What is Formwork?
o It should be capable of carrying all imposed dead and live loads
apart from its own weight.
o Formwork is a mould including all supporting structures, used to
shape and support the concrete until it attains sufficient strength to
carry its own weight.
Formwork is commonly made of
o Steel
o Timber
TIMBER FORMWORK
STEEL FORMWORK
 Formwork has been in use since the beginning of concrete
construction.
 New materials such as steel, plastics and fibreglass are used in
formwork.
 Greater attention is being given to the design, fabrication,
erection and dismantling of formwork
 Formwork is designed according to The ACI document SP-4.
Qualities of Formwork
 It should be water tight.
 It should be strong.
 It can be reusable.
 Its contact surface should be uniform.
 It should be according to the size of member.
• In order to successfully carry out its
function, formwork must achieve a balance
of following requirements:
• Containment
• Strength
• Resistance To Leakage
• Accuracy
• Ease Of Handling
• Finish And Reuse Potential
• Access For Concrete
• Economy
• Containment: formwork must be capable of shaping and
supporting the fluid concrete until it cures.
• Strength: formwork must be capable of safely withstanding
without distortion or danger the dead weight of the fluid
concrete is placed on it, labour weight, equipment weight and
any environmental loadings.
• Ease of Handling: form panels and units should be designed
so that their maximum size does not exceed that which can be
easily handled by hand or mechanical means.
– In addition all formwork must also be designed and
constructed to include facilities for adjustments, levelling,
easing and striking without damage to the form work or
concrete.
• Economy: all the formwork is very expensive. On average about 35%
of the total cost of any finished concrete unit or element can be
attributed to its formwork; of this just over 40% can be taken for
material for formwork and 60% for labour.
– The formwork designer must therefore not only consider the
maximum number of times that any form can be reused, but also
produce a design that will minimize the time taken for erection and
striking.
Major objectives considered in
formwork:
 Quality
 Safety
 Economy
 Quality:
Forms must be designed and built with sufficient stiffness and accuracy so that
the size, shape, position, and finish of the cast concrete are maintained.
Safety:
Forms must be built sufficient strength and factor of safety so that they have
the capable of all supporting loads.
 Economy:
Forms must be built efficiently, minimizing time and cost.
Requirements of formwork:
 Material should be cheap and re usable,
 It should be practically water proof, so that it should not
absorb water from concrete,
 Swelling and shrinkage should be minimum,
 Strong enough to with stand all external loads,
 Deflection should be minimum,
 Surface should be smooth, and afford easy striping,
 Light in weight, so that easy to transfer,
 Joints should be stiff, so that lateral deformation and leak is
minimum .
Three stages in the process :
a) Assembly and erection .
b) Concrete placement.
c) Stripping and dismantling.
• Formwork detail for different
structural members
In concrete construction formwork is
commonly provided for the following structural
members.
o Wall
o Column
o Slabs & Beams
o Stairs
o Chimneys
o Water tanks
o Cooling Towers
• Formwork for Wall
 It consists of
• Timber sheeting
• Vertical posts
• Horizontal members
• Rackers
• Stakes
• Wedges
 After completing one side of
formwork reinforcement is
provided at the place then the
second side formwork is
provided.
• Formwork for Column
• It consists of the following
– Side & End Planks
– Yoke
– Nut & Bolts
• Two end & two side planks
are joined by the yokes and
bolts.
• Formwork for columns
• Formwork for Slabs & beams:• It consists of
– Sole plates
– Wedges
– Props
– Head tree
– Planks
– Batten
– Ledgers
• Beam formwork rests
on head tree
• Slab form work rests on
battens and joists
• If prop height are more
than 8’ provide
horizontal braces.
• Lintel or Beam Formwork:
• FORMWORK FOR SLAB:
• FORMWORK FOR STAIRS:
• It consists of
– Vertical & inclined
posts
– Inclined members
-- Wooden Planks or
sheeting
– Stringer
– Riser Planks
• FORMWORK FOR STAIRS:
• FORMWORK FOR SPIRAL STAIRS :
• FORMWORK FOR CHIMNEYS:
For tall chimneys two types of forms
techniques are in generally use in our country
a) Jump form
b) Slip form
• Removal of formwork:
 Time of formwork removal depends on the following factors
1. Type of Cement
1. Rapid hardening cements require lesser time as compared to OPC
(Ordinary Portland Cement)
2. Ratio of concrete mix
1. Rich ratio concrete gain strength earlier as compared to weak
ratio concrete.
3. Weather condition
1. Hydration process accelerates in hot weather conditions as
compared to cold and humid weather conditions.
Time of Removal of formwork:
• First free end's support
should be removed.
• And then from right to left it
should be proceed.
• If we are removing from the
mid span then it will act as a
prop cantilever.
Cantilever slab
• In simply supported we
have to remove the
support from the mid
span to the ends.
• To meet the design
behavior.
Simply supported slab
• Maintenance of formwork:
• Due to continuous use wooden planks & steel plates
surfaces become uneven and require maintenance.
• For wooden formwork use cardboard or plastic fiber
board. Bolt hole places must also be repaired.
• For steel formwork plates must be leveled by mallet
and loose corners must be welded.
• Cost of formwork
 For normal works cost of formwork is about 30%-40% of the concrete cost.
 For special works cost of formwork is about 50%-60% of the concrete cost.
 Formwork cost is controlled by the following factors
• Formwork Material cost
• Formwork erecting cost
• Formwork removal cost
• Formwork jointing cost (Nails and Cables)
• Labor charges.
• Advantages of steel form work:
 It can be used for a no. of times.
 It is non absorbent.
 Smooth finish surface obtained.
 No shrinkage of formwork occurs.
 Easy to use.
 Its volume is less
 Its strength is more.
• LOADS ON FORMWORK:
• Dead load
 Self weight of formwork
 Pressure and loads from fresh concrete
 Reinforcement
• Imposed load
 Construction workers
 Stacking of materials
• Horizontal loads
• Environmental loads
 Accidental loads
 Wind loads
• References
• R.C.C Design by B.C.Punmia
• R.C.C Design by H.J.Shah
• Formwork Design Section 1500
• Doka Formwork Design
• Design of safe timber structures by Eva and
Tomi Torrati
Thank you
THANK YOU

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (20)

Superstructure construction
Superstructure constructionSuperstructure construction
Superstructure construction
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
 
Roofs
RoofsRoofs
Roofs
 
Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
 
Concrete
ConcreteConcrete
Concrete
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 
Types of stone masonry
Types of stone masonryTypes of stone masonry
Types of stone masonry
 
Damp Proof Course
Damp Proof Course Damp Proof Course
Damp Proof Course
 
BRICK MASONRY
BRICK MASONRYBRICK MASONRY
BRICK MASONRY
 
Scaffolding and formwork ppt
Scaffolding and  formwork pptScaffolding and  formwork ppt
Scaffolding and formwork ppt
 
Different rolled steel bars and sections
Different rolled steel bars and sectionsDifferent rolled steel bars and sections
Different rolled steel bars and sections
 
Shoring and underpinning
Shoring and underpinningShoring and underpinning
Shoring and underpinning
 
Foundations
FoundationsFoundations
Foundations
 
Reinforced Cement Concrete (RCC)
Reinforced Cement Concrete (RCC) Reinforced Cement Concrete (RCC)
Reinforced Cement Concrete (RCC)
 
TYPES OF TESTS ON CONCRETE
TYPES OF TESTS ON CONCRETETYPES OF TESTS ON CONCRETE
TYPES OF TESTS ON CONCRETE
 
Reinforced cement concrete
Reinforced cement concreteReinforced cement concrete
Reinforced cement concrete
 
Bricks
BricksBricks
Bricks
 
Scaffolding, underepinning and shoring
Scaffolding, underepinning and shoringScaffolding, underepinning and shoring
Scaffolding, underepinning and shoring
 

Andere mochten auch

Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryAbhishek Shah
 
Formwork design vs falsework design key differences
Formwork design vs falsework design  key differencesFormwork design vs falsework design  key differences
Formwork design vs falsework design key differencesscaffolddesign
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineeringFazal-E- Jalal
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyI'mMiss Lily
 
Basic Scaffolding Awareness
Basic Scaffolding AwarenessBasic Scaffolding Awareness
Basic Scaffolding Awarenessedale07
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 

Andere mochten auch (7)

Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
 
Formwork design vs falsework design key differences
Formwork design vs falsework design  key differencesFormwork design vs falsework design  key differences
Formwork design vs falsework design key differences
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineering
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction Technology
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 
Basic Scaffolding Awareness
Basic Scaffolding AwarenessBasic Scaffolding Awareness
Basic Scaffolding Awareness
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 

Ähnlich wie Formwork

Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar rautSAGAR RAUT
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdfFaizanSolanki
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shutteringKishor Ade
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
All you need to know about Construction Formwork
All you need to know about Construction FormworkAll you need to know about Construction Formwork
All you need to know about Construction FormworkAnkit Singhai
 
Introduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineeringIntroduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineeringUjasPandya2
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction purvi golecha
 
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdfFaizanSolanki
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTUVATSAL PATEL
 
types of formwork.pdf
types of formwork.pdftypes of formwork.pdf
types of formwork.pdfReigerRoyal
 
various types of scffolding and formwork with underpining
various types of scffolding and formwork with underpiningvarious types of scffolding and formwork with underpining
various types of scffolding and formwork with underpiningkuldeep361335
 

Ähnlich wie Formwork (20)

Formwork
FormworkFormwork
Formwork
 
FORMWORK.pptx
FORMWORK.pptxFORMWORK.pptx
FORMWORK.pptx
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar raut
 
Formwork
FormworkFormwork
Formwork
 
FormWork
FormWork FormWork
FormWork
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdf
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
All you need to know about Construction Formwork
All you need to know about Construction FormworkAll you need to know about Construction Formwork
All you need to know about Construction Formwork
 
Introduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineeringIntroduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineering
 
CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)
 
Gurme santoshkumar
Gurme santoshkumarGurme santoshkumar
Gurme santoshkumar
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
 
Formwork
FormworkFormwork
Formwork
 
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
 
Form Work
Form Work Form Work
Form Work
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU
 
types of formwork.pdf
types of formwork.pdftypes of formwork.pdf
types of formwork.pdf
 
formwork.pdf
formwork.pdfformwork.pdf
formwork.pdf
 
various types of scffolding and formwork with underpining
various types of scffolding and formwork with underpiningvarious types of scffolding and formwork with underpining
various types of scffolding and formwork with underpining
 

Kürzlich hochgeladen

Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 

Kürzlich hochgeladen (20)

Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 

Formwork

  • 2. What is Formwork? o It should be capable of carrying all imposed dead and live loads apart from its own weight. o Formwork is a mould including all supporting structures, used to shape and support the concrete until it attains sufficient strength to carry its own weight. Formwork is commonly made of o Steel o Timber
  • 5.  Formwork has been in use since the beginning of concrete construction.  New materials such as steel, plastics and fibreglass are used in formwork.  Greater attention is being given to the design, fabrication, erection and dismantling of formwork  Formwork is designed according to The ACI document SP-4.
  • 6. Qualities of Formwork  It should be water tight.  It should be strong.  It can be reusable.  Its contact surface should be uniform.  It should be according to the size of member.
  • 7. • In order to successfully carry out its function, formwork must achieve a balance of following requirements: • Containment • Strength • Resistance To Leakage • Accuracy • Ease Of Handling • Finish And Reuse Potential • Access For Concrete • Economy
  • 8. • Containment: formwork must be capable of shaping and supporting the fluid concrete until it cures. • Strength: formwork must be capable of safely withstanding without distortion or danger the dead weight of the fluid concrete is placed on it, labour weight, equipment weight and any environmental loadings.
  • 9. • Ease of Handling: form panels and units should be designed so that their maximum size does not exceed that which can be easily handled by hand or mechanical means. – In addition all formwork must also be designed and constructed to include facilities for adjustments, levelling, easing and striking without damage to the form work or concrete.
  • 10. • Economy: all the formwork is very expensive. On average about 35% of the total cost of any finished concrete unit or element can be attributed to its formwork; of this just over 40% can be taken for material for formwork and 60% for labour. – The formwork designer must therefore not only consider the maximum number of times that any form can be reused, but also produce a design that will minimize the time taken for erection and striking.
  • 11. Major objectives considered in formwork:  Quality  Safety  Economy
  • 12.  Quality: Forms must be designed and built with sufficient stiffness and accuracy so that the size, shape, position, and finish of the cast concrete are maintained. Safety: Forms must be built sufficient strength and factor of safety so that they have the capable of all supporting loads.  Economy: Forms must be built efficiently, minimizing time and cost.
  • 13. Requirements of formwork:  Material should be cheap and re usable,  It should be practically water proof, so that it should not absorb water from concrete,  Swelling and shrinkage should be minimum,  Strong enough to with stand all external loads,  Deflection should be minimum,  Surface should be smooth, and afford easy striping,  Light in weight, so that easy to transfer,  Joints should be stiff, so that lateral deformation and leak is minimum .
  • 14. Three stages in the process : a) Assembly and erection . b) Concrete placement. c) Stripping and dismantling.
  • 15. • Formwork detail for different structural members In concrete construction formwork is commonly provided for the following structural members. o Wall o Column o Slabs & Beams o Stairs o Chimneys o Water tanks o Cooling Towers
  • 16. • Formwork for Wall  It consists of • Timber sheeting • Vertical posts • Horizontal members • Rackers • Stakes • Wedges  After completing one side of formwork reinforcement is provided at the place then the second side formwork is provided.
  • 17. • Formwork for Column • It consists of the following – Side & End Planks – Yoke – Nut & Bolts • Two end & two side planks are joined by the yokes and bolts.
  • 18. • Formwork for columns
  • 19. • Formwork for Slabs & beams:• It consists of – Sole plates – Wedges – Props – Head tree – Planks – Batten – Ledgers • Beam formwork rests on head tree • Slab form work rests on battens and joists • If prop height are more than 8’ provide horizontal braces.
  • 20. • Lintel or Beam Formwork:
  • 22. • FORMWORK FOR STAIRS: • It consists of – Vertical & inclined posts – Inclined members -- Wooden Planks or sheeting – Stringer – Riser Planks
  • 23. • FORMWORK FOR STAIRS:
  • 24. • FORMWORK FOR SPIRAL STAIRS :
  • 25. • FORMWORK FOR CHIMNEYS: For tall chimneys two types of forms techniques are in generally use in our country a) Jump form b) Slip form
  • 26.
  • 27. • Removal of formwork:  Time of formwork removal depends on the following factors 1. Type of Cement 1. Rapid hardening cements require lesser time as compared to OPC (Ordinary Portland Cement) 2. Ratio of concrete mix 1. Rich ratio concrete gain strength earlier as compared to weak ratio concrete. 3. Weather condition 1. Hydration process accelerates in hot weather conditions as compared to cold and humid weather conditions.
  • 28. Time of Removal of formwork:
  • 29. • First free end's support should be removed. • And then from right to left it should be proceed. • If we are removing from the mid span then it will act as a prop cantilever. Cantilever slab
  • 30. • In simply supported we have to remove the support from the mid span to the ends. • To meet the design behavior. Simply supported slab
  • 31. • Maintenance of formwork: • Due to continuous use wooden planks & steel plates surfaces become uneven and require maintenance. • For wooden formwork use cardboard or plastic fiber board. Bolt hole places must also be repaired. • For steel formwork plates must be leveled by mallet and loose corners must be welded.
  • 32. • Cost of formwork  For normal works cost of formwork is about 30%-40% of the concrete cost.  For special works cost of formwork is about 50%-60% of the concrete cost.  Formwork cost is controlled by the following factors • Formwork Material cost • Formwork erecting cost • Formwork removal cost • Formwork jointing cost (Nails and Cables) • Labor charges.
  • 33. • Advantages of steel form work:  It can be used for a no. of times.  It is non absorbent.  Smooth finish surface obtained.  No shrinkage of formwork occurs.  Easy to use.  Its volume is less  Its strength is more.
  • 34. • LOADS ON FORMWORK: • Dead load  Self weight of formwork  Pressure and loads from fresh concrete  Reinforcement • Imposed load  Construction workers  Stacking of materials • Horizontal loads • Environmental loads  Accidental loads  Wind loads