1. Former NAS Moffett Field
Hangar 1 Removal Action Update
Bryce Bartelma, PG
Navy BRAC PMO West
August 9, 2012
RAB Meeting
1
2. Project Objective
• Control release of PCBs from Hangar 1 in accordance
with EE/CA (July 2008) and Action Memorandum
(December 2008)
Demolition of interior structures
Removal of contaminated siding
Application of weather-resistant coating to steel frame
2
3. Continued Monitoring and
Protection Measures
• Continued biological activity and
nesting deterrents
• Maintain storm water and ground
surface protection
• Navy and NASA air monitoring data
demonstrates control of air emissions
3
8. Remaining Tasks
• Scaffolding deconstruction
• Mezzanine prep and coat
• Final touch ups, cleaning
and surface soil removal
8
9. Schedule
• Complete Fieldwork and
Deconstruct Scaffolding
October 2012
• Final Cleaning and
Demobilize
November 2012
• Submit After Action
Completion Report
Winter/Spring 2013
9