MEJIA THERMAL POWER STATION
Presentation By:-
Thermal Power Plant Industrial Training
1.Rantu das
2.Saikat bera
3.Sayan saha
4.Somnath Bhattacharyya
5.Soudip mal
6.Sounak ghosh
7.Sourabh Kumar Bhattacharjee
8.Sourav kanrar
9.Sourav Sarkar
10.Shubhadip som
11.Subharup Chakraborty
12.Subrata kr. Paul
13.Sujoy Bhattacharjee
14.Subrata Mahato
Contents
1.Introduction
2.Overview of Mejia Thermal Power
Plant
3.Power plant layout
4.Main and Auxiliary Equipment
5.Stepwise operation
Introduction
A Thermal Power Plant converts the heat energy of coal into
electrical energy. Coal is burnt in a boiler which converts water
into steam. The expansion of steam in turbine produces
mechanical power which drives the alternator coupled to the
turbine.Thermal Power Plants contribute maximum to the
generation of Power for any country . Thermal Power Plants
constitute 75.43% of the total installed captive and non-captive
power generation in India . In thermal generating stations coal,
oil, natural gas etc. are employed as primary sources of energy.
Overview of MTPS
 Damodar Valley Corporation was established on 7th July 1948.
 The MTPS underthe DVC is thesecond largest thermal plant in West Bengal.
 It has thecapacityof 2340 MW with 4 units of 210 MW each, 2 units of 250 MW
each & 2 units of 500 MW each.
 With the introduction of another two units of 500 MW that is in construction itwill be the
largest in WestBengal.
 Mejia Thermal Power Station is located in theoutskirtsof Raniganj in Bankura District.
 The total power plant campus area is
surrounded by boundarywalls and is basically divided into two majorparts, first the Power
Plant area itself and the second is the Colony area for the residence and other facilities for
MTPSs employees.
Diagram of a typical coal-fired thermal power
station
General Layout of Thermal Power Station
General Layout of Thermal Power Station
MAJOR ELECTRICAL COMPONENTS OF
POWER PLANT:
MAIN AND AUXILIARY EQUIPMENTS
1. Coal handling plant
2. Pulverizing plant
3. Draft fans
4. Boiler
5. Ash handling plant
6. Turbine
7. Condenser
8. Cooling towers and ponds
9. Feed water heater
10. Economiser
11. Superheater and Reheater
12. Air preheater
Coal handling plant
•The function of coal handling plant is automatic feeding of coal to the boiler furnace.
• A thermal power plant burns enormous amounts of coal.
•A 200MW plant may require around 2000 tons of coal daily
Pulverising plant
In modern thermal power plant , coal is
pulverised i.e. ground to dust like size and
carried to the furnace in a stream of hotair.
Pulverising is a means of exposing a large
surfacearea to the action of oxygen and
consequently helping combustion.
Pulverising mills are further classifiedas:
1. Contact mill
2. Ball mill
3. Impact mill
ASH HANDLING PLANT
The percentage of ash in coal is 5% in good
quality coal & about 40% in poor quality coal.
Power plants generally use poor quality of
coal , thus amount of ash produced by it is quite
large.
A modern 1000MW plant produces about
4800 tons of ash daily.
The stations use some conveyor
arrangement to carry ash to dump sites.
Boiler
 Boileris an enclosed vessel in which water is
heated and circulated until the water is
turned in tosteamat the required pressure.
 Coal is burned inside the combustion
chamber of boiler. The products of
combustion are nothing butgases. These
gases which are at high temperature
vaporize the water inside the boiler to
steam.
 Boilers are classifiedas:
1. Fire tubeboilers
2. Water tubeboilers
3. Superheater
4. Reheater
BOILER OPERATION
• The steam produced in the boiler goes
to the steam drum and is then piped
through the primary, platen and final
super-heaters where it reaches the outlet
temperature of 560 C and 160 ksc
pressure
• At this point in the process they have
now turned the water into a very
powerful source of energy
• This rotates the turbine to which
generator is on the other end
• From rotating generator electricity is
produced
Reheate
rSome of the heat of superheated
steam is used to rotate the
turbine where it loses some of its
energy. The steam after reheating
is used to rotate the second
steam turbine where the heat is
converted to mechanical energy.
This mechanical energy is used to
run the alternator,
coupled to turbine ,
which is
there by
generating electrical energy.
Condenser
 Steam afterrotating steam turbinecomes tocondenser. Condenser refers
here to the shell and tube heat exchanger (orsurfacecondenser) installed
at the outlet of every steam turbine in Thermal power stations of utility
companies.
 The purpose is to condense the outlet (or exhaust) steam from steam
turbine to obtain maximum efficiency and also to get the condensed
steam in the formof purewater, otherwise known as condensate, back to
steamgeneratoror (boiler) as boiler feed water.
 Condensers are classifiedas:
i)Jetcondensers orcontactcondensers,
ii)Surfacecondensers.
Primary Air Fan
• Air to blow the coal from the mill to the
boiler, called the primary air, is supplied
by a large fan driven by a variable
speed motor
• When mixed with a stream of air the
powdered coal behaves more like a gas
than a solid
• Primary air does two jobs – heating the
coal powder and secondly lifting it into
the furnace through pipelines
Forced Draught (FD) Fan
• Each unit shall have two forced
draught fans
• The fans draw warm air from the top
of the boiler house through large air
heaters becoming the primary and
secondary air used for the boiler
combustion process
• The air heater warms the incoming
air by transferring heat energy from
the outgoing flue gases
Air Pre-Heater
(APH)• The air heaters use the remaining
heat energy in the flue gas to heat up
the combustion air for the boiler
• Efficiency is increased by using this
heat that would otherwise go up the
chimney. The air temperature leaving
the air heaters is at 300 C
• The air heaters use the remaining
heat energy and efficiency is
increased by using this heat that
would otherwise go up the chimney
INDUCED DRAUGHT
(ID) FAN
• Two induced draught fans draw
gases out of the boiler
• The gas has already passed
through the air heaters and
precipitators before it has reached
these fans
• The heat from the flue gases or
smoke is used in the air heaters to
heat up the primary and secondary
air
Chimney
• The chimney is 275 meters' high and
50,000 tonnes of reinforced concrete were
used to make it
• It consists of flues each of which serve
typically two or three boilers (two units)
• Each boiler has 4 passes with 7 fields each
containing high voltage electrodes
• These attract the dust or ash from the flue gases
• At regular intervals the electrodes are rapped with
motor-driven hammers and the PFAfalls into
hoppers below
• In a year 1,000 MW station may generate 1.5
million ton of ash
• This is one of the ways to clean up the flue gases
or smoke sent up the chimney
• Secondly this ash is used by construction industry
for use in building materials (bricks !!, Cement
Fillers)
Electro-Static
Precipitator
Cooling Towers
 The condensate (water) formed inthe
condenser after condensation is
initially at high temperature. This hot
water is passed to coolingtowers.
 It isa tower- or building-like device in
which atmospheric air (the heat
receiver) circulates in direct or
indirect contact with warmer water
(the heat source) and the water is
therebycooled.
 Types Of Cooling Tower-
1. Wet cooling tower
2. Dry cooling tower
Economizer
 Fluegases coming outof the boilercarry
lot of heat. Function of economizer is to
recover some of the heat from the heat
carried away in the flue gases up the
chimney and utilize for heating the feed
water to theboiler.
 It is placed in the passage of flue gases in
between the exit from the boiler and the
entry to thechimney.
 The use of economizer results in saving
in coal consumption, increase in
steaming rate and high boiler efficiency
but needs extra investment andincrease
in maintenance costs and floor area
required for theplant.
Steam Turbine
 A steam turbine is a device that
extracts thermal energy from
pressurized steam and uses it to
do mechanical work on arotating
outputshaft.
 The steam turbine is aform
of heat engine that derives much
of its improvement in
thermodynamic efficiency from
the use of multiple stages in the
expansion of the steam, which
results in a closer approach to the
ideal reversible expansionprocess.
Alternator
 An alternator is an electromechanical device that converts mechanical
energy to alternating current electrical energy. Most alternators use a
rotating magnetic field. Differentgeometries - such as a linearalternator
forusewith sterling engines - arealsooccasionally used. In principle, any
AC generator can be called an alternator, but usually the word refers to
small rotating machines driven by automotive and other internal
combustionengines.
Transformers
 It is adevice that transfers electricenergy
from one alternating-current circuit to
one or more other circuits, either
increasing (stepping up) or reducing
(stepping down) thevoltage.
 Transformers act through
electromagnetic induction; current in
the primary coil induces current in the
secondary coil. The secondary voltageis
calculated by multiplying the primary
voltage by the ratio of the number of
turns in the secondarycoil to that in the
primary.
SWITCH YARD
SWITCH YARD
 Placed where switching operation of power distribution isperformed.
 Air insulated switch yard of 220KV-400KV are used.
Main Components of SwitchYard:






Circuit breaker
Isolator
Lightening arrester
Bus bar
Current Transformer
Potential Transformer
CIRCUIT BREAKER
 These are used for automatic switching during normal or abnormal conditions .
Specification:
Manufacturer ABB Limited
Type of Circuit Breaker SF6
Rated Voltage 245 KV
Rated Current
Under Site Condition of 40 0C
Under Site Condition of 50 0C
4000 A
2000 A
Rated Frequency 50 Hz
ISOLATOR
 These are used to disconnect transmission line under no-load condition for safety,
isolation and maintenance.
Specification:
Rated current for site conditions 2000A
Rated Voltage 245 KV
Rated Frequency 50 Hz
Operating time of Isolator Less than 12 sec.
LIGHTENINGARRESTOR
 These are used to discharge lightning over voltages and switching over voltages to earth.
Specification:
Manufacturer Crompton Greaves Ltd, Nasik
Model No. ZLA X 25 C
Ref. Standard IEC 99 – 4. 1991
Rated Frequency 50 Hz
Max. Leakage Current 5 mA
BUS BAR
The conductors to which several incoming and outgoing
lines are connected.
cables are provided for
They are made up of Cu &Al,
The incoming and outgoing
metering purpose.
CURRENT TRANSFORMER
These are used to step-down currents for measurement, control &
protection.
Current transformers are used extensively for measuring current
and monitoring the operation of the power grid.
VOLTAGE TRANFORMER
 VT measure voltage and this parameter usedfor protection of system.
 For high voltage CVT(capacitive voltage transformer) is used instead of VT and
capacitors play divider role.
 We can also use these capacitors for PLC system.
Stepwise Operation of Thermal Power Plant
1)First the pulverized coal is burnt into the furnaceof boiler.
2) High pressure steam is produced in theboiler.
3) This steam is then passed through the super heater, where it further heated up.
4) This supper heated steam is then entered intoa turbineat high speed.
5)In turbine this steam force rotates the turbine blades that means here in the turbine
the stored potential energy of the high pressured steam is converted into mechanical
energy.
6)Afterrotating the turbine blades, the steam has lost its high pressure, passesoutof
turbine blades and enters intoacondenser.
7) in thecondenserthecold water is circulated with helpof pumpwhich condenses the
low pressure wetsteam.
8)This condensed water is then furthersupplied to low pressurewater heaterwhere the
low pressure steam increases the temperature of this feed water; it is then again heated
in a high pressure heaterwhere the high pressureof steam is used for heating.
9) The turbine in thermal powerstationactsasa prime moverof thealternator.
Efficiency of Thermal Power Station or Plant
The overall efficiency of a thermal power station or plant varies from 20% to 26%
and it depends upon plant capacity.
Mtps ppt

Weitere ähnliche Inhalte

Was ist angesagt?

Presentation on thermal power plant
Presentation on thermal power plantPresentation on thermal power plant
Presentation on thermal power plant
Rashmi Nimje
 
Fans in thermal power plants
Fans in thermal power plantsFans in thermal power plants
Fans in thermal power plants
SHIVAJI CHOUDHURY
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plant
SHIVAJI CHOUDHURY
 

Was ist angesagt? (20)

Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
 
kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training ppt
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Steam Boilers OR Steam Generators
Steam Boilers OR Steam GeneratorsSteam Boilers OR Steam Generators
Steam Boilers OR Steam Generators
 
Coal based power plant
Coal based power plantCoal based power plant
Coal based power plant
 
Presentation on thermal power plant
Presentation on thermal power plantPresentation on thermal power plant
Presentation on thermal power plant
 
Fans in thermal power plants
Fans in thermal power plantsFans in thermal power plants
Fans in thermal power plants
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plant
 
Waste heat recovery
Waste heat recoveryWaste heat recovery
Waste heat recovery
 
Ppt for power plant
Ppt for power plantPpt for power plant
Ppt for power plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Overview of Thermal Power Plants
Overview of Thermal Power PlantsOverview of Thermal Power Plants
Overview of Thermal Power Plants
 
Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)
 
kota super thermal power plant (kstps)
kota super thermal power plant (kstps)kota super thermal power plant (kstps)
kota super thermal power plant (kstps)
 
Coal Handling Plant
Coal Handling PlantCoal Handling Plant
Coal Handling Plant
 
Steam power plants
Steam power plantsSteam power plants
Steam power plants
 
POWER PLANT ENGINEERING
POWER PLANT ENGINEERING POWER PLANT ENGINEERING
POWER PLANT ENGINEERING
 
Steam thermal power plant(panki)
Steam thermal power plant(panki)Steam thermal power plant(panki)
Steam thermal power plant(panki)
 

Ähnlich wie Mtps ppt

Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02
arvind singh rathore
 
Thermal power plant Khedr, Hisar, Haryana
Thermal power plant Khedr, Hisar, HaryanaThermal power plant Khedr, Hisar, Haryana
Thermal power plant Khedr, Hisar, Haryana
Eesha Gupta
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
foxycrow
 

Ähnlich wie Mtps ppt (20)

Thermal Power Plant (Bathinda) PPT
Thermal Power Plant (Bathinda) PPTThermal Power Plant (Bathinda) PPT
Thermal Power Plant (Bathinda) PPT
 
Industrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarIndustrial training at NTPC Shaktinagar
Industrial training at NTPC Shaktinagar
 
Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02
 
Harsh ntpc
Harsh ntpcHarsh ntpc
Harsh ntpc
 
Bandel training
Bandel trainingBandel training
Bandel training
 
Thermal power plant Khedr, Hisar, Haryana
Thermal power plant Khedr, Hisar, HaryanaThermal power plant Khedr, Hisar, Haryana
Thermal power plant Khedr, Hisar, Haryana
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
thermal and nuclear power plant
 thermal and nuclear power plant thermal and nuclear power plant
thermal and nuclear power plant
 
KTPS
KTPSKTPS
KTPS
 
PPT ON THERMAL POWER PLANT (POLLUTION CONTROLLED)
PPT ON THERMAL POWER PLANT (POLLUTION  CONTROLLED)PPT ON THERMAL POWER PLANT (POLLUTION  CONTROLLED)
PPT ON THERMAL POWER PLANT (POLLUTION CONTROLLED)
 
ntpc thermal power plant.ppt
ntpc thermal power plant.pptntpc thermal power plant.ppt
ntpc thermal power plant.ppt
 
Ppt aman
Ppt amanPpt aman
Ppt aman
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORTTHERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
 
Emam training
Emam training Emam training
Emam training
 
ppt of ntpc dadri by emam raza khan
ppt of ntpc dadri by emam raza khan  ppt of ntpc dadri by emam raza khan
ppt of ntpc dadri by emam raza khan
 

Kürzlich hochgeladen

Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
HenryBriggs2
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 

Kürzlich hochgeladen (20)

Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptx
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 

Mtps ppt

  • 1. MEJIA THERMAL POWER STATION Presentation By:- Thermal Power Plant Industrial Training 1.Rantu das 2.Saikat bera 3.Sayan saha 4.Somnath Bhattacharyya 5.Soudip mal 6.Sounak ghosh 7.Sourabh Kumar Bhattacharjee 8.Sourav kanrar 9.Sourav Sarkar 10.Shubhadip som 11.Subharup Chakraborty 12.Subrata kr. Paul 13.Sujoy Bhattacharjee 14.Subrata Mahato
  • 2. Contents 1.Introduction 2.Overview of Mejia Thermal Power Plant 3.Power plant layout 4.Main and Auxiliary Equipment 5.Stepwise operation
  • 3. Introduction A Thermal Power Plant converts the heat energy of coal into electrical energy. Coal is burnt in a boiler which converts water into steam. The expansion of steam in turbine produces mechanical power which drives the alternator coupled to the turbine.Thermal Power Plants contribute maximum to the generation of Power for any country . Thermal Power Plants constitute 75.43% of the total installed captive and non-captive power generation in India . In thermal generating stations coal, oil, natural gas etc. are employed as primary sources of energy.
  • 4. Overview of MTPS  Damodar Valley Corporation was established on 7th July 1948.  The MTPS underthe DVC is thesecond largest thermal plant in West Bengal.  It has thecapacityof 2340 MW with 4 units of 210 MW each, 2 units of 250 MW each & 2 units of 500 MW each.  With the introduction of another two units of 500 MW that is in construction itwill be the largest in WestBengal.  Mejia Thermal Power Station is located in theoutskirtsof Raniganj in Bankura District.  The total power plant campus area is surrounded by boundarywalls and is basically divided into two majorparts, first the Power Plant area itself and the second is the Colony area for the residence and other facilities for MTPSs employees.
  • 5. Diagram of a typical coal-fired thermal power station
  • 6. General Layout of Thermal Power Station
  • 7. General Layout of Thermal Power Station
  • 8. MAJOR ELECTRICAL COMPONENTS OF POWER PLANT:
  • 9. MAIN AND AUXILIARY EQUIPMENTS 1. Coal handling plant 2. Pulverizing plant 3. Draft fans 4. Boiler 5. Ash handling plant 6. Turbine 7. Condenser 8. Cooling towers and ponds 9. Feed water heater 10. Economiser 11. Superheater and Reheater 12. Air preheater
  • 10. Coal handling plant •The function of coal handling plant is automatic feeding of coal to the boiler furnace. • A thermal power plant burns enormous amounts of coal. •A 200MW plant may require around 2000 tons of coal daily
  • 11. Pulverising plant In modern thermal power plant , coal is pulverised i.e. ground to dust like size and carried to the furnace in a stream of hotair. Pulverising is a means of exposing a large surfacearea to the action of oxygen and consequently helping combustion. Pulverising mills are further classifiedas: 1. Contact mill 2. Ball mill 3. Impact mill
  • 12. ASH HANDLING PLANT The percentage of ash in coal is 5% in good quality coal & about 40% in poor quality coal. Power plants generally use poor quality of coal , thus amount of ash produced by it is quite large. A modern 1000MW plant produces about 4800 tons of ash daily. The stations use some conveyor arrangement to carry ash to dump sites.
  • 13. Boiler  Boileris an enclosed vessel in which water is heated and circulated until the water is turned in tosteamat the required pressure.  Coal is burned inside the combustion chamber of boiler. The products of combustion are nothing butgases. These gases which are at high temperature vaporize the water inside the boiler to steam.  Boilers are classifiedas: 1. Fire tubeboilers 2. Water tubeboilers 3. Superheater 4. Reheater
  • 15. • The steam produced in the boiler goes to the steam drum and is then piped through the primary, platen and final super-heaters where it reaches the outlet temperature of 560 C and 160 ksc pressure • At this point in the process they have now turned the water into a very powerful source of energy • This rotates the turbine to which generator is on the other end • From rotating generator electricity is produced
  • 16. Reheate rSome of the heat of superheated steam is used to rotate the turbine where it loses some of its energy. The steam after reheating is used to rotate the second steam turbine where the heat is converted to mechanical energy. This mechanical energy is used to run the alternator, coupled to turbine , which is there by generating electrical energy.
  • 17. Condenser  Steam afterrotating steam turbinecomes tocondenser. Condenser refers here to the shell and tube heat exchanger (orsurfacecondenser) installed at the outlet of every steam turbine in Thermal power stations of utility companies.  The purpose is to condense the outlet (or exhaust) steam from steam turbine to obtain maximum efficiency and also to get the condensed steam in the formof purewater, otherwise known as condensate, back to steamgeneratoror (boiler) as boiler feed water.  Condensers are classifiedas: i)Jetcondensers orcontactcondensers, ii)Surfacecondensers.
  • 18. Primary Air Fan • Air to blow the coal from the mill to the boiler, called the primary air, is supplied by a large fan driven by a variable speed motor • When mixed with a stream of air the powdered coal behaves more like a gas than a solid • Primary air does two jobs – heating the coal powder and secondly lifting it into the furnace through pipelines
  • 19. Forced Draught (FD) Fan • Each unit shall have two forced draught fans • The fans draw warm air from the top of the boiler house through large air heaters becoming the primary and secondary air used for the boiler combustion process • The air heater warms the incoming air by transferring heat energy from the outgoing flue gases Air Pre-Heater (APH)• The air heaters use the remaining heat energy in the flue gas to heat up the combustion air for the boiler • Efficiency is increased by using this heat that would otherwise go up the chimney. The air temperature leaving the air heaters is at 300 C • The air heaters use the remaining heat energy and efficiency is increased by using this heat that would otherwise go up the chimney
  • 20. INDUCED DRAUGHT (ID) FAN • Two induced draught fans draw gases out of the boiler • The gas has already passed through the air heaters and precipitators before it has reached these fans • The heat from the flue gases or smoke is used in the air heaters to heat up the primary and secondary air Chimney • The chimney is 275 meters' high and 50,000 tonnes of reinforced concrete were used to make it • It consists of flues each of which serve typically two or three boilers (two units)
  • 21. • Each boiler has 4 passes with 7 fields each containing high voltage electrodes • These attract the dust or ash from the flue gases • At regular intervals the electrodes are rapped with motor-driven hammers and the PFAfalls into hoppers below • In a year 1,000 MW station may generate 1.5 million ton of ash • This is one of the ways to clean up the flue gases or smoke sent up the chimney • Secondly this ash is used by construction industry for use in building materials (bricks !!, Cement Fillers) Electro-Static Precipitator
  • 22. Cooling Towers  The condensate (water) formed inthe condenser after condensation is initially at high temperature. This hot water is passed to coolingtowers.  It isa tower- or building-like device in which atmospheric air (the heat receiver) circulates in direct or indirect contact with warmer water (the heat source) and the water is therebycooled.  Types Of Cooling Tower- 1. Wet cooling tower 2. Dry cooling tower
  • 23. Economizer  Fluegases coming outof the boilercarry lot of heat. Function of economizer is to recover some of the heat from the heat carried away in the flue gases up the chimney and utilize for heating the feed water to theboiler.  It is placed in the passage of flue gases in between the exit from the boiler and the entry to thechimney.  The use of economizer results in saving in coal consumption, increase in steaming rate and high boiler efficiency but needs extra investment andincrease in maintenance costs and floor area required for theplant.
  • 24. Steam Turbine  A steam turbine is a device that extracts thermal energy from pressurized steam and uses it to do mechanical work on arotating outputshaft.  The steam turbine is aform of heat engine that derives much of its improvement in thermodynamic efficiency from the use of multiple stages in the expansion of the steam, which results in a closer approach to the ideal reversible expansionprocess.
  • 25. Alternator  An alternator is an electromechanical device that converts mechanical energy to alternating current electrical energy. Most alternators use a rotating magnetic field. Differentgeometries - such as a linearalternator forusewith sterling engines - arealsooccasionally used. In principle, any AC generator can be called an alternator, but usually the word refers to small rotating machines driven by automotive and other internal combustionengines.
  • 26. Transformers  It is adevice that transfers electricenergy from one alternating-current circuit to one or more other circuits, either increasing (stepping up) or reducing (stepping down) thevoltage.  Transformers act through electromagnetic induction; current in the primary coil induces current in the secondary coil. The secondary voltageis calculated by multiplying the primary voltage by the ratio of the number of turns in the secondarycoil to that in the primary.
  • 28. SWITCH YARD  Placed where switching operation of power distribution isperformed.  Air insulated switch yard of 220KV-400KV are used. Main Components of SwitchYard:       Circuit breaker Isolator Lightening arrester Bus bar Current Transformer Potential Transformer
  • 29. CIRCUIT BREAKER  These are used for automatic switching during normal or abnormal conditions . Specification: Manufacturer ABB Limited Type of Circuit Breaker SF6 Rated Voltage 245 KV Rated Current Under Site Condition of 40 0C Under Site Condition of 50 0C 4000 A 2000 A Rated Frequency 50 Hz
  • 30. ISOLATOR  These are used to disconnect transmission line under no-load condition for safety, isolation and maintenance. Specification: Rated current for site conditions 2000A Rated Voltage 245 KV Rated Frequency 50 Hz Operating time of Isolator Less than 12 sec.
  • 31. LIGHTENINGARRESTOR  These are used to discharge lightning over voltages and switching over voltages to earth. Specification: Manufacturer Crompton Greaves Ltd, Nasik Model No. ZLA X 25 C Ref. Standard IEC 99 – 4. 1991 Rated Frequency 50 Hz Max. Leakage Current 5 mA
  • 32. BUS BAR The conductors to which several incoming and outgoing lines are connected. cables are provided for They are made up of Cu &Al, The incoming and outgoing metering purpose.
  • 33. CURRENT TRANSFORMER These are used to step-down currents for measurement, control & protection. Current transformers are used extensively for measuring current and monitoring the operation of the power grid.
  • 34. VOLTAGE TRANFORMER  VT measure voltage and this parameter usedfor protection of system.  For high voltage CVT(capacitive voltage transformer) is used instead of VT and capacitors play divider role.  We can also use these capacitors for PLC system.
  • 35. Stepwise Operation of Thermal Power Plant 1)First the pulverized coal is burnt into the furnaceof boiler. 2) High pressure steam is produced in theboiler. 3) This steam is then passed through the super heater, where it further heated up. 4) This supper heated steam is then entered intoa turbineat high speed. 5)In turbine this steam force rotates the turbine blades that means here in the turbine the stored potential energy of the high pressured steam is converted into mechanical energy. 6)Afterrotating the turbine blades, the steam has lost its high pressure, passesoutof turbine blades and enters intoacondenser. 7) in thecondenserthecold water is circulated with helpof pumpwhich condenses the low pressure wetsteam. 8)This condensed water is then furthersupplied to low pressurewater heaterwhere the low pressure steam increases the temperature of this feed water; it is then again heated in a high pressure heaterwhere the high pressureof steam is used for heating. 9) The turbine in thermal powerstationactsasa prime moverof thealternator.
  • 36. Efficiency of Thermal Power Station or Plant The overall efficiency of a thermal power station or plant varies from 20% to 26% and it depends upon plant capacity.