SlideShare ist ein Scribd-Unternehmen logo
1 von 11
Chapter 1
1. Which of the following is NOT a common feature of adaptive project management?
A. Iterative product development
B. Large amounts of upfront planning
C. Reduced time-to-market
D. Flexible product delivery
Answer: B Justification: Adaptive project management focuses on less upfront
planning, unlike Waterfall methods. This creates a fairly adaptable environment for
teams where they focus on only the immediate tasks at hand, complete them, and then
move to the next tasks. If there are any changes in requirements, then they are
incorporated into the next Sprint.
2. You are the CEO of a company operating four different projects. For which project
would you
implement Agile methodologies?
A. Constructing a 5-story apartment building with 6 apartments per floor
B. Working on the tenth stage of a long-term software implementation project in which
the project requirements were clearly defined and the delivery has, so far, met these
requirements
C. Developing software technology for a customer for a change management exercise
involving identifying the current as-is practices and developing a road-map for the tobe
process depending on the vision of the management team
D. Constructing an automobile in a factory based on a pre-developed prototype
Answer: C Justification: The key is to identify the amount of risk and uncertainty
involved in the project. Routine, low-risk projects with specific requirements can be
completed using the Waterfall technique. Projects involving a high degree of complexity,
and those in which there is a good chance that the requirements will change, should be
completed using Agile and Scrum.
3. Which of the following is NOT part of the Agile Manifesto?
A. Promote individuals over processes
B. Respond to change rather than make long-term plans
C. Have a specialized team rather than a cross-functional team
D. Working software is more important than comprehensive documentation
Answer: C Justification: Adaptive project development focuses on the cross-functional
nature of the teams. It is important to have cross-functional teams for clear and
transparent communication and smooth project progress.
4. As a project manager employing Agile practices in your organization, which of the
following
principles would you NOT employ?
A. Business and technical employees should work together.
B. Document every detail of new software before allowing its release.
C. Maintain colocated teams and promote face-to-face communication.
D. Welcome changing requirements, even late in development.
Answer: B Justification: Even though it is a good practice to try to document every detail
possible, it is more important to deliver working software at the end of each Sprint.
Because Agile process are Timeboxed, there may not be enough time to document
before the end of the Sprint. Most of the time,detailed documentation consumes a lot of
time while providing very little additional benefits, and a delayed release of the product
causes more harm.
5. Which of the following is NOT true regarding Agile methodologies?
A. Agile emphasizes people rather than processes.
B. Agile promotes minimal documentation, unlike the Waterfall technique.
C. Agile recommends a command-based leadership style.
D. Agile techniques focus on the adaptability of the project.
Answer: C Justification: Agile recommends a Servant Leadership style with high
degrees of collaboration and empowered teams.
6. Empirical process control is a Scrum principle that
A. is used in cases in which inputs are clearly defined.
B. focuses on providing control through frequent inspections and adaptations of
processes that are perfectly defined.
C. is employed in situations in which the processes generate unpredictable and
unrepeatable outputs.
D. is useful when a particular input always provides a specific output.
Answer: C Justification: While Empirical process control uses frequent inspections and
adaptations, it is more useful in and focused on volatile environments where the
requirements and the desired outputs are not clearly defined.
7. All the following are part of the Scrum principles EXCEPT:
A. Self-organization
B. Time-boxing
C. Value-based Prioritization
D. Defined process control
Answer: D Justification: Scrum uses Empirical Process Control.
8. Scrum projects are NOT applicable in which of the following environments?
A. Developing cutting-edge products
B. Frequently changing requirements
C. Volatile and hypercompetitive markets
D. None of the above
Answer: D Justification: A, B, and C list the environments where Scrum would be most
successful.
9. Product development using Scrum results in which of the following?
A. Transparency across the Scrum Team and Stakeholders
B. Adaptive product development environment
C. Features offering maximum business value are developed first
D. All of the above
Answer: D Justification: Scrum is designed such that provides transparency, so the
client can observe the work done at the end of each Sprint and continuously provide his
or her feedback.
10. Prioritized delivery in Scrum means which of the following:
A. Features that are the simplest and would not require much involvement from the
team will be completed first.
B. Features with the least or no interdependencies will be completed first to ensure
smooth and uninterrupted delivery.
C. Features that provide maximum business value will be completed first.
D. Features are developed on a first-in, first-out basis.
Answer: C Justification: The Product Owner prioritizes the Prioritized Product Backlog
according to business value. Therefore, the features that provide the most business
value are developed first.
Chapter 2
1. Which of the following is a core Scrum role?
A. Product Owner
B. Stakeholder
C. Project sponsor
D. Project manager
Answer: A
2. Who among the following is responsible for providing the Scrum Team with a
favorable environment for creating deliverables?
A. Scrum Master
B. Product Owner
C. Scrum Guidance Body
D. External stakeholders
Answer: A
3. Who among the following is responsible for creating an awareness of Scrum
practices among Scrum Team members?
A. Scrum Master
B. Product Owner
C. Scrum Team
D. Scrum Guidance Body
Answer: A
4. Who among the following is responsible for achieving the maximum business value of
the project?
A. Scrum Master
B. Product Owner
C. Scrum Team
D. External Stakeholders
Answer: B
5. Who among the following is responsible for creating deliverables in the Create
Deliverables process?
A. Chief Scrum Master
B. Portfolio Product Owner
C. Scrum Team leader
D. Scrum Team
Answer: D Justification: The Scrum Team is designed to be a group of self-motivated
individuals working together to reach a common objective. Scrum promotes team work
and collective responsibility as well as discouraging hierarchy among Scrum Team
members. Therefore, he Scrum Team as a whole is responsible for completing the
work.
6. The advantages of using a cross-functional team are
A. improved communication between members of the team.
B. faster decision making.
C. individual responsibility can be assigned to each member of the team depending
on their expertise.
D. both A and B.
Answer: D Justification: Scrum focuses on collective ownership, which means that
everyone needs to proactively participate in decision making and communicating. This
can speed up decision making and improve communication within the team.
7. Who among the following is responsible for deciding on the Acceptance Criteria for
various tasks?
A. Scrum Master
B. Product Owner
C. Scrum Team leader
D. Scrum Team
Answer: B
8. Who among the following represents the Voice of the Customer?
A. Chief Scrum Master
B. Product Owner
C. Scrum Team leader
D. Scrum Team members
Answer: B
9. Jason is responsible for resolving conflicts among Scrum Team members. What role
is he playing on a Scrum project?
A. Scrum Master
B. Product Owner
C. Scrum Team leader
D. Scrum Team
Answer: A
Chapter 3
1. The prioritized set of work to be done is known as
A. a User Story.
B. the Prioritized Product Backlog.
C. a Burndown chart.
D. accepted deliverables.
Answer: B
2. Which of the following is the definition of a User Story?
A. A statement describing the Product Vision
B. A document describing the priority of tasks to be completed in the project
C. A statement that expresses the desired end user functionality
D. A story providing information on similar tasks completed in previous Scrum
implementation projects
Answer: C
3. How are the Prioritized Product Backlog items arranged?
A. The smallest items are at the top.
B. The items with the least interdependencies are at the top.
C. The most complex items are at the top.
D. The items with the highest business value are at the top.
Answer: D
4. Who is responsible for creating User Stories in the Develop User Stories process?
A. Scrum Master
B. Product Owner
C. Scrum Team
D. Stakeholders
Answer: B
5. The responsibility for estimating items in the Prioritized Product Backlog in the Plan
and Estimate phase lies with the
A. Scrum Team.
B. Scrum Master.
C. Product Owner.
D. External team with considerable experience.
Answer: A
6. Which of the following is NOT an input to the Ship Deliverables process?
A. Accepted Deliverables
B. Release Planning Schedule
C. Product Owner
D. Impediment Log
Answer: D
7. How often are the Prioritized Product Backlog priorities changed?
A. Never
B. Whenever the Product Owner decides that an item has to be assigned higher
priority
C. Whenever the Scrum Master believes that an item has to be added
D. When senior management feels an item has to be added
Answer: B Justification: The Product Owner has the final say regarding any items that
have to be added to the Prioritized Product Backlog.
8. Which of the following tools is used by the Scrum Team to estimate Tasks in the
Estimate Tasks process?
A. User Story Writing Expertise
B. Wideband Delphi
C. Paired Comparison
D. JAD Sessions
Answer: B Justification: Wideband Delphi is a consensus-based technique used to
estimate tasks in the Estimate Tasks process.
9. Which of the following statements is NOT true?
A. Team velocity is a measure of the amount of work that a team can complete in a
Sprint.
B. Historical team velocity is used as an indicator when assigning tasks for each Sprint.
C. Team velocity is independent of team composition.
D. Team velocity is used in deciding release deadlines.
Answer: C Justification: Team velocity is unique to the composition of the team. Even
changing a person’s role can affect team velocity.
10. Which of the following is NOT discussed in a Daily Standup Meeting?
A. What the team member has accomplished since the last meeting
B. What the team member plans to work on until the next meeting
C. What the team member has learned from completing his or her work
D. What roadblocks the team member is facing
Answer: C
11. What is the duration of a typical Daily Standup Meeting?
A. 5 minutes
B. 1 hour
C. 15 minutes
D. Stand-up Meetings aren’t Time-boxed.
Answer: C Justification: The Daily Standup Meeting is Time-boxed to 15 minutes for the
general recommended team size (5–9 members) but might vary in proportion to team
size.
12. Ensuring that the Daily Standup Meetings are run in a timely and structured manner
is the responsibility of the
A. Scrum Master.
B. Product Owner.
C. Scrum Team Leader.
D. Group collectively.
Answer: A
13. The Sprint Burndown Chart is a tool used by teams to
A. Measure the work completed during a Sprint.
B. Measure the work left to be completed during a Sprint.
C. Calculate the amount of the team’s budget remaining.
D. Identify low-performing team members.
Answer: B Justification: The Sprint Burndown chart measures the work left to be
completed rather than work completed.
14. The meeting in which the team discusses the tasks to be completed in the next
Sprint is
known as the
A. Product Vision Meeting.
B. Sprint Planning Meeting.
C. Sprint Review Meeting.
D. Retrospect Sprint Meeting.
Answer: B
15. The meeting at the end of the Sprint in which the team presents its work to the
Product Owner is known as the
A. Product Vision Meeting.
B. Sprint Planning Meeting.
C. Sprint Review Meeting.
D. Retrospect Sprint Meeting.
Answer: C
16. The meeting in which the team analyzes the previous Sprint and identifies potential
process improvements is known as the
A. Product Vision Meeting.
B. Sprint Planning Meeting.
C. Sprint Review Meeting.
D. Retrospect Sprint Meeting.
Answer: D
17. During the Sprint Review Meeting,
A. the team presents the end product among themselves.
B. the Scrum Master can accept or reject the end product deliverable.
C. the team presents the end product deliverable to the Product Owner.
D. each team member can accept or reject the end product deliverable.
Answer: C
18. Which of the following activities is NOT a part of the Retrospect Sprint Meeting?
A. The team discusses the positives and negatives from the previous Sprint.
B. The team identifies issues faced in the previous Sprint and discusses how to
mitigate these issues in future Sprints.
C. The team reviews and identifies potential improvements to its functioning.
D. Based on suggested changes, the team proceeds to reprioritize the Prioritized
Product Backlog.
Answer: D
19. The advantages of the Groom the Prioritized Product Backlog process are the
following:
A. Knowledge gained from a previous Sprint is incorporated into future Sprints.
B. The latest business and technical requirements are added to the next Sprint.
C. Grooming ensures that the Prioritized Product Backlog is refined before the
Sprint Planning Meeting so that the team has a better idea of the requirements prior to
the meeting.
D. All of the above.
Answer: D
20. The responsibility of grooming the Prioritized Product Backlog lies with the
A. Product Owner.
B. Scrum Master.
C. Scrum Team.
D. External stakeholders.
Answer: A
21. Which of the following activities can be performed together during the Sprint
Planning Meeting?
A. Tasks Estimation and Release Planning
B. Product Backlog grooming and Task Planning
C. Task Planning and Tasks Estimation
D. Release Planning and Product Backlog grooming
Answer: C
22. Which of the following is NOT a part of the Sprint Planning Meeting?
A. The Product Owner explains the top Prioritized Product Backlog items to the
team.
B. The Scrum Team, in consultation with the Product Owner, estimates the tasks for
a given Sprint.
C. Based on estimates, the team commits to a few tasks to be completed in the next
Sprint.
D. The team gets feedback from Stakeholders.
Answer: D
23. You are a member of a Scrum Team, and you are instructed by the general
manager of your company to work on an urgent task that is not part of the current
Sprint. What do you do?
A. Take responsibility for the task, and tell the Product Owner to postpone the deadline
for the current Sprint.
B. Talk to the Scrum Master, and tell him or her to re-assign your tasks to someone
else.
C. Talk to the Product Owner, and tell him or her to re-assign your tasks to someone
else.
D. Inform the Scrum Master of the situation, and let him or her discuss the situation with
the GM.
E. Take no action because you are already busy.
Answer: D
24. For any ongoing Sprint, when can new User Stories be added?
A. When the Scrum Master adds the User Story to the Sprint Backlog
B. When the Product Owner approves the User Story
C. When the Scrum team approves the User Story
D. New User Stories can never be added to the Sprint
Answer: D Justification: The tasks of a current Sprint are never changed. If the
requirement is urgent, then the current Sprint should be cancelled and a new Sprint
should incorporate the requirements. However, the team keeps a list of additional tasks
that can be taken on if the team is able to complete tasks in a particular Sprint ahead of
time.
25. Acceptance criteria
A. Increases ambiguity regarding requirements.
B. Helps the team adhere to the quality norms regarding functionality.
C. Is determined by the Scrum Master in consultation with the team members.
D. Is determined by the Scrum Master in consultation with the Product Owner.
Answer: B
26. In which of the following processes in the Initiate phase is the length of the Sprint
determined?
A. Create Project Vision
B. Develop Epic(s)
C. Create Prioritized Product Backlog
D. Conduct Release Planning
Answer: D Justification: The duration of the Sprint is decided in the Conduct Release
Planning process.

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (20)

Agile Waterfall - Advantages & Disadvantages
Agile Waterfall - Advantages & DisadvantagesAgile Waterfall - Advantages & Disadvantages
Agile Waterfall - Advantages & Disadvantages
 
Scrum introduction
Scrum introductionScrum introduction
Scrum introduction
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
 
How to facilitate product backlog refinement sessions
How to facilitate product backlog refinement sessionsHow to facilitate product backlog refinement sessions
How to facilitate product backlog refinement sessions
 
Agile - Essential Scrum
Agile - Essential ScrumAgile - Essential Scrum
Agile - Essential Scrum
 
화해 제품팀이 일하는 방법
화해 제품팀이 일하는 방법화해 제품팀이 일하는 방법
화해 제품팀이 일하는 방법
 
Designing your kanban board to map your process
Designing your kanban board to map your processDesigning your kanban board to map your process
Designing your kanban board to map your process
 
Pgmp Certification Overview
Pgmp Certification OverviewPgmp Certification Overview
Pgmp Certification Overview
 
Scrum refinement
Scrum refinementScrum refinement
Scrum refinement
 
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...Project Management Fundamentals | Project Management Simplified | PMP® Traini...
Project Management Fundamentals | Project Management Simplified | PMP® Traini...
 
PMI-PgMP Application Development
PMI-PgMP Application DevelopmentPMI-PgMP Application Development
PMI-PgMP Application Development
 
Scrum training-manual 1
Scrum training-manual 1 Scrum training-manual 1
Scrum training-manual 1
 
Webaula 52 - Agile PMO e a transformação organizacional pela agilidade
Webaula 52 - Agile PMO e a transformação organizacional pela agilidadeWebaula 52 - Agile PMO e a transformação organizacional pela agilidade
Webaula 52 - Agile PMO e a transformação organizacional pela agilidade
 
Scrum values
Scrum valuesScrum values
Scrum values
 
Proposed Project Management Office
Proposed Project Management OfficeProposed Project Management Office
Proposed Project Management Office
 
Waterfall vs Agile : A Beginner's Guide in Project Management
Waterfall vs Agile : A Beginner's Guide in Project ManagementWaterfall vs Agile : A Beginner's Guide in Project Management
Waterfall vs Agile : A Beginner's Guide in Project Management
 
Project Scope Management | Project Management Tutorial | PMP® Certification T...
Project Scope Management | Project Management Tutorial | PMP® Certification T...Project Scope Management | Project Management Tutorial | PMP® Certification T...
Project Scope Management | Project Management Tutorial | PMP® Certification T...
 
Backlog Grooming - The Importance of Good Grooming Habits
Backlog Grooming - The Importance of Good Grooming HabitsBacklog Grooming - The Importance of Good Grooming Habits
Backlog Grooming - The Importance of Good Grooming Habits
 
Scrum in a nutshell
Scrum in a nutshellScrum in a nutshell
Scrum in a nutshell
 
Product Management framework
Product Management frameworkProduct Management framework
Product Management framework
 

Andere mochten auch (6)

Comparison
ComparisonComparison
Comparison
 
Taller scrum-agiles
Taller scrum-agilesTaller scrum-agiles
Taller scrum-agiles
 
Professional Scrum Product Owner I (PSPO-I)
Professional Scrum Product Owner I (PSPO-I)Professional Scrum Product Owner I (PSPO-I)
Professional Scrum Product Owner I (PSPO-I)
 
Chap 5 Estimating Project Times
Chap 5 Estimating Project TimesChap 5 Estimating Project Times
Chap 5 Estimating Project Times
 
Estimating Time & Costs
 Estimating Time & Costs Estimating Time & Costs
Estimating Time & Costs
 
My practice teaching portfolio
My practice teaching portfolioMy practice teaching portfolio
My practice teaching portfolio
 

Ähnlich wie Workbook answers

1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
jackiewalcutt
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
Daniel Hucks
 
Top success factors for successful agile delivery
Top success factors for successful agile deliveryTop success factors for successful agile delivery
Top success factors for successful agile delivery
Wipro
 
Mb5 858-q&a-demo-cert magic
Mb5 858-q&a-demo-cert magicMb5 858-q&a-demo-cert magic
Mb5 858-q&a-demo-cert magic
nikol
 

Ähnlich wie Workbook answers (20)

paperscrum
paperscrumpaperscrum
paperscrum
 
2016 bookmatter ace_thepmi-acp_exam
2016 bookmatter ace_thepmi-acp_exam2016 bookmatter ace_thepmi-acp_exam
2016 bookmatter ace_thepmi-acp_exam
 
Pmi acp-q&a-demo-cert magic
Pmi acp-q&a-demo-cert magicPmi acp-q&a-demo-cert magic
Pmi acp-q&a-demo-cert magic
 
Scrum.Pre_.PSM-II.by_.VCEplus.180q-DEMO.pdf
Scrum.Pre_.PSM-II.by_.VCEplus.180q-DEMO.pdfScrum.Pre_.PSM-II.by_.VCEplus.180q-DEMO.pdf
Scrum.Pre_.PSM-II.by_.VCEplus.180q-DEMO.pdf
 
Pmi acp exa- pmi agile certified practitioner
Pmi acp exa- pmi agile certified practitionerPmi acp exa- pmi agile certified practitioner
Pmi acp exa- pmi agile certified practitioner
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
 
Pmp questions and explanations
Pmp questions and explanationsPmp questions and explanations
Pmp questions and explanations
 
910 - Questions.pdf
910 - Questions.pdf910 - Questions.pdf
910 - Questions.pdf
 
Ctfl at - questões - ingles (1)
Ctfl   at - questões - ingles (1)Ctfl   at - questões - ingles (1)
Ctfl at - questões - ingles (1)
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions Complete
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
 
PMI ACP Classroom Question Paper
PMI ACP Classroom Question PaperPMI ACP Classroom Question Paper
PMI ACP Classroom Question Paper
 
Top success factors for successful agile delivery
Top success factors for successful agile deliveryTop success factors for successful agile delivery
Top success factors for successful agile delivery
 
Sample Agile Scrum Certification Exam Questions
Sample Agile Scrum Certification Exam QuestionsSample Agile Scrum Certification Exam Questions
Sample Agile Scrum Certification Exam Questions
 
SASM4_Sample.pdf
SASM4_Sample.pdfSASM4_Sample.pdf
SASM4_Sample.pdf
 
1
11
1
 
PMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with AnswersPMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with Answers
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdf
 
Mb5 858-q&a-demo-cert magic
Mb5 858-q&a-demo-cert magicMb5 858-q&a-demo-cert magic
Mb5 858-q&a-demo-cert magic
 

Kürzlich hochgeladen

AI Mastery 201: Elevating Your Workflow with Advanced LLM Techniques
AI Mastery 201: Elevating Your Workflow with Advanced LLM TechniquesAI Mastery 201: Elevating Your Workflow with Advanced LLM Techniques
AI Mastery 201: Elevating Your Workflow with Advanced LLM Techniques
VictorSzoltysek
 
The title is not connected to what is inside
The title is not connected to what is insideThe title is not connected to what is inside
The title is not connected to what is inside
shinachiaurasa2
 
TECUNIQUE: Success Stories: IT Service provider
TECUNIQUE: Success Stories: IT Service providerTECUNIQUE: Success Stories: IT Service provider
TECUNIQUE: Success Stories: IT Service provider
mohitmore19
 
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
masabamasaba
 
introduction-to-automotive Andoid os-csimmonds-ndctechtown-2021.pdf
introduction-to-automotive Andoid os-csimmonds-ndctechtown-2021.pdfintroduction-to-automotive Andoid os-csimmonds-ndctechtown-2021.pdf
introduction-to-automotive Andoid os-csimmonds-ndctechtown-2021.pdf
VishalKumarJha10
 
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICECHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Kürzlich hochgeladen (20)

%in kempton park+277-882-255-28 abortion pills for sale in kempton park
%in kempton park+277-882-255-28 abortion pills for sale in kempton park %in kempton park+277-882-255-28 abortion pills for sale in kempton park
%in kempton park+277-882-255-28 abortion pills for sale in kempton park
 
AI Mastery 201: Elevating Your Workflow with Advanced LLM Techniques
AI Mastery 201: Elevating Your Workflow with Advanced LLM TechniquesAI Mastery 201: Elevating Your Workflow with Advanced LLM Techniques
AI Mastery 201: Elevating Your Workflow with Advanced LLM Techniques
 
VTU technical seminar 8Th Sem on Scikit-learn
VTU technical seminar 8Th Sem on Scikit-learnVTU technical seminar 8Th Sem on Scikit-learn
VTU technical seminar 8Th Sem on Scikit-learn
 
The title is not connected to what is inside
The title is not connected to what is insideThe title is not connected to what is inside
The title is not connected to what is inside
 
Announcing Codolex 2.0 from GDK Software
Announcing Codolex 2.0 from GDK SoftwareAnnouncing Codolex 2.0 from GDK Software
Announcing Codolex 2.0 from GDK Software
 
TECUNIQUE: Success Stories: IT Service provider
TECUNIQUE: Success Stories: IT Service providerTECUNIQUE: Success Stories: IT Service provider
TECUNIQUE: Success Stories: IT Service provider
 
Architecture decision records - How not to get lost in the past
Architecture decision records - How not to get lost in the pastArchitecture decision records - How not to get lost in the past
Architecture decision records - How not to get lost in the past
 
%in Bahrain+277-882-255-28 abortion pills for sale in Bahrain
%in Bahrain+277-882-255-28 abortion pills for sale in Bahrain%in Bahrain+277-882-255-28 abortion pills for sale in Bahrain
%in Bahrain+277-882-255-28 abortion pills for sale in Bahrain
 
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
 
%in tembisa+277-882-255-28 abortion pills for sale in tembisa
%in tembisa+277-882-255-28 abortion pills for sale in tembisa%in tembisa+277-882-255-28 abortion pills for sale in tembisa
%in tembisa+277-882-255-28 abortion pills for sale in tembisa
 
introduction-to-automotive Andoid os-csimmonds-ndctechtown-2021.pdf
introduction-to-automotive Andoid os-csimmonds-ndctechtown-2021.pdfintroduction-to-automotive Andoid os-csimmonds-ndctechtown-2021.pdf
introduction-to-automotive Andoid os-csimmonds-ndctechtown-2021.pdf
 
%in Midrand+277-882-255-28 abortion pills for sale in midrand
%in Midrand+277-882-255-28 abortion pills for sale in midrand%in Midrand+277-882-255-28 abortion pills for sale in midrand
%in Midrand+277-882-255-28 abortion pills for sale in midrand
 
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICECHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
 
Microsoft AI Transformation Partner Playbook.pdf
Microsoft AI Transformation Partner Playbook.pdfMicrosoft AI Transformation Partner Playbook.pdf
Microsoft AI Transformation Partner Playbook.pdf
 
%in Harare+277-882-255-28 abortion pills for sale in Harare
%in Harare+277-882-255-28 abortion pills for sale in Harare%in Harare+277-882-255-28 abortion pills for sale in Harare
%in Harare+277-882-255-28 abortion pills for sale in Harare
 
Crypto Cloud Review - How To Earn Up To $500 Per DAY Of Bitcoin 100% On AutoP...
Crypto Cloud Review - How To Earn Up To $500 Per DAY Of Bitcoin 100% On AutoP...Crypto Cloud Review - How To Earn Up To $500 Per DAY Of Bitcoin 100% On AutoP...
Crypto Cloud Review - How To Earn Up To $500 Per DAY Of Bitcoin 100% On AutoP...
 
Right Money Management App For Your Financial Goals
Right Money Management App For Your Financial GoalsRight Money Management App For Your Financial Goals
Right Money Management App For Your Financial Goals
 
%in ivory park+277-882-255-28 abortion pills for sale in ivory park
%in ivory park+277-882-255-28 abortion pills for sale in ivory park %in ivory park+277-882-255-28 abortion pills for sale in ivory park
%in ivory park+277-882-255-28 abortion pills for sale in ivory park
 
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
call girls in Vaishali (Ghaziabad) 🔝 >༒8448380779 🔝 genuine Escort Service 🔝✔️✔️
 
Chinsurah Escorts ☎️8617697112 Starting From 5K to 15K High Profile Escorts ...
Chinsurah Escorts ☎️8617697112  Starting From 5K to 15K High Profile Escorts ...Chinsurah Escorts ☎️8617697112  Starting From 5K to 15K High Profile Escorts ...
Chinsurah Escorts ☎️8617697112 Starting From 5K to 15K High Profile Escorts ...
 

Workbook answers

  • 1. Chapter 1 1. Which of the following is NOT a common feature of adaptive project management? A. Iterative product development B. Large amounts of upfront planning C. Reduced time-to-market D. Flexible product delivery Answer: B Justification: Adaptive project management focuses on less upfront planning, unlike Waterfall methods. This creates a fairly adaptable environment for teams where they focus on only the immediate tasks at hand, complete them, and then move to the next tasks. If there are any changes in requirements, then they are incorporated into the next Sprint. 2. You are the CEO of a company operating four different projects. For which project would you implement Agile methodologies? A. Constructing a 5-story apartment building with 6 apartments per floor B. Working on the tenth stage of a long-term software implementation project in which the project requirements were clearly defined and the delivery has, so far, met these requirements C. Developing software technology for a customer for a change management exercise involving identifying the current as-is practices and developing a road-map for the tobe process depending on the vision of the management team D. Constructing an automobile in a factory based on a pre-developed prototype Answer: C Justification: The key is to identify the amount of risk and uncertainty involved in the project. Routine, low-risk projects with specific requirements can be completed using the Waterfall technique. Projects involving a high degree of complexity, and those in which there is a good chance that the requirements will change, should be completed using Agile and Scrum. 3. Which of the following is NOT part of the Agile Manifesto? A. Promote individuals over processes B. Respond to change rather than make long-term plans C. Have a specialized team rather than a cross-functional team D. Working software is more important than comprehensive documentation Answer: C Justification: Adaptive project development focuses on the cross-functional nature of the teams. It is important to have cross-functional teams for clear and transparent communication and smooth project progress.
  • 2. 4. As a project manager employing Agile practices in your organization, which of the following principles would you NOT employ? A. Business and technical employees should work together. B. Document every detail of new software before allowing its release. C. Maintain colocated teams and promote face-to-face communication. D. Welcome changing requirements, even late in development. Answer: B Justification: Even though it is a good practice to try to document every detail possible, it is more important to deliver working software at the end of each Sprint. Because Agile process are Timeboxed, there may not be enough time to document before the end of the Sprint. Most of the time,detailed documentation consumes a lot of time while providing very little additional benefits, and a delayed release of the product causes more harm. 5. Which of the following is NOT true regarding Agile methodologies? A. Agile emphasizes people rather than processes. B. Agile promotes minimal documentation, unlike the Waterfall technique. C. Agile recommends a command-based leadership style. D. Agile techniques focus on the adaptability of the project. Answer: C Justification: Agile recommends a Servant Leadership style with high degrees of collaboration and empowered teams. 6. Empirical process control is a Scrum principle that A. is used in cases in which inputs are clearly defined. B. focuses on providing control through frequent inspections and adaptations of processes that are perfectly defined. C. is employed in situations in which the processes generate unpredictable and unrepeatable outputs. D. is useful when a particular input always provides a specific output. Answer: C Justification: While Empirical process control uses frequent inspections and adaptations, it is more useful in and focused on volatile environments where the requirements and the desired outputs are not clearly defined. 7. All the following are part of the Scrum principles EXCEPT: A. Self-organization B. Time-boxing C. Value-based Prioritization D. Defined process control Answer: D Justification: Scrum uses Empirical Process Control.
  • 3. 8. Scrum projects are NOT applicable in which of the following environments? A. Developing cutting-edge products B. Frequently changing requirements C. Volatile and hypercompetitive markets D. None of the above Answer: D Justification: A, B, and C list the environments where Scrum would be most successful. 9. Product development using Scrum results in which of the following? A. Transparency across the Scrum Team and Stakeholders B. Adaptive product development environment C. Features offering maximum business value are developed first D. All of the above Answer: D Justification: Scrum is designed such that provides transparency, so the client can observe the work done at the end of each Sprint and continuously provide his or her feedback. 10. Prioritized delivery in Scrum means which of the following: A. Features that are the simplest and would not require much involvement from the team will be completed first. B. Features with the least or no interdependencies will be completed first to ensure smooth and uninterrupted delivery. C. Features that provide maximum business value will be completed first. D. Features are developed on a first-in, first-out basis. Answer: C Justification: The Product Owner prioritizes the Prioritized Product Backlog according to business value. Therefore, the features that provide the most business value are developed first.
  • 4. Chapter 2 1. Which of the following is a core Scrum role? A. Product Owner B. Stakeholder C. Project sponsor D. Project manager Answer: A 2. Who among the following is responsible for providing the Scrum Team with a favorable environment for creating deliverables? A. Scrum Master B. Product Owner C. Scrum Guidance Body D. External stakeholders Answer: A 3. Who among the following is responsible for creating an awareness of Scrum practices among Scrum Team members? A. Scrum Master B. Product Owner C. Scrum Team D. Scrum Guidance Body Answer: A 4. Who among the following is responsible for achieving the maximum business value of the project? A. Scrum Master B. Product Owner C. Scrum Team D. External Stakeholders Answer: B 5. Who among the following is responsible for creating deliverables in the Create Deliverables process? A. Chief Scrum Master B. Portfolio Product Owner C. Scrum Team leader D. Scrum Team Answer: D Justification: The Scrum Team is designed to be a group of self-motivated individuals working together to reach a common objective. Scrum promotes team work and collective responsibility as well as discouraging hierarchy among Scrum Team members. Therefore, he Scrum Team as a whole is responsible for completing the work.
  • 5. 6. The advantages of using a cross-functional team are A. improved communication between members of the team. B. faster decision making. C. individual responsibility can be assigned to each member of the team depending on their expertise. D. both A and B. Answer: D Justification: Scrum focuses on collective ownership, which means that everyone needs to proactively participate in decision making and communicating. This can speed up decision making and improve communication within the team. 7. Who among the following is responsible for deciding on the Acceptance Criteria for various tasks? A. Scrum Master B. Product Owner C. Scrum Team leader D. Scrum Team Answer: B 8. Who among the following represents the Voice of the Customer? A. Chief Scrum Master B. Product Owner C. Scrum Team leader D. Scrum Team members Answer: B 9. Jason is responsible for resolving conflicts among Scrum Team members. What role is he playing on a Scrum project? A. Scrum Master B. Product Owner C. Scrum Team leader D. Scrum Team Answer: A
  • 6. Chapter 3 1. The prioritized set of work to be done is known as A. a User Story. B. the Prioritized Product Backlog. C. a Burndown chart. D. accepted deliverables. Answer: B 2. Which of the following is the definition of a User Story? A. A statement describing the Product Vision B. A document describing the priority of tasks to be completed in the project C. A statement that expresses the desired end user functionality D. A story providing information on similar tasks completed in previous Scrum implementation projects Answer: C 3. How are the Prioritized Product Backlog items arranged? A. The smallest items are at the top. B. The items with the least interdependencies are at the top. C. The most complex items are at the top. D. The items with the highest business value are at the top. Answer: D 4. Who is responsible for creating User Stories in the Develop User Stories process? A. Scrum Master B. Product Owner C. Scrum Team D. Stakeholders Answer: B 5. The responsibility for estimating items in the Prioritized Product Backlog in the Plan and Estimate phase lies with the A. Scrum Team. B. Scrum Master. C. Product Owner. D. External team with considerable experience. Answer: A
  • 7. 6. Which of the following is NOT an input to the Ship Deliverables process? A. Accepted Deliverables B. Release Planning Schedule C. Product Owner D. Impediment Log Answer: D 7. How often are the Prioritized Product Backlog priorities changed? A. Never B. Whenever the Product Owner decides that an item has to be assigned higher priority C. Whenever the Scrum Master believes that an item has to be added D. When senior management feels an item has to be added Answer: B Justification: The Product Owner has the final say regarding any items that have to be added to the Prioritized Product Backlog. 8. Which of the following tools is used by the Scrum Team to estimate Tasks in the Estimate Tasks process? A. User Story Writing Expertise B. Wideband Delphi C. Paired Comparison D. JAD Sessions Answer: B Justification: Wideband Delphi is a consensus-based technique used to estimate tasks in the Estimate Tasks process. 9. Which of the following statements is NOT true? A. Team velocity is a measure of the amount of work that a team can complete in a Sprint. B. Historical team velocity is used as an indicator when assigning tasks for each Sprint. C. Team velocity is independent of team composition. D. Team velocity is used in deciding release deadlines. Answer: C Justification: Team velocity is unique to the composition of the team. Even changing a person’s role can affect team velocity.
  • 8. 10. Which of the following is NOT discussed in a Daily Standup Meeting? A. What the team member has accomplished since the last meeting B. What the team member plans to work on until the next meeting C. What the team member has learned from completing his or her work D. What roadblocks the team member is facing Answer: C 11. What is the duration of a typical Daily Standup Meeting? A. 5 minutes B. 1 hour C. 15 minutes D. Stand-up Meetings aren’t Time-boxed. Answer: C Justification: The Daily Standup Meeting is Time-boxed to 15 minutes for the general recommended team size (5–9 members) but might vary in proportion to team size. 12. Ensuring that the Daily Standup Meetings are run in a timely and structured manner is the responsibility of the A. Scrum Master. B. Product Owner. C. Scrum Team Leader. D. Group collectively. Answer: A 13. The Sprint Burndown Chart is a tool used by teams to A. Measure the work completed during a Sprint. B. Measure the work left to be completed during a Sprint. C. Calculate the amount of the team’s budget remaining. D. Identify low-performing team members. Answer: B Justification: The Sprint Burndown chart measures the work left to be completed rather than work completed. 14. The meeting in which the team discusses the tasks to be completed in the next Sprint is known as the A. Product Vision Meeting. B. Sprint Planning Meeting. C. Sprint Review Meeting. D. Retrospect Sprint Meeting. Answer: B
  • 9. 15. The meeting at the end of the Sprint in which the team presents its work to the Product Owner is known as the A. Product Vision Meeting. B. Sprint Planning Meeting. C. Sprint Review Meeting. D. Retrospect Sprint Meeting. Answer: C 16. The meeting in which the team analyzes the previous Sprint and identifies potential process improvements is known as the A. Product Vision Meeting. B. Sprint Planning Meeting. C. Sprint Review Meeting. D. Retrospect Sprint Meeting. Answer: D 17. During the Sprint Review Meeting, A. the team presents the end product among themselves. B. the Scrum Master can accept or reject the end product deliverable. C. the team presents the end product deliverable to the Product Owner. D. each team member can accept or reject the end product deliverable. Answer: C 18. Which of the following activities is NOT a part of the Retrospect Sprint Meeting? A. The team discusses the positives and negatives from the previous Sprint. B. The team identifies issues faced in the previous Sprint and discusses how to mitigate these issues in future Sprints. C. The team reviews and identifies potential improvements to its functioning. D. Based on suggested changes, the team proceeds to reprioritize the Prioritized Product Backlog. Answer: D 19. The advantages of the Groom the Prioritized Product Backlog process are the following: A. Knowledge gained from a previous Sprint is incorporated into future Sprints. B. The latest business and technical requirements are added to the next Sprint. C. Grooming ensures that the Prioritized Product Backlog is refined before the Sprint Planning Meeting so that the team has a better idea of the requirements prior to the meeting. D. All of the above. Answer: D
  • 10. 20. The responsibility of grooming the Prioritized Product Backlog lies with the A. Product Owner. B. Scrum Master. C. Scrum Team. D. External stakeholders. Answer: A 21. Which of the following activities can be performed together during the Sprint Planning Meeting? A. Tasks Estimation and Release Planning B. Product Backlog grooming and Task Planning C. Task Planning and Tasks Estimation D. Release Planning and Product Backlog grooming Answer: C 22. Which of the following is NOT a part of the Sprint Planning Meeting? A. The Product Owner explains the top Prioritized Product Backlog items to the team. B. The Scrum Team, in consultation with the Product Owner, estimates the tasks for a given Sprint. C. Based on estimates, the team commits to a few tasks to be completed in the next Sprint. D. The team gets feedback from Stakeholders. Answer: D 23. You are a member of a Scrum Team, and you are instructed by the general manager of your company to work on an urgent task that is not part of the current Sprint. What do you do? A. Take responsibility for the task, and tell the Product Owner to postpone the deadline for the current Sprint. B. Talk to the Scrum Master, and tell him or her to re-assign your tasks to someone else. C. Talk to the Product Owner, and tell him or her to re-assign your tasks to someone else. D. Inform the Scrum Master of the situation, and let him or her discuss the situation with the GM. E. Take no action because you are already busy. Answer: D
  • 11. 24. For any ongoing Sprint, when can new User Stories be added? A. When the Scrum Master adds the User Story to the Sprint Backlog B. When the Product Owner approves the User Story C. When the Scrum team approves the User Story D. New User Stories can never be added to the Sprint Answer: D Justification: The tasks of a current Sprint are never changed. If the requirement is urgent, then the current Sprint should be cancelled and a new Sprint should incorporate the requirements. However, the team keeps a list of additional tasks that can be taken on if the team is able to complete tasks in a particular Sprint ahead of time. 25. Acceptance criteria A. Increases ambiguity regarding requirements. B. Helps the team adhere to the quality norms regarding functionality. C. Is determined by the Scrum Master in consultation with the team members. D. Is determined by the Scrum Master in consultation with the Product Owner. Answer: B 26. In which of the following processes in the Initiate phase is the length of the Sprint determined? A. Create Project Vision B. Develop Epic(s) C. Create Prioritized Product Backlog D. Conduct Release Planning Answer: D Justification: The duration of the Sprint is decided in the Conduct Release Planning process.