SlideShare ist ein Scribd-Unternehmen logo
1 von 11
A.4.1.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1, 2, 3 Y 4:

1

3

2

Mu =

53.82 Ton.m

Vu =
0.55

20.37 Ton

A.4.2.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 1, 2, 3 Y 4:

4

1

Mu =

3

2

70.98 Ton.m

d = h-3-(5/8")/2
d=
51.206

Vu =
0.55

1

28.28 Ton

d = h-3-(5/8")/2
d=
51.206

1

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As = Mu/(o*fy*(d-a/2)
As =
0.00
31.109
5%
32.664
-5%
29.553
cantidad de fierros =

As *d-0.17647*As^2/2-Mu/(o*fy)
cm2
Paralelo al trafico se diseña este acero
16 fierros
5/8
@
0.10 cm

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
41.845
cm2
5%
43.9375
-5%
39.753
Paralelo al trafico se diseña este acero
cantidad de fierros =
21 fierros
5/8
@
0.10 cm

Cheque de cuantia maxima:

Cheque de cuantia maxima:

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

p=

0.00608

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
8.608
Fierros =

8.-ACERO TRAS VERS AL S UPERI OR

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
45.4128

VERDADERO

VERDADERO

SI h<= 600 mm

VERDADERO

Fierros =

16
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR

Analisis para un metro

As =

0.00817

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
11.58

12
3/8"
@ 0.125 cm
acero perpendicuar al trafico

As >= 0.75*Ag/fy

p=

7.- DI S EÑO DE ACERO TRANS VERS AL

@

As >= 0.75*Ag/fy

Analisis para un metro

As =
0.33 cm ambos sentidos

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
45.4128

VERDADERO

@

0.33 cm ambos sentidos

4
A.4.3.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 1, 2, 3 Y 4:

1

Mu =

3

2

81.03 Ton.m

Vu =
0.55

31.76 Ton

d = h-3-(5/8")/2
d=
51.206

1
a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
48.355
cm2
5%
50.7723
-5%
45.937
Paralelo al trafico se diseña este acero
cantidad de fierros =
24 fierros
5/8
@
0.10 cm
Cheque de cuantia maxima:
Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214
p=

0.00944

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
13.38
Fierros =

19
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR
As >= 0.75*Ag/fy

Analisis para un metro

As =

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
45.4128

VERDADERO

@

0.33 cm ambos sentidos

4
B.3.1.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1 Y 3 M (+):

1

Mu =

3

2

37.44 Ton.m

Vu =
0.45

27.03 Ton

B.3.1.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 2 Y 4 M (-):

4

1

3

2

Mu =

37.44 Ton.m

d = h-3-(5/8")/2
d=
41.206

Vu =
0.45

1

20.06 Ton

d = h-3-(5/8")/2
d=
41.206

1

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
27.0136 cm2
5%
28.3642
-5%
25.6629
Paralelo al trafico se diseña este acero
cantidad de fierros =
14 fierros
5/8
@
0.10 cm

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
27.0136 cm2
5%
28.3642
-5%
25.6629
Paralelo al trafico se diseña este acero
cantidad de fierros =
14 fierros
5/8
@
0.10 cm

Cheque de cuantia maxima:

Cheque de cuantia maxima:

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

p=

0.00656

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

8.-ACERO TRAS VERS AL S UPERI OR

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

SI h<= 600 mm

VERDADERO

Fierros =

11
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR

Analisis para un metro

As =

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
7.475

11
3/8"
@ 0.125 cm
acero perpendicuar al trafico

As >= 0.75*Ag/fy

0.00656

7.- DI S EÑO DE ACERO TRANS VERS AL

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
7.475
Fierros =

p=

@

As >= 0.75*Ag/fy

Analisis para un metro

As =
0.33 cm ambos sentidos

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4
B.3.1.3.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1 Y 3 M (-):

1

3

2

Mu =

43.53 Ton.m

Vu =
0.45

30.82 Ton

B.3.1.4.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 2 Y 4 M (-):

4

1

3

2

Mu =

43.53 Ton.m

d = h-3-(5/8")/2
d=
41.206

Vu =
0.45

1

23.32 Ton

d = h-3-(5/8")/2
d=
41.206

1

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
31.7493 cm2
5%
33.3368
-5%
30.1619
Paralelo al trafico se diseña este acero
cantidad de fierros =
16 fierros
5/8
@
0.10 cm

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
31.7493 cm2
5%
33.3368
-5%
30.1619
Paralelo al trafico se diseña este acero
cantidad de fierros =
16 fierros
5/8
@
0.10 cm

Cheque de cuantia maxima:

Cheque de cuantia maxima:

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

p=

0.00770

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

p=

0.00770

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL

VERDADERO

SI h<= 600 mm

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
8.785

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
8.785

Fierros =

Fierros =

12
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR
As >= 0.75*Ag/fy

8.-ACERO TRAS VERS AL S UPERI OR

Analisis para un metro

As =

0.4464

Fierros =

1

cm2
3/8"

12
3/8"
@ 0.125 cm
acero perpendicuar al trafico

@

As >= 0.75*Ag/fy

Analisis para un metro

As =
0.33 cm ambos sentidos

0.4464

Fierros =

1

9.- CHEQUEO POR CORTE:

9.- CHEQUEO POR CORTE:

Vs + Vc >= Vu

cm2
3/8"

Vs + Vc >= Vu

0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4
B.3.2.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 1 Y 3 M (+):

1

Mu =

3

2

84.90 Ton.m

Vu =
0.45

20.80 Ton

B.3.2.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 2 Y 4 M (+):

4

1

Mu =

3

2

84.90 Ton.m

d = h-3-(5/8")/2
d=
41.206

Vu =
0.45

18.10 Ton

d = h-3-(5/8")/2
d=
41.206

1

1
a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
67.457
cm2
5%
70.8303
-5%
64.085
Paralelo al trafico se diseña este acero
cantidad de fierros =
34 fierros
5/8
@
0.10 cm

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
67.457
cm2
5%
70.8303
-5%
64.085
Paralelo al trafico se diseña este acero
cantidad de fierros =
34 fierros
5/8
@
0.10 cm

Cheque de cuantia maxima:

Cheque de cuantia maxima:

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

p=

0.01637

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

VERDADERO

26
3/8"
@ 0.125 cm
acero perpendicuar al trafico

As =

Analisis para un metro

0.4464

Fierros =

1

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

SI h<= 600 mm

Fierros =

VERDADERO

26
3/8"
@ 0.125 cm
acero perpendicuar al trafico

@

As >= 0.75*Ag/fy

Analisis para un metro

As =

cm2
3/8"

VERDADERO

8.-ACERO TRAS VERS AL S UPERI OR

8.-ACERO TRAS VERS AL S UPERI OR
As >= 0.75*Ag/fy

0.01637

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
18.67

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
18.67
Fierros =

p=

7.- DI S EÑO DE ACERO TRANS VERS AL

0.33 cm ambos sentidos

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4
B.3.2.3.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 1 Y 3 M (+):

1

3

2

Mu =

54.54 Ton.m

Vu =

B.3.2.4.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 2 Y 4 M (+):

4

34.98 Ton

1

Mu =

3

2

54.54 Ton.m

d = h-3-(5/8")/2
0.45
d=
41.206

Vu =

26.95 Ton

d = h-3-(5/8")/2
0.45
d=
41.206

1

1

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
40.606
cm2
5%
42.6362
-5%
38.576
Paralelo al trafico se diseña este acero
cantidad de fierros =
20 fierros
5/8
@
0.10 cm

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
40.606
cm2
5%
42.6362
-5%
38.576
Paralelo al trafico se diseña este acero
cantidad de fierros =
20 fierros
5/8
@
0.10 cm

Cheque de cuantia maxima:

Cheque de cuantia maxima:

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

p=

0.00985

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

8.-ACERO TRAS VERS AL S UPERI OR

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

SI h<= 600 mm

VERDADERO

Fierros =

16
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR

Analisis para un metro

As =

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST = 27.67 As
Ast =
11.24

16
3/8"
@ 0.125 cm
acero perpendicuar al trafico

As >= 0.75*Ag/fy

0.00985

7.- DI S EÑO DE ACERO TRANS VERS AL

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
11.24
Fierros =

p=

@

As >= 0.75*Ag/fy

Analisis para un metro

As =
0.33 cm ambos sentidos

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4
C.3.1.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1 Y 4 M (+):

1

3

2

Mu =

38.69 Ton.m

Vu =
0.45

26.72 Ton

d = h-3-(5/8")/2
d=
41.206

1
a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
27.9767 cm2
5%
29.3755
-5%
26.5779
Paralelo al trafico se diseña este acero
cantidad de fierros =
14 fierros
5/8
@
0.10 cm
Cheque de cuantia maxima:
Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214
p=

0.00679

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
7.741
Fierros =

11
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR
As >= 0.75*Ag/fy

Analisis para un metro

As =

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4
C.3.1.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 2 Y 3 M (+):

1

3

2

Mu =

26.36 Ton.m

Vu =
0.45

23.13 Ton

C.3.1.3.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1 Y 4 M (-):

4

1

Mu =

44.38 Ton.m

d = h-3-(5/8")/2
d=
41.206

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214
0.00453

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

d = h-3-(5/8")/2
d=
41.206

8.-ACERO TRAS VERS AL S UPERI OR

Fierros =

1

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
VERDADERO

0.00787

@

VERDADERO

0.33 cm ambos sentidos

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
8.97
13
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR
Analisis para un metro

As =

0.4464

Fierros =

cm2
3/8"

p=

7.- DI S EÑO DE ACERO TRANS VERS AL

As >= 0.75*Ag/fy

Analisis para un metro

0.4464

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

Fierros =

7
3/8"
@ 0.125 cm
acero perpendicuar al trafico

As =

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
32.4192 cm2
5%
34.0401
-5%
30.7982
Paralelo al trafico se diseña este acero
cantidad de fierros =
16 fierros
5/8
@
0.10 cm

SI h<= 600 mm

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
5.165

36.5442

Ton

Cheque de cuantia maxima:

Cheque de cuantia maxima:

As >= 0.75*Ag/fy

30.52

1

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
18.665
cm2
5%
19.5983
-5%
17.7318
Paralelo al trafico se diseña este acero
cantidad de fierros =
9
fierros
5/8
@
0.10 cm

Fierros =

Vu =
0.45

1

p=

3

2

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4
C.3.1.4.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 2 Y 3 M (-):

1

3

2

Mu =

35.66 Ton.m

Vu =
0.45

26.73 Ton

C.3.2.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 1 Y 4 M (-):

4

1

Mu =

3

2

49.90 Ton.m

d = h-3-(5/8")/2
d=
41.206

Vu =
0.45

1

30.35 Ton

d = h-3-(5/8")/2
d=
41.206

1

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
25.6498 cm2
5%
26.9322
-5%
24.3673
Paralelo al trafico se diseña este acero
cantidad de fierros =
13 fierros
5/8
@
0.10 cm

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As = Mu/(o*fy*(d-a/2)
As =
0.00
36.825
5%
38.666
-5%
34.984
cantidad de fierros =

As *d-0.17647*As^2/2-Mu/(o*fy)
cm2
Paralelo al trafico se diseña este acero
18 fierros
5/8
@
0.10 cm

Cheque de cuantia maxima:

Cheque de cuantia maxima:

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

p=

0.00622

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

p=

0.00894

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL

VERDADERO

SI h<= 600 mm

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
7.097

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
10.19

Fierros =

Fierros =

10
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR
As >= 0.75*Ag/fy

8.-ACERO TRAS VERS AL S UPERI OR

Analisis para un metro

As =

0.4464

Fierros =

1

cm2
3/8"

14
3/8"
@ 0.125 cm
acero perpendicuar al trafico

@

As >= 0.75*Ag/fy

Analisis para un metro

As =
0.33 cm ambos sentidos

0.4464

Fierros =

1

9.- CHEQUEO POR CORTE:

9.- CHEQUEO POR CORTE:

Vs + Vc >= Vu

cm2
3/8"

Vs + Vc >= Vu

0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4
C.3.2.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 2 Y 3 M (-):

1

Mu =

3

2

36.17 Ton.m

Vu =

24.17 Ton

C.3.3.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 1 Y 4 M (-):

4

1

Mu =

3

2

56.11 Ton.m

d = h-3-(5/8")/2
0.45
d=
41.206

Vu =

34.69 Ton

d = h-3-(5/8")/2
0.45
d=
41.206

1

1

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
26.040
cm2
5%
27.3416
-5%
24.738
Paralelo al trafico se diseña este acero
cantidad de fierros =
13 fierros
5/8
@
0.10 cm

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
41.902
cm2
5%
43.9973
-5%
39.807
Paralelo al trafico se diseña este acero
cantidad de fierros =
21 fierros
5/8
@
0.10 cm

Cheque de cuantia maxima:

Cheque de cuantia maxima:

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

p=

0.00632

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
7.205
Fierros =

8.-ACERO TRAS VERS AL S UPERI OR

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

VERDADERO

SI h<= 600 mm

VERDADERO

Fierros =

16
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR

Analisis para un metro

As =

0.01017

AST < 1750/(L^0.5) <= 50% > As
AST = 27.67 As
Ast =
11.59

10
3/8"
@ 0.125 cm
acero perpendicuar al trafico

As >= 0.75*Ag/fy

p=

7.- DI S EÑO DE ACERO TRANS VERS AL

@

As >= 0.75*Ag/fy

Analisis para un metro

As =
0.33 cm ambos sentidos

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4
C.3.3.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 2 Y 3 M (-):

1

Mu =

3

2

39.08 Ton.m

Vu =

30.72 Ton

d = h-3-(5/8")/2
0.45
d=
41.206
1
a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
28.278
cm2
5%
29.6921
-5%
26.864
Paralelo al trafico se diseña este acero
cantidad de fierros =
14 fierros
5/8
@
0.10 cm
Cheque de cuantia maxima:
Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214
p=

0.00686

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST = 27.67 As
Ast =
7.825
Fierros =

11
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR
As >= 0.75*Ag/fy

Analisis para un metro

As =

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4

Weitere ähnliche Inhalte

Was ist angesagt?

Kites team l5
Kites team l5Kites team l5
Kites team l5
aero103
 
INDUSTRIAL BUILDING GANTRY GIRDER
INDUSTRIAL BUILDING  GANTRY GIRDERINDUSTRIAL BUILDING  GANTRY GIRDER
INDUSTRIAL BUILDING GANTRY GIRDER
Harsh Shani
 
Column sections Classification
Column sections ClassificationColumn sections Classification
Column sections Classification
Kingsley Aboagye
 
Masonry Shear Wall Design-Excel Sheet 2
Masonry Shear Wall Design-Excel Sheet 2Masonry Shear Wall Design-Excel Sheet 2
Masonry Shear Wall Design-Excel Sheet 2
Yongsheng (Jack) Jiao
 

Was ist angesagt? (20)

22-Design of Four Bolt Extended Endplate Connection (Steel Structural Design ...
22-Design of Four Bolt Extended Endplate Connection (Steel Structural Design ...22-Design of Four Bolt Extended Endplate Connection (Steel Structural Design ...
22-Design of Four Bolt Extended Endplate Connection (Steel Structural Design ...
 
Kites team l5
Kites team l5Kites team l5
Kites team l5
 
INDUSTRIAL BUILDING GANTRY GIRDER
INDUSTRIAL BUILDING  GANTRY GIRDERINDUSTRIAL BUILDING  GANTRY GIRDER
INDUSTRIAL BUILDING GANTRY GIRDER
 
Design of isolated footing by ACI code
Design of isolated footing by ACI codeDesign of isolated footing by ACI code
Design of isolated footing by ACI code
 
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
 
Form 1: Measurements
Form 1: MeasurementsForm 1: Measurements
Form 1: Measurements
 
Structural building by engineer abdikani farah ahmed(enggalaydh)
Structural building by engineer abdikani farah ahmed(enggalaydh)Structural building by engineer abdikani farah ahmed(enggalaydh)
Structural building by engineer abdikani farah ahmed(enggalaydh)
 
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
 
Subok pang defense
Subok pang defenseSubok pang defense
Subok pang defense
 
Engineering example calculation
Engineering example calculationEngineering example calculation
Engineering example calculation
 
Undeterminate problems
Undeterminate problemsUndeterminate problems
Undeterminate problems
 
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAPPERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
 
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
 
Chapter 12
Chapter 12Chapter 12
Chapter 12
 
Doubly reinforced beam]
Doubly reinforced beam]Doubly reinforced beam]
Doubly reinforced beam]
 
MasonryShearWall Design-1 Sheet1
MasonryShearWall Design-1 Sheet1MasonryShearWall Design-1 Sheet1
MasonryShearWall Design-1 Sheet1
 
Column sections Classification
Column sections ClassificationColumn sections Classification
Column sections Classification
 
Design of Cantilever retaining wall
Design of Cantilever retaining wallDesign of Cantilever retaining wall
Design of Cantilever retaining wall
 
Masonry Shear Wall Design-Excel Sheet 2
Masonry Shear Wall Design-Excel Sheet 2Masonry Shear Wall Design-Excel Sheet 2
Masonry Shear Wall Design-Excel Sheet 2
 
6. diseño de puente compuesto2
6. diseño de puente compuesto26. diseño de puente compuesto2
6. diseño de puente compuesto2
 

Andere mochten auch

Sarah colina principle 2
Sarah colina principle 2Sarah colina principle 2
Sarah colina principle 2
Anne Acosta
 
Wena ganda chos!
Wena ganda chos!Wena ganda chos!
Wena ganda chos!
Anne Acosta
 
Costs associated with production
Costs associated with productionCosts associated with production
Costs associated with production
Anne Acosta
 
Production and costs concepts
Production and costs  conceptsProduction and costs  concepts
Production and costs concepts
Anne Acosta
 

Andere mochten auch (20)

το κουτι της πανδωρας A
το κουτι της πανδωρας    Aτο κουτι της πανδωρας    A
το κουτι της πανδωρας A
 
4 soal ukk tkj xi istalasi os dasar 2013
4 soal ukk tkj xi istalasi os dasar 20134 soal ukk tkj xi istalasi os dasar 2013
4 soal ukk tkj xi istalasi os dasar 2013
 
Remote detection of illegal usage of electricity
Remote detection of illegal usage of electricityRemote detection of illegal usage of electricity
Remote detection of illegal usage of electricity
 
motoFANkowy tutorial odc. 1
motoFANkowy tutorial odc. 1motoFANkowy tutorial odc. 1
motoFANkowy tutorial odc. 1
 
Common Online Terminologies
Common Online TerminologiesCommon Online Terminologies
Common Online Terminologies
 
motoFANki_2014
motoFANki_2014motoFANki_2014
motoFANki_2014
 
Sarah colina principle 2
Sarah colina principle 2Sarah colina principle 2
Sarah colina principle 2
 
Jamaica accidents
Jamaica   accidentsJamaica   accidents
Jamaica accidents
 
Wena ganda chos!
Wena ganda chos!Wena ganda chos!
Wena ganda chos!
 
motoFANki_2014_coś więcej
motoFANki_2014_coś więcejmotoFANki_2014_coś więcej
motoFANki_2014_coś więcej
 
Presentation1 1
Presentation1 1Presentation1 1
Presentation1 1
 
Costs associated with production
Costs associated with productionCosts associated with production
Costs associated with production
 
Production and costs concepts
Production and costs  conceptsProduction and costs  concepts
Production and costs concepts
 
Step by Step - Reusing old features to build new ones
Step by Step - Reusing old features to build new onesStep by Step - Reusing old features to build new ones
Step by Step - Reusing old features to build new ones
 
E-Mode LNA
E-Mode LNAE-Mode LNA
E-Mode LNA
 
Chop - Shop Barbers, Crane Lane
Chop - Shop Barbers, Crane LaneChop - Shop Barbers, Crane Lane
Chop - Shop Barbers, Crane Lane
 
Edu carex core_module
Edu carex core_moduleEdu carex core_module
Edu carex core_module
 
Nuclear power plant
Nuclear power plantNuclear power plant
Nuclear power plant
 
áóôåéá óïâáñá
áóôåéá óïâáñááóôåéá óïâáñá
áóôåéá óïâáñá
 
Ex.arithmoi
Ex.arithmoiEx.arithmoi
Ex.arithmoi
 

Ähnlich wie Calculo 1

Rcc Design Sheets
Rcc Design SheetsRcc Design Sheets
Rcc Design Sheets
klecivil
 
Foundation Reinforcement Calcs & Connection Calcs
Foundation Reinforcement Calcs & Connection CalcsFoundation Reinforcement Calcs & Connection Calcs
Foundation Reinforcement Calcs & Connection Calcs
Magdel Kotze
 

Ähnlich wie Calculo 1 (20)

Ch 8.pdf
Ch 8.pdfCh 8.pdf
Ch 8.pdf
 
Roof Truss Design (By Hamza Waheed UET Lahore )
Roof Truss Design (By Hamza Waheed UET Lahore )Roof Truss Design (By Hamza Waheed UET Lahore )
Roof Truss Design (By Hamza Waheed UET Lahore )
 
Rcc Design Sheets
Rcc Design SheetsRcc Design Sheets
Rcc Design Sheets
 
Rcc member design steps
Rcc member design stepsRcc member design steps
Rcc member design steps
 
Calculo de acero en vigas ok
Calculo de acero en vigas okCalculo de acero en vigas ok
Calculo de acero en vigas ok
 
Singly R.C. beam
Singly R.C. beam  Singly R.C. beam
Singly R.C. beam
 
Harshal
HarshalHarshal
Harshal
 
طه
طهطه
طه
 
Design calculations of raft foundation
Design calculations of raft foundationDesign calculations of raft foundation
Design calculations of raft foundation
 
onw way slab design
onw way slab designonw way slab design
onw way slab design
 
Design of stairs
Design of stairsDesign of stairs
Design of stairs
 
Baseplate
BaseplateBaseplate
Baseplate
 
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxDESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
 
Design and analysis of school building
Design and analysis of school buildingDesign and analysis of school building
Design and analysis of school building
 
Doubly reinforced beam design
Doubly reinforced beam   designDoubly reinforced beam   design
Doubly reinforced beam design
 
Perancangan Alat Proses Styrene Production
Perancangan Alat Proses Styrene ProductionPerancangan Alat Proses Styrene Production
Perancangan Alat Proses Styrene Production
 
Design of footing
Design of footingDesign of footing
Design of footing
 
Power screw application
Power screw applicationPower screw application
Power screw application
 
Puentes
PuentesPuentes
Puentes
 
Foundation Reinforcement Calcs & Connection Calcs
Foundation Reinforcement Calcs & Connection CalcsFoundation Reinforcement Calcs & Connection Calcs
Foundation Reinforcement Calcs & Connection Calcs
 

Kürzlich hochgeladen

The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 

Kürzlich hochgeladen (20)

How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptx
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 

Calculo 1

  • 1. A.4.1.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1, 2, 3 Y 4: 1 3 2 Mu = 53.82 Ton.m Vu = 0.55 20.37 Ton A.4.2.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 1, 2, 3 Y 4: 4 1 Mu = 3 2 70.98 Ton.m d = h-3-(5/8")/2 d= 51.206 Vu = 0.55 1 28.28 Ton d = h-3-(5/8")/2 d= 51.206 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As = Mu/(o*fy*(d-a/2) As = 0.00 31.109 5% 32.664 -5% 29.553 cantidad de fierros = As *d-0.17647*As^2/2-Mu/(o*fy) cm2 Paralelo al trafico se diseña este acero 16 fierros 5/8 @ 0.10 cm a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 41.845 cm2 5% 43.9375 -5% 39.753 Paralelo al trafico se diseña este acero cantidad de fierros = 21 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00608 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 8.608 Fierros = 8.-ACERO TRAS VERS AL S UPERI OR 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 45.4128 VERDADERO VERDADERO SI h<= 600 mm VERDADERO Fierros = 16 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR Analisis para un metro As = 0.00817 AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 11.58 12 3/8" @ 0.125 cm acero perpendicuar al trafico As >= 0.75*Ag/fy p= 7.- DI S EÑO DE ACERO TRANS VERS AL @ As >= 0.75*Ag/fy Analisis para un metro As = 0.33 cm ambos sentidos 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 45.4128 VERDADERO @ 0.33 cm ambos sentidos 4
  • 2. A.4.3.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 1, 2, 3 Y 4: 1 Mu = 3 2 81.03 Ton.m Vu = 0.55 31.76 Ton d = h-3-(5/8")/2 d= 51.206 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 48.355 cm2 5% 50.7723 -5% 45.937 Paralelo al trafico se diseña este acero cantidad de fierros = 24 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00944 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 13.38 Fierros = 19 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR As >= 0.75*Ag/fy Analisis para un metro As = 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 45.4128 VERDADERO @ 0.33 cm ambos sentidos 4
  • 3. B.3.1.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1 Y 3 M (+): 1 Mu = 3 2 37.44 Ton.m Vu = 0.45 27.03 Ton B.3.1.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 2 Y 4 M (-): 4 1 3 2 Mu = 37.44 Ton.m d = h-3-(5/8")/2 d= 41.206 Vu = 0.45 1 20.06 Ton d = h-3-(5/8")/2 d= 41.206 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 27.0136 cm2 5% 28.3642 -5% 25.6629 Paralelo al trafico se diseña este acero cantidad de fierros = 14 fierros 5/8 @ 0.10 cm a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 27.0136 cm2 5% 28.3642 -5% 25.6629 Paralelo al trafico se diseña este acero cantidad de fierros = 14 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00656 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm 8.-ACERO TRAS VERS AL S UPERI OR 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO SI h<= 600 mm VERDADERO Fierros = 11 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR Analisis para un metro As = VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 7.475 11 3/8" @ 0.125 cm acero perpendicuar al trafico As >= 0.75*Ag/fy 0.00656 7.- DI S EÑO DE ACERO TRANS VERS AL VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 7.475 Fierros = p= @ As >= 0.75*Ag/fy Analisis para un metro As = 0.33 cm ambos sentidos 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4
  • 4. B.3.1.3.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1 Y 3 M (-): 1 3 2 Mu = 43.53 Ton.m Vu = 0.45 30.82 Ton B.3.1.4.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 2 Y 4 M (-): 4 1 3 2 Mu = 43.53 Ton.m d = h-3-(5/8")/2 d= 41.206 Vu = 0.45 1 23.32 Ton d = h-3-(5/8")/2 d= 41.206 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 31.7493 cm2 5% 33.3368 -5% 30.1619 Paralelo al trafico se diseña este acero cantidad de fierros = 16 fierros 5/8 @ 0.10 cm a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 31.7493 cm2 5% 33.3368 -5% 30.1619 Paralelo al trafico se diseña este acero cantidad de fierros = 16 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00770 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm p= 0.00770 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL VERDADERO SI h<= 600 mm VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 8.785 AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 8.785 Fierros = Fierros = 12 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR As >= 0.75*Ag/fy 8.-ACERO TRAS VERS AL S UPERI OR Analisis para un metro As = 0.4464 Fierros = 1 cm2 3/8" 12 3/8" @ 0.125 cm acero perpendicuar al trafico @ As >= 0.75*Ag/fy Analisis para un metro As = 0.33 cm ambos sentidos 0.4464 Fierros = 1 9.- CHEQUEO POR CORTE: 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu cm2 3/8" Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4
  • 5. B.3.2.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 1 Y 3 M (+): 1 Mu = 3 2 84.90 Ton.m Vu = 0.45 20.80 Ton B.3.2.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 2 Y 4 M (+): 4 1 Mu = 3 2 84.90 Ton.m d = h-3-(5/8")/2 d= 41.206 Vu = 0.45 18.10 Ton d = h-3-(5/8")/2 d= 41.206 1 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 67.457 cm2 5% 70.8303 -5% 64.085 Paralelo al trafico se diseña este acero cantidad de fierros = 34 fierros 5/8 @ 0.10 cm a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 67.457 cm2 5% 70.8303 -5% 64.085 Paralelo al trafico se diseña este acero cantidad de fierros = 34 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.01637 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm VERDADERO 26 3/8" @ 0.125 cm acero perpendicuar al trafico As = Analisis para un metro 0.4464 Fierros = 1 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO SI h<= 600 mm Fierros = VERDADERO 26 3/8" @ 0.125 cm acero perpendicuar al trafico @ As >= 0.75*Ag/fy Analisis para un metro As = cm2 3/8" VERDADERO 8.-ACERO TRAS VERS AL S UPERI OR 8.-ACERO TRAS VERS AL S UPERI OR As >= 0.75*Ag/fy 0.01637 AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 18.67 AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 18.67 Fierros = p= 7.- DI S EÑO DE ACERO TRANS VERS AL 0.33 cm ambos sentidos 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4
  • 6. B.3.2.3.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 1 Y 3 M (+): 1 3 2 Mu = 54.54 Ton.m Vu = B.3.2.4.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 2 Y 4 M (+): 4 34.98 Ton 1 Mu = 3 2 54.54 Ton.m d = h-3-(5/8")/2 0.45 d= 41.206 Vu = 26.95 Ton d = h-3-(5/8")/2 0.45 d= 41.206 1 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 40.606 cm2 5% 42.6362 -5% 38.576 Paralelo al trafico se diseña este acero cantidad de fierros = 20 fierros 5/8 @ 0.10 cm a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 40.606 cm2 5% 42.6362 -5% 38.576 Paralelo al trafico se diseña este acero cantidad de fierros = 20 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00985 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm 8.-ACERO TRAS VERS AL S UPERI OR 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO SI h<= 600 mm VERDADERO Fierros = 16 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR Analisis para un metro As = VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 11.24 16 3/8" @ 0.125 cm acero perpendicuar al trafico As >= 0.75*Ag/fy 0.00985 7.- DI S EÑO DE ACERO TRANS VERS AL VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 11.24 Fierros = p= @ As >= 0.75*Ag/fy Analisis para un metro As = 0.33 cm ambos sentidos 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4
  • 7. C.3.1.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1 Y 4 M (+): 1 3 2 Mu = 38.69 Ton.m Vu = 0.45 26.72 Ton d = h-3-(5/8")/2 d= 41.206 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 27.9767 cm2 5% 29.3755 -5% 26.5779 Paralelo al trafico se diseña este acero cantidad de fierros = 14 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00679 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 7.741 Fierros = 11 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR As >= 0.75*Ag/fy Analisis para un metro As = 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4
  • 8. C.3.1.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 2 Y 3 M (+): 1 3 2 Mu = 26.36 Ton.m Vu = 0.45 23.13 Ton C.3.1.3.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1 Y 4 M (-): 4 1 Mu = 44.38 Ton.m d = h-3-(5/8")/2 d= 41.206 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 0.00453 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm d = h-3-(5/8")/2 d= 41.206 8.-ACERO TRAS VERS AL S UPERI OR Fierros = 1 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu VERDADERO 0.00787 @ VERDADERO 0.33 cm ambos sentidos VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 8.97 13 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR Analisis para un metro As = 0.4464 Fierros = cm2 3/8" p= 7.- DI S EÑO DE ACERO TRANS VERS AL As >= 0.75*Ag/fy Analisis para un metro 0.4464 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 Fierros = 7 3/8" @ 0.125 cm acero perpendicuar al trafico As = a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 32.4192 cm2 5% 34.0401 -5% 30.7982 Paralelo al trafico se diseña este acero cantidad de fierros = 16 fierros 5/8 @ 0.10 cm SI h<= 600 mm VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 5.165 36.5442 Ton Cheque de cuantia maxima: Cheque de cuantia maxima: As >= 0.75*Ag/fy 30.52 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 18.665 cm2 5% 19.5983 -5% 17.7318 Paralelo al trafico se diseña este acero cantidad de fierros = 9 fierros 5/8 @ 0.10 cm Fierros = Vu = 0.45 1 p= 3 2 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4
  • 9. C.3.1.4.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 2 Y 3 M (-): 1 3 2 Mu = 35.66 Ton.m Vu = 0.45 26.73 Ton C.3.2.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 1 Y 4 M (-): 4 1 Mu = 3 2 49.90 Ton.m d = h-3-(5/8")/2 d= 41.206 Vu = 0.45 1 30.35 Ton d = h-3-(5/8")/2 d= 41.206 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 25.6498 cm2 5% 26.9322 -5% 24.3673 Paralelo al trafico se diseña este acero cantidad de fierros = 13 fierros 5/8 @ 0.10 cm a = As*fy/(0.85*f¨c*b) a= 0.176 As As = Mu/(o*fy*(d-a/2) As = 0.00 36.825 5% 38.666 -5% 34.984 cantidad de fierros = As *d-0.17647*As^2/2-Mu/(o*fy) cm2 Paralelo al trafico se diseña este acero 18 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00622 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm p= 0.00894 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL VERDADERO SI h<= 600 mm VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 7.097 AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 10.19 Fierros = Fierros = 10 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR As >= 0.75*Ag/fy 8.-ACERO TRAS VERS AL S UPERI OR Analisis para un metro As = 0.4464 Fierros = 1 cm2 3/8" 14 3/8" @ 0.125 cm acero perpendicuar al trafico @ As >= 0.75*Ag/fy Analisis para un metro As = 0.33 cm ambos sentidos 0.4464 Fierros = 1 9.- CHEQUEO POR CORTE: 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu cm2 3/8" Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4
  • 10. C.3.2.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 2 Y 3 M (-): 1 Mu = 3 2 36.17 Ton.m Vu = 24.17 Ton C.3.3.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 1 Y 4 M (-): 4 1 Mu = 3 2 56.11 Ton.m d = h-3-(5/8")/2 0.45 d= 41.206 Vu = 34.69 Ton d = h-3-(5/8")/2 0.45 d= 41.206 1 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 26.040 cm2 5% 27.3416 -5% 24.738 Paralelo al trafico se diseña este acero cantidad de fierros = 13 fierros 5/8 @ 0.10 cm a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 41.902 cm2 5% 43.9973 -5% 39.807 Paralelo al trafico se diseña este acero cantidad de fierros = 21 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00632 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 7.205 Fierros = 8.-ACERO TRAS VERS AL S UPERI OR 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO VERDADERO SI h<= 600 mm VERDADERO Fierros = 16 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR Analisis para un metro As = 0.01017 AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 11.59 10 3/8" @ 0.125 cm acero perpendicuar al trafico As >= 0.75*Ag/fy p= 7.- DI S EÑO DE ACERO TRANS VERS AL @ As >= 0.75*Ag/fy Analisis para un metro As = 0.33 cm ambos sentidos 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4
  • 11. C.3.3.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 2 Y 3 M (-): 1 Mu = 3 2 39.08 Ton.m Vu = 30.72 Ton d = h-3-(5/8")/2 0.45 d= 41.206 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 28.278 cm2 5% 29.6921 -5% 26.864 Paralelo al trafico se diseña este acero cantidad de fierros = 14 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00686 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 7.825 Fierros = 11 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR As >= 0.75*Ag/fy Analisis para un metro As = 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4