SlideShare ist ein Scribd-Unternehmen logo
PREPARED BY:-
Karm Balar
Asst. Prof.
S.S.A.S.I.T.
S.S.A.S.I.T G.T.U
SHREE SWAMI ATMANAND SARASWATI
INSTITUTE OF TECHNOLOGY, SURAT
Construction management
Introduction
Resource leveling
Resource allocation
Other schedules derived from project schedules
Network crashing and cost-time trade-off
Contents
The scheduling of activities, so that none of the precedence
relationships are violated and none of the resource availabilities
are exceeded, is a difficult task and can result in a number of
combinations of possible early start and late start schedules.
In literature, scheduling problems with limited resources is
classified as large combinatorial problem.
A number of programs based on some rules of thumb (also called
heuristic) have been developed to solve such problems.
These heuristic programs for resource scheduling can be broadly
classified under two categories: (1) Resource leveling and (2)
Resource allocation
Introduction
The resource allocation procedure mainly consists of two activities:
(i) Resource smoothing
(ii) Resource levelling.
Resource Leveling and Resource Smoothing are two resource optimization
techniques. Resource Leveling is performed to balance the demand and
supply of resources. Resource Smoothing is performed to achieve a more
uniform resource utilization over a period of time. Resource Leveling may
change the critical path of the project, whereas Resource Smoothing does
not.
Methods of resource allocation
Resource smoothing
Resource Smoothing: Resource Smoothing is a resource optimization
technique in which the Project Manager adjusts the timing of different
activities so that the requirement for resources does not exceed a certain
pre-defined limit. The objective is to complete the work by the required
date while avoiding peaks resource demand.
The intelligent utilization of floats can smoothen the demand of resources
to the maximum possible extent is called resource Smoothing. In other
words, activities may only be delayed within their free and total float.
The resource smoothing is applied in such a way that the total project
duration remains the same i.e. there is no change in the total duration of
the project. First, the periods of minimum demand for resources are
determined or located and the activities are shifted according to the
availability of float and requirement of resources. Thus the intelligent use
of floats can smoothen the demand to the maximum possible extent. This
type of resource allocation is known as resource smoothing
Resource leveling
Resource Leveling is a resource optimization technique in which the
Project Manager adjusts the start dates and finish dates of different
activities in order to balance the demand for resources vs available supply.
If the demand of a resource is more than its availability, then the only
alternative is to delay the activity having maximum float. This process is
called resource levelling. If there are more than one activities requiring
the same amount of resources, in that case activity having minimum
duration is chosen for resource reallocation. Resource levelling is
adopted in case there is restriction on the availability resources
Resource levelling, Scenario A:
 For example, if there are two task on project network diagram and they are
scheduled on the same time period and both required the same resource,
“X”.
 Task A is on critical path, Task B is on non-critical path which means
which has float.
 Further assume, the task A is high priority task than the task B.
 In this situation, if we perform resource levelling, the project schedule or
critical path may or may not change.
 If the levelling delay within the free or total float the project schedule will
not change otherwise it will get changed.
Resource levelling, Scenario B:
 For example, if both task A and B are on critical path and they are
scheduled on the same time period and required the same resource, “X”.
 If we perform resource leveling in this situation then the project schedule or
critical path will surely get changed.
 It doesn’t matter which task of the two are high-priority than other.
Complete within given time
Complete within given resources
Scheduling is a process for setting in order the various planned activities by fixing the
starting and finishing dates to each part of the work in such a manner that the whole
work should be done in an orderly and systematic way.
For example, a railway map will show a passenger, the route by which he will travel from
one place to another and stations along that route. But the time table will give him the
time element that is the hour when his journey will begin, the time at which the train will
reach at various stations and also the total time that will be required to reach the
destination.
In the same way the planning department will have to frame a time schedule for a
project which will assign definite timings for individual constructional operations
leading to finished product.
SCHEDULING
1) Construction schedule
2) Staff schedule
3) Labor schedule
4) Material schedule
5) Financial schedule
6) Equipment schedule
7) Invoice schedule
8) Estimation of direct and indirect costs
Schedules derived from project schedule
The main objective of network planning is to complete the job within the stipulated
time at minimum cost. At times it becomes necessary to accelerate the completion of
work. This be made possible only by reducing the duration of critical activities. The
duration of critical path can be reduced by the deployment of additional resources e. g
additional labour, shuttering, centering etc., which again increases the cost.
While exploring the possibility of accelerating project completion by arranging additional
critical activities, the following questions require careful consideration.
To what extent the project duration be reduced ?
What is the lowest cost for reducing the project duration to the specified date?
What is the project duration for which the total project cost is the lowest?
Cost time analysis provides answers to these questions. The durations of critical
activities may be reduced in two ways (i) by deploying more resources for early
completion of such activities. (ii) by relaxing the technical specifications for such
activities.
TIME - COST TRADE OFF
If the duration is made longer, cost will be reduced. on the other hand, reducing the
project duration would increase the cost of the project. A decision on this will depend on
whether the commitment of additional resources and expenses is worthwhile.
The Optimum duration will be one which gives the most economic cost for completing
the project. In CPM there are two time cost estimates for each activity:
1. Normal estimate : In normal estimate, highlighting on cost, time being associated
with minimum cost.
2. Crash estimate : In crash estimate emphasis is given to absolute minimum time
required to complete the job. The necessary cost to complete the project with in the
minimum time is provided.
Updating can be defined as planning and programming of the
remaining portion of an activity job, by introducing the latest
information available.
At the end of day of work, the activities of the project must either be
completed, in progress or they may not have started yet.
Some of the activities may not have achieved the required percentage
of progress, which was planned to have achieved on the day of
updating.
Updating
As far as progress is concerned, three possibilities exists:
i) Some or all activities are progressing as per schedule.
ii) Some or all activities are ahead of schedule.
iii) Some or all activities are behind schedule.
If all activities are progressing as per schedule, there is no need for
updating the
network. But, in case of activities are behind schedule, the process of
updating is required to revive the time schedule of various activities on
the arrow diagram. Such revision is known as updating.
Module :-5 project scheduling and resource levelling

Weitere ähnliche Inhalte

Was ist angesagt?

Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
rathodjaydeep2
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
jmd2011
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
akashpadole
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
nazi2020
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
Nicola2903
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
chandkec
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
adeelmunir158
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
Vîñõđ Kůmåř
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
srinivas2036
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
upendar aavula
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
Asif Sultan Razu
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
Institute of Rural Management
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
Aditi Garg
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
Guhan M
 
construction project planing
 construction project planing construction project planing
construction project planing
SANJEEV Wazir
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
masilamani ramasamy
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Mr. Ramesh Nayaka
 
Scheduling of a project
Scheduling of a projectScheduling of a project
Scheduling of a project
Sailish Cephas
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
sneha saranya
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
Susitra Anandan
 

Was ist angesagt? (20)

Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Scheduling of a project
Scheduling of a projectScheduling of a project
Scheduling of a project
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 

Ähnlich wie Module :-5 project scheduling and resource levelling

TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
KHUSHBU SHAH
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
SHAZEBALIKHAN1
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
TecnicoItca
 
B012440511
B012440511B012440511
B012440511
IOSR Journals
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6
IOSRJMCE
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
DejeneTsegaye6
 
Modul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatanModul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatan
melchioreq
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
Somashekar S.M
 
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...An Introduction To The Resource Constrained Project Scheduling Problem Solvin...
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...
Courtney Esco
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
stilliegeorgiana
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
Golam Bitonsir
 
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
HIMADRI BANERJI
 
ch09s.ppt
ch09s.pptch09s.ppt
ch09s.ppt
TecnicoItca
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
SHAZEBALIKHAN1
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
dmdk12
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
Lii Van
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
Zulfiquer Ahmed Amin
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
Naveed Salman
 
Ch6 resources
Ch6 resourcesCh6 resources
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
sslovepk
 

Ähnlich wie Module :-5 project scheduling and resource levelling (20)

TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
B012440511
B012440511B012440511
B012440511
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
 
Modul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatanModul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatan
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
 
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...An Introduction To The Resource Constrained Project Scheduling Problem Solvin...
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
 
ch09s.ppt
ch09s.pptch09s.ppt
ch09s.ppt
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
Ch6 resources
Ch6 resourcesCh6 resources
Ch6 resources
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 

Mehr von Shree Swami atmanand saraswati inst. of technology, surat

INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart citiesINFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
Shree Swami atmanand saraswati inst. of technology, surat
 
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systemsINFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
Shree Swami atmanand saraswati inst. of technology, surat
 
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Shree Swami atmanand saraswati inst. of technology, surat
 
BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)
Shree Swami atmanand saraswati inst. of technology, surat
 
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
Shree Swami atmanand saraswati inst. of technology, surat
 
MODULE 2 PROJECT ORGANIZATION (updated)
MODULE 2 PROJECT ORGANIZATION (updated)MODULE 2 PROJECT ORGANIZATION (updated)
MODULE 2 PROJECT ORGANIZATION (updated)
Shree Swami atmanand saraswati inst. of technology, surat
 
BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)BCT- Module 5 a coffer-dam (Part_2)
BCT - Module 5 special work
BCT - Module 5 special workBCT - Module 5 special work
Module :- 8 Job layout (PART 2)
Module :- 8 Job layout (PART 2)Module :- 8 Job layout (PART 2)
Module :- 8 material management
Module :- 8 material managementModule :- 8 material management
Mod 3 construction economics
Mod 3 construction economicsMod 3 construction economics
MODULE 2 project organization
MODULE 2 project organizationMODULE 2 project organization
MODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction ManagementMODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction Management
Shree Swami atmanand saraswati inst. of technology, surat
 
Che 10 engineering fundamental
Che  10 engineering fundamentalChe  10 engineering fundamental
Chapter 9 introduction to construction equipments
Chapter  9 introduction to construction equipmentsChapter  9 introduction to construction equipments
Chapter 9 introduction to construction equipments
Shree Swami atmanand saraswati inst. of technology, surat
 
CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
Che 1 pile foundation
Che 1 pile foundationChe 1 pile foundation
Ch 5 b remote sensing
Ch 5 b remote sensingCh 5 b remote sensing
Ch 5 a gps
Ch 5 a gpsCh 5 a gps
Ch 5 levelling
Ch 5 levellingCh 5 levelling

Mehr von Shree Swami atmanand saraswati inst. of technology, surat (20)

INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart citiesINFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
 
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systemsINFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
 
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
 
BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)
 
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
 
MODULE 2 PROJECT ORGANIZATION (updated)
MODULE 2 PROJECT ORGANIZATION (updated)MODULE 2 PROJECT ORGANIZATION (updated)
MODULE 2 PROJECT ORGANIZATION (updated)
 
BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)
 
BCT - Module 5 special work
BCT - Module 5 special workBCT - Module 5 special work
BCT - Module 5 special work
 
Module :- 8 Job layout (PART 2)
Module :- 8 Job layout (PART 2)Module :- 8 Job layout (PART 2)
Module :- 8 Job layout (PART 2)
 
Module :- 8 material management
Module :- 8 material managementModule :- 8 material management
Module :- 8 material management
 
Mod 3 construction economics
Mod 3 construction economicsMod 3 construction economics
Mod 3 construction economics
 
MODULE 2 project organization
MODULE 2 project organizationMODULE 2 project organization
MODULE 2 project organization
 
MODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction ManagementMODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction Management
 
Che 10 engineering fundamental
Che  10 engineering fundamentalChe  10 engineering fundamental
Che 10 engineering fundamental
 
Chapter 9 introduction to construction equipments
Chapter  9 introduction to construction equipmentsChapter  9 introduction to construction equipments
Chapter 9 introduction to construction equipments
 
CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)
 
Che 1 pile foundation
Che 1 pile foundationChe 1 pile foundation
Che 1 pile foundation
 
Ch 5 b remote sensing
Ch 5 b remote sensingCh 5 b remote sensing
Ch 5 b remote sensing
 
Ch 5 a gps
Ch 5 a gpsCh 5 a gps
Ch 5 a gps
 
Ch 5 levelling
Ch 5 levellingCh 5 levelling
Ch 5 levelling
 

Kürzlich hochgeladen

What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
GeorgeMilliken2
 
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective UpskillingYour Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Excellence Foundation for South Sudan
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
Priyankaranawat4
 
IGCSE Biology Chapter 14- Reproduction in Plants.pdf
IGCSE Biology Chapter 14- Reproduction in Plants.pdfIGCSE Biology Chapter 14- Reproduction in Plants.pdf
IGCSE Biology Chapter 14- Reproduction in Plants.pdf
Amin Marwan
 
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
Nguyen Thanh Tu Collection
 
Liberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdfLiberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdf
WaniBasim
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
TechSoup
 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
EduSkills OECD
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
eBook.com.bd (প্রয়োজনীয় বাংলা বই)
 
ZK on Polkadot zero knowledge proofs - sub0.pptx
ZK on Polkadot zero knowledge proofs - sub0.pptxZK on Polkadot zero knowledge proofs - sub0.pptx
ZK on Polkadot zero knowledge proofs - sub0.pptx
dot55audits
 
Temple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation resultsTemple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation results
Krassimira Luka
 
Main Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docxMain Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docx
adhitya5119
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
Himanshu Rai
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
Celine George
 
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptxPengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Fajar Baskoro
 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
haiqairshad
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
Jean Carlos Nunes Paixão
 
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptxChapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Denish Jangid
 
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptxNEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
iammrhaywood
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
Nicholas Montgomery
 

Kürzlich hochgeladen (20)

What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
 
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective UpskillingYour Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective Upskilling
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
 
IGCSE Biology Chapter 14- Reproduction in Plants.pdf
IGCSE Biology Chapter 14- Reproduction in Plants.pdfIGCSE Biology Chapter 14- Reproduction in Plants.pdf
IGCSE Biology Chapter 14- Reproduction in Plants.pdf
 
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
 
Liberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdfLiberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdf
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
 
ZK on Polkadot zero knowledge proofs - sub0.pptx
ZK on Polkadot zero knowledge proofs - sub0.pptxZK on Polkadot zero knowledge proofs - sub0.pptx
ZK on Polkadot zero knowledge proofs - sub0.pptx
 
Temple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation resultsTemple of Asclepius in Thrace. Excavation results
Temple of Asclepius in Thrace. Excavation results
 
Main Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docxMain Java[All of the Base Concepts}.docx
Main Java[All of the Base Concepts}.docx
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
 
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptxPengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptx
 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
 
Chapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptxChapter wise All Notes of First year Basic Civil Engineering.pptx
Chapter wise All Notes of First year Basic Civil Engineering.pptx
 
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptxNEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
NEWSPAPERS - QUESTION 1 - REVISION POWERPOINT.pptx
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
 

Module :-5 project scheduling and resource levelling

  • 1. PREPARED BY:- Karm Balar Asst. Prof. S.S.A.S.I.T. S.S.A.S.I.T G.T.U SHREE SWAMI ATMANAND SARASWATI INSTITUTE OF TECHNOLOGY, SURAT Construction management
  • 2. Introduction Resource leveling Resource allocation Other schedules derived from project schedules Network crashing and cost-time trade-off Contents
  • 3. The scheduling of activities, so that none of the precedence relationships are violated and none of the resource availabilities are exceeded, is a difficult task and can result in a number of combinations of possible early start and late start schedules. In literature, scheduling problems with limited resources is classified as large combinatorial problem. A number of programs based on some rules of thumb (also called heuristic) have been developed to solve such problems. These heuristic programs for resource scheduling can be broadly classified under two categories: (1) Resource leveling and (2) Resource allocation Introduction
  • 4. The resource allocation procedure mainly consists of two activities: (i) Resource smoothing (ii) Resource levelling. Resource Leveling and Resource Smoothing are two resource optimization techniques. Resource Leveling is performed to balance the demand and supply of resources. Resource Smoothing is performed to achieve a more uniform resource utilization over a period of time. Resource Leveling may change the critical path of the project, whereas Resource Smoothing does not. Methods of resource allocation
  • 5. Resource smoothing Resource Smoothing: Resource Smoothing is a resource optimization technique in which the Project Manager adjusts the timing of different activities so that the requirement for resources does not exceed a certain pre-defined limit. The objective is to complete the work by the required date while avoiding peaks resource demand. The intelligent utilization of floats can smoothen the demand of resources to the maximum possible extent is called resource Smoothing. In other words, activities may only be delayed within their free and total float.
  • 6. The resource smoothing is applied in such a way that the total project duration remains the same i.e. there is no change in the total duration of the project. First, the periods of minimum demand for resources are determined or located and the activities are shifted according to the availability of float and requirement of resources. Thus the intelligent use of floats can smoothen the demand to the maximum possible extent. This type of resource allocation is known as resource smoothing
  • 7. Resource leveling Resource Leveling is a resource optimization technique in which the Project Manager adjusts the start dates and finish dates of different activities in order to balance the demand for resources vs available supply. If the demand of a resource is more than its availability, then the only alternative is to delay the activity having maximum float. This process is called resource levelling. If there are more than one activities requiring the same amount of resources, in that case activity having minimum duration is chosen for resource reallocation. Resource levelling is adopted in case there is restriction on the availability resources
  • 8. Resource levelling, Scenario A:  For example, if there are two task on project network diagram and they are scheduled on the same time period and both required the same resource, “X”.  Task A is on critical path, Task B is on non-critical path which means which has float.  Further assume, the task A is high priority task than the task B.  In this situation, if we perform resource levelling, the project schedule or critical path may or may not change.  If the levelling delay within the free or total float the project schedule will not change otherwise it will get changed. Resource levelling, Scenario B:  For example, if both task A and B are on critical path and they are scheduled on the same time period and required the same resource, “X”.  If we perform resource leveling in this situation then the project schedule or critical path will surely get changed.  It doesn’t matter which task of the two are high-priority than other.
  • 9. Complete within given time Complete within given resources
  • 10. Scheduling is a process for setting in order the various planned activities by fixing the starting and finishing dates to each part of the work in such a manner that the whole work should be done in an orderly and systematic way. For example, a railway map will show a passenger, the route by which he will travel from one place to another and stations along that route. But the time table will give him the time element that is the hour when his journey will begin, the time at which the train will reach at various stations and also the total time that will be required to reach the destination. In the same way the planning department will have to frame a time schedule for a project which will assign definite timings for individual constructional operations leading to finished product. SCHEDULING
  • 11. 1) Construction schedule 2) Staff schedule 3) Labor schedule 4) Material schedule 5) Financial schedule 6) Equipment schedule 7) Invoice schedule 8) Estimation of direct and indirect costs Schedules derived from project schedule
  • 12.
  • 13.
  • 14.
  • 15.
  • 16. The main objective of network planning is to complete the job within the stipulated time at minimum cost. At times it becomes necessary to accelerate the completion of work. This be made possible only by reducing the duration of critical activities. The duration of critical path can be reduced by the deployment of additional resources e. g additional labour, shuttering, centering etc., which again increases the cost. While exploring the possibility of accelerating project completion by arranging additional critical activities, the following questions require careful consideration. To what extent the project duration be reduced ? What is the lowest cost for reducing the project duration to the specified date? What is the project duration for which the total project cost is the lowest? Cost time analysis provides answers to these questions. The durations of critical activities may be reduced in two ways (i) by deploying more resources for early completion of such activities. (ii) by relaxing the technical specifications for such activities. TIME - COST TRADE OFF
  • 17. If the duration is made longer, cost will be reduced. on the other hand, reducing the project duration would increase the cost of the project. A decision on this will depend on whether the commitment of additional resources and expenses is worthwhile. The Optimum duration will be one which gives the most economic cost for completing the project. In CPM there are two time cost estimates for each activity: 1. Normal estimate : In normal estimate, highlighting on cost, time being associated with minimum cost. 2. Crash estimate : In crash estimate emphasis is given to absolute minimum time required to complete the job. The necessary cost to complete the project with in the minimum time is provided.
  • 18. Updating can be defined as planning and programming of the remaining portion of an activity job, by introducing the latest information available. At the end of day of work, the activities of the project must either be completed, in progress or they may not have started yet. Some of the activities may not have achieved the required percentage of progress, which was planned to have achieved on the day of updating. Updating
  • 19. As far as progress is concerned, three possibilities exists: i) Some or all activities are progressing as per schedule. ii) Some or all activities are ahead of schedule. iii) Some or all activities are behind schedule. If all activities are progressing as per schedule, there is no need for updating the network. But, in case of activities are behind schedule, the process of updating is required to revive the time schedule of various activities on the arrow diagram. Such revision is known as updating.