a m i a d w a t e r s y s t e m s
C A S E S T U D Y
GENERAL DESCRIPTION
SUMMARY
Water Source: Bore Water 
Water Use: Potable Water
Problem: High Levels of Iron, Manganese and Arsenic
Solution: Automatic Deep DMI-65 Media Filtration System.
BACKGROUND
North East Water provides water and sewerage services to 38 towns, villages and cities in North East Victoria,
serving an estimated population of 95,000 people in an area of approximately 20,000 square kilometres.
The region extends from Corryong in the east, along the Murray River to Yarrawonga, then south to Benalla and
the alpine towns of Bright, Mt. Beauty and Dartmouth.
The communities serviced are diverse in size and characteristics. They range from about 12,300 assessments
in Wodonga to less than 50 in the rural hamlet of St. James.
Major industrial customers are situated in Wodonga, Wangaratta, Rutherglen, Benalla and Myrtleford.
The Authority's head office is located in Wodonga, and it houses the administrative support and technical
services areas of the business.
North East Water's two major functions are treatment and distribution. System distribution operates from
Wodonga and Wangaratta, with local support centres at Benalla, Yarrawonga, Bright, Mt Beauty, Beechworth
and Rutherglen. The Authority operates 30 water treatment sites throughout the region.
North East Water is under significant pressure to ensure that the town of Wangaratta with 16,000 people
continues to supply its residents with treated potable water. The area has suffered severely under the current
drought and the decision was made by the board that North East Water will have to extract and treat bore water
for potable water to avoid potential political ramifications.
By: Jon Coetzee
North East Water (NEW) employed the services of Amiad and their subcontractors to ensure quality bore water
treatment plants are delivered on time and on budget. NEW propose to utilise two bores delivering 40 l/s (3.5
MLD) each at the Kerr Street site in Wangaratta. Amiad has to design, manufacture and deliver two (2)
containerised 3.5 MLD packaged water treatment plants.
The following abstract from the water analysis was provided to design the water treatment plant:
THE CHALLENGE
Amiad designed, manufactured, delivered, installed and commissioned two potable water treatment plants that
will consist of two (2) 40ft containers each. Each of the four (4) containers is fitted with four (4) media vessels.
Each of the vessels has four (4) valves.
Each of the containers will have to have a separate PLC/Citect control system that will enable NEW to use the
two 3.5 MLD plants independently or together. Each 3.5 MLD packaged plant must also have the ability to
separate into two (2) 1.75 MLD packaged plants. The container housing the controller can then be used as a
1.75 MLD treatment plant as a stand-alone unit or together with the other 3.5 MLD systems. This will give
NEW the functionality of either 2 x 3.5 MLD, or 1 x 7 MLD, or 2 x 1.75 MLD or 1 x 5.25 MLD water treatment
plants.
The four vessels in each container is spaced around the centre of the container, leaving enough space on either
end of the container for the controller and PC, compressor and instrumentation, chemical dosing and storage
respectively. Since the space in each container is limited, Amiad designed each container with five personal
access doors for monitoring and control, and four roof hatches for maintenance and media replacement. The
safe access to the roof hatches are via a caged ladder that leads up to a platform fitted with handrails.
Each media vessel backwash with the filtered water from the remaining media vessel in each container, thus
no additional backwash tank and pump is required. Backwash is initiated by time, pressure differential across
the system or manually. The PLC controller controls the backwash cycle. Since the plant had to be commissioned
without the Citect PLC connected the control panel is fitted with sufficient push button controls and LED displays.
The commissioned water treatment plant offers a Citect PLC that is used for a system overview, a mimic panel,
a menu for parameter changes and trending of the system and water quality properties.
THE SOLUTION
1.6 – 2.0 mg/l
6.7 – 6.8
0.2 – 0.4 mg/l
0.01 – 0.014 mg/l
0.5 – 10 NTU
0.1 mg/l
ADWG 2004 or better
Water source Bore water Requirements
Iron
pH
Mn
Arsenic
Turbidity
Sulphides
Standard/Guideline:*
< 0.3 mg/l
6.5 – 8.5
< 0.02 mg/l
< 0.007 mg/l
< 2 NTU
a m i a d w a t e r s y s t e m s
THE RESULT
The two 3.5MLD water treatment plants deliver treated water that complies and in certain cases exceed the
Australian drinking water guidelines.
Water source Bore water Requirements
Iron
pH
Mn
Arsenic
Turbidity
Sulphides
Standard/Guideline
Results
1.6 – 2.0 mg/l
6.7 – 6.8 mg/l
0.2 – 0.4 mg/l
0.01 – 0.014 mg/l
0.5 – 10 NTU
0.1 mg/l
< 0.3 mg/l
6.5 – 8.5
< 0.02 mg/l
< 0.007 mg/l
< 2 NTU
0.01 mg/l
7
0.008 mg/l
<0.001
0.07 NTU
<0.1 mg/l
ADWG 2004 or b etter
a m i a d w a t e r s y s t e m s
Amiad news is published by: Amiad Australia Pty Ltd, 3/15 Brisbane st, Eltham. VIC 3095
Tel: 03 9439 3533 Fax: 03 9439 1612 E-mail: sales@amiad.com.au

Weitere ähnliche Inhalte

Was ist angesagt?

Evac Building and Industry Vacuum Drainage Brochure
Evac Building and Industry Vacuum Drainage BrochureEvac Building and Industry Vacuum Drainage Brochure
Evac Building and Industry Vacuum Drainage BrochureJustin Shuler
 
Rainwater harvesting ltd international distributor pack np
Rainwater harvesting ltd international distributor pack npRainwater harvesting ltd international distributor pack np
Rainwater harvesting ltd international distributor pack npRainwaterharvesting
 
Fish Market Drainage At Abu Hamour
Fish Market Drainage At Abu HamourFish Market Drainage At Abu Hamour
Fish Market Drainage At Abu HamourMohamed ElSirsy
 
Rainwater Harvesting Ltd- UK distributors brochure.
Rainwater Harvesting Ltd- UK distributors brochure.   Rainwater Harvesting Ltd- UK distributors brochure.
Rainwater Harvesting Ltd- UK distributors brochure. Rainwaterharvesting
 
Présentation du kit Fontaine de Vie
Présentation du kit Fontaine de Vie Présentation du kit Fontaine de Vie
Présentation du kit Fontaine de Vie MaxHymum
 
Ha copy of flocktons jul 03 2015 ha presentation
Ha copy of flocktons jul 03 2015 ha presentationHa copy of flocktons jul 03 2015 ha presentation
Ha copy of flocktons jul 03 2015 ha presentationEd Vass
 

Was ist angesagt? (6)

Evac Building and Industry Vacuum Drainage Brochure
Evac Building and Industry Vacuum Drainage BrochureEvac Building and Industry Vacuum Drainage Brochure
Evac Building and Industry Vacuum Drainage Brochure
 
Rainwater harvesting ltd international distributor pack np
Rainwater harvesting ltd international distributor pack npRainwater harvesting ltd international distributor pack np
Rainwater harvesting ltd international distributor pack np
 
Fish Market Drainage At Abu Hamour
Fish Market Drainage At Abu HamourFish Market Drainage At Abu Hamour
Fish Market Drainage At Abu Hamour
 
Rainwater Harvesting Ltd- UK distributors brochure.
Rainwater Harvesting Ltd- UK distributors brochure.   Rainwater Harvesting Ltd- UK distributors brochure.
Rainwater Harvesting Ltd- UK distributors brochure.
 
Présentation du kit Fontaine de Vie
Présentation du kit Fontaine de Vie Présentation du kit Fontaine de Vie
Présentation du kit Fontaine de Vie
 
Ha copy of flocktons jul 03 2015 ha presentation
Ha copy of flocktons jul 03 2015 ha presentationHa copy of flocktons jul 03 2015 ha presentation
Ha copy of flocktons jul 03 2015 ha presentation
 

Andere mochten auch

Presented at Aust. Engineering conference - Overcoming Barriers to Sustainabi...
Presented at Aust. Engineering conference - Overcoming Barriers to Sustainabi...Presented at Aust. Engineering conference - Overcoming Barriers to Sustainabi...
Presented at Aust. Engineering conference - Overcoming Barriers to Sustainabi...SIMON ROONEY
 
Segunda evaluacion
Segunda evaluacionSegunda evaluacion
Segunda evaluacionandrecar123
 
Airnbn's Effect on Japan's Economy
Airnbn's Effect on Japan's EconomyAirnbn's Effect on Japan's Economy
Airnbn's Effect on Japan's EconomyLeah Dellicarpini
 
Programas para presentaciones
Programas para presentacionesProgramas para presentaciones
Programas para presentacionesIvonne Juarez
 
Chronological resume
Chronological resumeChronological resume
Chronological resumeDavid Clarke
 
Medios de comunicación, alfredo murcia, fredy castillo
Medios de comunicación, alfredo murcia, fredy castilloMedios de comunicación, alfredo murcia, fredy castillo
Medios de comunicación, alfredo murcia, fredy castilloAlfredo J Murcia P
 

Andere mochten auch (8)

Concepto de Obligación
Concepto de ObligaciónConcepto de Obligación
Concepto de Obligación
 
Presented at Aust. Engineering conference - Overcoming Barriers to Sustainabi...
Presented at Aust. Engineering conference - Overcoming Barriers to Sustainabi...Presented at Aust. Engineering conference - Overcoming Barriers to Sustainabi...
Presented at Aust. Engineering conference - Overcoming Barriers to Sustainabi...
 
Segunda evaluacion
Segunda evaluacionSegunda evaluacion
Segunda evaluacion
 
EXECSUM PHARMA 2016
EXECSUM PHARMA 2016EXECSUM PHARMA 2016
EXECSUM PHARMA 2016
 
Airnbn's Effect on Japan's Economy
Airnbn's Effect on Japan's EconomyAirnbn's Effect on Japan's Economy
Airnbn's Effect on Japan's Economy
 
Programas para presentaciones
Programas para presentacionesProgramas para presentaciones
Programas para presentaciones
 
Chronological resume
Chronological resumeChronological resume
Chronological resume
 
Medios de comunicación, alfredo murcia, fredy castillo
Medios de comunicación, alfredo murcia, fredy castilloMedios de comunicación, alfredo murcia, fredy castillo
Medios de comunicación, alfredo murcia, fredy castillo
 

Ähnlich wie Iron&Manganese-removal-NE-Water

BWT_Seawater_desalination_web
BWT_Seawater_desalination_webBWT_Seawater_desalination_web
BWT_Seawater_desalination_webThomas Larsen
 
IMAGUA_WATER_TECHNOLOGIES_EN_AF
IMAGUA_WATER_TECHNOLOGIES_EN_AFIMAGUA_WATER_TECHNOLOGIES_EN_AF
IMAGUA_WATER_TECHNOLOGIES_EN_AFWilfred Nhemwa
 
Dew point proposal for city of santa cruz v6
Dew point   proposal for city of santa cruz v6Dew point   proposal for city of santa cruz v6
Dew point proposal for city of santa cruz v6ru55e11
 
Dew point proposal for city of santa cruz v5
Dew point   proposal for city of santa cruz v5Dew point   proposal for city of santa cruz v5
Dew point proposal for city of santa cruz v5ru55e11
 
Desalination plant
Desalination plantDesalination plant
Desalination plantLincy Jancy
 
Paper id 252014156
Paper id 252014156Paper id 252014156
Paper id 252014156IJRAT
 
BIOLOGY-REVERSE OSMOSIS
BIOLOGY-REVERSE OSMOSISBIOLOGY-REVERSE OSMOSIS
BIOLOGY-REVERSE OSMOSISalenashik
 
Planning and management of water
Planning and management of waterPlanning and management of water
Planning and management of waterSiddhi Vakharia
 
ITIKI's Water Safety Plan
ITIKI's Water Safety PlanITIKI's Water Safety Plan
ITIKI's Water Safety PlanLynda Shelley
 
Microcontroller Based automatic AQUAPONICS SYSTEM
Microcontroller Based automatic AQUAPONICS SYSTEMMicrocontroller Based automatic AQUAPONICS SYSTEM
Microcontroller Based automatic AQUAPONICS SYSTEMIRJET Journal
 
Dew Point Proposal for City of Santa Cruz v6
Dew Point Proposal for City of Santa Cruz v6Dew Point Proposal for City of Santa Cruz v6
Dew Point Proposal for City of Santa Cruz v6Robert Singleton
 
160268_Brochure Desalination_EN_LR (2)
160268_Brochure Desalination_EN_LR (2)160268_Brochure Desalination_EN_LR (2)
160268_Brochure Desalination_EN_LR (2)Ludovic Renoux
 

Ähnlich wie Iron&Manganese-removal-NE-Water (20)

BWT_Seawater_desalination_web
BWT_Seawater_desalination_webBWT_Seawater_desalination_web
BWT_Seawater_desalination_web
 
Water industry
Water industryWater industry
Water industry
 
Brochure Smart City, Watertreatment
Brochure Smart City, WatertreatmentBrochure Smart City, Watertreatment
Brochure Smart City, Watertreatment
 
Watertek
WatertekWatertek
Watertek
 
IMAGUA_WATER_TECHNOLOGIES_EN_AF
IMAGUA_WATER_TECHNOLOGIES_EN_AFIMAGUA_WATER_TECHNOLOGIES_EN_AF
IMAGUA_WATER_TECHNOLOGIES_EN_AF
 
engineered-systems
engineered-systemsengineered-systems
engineered-systems
 
Engineered systems
Engineered systemsEngineered systems
Engineered systems
 
Dew point proposal for city of santa cruz v6
Dew point   proposal for city of santa cruz v6Dew point   proposal for city of santa cruz v6
Dew point proposal for city of santa cruz v6
 
Dew point proposal for city of santa cruz v5
Dew point   proposal for city of santa cruz v5Dew point   proposal for city of santa cruz v5
Dew point proposal for city of santa cruz v5
 
Desalination plant
Desalination plantDesalination plant
Desalination plant
 
Paper id 252014156
Paper id 252014156Paper id 252014156
Paper id 252014156
 
BIOLOGY-REVERSE OSMOSIS
BIOLOGY-REVERSE OSMOSISBIOLOGY-REVERSE OSMOSIS
BIOLOGY-REVERSE OSMOSIS
 
Planning and management of water
Planning and management of waterPlanning and management of water
Planning and management of water
 
Desalination
DesalinationDesalination
Desalination
 
ITIKI's Water Safety Plan
ITIKI's Water Safety PlanITIKI's Water Safety Plan
ITIKI's Water Safety Plan
 
Sodium hypoclorite plant
Sodium hypoclorite plantSodium hypoclorite plant
Sodium hypoclorite plant
 
Microcontroller Based automatic AQUAPONICS SYSTEM
Microcontroller Based automatic AQUAPONICS SYSTEMMicrocontroller Based automatic AQUAPONICS SYSTEM
Microcontroller Based automatic AQUAPONICS SYSTEM
 
Dew Point Proposal for City of Santa Cruz v6
Dew Point Proposal for City of Santa Cruz v6Dew Point Proposal for City of Santa Cruz v6
Dew Point Proposal for City of Santa Cruz v6
 
IRWD Michelson Water Recycling Plant Phase 2 Expansion
IRWD Michelson Water Recycling Plant Phase 2 ExpansionIRWD Michelson Water Recycling Plant Phase 2 Expansion
IRWD Michelson Water Recycling Plant Phase 2 Expansion
 
160268_Brochure Desalination_EN_LR (2)
160268_Brochure Desalination_EN_LR (2)160268_Brochure Desalination_EN_LR (2)
160268_Brochure Desalination_EN_LR (2)
 

Iron&Manganese-removal-NE-Water

  • 1. a m i a d w a t e r s y s t e m s C A S E S T U D Y GENERAL DESCRIPTION SUMMARY Water Source: Bore Water  Water Use: Potable Water Problem: High Levels of Iron, Manganese and Arsenic Solution: Automatic Deep DMI-65 Media Filtration System. BACKGROUND North East Water provides water and sewerage services to 38 towns, villages and cities in North East Victoria, serving an estimated population of 95,000 people in an area of approximately 20,000 square kilometres. The region extends from Corryong in the east, along the Murray River to Yarrawonga, then south to Benalla and the alpine towns of Bright, Mt. Beauty and Dartmouth. The communities serviced are diverse in size and characteristics. They range from about 12,300 assessments in Wodonga to less than 50 in the rural hamlet of St. James. Major industrial customers are situated in Wodonga, Wangaratta, Rutherglen, Benalla and Myrtleford. The Authority's head office is located in Wodonga, and it houses the administrative support and technical services areas of the business. North East Water's two major functions are treatment and distribution. System distribution operates from Wodonga and Wangaratta, with local support centres at Benalla, Yarrawonga, Bright, Mt Beauty, Beechworth and Rutherglen. The Authority operates 30 water treatment sites throughout the region. North East Water is under significant pressure to ensure that the town of Wangaratta with 16,000 people continues to supply its residents with treated potable water. The area has suffered severely under the current drought and the decision was made by the board that North East Water will have to extract and treat bore water for potable water to avoid potential political ramifications. By: Jon Coetzee
  • 2. North East Water (NEW) employed the services of Amiad and their subcontractors to ensure quality bore water treatment plants are delivered on time and on budget. NEW propose to utilise two bores delivering 40 l/s (3.5 MLD) each at the Kerr Street site in Wangaratta. Amiad has to design, manufacture and deliver two (2) containerised 3.5 MLD packaged water treatment plants. The following abstract from the water analysis was provided to design the water treatment plant: THE CHALLENGE Amiad designed, manufactured, delivered, installed and commissioned two potable water treatment plants that will consist of two (2) 40ft containers each. Each of the four (4) containers is fitted with four (4) media vessels. Each of the vessels has four (4) valves. Each of the containers will have to have a separate PLC/Citect control system that will enable NEW to use the two 3.5 MLD plants independently or together. Each 3.5 MLD packaged plant must also have the ability to separate into two (2) 1.75 MLD packaged plants. The container housing the controller can then be used as a 1.75 MLD treatment plant as a stand-alone unit or together with the other 3.5 MLD systems. This will give NEW the functionality of either 2 x 3.5 MLD, or 1 x 7 MLD, or 2 x 1.75 MLD or 1 x 5.25 MLD water treatment plants. The four vessels in each container is spaced around the centre of the container, leaving enough space on either end of the container for the controller and PC, compressor and instrumentation, chemical dosing and storage respectively. Since the space in each container is limited, Amiad designed each container with five personal access doors for monitoring and control, and four roof hatches for maintenance and media replacement. The safe access to the roof hatches are via a caged ladder that leads up to a platform fitted with handrails. Each media vessel backwash with the filtered water from the remaining media vessel in each container, thus no additional backwash tank and pump is required. Backwash is initiated by time, pressure differential across the system or manually. The PLC controller controls the backwash cycle. Since the plant had to be commissioned without the Citect PLC connected the control panel is fitted with sufficient push button controls and LED displays. The commissioned water treatment plant offers a Citect PLC that is used for a system overview, a mimic panel, a menu for parameter changes and trending of the system and water quality properties. THE SOLUTION 1.6 – 2.0 mg/l 6.7 – 6.8 0.2 – 0.4 mg/l 0.01 – 0.014 mg/l 0.5 – 10 NTU 0.1 mg/l ADWG 2004 or better Water source Bore water Requirements Iron pH Mn Arsenic Turbidity Sulphides Standard/Guideline:* < 0.3 mg/l 6.5 – 8.5 < 0.02 mg/l < 0.007 mg/l < 2 NTU a m i a d w a t e r s y s t e m s
  • 3. THE RESULT The two 3.5MLD water treatment plants deliver treated water that complies and in certain cases exceed the Australian drinking water guidelines. Water source Bore water Requirements Iron pH Mn Arsenic Turbidity Sulphides Standard/Guideline Results 1.6 – 2.0 mg/l 6.7 – 6.8 mg/l 0.2 – 0.4 mg/l 0.01 – 0.014 mg/l 0.5 – 10 NTU 0.1 mg/l < 0.3 mg/l 6.5 – 8.5 < 0.02 mg/l < 0.007 mg/l < 2 NTU 0.01 mg/l 7 0.008 mg/l <0.001 0.07 NTU <0.1 mg/l ADWG 2004 or b etter a m i a d w a t e r s y s t e m s Amiad news is published by: Amiad Australia Pty Ltd, 3/15 Brisbane st, Eltham. VIC 3095 Tel: 03 9439 3533 Fax: 03 9439 1612 E-mail: sales@amiad.com.au