TIME   -   TWO HOURS
                       TVS-Mysore
ABOUT HIRANO SAN




Full name       - Mr HIROYUKI HIRANO

Author of       - JUST IN TIME - FACTORY REVOLUTION

Consultant on   - JIT




     PREACHES & PRACTICES INNOVATION




                                                 TVS-Mysore
JIT FACTORY REVOLTUION
         BY
  Mr HIROYUKI HIRANO




                         TVS-Mysore
JIT FACTORY REVOLUTION
                               STEPS IN IMPLEMENTING JIT PRODUCTION

                                                       JUST IN TIME


                                                           STEP 5
MANPOWER REDUCTION




                     JIDOKA-HUMAN AUTOMATION                               MAINTENANCE & SAFETY
                                                 STANDARDISED OPERATIONS




                                                                                                     VISUAL CONTROL
                                                          STEP 4
                                  CHANGEOVER                               QUALITY ASSURANCE
                                                        LEVELLING

                                                          STEP 3
                     MULTI -PROCESS OPERATIONS                             KANBAN
                                                   FLOW MANUFACTURING

                                                           STEP 2

                                                           5S

                                                           STEP 1

                                                  AWARENESS REVOLUTION
                                                                                               TVS-Mysore
JIT FACTORY REVOLUTION
          TOPICS

1    INTRODUCTION
2    AWARENESS REVOLUTION
3    5S
4    FLOW MANUFACTURING
5    STANDARD OPERATIONS
6    MULTI PROCESS HANDLING
7    REDUCING WORKER HOURS
8    LEVELLING PRODUCTION
9    JIDOKA
10   CHANGEOVER
11   QUALITY ASSURANCE
12   KANBAN
13   MAINTENANCE & SAFETY

                                TVS-Mysore
JIT FACTORY REVOLUTION
                           1       INTRODUCTION

CELL SHOULD BE FLEXIBLE




FLEXIBILITY TO ADAPT TO CHANGES IN DEMAND, PRODUCT MIX & PRODUCT DESIGN


WITHIN CELL      -       ONE PIECE FLOW
                 -       REDUCED SETUP TIME
                 -       IMPROVED M/Cs TO INFORM OPERATORS ABOUT PROBLEMS
                 -       MEASURES TO PREVENT DEFECTS & BREAKDOWNS


BETWEEN CELLS -          SMALL LOTS - UNIFORM SIZE - KANBAN
                 -       PULL CONTROL

              “JIT MEANS TRIMMING LOSSES - AN ORDEAL FOR SURVIVAL”
                                                                     TVS-Mysore
JIT FACTORY REVOLUTION
    2        AWARENESS REVOLUTION


ASSUME CURRENT PRODUCTION SYSTEM IS THE WORST



          CHANGE IN THE WAY OF THINKING



         INSTALL NEW CORPORATE CULTURE



  OPERATORS TO LEARN NEW METHODS - TRAINING



        HAVE CLEAR POLICIES FOR RESISITANCE



                                                TVS-Mysore
JIT FACTORY REVOLUTION
 TEN COMMANDMENTS OF INNOVATION

1 - DISCARD FIXED IDEAS

2 - THINK HOW IT CAN BE DONE THAN, HOW IT WON’T

3 - DENY STATUS QUO

4 - DON’T SEEK PERFECTION

5 - CORRECT MISTAKES AS SOON AS THEY ARE FOUND

6 - INNOVATION NEEDS NO MONEY

7 - PROBLEMS ARE OPPORTUNITIES TO USE OUR BRAINS

8 - ASK WHY 5 TIMES

9 - IDEAS OF 10 ARE BETTER THAN KNOWLEDGE OF 1

10 - INNOVATION NEVER ENDS

                                                   TVS-Mysore
JIT FACTORY REVOLUTION
                    INNOVATION CYCLE


                                  ACT     PLAN
IMPROVEMENT CYCLE
KAIZEN
                                 CHECK     DO




                                  AC          T
                                    T
                                           RGE
                                         TA
INNOVATION CYCLE                                    VISION /
                                CHECK     IMAGE    PICTURE /
KAIKAKU                                             DREAM
                                         PL
                                    DO     AN



                                                  TVS-Mysore
JIT FACTORY REVOLUTION
                   3       5S


        SEIRI          -        PROPER ARRANGEMENT


        SEITON         -        ORDERLINESS


        SEISO          -        CLEANLINESS


        SEIKITSU       -        CLEANUP


        SHITSUKE       -        DISCIPLINE




WE ARE BEHIND TIMES IF WE STILL SWEEP THE FLOORS

                                                   TVS-Mysore
JIT FACTORY REVOLUTION
                     4        FLOW MANUFACTURING


                           PRODUCING ONE PIECE AT A TIME


CYCLE TIME IS THE TIME IT TAKES TO CARRY ONE PART ALL THE WAY THROUGH THE CELL

                                         WORKING HOURS / DAY
              TAKT TIME        =
                                               DAILY RATE



                                       MONTHLY QUANTITY REQUIRED
              DAILY RATE       =
                                       WORKING DAYS PER MONTH

               MULTI PROCESS HANDLING & SMALL INLINE MACHINES

                                                                   TVS-Mysore
JIT FACTORY REVOLUTION
          5      STANDARD OPERATIONS




      RULES & METHODS TO PRODUCE QUALITY PRODUCTS,


                 SAFELY & INEXPENSIVELY


 BY EFFICIENT ARRANGEMENT OF PEOPLE, PRODUCT & MACHINES




STANDARD OPERATIONS BULLETINS & MANUALS ON WORK METHODS

                                                      TVS-Mysore
JIT FACTORY REVOLUTION
     6        MULTI PROCESS HANDLING


 ONE OPERATOR HANDLES SEVERAL PROCESS IN A CELL



DE-LINEATE JOBS PERFORMED BY MACHINE & OPERATORS
         (MACHINES CAN WORK INDEPENDENTLY)


MAKE CELLS U SHAPED & GIVE MACHINES JIDOKA FUNCTION


         OPERATORS TO STAND WHILE WORKING


         TRAIN OPERATORS TO BE MULTI SKILLED



   FOLLOW RABBIT CHASE - PRODUCTIVITY MAY GO UP

                                                      TVS-Mysore
JIT FACTORY REVOLUTION
       7      REDUCING OPERATOR HOURS


  TO PRODUCE GOODS WITH MINIMUM NUMBER OF OPERATORS
      ADJUSTING TO CHANGING MARKET REQUIREMENTS




   MAKE MACHINES EASY TO MOVE BY ATTACHING CASTORS


STANDARDISE OPERATIONS SO EVERYONE CAN PERFORM THE JOB


TRAIN OPERATORS THROUGH JOB ROTATION TO BE MULTI SKILLED




DO NOT ASSIGN FIXED NUMBER OF OPERATORS TO ANY PROCESS
    IT SHOULD VARY ACCORDING TO PRODUCTION QUANTITY

                                                      TVS-Mysore
JIT FACTORY REVOLUTION
             8       LEVELLING PRODUCTION


       TO PRODUCE THE SAME QUANTITY OF AN ITEM EVERY DAY



       CALCULATE CYCLE TIMES BASED ON MONTHLY VOLUMES


              MAKE CYCLE LIST BASED ON CYCLE TIME


                   SHORTEN CHANGEOVER TIMES


                      CREATE SMOOTH FLOW




INFORMATION & PARTS ARE DELIVERED TO THE LINE SEVERAL TIMES DAILY

                                                           TVS-Mysore
JIT FACTORY REVOLUTION
                    LINE CYCLE TIME =       4.8 min / UNIT
                    WORK TIME       =       480 min / DAY
MONTHLY REQUIRED        -       X       =        1000
                                Y       =         600
                                Z       =         400
                                                 2000

MONTHLY PRODUCTION SCHEDULE X           =        50 / DAY
(20 WORKING DAYS)               Y       =        30 / DAY
                                Z       =        20 / DAY

DAILY PRODUCTION SCHEDULE       X       =        50 - 08:00 - 12:00
                                Y       =        30 - 12:30 - 15:00
                                Z       =        20 - 15:00 - 16:30

LEVELLED PRODUCTION             X       =        50 - ONE IN 9.6 min
                                Y       =        30 - ONE IN 16 min
                                Z       =        20 - ONE IN 24 min
                                                                       TVS-Mysore
JIT FACTORY REVOLUTION
                          SEQUENCING OF PARTS FOR LEVELLED PRODUCTION



      X - ONE IN 9.6 MINUTES                                         Y - ONE IN 16 MINUTES                                        Z - ONE IN 24 MINUTES



Z      X     Y      X      Y      X         Z    X      Y      X      Y    X      Z      X      Y      X      Y      X      Z      X     Y    X     Y     X     Z




4.8   4.8   4.8    4.8    4.8    4.8    4.8     4.8    4.8    4.8    4.8   4.8   4.8    4.8    4.8    4.8    4.8    4.8    4.8    4.8   4.8   4.8   4.8   4.8   4.8

4.8   9.6   14.4   19.2   24.0   28.8   33.6    38.4   43.2   48.0   52.8 57.6   62.4   67.2   72.0   76.8   81.6   86.4   91.2   96.0 100.8 105.6 110.4 115.2 120.0




      At the end of 480 minutes X                50
                                        Y        33
                                        Z        17




                                                                                                                                                TVS-Mysore
JIT FACTORY REVOLUTION
                     9       JIDOKA


             AUTOMATION WITH A HUMAN TOUCH


     AUTONOMATION - AUTOMATIC CONTROL OF DEFECTS


      INSTALL A MECHANISM ( SENSOR) IN THE MACHINE
          THAT PERMITS THEM TO DETECT DEFECTS
                             &
         STOPS THE MACHINE WHEN DEFECTS OCCUR


                         POKA YOKE




MANUAL ----- MECHANISATION ---- AUTOMATION ---- AUTONOMATION

                                                          TVS-Mysore
JIT FACTORY REVOLUTION
                         10       CHANGEOVER

THE TIME BETWEEN THE LAST GOOD PRODUCT OF ONE TYPE TO THE FIRST GOOD
                      PRODUCT OF THE NEXT TYPE


      CHANGEOVER TIME IS THE SUM OF INTERNAL & EXTERNAL TIMES
     INTERNAL - PROCESS MUST BE STOPPED TO PERFORM CHANGEOVER
            EXTERNAL - TIME SPENT WHILE THE PROCESS IS RUNNING

   STEP 1    -       ANALYSE CHANGEOVER
   STEP 2    -       IDENTIFY & ELIMINATE WASTE
   STEP 3    -       MAKE INTERNAL CHANGEOVERS EXTERNAL
   STEP 4    -       IMPROVE INTERNAL CHANGEOVERS
                     (Bolts tighten with one turn, eliminate adjustment…)
   STEP 5    -       IMPROVE EXTERNAL CHANGEOVERS
                     (Use charts, assign workers…..)
                          BOLTS ARE OUR ENEMIES
                                                                            TVS-Mysore
JIT FACTORY REVOLUTION
                 11       QUALITY ASSURANCE

MAINTAINING QUALITY USING OPERATORS, MANUFACTURING SYSTEM DESIGN &
          PRODUCTION METHODS TO SATISFY CUSTOMER NEEDS




STEP 1   -     OPERATOR - Disciplined, well trained & multi skilled


STEP 2   -     MATERIALS - Source control


STEP 3   -     MACHINES - Pokayoke, TEI for safety & maintenance


STEP 4   -     METHOD - Flow manufacturing cells & standard operations


STEP 5   -     INFORMATION - Visual control



                                                                      TVS-Mysore
JIT FACTORY REVOLUTION
                            12      KANBAN
    A TOOL THAT CARRIES INFORMATION TO FACILITATE PRODUCTION CONTROL

RULES
- SUBSEQUENT PROCESS GOES TO FORMER PROCESS FOR PARTS


- FORMER PROCESS PRODUCES QUANTITY REMOVED BY SUBSEQUENT PROCESS


- QUALITY IS BUILT INTO THE PRODUCT - DEFECT NOT SENT TO NEXT PROCESS


- KANBAN ALWAYS ACCOMPANY PRODUCT - VISUAL CONTROL


- PRODUCTION QUANTITIES ARE LEVELLED TO AVOID FLUCTUATIONS


- REDUCING KANBAN REVEALS PLACES WHERE IMPROVEMENTS ARE NEEDED
     PRODUCTION ORDERING KANBAN - WITHDRAWAL / CONVEYANCE KANBAN
                                                                 TVS-Mysore
JIT FACTORY REVOLUTION
13     MAINTENANCE & SAFETY

      3 RULES OF MAINTENANCE


             CLEAN UP
          OIL APPLICATION
               CHECK



         4 RULES OF SAFETY


SEPARATE MACHINES FROM OPERATORS
     FOLLOW SAFETY STANDARDS
           FOLLOW RULES
     FIND REAL CAUSES & PREVENT


                                    TVS-Mysore
HIRANO SAN


GUIDELINES




             TVS-Mysore
HIRANOSAN GUIDELINES



          DREAM




CURRENT




                       TVS-Mysore
HIRANOSAN GUIDELINES


             Use KAIKAKU in place of KAIZEN
    KAIZEN                                    KAIKAKU


(Continuos improvement)                  (Innovation)




              Small change                         Big change
              making better                        Revolution




                                                        TVS-Mysore
HIRANOSAN GUIDELINES


         Use JIT improvement in place of IE improvement
      IE improvement                          JIT improvement


   (inductive approach)                    (deductive approach)


ANALYSIS OF CURRENT CONDITIONS            IDEAL SYSTEM AS GOOD




                   INNOVATION = IN NOVA TION



                       INTO THE NEW STAR = FUTURE
                                                          TVS-Mysore
HIRANOSAN GUIDELINES
           STEPS FOR KAIKAKU

                                  FOREST
                                  (MORI)
STEP : 1




STEP : 2                          SMALL FOREST
                                     (HASHI)




                                  SINGLE TREE
STEP : 3                              (KI)



                                    TVS-Mysore
HIRANOSAN GUIDELINES
                   STEPS FOR KAIKAKU

                                SUPPLIER
               D    C   B   A
           E

STEP : 1                                      AS A WHOLE



           F
               G    H   I   J
                                  CUSTOMER8




               D    C   B   A
           E
STEP : 2                                      IN A CELL
           F




               G    H   I   J




                                              IN A MACHINE
STEP : 3



                                                  TVS-Mysore
HIRANOSAN GUIDELINES

                   Guidelines



* Focus on managament benefit (Watch the forest)
 IE benefit will not be much visible & require
 money (Ki)


* Introduce “Rabbit chase” (including sub assembly)


* Have only one hour stock for process


* Introduce Auto door open & close




                                                      TVS-Mysore
HIRANOSAN GUIDELINES

                Guidelines
* Introduce auto ejection of component


* Introduce auto fixture cleaning


* Have uniform cycle time


* Have single Input / Output point in a machine


* Do not have common machine for two parts in a cell


* Standardize process sign board


* Adhere to 3R (3-regulations)
  1. Name      2. Quantity       3. Location
                                                       TVS-Mysore
HIRANOSAN GUIDELINES

                   Guidelines


* Introduce single piece work flow
 1. Fix the WIP required
 2. No Dango production


* Big sign board
 (nick name should be decided by concerned operators)


* Have KAIKAKU board in cell


* Empty bin should be kept on bottom rack
 (without reversing)



                                                        TVS-Mysore
HIRANOSAN GUIDELINES

                                 Guidelines


* Have separate trolley for “tested ok”&“to be tested”
 (Tsurube concept)


* We must figurise operator movement - operator to be on the move
 (operator should stand only while working)


* Use both hands wherever required


* KIT implementation in engine assy
 (for big parts which require body twist while picking & occupying more space)




                                                                        TVS-Mysore
HIRANOSAN GUIDELINES

                        Guidelines
* Work flow line should be “straight line”
 (3M I - Man, Machine, Material & Information)
   No shoulder movement
   (paper kept under the arm should not fall)
   Loading point should be at elbow level
   No up&down (DEKO BOKA)or zig-zag


* No back tracking


* No return movement without any work
 (Loading & unloading should be done by the same person)




                                                           TVS-Mysore
HIRANOSAN GUIDELINES

               Guidelines




* Implement the KAIKAKU points immediately


  within one day - A rank
  within two days - B rank
  more than two days - C rank


  if it is required to have time more than three days,
  then plan today and have A rank for plan




                                                         TVS-Mysore
HIRANOSAN GUIDELINES
                                MUDA TORI
                           (PROCEDURE TO REMOVE WASTE)


   FOR PRODUCTIVITY TO IMPROVE : NEVER SMALL ISLANDS - ONLY BIG ISLAND

                       A                      B               C

SMALL ISLANDS




BIG ISLAND
                                             ABC
STEP I - HITO ATSUME
OPERATOR GATHER




                                                                  TVS-Mysore
HIRANOSAN GUIDELINES
                            MUDA TORI - contd...
                             (PROCEDURE TO REMOVE WASTE)

                                         AB       BC
STEP II - SHIGOTO ATSUME
VALUE GATHER




STEP III - MUDA ATSUME
WASTE GATHER




STEP IV - SHOUZIN
RESULT


         TOOLCHANGE IN A BIG ISLAND      -        STOP ALL MACHINES AND DO
                                                                     TVS-Mysore
HIRANOSAN GUIDELINES
                                       TSURUBE
                   (Pronounced as THU RU BE, means SUPPLY ONE, RECEIVE ONE)
                                                                              400 Years ago
                                                                                in Japan




IF, IN A CELL, A PART HAS TO GO
OUT FOR AN INTERMEDIATE
OPERATION, FOLLOW TSURUBE
SYSTEM




                                                                                   TVS-Mysore
HIRANOSAN GUIDELINES
              REVERSE FLOW OPERATION OF A CELL
                                    OUT                               IN


SEIJUN - CORRECT SEQUENCING               7   6   5   4   3   2   1
                                                                            MAN
MAN & WORK FLOW IN THE SAME
DIRECTION                                                                   WORK
                                          1   2   3   4   5   6   7


                                    IN                                OUT

                                     IN                               OUT


                                          1   2   3   4   5   6   7
                                                                             MAN
GYAKUJUN - REVERSE SEQUENCING
                                                                            WORK
MAN & WORK FLOW IN OPPOSITE
DIRECTIONS                                1   2   3   4   5   6   7



                   JAPANESE     -    IN   RANK A LINES                OUT
                                                                      TVS-Mysore
HIRANOSAN GUIDELINES
                  DETAILS AT ENTRANCE OF A CELL

CELL NAME BOARD

                                                          WHEEL HUB CELL


                                             R-50
                                                 F-40            R-40
                                     T
                                    R        W AS H              B RO      R&F-3
                                                                                   0
                                                                 ACH      DRILL
                                                                                           0-F
                                                                                            2
CELL LAYOUT                         T
                                    R                                                       RT
                                                                                           NU


                                                                                                    0
                                                                                                 F-1
                                                          R-10          R-20                         RN
                                             P            TURN          TURN
                                                                                       P          TU




                                                        TAKT TIME = 104 SECONDS
TAKT TIME / CYCLE TIME
                                                   CYCLE TIME = 129 SECONDS


    SHOP SIGN BOARD FOR ALL AREAS        -                VCS ON TOP OF BOARDS
                                                                                       TVS-Mysore
HIRANOSAN GUIDELINES
              DETAILS AT ENTRANCE OF A CELL - contd...
MAN MACHINE CHART
       HAND     -


       MACHINE -
       WALKING -
       WAITING -



                                  PROCESS No.       - 10
PROCESS DETAILS                   PROCESS NAME - TURNING & FACING
                                  CYCLE TIME        - 108 SECONDS




OPERATORS NAME &
PHOTO

                                  M1033 - LOKESHA          M1007 - NAGARAJA
                                                                  TVS-Mysore
HIRANOSAN GUIDELINES
                         CELL DESIGN

OPERATOR / PART
FLOW DIRECTION TO
BE ANTICLOCKWISE




                                                              BROAC
                                                               R-40
                                  TR




                                                                          DRILL
                                                                          R&F-30
                                                      R-50
                                       W ASH
                                               F-40
LOCATION FOR




                                                                    H
                                                                                       0-F
                                                                                        2
TROLLIES & PALLETS
                                                                                        RT
                                                                                       NU




                             TR
TO BE CONVENIENT
TO OPERATOR                                                                                     0
                                                                                             F-1
                                                       R-10             R-20                     RN
                                       P                                           P          TU
                                                      TURN              TURN




OPERATOR WALKING
ZONE INSIDE CELL TO BE
MARKED BY WHITE LINE -
FOR FREE MOVEMENT


                                                                                       TVS-Mysore
HIRANOSAN GUIDELINES
                        CELL DESIGN

            OPERATOR HAND MOVEMENT TO BE AS A FLOW
           NO BACK TRACKING / NO SHOULDER MOVEMENT




OPERATOR EYE LEVEL TO BE MAINTAINED AT SAME LEVEL WITHIN THE CELL




  PROVIDE REMIDER TOKENS FOR OPERATORS TO USE DURING BREAKS




                                                           TVS-Mysore
HIRANOSAN GUIDELINES
                        CELL DESIGN - contd...

FLOW DIRECTION TO
BE MARKED ON
CHUTES




         DENOTE PROCESS TIMES IN SECONDS & SETUP TIMES IN MINUTES




         GAUGES TO BE KEPT ON THE MACHINE - NOT ON GAUGE STANDS




                                                               TVS-Mysore
HIRANOSAN GUIDELINES
               CELL DESIGN - contd...

          MACHINES TO BE CLOSE TO EACH OTHER


- BRING CHECK POINTS TO REAR OR FRONT OF MACHINE
- MAKE ACCESSORIES BEHIND THE MACHINE EASILY MOVABLE
- AS A LAST OPTION MOVE MACHINES APART




           DO NOT HAVE SNAKES ON THE FLOOR
                      LOOSE WIRES


                                                       TVS-Mysore
HIRANOSAN GUIDELINES
                         CELL DESIGN - contd...


PROVIDE TAB SWITCH FOR CYCLE START




PROVIDE AUTO UNCLAMP & AUTO UNLOADING
IT IS CHEAPER TO AUTOMATE UNLOADING THAN LOADING
eg: NET TO CATCH PART WHEN CHUCK IS OPENED / EJECTOR IN
THE FIXTURE WITH CHUTE TO BRING PART OUT




                                                          TVS-Mysore
HIRANOSAN GUIDELINES
                        CELL DESIGN - contd...

AT EACH MACHINE OPERATOR TO LOAD PART, PICK UNLOADED PART & HIT TAB SWITCH
                      AS HE MOVES TO NEXT MACHINE




          OPERATOR TO OPERATE ALL MACHINES - MPO - RABBIT CHASE


       OPERATOR NOT TO WATCH THE MACHINE - MAN MACHINE SEPARATE

                                                                  TVS-Mysore
HIRANOSAN GUIDELINES
                 CELL DESIGN - contd...


       PROVIDE WIRE IN FRONT OF MACHINES TO HANG VCS




       PROVIDE PROPER ILLUMINATION TO INSIDE OF CELL




HAVE ALL DETAILS DISPLAYED RATHER THAN IN FILES - OPEN SYSTEM




        MONITOR PRODUCTIVITY OF CELL - OUTPUT / MAN
                                                         TVS-Mysore
HIRANOSAN GUIDELINES
                           TYPES OF CELLS

U LINE




W LINE



T LINE



PLUS LINE



FLOWER LINE


    HAVE SIGNAL AT CENTER TO INDICATE TO OPERATOR WHICH CELL TO OPERATE
                                                                TVS-Mysore
HIRANOSAN GUIDELINES
                                 ASSEMBLY
                                 OPERATION TIME
BALANCING RATIO =                                          x 100
                         TAKT TIME x TOTAL No. OF STAGES



LOSS RATIO = 100 - BALANCING RATIO



       MARK LINE ON CONVEYOR TO INDICATE START OF WORK FOR OPERATOR
    TIME BETWEEN STOP OF WORK & COINCIDING OF LINE IS SLACK IN THAT STAGE
                         WAITING MUDA WILL BE VISIBLE




       MARK IN & OUT ON SUPERMARKET STANDS TO INDICATE FLOW OF PARTS



                                                                   TVS-Mysore
HIRANOSAN GUIDELINES
                ANDONS
                             AAASDASDKRWQEOF
                             EMPTY          FULL
                              KJFSDKLJKFASD4


TAXI ANDON
SEPARATION




HIRE ANDON                        ROW A          ROW B
CONCENTRATION                 1     2   3    4     5     6

                              7    8    9    10   11   12

                              13 14 15       16 17 18




                                            TVS-Mysore
HIRANOSAN GUIDELINES
                             ANDONS




ALL ANDONS TO BE OF          TSL                        TSL
                      TC20         TC30          TC20         TC30
THE SAME ORDER




ALL ANDONS TO BE OF
THE SAME HEIGHT -
VISIBLE FROM
GANGWAY                      TSL                        TSL
                      TC20         TC30          TC20         TC30




                      PET BOTTLES - LOW COST
                                                          TVS-Mysore
HIRANOSAN GUIDELINES
             THREE REGULATION FOR KEEPING PARTS

                                                                  Bolts
1 - PROVIDE LOCATION




2 - PROVIDE IDENTIFICATION / NAME BOARD

                                                                  Bolts
                                                                   4
                                                                 Pallets
                                                                 1000x4

3 - SPECIFY QUANTITY




      SPECIFY INVENTORY OF MATERIAL IN DAYS - INVENTORY OF WIP IN HOURS
                                                                  TVS-Mysore
HIRANOSAN GUIDELINES
                        STORAGE OF PARTS



DO NOT KEEP PARTS ABOVE EYE LEVEL




DO NOT KEEP PARTS BELOW KNEE LEVEL




                                                TVS-Mysore
HIRANOSAN GUIDELINES
                               YELLOW LINE


YELLOW LINE IS A WALL
CANNOT / DO NOT CROSS IT




MARK TIGER LINE FOR CROSSING
YELLOW LINE - MEN & MATERIAL




                                                    TVS-Mysore
HIRANOSAN GUIDELINES
                             YELLOW LINE


PROVIDE CHAMFERS AT
CORNERS OF GANGWAYS




MARK ARROWS ON GANGWAYS TO
SHOW WALKING DIRECTION                                    O
                                                          P
                                                          S
                                                          T




                                            STOP
MARK “STOP” SIGN AT
INTERSECTIONS OF GANGWAYS




       AVOID PROTRUSIONS INTO THE GANGWAY - YELLOW LINE IS A WALL

                                                              TVS-Mysore
HIRANOSAN GUIDELINES
                 KAIKAKU MEASURES
* Productivity     - In terms of out/shift


* Inventory        - Total WIP


* Lead time         - Time to convert raw material to finish


* Walking distance - In terms of steps/cycle


* Operators        - In numbers


* Cycle time       - Rhythm at which product comes out


* Takt time       - Available time in sec / (qty. to be supplied)
                    (does not include allowance)
                                                                    TVS-Mysore
HIRANOSAN GUIDELINES

       Implement “Self KAIKAKU”



* Understand JITs 10 commandments


* Understand Hiranosan’s guidelines


* Conduct audit assuming yourself as Hiranosan


* Follow the KAIKAKU steps




                                                 TVS-Mysore
BIG ISLAND -         WHEEL HUB & PANEL



OUTPUT (Scooty & Spectra)      -    600 / day in 2 shifts




                                                  TVS-Mysore
TVS-Mysore

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (20)

5-Why Training
5-Why Training5-Why Training
5-Why Training
 
Kaizen & Small Group Activities
Kaizen & Small Group ActivitiesKaizen & Small Group Activities
Kaizen & Small Group Activities
 
Toyota production system
Toyota production systemToyota production system
Toyota production system
 
Toyota production system
Toyota production systemToyota production system
Toyota production system
 
Lean Manufacturing
Lean ManufacturingLean Manufacturing
Lean Manufacturing
 
Lean Standard or Standardized Work Training Module
Lean Standard or Standardized Work Training ModuleLean Standard or Standardized Work Training Module
Lean Standard or Standardized Work Training Module
 
Oee Explained
Oee ExplainedOee Explained
Oee Explained
 
Webinar on Daily Work Management
Webinar on Daily Work ManagementWebinar on Daily Work Management
Webinar on Daily Work Management
 
5 Steps to implementing Lean
5  Steps to implementing Lean5  Steps to implementing Lean
5 Steps to implementing Lean
 
Overall Equipment Effectiveness
Overall Equipment EffectivenessOverall Equipment Effectiveness
Overall Equipment Effectiveness
 
History of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 PrincipalHistory of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 Principal
 
Jishu hozen
Jishu  hozenJishu  hozen
Jishu hozen
 
The mystery of OEE
The mystery of OEEThe mystery of OEE
The mystery of OEE
 
Toyota Production System
Toyota Production SystemToyota Production System
Toyota Production System
 
Kaizen Ppt
Kaizen PptKaizen Ppt
Kaizen Ppt
 
The Toyota Way
The Toyota WayThe Toyota Way
The Toyota Way
 
The Seven Wastes
The Seven WastesThe Seven Wastes
The Seven Wastes
 
Toyota Production System
Toyota Production SystemToyota Production System
Toyota Production System
 
OFFICE TPM PPT
OFFICE TPM PPTOFFICE TPM PPT
OFFICE TPM PPT
 
Mark Graban - Kaizen Presentation for Spain
Mark Graban - Kaizen Presentation for SpainMark Graban - Kaizen Presentation for Spain
Mark Graban - Kaizen Presentation for Spain
 

Andere mochten auch

AIBS + NOIDA + OSCM + ASHISH + ANUJ MEHTA + TVS MOTORS
AIBS + NOIDA + OSCM + ASHISH + ANUJ MEHTA + TVS MOTORSAIBS + NOIDA + OSCM + ASHISH + ANUJ MEHTA + TVS MOTORS
AIBS + NOIDA + OSCM + ASHISH + ANUJ MEHTA + TVS MOTORSguest620314
 
Jit principles
Jit principlesJit principles
Jit principlesamarshelke
 
TVS Case Study
TVS Case StudyTVS Case Study
TVS Case Studyjyoraji
 
Lean Manufacturing - Manufactura Esbelta
Lean Manufacturing - Manufactura EsbeltaLean Manufacturing - Manufactura Esbelta
Lean Manufacturing - Manufactura EsbeltaBOM Consulting Group
 

Andere mochten auch (6)

AIBS + NOIDA + OSCM + ASHISH + ANUJ MEHTA + TVS MOTORS
AIBS + NOIDA + OSCM + ASHISH + ANUJ MEHTA + TVS MOTORSAIBS + NOIDA + OSCM + ASHISH + ANUJ MEHTA + TVS MOTORS
AIBS + NOIDA + OSCM + ASHISH + ANUJ MEHTA + TVS MOTORS
 
Jit principles
Jit principlesJit principles
Jit principles
 
Operation management problems
Operation management problemsOperation management problems
Operation management problems
 
TVS Case Study
TVS Case StudyTVS Case Study
TVS Case Study
 
Lean Manufacturing - Manufactura Esbelta
Lean Manufacturing - Manufactura EsbeltaLean Manufacturing - Manufactura Esbelta
Lean Manufacturing - Manufactura Esbelta
 
Tvs motors
Tvs motors Tvs motors
Tvs motors
 

Ähnlich wie JIT

Greentex indonesia utama lean implementation
Greentex indonesia utama lean implementationGreentex indonesia utama lean implementation
Greentex indonesia utama lean implementationAji Wijaya Kusuma
 
Agile in highly regulated environments
Agile in highly regulated environmentsAgile in highly regulated environments
Agile in highly regulated environmentsValtech UK
 
Operations management takira motors
Operations management takira motorsOperations management takira motors
Operations management takira motorsShrey Agarwal
 
APPLICATION OF LEAN PRACTICES FOR IDENTIFICATION OF SOLUTIONS IN REDUCING FUR...
APPLICATION OF LEAN PRACTICES FOR IDENTIFICATION OF SOLUTIONS IN REDUCING FUR...APPLICATION OF LEAN PRACTICES FOR IDENTIFICATION OF SOLUTIONS IN REDUCING FUR...
APPLICATION OF LEAN PRACTICES FOR IDENTIFICATION OF SOLUTIONS IN REDUCING FUR...IRJET Journal
 
Operation management
Operation management   Operation management
Operation management Nevedida
 
Ifs kaizen costing and value analysis
Ifs kaizen costing and value analysisIfs kaizen costing and value analysis
Ifs kaizen costing and value analysismanucprince
 
Safety Expectations of a Site Leader
Safety Expectations of a Site LeaderSafety Expectations of a Site Leader
Safety Expectations of a Site LeaderStephen_Forster
 

Ähnlich wie JIT (20)

Greentex indonesia utama lean implementation
Greentex indonesia utama lean implementationGreentex indonesia utama lean implementation
Greentex indonesia utama lean implementation
 
J I T
J I TJ I T
J I T
 
5 Steps Kaizen
5 Steps Kaizen5 Steps Kaizen
5 Steps Kaizen
 
Kaizen training
Kaizen trainingKaizen training
Kaizen training
 
What is-six-sigma
What is-six-sigmaWhat is-six-sigma
What is-six-sigma
 
NG BB 17 Takt Time
NG BB 17 Takt TimeNG BB 17 Takt Time
NG BB 17 Takt Time
 
Agile in highly regulated environments
Agile in highly regulated environmentsAgile in highly regulated environments
Agile in highly regulated environments
 
KAIZEN
KAIZENKAIZEN
KAIZEN
 
Pulljit Sample
Pulljit SamplePulljit Sample
Pulljit Sample
 
PullJIT_sample-1
PullJIT_sample-1PullJIT_sample-1
PullJIT_sample-1
 
Spc training[1]
Spc training[1]Spc training[1]
Spc training[1]
 
Spc training[1]
Spc training[1]Spc training[1]
Spc training[1]
 
Operations management takira motors
Operations management takira motorsOperations management takira motors
Operations management takira motors
 
APPLICATION OF LEAN PRACTICES FOR IDENTIFICATION OF SOLUTIONS IN REDUCING FUR...
APPLICATION OF LEAN PRACTICES FOR IDENTIFICATION OF SOLUTIONS IN REDUCING FUR...APPLICATION OF LEAN PRACTICES FOR IDENTIFICATION OF SOLUTIONS IN REDUCING FUR...
APPLICATION OF LEAN PRACTICES FOR IDENTIFICATION OF SOLUTIONS IN REDUCING FUR...
 
Operation management
Operation management   Operation management
Operation management
 
Tpm
Tpm Tpm
Tpm
 
Tpm
Tpm Tpm
Tpm
 
Ifs kaizen costing and value analysis
Ifs kaizen costing and value analysisIfs kaizen costing and value analysis
Ifs kaizen costing and value analysis
 
What is-six-sigma69
What is-six-sigma69What is-six-sigma69
What is-six-sigma69
 
Safety Expectations of a Site Leader
Safety Expectations of a Site LeaderSafety Expectations of a Site Leader
Safety Expectations of a Site Leader
 

Kürzlich hochgeladen

How To Fix Mercedes Benz Anti-Theft Protection Activation Issue
How To Fix Mercedes Benz Anti-Theft Protection Activation IssueHow To Fix Mercedes Benz Anti-Theft Protection Activation Issue
How To Fix Mercedes Benz Anti-Theft Protection Activation IssueTerry Sayther Automotive
 
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...Delhi Call girls
 
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhi
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhiHauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhi
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhiHot Call Girls In Sector 58 (Noida)
 
FULL ENJOY - 9953040155 Call Girls in Sector 61 | Noida
FULL ENJOY - 9953040155 Call Girls in Sector 61 | NoidaFULL ENJOY - 9953040155 Call Girls in Sector 61 | Noida
FULL ENJOY - 9953040155 Call Girls in Sector 61 | NoidaMalviyaNagarCallGirl
 
Introduction of Basic of Paint Technology
Introduction of Basic of Paint TechnologyIntroduction of Basic of Paint Technology
Introduction of Basic of Paint TechnologyRaghavendraMishra19
 
꧁༒☬ 7042364481 (Call Girl) In Dwarka Delhi Escort Service In Delhi Ncr☬༒꧂
꧁༒☬ 7042364481 (Call Girl) In Dwarka Delhi Escort Service In Delhi Ncr☬༒꧂꧁༒☬ 7042364481 (Call Girl) In Dwarka Delhi Escort Service In Delhi Ncr☬༒꧂
꧁༒☬ 7042364481 (Call Girl) In Dwarka Delhi Escort Service In Delhi Ncr☬༒꧂Hot Call Girls In Sector 58 (Noida)
 
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...Delhi Call girls
 
VIP Russian Call Girls in Jamshedpur Deepika 8250192130 Independent Escort Se...
VIP Russian Call Girls in Jamshedpur Deepika 8250192130 Independent Escort Se...VIP Russian Call Girls in Jamshedpur Deepika 8250192130 Independent Escort Se...
VIP Russian Call Girls in Jamshedpur Deepika 8250192130 Independent Escort Se...Suhani Kapoor
 
BLUE VEHICLES the kids picture show 2024
BLUE VEHICLES the kids picture show 2024BLUE VEHICLES the kids picture show 2024
BLUE VEHICLES the kids picture show 2024AHOhOops1
 
Dubai Call Girls Size E6 (O525547819) Call Girls In Dubai
Dubai Call Girls  Size E6 (O525547819) Call Girls In DubaiDubai Call Girls  Size E6 (O525547819) Call Girls In Dubai
Dubai Call Girls Size E6 (O525547819) Call Girls In Dubaikojalkojal131
 
Innovating Manufacturing with CNC Technology
Innovating Manufacturing with CNC TechnologyInnovating Manufacturing with CNC Technology
Innovating Manufacturing with CNC Technologyquickpartslimitlessm
 
VIP Mumbai Call Girls Thakur village Just Call 9920874524 with A/C Room Cash ...
VIP Mumbai Call Girls Thakur village Just Call 9920874524 with A/C Room Cash ...VIP Mumbai Call Girls Thakur village Just Call 9920874524 with A/C Room Cash ...
VIP Mumbai Call Girls Thakur village Just Call 9920874524 with A/C Room Cash ...Garima Khatri
 
定制(Cantab毕业证书)剑桥大学毕业证成绩单原版一比一
定制(Cantab毕业证书)剑桥大学毕业证成绩单原版一比一定制(Cantab毕业证书)剑桥大学毕业证成绩单原版一比一
定制(Cantab毕业证书)剑桥大学毕业证成绩单原版一比一mjyguplun
 
Vip Hot🥵 Call Girls Delhi Delhi {9711199012} Avni Thakur 🧡😘 High Profile Girls
Vip Hot🥵 Call Girls Delhi Delhi {9711199012} Avni Thakur 🧡😘 High Profile GirlsVip Hot🥵 Call Girls Delhi Delhi {9711199012} Avni Thakur 🧡😘 High Profile Girls
Vip Hot🥵 Call Girls Delhi Delhi {9711199012} Avni Thakur 🧡😘 High Profile Girlsshivangimorya083
 
Alina 7042364481 Call Girls Service Pochanpur Colony - independent Pochanpur ...
Alina 7042364481 Call Girls Service Pochanpur Colony - independent Pochanpur ...Alina 7042364481 Call Girls Service Pochanpur Colony - independent Pochanpur ...
Alina 7042364481 Call Girls Service Pochanpur Colony - independent Pochanpur ...Hot Call Girls In Sector 58 (Noida)
 
(COD) ̄Young Call Girls In Dwarka , New Delhi꧁❤ 7042364481❤꧂ Escorts Service i...
(COD) ̄Young Call Girls In Dwarka , New Delhi꧁❤ 7042364481❤꧂ Escorts Service i...(COD) ̄Young Call Girls In Dwarka , New Delhi꧁❤ 7042364481❤꧂ Escorts Service i...
(COD) ̄Young Call Girls In Dwarka , New Delhi꧁❤ 7042364481❤꧂ Escorts Service i...Hot Call Girls In Sector 58 (Noida)
 
Call me @ 9892124323 Call Girl in Andheri East With Free Home Delivery
Call me @ 9892124323 Call Girl in Andheri East With Free Home DeliveryCall me @ 9892124323 Call Girl in Andheri East With Free Home Delivery
Call me @ 9892124323 Call Girl in Andheri East With Free Home DeliveryPooja Nehwal
 

Kürzlich hochgeladen (20)

How To Fix Mercedes Benz Anti-Theft Protection Activation Issue
How To Fix Mercedes Benz Anti-Theft Protection Activation IssueHow To Fix Mercedes Benz Anti-Theft Protection Activation Issue
How To Fix Mercedes Benz Anti-Theft Protection Activation Issue
 
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...
 
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhi
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhiHauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhi
Hauz Khas Call Girls ☎ 7042364481 independent Escorts Service in delhi
 
FULL ENJOY - 9953040155 Call Girls in Sector 61 | Noida
FULL ENJOY - 9953040155 Call Girls in Sector 61 | NoidaFULL ENJOY - 9953040155 Call Girls in Sector 61 | Noida
FULL ENJOY - 9953040155 Call Girls in Sector 61 | Noida
 
Introduction of Basic of Paint Technology
Introduction of Basic of Paint TechnologyIntroduction of Basic of Paint Technology
Introduction of Basic of Paint Technology
 
꧁༒☬ 7042364481 (Call Girl) In Dwarka Delhi Escort Service In Delhi Ncr☬༒꧂
꧁༒☬ 7042364481 (Call Girl) In Dwarka Delhi Escort Service In Delhi Ncr☬༒꧂꧁༒☬ 7042364481 (Call Girl) In Dwarka Delhi Escort Service In Delhi Ncr☬༒꧂
꧁༒☬ 7042364481 (Call Girl) In Dwarka Delhi Escort Service In Delhi Ncr☬༒꧂
 
Call Girls In Kirti Nagar 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
Call Girls In Kirti Nagar 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICECall Girls In Kirti Nagar 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
Call Girls In Kirti Nagar 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
 
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...
Call Girls in Malviya Nagar Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts Ser...
 
Hotel Escorts Sushant Golf City - 9548273370 Call Girls Service in Lucknow, c...
Hotel Escorts Sushant Golf City - 9548273370 Call Girls Service in Lucknow, c...Hotel Escorts Sushant Golf City - 9548273370 Call Girls Service in Lucknow, c...
Hotel Escorts Sushant Golf City - 9548273370 Call Girls Service in Lucknow, c...
 
Call Girls in Shri Niwas Puri Delhi 💯Call Us 🔝9953056974🔝
Call Girls in  Shri Niwas Puri  Delhi 💯Call Us 🔝9953056974🔝Call Girls in  Shri Niwas Puri  Delhi 💯Call Us 🔝9953056974🔝
Call Girls in Shri Niwas Puri Delhi 💯Call Us 🔝9953056974🔝
 
VIP Russian Call Girls in Jamshedpur Deepika 8250192130 Independent Escort Se...
VIP Russian Call Girls in Jamshedpur Deepika 8250192130 Independent Escort Se...VIP Russian Call Girls in Jamshedpur Deepika 8250192130 Independent Escort Se...
VIP Russian Call Girls in Jamshedpur Deepika 8250192130 Independent Escort Se...
 
BLUE VEHICLES the kids picture show 2024
BLUE VEHICLES the kids picture show 2024BLUE VEHICLES the kids picture show 2024
BLUE VEHICLES the kids picture show 2024
 
Dubai Call Girls Size E6 (O525547819) Call Girls In Dubai
Dubai Call Girls  Size E6 (O525547819) Call Girls In DubaiDubai Call Girls  Size E6 (O525547819) Call Girls In Dubai
Dubai Call Girls Size E6 (O525547819) Call Girls In Dubai
 
Innovating Manufacturing with CNC Technology
Innovating Manufacturing with CNC TechnologyInnovating Manufacturing with CNC Technology
Innovating Manufacturing with CNC Technology
 
VIP Mumbai Call Girls Thakur village Just Call 9920874524 with A/C Room Cash ...
VIP Mumbai Call Girls Thakur village Just Call 9920874524 with A/C Room Cash ...VIP Mumbai Call Girls Thakur village Just Call 9920874524 with A/C Room Cash ...
VIP Mumbai Call Girls Thakur village Just Call 9920874524 with A/C Room Cash ...
 
定制(Cantab毕业证书)剑桥大学毕业证成绩单原版一比一
定制(Cantab毕业证书)剑桥大学毕业证成绩单原版一比一定制(Cantab毕业证书)剑桥大学毕业证成绩单原版一比一
定制(Cantab毕业证书)剑桥大学毕业证成绩单原版一比一
 
Vip Hot🥵 Call Girls Delhi Delhi {9711199012} Avni Thakur 🧡😘 High Profile Girls
Vip Hot🥵 Call Girls Delhi Delhi {9711199012} Avni Thakur 🧡😘 High Profile GirlsVip Hot🥵 Call Girls Delhi Delhi {9711199012} Avni Thakur 🧡😘 High Profile Girls
Vip Hot🥵 Call Girls Delhi Delhi {9711199012} Avni Thakur 🧡😘 High Profile Girls
 
Alina 7042364481 Call Girls Service Pochanpur Colony - independent Pochanpur ...
Alina 7042364481 Call Girls Service Pochanpur Colony - independent Pochanpur ...Alina 7042364481 Call Girls Service Pochanpur Colony - independent Pochanpur ...
Alina 7042364481 Call Girls Service Pochanpur Colony - independent Pochanpur ...
 
(COD) ̄Young Call Girls In Dwarka , New Delhi꧁❤ 7042364481❤꧂ Escorts Service i...
(COD) ̄Young Call Girls In Dwarka , New Delhi꧁❤ 7042364481❤꧂ Escorts Service i...(COD) ̄Young Call Girls In Dwarka , New Delhi꧁❤ 7042364481❤꧂ Escorts Service i...
(COD) ̄Young Call Girls In Dwarka , New Delhi꧁❤ 7042364481❤꧂ Escorts Service i...
 
Call me @ 9892124323 Call Girl in Andheri East With Free Home Delivery
Call me @ 9892124323 Call Girl in Andheri East With Free Home DeliveryCall me @ 9892124323 Call Girl in Andheri East With Free Home Delivery
Call me @ 9892124323 Call Girl in Andheri East With Free Home Delivery
 

JIT

  • 1. TIME - TWO HOURS TVS-Mysore
  • 2. ABOUT HIRANO SAN Full name - Mr HIROYUKI HIRANO Author of - JUST IN TIME - FACTORY REVOLUTION Consultant on - JIT PREACHES & PRACTICES INNOVATION TVS-Mysore
  • 3. JIT FACTORY REVOLTUION BY Mr HIROYUKI HIRANO TVS-Mysore
  • 4. JIT FACTORY REVOLUTION STEPS IN IMPLEMENTING JIT PRODUCTION JUST IN TIME STEP 5 MANPOWER REDUCTION JIDOKA-HUMAN AUTOMATION MAINTENANCE & SAFETY STANDARDISED OPERATIONS VISUAL CONTROL STEP 4 CHANGEOVER QUALITY ASSURANCE LEVELLING STEP 3 MULTI -PROCESS OPERATIONS KANBAN FLOW MANUFACTURING STEP 2 5S STEP 1 AWARENESS REVOLUTION TVS-Mysore
  • 5. JIT FACTORY REVOLUTION TOPICS 1 INTRODUCTION 2 AWARENESS REVOLUTION 3 5S 4 FLOW MANUFACTURING 5 STANDARD OPERATIONS 6 MULTI PROCESS HANDLING 7 REDUCING WORKER HOURS 8 LEVELLING PRODUCTION 9 JIDOKA 10 CHANGEOVER 11 QUALITY ASSURANCE 12 KANBAN 13 MAINTENANCE & SAFETY TVS-Mysore
  • 6. JIT FACTORY REVOLUTION 1 INTRODUCTION CELL SHOULD BE FLEXIBLE FLEXIBILITY TO ADAPT TO CHANGES IN DEMAND, PRODUCT MIX & PRODUCT DESIGN WITHIN CELL - ONE PIECE FLOW - REDUCED SETUP TIME - IMPROVED M/Cs TO INFORM OPERATORS ABOUT PROBLEMS - MEASURES TO PREVENT DEFECTS & BREAKDOWNS BETWEEN CELLS - SMALL LOTS - UNIFORM SIZE - KANBAN - PULL CONTROL “JIT MEANS TRIMMING LOSSES - AN ORDEAL FOR SURVIVAL” TVS-Mysore
  • 7. JIT FACTORY REVOLUTION 2 AWARENESS REVOLUTION ASSUME CURRENT PRODUCTION SYSTEM IS THE WORST CHANGE IN THE WAY OF THINKING INSTALL NEW CORPORATE CULTURE OPERATORS TO LEARN NEW METHODS - TRAINING HAVE CLEAR POLICIES FOR RESISITANCE TVS-Mysore
  • 8. JIT FACTORY REVOLUTION TEN COMMANDMENTS OF INNOVATION 1 - DISCARD FIXED IDEAS 2 - THINK HOW IT CAN BE DONE THAN, HOW IT WON’T 3 - DENY STATUS QUO 4 - DON’T SEEK PERFECTION 5 - CORRECT MISTAKES AS SOON AS THEY ARE FOUND 6 - INNOVATION NEEDS NO MONEY 7 - PROBLEMS ARE OPPORTUNITIES TO USE OUR BRAINS 8 - ASK WHY 5 TIMES 9 - IDEAS OF 10 ARE BETTER THAN KNOWLEDGE OF 1 10 - INNOVATION NEVER ENDS TVS-Mysore
  • 9. JIT FACTORY REVOLUTION INNOVATION CYCLE ACT PLAN IMPROVEMENT CYCLE KAIZEN CHECK DO AC T T RGE TA INNOVATION CYCLE VISION / CHECK IMAGE PICTURE / KAIKAKU DREAM PL DO AN TVS-Mysore
  • 10. JIT FACTORY REVOLUTION 3 5S SEIRI - PROPER ARRANGEMENT SEITON - ORDERLINESS SEISO - CLEANLINESS SEIKITSU - CLEANUP SHITSUKE - DISCIPLINE WE ARE BEHIND TIMES IF WE STILL SWEEP THE FLOORS TVS-Mysore
  • 11. JIT FACTORY REVOLUTION 4 FLOW MANUFACTURING PRODUCING ONE PIECE AT A TIME CYCLE TIME IS THE TIME IT TAKES TO CARRY ONE PART ALL THE WAY THROUGH THE CELL WORKING HOURS / DAY TAKT TIME = DAILY RATE MONTHLY QUANTITY REQUIRED DAILY RATE = WORKING DAYS PER MONTH MULTI PROCESS HANDLING & SMALL INLINE MACHINES TVS-Mysore
  • 12. JIT FACTORY REVOLUTION 5 STANDARD OPERATIONS RULES & METHODS TO PRODUCE QUALITY PRODUCTS, SAFELY & INEXPENSIVELY BY EFFICIENT ARRANGEMENT OF PEOPLE, PRODUCT & MACHINES STANDARD OPERATIONS BULLETINS & MANUALS ON WORK METHODS TVS-Mysore
  • 13. JIT FACTORY REVOLUTION 6 MULTI PROCESS HANDLING ONE OPERATOR HANDLES SEVERAL PROCESS IN A CELL DE-LINEATE JOBS PERFORMED BY MACHINE & OPERATORS (MACHINES CAN WORK INDEPENDENTLY) MAKE CELLS U SHAPED & GIVE MACHINES JIDOKA FUNCTION OPERATORS TO STAND WHILE WORKING TRAIN OPERATORS TO BE MULTI SKILLED FOLLOW RABBIT CHASE - PRODUCTIVITY MAY GO UP TVS-Mysore
  • 14. JIT FACTORY REVOLUTION 7 REDUCING OPERATOR HOURS TO PRODUCE GOODS WITH MINIMUM NUMBER OF OPERATORS ADJUSTING TO CHANGING MARKET REQUIREMENTS MAKE MACHINES EASY TO MOVE BY ATTACHING CASTORS STANDARDISE OPERATIONS SO EVERYONE CAN PERFORM THE JOB TRAIN OPERATORS THROUGH JOB ROTATION TO BE MULTI SKILLED DO NOT ASSIGN FIXED NUMBER OF OPERATORS TO ANY PROCESS IT SHOULD VARY ACCORDING TO PRODUCTION QUANTITY TVS-Mysore
  • 15. JIT FACTORY REVOLUTION 8 LEVELLING PRODUCTION TO PRODUCE THE SAME QUANTITY OF AN ITEM EVERY DAY CALCULATE CYCLE TIMES BASED ON MONTHLY VOLUMES MAKE CYCLE LIST BASED ON CYCLE TIME SHORTEN CHANGEOVER TIMES CREATE SMOOTH FLOW INFORMATION & PARTS ARE DELIVERED TO THE LINE SEVERAL TIMES DAILY TVS-Mysore
  • 16. JIT FACTORY REVOLUTION LINE CYCLE TIME = 4.8 min / UNIT WORK TIME = 480 min / DAY MONTHLY REQUIRED - X = 1000 Y = 600 Z = 400 2000 MONTHLY PRODUCTION SCHEDULE X = 50 / DAY (20 WORKING DAYS) Y = 30 / DAY Z = 20 / DAY DAILY PRODUCTION SCHEDULE X = 50 - 08:00 - 12:00 Y = 30 - 12:30 - 15:00 Z = 20 - 15:00 - 16:30 LEVELLED PRODUCTION X = 50 - ONE IN 9.6 min Y = 30 - ONE IN 16 min Z = 20 - ONE IN 24 min TVS-Mysore
  • 17. JIT FACTORY REVOLUTION SEQUENCING OF PARTS FOR LEVELLED PRODUCTION X - ONE IN 9.6 MINUTES Y - ONE IN 16 MINUTES Z - ONE IN 24 MINUTES Z X Y X Y X Z X Y X Y X Z X Y X Y X Z X Y X Y X Z 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 9.6 14.4 19.2 24.0 28.8 33.6 38.4 43.2 48.0 52.8 57.6 62.4 67.2 72.0 76.8 81.6 86.4 91.2 96.0 100.8 105.6 110.4 115.2 120.0 At the end of 480 minutes X 50 Y 33 Z 17 TVS-Mysore
  • 18. JIT FACTORY REVOLUTION 9 JIDOKA AUTOMATION WITH A HUMAN TOUCH AUTONOMATION - AUTOMATIC CONTROL OF DEFECTS INSTALL A MECHANISM ( SENSOR) IN THE MACHINE THAT PERMITS THEM TO DETECT DEFECTS & STOPS THE MACHINE WHEN DEFECTS OCCUR POKA YOKE MANUAL ----- MECHANISATION ---- AUTOMATION ---- AUTONOMATION TVS-Mysore
  • 19. JIT FACTORY REVOLUTION 10 CHANGEOVER THE TIME BETWEEN THE LAST GOOD PRODUCT OF ONE TYPE TO THE FIRST GOOD PRODUCT OF THE NEXT TYPE CHANGEOVER TIME IS THE SUM OF INTERNAL & EXTERNAL TIMES INTERNAL - PROCESS MUST BE STOPPED TO PERFORM CHANGEOVER EXTERNAL - TIME SPENT WHILE THE PROCESS IS RUNNING STEP 1 - ANALYSE CHANGEOVER STEP 2 - IDENTIFY & ELIMINATE WASTE STEP 3 - MAKE INTERNAL CHANGEOVERS EXTERNAL STEP 4 - IMPROVE INTERNAL CHANGEOVERS (Bolts tighten with one turn, eliminate adjustment…) STEP 5 - IMPROVE EXTERNAL CHANGEOVERS (Use charts, assign workers…..) BOLTS ARE OUR ENEMIES TVS-Mysore
  • 20. JIT FACTORY REVOLUTION 11 QUALITY ASSURANCE MAINTAINING QUALITY USING OPERATORS, MANUFACTURING SYSTEM DESIGN & PRODUCTION METHODS TO SATISFY CUSTOMER NEEDS STEP 1 - OPERATOR - Disciplined, well trained & multi skilled STEP 2 - MATERIALS - Source control STEP 3 - MACHINES - Pokayoke, TEI for safety & maintenance STEP 4 - METHOD - Flow manufacturing cells & standard operations STEP 5 - INFORMATION - Visual control TVS-Mysore
  • 21. JIT FACTORY REVOLUTION 12 KANBAN A TOOL THAT CARRIES INFORMATION TO FACILITATE PRODUCTION CONTROL RULES - SUBSEQUENT PROCESS GOES TO FORMER PROCESS FOR PARTS - FORMER PROCESS PRODUCES QUANTITY REMOVED BY SUBSEQUENT PROCESS - QUALITY IS BUILT INTO THE PRODUCT - DEFECT NOT SENT TO NEXT PROCESS - KANBAN ALWAYS ACCOMPANY PRODUCT - VISUAL CONTROL - PRODUCTION QUANTITIES ARE LEVELLED TO AVOID FLUCTUATIONS - REDUCING KANBAN REVEALS PLACES WHERE IMPROVEMENTS ARE NEEDED PRODUCTION ORDERING KANBAN - WITHDRAWAL / CONVEYANCE KANBAN TVS-Mysore
  • 22. JIT FACTORY REVOLUTION 13 MAINTENANCE & SAFETY 3 RULES OF MAINTENANCE CLEAN UP OIL APPLICATION CHECK 4 RULES OF SAFETY SEPARATE MACHINES FROM OPERATORS FOLLOW SAFETY STANDARDS FOLLOW RULES FIND REAL CAUSES & PREVENT TVS-Mysore
  • 23. HIRANO SAN GUIDELINES TVS-Mysore
  • 24. HIRANOSAN GUIDELINES DREAM CURRENT TVS-Mysore
  • 25. HIRANOSAN GUIDELINES Use KAIKAKU in place of KAIZEN KAIZEN KAIKAKU (Continuos improvement) (Innovation) Small change Big change making better Revolution TVS-Mysore
  • 26. HIRANOSAN GUIDELINES Use JIT improvement in place of IE improvement IE improvement JIT improvement (inductive approach) (deductive approach) ANALYSIS OF CURRENT CONDITIONS IDEAL SYSTEM AS GOOD INNOVATION = IN NOVA TION INTO THE NEW STAR = FUTURE TVS-Mysore
  • 27. HIRANOSAN GUIDELINES STEPS FOR KAIKAKU FOREST (MORI) STEP : 1 STEP : 2 SMALL FOREST (HASHI) SINGLE TREE STEP : 3 (KI) TVS-Mysore
  • 28. HIRANOSAN GUIDELINES STEPS FOR KAIKAKU SUPPLIER D C B A E STEP : 1 AS A WHOLE F G H I J CUSTOMER8 D C B A E STEP : 2 IN A CELL F G H I J IN A MACHINE STEP : 3 TVS-Mysore
  • 29. HIRANOSAN GUIDELINES Guidelines * Focus on managament benefit (Watch the forest) IE benefit will not be much visible & require money (Ki) * Introduce “Rabbit chase” (including sub assembly) * Have only one hour stock for process * Introduce Auto door open & close TVS-Mysore
  • 30. HIRANOSAN GUIDELINES Guidelines * Introduce auto ejection of component * Introduce auto fixture cleaning * Have uniform cycle time * Have single Input / Output point in a machine * Do not have common machine for two parts in a cell * Standardize process sign board * Adhere to 3R (3-regulations) 1. Name 2. Quantity 3. Location TVS-Mysore
  • 31. HIRANOSAN GUIDELINES Guidelines * Introduce single piece work flow 1. Fix the WIP required 2. No Dango production * Big sign board (nick name should be decided by concerned operators) * Have KAIKAKU board in cell * Empty bin should be kept on bottom rack (without reversing) TVS-Mysore
  • 32. HIRANOSAN GUIDELINES Guidelines * Have separate trolley for “tested ok”&“to be tested” (Tsurube concept) * We must figurise operator movement - operator to be on the move (operator should stand only while working) * Use both hands wherever required * KIT implementation in engine assy (for big parts which require body twist while picking & occupying more space) TVS-Mysore
  • 33. HIRANOSAN GUIDELINES Guidelines * Work flow line should be “straight line” (3M I - Man, Machine, Material & Information) No shoulder movement (paper kept under the arm should not fall) Loading point should be at elbow level No up&down (DEKO BOKA)or zig-zag * No back tracking * No return movement without any work (Loading & unloading should be done by the same person) TVS-Mysore
  • 34. HIRANOSAN GUIDELINES Guidelines * Implement the KAIKAKU points immediately within one day - A rank within two days - B rank more than two days - C rank if it is required to have time more than three days, then plan today and have A rank for plan TVS-Mysore
  • 35. HIRANOSAN GUIDELINES MUDA TORI (PROCEDURE TO REMOVE WASTE) FOR PRODUCTIVITY TO IMPROVE : NEVER SMALL ISLANDS - ONLY BIG ISLAND A B C SMALL ISLANDS BIG ISLAND ABC STEP I - HITO ATSUME OPERATOR GATHER TVS-Mysore
  • 36. HIRANOSAN GUIDELINES MUDA TORI - contd... (PROCEDURE TO REMOVE WASTE) AB BC STEP II - SHIGOTO ATSUME VALUE GATHER STEP III - MUDA ATSUME WASTE GATHER STEP IV - SHOUZIN RESULT TOOLCHANGE IN A BIG ISLAND - STOP ALL MACHINES AND DO TVS-Mysore
  • 37. HIRANOSAN GUIDELINES TSURUBE (Pronounced as THU RU BE, means SUPPLY ONE, RECEIVE ONE) 400 Years ago in Japan IF, IN A CELL, A PART HAS TO GO OUT FOR AN INTERMEDIATE OPERATION, FOLLOW TSURUBE SYSTEM TVS-Mysore
  • 38. HIRANOSAN GUIDELINES REVERSE FLOW OPERATION OF A CELL OUT IN SEIJUN - CORRECT SEQUENCING 7 6 5 4 3 2 1 MAN MAN & WORK FLOW IN THE SAME DIRECTION WORK 1 2 3 4 5 6 7 IN OUT IN OUT 1 2 3 4 5 6 7 MAN GYAKUJUN - REVERSE SEQUENCING WORK MAN & WORK FLOW IN OPPOSITE DIRECTIONS 1 2 3 4 5 6 7 JAPANESE - IN RANK A LINES OUT TVS-Mysore
  • 39. HIRANOSAN GUIDELINES DETAILS AT ENTRANCE OF A CELL CELL NAME BOARD WHEEL HUB CELL R-50 F-40 R-40 T R W AS H B RO R&F-3 0 ACH DRILL 0-F 2 CELL LAYOUT T R RT NU 0 F-1 R-10 R-20 RN P TURN TURN P TU TAKT TIME = 104 SECONDS TAKT TIME / CYCLE TIME CYCLE TIME = 129 SECONDS SHOP SIGN BOARD FOR ALL AREAS - VCS ON TOP OF BOARDS TVS-Mysore
  • 40. HIRANOSAN GUIDELINES DETAILS AT ENTRANCE OF A CELL - contd... MAN MACHINE CHART HAND - MACHINE - WALKING - WAITING - PROCESS No. - 10 PROCESS DETAILS PROCESS NAME - TURNING & FACING CYCLE TIME - 108 SECONDS OPERATORS NAME & PHOTO M1033 - LOKESHA M1007 - NAGARAJA TVS-Mysore
  • 41. HIRANOSAN GUIDELINES CELL DESIGN OPERATOR / PART FLOW DIRECTION TO BE ANTICLOCKWISE BROAC R-40 TR DRILL R&F-30 R-50 W ASH F-40 LOCATION FOR H 0-F 2 TROLLIES & PALLETS RT NU TR TO BE CONVENIENT TO OPERATOR 0 F-1 R-10 R-20 RN P P TU TURN TURN OPERATOR WALKING ZONE INSIDE CELL TO BE MARKED BY WHITE LINE - FOR FREE MOVEMENT TVS-Mysore
  • 42. HIRANOSAN GUIDELINES CELL DESIGN OPERATOR HAND MOVEMENT TO BE AS A FLOW NO BACK TRACKING / NO SHOULDER MOVEMENT OPERATOR EYE LEVEL TO BE MAINTAINED AT SAME LEVEL WITHIN THE CELL PROVIDE REMIDER TOKENS FOR OPERATORS TO USE DURING BREAKS TVS-Mysore
  • 43. HIRANOSAN GUIDELINES CELL DESIGN - contd... FLOW DIRECTION TO BE MARKED ON CHUTES DENOTE PROCESS TIMES IN SECONDS & SETUP TIMES IN MINUTES GAUGES TO BE KEPT ON THE MACHINE - NOT ON GAUGE STANDS TVS-Mysore
  • 44. HIRANOSAN GUIDELINES CELL DESIGN - contd... MACHINES TO BE CLOSE TO EACH OTHER - BRING CHECK POINTS TO REAR OR FRONT OF MACHINE - MAKE ACCESSORIES BEHIND THE MACHINE EASILY MOVABLE - AS A LAST OPTION MOVE MACHINES APART DO NOT HAVE SNAKES ON THE FLOOR LOOSE WIRES TVS-Mysore
  • 45. HIRANOSAN GUIDELINES CELL DESIGN - contd... PROVIDE TAB SWITCH FOR CYCLE START PROVIDE AUTO UNCLAMP & AUTO UNLOADING IT IS CHEAPER TO AUTOMATE UNLOADING THAN LOADING eg: NET TO CATCH PART WHEN CHUCK IS OPENED / EJECTOR IN THE FIXTURE WITH CHUTE TO BRING PART OUT TVS-Mysore
  • 46. HIRANOSAN GUIDELINES CELL DESIGN - contd... AT EACH MACHINE OPERATOR TO LOAD PART, PICK UNLOADED PART & HIT TAB SWITCH AS HE MOVES TO NEXT MACHINE OPERATOR TO OPERATE ALL MACHINES - MPO - RABBIT CHASE OPERATOR NOT TO WATCH THE MACHINE - MAN MACHINE SEPARATE TVS-Mysore
  • 47. HIRANOSAN GUIDELINES CELL DESIGN - contd... PROVIDE WIRE IN FRONT OF MACHINES TO HANG VCS PROVIDE PROPER ILLUMINATION TO INSIDE OF CELL HAVE ALL DETAILS DISPLAYED RATHER THAN IN FILES - OPEN SYSTEM MONITOR PRODUCTIVITY OF CELL - OUTPUT / MAN TVS-Mysore
  • 48. HIRANOSAN GUIDELINES TYPES OF CELLS U LINE W LINE T LINE PLUS LINE FLOWER LINE HAVE SIGNAL AT CENTER TO INDICATE TO OPERATOR WHICH CELL TO OPERATE TVS-Mysore
  • 49. HIRANOSAN GUIDELINES ASSEMBLY OPERATION TIME BALANCING RATIO = x 100 TAKT TIME x TOTAL No. OF STAGES LOSS RATIO = 100 - BALANCING RATIO MARK LINE ON CONVEYOR TO INDICATE START OF WORK FOR OPERATOR TIME BETWEEN STOP OF WORK & COINCIDING OF LINE IS SLACK IN THAT STAGE WAITING MUDA WILL BE VISIBLE MARK IN & OUT ON SUPERMARKET STANDS TO INDICATE FLOW OF PARTS TVS-Mysore
  • 50. HIRANOSAN GUIDELINES ANDONS AAASDASDKRWQEOF EMPTY FULL KJFSDKLJKFASD4 TAXI ANDON SEPARATION HIRE ANDON ROW A ROW B CONCENTRATION 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 TVS-Mysore
  • 51. HIRANOSAN GUIDELINES ANDONS ALL ANDONS TO BE OF TSL TSL TC20 TC30 TC20 TC30 THE SAME ORDER ALL ANDONS TO BE OF THE SAME HEIGHT - VISIBLE FROM GANGWAY TSL TSL TC20 TC30 TC20 TC30 PET BOTTLES - LOW COST TVS-Mysore
  • 52. HIRANOSAN GUIDELINES THREE REGULATION FOR KEEPING PARTS Bolts 1 - PROVIDE LOCATION 2 - PROVIDE IDENTIFICATION / NAME BOARD Bolts 4 Pallets 1000x4 3 - SPECIFY QUANTITY SPECIFY INVENTORY OF MATERIAL IN DAYS - INVENTORY OF WIP IN HOURS TVS-Mysore
  • 53. HIRANOSAN GUIDELINES STORAGE OF PARTS DO NOT KEEP PARTS ABOVE EYE LEVEL DO NOT KEEP PARTS BELOW KNEE LEVEL TVS-Mysore
  • 54. HIRANOSAN GUIDELINES YELLOW LINE YELLOW LINE IS A WALL CANNOT / DO NOT CROSS IT MARK TIGER LINE FOR CROSSING YELLOW LINE - MEN & MATERIAL TVS-Mysore
  • 55. HIRANOSAN GUIDELINES YELLOW LINE PROVIDE CHAMFERS AT CORNERS OF GANGWAYS MARK ARROWS ON GANGWAYS TO SHOW WALKING DIRECTION O P S T STOP MARK “STOP” SIGN AT INTERSECTIONS OF GANGWAYS AVOID PROTRUSIONS INTO THE GANGWAY - YELLOW LINE IS A WALL TVS-Mysore
  • 56. HIRANOSAN GUIDELINES KAIKAKU MEASURES * Productivity - In terms of out/shift * Inventory - Total WIP * Lead time - Time to convert raw material to finish * Walking distance - In terms of steps/cycle * Operators - In numbers * Cycle time - Rhythm at which product comes out * Takt time - Available time in sec / (qty. to be supplied) (does not include allowance) TVS-Mysore
  • 57. HIRANOSAN GUIDELINES Implement “Self KAIKAKU” * Understand JITs 10 commandments * Understand Hiranosan’s guidelines * Conduct audit assuming yourself as Hiranosan * Follow the KAIKAKU steps TVS-Mysore
  • 58. BIG ISLAND - WHEEL HUB & PANEL OUTPUT (Scooty & Spectra) - 600 / day in 2 shifts TVS-Mysore