1. MERC’s Public Hearing
in the matter of
R-Infra-D’s application for
Distribution License
Case 65 of 2011
J
Sandeep N. Ohri
U Authorised Consumer Representative
L
sandeep.ohri@ymail.com
2
9833097575
0
1
1
2. Background
• RINFRA is currently operating under the Bombay
Suburban Electric License
– This expires on 15-Aug-2011
• RINFRA had earlier claimed that this License does
not expire
– However MERC has already ruled that it does expire and
that RINFRA must apply for a fresh license
• As per the EA2003, a fresh application is to be made
J
U
L
– All such applications must be presented before the Public
2 • Hence, we are here today!!
0
1 2
1
3. Objectives of EA 2003
• The Electricity Act, 2003 wants:
– To promote competition
– To protect consumer interest
– To develop the power industry
• If Licenses will be given only to companies who
have ‘experience’
– There is no choice but to select from amongst the existing
J
players
U
L – Which will limit competition
2
0 Is this market closed for all new entrants?
1 3
1
4. What should we consider?
• Matters of Law
– Does the Section / Regulation exist?
– Has due process been followed?
– Is the Authority competent and empowered?
• Matters of Fact
– Is the data submitted, factual?
– Have the events claimed to have taken place, actually
J occurred?
U
L – Has evidence been presented and is it sufficient?
2
0 But, shouldn’t we care about Track Record?
1 4
1
5. RINFRA has a POOR Track Record!
• Operating in the comfort zone of a monopoly
– Has not faced ‘competition’ for 80 years (Air India & MTNL
were also once a monopoly – were they the best?)
– In fact, has made every attempt to thwart it!
• The worst power procurement record amongst all
the Mumbai DISCOMs
– Failed to protect its own customers by not securing the
available 500 MW from Tata
J
U – Even ASCI pointed out that incredibly high costs were on
L
account of absence of an LT PPA
2
0 Its irresponsibility is being paid for by Consumers!
1 5
1
6. Top 5 Projects – all delayed
• Most by a year, some by 3 years!!
J
U
L
2
0 This seems to be the ‘standard’ for this Group
1 6
1
7. No Transparency in Accounts
• Has failed to maintain and submit separate
Accounts for the Mumbai Licensed business
– In complete violation of MERC’s Regulations
• Has also shelved the demerger plan
– We will not know if any funds are being diverted!
J
U
L
2
0 Are electricity consumers paying for the METRO?
1 7
1
8. Just one Technical Issue
• Affidavit signed by Ramesh Shenoy states:
“there are no proceedings pending in any court of
law/tribunal or arbitrator or any other authority, wherein
the applicant is a party and where issues arising and or
reliefs sought are identical or similar to the issues arising in
the matter pending before the commission”
• But RINFRA has already filed an Appeal in ATE in
Case No. 78 of 2010
J – That Order stated that RINFRA’s present License expires
U
L – Isn’t this a ‘similar’ issue?
2
0 What is the penalty for lying in an Affidavit?
1 8
1
9. Data to be reconciled
• The Hon’ble Commission to correlate present
submissions, with earlier ARR filings
– Details of Distribution / Transmission projects managed
in the last 5 years (pg 9)
– Average consumers, Quantum of Energy Distributed &
Revenue collected (pg 12)
– Expenses (pg 13)
• Also check what has been submitted in various
J
U
other Petitions (Case 40 of 2009, etc.)
L
2
0 I trust we’re not expected to become Auditors!!
1 9
1
10. 5Y Business Plan Data
FY 2010-11 FY FY Change in Change in
Parameter
(ARR) 2011-12 2015-16 4 years 5 years
No. of
26,83,887 27,67,528 30,41,741 9.9 % 13.3 %
Consumers
Sale of
7875 6695 8361 24.9 % 6.2 %
Electricity (MU)
Revenue pg 19
5342 4426 5398 21.9 % 1.1 %
(Rs. Cr.)
Capital Base
3313 3864 5932 53.5 % 79.1 %
(Rs. Cr.)
J
U
L Incidentally, the data given on pg 338 is inconsistent with the data on pg 19
2
0 Increased Capital Base WILL result in higher tariff
1 10
1
11. Tamasoma jyotir gamaya
(From darkness unto light)
I sincerely thank the Hon’ble Commission for this
opportunity, the time and their patience!
Thank you !!
Contact: Sandeep N. Ohri
J Email: sandeep.ohri@ymail.com
U
L Mobile: 98 33 09 7575
2 Moderator: http://groups.yahoo.com/group/bijlee
0
1
1