Good Neighbourly Relations
Committee
May 8, 2018
Update on work on the Jacques Cartier Bridge
(Montreal sector)
2
Agenda
Good Neighbourly Relations
Committee
+ Work on the steel structure
- Work status
- Planning for the coming weeks
...
3
Steel work 2017-2019
4
Work status
+ Contractor: Stellaire Construction
+ Work monitoring: WSC
+ Acoustic walls complete (80% of the site)
+ Re...
5
Steel work schedule
+ Work planned for the coming weeks
- Installation of scaffolding (20% complete)
- Installation of n...
6
Steel work schedule
+ Work shifts
- Work shift from Monday to Friday until December
• 7:00 a.m. to 5:30 p.m. (10 workers...
7
Current location of
sound level meters
De
Maisonneuve
Campion
8
Noise management
Noise management plan – steelwork site
+ Ongoing – Installation of acoustic barriers + noise
screens (8...
9
Noise management
Measures have been monitored since start-up
+ Confinement of compressors (shelters made from plywood,
s...
10
Noise management
Measures have been monitored since start-up
+ Optimization of the work area
+ Attention paid to the ch...
11
Upcoming steel work
Start-up in August 2018
between Ste-Catherine and Falardeau
12
Other work
+ Jacques Cartier Bridge multipurpose
path: opened April 2
+ Replacement of 266 guard-rail
sections on the m...
13
Partners
+ Organization that recovers
bottles for deposit and recyclable
materials for people in a situation
of poverty...
Discussion period
15
Let’s stay connected!
Information and communication tools
+ Notices to residents
+ Work advisories available online and...
Jacques Cartier Bridge Good Neighbourly Relations Committee - May 8, 2018
Nächste SlideShare
Wird geladen in …5
×

Jacques Cartier Bridge Good Neighbourly Relations Committee - May 8, 2018

71 Aufrufe

Veröffentlicht am

Update on work on the Jacques Cartier Bridge (Montreal sector)

Veröffentlicht in: Ingenieurwesen
  • Als Erste(r) kommentieren

  • Gehören Sie zu den Ersten, denen das gefällt!

Jacques Cartier Bridge Good Neighbourly Relations Committee - May 8, 2018

  1. 1. Good Neighbourly Relations Committee May 8, 2018 Update on work on the Jacques Cartier Bridge (Montreal sector)
  2. 2. 2 Agenda Good Neighbourly Relations Committee + Work on the steel structure - Work status - Planning for the coming weeks - Noise mitigation measures + Other updates + Discussion period + Next meeting
  3. 3. 3 Steel work 2017-2019
  4. 4. 4 Work status + Contractor: Stellaire Construction + Work monitoring: WSC + Acoustic walls complete (80% of the site) + Reinforcement work has started + Work end date: December 2018 Acoustic panels on De Maisonneuve Boulevard
  5. 5. 5 Steel work schedule + Work planned for the coming weeks - Installation of scaffolding (20% complete) - Installation of noise mitigation measures (20% complete) • Boom lift, forklift and a tracked carrier at the site - Steel repairs • Removal of rivets during the day • Reinforcement of steel towers • Reinforcement of steel plates (night)
  6. 6. 6 Steel work schedule + Work shifts - Work shift from Monday to Friday until December • 7:00 a.m. to 5:30 p.m. (10 workers) - Work shift at night from Monday to Thursday • 9:00 p.m. to 5:30 a.m. (10 workers) • Night work consists of installing steel reinforcement components
  7. 7. 7 Current location of sound level meters De Maisonneuve Campion
  8. 8. 8 Noise management Noise management plan – steelwork site + Ongoing – Installation of acoustic barriers + noise screens (80% complete) + Strict oversight of noise by the monitoring team + Optimization of work schedules (as much noisy work as possible planned during the day)
  9. 9. 9 Noise management Measures have been monitored since start-up + Confinement of compressors (shelters made from plywood, soundproofing panels and soundproofing wool) + Sound barrier installed near 2004 De Maisonneuve + Low-noise generator
  10. 10. 10 Noise management Measures have been monitored since start-up + Optimization of the work area + Attention paid to the choice and position of temporary lighting + Contractor's work method + Site set up to reduce backing up of gangway delivery truck + Boom lift with a white-noise back-up alarm + Forklift truck with a white-noise back-up alarm or flagger used + Prebuilt gangway + Screws used as much as possible instead of nails
  11. 11. 11 Upcoming steel work Start-up in August 2018 between Ste-Catherine and Falardeau
  12. 12. 12 Other work + Jacques Cartier Bridge multipurpose path: opened April 2 + Replacement of 266 guard-rail sections on the multipurpose path side: ongoing + Replacement of 266 guard rails on the sidewalk side: ongoing + Results of the pilot winter maintenance project on the multipurpose path: to be released at the end of summer
  13. 13. 13 Partners + Organization that recovers bottles for deposit and recyclable materials for people in a situation of poverty + JCCBI has supported this cause for several years and is loaning out a piece of land free of charge + June to September 2018 + 3 containers, a chemical toilet and small tents at the site
  14. 14. Discussion period
  15. 15. 15 Let’s stay connected! Information and communication tools + Notices to residents + Work advisories available online and via e-mail alerts + Resource people + Good Neighbourly Relations Committee + Twitter account for the Jacques Cartier Bridge @pontJCBridge + www.JacquesCartierChamplain.ca Questions or comments? + 450-651-8771 + communications@pjcci.ca Next meeting TBD (mid-June to mid-July)

×