-Rakesh Sunari
Magar(77)
-Pawan Bhatta(65)
-Nirajan Dahal(58)
-Needesh
Budhathoki(56)
Prof. Dr. Padma Bahadur
Shahi
1
Background
 As per our syllabus, we fourth year students have to
present our final year project in our desired field of
interest. It is a vital part of IOE syllabus in order to
make students competent to work in the actual field.
 We have chosen rural road development project
among the number of options available in
transportation project.
 We want to experience the working technique with
new innovative concept of ours while designing a road
in a sense of future demand that is structurally, eco-
friendly and atheistically designed.2
Intro
T
R
A
N
S
P
O
R
T
A
T
I
O
N
 Transportation plays a vital role in
basic infrastructure development in
mountainous country like Nepal.
 It is a social property.
 It is demand fulfilling demand.
3
Objectives and Scope
 To setup an alignment of a road as per the
environmental condition.
 To consider gradient, earthwork, road components
(drainage, retaining walls), geometric properties of the
road properly in the design.
 To prepare economical and stable road in rural areas.
 To link urban and rural areas with comfort, wide, safe,
smooth road.
4
Objectives and Scope
 For the overall development of country.
 To minimize the risk of loss of property and lives
by designing stable roads.
 To know the importance of team work.
 To design the road with innovative concept that is
structurally, atheistically and eco-friendly aspect.
5
Gantt chart
WORKING SCHEDULE
6
METHODOLOGY
 Planning
 Survey
 Preliminary Design
 Geometric Design
 Detailing
 Calculation
 Plotting
 Modeling
 Analysis
 Report Preparation
7
The work to be performed while
doing our project are listed as series
below:
Project PERT Chart
START
Pre synopsis
submission
Site
Selection
Reconnaissan
ce survey
11 th Nov , 2014
8
Survey and
data plot
Tests of soil
samples
Computation and
design
Traffic count
9
Project report
submission
Conclusion END
2015
10
ROAD SITE
Pang Gaun to Tika Bhairav (2.5km)
Location:
 Zone: Bagmati
 District: Lalitpur
 VDC: Pang Gaun
11
12
MAP STUDY
Location :- Where are things situated?
 A location can be specific for example, it can be
stated as coordinates of longitude and latitude or as a
distance from one place to another place.
eg. In our case, road site’s location is south east from
the valley.
 Latitudes/easting are imaginary lines running parallel
to the Equator.
 Longitudes(departures)/northing are imaginary lines
running parallel to the Prime Meridian.
13
MAP STUDY
14
Place :- What makes a place different from other
places? Differences might be defined in terms of
climate, physical features, or the people who live
there and their traditions.
Human-environment interaction :- What are the
relationships among people and places? How
have people changed the environment to better
suit their needs?
SOCIO-ECONOMIC
CONDITION
 The major caste in this area are newars, brahmin,
chhetri, sarkis, etc.
 Mainly the people are involved in agriculture.
 People are not well educated.
 The economic condition is poor.
Equipments used in geometric
survey
GPS (Global Positioning System)
 2 numbers
 Principle:
Satellites based allocation of a position by
latitude, departure and elevation.
16
Geometric design
17
 Profile
 Plan
 Cross section
18
fig. Plan (central alignment only)
Pavement design
 Traffic count
 CBR test
19
Traffic study
 A traffic study is an engineering investigation
to evaluate a transportation system.
 A study typically consists of collecting data,
projecting traffic volumes, and identifying the
improvements required for the transportation
system.
20
Traffic Count
 A traffic count is a count of traffic along a
particular road, either done electronically or by
people counting by the side of the road.
 Traffic counts can be used by local councils to
identify which routes are used most, and to either
improve that road or provide an alternative if
there is an excessive amount of traffic.
Traffic Count
Leaving the valley Entering the valley
22
bike car/jeep bus
Truck
( unloaded)
Truck
(loaded)
Heavy
(tipper) tandem
19 5 2 1 8 1 0
11 2 4 1 3 1 0
8 2 3 4 13 2 1
9 3 1 1 12 0 0
bike car/jeep bus
Truck
( unloaded)
Truck
(loaded)
Heavy
(tipper) tandem
15 2 4 5 3 0 0
7 4 1 6 0 0 0
11 1 1 2 0 0 0
6 3 6 12 0 0 0
minutes
15
other 15
other 15
other 15
39 10 12 25 3 0 0 47 12 10 7 36 4 1total
Therefore,
Total traffic volume= 206 vehicles per hour
23
CBR test
24
CBR test
25
26
CB
R
= CBR [%]
p = measured pressure for site soils [N/mm²]
ps
= pressure to achieve equal penetration on standard
soil [N/mm²]
27
CBR VALUE SUBGRADE STRENGTH
3% and less Poor
3% - 5% Normal
5% - 15% Good
CONCLUSION
 Geometric analysis of different roads has become
evitable in today’s world. So, we are quite interested
in indulging us in this research as we have interest
towards this subject. Further in Nepal, geometric
analysis of roads are to be done and for this we want
to prepare ourselves.
 We believe that after the completion of this project we
are not only capable of geometrically analyzing
existing as well as newly prepared roads but also can
put forward our suggestions to ensure or increase the
safety, strength and durability of the roads.
28
design references
 Rural Road Standard, DOLIDAR
 Pavement Design Guidelines, DOR
29
Thank
You!!!
30

Weitere ähnliche Inhalte

Was ist angesagt?

Ce2026 traffic engineering and management notes
Ce2026 traffic engineering and management notesCe2026 traffic engineering and management notes
Ce2026 traffic engineering and management notesNayana 54321
 
1.introduction to highway engineering
1.introduction to highway engineering1.introduction to highway engineering
1.introduction to highway engineeringholegajendra
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work reportAbdul rahman kureshi
 
National Urban Transport Policy
National Urban Transport PolicyNational Urban Transport Policy
National Urban Transport PolicyAshu Kedia
 
Project Research Proposal Design of 4.5km road
Project Research Proposal  Design of 4.5km  roadProject Research Proposal  Design of 4.5km  road
Project Research Proposal Design of 4.5km roadSyed Hazoor Ali Shah
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONGLA University
 
Traffic & Transportation surveys
Traffic & Transportation surveysTraffic & Transportation surveys
Traffic & Transportation surveysDhwani Shah
 
Transportation Engineering I
Transportation Engineering ITransportation Engineering I
Transportation Engineering IShradhesh Marve
 
Spot speed studies and speed delay time survey
Spot speed studies and speed delay time surveySpot speed studies and speed delay time survey
Spot speed studies and speed delay time surveySai Santosh Yakkali
 
Chapter 1 traffic characterstics
Chapter 1 traffic charactersticsChapter 1 traffic characterstics
Chapter 1 traffic charactersticsAnkit Patel
 
highway development in india
highway development in indiahighway development in india
highway development in indiaPrathi Baa
 
Highway construction PPT
Highway construction PPTHighway construction PPT
Highway construction PPTVikas Sukhwal
 
1.TRAFFIC CHARACTERISTICS (TE) 2170613 GTU
1.TRAFFIC CHARACTERISTICS (TE) 2170613 GTU1.TRAFFIC CHARACTERISTICS (TE) 2170613 GTU
1.TRAFFIC CHARACTERISTICS (TE) 2170613 GTUVATSAL PATEL
 
TRANSPORTATION PLANNING
TRANSPORTATION PLANNINGTRANSPORTATION PLANNING
TRANSPORTATION PLANNINGintan fatihah
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADGLA University
 
Land use transportation relation
Land use  transportation relationLand use  transportation relation
Land use transportation relationSiddhi Vakharia
 

Was ist angesagt? (20)

Road construction report
Road construction reportRoad construction report
Road construction report
 
Ce2026 traffic engineering and management notes
Ce2026 traffic engineering and management notesCe2026 traffic engineering and management notes
Ce2026 traffic engineering and management notes
 
1. i Highway Planning.pdf
1. i  Highway Planning.pdf1. i  Highway Planning.pdf
1. i Highway Planning.pdf
 
1.introduction to highway engineering
1.introduction to highway engineering1.introduction to highway engineering
1.introduction to highway engineering
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work report
 
National Urban Transport Policy
National Urban Transport PolicyNational Urban Transport Policy
National Urban Transport Policy
 
Project Research Proposal Design of 4.5km road
Project Research Proposal  Design of 4.5km  roadProject Research Proposal  Design of 4.5km  road
Project Research Proposal Design of 4.5km road
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTION
 
Traffic & Transportation surveys
Traffic & Transportation surveysTraffic & Transportation surveys
Traffic & Transportation surveys
 
Transportation Engineering I
Transportation Engineering ITransportation Engineering I
Transportation Engineering I
 
Spot speed studies and speed delay time survey
Spot speed studies and speed delay time surveySpot speed studies and speed delay time survey
Spot speed studies and speed delay time survey
 
Chapter 1 traffic characterstics
Chapter 1 traffic charactersticsChapter 1 traffic characterstics
Chapter 1 traffic characterstics
 
highway development in india
highway development in indiahighway development in india
highway development in india
 
Traffic engineering
Traffic engineeringTraffic engineering
Traffic engineering
 
Highway construction PPT
Highway construction PPTHighway construction PPT
Highway construction PPT
 
1.TRAFFIC CHARACTERISTICS (TE) 2170613 GTU
1.TRAFFIC CHARACTERISTICS (TE) 2170613 GTU1.TRAFFIC CHARACTERISTICS (TE) 2170613 GTU
1.TRAFFIC CHARACTERISTICS (TE) 2170613 GTU
 
TRANSPORTATION PLANNING
TRANSPORTATION PLANNINGTRANSPORTATION PLANNING
TRANSPORTATION PLANNING
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
 
Land use transportation relation
Land use  transportation relationLand use  transportation relation
Land use transportation relation
 
UNDERPASS DESIGN
UNDERPASS DESIGNUNDERPASS DESIGN
UNDERPASS DESIGN
 

Andere mochten auch

STOMP sample project presentation
STOMP sample project presentationSTOMP sample project presentation
STOMP sample project presentationsburakharper
 
Project planning and feasibility study
Project planning and feasibility studyProject planning and feasibility study
Project planning and feasibility studyMars Mfyam
 
Bankole (Guttmacher) - Unsafe Abortion
Bankole (Guttmacher) - Unsafe AbortionBankole (Guttmacher) - Unsafe Abortion
Bankole (Guttmacher) - Unsafe Abortionguestc7da32
 
Determining the Mathematical ROI of a Project Management Office (PMO) Impleme...
Determining the Mathematical ROI of a Project Management Office (PMO) Impleme...Determining the Mathematical ROI of a Project Management Office (PMO) Impleme...
Determining the Mathematical ROI of a Project Management Office (PMO) Impleme...Ricardo Viana Vargas
 
Thesis Defence for Doctor of Information Science
Thesis Defence for Doctor of Information ScienceThesis Defence for Doctor of Information Science
Thesis Defence for Doctor of Information ScienceYuma Inoue
 
Abortions and Post Abortion Care
Abortions and Post Abortion CareAbortions and Post Abortion Care
Abortions and Post Abortion CareMubarak Yusuf
 
How to Give a TED Worthy Presentation
How to Give a TED Worthy PresentationHow to Give a TED Worthy Presentation
How to Give a TED Worthy PresentationBrooke Estin
 
Online Quiz System Project PPT
Online Quiz System Project PPTOnline Quiz System Project PPT
Online Quiz System Project PPTShanthan Reddy
 
Earthquake Resistant Designs
Earthquake Resistant DesignsEarthquake Resistant Designs
Earthquake Resistant DesignsJNTU
 
Web design proposal sample
Web design proposal sampleWeb design proposal sample
Web design proposal sampleAdviacent
 
Sample project abstract
Sample project abstractSample project abstract
Sample project abstractklezeh
 
abortion ppt
abortion pptabortion ppt
abortion pptAmeenah
 
Sample Project Proposal Design Document
Sample Project Proposal Design DocumentSample Project Proposal Design Document
Sample Project Proposal Design DocumentArturo Pelayo
 
My Thesis Defense Presentation
My Thesis Defense PresentationMy Thesis Defense Presentation
My Thesis Defense PresentationDavid Onoue
 

Andere mochten auch (20)

STOMP sample project presentation
STOMP sample project presentationSTOMP sample project presentation
STOMP sample project presentation
 
Sample project
Sample projectSample project
Sample project
 
Online quiz system
Online quiz systemOnline quiz system
Online quiz system
 
Project planning and feasibility study
Project planning and feasibility studyProject planning and feasibility study
Project planning and feasibility study
 
The socio-economic burden of unsafe abortion for women and households in Zambia
The socio-economic burden of unsafe abortion for women and households in ZambiaThe socio-economic burden of unsafe abortion for women and households in Zambia
The socio-economic burden of unsafe abortion for women and households in Zambia
 
Unsafe Abortion
Unsafe AbortionUnsafe Abortion
Unsafe Abortion
 
Bankole (Guttmacher) - Unsafe Abortion
Bankole (Guttmacher) - Unsafe AbortionBankole (Guttmacher) - Unsafe Abortion
Bankole (Guttmacher) - Unsafe Abortion
 
Determining the Mathematical ROI of a Project Management Office (PMO) Impleme...
Determining the Mathematical ROI of a Project Management Office (PMO) Impleme...Determining the Mathematical ROI of a Project Management Office (PMO) Impleme...
Determining the Mathematical ROI of a Project Management Office (PMO) Impleme...
 
Thesis Defence for Doctor of Information Science
Thesis Defence for Doctor of Information ScienceThesis Defence for Doctor of Information Science
Thesis Defence for Doctor of Information Science
 
Abortions and Post Abortion Care
Abortions and Post Abortion CareAbortions and Post Abortion Care
Abortions and Post Abortion Care
 
How to Give a TED Worthy Presentation
How to Give a TED Worthy PresentationHow to Give a TED Worthy Presentation
How to Give a TED Worthy Presentation
 
Online Quiz System Project PPT
Online Quiz System Project PPTOnline Quiz System Project PPT
Online Quiz System Project PPT
 
Earthquake Resistant Designs
Earthquake Resistant DesignsEarthquake Resistant Designs
Earthquake Resistant Designs
 
Web design proposal sample
Web design proposal sampleWeb design proposal sample
Web design proposal sample
 
Sample project abstract
Sample project abstractSample project abstract
Sample project abstract
 
abortion ppt
abortion pptabortion ppt
abortion ppt
 
Project proposal
Project proposalProject proposal
Project proposal
 
Sample Project Proposal Design Document
Sample Project Proposal Design DocumentSample Project Proposal Design Document
Sample Project Proposal Design Document
 
My Thesis Defense Presentation
My Thesis Defense PresentationMy Thesis Defense Presentation
My Thesis Defense Presentation
 
Project proposal
Project proposalProject proposal
Project proposal
 

Ähnlich wie project work presentation on road feasibility study (need to be corrected but can be used as reference)

Impact of Transportation System on Land Use in CBD area of Pabna Municipality...
Impact of Transportation System on Land Use in CBD area of Pabna Municipality...Impact of Transportation System on Land Use in CBD area of Pabna Municipality...
Impact of Transportation System on Land Use in CBD area of Pabna Municipality...Md. Merazul Islam Abir
 
Impact of Different Types of Land Use on Transportation System of Dhaka City ...
Impact of Different Types of Land Use on Transportation System of Dhaka City ...Impact of Different Types of Land Use on Transportation System of Dhaka City ...
Impact of Different Types of Land Use on Transportation System of Dhaka City ...Shahadat Hossain Shakil
 
IRJET- Rural Road Design and Development
IRJET- Rural Road Design and DevelopmentIRJET- Rural Road Design and Development
IRJET- Rural Road Design and DevelopmentIRJET Journal
 
Identification of Suitable Landfill Site using Geographical Information Syste...
Identification of Suitable Landfill Site using Geographical Information Syste...Identification of Suitable Landfill Site using Geographical Information Syste...
Identification of Suitable Landfill Site using Geographical Information Syste...Trupti Lokhande
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
Applications of GIS in Municipal Solid Waste Management
Applications of GIS in Municipal Solid Waste ManagementApplications of GIS in Municipal Solid Waste Management
Applications of GIS in Municipal Solid Waste ManagementVignesh Sekar
 
Landscape design for multimodal transport corridors
Landscape design for multimodal transport corridorsLandscape design for multimodal transport corridors
Landscape design for multimodal transport corridorsGeeva Chandana
 
Route optimization of solid waste transportation in part of Lucknow- Capital ...
Route optimization of solid waste transportation in part of Lucknow- Capital ...Route optimization of solid waste transportation in part of Lucknow- Capital ...
Route optimization of solid waste transportation in part of Lucknow- Capital ...IRJET Journal
 
Mode choice between roadway and waterway
Mode choice between roadway and waterwayMode choice between roadway and waterway
Mode choice between roadway and waterwayAglaia Connect
 
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGM
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGMNorthern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGM
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGMPlace North West
 
Study is to perform roadway condition survey of link road between panthapath ...
Study is to perform roadway condition survey of link road between panthapath ...Study is to perform roadway condition survey of link road between panthapath ...
Study is to perform roadway condition survey of link road between panthapath ...Khaza Ahmed Palash
 
Remote Sensing and GIS-Based Monitoring of Land Use Change in Nagpur District...
Remote Sensing and GIS-Based Monitoring of Land Use Change in Nagpur District...Remote Sensing and GIS-Based Monitoring of Land Use Change in Nagpur District...
Remote Sensing and GIS-Based Monitoring of Land Use Change in Nagpur District...IRJET Journal
 
civil engineers project work .docx
civil engineers project work .docxcivil engineers project work .docx
civil engineers project work .docxVijay Kumar
 
roadway condition survey
roadway condition surveyroadway condition survey
roadway condition surveymruemran
 
A Review of "Evaluation of the Need for Highway Redesign and Modernization."
A Review of "Evaluation of the Need for Highway Redesign and Modernization."A Review of "Evaluation of the Need for Highway Redesign and Modernization."
A Review of "Evaluation of the Need for Highway Redesign and Modernization."IRJET Journal
 
Training report of road construction
Training report of road constructionTraining report of road construction
Training report of road constructionManavSinghal8
 

Ähnlich wie project work presentation on road feasibility study (need to be corrected but can be used as reference) (20)

Impact of Transportation System on Land Use in CBD area of Pabna Municipality...
Impact of Transportation System on Land Use in CBD area of Pabna Municipality...Impact of Transportation System on Land Use in CBD area of Pabna Municipality...
Impact of Transportation System on Land Use in CBD area of Pabna Municipality...
 
Impact of Different Types of Land Use on Transportation System of Dhaka City ...
Impact of Different Types of Land Use on Transportation System of Dhaka City ...Impact of Different Types of Land Use on Transportation System of Dhaka City ...
Impact of Different Types of Land Use on Transportation System of Dhaka City ...
 
IRJET- Rural Road Design and Development
IRJET- Rural Road Design and DevelopmentIRJET- Rural Road Design and Development
IRJET- Rural Road Design and Development
 
Identification of Suitable Landfill Site using Geographical Information Syste...
Identification of Suitable Landfill Site using Geographical Information Syste...Identification of Suitable Landfill Site using Geographical Information Syste...
Identification of Suitable Landfill Site using Geographical Information Syste...
 
Rmtsp
RmtspRmtsp
Rmtsp
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Applications of GIS in Municipal Solid Waste Management
Applications of GIS in Municipal Solid Waste ManagementApplications of GIS in Municipal Solid Waste Management
Applications of GIS in Municipal Solid Waste Management
 
Land use planning
Land use planningLand use planning
Land use planning
 
SNEAPA 2013 Friday e2_gis
SNEAPA 2013 Friday e2_gisSNEAPA 2013 Friday e2_gis
SNEAPA 2013 Friday e2_gis
 
Landscape design for multimodal transport corridors
Landscape design for multimodal transport corridorsLandscape design for multimodal transport corridors
Landscape design for multimodal transport corridors
 
BIKE IT MAKATI
BIKE IT MAKATIBIKE IT MAKATI
BIKE IT MAKATI
 
Route optimization of solid waste transportation in part of Lucknow- Capital ...
Route optimization of solid waste transportation in part of Lucknow- Capital ...Route optimization of solid waste transportation in part of Lucknow- Capital ...
Route optimization of solid waste transportation in part of Lucknow- Capital ...
 
Mode choice between roadway and waterway
Mode choice between roadway and waterwayMode choice between roadway and waterway
Mode choice between roadway and waterway
 
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGM
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGMNorthern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGM
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGM
 
Study is to perform roadway condition survey of link road between panthapath ...
Study is to perform roadway condition survey of link road between panthapath ...Study is to perform roadway condition survey of link road between panthapath ...
Study is to perform roadway condition survey of link road between panthapath ...
 
Remote Sensing and GIS-Based Monitoring of Land Use Change in Nagpur District...
Remote Sensing and GIS-Based Monitoring of Land Use Change in Nagpur District...Remote Sensing and GIS-Based Monitoring of Land Use Change in Nagpur District...
Remote Sensing and GIS-Based Monitoring of Land Use Change in Nagpur District...
 
civil engineers project work .docx
civil engineers project work .docxcivil engineers project work .docx
civil engineers project work .docx
 
roadway condition survey
roadway condition surveyroadway condition survey
roadway condition survey
 
A Review of "Evaluation of the Need for Highway Redesign and Modernization."
A Review of "Evaluation of the Need for Highway Redesign and Modernization."A Review of "Evaluation of the Need for Highway Redesign and Modernization."
A Review of "Evaluation of the Need for Highway Redesign and Modernization."
 
Training report of road construction
Training report of road constructionTraining report of road construction
Training report of road construction
 

Kürzlich hochgeladen

CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLManishPatel169454
 

Kürzlich hochgeladen (20)

CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 

project work presentation on road feasibility study (need to be corrected but can be used as reference)

  • 1. -Rakesh Sunari Magar(77) -Pawan Bhatta(65) -Nirajan Dahal(58) -Needesh Budhathoki(56) Prof. Dr. Padma Bahadur Shahi 1
  • 2. Background  As per our syllabus, we fourth year students have to present our final year project in our desired field of interest. It is a vital part of IOE syllabus in order to make students competent to work in the actual field.  We have chosen rural road development project among the number of options available in transportation project.  We want to experience the working technique with new innovative concept of ours while designing a road in a sense of future demand that is structurally, eco- friendly and atheistically designed.2
  • 3. Intro T R A N S P O R T A T I O N  Transportation plays a vital role in basic infrastructure development in mountainous country like Nepal.  It is a social property.  It is demand fulfilling demand. 3
  • 4. Objectives and Scope  To setup an alignment of a road as per the environmental condition.  To consider gradient, earthwork, road components (drainage, retaining walls), geometric properties of the road properly in the design.  To prepare economical and stable road in rural areas.  To link urban and rural areas with comfort, wide, safe, smooth road. 4
  • 5. Objectives and Scope  For the overall development of country.  To minimize the risk of loss of property and lives by designing stable roads.  To know the importance of team work.  To design the road with innovative concept that is structurally, atheistically and eco-friendly aspect. 5
  • 7. METHODOLOGY  Planning  Survey  Preliminary Design  Geometric Design  Detailing  Calculation  Plotting  Modeling  Analysis  Report Preparation 7 The work to be performed while doing our project are listed as series below:
  • 8. Project PERT Chart START Pre synopsis submission Site Selection Reconnaissan ce survey 11 th Nov , 2014 8
  • 9. Survey and data plot Tests of soil samples Computation and design Traffic count 9
  • 11. ROAD SITE Pang Gaun to Tika Bhairav (2.5km) Location:  Zone: Bagmati  District: Lalitpur  VDC: Pang Gaun 11
  • 12. 12
  • 13. MAP STUDY Location :- Where are things situated?  A location can be specific for example, it can be stated as coordinates of longitude and latitude or as a distance from one place to another place. eg. In our case, road site’s location is south east from the valley.  Latitudes/easting are imaginary lines running parallel to the Equator.  Longitudes(departures)/northing are imaginary lines running parallel to the Prime Meridian. 13
  • 14. MAP STUDY 14 Place :- What makes a place different from other places? Differences might be defined in terms of climate, physical features, or the people who live there and their traditions. Human-environment interaction :- What are the relationships among people and places? How have people changed the environment to better suit their needs?
  • 15. SOCIO-ECONOMIC CONDITION  The major caste in this area are newars, brahmin, chhetri, sarkis, etc.  Mainly the people are involved in agriculture.  People are not well educated.  The economic condition is poor.
  • 16. Equipments used in geometric survey GPS (Global Positioning System)  2 numbers  Principle: Satellites based allocation of a position by latitude, departure and elevation. 16
  • 17. Geometric design 17  Profile  Plan  Cross section
  • 18. 18 fig. Plan (central alignment only)
  • 19. Pavement design  Traffic count  CBR test 19
  • 20. Traffic study  A traffic study is an engineering investigation to evaluate a transportation system.  A study typically consists of collecting data, projecting traffic volumes, and identifying the improvements required for the transportation system. 20
  • 21. Traffic Count  A traffic count is a count of traffic along a particular road, either done electronically or by people counting by the side of the road.  Traffic counts can be used by local councils to identify which routes are used most, and to either improve that road or provide an alternative if there is an excessive amount of traffic.
  • 22. Traffic Count Leaving the valley Entering the valley 22 bike car/jeep bus Truck ( unloaded) Truck (loaded) Heavy (tipper) tandem 19 5 2 1 8 1 0 11 2 4 1 3 1 0 8 2 3 4 13 2 1 9 3 1 1 12 0 0 bike car/jeep bus Truck ( unloaded) Truck (loaded) Heavy (tipper) tandem 15 2 4 5 3 0 0 7 4 1 6 0 0 0 11 1 1 2 0 0 0 6 3 6 12 0 0 0 minutes 15 other 15 other 15 other 15 39 10 12 25 3 0 0 47 12 10 7 36 4 1total
  • 23. Therefore, Total traffic volume= 206 vehicles per hour 23
  • 26. 26 CB R = CBR [%] p = measured pressure for site soils [N/mm²] ps = pressure to achieve equal penetration on standard soil [N/mm²]
  • 27. 27 CBR VALUE SUBGRADE STRENGTH 3% and less Poor 3% - 5% Normal 5% - 15% Good
  • 28. CONCLUSION  Geometric analysis of different roads has become evitable in today’s world. So, we are quite interested in indulging us in this research as we have interest towards this subject. Further in Nepal, geometric analysis of roads are to be done and for this we want to prepare ourselves.  We believe that after the completion of this project we are not only capable of geometrically analyzing existing as well as newly prepared roads but also can put forward our suggestions to ensure or increase the safety, strength and durability of the roads. 28
  • 29. design references  Rural Road Standard, DOLIDAR  Pavement Design Guidelines, DOR 29