 0 2 87% Dec’21/ Dec’22 LADAKH RECPDCL 1 1 0 0 94% Dec’21/ Sep’22 Meter Test Lab Urban J&K J/KPDCL 1 1 0 0 8% Awarded LADAKH LPDD 2 0 2 0 0% Dropped
  • 13. Ongoing Physical Progress- 3/4 Project Description Area Region PIA Sub-Projects Sactioned Sub- Projects Awarded Sub-Projects Yet to be awarded Sub- Projects Completed % Physical Progress Date of Completio n RoBW Rural Part B JAMMU JPDCL 37 37 0 37 100% Completed KASHMIR KPDCL 46 46 0 46 100% Completed LADAKH LPDD 4 4 0 4 100% Completed UGC Rural Part B JAMMU JPDCL 1 1 0 1 100% Completed KASHMIR KPDCL 1 1 0 1 100% Completed SS @ IA Rural Part B JAMMU JPDCL 16 16 0 16 100% Completed KASHMIR KPDCL 4 4 0 1 92% Oct- 22/Nov-22 Shrine Works Rural Part B JAMMU JPDCL 12 12 0 10 91% Sep-22 KASHMIR KPDCL 10 10 0 8 99% Sept-22 LADAKH LPDD 27 27 0 27 100% Completed Return
  • 14. Ongoing Physical Progress- 4/4 Project Description Area Region PIA Sub-Projects Sactioned Sub- Projects Awarded Sub-Projects Yet to be awarded Sub- Projects Completed % Physical Progress Date of Completio n Smart Metering (1.15 Lakh) New Technology JAMMU RECPDCL 1 1 0 1 100% Completed KASHMIR RECPDCL 1 1 0 1 100% Completed Smart Grid New Technology J&K PGCIL 1 0 1 0 Dropped LADAKH PGCIL 2 0 2 0 Grand Total 199 194 5* 165 * 05 sub projects (yet to be awarded)have been dropped, reducing the Total sub projects to 194.
  • 15. Additional Physical Progress (1/3) As on 30th September 2022 Project Des. Area Region PIA Sub- Projects Sanctioned Sub-Projects Awarded Sub- Projects Yet to be awarded Sub- Projects Completed % Physical Progress Date of Completi on Equipment ordered Distributi on Strength ening Rural JAMMU JPDCL 7 7 0 0 3% Dec-22 DTs-147 , Conductors- 38 kms,Poles- 2726 PGCIL 3 3 0 0 3% Dec-22 All equipment ordered KASHMIR KPDCL 6 6 0 0 6% Dec-22 DTs-216, Poles- 2500, Conductors- 302 kms PGCIL 3 3 0 0 8% Dec-22 All equipment ordered LADAKH PGCIL 2 2 0 0 2% Dec-22 All equipment ordered
  • 16. Additional Physical Progress (2/3) As on 30th September 2022 Distribution Strengthenin g Urban JAMMU JPDCL 4 4 0 0 3% Dec-22 PTR-3,Power cables,Poles- 1159, DTs-303,Conductors- 400 kms RECPDCL 1 1 0 0 15% Dec-22 PTR, VCBs,C&R Panels,Poles-1368,DTs- 361,Conductors-102 kms KASHMIR KPDCL 3 3 0 0 6% Dec-22 Poles-740,Conductors-92 kms RECPDCL 3 3 0 0 1% Dec-22 PTR-3,DTs-308,Conductors- 35 kms LADAKH RECPDCL 1 1 0 0 0% Dec-22 DTs-50,Poles- 540,Conductors-73 kms Project Des. Area Region PIA Sub- Projects Sanctio ned Sub- Projects Awarde d Sub- Projects Yet to be awarded Sub- Projects Complete d % Physical Progress Date of Completi on Equipment ordered
  • 17. UGC Rural Part B JAMMU JPDCL 3 3 0 0 0 Dec-22 KASHMIR KPDCL 2 2 0 0 0 Dec-22 SS @ IA JAMMU JPDCL 1 1 0 0 0 Dec-22 KASHMIR KPDCL 1 1 0 0 0 Dec-22 Additional Total 40 40 0 0 Project Des. Area Region PIA Sub- Projects Sanctio ned Sub- Projects Awarde d Sub- Projects Yet to be awarded Sub- Projects Complete d % Physical Progress Date of Completi on Equipment ordered Additional Physical Progress (2/3) As on 30th September 2022
  • 18. Project Description Area Region PIA Issues/ Reasons for delay Distribution Strengthening Rural JAMMU JPDCL  DTs, 11 kV & LT Lines: Slow pace of work of execution by M/s Shalakha Infratech Pvt.Ltd in Doda & Kishtwar districts. (same shall be completed by Sept'22) PGCIL  All works completed. KASHMIR KPDCL • Poor progress of work by M/s Shalaka Infra. PGCIL • All works completed. LADAKH PGCIL • Balance: 5 nos villages (4 nos under Wild life) & 1no 33kV Pinchmik S/s • Work under progress in all balance 5 nos villages and 1 no Pinchmik S/s • Reason of Delay: LPDD gave clearance for resumption of overhead work only on 18th July'22. Target- Nov'22 Ongoing projects- issues(1/2)
  • 19. Distribution Strengthenin g Urban JAMMU JPDCL  33/11 kV S/s: Delay in land allotment.  33 kV Lines: Due to restricted availability of shutdowns RECPDCL  33 kV Line : Shutdown related issue and RoW issues  11 kV Line: Limited Hours shutdown and RoW issues. KASHMIR KPDCL  Delay in allotment of land at one receiving station in Budgam due to litigation which finally got dismissed in Aug-21 post which work was started. Station Stand Test charged on 2nd October 2022 RECPDCL  33/11 kV S/s: Delay in allotment of Land  33 kV Line Shutdown related issue  HT Line & LT Line: Shutdowns and RoW issues LADAKH RECPDCL  66/11 kV S/s and 66 kV line: limited working season. Ongoing projects issues(2/2) Project Description Area Region PIA Issues/ Reasons for delay SS @ IA Rural Part B KASHMIR KPDCL  Delay due to allotment of land by Industrial department within Industrial estates, Covid Restrictions and lock downs resulting in de- mobilization by contractors. Shrine Works JAMMU JPDCL  Delay on the part of TKC due to some payment issue.
  • 20. Additional Project implementation issues Project Description Area Region PIA Remarks/ Reasons for delay Distribution Strengthening Rural JAMMU PGCIL  Advance @ 30% (Rs 11.32 Cr) not received from REC for central share of Ladakh UT.  Advance @ 30% (Rs 10.12 Cr) for State share not received from J&K UT (7.83 Cr) and Ladakh UT (2.29 Cr). Urban JAMMU RECPDCL  Out of the proposed 5 New substations in Jammu Circle under PMDP(U), where RECPDCL is PIA, all 5 Lands have been identified. Further, out of 5 Nos. identified lands, 02 Nos. Land at Arnia & Talab Tillo are handed over to RECPDCL. Remaining 3 No. Land at RS Pura(Barnota), Roopnagar & Bhatindi(Sunjwan) are yet to be handed over. KASHMIR RECPDCL  Land has been identified for all proposed 4 New substations in Srinagar Circle under PMDP(U) where RECPDCL is PIA. Further, KPDCL has instructed to take up the works at 4 Nos. identified locations for new 33/11 kV S/s. However, 1 land at Tengpora is under Court stay ( District court ). Issued highlighted by PGCIL & RECPDCL in regard to land acquisition for additional projects
  • 23. Comparison table of state share release(1/2) Region PIA December 2021 September 2022 State Share State share released % State Released State Share State share released % State Released Rural JPDCL 65.32 67.21 103% 63.55 54.71 86% KPDCL 56.04 78.82 141% 55.52 65.83 119% LPDD 1.62 1.43 88% 1.62 1.43 88% PGCIL 38.14 13.05 34% 38.14 29.54 77% Total 161.11 160.51 100% 158.83 151.50 95% Urban JPDCL 16.88 25.54 151% 16.98 15.15 89% JPDCL/KPDCL 3.76 0.00 0% 1.68 0.00 0% KPDCL 22.65 58.23 257% 22.37 30.30 135% LPDD 0.24 0.00 0% 0 0 0% RECPDCL 63.72 27.29 43% 63.80 57.16 90% Total 107.26 111.06 104% 104.83 102.61 98% New Tech PGCIL 14.06 0.00 0% 0 0 0% RECPDCL 12.51 0.00 0% 12.58 8.49 68% Total 26.57 0.00 0% 12.58 8.49 68% Grand Total 294.94 271.57 92% 276.24 262.60 95% Return
  • 24. Comparison of state share release(2/2) As can be seen from above table of Fund Status for the Month of Dec-21 and September-22 a. State-share released amount for PGCIL has gone up from Rs. 13.05 cr (34%) in Dec-21 to Rs. 29.54 cr (77%) in July 2022. However, there is no change in the month of September 2022. b. State-share released amount for RECPDCL has gone up from Rs. 0 cr (0%) in Dec-21 to Rs. 8.49 (68%) in July 22 for PMDP (New Technology). However, there is no change in the month of September 2022. Return
  • 25. PIA Charges Work Package Area PIA PIA Charges Sanctioned PIA Charges Eligible PIA charges Released Ongoing Rural PGCIL 16.38 13.34 9.92 Urban RECPDCL 37.64 37.64 27.74 New Technology PGCIL 8.29 0.00 0.00 RECPDCL 7.43 7.42 0.00 Ongoing Total 69.74 58.40 37.66 Additional Rural PGCIL 12.07 10.35 0.00 Urban RECPDCL 17.11 12.27 0.00 Additional Total 29.17 22.62 0.00 Re-appropriation- PMDP (R) AND PMDP(U) New Technology RECPDCL 7.22+3.62 0+3.62 0.00 Grand Total 109.75 84.64 37.66 Note: (a) PIA charges includes for Ongoing and Additional Works as Additional Fund. (b) In addition to PIA charges payable to POWERGRID by MOP for ongoing PMDP, State PIA charges of Rs 2.6 Cr (J&K UT- 2.24 Cr & Ladakh UT- 0.36 Cr) is also pending from DISCOMs. (c) For Additional PMDP Works, advance payment of PIA charges of Rs 1.95 Cr (J&K UT- 1.62 Cr & Ladakh UT- Rs 0.33 Cr) is also pending from DISCOMs to PGCIL Return
  • 26. Work Package Area PIA PMA PMA Charges Sanctioned PMA Charges Eligible PMA charges Released Ongoing Rural JPDCL RECPDCL 2.02 1.88 1.25 KPDCL RECPDCL 1.69 1.65 0.58 LPDD RECPDCL 0.05 0.05 0.00 PGCIL RECPDCL 1.39 1.13 0.86 Rural Total 5.15 4.71 2.69 Urban JPDCL RECPDCL 0.86 0.85 0.06 JPDCL/KPDCL* 0.19 0.08 0.00 KPDCL RECPDCL 1.14 1.12 0.16 LPDD $ Wapcos 0.01 0.00 0.00 RECPDCL Voyant solution 3.19 3.19 0.00 Urban Total 5.39 5.24 0.22 New Technology PGCIL $ 0.70 0.00 0.00 RECPDCL JPDCL & KPDCL 0.63 0.63 0.00 New Technology Total 1.33 0.63 0.00 Ongoing Total 11.83 10.58 2.90 PMA Charges-1/2 Return
  • 27. Work Package Area PIA PMA PMA Charges Sanctioned PMA Charges Eligible PMA charges Released Additional Rural JPDCL RECPDCL 0.94 0.67 0.00 KPDCL RECPDCL 0.68 0.41 0.00 PGCIL RECPDCL 1.02 0.88 0.00 Rural Total 2.64 1.96 0.00 Urban JPDCL RECPDCL 0.43 0.35 0.00 KPDCL RECPDCL 0.26 0.16 0.00 RECPDCL Voyant solution 1.45 1.04 0.00 Urban Total 2.13 1.56 0.00 Additional Total 4.77 3.51 0.00 Re-appropriation- PMDP(R+U) New Technology RECPDCL* 0.90 0.90 0.00 Grand Total 17.50 14.99 2.90 PMA Charges-2/2 a. $ Corresponds to Smart Grid Project worth Rs 140.5 Crore which has been dropped. b. $$ Corresponds to Meter Test Lab worth Rs 2.43 Crore which has been surrendered. Return
  • 28. Region PIA 66/11,33/11KV Sub-Stations 66KV & 33KV Lines Sanctio ned Nos Awarde d Nos Surve yed Approv ed Equipment ordered, Nos Status of Land Acquisition Sanctione d Scope (CKm) awarded ,Ckm Survey ed Approv ed Conductor and Poles ordered ROW issues if any Jammu JPDCL 4 4 4 4 PowerCables,PT R-3 Acquired -4 91 91 93 93 200 nos. Nil RECPDCL 5 5 2 2 PTR, 33kV VCBs, 11kV VCB panels, C&R Panels, Capacitor banks and associated equipments. Acquired - 2, Identified -3 169.68 169.68 103.35 103.35 71.5 Ckms/850 nos. Nil Kashmir KPDCL 2 2 2 2 Acquired-2 30.5 30.5 9 9 30 ckms/310 nos. Nil RECPDCL 7 7 7 7 PTR-3 Acquired-6, Under Court stay-1 24 18 24.4 24.4 5 kms Nil Ladakh RECPDCL 0 0 0 0 0 0 0 0 0 0 Nil Additional Projects status Urban(Sub-stations and HT LT lines) 1/4 Return Sub-station Land acquisition status in Urban area: Out of 18 awarded substations , Land Acquired for 14 SS, Land for 01 SS are under court stay and land for 03 nos SS has been identified.
  • 29. Region PIA DTs installation, Nos 11KV Feeders,CKm Sanctioned (DTs) awarded Surveyed Approved DTs ordered Nos Sanctioned 11 KV line awarded Surveyed Approved Conductor and Poles ordered, kms/Nos ROW issues if any Jammu JPDCL 383 383 354 354 303 147 147 99 99 400.5 kms / 959 nos. Nil RECPDCL 1258 1258 435 435 361 120 120 77.3 77.3 30 Ckms/518 nos. Nil Kashmir KPDCL 202 202 201 201 0 86.5 86.5 45.31 45.31 61 ckms/426 nos. Nil RECPDCL 4825 2482 685 685 308 228.5 166.5 109.4 109.4 30 Ckms Nil Ladakh RECPDCL 231 102 50 50 50 123 123 35.61 35.61 73 ms/540 nos. Nil Additional Projects status Urban(DTs, HT/LT Feeders) 2/4 Return Region PIA LT Feeders, CKM Sanctioned (LT line ) awarded Surveyed Approved Conductor and Poles ordered, kms/Nos ROW issues if any Jammu JPDCL 221 221 171 171 52.5 kms / 1413 nos. Nil RECPDCL 44.7 44.7 44.7 44.7 27 kms/412 Nos. Nil Kashmir KPDCL 315.88 316.13 260.24 225 133 kms/1600 nos. Nil RECPDCL 219 219 219 219 68 kms Nil Ladakh RECPDCL 108 40 106 106 5 kms/650 nos. Nil
  • 30. Regio n PIA 66/11,33/11KV Sub-Stations 66KV & 33KV Lines Sanctio ned Nos Awarde d Nos Surveyed Approved Equipment ordered, Nos Status of Land Acquisition Sanctione d Scope (CKm) awarded, Ckm Surveye d Approved Conductor and Poles ordered ROW issues if any Jammu JPDCL 25 25 24 24 Materials in pipeline Acquired-24 78 78 43 43 226 nos. Nil PGCIL 9 6 6 6 (restricted within sanctioned fund) Engineering. Completed & Eqp ordered. Acquired-6 42 42 22 22 (restricted within sanctioned fund) All ordered Nil Kashmi r KPDCL 1 1 1 1 Acquired-1 141.76 137.6 140.5 140.5 54 kms/384 nos. Nil PGCIL 19 19 19 16 (restricted within sanctioned fund) Engineering. Completed & Eqp ordered. Acquired-16 98 48 18.1 18.1 (restricted within sanctioned fund) All ordered Nil Ladakh PGCIL 3 3 3 3 Engineering. Completed & Eqp ordered. Acquired-3 111 111 109 109 (restricted within sanctioned fund) All ordered Nil Additional Projects status Rural (Sub-stations and HT LT lines) 3/4 Return Sub-station Land acquisition status in Rural Out of 53 awarded substations , Land Acquired for all 53 SS
  • 31. Region PIA DTs installation, Nos 11KV Feeders,CKm Sanction ed (DTs) awarded Surveye d Approved DTs ordered, Nos Sanction ed (11 KV line awarde d Survey ed Approved Conductor and Poles ordered, kms/Nos ROW issues if any Jammu JPDCL 460 460 292 292 147 424.21 424.21 293.4 293.4 38 kms/2500 nos Nil PGCIL 183 147 139 139 (restricted within sanctioned fund) 139 198.88 179.9 177.9 177.9 (restricted within sanctioned fund) All ordered Nil Kashmir KPDCL 422 422 321 321 216 500.4 469.1 418 418 248 kms/2115 nos. Nil PGCIL 388 265 214 214 (restricted within sanctioned fund) 214 102.51 74.6 62.5 62.5(restricted within sanctioned fund) All ordered Nil Ladakh PGCIL 3 3 3 3 3 42.81 42.81 20.81 20.81(restricted within sanctioned fund) All ordered Nil Additional Projects status Rural (DTs, HT/LT Feeders) 4/4 Return Region PIA LT Feeders, CKM Sanctioned (LT line ) awarded Surveyed Approved Conductor and Poles ordered, kms/Nos ROW issues if any Jammu JPDCL 618.4 618.4 470.8 470.8 140 kms/2380 nos Nil PGCIL 302.65 227.2 364.17 364.17(due to site requirement) All ordered. Nil Kashmir KPDCL 659.6 602.2 641.9 641.9 441.9 kms/6288 nos. Nil PGCIL 386.95 233.5 188.3 188.3(restricted within sanctioned fund) All ordered Nil Ladakh PGCIL 4 4 0.5 0.5(restricted within sanctioned fund) All ordered Nil