Padma Multipurpose Bridge Project
Presented By
Padma Bridge is one of the most challenging projects in the
world. We are constructing the Bridge on the second
largest river flow in the world. Every second,
approximately 140,000 cubic metre water flows through
the project area. Twenty second flowing of that amount will
be sufficient to meet one day drinking water demand of
Dhaka city. Another challenge is scour depth. We have also
considered earthquake related dangers. That's why we are
using the second most powerful pile hammer in the world
for this project.
Introduction
River training is another challenge. It requires huge amount of
money. Last year there was serious river erosion in the Mawa
area, and as a consequence we had to change our design to
cope with such types of calamities. It might take more than
three years to complete the river training works.
General Information
• Main Bridge (6.15 km long)
• River Training Works(14 km length)
• Janjira Approach Road & Selected Bridge End Facilities (10.5 km
length)
• Mawa Approach Road & Selected Bridge End Facilities (1.5 km
length)
• Land Acquisition: About 1408.54 hectre
Financing
Project cost is estimated to be US$3.00 billion. The Padma
Multipurpose Bridge (PMB) project was designed to be funded by
donors such as the World Bank, Japan International Cooperation
Agency (JICA), Asian Development Bank (ADB) and Islamic
Development Bank (IDB). After a scandal of alleged corruption by
some people associated with project preparation the World Bank
withdrew its commitment and other donors followed. The project
is now being funded from own resources of the Government of
Bangladesh. The state-owned company has constructed structures
like the famous 36 km Hangzhou Bay Bridge, the longest sea-
crossing bridge in the world. Padma Bridge, when commissioned,
will boost the GDP by as much as 1.2 percent.
And the Estimated Project Cost (as per
Final Design) is…
BDT 205072 Million or,
USD 2.972 Billion (Including VAT and IT)
Ministry
Padma Multipurpose Bridge Project.Ministry of Road Transport and
Bridges, Bridges Division, Bangladesh Bridge Authority. The World
Bank initially refused to sanction the proposed loan for
constructing the bridge and imposed conditions for the
continuation of loan talks with the government. In accordance with
one of these conditions Communications Minister Syed Abul
Hossain had to resign, as he was found to be involved in the
corruption.Now Mr. Obaidul Quader, Ministry of Road
Transport & Bridges Government of the People’s Republic of
Bangladesh.
Components of the Project
• Main Bridge
• River Training Works(RTW)
• Janjira Approach Road & Selected
Bridge End Facilities
• Mawa Approach Road & Selected
Bridge End Facilities
• Service Area-2
• Resettlement
• Environment
• Land Acquisition
• CSC(Main Bridge & RTW)
• CSC(Approach Roads & Service
Area-2)
• Engineering Support & Safety
Team(ESST
It will be capable as a gainer of generally people in our economical
society.Because it has created a greatest opportunity for inter communication
with other areas of our country.It will save the wasting time of people.People will
be able to connect easily with their peer.It will save their valuable time.As we
know journey by bus or car is easier then train or ship.In business perspective,
industrial and agriculture products are so much benificial for digital
market.Basically many products creat in Dhaka.For transferring these products
to rural area, the bridge is needed urgently. It will also help people for making
interpersonal relationship.
Impacts on Society
Project Impacts
Total land acquired 1,100 ha
Total AHs – 15,261 (80,000 persons)
Close to 5,000 households to be
relocated
3,000 hhs preferred “self relocation”
2,000 hhs to project Resettlement
Sites
Removal of trees and vegetation
Disturbance of aquatic wildlife
Hilsa and other catches
Migratory birds
After 3 years relocated families are stay on rehabilitation center. They are almost
happy their. But some people says they are not proper happy and they have some
dissatisfaction. Example :
SahadatHossen, a resident of rehabilitation site no 1 at Kumarbhog , would be
one of those who would have to leave his ancestral home.But he said he would be
happy to vacate his land for building the bridge in national interest.
By facilitating transportation across the river, the Padma Bridge is expected lead
to the greater integration of regional markets within the Bangladeshi national
economy. On the basis of their suitability of capture primary and secondary
economic impacts of construction project, three different types of economy wide
models are employed in addition to traditional traffic model to capture the total
and economy wide impacts of Padma Bridge.
Economic Aspect
of Padma Bridge
Economic Aspect
of Padma Bridge
What is EIA?
• Environmental Impact Assessment (EIA) is the process by which the anticipated
effects on the environment of a proposed development or project are
measured. If the likely effects are unacceptable, design measures or other
relevant mitigation measures can be taken to reduce or avoid those effects.
• The document from this process is called an Environmental Impact Statement
(EIS).
Environmental Impacts of Padma Bridge
• About 295,072 trees loss (Excluding 485,074 bamboo and banana trees)
• Crops 24,684 tons
• Loss of fish breeding area about 767 ha, 12 ha fishing ponds will be filled up, etc.
• Generate about 50 Million cubic meter dredge material from the river
• Traffic congestion, safety hazards, noise pollution, sanitation, health and
hygiene, waste generation etc.
Conclusions
Around 39% construction work of the 6.15-kilometre-long two-tier Padma
Multipurpose Bridge has been completed.The China Major Bridge Engineering
Corporation (MBEC), which was appointed for the main bridge, will carry out
the work. The soil testing and dredging works have been going on for the last
four months for the river training.The bridge will have a total of 42 pillars. Each
will have six piles beneath. Steel spans will be placed on the pillars. The bridge
will have a total of 41 spans. According to work plan: November 2014 . Now a
days The Project Progress : 40.50% .Work end date according to work plan:
November 2018
Padma Brige Project 2017 Slide

Weitere ähnliche Inhalte

Was ist angesagt?

Presentation about Padma Bridge.pptx
Presentation about Padma Bridge.pptxPresentation about Padma Bridge.pptx
Presentation about Padma Bridge.pptxMdAbiAbdullah1
 
Metro Rail in Dhaka City
Metro Rail in Dhaka CityMetro Rail in Dhaka City
Metro Rail in Dhaka CityAriful Islam
 
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goals
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goalsPADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goals
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goalsSajal Eahsan
 
Analysis and Review of EIA of Padma Multipurpose Bridge Project in Bangladesh
Analysis and Review of EIA of Padma Multipurpose Bridge Project in BangladeshAnalysis and Review of EIA of Padma Multipurpose Bridge Project in Bangladesh
Analysis and Review of EIA of Padma Multipurpose Bridge Project in BangladeshRituSaha3
 
Metro rail in Dhaka city
Metro rail in Dhaka cityMetro rail in Dhaka city
Metro rail in Dhaka cityHusnul Abid
 
Inland water transportation (IWT) of Bangladesh: Container perspective.
Inland water transportation (IWT) of Bangladesh: Container perspective.Inland water transportation (IWT) of Bangladesh: Container perspective.
Inland water transportation (IWT) of Bangladesh: Container perspective.Mostafa Shaheen
 
Presentation for Dhaka Metro Rail.pptx
Presentation for Dhaka Metro Rail.pptxPresentation for Dhaka Metro Rail.pptx
Presentation for Dhaka Metro Rail.pptxSabujMahmud2
 
Recent infrastructural development in bangladesh and it’s impact on economy
Recent infrastructural development in bangladesh and it’s impact on economyRecent infrastructural development in bangladesh and it’s impact on economy
Recent infrastructural development in bangladesh and it’s impact on economyTanu Kirttania
 
Karnaphuli Tunnel presentation.
Karnaphuli Tunnel presentation.Karnaphuli Tunnel presentation.
Karnaphuli Tunnel presentation.Ali Ahamed
 
History of road in Nepal
History of road in NepalHistory of road in Nepal
History of road in Nepalpnbastola
 
Training report of road construction
Training report of road constructionTraining report of road construction
Training report of road constructionManavSinghal8
 

Was ist angesagt? (20)

padma bridge presention
padma bridge presentionpadma bridge presention
padma bridge presention
 
Presentation about Padma Bridge.pptx
Presentation about Padma Bridge.pptxPresentation about Padma Bridge.pptx
Presentation about Padma Bridge.pptx
 
Metro Rail in Dhaka City
Metro Rail in Dhaka CityMetro Rail in Dhaka City
Metro Rail in Dhaka City
 
Dhaka metro rail project
Dhaka metro rail projectDhaka metro rail project
Dhaka metro rail project
 
PMBP SALIENTS
PMBP SALIENTSPMBP SALIENTS
PMBP SALIENTS
 
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goals
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goalsPADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goals
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goals
 
CSC-PMBP
CSC-PMBPCSC-PMBP
CSC-PMBP
 
Analysis and Review of EIA of Padma Multipurpose Bridge Project in Bangladesh
Analysis and Review of EIA of Padma Multipurpose Bridge Project in BangladeshAnalysis and Review of EIA of Padma Multipurpose Bridge Project in Bangladesh
Analysis and Review of EIA of Padma Multipurpose Bridge Project in Bangladesh
 
Metro rail in Dhaka city
Metro rail in Dhaka cityMetro rail in Dhaka city
Metro rail in Dhaka city
 
Inland water transportation (IWT) of Bangladesh: Container perspective.
Inland water transportation (IWT) of Bangladesh: Container perspective.Inland water transportation (IWT) of Bangladesh: Container perspective.
Inland water transportation (IWT) of Bangladesh: Container perspective.
 
Metro rail
Metro railMetro rail
Metro rail
 
Dhaka metro rail
Dhaka metro railDhaka metro rail
Dhaka metro rail
 
Metro rail
Metro railMetro rail
Metro rail
 
Presentation for Dhaka Metro Rail.pptx
Presentation for Dhaka Metro Rail.pptxPresentation for Dhaka Metro Rail.pptx
Presentation for Dhaka Metro Rail.pptx
 
Recent infrastructural development in bangladesh and it’s impact on economy
Recent infrastructural development in bangladesh and it’s impact on economyRecent infrastructural development in bangladesh and it’s impact on economy
Recent infrastructural development in bangladesh and it’s impact on economy
 
Karnaphuli Tunnel presentation.
Karnaphuli Tunnel presentation.Karnaphuli Tunnel presentation.
Karnaphuli Tunnel presentation.
 
Metro Rail and the City
Metro Rail and the CityMetro Rail and the City
Metro Rail and the City
 
History of road in Nepal
History of road in NepalHistory of road in Nepal
History of road in Nepal
 
Delhi Gurgaon Expressway PPP
Delhi Gurgaon Expressway PPPDelhi Gurgaon Expressway PPP
Delhi Gurgaon Expressway PPP
 
Training report of road construction
Training report of road constructionTraining report of road construction
Training report of road construction
 

Ähnlich wie Padma Brige Project 2017 Slide

Melamchi Water Supply Project
Melamchi Water Supply ProjectMelamchi Water Supply Project
Melamchi Water Supply ProjectChandanGupta201
 
River inter linking is it really a mirage
River inter linking   is it really a mirageRiver inter linking   is it really a mirage
River inter linking is it really a miragePeriasamy K
 
Tipaimukh dam & Bangladesh- M Shahriar Sonet
Tipaimukh dam & Bangladesh- M Shahriar SonetTipaimukh dam & Bangladesh- M Shahriar Sonet
Tipaimukh dam & Bangladesh- M Shahriar SonetM Shahriar Sonet
 
2014 IRF GRAA Winners
2014 IRF GRAA Winners2014 IRF GRAA Winners
2014 IRF GRAA WinnersLars Forslöf
 
Punasa report on indra sagar Dam, 9608684800
Punasa  report on indra sagar Dam, 9608684800Punasa  report on indra sagar Dam, 9608684800
Punasa report on indra sagar Dam, 9608684800PRIYANSHU KUMAR
 
Brahmaputra river protection By Dipankar Das
Brahmaputra river protection By Dipankar DasBrahmaputra river protection By Dipankar Das
Brahmaputra river protection By Dipankar DasDipankar Das
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONGLA University
 
Multipurpose River Valley Projects and alternate water supply methods
Multipurpose River Valley Projects and alternate water supply methodsMultipurpose River Valley Projects and alternate water supply methods
Multipurpose River Valley Projects and alternate water supply methodsTannya
 
Interlinking of rivers in india
Interlinking of rivers in indiaInterlinking of rivers in india
Interlinking of rivers in indiaIqura Malik
 
Bandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,IndiaBandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,Indiaoyepuneeta
 
The analysis of the road’s ecological environment and case study
The analysis of the road’s ecological environment and case studyThe analysis of the road’s ecological environment and case study
The analysis of the road’s ecological environment and case studyIJERA Editor
 
Critical Study on Kochi Barrage
Critical Study on Kochi BarrageCritical Study on Kochi Barrage
Critical Study on Kochi BarrageIRJET Journal
 
Eia Karachi Thatta Dual Carriageway Project
Eia Karachi Thatta Dual Carriageway ProjectEia Karachi Thatta Dual Carriageway Project
Eia Karachi Thatta Dual Carriageway Projectzubeditufail
 
Bogibeel Rail cum Road Bridge.pptx
Bogibeel Rail cum Road Bridge.pptxBogibeel Rail cum Road Bridge.pptx
Bogibeel Rail cum Road Bridge.pptxANURAGSWAIN12
 

Ähnlich wie Padma Brige Project 2017 Slide (20)

Hrm raw ppt
Hrm raw pptHrm raw ppt
Hrm raw ppt
 
Melamchi Water Supply Project
Melamchi Water Supply ProjectMelamchi Water Supply Project
Melamchi Water Supply Project
 
River inter linking is it really a mirage
River inter linking   is it really a mirageRiver inter linking   is it really a mirage
River inter linking is it really a mirage
 
EIA Report of Orange Line Train
EIA Report of Orange Line TrainEIA Report of Orange Line Train
EIA Report of Orange Line Train
 
Nl infrastructure oct 3 - oct 9, 2015
Nl infrastructure oct 3 - oct 9, 2015Nl infrastructure oct 3 - oct 9, 2015
Nl infrastructure oct 3 - oct 9, 2015
 
PWD, national highway
PWD, national highwayPWD, national highway
PWD, national highway
 
Tipaimukh dam & Bangladesh- M Shahriar Sonet
Tipaimukh dam & Bangladesh- M Shahriar SonetTipaimukh dam & Bangladesh- M Shahriar Sonet
Tipaimukh dam & Bangladesh- M Shahriar Sonet
 
Iee ppt
Iee pptIee ppt
Iee ppt
 
2014 IRF GRAA Winners
2014 IRF GRAA Winners2014 IRF GRAA Winners
2014 IRF GRAA Winners
 
Punasa report on indra sagar Dam, 9608684800
Punasa  report on indra sagar Dam, 9608684800Punasa  report on indra sagar Dam, 9608684800
Punasa report on indra sagar Dam, 9608684800
 
Brahmaputra river protection By Dipankar Das
Brahmaputra river protection By Dipankar DasBrahmaputra river protection By Dipankar Das
Brahmaputra river protection By Dipankar Das
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTION
 
Multipurpose River Valley Projects and alternate water supply methods
Multipurpose River Valley Projects and alternate water supply methodsMultipurpose River Valley Projects and alternate water supply methods
Multipurpose River Valley Projects and alternate water supply methods
 
Interlinking of rivers in india
Interlinking of rivers in indiaInterlinking of rivers in india
Interlinking of rivers in india
 
Bandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,IndiaBandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,India
 
41946 ind-seia
41946 ind-seia41946 ind-seia
41946 ind-seia
 
The analysis of the road’s ecological environment and case study
The analysis of the road’s ecological environment and case studyThe analysis of the road’s ecological environment and case study
The analysis of the road’s ecological environment and case study
 
Critical Study on Kochi Barrage
Critical Study on Kochi BarrageCritical Study on Kochi Barrage
Critical Study on Kochi Barrage
 
Eia Karachi Thatta Dual Carriageway Project
Eia Karachi Thatta Dual Carriageway ProjectEia Karachi Thatta Dual Carriageway Project
Eia Karachi Thatta Dual Carriageway Project
 
Bogibeel Rail cum Road Bridge.pptx
Bogibeel Rail cum Road Bridge.pptxBogibeel Rail cum Road Bridge.pptx
Bogibeel Rail cum Road Bridge.pptx
 

Kürzlich hochgeladen

VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...SUHANI PANDEY
 
2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31JSchaus & Associates
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterChristina Parmionova
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...tanu pandey
 
Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...
Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...
Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...SUHANI PANDEY
 
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)Congressional Budget Office
 
Call Girls in Sarita Vihar Delhi Just Call 👉👉9873777170 Independent Female ...
Call Girls in  Sarita Vihar Delhi Just Call 👉👉9873777170  Independent Female ...Call Girls in  Sarita Vihar Delhi Just Call 👉👉9873777170  Independent Female ...
Call Girls in Sarita Vihar Delhi Just Call 👉👉9873777170 Independent Female ...adilkhan87451
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learningNAP Global Network
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'NAP Global Network
 
1935 CONSTITUTION REPORT IN RIPH FINALLS
1935 CONSTITUTION REPORT IN RIPH FINALLS1935 CONSTITUTION REPORT IN RIPH FINALLS
1935 CONSTITUTION REPORT IN RIPH FINALLSarandianics
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Dipal Arora
 
SMART BANGLADESH I PPTX I SLIDE IShovan Prita Paul.pptx
SMART BANGLADESH  I    PPTX   I    SLIDE   IShovan Prita Paul.pptxSMART BANGLADESH  I    PPTX   I    SLIDE   IShovan Prita Paul.pptx
SMART BANGLADESH I PPTX I SLIDE IShovan Prita Paul.pptxShovan Prita Paul .
 
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...tanu pandey
 
A Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisA Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisChristina Parmionova
 
celebrity 💋 Nagpur Escorts Just Dail 8250092165 service available anytime 24 ...
celebrity 💋 Nagpur Escorts Just Dail 8250092165 service available anytime 24 ...celebrity 💋 Nagpur Escorts Just Dail 8250092165 service available anytime 24 ...
celebrity 💋 Nagpur Escorts Just Dail 8250092165 service available anytime 24 ...Call Girls in Nagpur High Profile
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCNAP Global Network
 
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...nehasharma67844
 

Kürzlich hochgeladen (20)

VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
 
2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - Poster
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...
Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...
Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...
 
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
Call Girls in Sarita Vihar Delhi Just Call 👉👉9873777170 Independent Female ...
Call Girls in  Sarita Vihar Delhi Just Call 👉👉9873777170  Independent Female ...Call Girls in  Sarita Vihar Delhi Just Call 👉👉9873777170  Independent Female ...
Call Girls in Sarita Vihar Delhi Just Call 👉👉9873777170 Independent Female ...
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
 
1935 CONSTITUTION REPORT IN RIPH FINALLS
1935 CONSTITUTION REPORT IN RIPH FINALLS1935 CONSTITUTION REPORT IN RIPH FINALLS
1935 CONSTITUTION REPORT IN RIPH FINALLS
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
SMART BANGLADESH I PPTX I SLIDE IShovan Prita Paul.pptx
SMART BANGLADESH  I    PPTX   I    SLIDE   IShovan Prita Paul.pptxSMART BANGLADESH  I    PPTX   I    SLIDE   IShovan Prita Paul.pptx
SMART BANGLADESH I PPTX I SLIDE IShovan Prita Paul.pptx
 
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
A Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisA Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental Crisis
 
celebrity 💋 Nagpur Escorts Just Dail 8250092165 service available anytime 24 ...
celebrity 💋 Nagpur Escorts Just Dail 8250092165 service available anytime 24 ...celebrity 💋 Nagpur Escorts Just Dail 8250092165 service available anytime 24 ...
celebrity 💋 Nagpur Escorts Just Dail 8250092165 service available anytime 24 ...
 
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
 
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...Call Girls In datia Escorts ☎️7427069034  🔝 💃 Enjoy 24/7 Escort Service Enjoy...
Call Girls In datia Escorts ☎️7427069034 🔝 💃 Enjoy 24/7 Escort Service Enjoy...
 

Padma Brige Project 2017 Slide

  • 3. Padma Bridge is one of the most challenging projects in the world. We are constructing the Bridge on the second largest river flow in the world. Every second, approximately 140,000 cubic metre water flows through the project area. Twenty second flowing of that amount will be sufficient to meet one day drinking water demand of Dhaka city. Another challenge is scour depth. We have also considered earthquake related dangers. That's why we are using the second most powerful pile hammer in the world for this project. Introduction
  • 4. River training is another challenge. It requires huge amount of money. Last year there was serious river erosion in the Mawa area, and as a consequence we had to change our design to cope with such types of calamities. It might take more than three years to complete the river training works.
  • 5. General Information • Main Bridge (6.15 km long) • River Training Works(14 km length) • Janjira Approach Road & Selected Bridge End Facilities (10.5 km length) • Mawa Approach Road & Selected Bridge End Facilities (1.5 km length) • Land Acquisition: About 1408.54 hectre
  • 6. Financing Project cost is estimated to be US$3.00 billion. The Padma Multipurpose Bridge (PMB) project was designed to be funded by donors such as the World Bank, Japan International Cooperation Agency (JICA), Asian Development Bank (ADB) and Islamic Development Bank (IDB). After a scandal of alleged corruption by some people associated with project preparation the World Bank withdrew its commitment and other donors followed. The project is now being funded from own resources of the Government of Bangladesh. The state-owned company has constructed structures like the famous 36 km Hangzhou Bay Bridge, the longest sea- crossing bridge in the world. Padma Bridge, when commissioned, will boost the GDP by as much as 1.2 percent.
  • 7. And the Estimated Project Cost (as per Final Design) is… BDT 205072 Million or, USD 2.972 Billion (Including VAT and IT)
  • 8. Ministry Padma Multipurpose Bridge Project.Ministry of Road Transport and Bridges, Bridges Division, Bangladesh Bridge Authority. The World Bank initially refused to sanction the proposed loan for constructing the bridge and imposed conditions for the continuation of loan talks with the government. In accordance with one of these conditions Communications Minister Syed Abul Hossain had to resign, as he was found to be involved in the corruption.Now Mr. Obaidul Quader, Ministry of Road Transport & Bridges Government of the People’s Republic of Bangladesh.
  • 9. Components of the Project • Main Bridge • River Training Works(RTW) • Janjira Approach Road & Selected Bridge End Facilities • Mawa Approach Road & Selected Bridge End Facilities • Service Area-2 • Resettlement • Environment • Land Acquisition • CSC(Main Bridge & RTW) • CSC(Approach Roads & Service Area-2) • Engineering Support & Safety Team(ESST
  • 10. It will be capable as a gainer of generally people in our economical society.Because it has created a greatest opportunity for inter communication with other areas of our country.It will save the wasting time of people.People will be able to connect easily with their peer.It will save their valuable time.As we know journey by bus or car is easier then train or ship.In business perspective, industrial and agriculture products are so much benificial for digital market.Basically many products creat in Dhaka.For transferring these products to rural area, the bridge is needed urgently. It will also help people for making interpersonal relationship. Impacts on Society
  • 11. Project Impacts Total land acquired 1,100 ha Total AHs – 15,261 (80,000 persons) Close to 5,000 households to be relocated 3,000 hhs preferred “self relocation” 2,000 hhs to project Resettlement Sites Removal of trees and vegetation Disturbance of aquatic wildlife Hilsa and other catches Migratory birds
  • 12. After 3 years relocated families are stay on rehabilitation center. They are almost happy their. But some people says they are not proper happy and they have some dissatisfaction. Example : SahadatHossen, a resident of rehabilitation site no 1 at Kumarbhog , would be one of those who would have to leave his ancestral home.But he said he would be happy to vacate his land for building the bridge in national interest.
  • 13. By facilitating transportation across the river, the Padma Bridge is expected lead to the greater integration of regional markets within the Bangladeshi national economy. On the basis of their suitability of capture primary and secondary economic impacts of construction project, three different types of economy wide models are employed in addition to traditional traffic model to capture the total and economy wide impacts of Padma Bridge. Economic Aspect of Padma Bridge
  • 15. What is EIA? • Environmental Impact Assessment (EIA) is the process by which the anticipated effects on the environment of a proposed development or project are measured. If the likely effects are unacceptable, design measures or other relevant mitigation measures can be taken to reduce or avoid those effects. • The document from this process is called an Environmental Impact Statement (EIS).
  • 16. Environmental Impacts of Padma Bridge • About 295,072 trees loss (Excluding 485,074 bamboo and banana trees) • Crops 24,684 tons • Loss of fish breeding area about 767 ha, 12 ha fishing ponds will be filled up, etc. • Generate about 50 Million cubic meter dredge material from the river • Traffic congestion, safety hazards, noise pollution, sanitation, health and hygiene, waste generation etc.
  • 17. Conclusions Around 39% construction work of the 6.15-kilometre-long two-tier Padma Multipurpose Bridge has been completed.The China Major Bridge Engineering Corporation (MBEC), which was appointed for the main bridge, will carry out the work. The soil testing and dredging works have been going on for the last four months for the river training.The bridge will have a total of 42 pillars. Each will have six piles beneath. Steel spans will be placed on the pillars. The bridge will have a total of 41 spans. According to work plan: November 2014 . Now a days The Project Progress : 40.50% .Work end date according to work plan: November 2018