SlideShare ist ein Scribd-Unternehmen logo
1 von 17
Downloaden Sie, um offline zu lesen
MAINTENANCE AND INSTALLATION
OF
CIRCUIT BREAKER
By,
Rohini Haridas
Assistant Professor,
Dept of Electrical Engineering,
SSGM College of Engineering,Shegaon
Lack of maintenance may results in failure in
operation
Maintenance
Breakdown or
corrective
maintenance
Preventive
maintenance
Breakdown or corrective maintenance
activities are undertaken after failure of an
equipment
Such a maintenance results in outage of circuitSuch a maintenance results in outage of circuit
breaker and supply
In general, it consist of locating the trouble ,
repair and recommissioning
Preventive maintenance
is undertaken to ensure smooth and efficient
working of a system, equipment.
This type of maintenance is undertaken as per
schedule before breakdown of a system or
equipment
Repair or replacements are made to ensure that no
breakdown occurs at any time during the service
For switchgear and protective equipment,
preventive maintenance is recommendedpreventive maintenance is recommended
because failure of a switchgear can not be
permitted
General Maintenance
Activities
Inspection Servicing Examination Overhaul
Steps in maintenance of CB
1. General Inspection
o Observe the Circuit Breaker visually .
o Note the cleanliness, terminals, earth connections,
reading of counters, level of quenching medium
and pressure of quenching medium
2. Cleaning and drying
o Use clean cloths which does not leave fibers or
particles on the surface
o Use air pressure jet for cleaningo Use air pressure jet for cleaning
o Other cleansing agents recommended by
manufacturer
3. Insulation surface
o Inspect visually, carefully for the signs of cracks
or any other defects
o Clean the internal surfaces and external insulating
surfacessurfaces
o Insulation should be free from electrical or
mechanical defects
o Perform insulation resistance test, it gives
indication about the health of insulation
4. Drying
Circuit breaker pole can be internally dried by
circulating dry hot air.circulating dry hot air.
5. Interrupter
o Observation, cleaning, replacement of main/arching
contacts .
o Cleaning of other parts as well
o Removal of carbon decomposed product
o Cleaning terminals and sliding contact surface
o Cleaning of venting systems to ensure free passage of
oil/gas
6. Mechanism
• Check operation open and close
• Checking simultaneous opening and closing of
three poles
• Check operation counter
• If the mechanism has operated more than 1000
times, it needs very close operation and may need
overhaul
7. Main connections
Ensure that good contact is maintained
and connections are right and secure
8. Earth connections
9. Auxiliary devices
10. Isolating contacts
11. Overload devices and protective relays11. Overload devices and protective relays
12. CT and PT
13.Final verification
INSTALLATION
1) Check the readiness of foundations and their
dimensions as per the drawing
2) Check the level of foundation surface2) Check the level of foundation surface
3) Place the base frame of circuit breaker in position
4) Assemble operating mechanism in its position
5) Give auxiliary supply
6)Tighten all bolts and other hardware
7) If provision available, operate slow opening and
closing
8) Measure insulation resistance
9)Fill quenching medium after drying
10) Check leakage and ensure leakage free assembly
11) Check its opening and closing operation
12) Measure timing and check simultaneous
operation of three polesoperation of three poles
13) Operate the CB by operating relevant relays

Weitere ähnliche Inhalte

Was ist angesagt?

Installation Operation & Maintenance of 33kV & 11kV Switchgear
Installation   Operation & Maintenance of 33kV & 11kV SwitchgearInstallation   Operation & Maintenance of 33kV & 11kV Switchgear
Installation Operation & Maintenance of 33kV & 11kV SwitchgearSheikh Nazmul Islam
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & MaintenanceHimansu Pradhan
 
Unit 06 - Substation and maintenance
Unit 06 - Substation and maintenanceUnit 06 - Substation and maintenance
Unit 06 - Substation and maintenancePremanandDesai
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTCRohit Dave
 
Maintenance schedule of Substation.
Maintenance schedule of Substation.Maintenance schedule of Substation.
Maintenance schedule of Substation.Sheikh Nazmul Islam
 
**Lightning Arrester Presentation**
**Lightning Arrester Presentation****Lightning Arrester Presentation**
**Lightning Arrester Presentation**SKPAMB
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentationNadir Baloch
 
Transformer design and protection
Transformer design and protectionTransformer design and protection
Transformer design and protectionashwin fcc
 
Transformers protection, an introduction
Transformers protection, an introductionTransformers protection, an introduction
Transformers protection, an introductionH. Kheir
 
Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guideSlides Hub
 
Operation and maintenance of transformer
Operation and maintenance of transformerOperation and maintenance of transformer
Operation and maintenance of transformerKapil Singh
 
Introduction to power system protection
Introduction to power system protectionIntroduction to power system protection
Introduction to power system protectionSaifUrrehman183
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substationsvishalgohel12195
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer ProtectionAng Sovann
 
Transformer maintenance
Transformer maintenance Transformer maintenance
Transformer maintenance Molla Morshad
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformervikasgupta1965
 

Was ist angesagt? (20)

Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Installation   Operation & Maintenance of 33kV & 11kV SwitchgearInstallation   Operation & Maintenance of 33kV & 11kV Switchgear
Installation Operation & Maintenance of 33kV & 11kV Switchgear
 
Electrical maintenance
Electrical maintenanceElectrical maintenance
Electrical maintenance
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
 
Unit 06 - Substation and maintenance
Unit 06 - Substation and maintenanceUnit 06 - Substation and maintenance
Unit 06 - Substation and maintenance
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTC
 
Maintenance schedule of Substation.
Maintenance schedule of Substation.Maintenance schedule of Substation.
Maintenance schedule of Substation.
 
**Lightning Arrester Presentation**
**Lightning Arrester Presentation****Lightning Arrester Presentation**
**Lightning Arrester Presentation**
 
Vacuum circuit breaker
Vacuum circuit breakerVacuum circuit breaker
Vacuum circuit breaker
 
Relays
RelaysRelays
Relays
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
Transformer design and protection
Transformer design and protectionTransformer design and protection
Transformer design and protection
 
Transformers protection, an introduction
Transformers protection, an introductionTransformers protection, an introduction
Transformers protection, an introduction
 
Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guide
 
Operation and maintenance of transformer
Operation and maintenance of transformerOperation and maintenance of transformer
Operation and maintenance of transformer
 
Introduction to power system protection
Introduction to power system protectionIntroduction to power system protection
Introduction to power system protection
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
 
Transformer maintenance
Transformer maintenance Transformer maintenance
Transformer maintenance
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 

Andere mochten auch

2.components in a substation breaker
2.components in a substation   breaker2.components in a substation   breaker
2.components in a substation breakerayyadurai SHANMUGAM
 
Testing and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation EquipmentsTesting and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation EquipmentsSumeet Ratnawat
 
Er. rahul sharma circuit breaker
Er. rahul sharma circuit breakerEr. rahul sharma circuit breaker
Er. rahul sharma circuit breakerRahul Ruddra
 
Low Voltage Circuit Breaker
Low Voltage Circuit BreakerLow Voltage Circuit Breaker
Low Voltage Circuit BreakerAbdul Haseeb
 
Electrical components 8
Electrical components 8Electrical components 8
Electrical components 8RIFFAT_ZAHID
 
TRANSFORMER OIL TESTING FOR CORROSIVE SULFUR BY SHIVAKUMAR ...
TRANSFORMER OIL TESTING FOR CORROSIVE SULFUR BY SHIVAKUMAR                   ...TRANSFORMER OIL TESTING FOR CORROSIVE SULFUR BY SHIVAKUMAR                   ...
TRANSFORMER OIL TESTING FOR CORROSIVE SULFUR BY SHIVAKUMAR ...Shivakumar Shivu
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalNihal Shiroya
 
Circuit protection devices perfect ppt
Circuit protection devices perfect ppt Circuit protection devices perfect ppt
Circuit protection devices perfect ppt vikram rajpurohit
 
Digital testing of high voltage circuit breaker
Digital testing of high voltage circuit breakerDigital testing of high voltage circuit breaker
Digital testing of high voltage circuit breakerneeraj prasad
 
Circuit breaker Maintenance By Mobile Agent Software Technology
Circuit breaker Maintenance By Mobile Agent Software TechnologyCircuit breaker Maintenance By Mobile Agent Software Technology
Circuit breaker Maintenance By Mobile Agent Software Technologysiddhartha muduli
 
Best transformer-test-procedures-en
Best transformer-test-procedures-enBest transformer-test-procedures-en
Best transformer-test-procedures-enSuresh Patil
 
Kemalangan ditempat kerja
Kemalangan ditempat kerjaKemalangan ditempat kerja
Kemalangan ditempat kerjasyahirahhjsaad
 
Keselamatan & kesihatan pekerjaan
Keselamatan & kesihatan pekerjaanKeselamatan & kesihatan pekerjaan
Keselamatan & kesihatan pekerjaanHukaida Hamzah
 
Hand and power tool safety power point
Hand and power tool safety power pointHand and power tool safety power point
Hand and power tool safety power pointShane Johns
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHShankar Singh
 
Transformer testing
Transformer testingTransformer testing
Transformer testingajayknows
 

Andere mochten auch (20)

2.components in a substation breaker
2.components in a substation   breaker2.components in a substation   breaker
2.components in a substation breaker
 
Testing of cb
Testing of cbTesting of cb
Testing of cb
 
Testing and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation EquipmentsTesting and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation Equipments
 
Er. rahul sharma circuit breaker
Er. rahul sharma circuit breakerEr. rahul sharma circuit breaker
Er. rahul sharma circuit breaker
 
Low Voltage Circuit Breaker
Low Voltage Circuit BreakerLow Voltage Circuit Breaker
Low Voltage Circuit Breaker
 
Electrical components 8
Electrical components 8Electrical components 8
Electrical components 8
 
TRANSFORMER OIL TESTING FOR CORROSIVE SULFUR BY SHIVAKUMAR ...
TRANSFORMER OIL TESTING FOR CORROSIVE SULFUR BY SHIVAKUMAR                   ...TRANSFORMER OIL TESTING FOR CORROSIVE SULFUR BY SHIVAKUMAR                   ...
TRANSFORMER OIL TESTING FOR CORROSIVE SULFUR BY SHIVAKUMAR ...
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihal
 
final yr project-1
final yr project-1final yr project-1
final yr project-1
 
Circuit protection devices perfect ppt
Circuit protection devices perfect ppt Circuit protection devices perfect ppt
Circuit protection devices perfect ppt
 
Digital testing of high voltage circuit breaker
Digital testing of high voltage circuit breakerDigital testing of high voltage circuit breaker
Digital testing of high voltage circuit breaker
 
Circuit breaker Maintenance By Mobile Agent Software Technology
Circuit breaker Maintenance By Mobile Agent Software TechnologyCircuit breaker Maintenance By Mobile Agent Software Technology
Circuit breaker Maintenance By Mobile Agent Software Technology
 
Best transformer-test-procedures-en
Best transformer-test-procedures-enBest transformer-test-procedures-en
Best transformer-test-procedures-en
 
Circuit breakers
Circuit breakersCircuit breakers
Circuit breakers
 
Hand tools and hand hazards ppt
Hand tools and hand hazards pptHand tools and hand hazards ppt
Hand tools and hand hazards ppt
 
Kemalangan ditempat kerja
Kemalangan ditempat kerjaKemalangan ditempat kerja
Kemalangan ditempat kerja
 
Keselamatan & kesihatan pekerjaan
Keselamatan & kesihatan pekerjaanKeselamatan & kesihatan pekerjaan
Keselamatan & kesihatan pekerjaan
 
Hand and power tool safety power point
Hand and power tool safety power pointHand and power tool safety power point
Hand and power tool safety power point
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
 
Transformer testing
Transformer testingTransformer testing
Transformer testing
 

Ähnlich wie Ppt maintenance cb(encrypted)

Maintenance of Substation Equipment | Operation And Maintenance Of Substation
Maintenance of Substation Equipment | Operation And Maintenance Of SubstationMaintenance of Substation Equipment | Operation And Maintenance Of Substation
Maintenance of Substation Equipment | Operation And Maintenance Of SubstationSystem Protection
 
switchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptxswitchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptxDrNiveditaSingh3
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)SAJJAD KHUDHUR ABBAS
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updatedPersonal Secret
 
Electrical testing javid iqbal sodagar
Electrical testing javid iqbal sodagarElectrical testing javid iqbal sodagar
Electrical testing javid iqbal sodagarjavid iqbal sodagar
 
Student Declaration on Submission I confirm that all the work in.docx
Student Declaration on Submission I confirm that all the work in.docxStudent Declaration on Submission I confirm that all the work in.docx
Student Declaration on Submission I confirm that all the work in.docxflorriezhamphrey3065
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewMark Platten
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear johny renoald
 
quy trình bảo dưỡng máy thở
quy trình bảo dưỡng máy thởquy trình bảo dưỡng máy thở
quy trình bảo dưỡng máy thởHung Nguyen
 
Alignment of-kiln
Alignment of-kilnAlignment of-kiln
Alignment of-kilnmkpq pasha
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushingNovia Putri
 
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.ppt
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.pptSVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.ppt
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.pptssuser4b097a
 
HT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
HT & LT Bus Ducts Manufacturer in Telangana and Andhra PradeshHT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
HT & LT Bus Ducts Manufacturer in Telangana and Andhra PradeshMohit Bathineni
 
'docslide.us_hv-testing.ppt
'docslide.us_hv-testing.ppt'docslide.us_hv-testing.ppt
'docslide.us_hv-testing.pptThien Phan Bản
 

Ähnlich wie Ppt maintenance cb(encrypted) (20)

Maintenance of Substation Equipment | Operation And Maintenance Of Substation
Maintenance of Substation Equipment | Operation And Maintenance Of SubstationMaintenance of Substation Equipment | Operation And Maintenance Of Substation
Maintenance of Substation Equipment | Operation And Maintenance Of Substation
 
switchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptxswitchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptx
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
SD.pptx
SD.pptxSD.pptx
SD.pptx
 
SHUTDOWN
SHUTDOWNSHUTDOWN
SHUTDOWN
 
Psg 5 2 mark
Psg 5 2 markPsg 5 2 mark
Psg 5 2 mark
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
Electrical testing javid iqbal sodagar
Electrical testing javid iqbal sodagarElectrical testing javid iqbal sodagar
Electrical testing javid iqbal sodagar
 
Student Declaration on Submission I confirm that all the work in.docx
Student Declaration on Submission I confirm that all the work in.docxStudent Declaration on Submission I confirm that all the work in.docx
Student Declaration on Submission I confirm that all the work in.docx
 
PPT-on-false-air.ppt
PPT-on-false-air.pptPPT-on-false-air.ppt
PPT-on-false-air.ppt
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For review
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
quy trình bảo dưỡng máy thở
quy trình bảo dưỡng máy thởquy trình bảo dưỡng máy thở
quy trình bảo dưỡng máy thở
 
Alignment of-kiln
Alignment of-kilnAlignment of-kiln
Alignment of-kiln
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
 
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.ppt
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.pptSVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.ppt
SVC 33- TCR WORK SHOP-3#Intro to PreComm & Comm.ppt
 
Technician Training: Safety basics
Technician Training: Safety basicsTechnician Training: Safety basics
Technician Training: Safety basics
 
HT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
HT & LT Bus Ducts Manufacturer in Telangana and Andhra PradeshHT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
HT & LT Bus Ducts Manufacturer in Telangana and Andhra Pradesh
 
'docslide.us_hv-testing.ppt
'docslide.us_hv-testing.ppt'docslide.us_hv-testing.ppt
'docslide.us_hv-testing.ppt
 

Mehr von Rohini Haridas

Rohini haridas wind energy
Rohini haridas wind energyRohini haridas wind energy
Rohini haridas wind energyRohini Haridas
 
Protection of transmission lines (distance)
Protection of transmission lines (distance)Protection of transmission lines (distance)
Protection of transmission lines (distance)Rohini Haridas
 
Miniature circuit breaker(encrypted)
Miniature circuit breaker(encrypted)Miniature circuit breaker(encrypted)
Miniature circuit breaker(encrypted)Rohini Haridas
 
Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)Rohini Haridas
 
Circuit breaker(encrypted)
Circuit breaker(encrypted)Circuit breaker(encrypted)
Circuit breaker(encrypted)Rohini Haridas
 
Protection of alternator(encrypted)
Protection of alternator(encrypted)Protection of alternator(encrypted)
Protection of alternator(encrypted)Rohini Haridas
 
Construction of dc machines
Construction of dc machinesConstruction of dc machines
Construction of dc machinesRohini Haridas
 
Stepper motor(encrypted)
Stepper motor(encrypted)Stepper motor(encrypted)
Stepper motor(encrypted)Rohini Haridas
 
Testing of dc machines_I
Testing of dc machines_ITesting of dc machines_I
Testing of dc machines_IRohini Haridas
 

Mehr von Rohini Haridas (10)

Rohini haridas wind energy
Rohini haridas wind energyRohini haridas wind energy
Rohini haridas wind energy
 
Magnetic circuit
Magnetic circuitMagnetic circuit
Magnetic circuit
 
Protection of transmission lines (distance)
Protection of transmission lines (distance)Protection of transmission lines (distance)
Protection of transmission lines (distance)
 
Miniature circuit breaker(encrypted)
Miniature circuit breaker(encrypted)Miniature circuit breaker(encrypted)
Miniature circuit breaker(encrypted)
 
Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)Protection of transmission lines(encrypted)
Protection of transmission lines(encrypted)
 
Circuit breaker(encrypted)
Circuit breaker(encrypted)Circuit breaker(encrypted)
Circuit breaker(encrypted)
 
Protection of alternator(encrypted)
Protection of alternator(encrypted)Protection of alternator(encrypted)
Protection of alternator(encrypted)
 
Construction of dc machines
Construction of dc machinesConstruction of dc machines
Construction of dc machines
 
Stepper motor(encrypted)
Stepper motor(encrypted)Stepper motor(encrypted)
Stepper motor(encrypted)
 
Testing of dc machines_I
Testing of dc machines_ITesting of dc machines_I
Testing of dc machines_I
 

Kürzlich hochgeladen

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 

Kürzlich hochgeladen (20)

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 

Ppt maintenance cb(encrypted)

  • 1. MAINTENANCE AND INSTALLATION OF CIRCUIT BREAKER By, Rohini Haridas Assistant Professor, Dept of Electrical Engineering, SSGM College of Engineering,Shegaon
  • 2. Lack of maintenance may results in failure in operation Maintenance Breakdown or corrective maintenance Preventive maintenance
  • 3. Breakdown or corrective maintenance activities are undertaken after failure of an equipment Such a maintenance results in outage of circuitSuch a maintenance results in outage of circuit breaker and supply In general, it consist of locating the trouble , repair and recommissioning
  • 4. Preventive maintenance is undertaken to ensure smooth and efficient working of a system, equipment. This type of maintenance is undertaken as per schedule before breakdown of a system or equipment Repair or replacements are made to ensure that no breakdown occurs at any time during the service
  • 5. For switchgear and protective equipment, preventive maintenance is recommendedpreventive maintenance is recommended because failure of a switchgear can not be permitted
  • 7. Steps in maintenance of CB 1. General Inspection o Observe the Circuit Breaker visually . o Note the cleanliness, terminals, earth connections, reading of counters, level of quenching medium and pressure of quenching medium
  • 8. 2. Cleaning and drying o Use clean cloths which does not leave fibers or particles on the surface o Use air pressure jet for cleaningo Use air pressure jet for cleaning o Other cleansing agents recommended by manufacturer
  • 9. 3. Insulation surface o Inspect visually, carefully for the signs of cracks or any other defects o Clean the internal surfaces and external insulating surfacessurfaces o Insulation should be free from electrical or mechanical defects o Perform insulation resistance test, it gives indication about the health of insulation
  • 10. 4. Drying Circuit breaker pole can be internally dried by circulating dry hot air.circulating dry hot air.
  • 11. 5. Interrupter o Observation, cleaning, replacement of main/arching contacts . o Cleaning of other parts as well o Removal of carbon decomposed product o Cleaning terminals and sliding contact surface o Cleaning of venting systems to ensure free passage of oil/gas
  • 12. 6. Mechanism • Check operation open and close • Checking simultaneous opening and closing of three poles • Check operation counter • If the mechanism has operated more than 1000 times, it needs very close operation and may need overhaul
  • 13. 7. Main connections Ensure that good contact is maintained and connections are right and secure
  • 14. 8. Earth connections 9. Auxiliary devices 10. Isolating contacts 11. Overload devices and protective relays11. Overload devices and protective relays 12. CT and PT 13.Final verification
  • 15. INSTALLATION 1) Check the readiness of foundations and their dimensions as per the drawing 2) Check the level of foundation surface2) Check the level of foundation surface 3) Place the base frame of circuit breaker in position 4) Assemble operating mechanism in its position
  • 16. 5) Give auxiliary supply 6)Tighten all bolts and other hardware 7) If provision available, operate slow opening and closing 8) Measure insulation resistance 9)Fill quenching medium after drying 10) Check leakage and ensure leakage free assembly
  • 17. 11) Check its opening and closing operation 12) Measure timing and check simultaneous operation of three polesoperation of three poles 13) Operate the CB by operating relevant relays