Overview of the Tulia
CAES Bulk Electric
Storage Project
April 2013
Agenda
2
I. What is CAES?
II. Why Tulia and Economic Development
III. Need for Storage and our Progress
IV. Subsurface Technology
V. Milestones
VI. Questions?
Tulia I Rapid Response Storage and Generation Facility
What is CAES?
Commercially proven in two facilities, Compressed Air Energy Storage (CAES) 
is the most flexible technology for the bulk storage of electricity
 Two commercial‐scale 
units have been 
operating reliably for 
two decades.
 Two commercial‐scale 
units have been 
operating reliably for 
two decades.
 Can optimize sales and 
purchases of energy 
and ancillary services
 Can optimize sales and 
purchases of energy 
and ancillary services
 Compressed air  is released , mixed with a  small amount of natural gas, 
and used to fire a  turbines for generation of electricity  when it  is most 
needed and when prices are higher.
 Compressed air  is released , mixed with a  small amount of natural gas, 
and used to fire a  turbines for generation of electricity  when it  is most 
needed and when prices are higher.
 Can store and generate 
simultaneously
 Can store and generate 
simultaneously
Electricity from grid
or behind meter source
3
The Right Place in Texas
4
• Geology 
• Wind 
• Water 
• Technology 
• Electric Transmission 
• Gas Pipeline
• Potential Revenue 
• Regulation is Right
TULIA CAES PLANT
CAES 7-mile double-
circuit 345 kV line
345 kV CREZ loop from
Nazareth to Silverton
Silverton
Collection Station
Amarillo
South to
Swisher
County
SPP 230
kV Line
Proposed Interconnection of Tulia 1 CAES plant to
ERCOT 345 kV CREZ system.
PowerSouth Energy Cooperative
5
Cavern
Wellhead
CAES Unit
Tulia Economic Development
6
Facility Staffing Plan
Description Number
Plant Manager 1
Operations Manager 1
Shift Operators 12
Leaching Field Operators 3
Maintenance Manager 1
Mechanical Technicians 8
I&E Technicians 6
Maintenance Assistants 2
Groundskeeper 1
Janitor 1
Warehouse 1
Accounting/Payroll 3
Security 4
Administrative 1
Total Staff 45
The Facility is to be staffed 24 hours a day 7 days a week. Operating staff is to work in 12-hour
shifts on a rotating schedule. The management and maintenance staff is to work a normal
weekday schedule and work on nights or weekends, as required. Major maintenance crews will
be employed as required.
The Need For Bulk Energy Storage
7
• The electric grid operates entirely on demand – generation must meet demand at all times
– Grid operators balance supply and demand to maintain the stability of the system
• Responsive generating units are dispatched to meet peaks in demand and ramped down when load tapers off
• Fast response units, however, can be expensive to operate, leading to spikes in power prices when demand is high
– Efficient bulk energy storage can be used to help maintain grid stability at attractive cost
• Stored power can be dispatched extremely quickly to meet peak demand
• Lower fuel costs than conventional thermal quick response units
Greater Penetration of Renewable Energy Resources + Grid Stability
• Power landscape is shifting toward a greater reliance on renewable forms of power generation (e.g. wind)
– While renewable resources are attractive for their environmental characteristics, they often prove to be
significantly less reliable sources of power than conventional thermal resources
• Power is generated intermittently (i.e. whenever the wind blows) and output can be highly variable
• Accordingly, the growth in renewable energy resources creates a more volatile grid system
• As wind resources lend to a “peak-ier” system, bulk energy storage can be used to efficiently regulate the
balance between electric supply and demand
– Further, renewable resources may generate power at suboptimal times
• In West Texas, for example, the wind blows primarily during the nighttime hours when demand is low
• Bulk energy storage can be used to “time-shift” excess power, storing it and making it available during
periods of greater demand
Summary of the Tulia CAES Project
8
• Chamisa Energy, LLC (“Chamisa”) is developing a 270MW Compressed Air Energy Storage (“CAES”)
facility (“Tulia I”) in Swisher County, Texas
• Chamisa owns the land on which the Tulia I site will be located, having acquired the plot following a
careful analysis of the surrounding region’s geology, the site’s physical proximity to wind generating
resources and the ability to efficiently interconnect to the ERCOT grid
• Tulia I will employ proven CAES technology to capitalize on a compelling market opportunity, as the
high-wind-penetrated yet overall resource constrained ERCOT market provides an exceptional platform
to capture the full range of economics available to CAES technology, including:
– Transforming wind , or another renewable, into a fully dispatchable generating resource
– Serving any of base, intermediate and peak load
– Providing Ancillary Services
– Arbitraging on-peak/off-peak energy prices
• The project is expected to generate 25-year unlevered returns of 17-30% based on third-party power
market consultant analysis
• The Tulia I team has achieved significant development milestones to date and has a credible
development plan for the construction of the facility
Bedded Salt Caverns
Geophysical Well Logs and Stratigraphy Confirms Salt Formations
14 11 6
SWISHER HALE
South
B’Interpretations based
on core descriptions
North
B
Top of San
Andres
Formation
Chamisa anticipates
locating the caverns in the
Upper San Andreas
Formation, which is
comprised mainly of salt
Subsurface Development
• Chamisa engaged RESPEC Consulting & Services to perform extensive geomechanical modeling and analysis in order
to inform the selection of an appropriate number of caverns, their depth and design
– Thermal finite element model used to predict temperatures in the rock surrounding the caverns as a function of time
– Temporal rock temperatures and mechanical loading used in thermomechanical finite element model to predict cavern
stress
• Key modeling assumptions:
– Casing seat at 2,284 feet
– Cavern roof at 2,324 feet (roof salt thickness of 50 feet)
– Cavern floor at 2,424 feet
– Maximum radius of 150 feet
– Cavern usable air storage volume of 733,500 bbls (each)
– Cavern fully cycled over a 48-hour period
• In consultation with RESPEC, Lonquist and Glorieta Geoscience, Chamisa has assumed a conservative cavern plan
– Caverns will be limited to a maximum pressure swing of 0.21 psi/ft at the casing seat (~480 psi), ranging from 0.64-
0.85 psi/ft
– This will allow for 6.6 mmlbs of working gas and 18 hours of storage (assuming a withdrawal rate of 101 lb/s)
• Based on the simulations analyzed by RESPEC, the caverns are projected to experience minimal tensile stresses with
high factors of safety in the surrounding siltstone
– The cavern plan will be refined following the drilling and analysis of the onsite test core
– Ultimately, Chamisa’s cavern plan may prove to be overly conservative, which would allow for the development of
fewer caverns while maintaining the same total amount of storage and operating parameters
Cavern Location and Design
Source: Chamisa Energy, LLC; RESPEC; Lonquist & Co. LLC
Subsurface Development (Cont.)
Cavern Location and Design (Cont.)
Source: Chamisa Energy, LLC; RESPEC; Lonquist & Co. LLC
Cavern Design Close-Up of Cavern Area
CAES Cycle Working Gas CAES Cycles – Casing Seat Pressure
0 50 100 150 200 250 300
2,200
2,250
2,300
2,350
2,400
2,450
2,500
Radius (ft)
Depth (ft)
Siltstone
Salt
Anhydrite
-10
0
10
20
30
40
50
60
70
80
90
100
110
0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00
WorkingGas(%)
Time (days)
0.60
0.65
0.70
0.75
0.80
0.85
0.90
0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00
PressureGradientatCasingSeat(psi/ft)
Time (days)
0.61 to 0.85 psi/ft
0.64 to 0.85 psi/ft
0.63 to 0.85 psi/ft
Subsurface Development (Cont.)
Cavern Location and Design (Cont.)
Source: Chamisa Energy, LLC; RESPEC; Lonquist & Co. LLC
Potential for Tensile Fracture Siltstone Factors of Safety (25 years)
Potential for Salt Dilation Cavern Closure
70
80
90
100
110
120
‐2,000
‐1,500
‐1,000
‐500
0
500
364.00 364.25 364.50 364.75 365.00 365.25 365.50 365.75 366.00
Temperature (°F)
Stress (psi)
Days into 1st Year of Cycling
0.64 to 0.85 psi/ft
Maximum Principal Stress
Normal Stress (Negative of Cavern Pressure)
Cavern Wall Temperature
Note: Tensile Stresses are Positive
Development Milestones Completed
13
Chamisa has invested
approximately $5-10mm
in land acquisition and
project development
costs to date
Date Milestone
October 2010 Completed Phase I environmental review
July 2011 Acquired TCEQ groundwater protection letter
July 2011 Acquired surface water permit
July 2011 Completed acquisition of site and all mineral rights
December 2011 Completed PILOT agreement negotiations with local governments
March 2012 Acquired TRRC test core drilling permit
March 2012 Received favorable rule change from PUCT for energy storage
April 2012 Acquired TRRC P-5 operators permit
October 2012 Signed ESA with Dresser Rand and Lonquist
November 2012 Engaged SAIC as Independent Engineer / Power Market Consultant
December 2012 Filed air permit with EPA
December 2012 ERCOT began implementation of energy storage rule change
January 2013 Filed air permit with TCEQ
February 2013 Received Class 3 proposal from Dresser Rand
February 2013 Received preliminary geo-mechanical analysis from RESPEC
February 2013 Finalized preliminary cavern design and solution mining plan
March 2013 Received Power Market Consultant report
March 2013 Received Independent Engineer report
March 2013 Received air permit from TCEQ
Key Project Milestones Remaining
Date Milestone
Q2 2013 Issue FEED RFP
Q2 2013 File Rule 97 and Rule 9 permit applications
Q3 2013 Drill & analyze on-site test core
Q3-Q4 2013 Refine cavern design and solution mining plan
Q4 2013 Finalize contract with Dresser Rand, order long-lead time items
Q4 2013 Finalize selection of and negotiate contract with EPC contractor
Q1 2014 Commence well and cavern drilling
Q1 2015 Commence cavern leaching
2016 Construct balance of plant
2016 Construct transmission line and gas pipeline
Q2 2016 Begin installation of Dresser Rand equipment
Q1 2017 Begin conversion of caverns to air service
Q3 2017 Commence operations
14
The critical near-term
milestone will be the
drilling and analysis of
the on-site test core
Tulia I Rapid Response Storage and Generation Facility 15
Questions

Weitere ähnliche Inhalte

Was ist angesagt?

Study of Compressed Air Energy Storage Power Generation System and its Perfor...
Study of Compressed Air Energy Storage Power Generation System and its Perfor...Study of Compressed Air Energy Storage Power Generation System and its Perfor...
Study of Compressed Air Energy Storage Power Generation System and its Perfor...
Waqas Ali Tunio
 
Caes gen presentation
Caes gen presentationCaes gen presentation
Caes gen presentation
LukeBatten
 
Maulin Trivedi1_Presentation
Maulin Trivedi1_PresentationMaulin Trivedi1_Presentation
Maulin Trivedi1_Presentation
Maulin Trivedi
 
Wind Energy Nguyen Hoang Viet Final
Wind Energy   Nguyen Hoang Viet FinalWind Energy   Nguyen Hoang Viet Final
Wind Energy Nguyen Hoang Viet Final
Viet NguyenHoang
 
Energia solar thermal energy storage systems
Energia solar   thermal energy storage systemsEnergia solar   thermal energy storage systems
Energia solar thermal energy storage systems
Usama Abudawud
 
James R. Connell P.E. - October 13, 2011
James R. Connell P.E. - October 13, 2011James R. Connell P.E. - October 13, 2011
James R. Connell P.E. - October 13, 2011
p21decision
 

Was ist angesagt? (20)

Study of Compressed Air Energy Storage Power Generation System and its Perfor...
Study of Compressed Air Energy Storage Power Generation System and its Perfor...Study of Compressed Air Energy Storage Power Generation System and its Perfor...
Study of Compressed Air Energy Storage Power Generation System and its Perfor...
 
Caes gen presentation
Caes gen presentationCaes gen presentation
Caes gen presentation
 
Energy storage systems
Energy storage systemsEnergy storage systems
Energy storage systems
 
Maulin Trivedi1_Presentation
Maulin Trivedi1_PresentationMaulin Trivedi1_Presentation
Maulin Trivedi1_Presentation
 
Conventional Power generation
Conventional Power generationConventional Power generation
Conventional Power generation
 
Economic selection of type of genration and types of equipment used in power...
 Economic selection of type of genration and types of equipment used in power... Economic selection of type of genration and types of equipment used in power...
Economic selection of type of genration and types of equipment used in power...
 
POWER PLANT ECONOMICS AND ENVIRONMENTAL CONSIDERATIONS - SNIST
POWER  PLANT  ECONOMICS AND ENVIRONMENTAL  CONSIDERATIONS - SNISTPOWER  PLANT  ECONOMICS AND ENVIRONMENTAL  CONSIDERATIONS - SNIST
POWER PLANT ECONOMICS AND ENVIRONMENTAL CONSIDERATIONS - SNIST
 
power plant engineering
power plant engineeringpower plant engineering
power plant engineering
 
Wind Energy Nguyen Hoang Viet Final
Wind Energy   Nguyen Hoang Viet FinalWind Energy   Nguyen Hoang Viet Final
Wind Energy Nguyen Hoang Viet Final
 
Energy Storage Solutions - Technology Deployment Analysis
Energy Storage Solutions - Technology Deployment AnalysisEnergy Storage Solutions - Technology Deployment Analysis
Energy Storage Solutions - Technology Deployment Analysis
 
Mechanical energy storage
Mechanical energy storage Mechanical energy storage
Mechanical energy storage
 
Energy Resources
Energy ResourcesEnergy Resources
Energy Resources
 
Energy storage technologies
Energy storage technologiesEnergy storage technologies
Energy storage technologies
 
Energia solar thermal energy storage systems
Energia solar   thermal energy storage systemsEnergia solar   thermal energy storage systems
Energia solar thermal energy storage systems
 
Electrical power generation and its types
Electrical power generation and its typesElectrical power generation and its types
Electrical power generation and its types
 
James R. Connell P.E. - October 13, 2011
James R. Connell P.E. - October 13, 2011James R. Connell P.E. - October 13, 2011
James R. Connell P.E. - October 13, 2011
 
IRJET- Rankine Cycle Coupled with Heliostat Solar Receiver; A Review
IRJET- Rankine Cycle Coupled with Heliostat Solar Receiver; A ReviewIRJET- Rankine Cycle Coupled with Heliostat Solar Receiver; A Review
IRJET- Rankine Cycle Coupled with Heliostat Solar Receiver; A Review
 
Gould - Thermal Energy Storage
Gould - Thermal Energy StorageGould - Thermal Energy Storage
Gould - Thermal Energy Storage
 
Electrical Power generation
Electrical Power generationElectrical Power generation
Electrical Power generation
 
Ppt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distributionPpt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distribution
 

Andere mochten auch

Compressor And Compressed Air Systems
Compressor And Compressed Air SystemsCompressor And Compressed Air Systems
Compressor And Compressed Air Systems
Saurabh Jain
 
thermo chemical energy storage system for solar plants
thermo chemical energy storage system for solar plantsthermo chemical energy storage system for solar plants
thermo chemical energy storage system for solar plants
Rajneesh Gautam
 
Buku tutorial
Buku tutorialBuku tutorial
Buku tutorial
rahim4533
 
compressores herméticos
compressores herméticoscompressores herméticos
compressores herméticos
sr adil
 
Manual de aplicação de compressores embraco 2
Manual de aplicação de compressores embraco 2Manual de aplicação de compressores embraco 2
Manual de aplicação de compressores embraco 2
Denis Palheiro
 
Application Note—Compressed Air
Application Note—Compressed AirApplication Note—Compressed Air
Application Note—Compressed Air
Leonardo ENERGY
 
Adele adiabatic compressed-air energy storage for electricity supply
Adele   adiabatic compressed-air energy storage for electricity supplyAdele   adiabatic compressed-air energy storage for electricity supply
Adele adiabatic compressed-air energy storage for electricity supply
Júlio César Spillere Ronchi
 

Andere mochten auch (20)

Energy Conservation in Compressed Air System.
Energy Conservation in Compressed Air System.Energy Conservation in Compressed Air System.
Energy Conservation in Compressed Air System.
 
Energy Storage System
Energy Storage SystemEnergy Storage System
Energy Storage System
 
Flywheel Energy Storage System
Flywheel Energy Storage SystemFlywheel Energy Storage System
Flywheel Energy Storage System
 
Compressor And Compressed Air Systems
Compressor And Compressed Air SystemsCompressor And Compressed Air Systems
Compressor And Compressed Air Systems
 
Compressed Air Energy Storage at the North Campus of Durham College and the ...
Compressed Air Energy Storage at the  North Campus of Durham College and the ...Compressed Air Energy Storage at the  North Campus of Durham College and the ...
Compressed Air Energy Storage at the North Campus of Durham College and the ...
 
thermo chemical energy storage system for solar plants
thermo chemical energy storage system for solar plantsthermo chemical energy storage system for solar plants
thermo chemical energy storage system for solar plants
 
Energy Materna
Energy MaternaEnergy Materna
Energy Materna
 
Buku tutorial
Buku tutorialBuku tutorial
Buku tutorial
 
compressores herméticos
compressores herméticoscompressores herméticos
compressores herméticos
 
2441 unit23
2441 unit232441 unit23
2441 unit23
 
guia básico para compressores
guia básico para compressores   guia básico para compressores
guia básico para compressores
 
Manual de aplicação de compressores embraco 2
Manual de aplicação de compressores embraco 2Manual de aplicação de compressores embraco 2
Manual de aplicação de compressores embraco 2
 
Application Note—Compressed Air
Application Note—Compressed AirApplication Note—Compressed Air
Application Note—Compressed Air
 
Caes yakima full report
Caes yakima full reportCaes yakima full report
Caes yakima full report
 
Adele adiabatic compressed-air energy storage for electricity supply
Adele   adiabatic compressed-air energy storage for electricity supplyAdele   adiabatic compressed-air energy storage for electricity supply
Adele adiabatic compressed-air energy storage for electricity supply
 
Compressors
CompressorsCompressors
Compressors
 
compressors
compressorscompressors
compressors
 
Air & Refrigeration Compressors – sizing & selection software
Air & Refrigeration Compressors – sizing & selection softwareAir & Refrigeration Compressors – sizing & selection software
Air & Refrigeration Compressors – sizing & selection software
 
Screw compressor
Screw compressorScrew compressor
Screw compressor
 
Compressor tabela de aplicação (2)
Compressor   tabela de aplicação (2)Compressor   tabela de aplicação (2)
Compressor tabela de aplicação (2)
 

Ähnlich wie Compressed Air Wind Energy Storage

Wind Energy For Geoscience Students
Wind Energy For Geoscience Students Wind Energy For Geoscience Students
Wind Energy For Geoscience Students
Keshav Letourneau
 
Natural Gas an Inside Propective 2-19-14
Natural Gas an Inside Propective 2-19-14Natural Gas an Inside Propective 2-19-14
Natural Gas an Inside Propective 2-19-14
James M. Bright, P.E.
 
Archimedes Screw as a Low Head Hydropower Generator
Archimedes Screw as a Low Head Hydropower GeneratorArchimedes Screw as a Low Head Hydropower Generator
Archimedes Screw as a Low Head Hydropower Generator
Christos Charisiadis
 
Joel Link - GW Solar Symposium 2012
Joel Link  - GW Solar Symposium 2012Joel Link  - GW Solar Symposium 2012
Joel Link - GW Solar Symposium 2012
GW Solar Institute
 
2015 SNAME_Schellstede_2014DEC05 (1)
2015 SNAME_Schellstede_2014DEC05 (1)2015 SNAME_Schellstede_2014DEC05 (1)
2015 SNAME_Schellstede_2014DEC05 (1)
Herman J. Schellstede
 
Urban_Daniel_Energy_FinalReport
Urban_Daniel_Energy_FinalReportUrban_Daniel_Energy_FinalReport
Urban_Daniel_Energy_FinalReport
Daniel Urban
 

Ähnlich wie Compressed Air Wind Energy Storage (20)

Ocean renewable energy storage (ORES) system
Ocean renewable energy storage (ORES) systemOcean renewable energy storage (ORES) system
Ocean renewable energy storage (ORES) system
 
Pre-Feasibility Study of a 1000 MW Pumped Storage Plant in Saudi Arabia
Pre-Feasibility Study of a 1000 MW Pumped Storage Plant in Saudi ArabiaPre-Feasibility Study of a 1000 MW Pumped Storage Plant in Saudi Arabia
Pre-Feasibility Study of a 1000 MW Pumped Storage Plant in Saudi Arabia
 
Energy storage (why & how)
Energy storage (why & how)Energy storage (why & how)
Energy storage (why & how)
 
CESC-TGS REPORT
CESC-TGS REPORTCESC-TGS REPORT
CESC-TGS REPORT
 
Compressed Air Energy Storage
Compressed Air Energy StorageCompressed Air Energy Storage
Compressed Air Energy Storage
 
project presentation prepared_052934.pptx
project presentation prepared_052934.pptxproject presentation prepared_052934.pptx
project presentation prepared_052934.pptx
 
Wind Energy For Geoscience Students
Wind Energy For Geoscience Students Wind Energy For Geoscience Students
Wind Energy For Geoscience Students
 
Energy storage system
Energy storage systemEnergy storage system
Energy storage system
 
Energy storage system
Energy storage systemEnergy storage system
Energy storage system
 
Nwtc turb sim workshop september 22 24, 2008- boundary layer dynamics and wi...
Nwtc turb sim workshop september 22 24, 2008-  boundary layer dynamics and wi...Nwtc turb sim workshop september 22 24, 2008-  boundary layer dynamics and wi...
Nwtc turb sim workshop september 22 24, 2008- boundary layer dynamics and wi...
 
Natural Gas an Inside Propective 2-19-14
Natural Gas an Inside Propective 2-19-14Natural Gas an Inside Propective 2-19-14
Natural Gas an Inside Propective 2-19-14
 
Ocean thermal energy conversion
Ocean thermal energy conversionOcean thermal energy conversion
Ocean thermal energy conversion
 
Energy Security and Innovation Observing System for the Subsurface (ESIOS) Up...
Energy Security and Innovation Observing System for the Subsurface (ESIOS) Up...Energy Security and Innovation Observing System for the Subsurface (ESIOS) Up...
Energy Security and Innovation Observing System for the Subsurface (ESIOS) Up...
 
OTEC
OTECOTEC
OTEC
 
Archimedes Screw as a Low Head Hydropower Generator
Archimedes Screw as a Low Head Hydropower GeneratorArchimedes Screw as a Low Head Hydropower Generator
Archimedes Screw as a Low Head Hydropower Generator
 
Rebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-futureRebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-future
 
Joel Link - GW Solar Symposium 2012
Joel Link  - GW Solar Symposium 2012Joel Link  - GW Solar Symposium 2012
Joel Link - GW Solar Symposium 2012
 
UNIT 1 CIV 880.pptx
UNIT 1 CIV 880.pptxUNIT 1 CIV 880.pptx
UNIT 1 CIV 880.pptx
 
2015 SNAME_Schellstede_2014DEC05 (1)
2015 SNAME_Schellstede_2014DEC05 (1)2015 SNAME_Schellstede_2014DEC05 (1)
2015 SNAME_Schellstede_2014DEC05 (1)
 
Urban_Daniel_Energy_FinalReport
Urban_Daniel_Energy_FinalReportUrban_Daniel_Energy_FinalReport
Urban_Daniel_Energy_FinalReport
 

Mehr von Ports-To-Plains Blog

Mehr von Ports-To-Plains Blog (20)

Canada and U.S. Trade Overview
Canada and U.S. Trade Overview Canada and U.S. Trade Overview
Canada and U.S. Trade Overview
 
2013 Ports-to-Plains Alliance Energy Conference Handouts
2013 Ports-to-Plains Alliance Energy Conference Handouts2013 Ports-to-Plains Alliance Energy Conference Handouts
2013 Ports-to-Plains Alliance Energy Conference Handouts
 
Energy Development Impact on Transportation Infrastructure
Energy Development Impact on Transportation InfrastructureEnergy Development Impact on Transportation Infrastructure
Energy Development Impact on Transportation Infrastructure
 
Wind Energy's Future and the Impact on U.S. Manufacturing
Wind Energy's Future and the Impact on U.S. ManufacturingWind Energy's Future and the Impact on U.S. Manufacturing
Wind Energy's Future and the Impact on U.S. Manufacturing
 
Fuels Policy, Ethanol and RFS Reform Political and Policy Implications on Gas...
Fuels Policy, Ethanol and RFS Reform Political and Policy Implications on Gas...Fuels Policy, Ethanol and RFS Reform Political and Policy Implications on Gas...
Fuels Policy, Ethanol and RFS Reform Political and Policy Implications on Gas...
 
Ports-to-Plains Letter Submitted to Department of State
Ports-to-Plains Letter Submitted to Department of StatePorts-to-Plains Letter Submitted to Department of State
Ports-to-Plains Letter Submitted to Department of State
 
News Release Keystone XL Supporting SEIS Finding 041813
News Release Keystone XL Supporting SEIS Finding 041813News Release Keystone XL Supporting SEIS Finding 041813
News Release Keystone XL Supporting SEIS Finding 041813
 
Ports-to-Plains: The Importance of a Statewide Transportation to Colorado's E...
Ports-to-Plains: The Importance of a Statewide Transportation to Colorado's E...Ports-to-Plains: The Importance of a Statewide Transportation to Colorado's E...
Ports-to-Plains: The Importance of a Statewide Transportation to Colorado's E...
 
2013 Energy Conference Save the Date
2013 Energy Conference Save the Date2013 Energy Conference Save the Date
2013 Energy Conference Save the Date
 
February 2013 Update from the Ports-to-Plains Alliance
February 2013 Update from the Ports-to-Plains AllianceFebruary 2013 Update from the Ports-to-Plains Alliance
February 2013 Update from the Ports-to-Plains Alliance
 
Draft Supplemental EIS for the Keystone XL Project
Draft Supplemental EIS for the Keystone XL ProjectDraft Supplemental EIS for the Keystone XL Project
Draft Supplemental EIS for the Keystone XL Project
 
PTP supports Heineman Keystone XL Pipeline Decision
PTP supports Heineman Keystone XL Pipeline DecisionPTP supports Heineman Keystone XL Pipeline Decision
PTP supports Heineman Keystone XL Pipeline Decision
 
Keystone XL Letter Dec 2012 NEDEQ
Keystone XL Letter Dec 2012 NEDEQKeystone XL Letter Dec 2012 NEDEQ
Keystone XL Letter Dec 2012 NEDEQ
 
News Release PTP Keystone XL Nebraska
News Release PTP Keystone XL NebraskaNews Release PTP Keystone XL Nebraska
News Release PTP Keystone XL Nebraska
 
Ports-to-Plains Alliance Webinar 113012
Ports-to-Plains Alliance Webinar 113012Ports-to-Plains Alliance Webinar 113012
Ports-to-Plains Alliance Webinar 113012
 
Nebraska Trade Relationships 2004 – 2011
Nebraska Trade Relationships 2004 – 2011Nebraska Trade Relationships 2004 – 2011
Nebraska Trade Relationships 2004 – 2011
 
Comments on Interim Guidance on State Freight Plans and State Advisory Commit...
Comments on Interim Guidance on State Freight Plans and State Advisory Commit...Comments on Interim Guidance on State Freight Plans and State Advisory Commit...
Comments on Interim Guidance on State Freight Plans and State Advisory Commit...
 
Interim Guidance on State Freight Plans and State Freight Advisory Committees
Interim Guidance on State Freight Plans and State Freight Advisory CommitteesInterim Guidance on State Freight Plans and State Freight Advisory Committees
Interim Guidance on State Freight Plans and State Freight Advisory Committees
 
Ports-to-Plains Alliance Northern Working Group Strategic Plan October 2012
Ports-to-Plains Alliance Northern Working Group Strategic Plan October 2012Ports-to-Plains Alliance Northern Working Group Strategic Plan October 2012
Ports-to-Plains Alliance Northern Working Group Strategic Plan October 2012
 
South Dakota Trade Relationships 2004-2011
South Dakota Trade Relationships 2004-2011South Dakota Trade Relationships 2004-2011
South Dakota Trade Relationships 2004-2011
 

Kürzlich hochgeladen

IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
Enterprise Knowledge
 

Kürzlich hochgeladen (20)

Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 

Compressed Air Wind Energy Storage

  • 1. Overview of the Tulia CAES Bulk Electric Storage Project April 2013
  • 2. Agenda 2 I. What is CAES? II. Why Tulia and Economic Development III. Need for Storage and our Progress IV. Subsurface Technology V. Milestones VI. Questions?
  • 3. Tulia I Rapid Response Storage and Generation Facility What is CAES? Commercially proven in two facilities, Compressed Air Energy Storage (CAES)  is the most flexible technology for the bulk storage of electricity  Two commercial‐scale  units have been  operating reliably for  two decades.  Two commercial‐scale  units have been  operating reliably for  two decades.  Can optimize sales and  purchases of energy  and ancillary services  Can optimize sales and  purchases of energy  and ancillary services  Compressed air  is released , mixed with a  small amount of natural gas,  and used to fire a  turbines for generation of electricity  when it  is most  needed and when prices are higher.  Compressed air  is released , mixed with a  small amount of natural gas,  and used to fire a  turbines for generation of electricity  when it  is most  needed and when prices are higher.  Can store and generate  simultaneously  Can store and generate  simultaneously Electricity from grid or behind meter source 3
  • 4. The Right Place in Texas 4 • Geology  • Wind  • Water  • Technology  • Electric Transmission  • Gas Pipeline • Potential Revenue  • Regulation is Right TULIA CAES PLANT CAES 7-mile double- circuit 345 kV line 345 kV CREZ loop from Nazareth to Silverton Silverton Collection Station Amarillo South to Swisher County SPP 230 kV Line Proposed Interconnection of Tulia 1 CAES plant to ERCOT 345 kV CREZ system.
  • 6. Tulia Economic Development 6 Facility Staffing Plan Description Number Plant Manager 1 Operations Manager 1 Shift Operators 12 Leaching Field Operators 3 Maintenance Manager 1 Mechanical Technicians 8 I&E Technicians 6 Maintenance Assistants 2 Groundskeeper 1 Janitor 1 Warehouse 1 Accounting/Payroll 3 Security 4 Administrative 1 Total Staff 45 The Facility is to be staffed 24 hours a day 7 days a week. Operating staff is to work in 12-hour shifts on a rotating schedule. The management and maintenance staff is to work a normal weekday schedule and work on nights or weekends, as required. Major maintenance crews will be employed as required.
  • 7. The Need For Bulk Energy Storage 7 • The electric grid operates entirely on demand – generation must meet demand at all times – Grid operators balance supply and demand to maintain the stability of the system • Responsive generating units are dispatched to meet peaks in demand and ramped down when load tapers off • Fast response units, however, can be expensive to operate, leading to spikes in power prices when demand is high – Efficient bulk energy storage can be used to help maintain grid stability at attractive cost • Stored power can be dispatched extremely quickly to meet peak demand • Lower fuel costs than conventional thermal quick response units Greater Penetration of Renewable Energy Resources + Grid Stability • Power landscape is shifting toward a greater reliance on renewable forms of power generation (e.g. wind) – While renewable resources are attractive for their environmental characteristics, they often prove to be significantly less reliable sources of power than conventional thermal resources • Power is generated intermittently (i.e. whenever the wind blows) and output can be highly variable • Accordingly, the growth in renewable energy resources creates a more volatile grid system • As wind resources lend to a “peak-ier” system, bulk energy storage can be used to efficiently regulate the balance between electric supply and demand – Further, renewable resources may generate power at suboptimal times • In West Texas, for example, the wind blows primarily during the nighttime hours when demand is low • Bulk energy storage can be used to “time-shift” excess power, storing it and making it available during periods of greater demand
  • 8. Summary of the Tulia CAES Project 8 • Chamisa Energy, LLC (“Chamisa”) is developing a 270MW Compressed Air Energy Storage (“CAES”) facility (“Tulia I”) in Swisher County, Texas • Chamisa owns the land on which the Tulia I site will be located, having acquired the plot following a careful analysis of the surrounding region’s geology, the site’s physical proximity to wind generating resources and the ability to efficiently interconnect to the ERCOT grid • Tulia I will employ proven CAES technology to capitalize on a compelling market opportunity, as the high-wind-penetrated yet overall resource constrained ERCOT market provides an exceptional platform to capture the full range of economics available to CAES technology, including: – Transforming wind , or another renewable, into a fully dispatchable generating resource – Serving any of base, intermediate and peak load – Providing Ancillary Services – Arbitraging on-peak/off-peak energy prices • The project is expected to generate 25-year unlevered returns of 17-30% based on third-party power market consultant analysis • The Tulia I team has achieved significant development milestones to date and has a credible development plan for the construction of the facility
  • 9. Bedded Salt Caverns Geophysical Well Logs and Stratigraphy Confirms Salt Formations 14 11 6 SWISHER HALE South B’Interpretations based on core descriptions North B Top of San Andres Formation Chamisa anticipates locating the caverns in the Upper San Andreas Formation, which is comprised mainly of salt
  • 10. Subsurface Development • Chamisa engaged RESPEC Consulting & Services to perform extensive geomechanical modeling and analysis in order to inform the selection of an appropriate number of caverns, their depth and design – Thermal finite element model used to predict temperatures in the rock surrounding the caverns as a function of time – Temporal rock temperatures and mechanical loading used in thermomechanical finite element model to predict cavern stress • Key modeling assumptions: – Casing seat at 2,284 feet – Cavern roof at 2,324 feet (roof salt thickness of 50 feet) – Cavern floor at 2,424 feet – Maximum radius of 150 feet – Cavern usable air storage volume of 733,500 bbls (each) – Cavern fully cycled over a 48-hour period • In consultation with RESPEC, Lonquist and Glorieta Geoscience, Chamisa has assumed a conservative cavern plan – Caverns will be limited to a maximum pressure swing of 0.21 psi/ft at the casing seat (~480 psi), ranging from 0.64- 0.85 psi/ft – This will allow for 6.6 mmlbs of working gas and 18 hours of storage (assuming a withdrawal rate of 101 lb/s) • Based on the simulations analyzed by RESPEC, the caverns are projected to experience minimal tensile stresses with high factors of safety in the surrounding siltstone – The cavern plan will be refined following the drilling and analysis of the onsite test core – Ultimately, Chamisa’s cavern plan may prove to be overly conservative, which would allow for the development of fewer caverns while maintaining the same total amount of storage and operating parameters Cavern Location and Design Source: Chamisa Energy, LLC; RESPEC; Lonquist & Co. LLC
  • 11. Subsurface Development (Cont.) Cavern Location and Design (Cont.) Source: Chamisa Energy, LLC; RESPEC; Lonquist & Co. LLC Cavern Design Close-Up of Cavern Area CAES Cycle Working Gas CAES Cycles – Casing Seat Pressure 0 50 100 150 200 250 300 2,200 2,250 2,300 2,350 2,400 2,450 2,500 Radius (ft) Depth (ft) Siltstone Salt Anhydrite -10 0 10 20 30 40 50 60 70 80 90 100 110 0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 WorkingGas(%) Time (days) 0.60 0.65 0.70 0.75 0.80 0.85 0.90 0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 PressureGradientatCasingSeat(psi/ft) Time (days) 0.61 to 0.85 psi/ft 0.64 to 0.85 psi/ft 0.63 to 0.85 psi/ft
  • 12. Subsurface Development (Cont.) Cavern Location and Design (Cont.) Source: Chamisa Energy, LLC; RESPEC; Lonquist & Co. LLC Potential for Tensile Fracture Siltstone Factors of Safety (25 years) Potential for Salt Dilation Cavern Closure 70 80 90 100 110 120 ‐2,000 ‐1,500 ‐1,000 ‐500 0 500 364.00 364.25 364.50 364.75 365.00 365.25 365.50 365.75 366.00 Temperature (°F) Stress (psi) Days into 1st Year of Cycling 0.64 to 0.85 psi/ft Maximum Principal Stress Normal Stress (Negative of Cavern Pressure) Cavern Wall Temperature Note: Tensile Stresses are Positive
  • 13. Development Milestones Completed 13 Chamisa has invested approximately $5-10mm in land acquisition and project development costs to date Date Milestone October 2010 Completed Phase I environmental review July 2011 Acquired TCEQ groundwater protection letter July 2011 Acquired surface water permit July 2011 Completed acquisition of site and all mineral rights December 2011 Completed PILOT agreement negotiations with local governments March 2012 Acquired TRRC test core drilling permit March 2012 Received favorable rule change from PUCT for energy storage April 2012 Acquired TRRC P-5 operators permit October 2012 Signed ESA with Dresser Rand and Lonquist November 2012 Engaged SAIC as Independent Engineer / Power Market Consultant December 2012 Filed air permit with EPA December 2012 ERCOT began implementation of energy storage rule change January 2013 Filed air permit with TCEQ February 2013 Received Class 3 proposal from Dresser Rand February 2013 Received preliminary geo-mechanical analysis from RESPEC February 2013 Finalized preliminary cavern design and solution mining plan March 2013 Received Power Market Consultant report March 2013 Received Independent Engineer report March 2013 Received air permit from TCEQ
  • 14. Key Project Milestones Remaining Date Milestone Q2 2013 Issue FEED RFP Q2 2013 File Rule 97 and Rule 9 permit applications Q3 2013 Drill & analyze on-site test core Q3-Q4 2013 Refine cavern design and solution mining plan Q4 2013 Finalize contract with Dresser Rand, order long-lead time items Q4 2013 Finalize selection of and negotiate contract with EPC contractor Q1 2014 Commence well and cavern drilling Q1 2015 Commence cavern leaching 2016 Construct balance of plant 2016 Construct transmission line and gas pipeline Q2 2016 Begin installation of Dresser Rand equipment Q1 2017 Begin conversion of caverns to air service Q3 2017 Commence operations 14 The critical near-term milestone will be the drilling and analysis of the on-site test core
  • 15. Tulia I Rapid Response Storage and Generation Facility 15 Questions