// Faster, Yet Less Risky Projects
through Goal-Based Schedule Acceleration


              Dr. Dan Patterson, PMP
               CEO & President, Acumen

                  November 2011




                                +1 512 291 6261 // info@projectacumen.com

                                         www.projectacumen.com
Table of Contents

  Introduction ................................................................................................................. 3	
  
  What is Goal-Based Schedule Acceleration? ................................................................ 3	
  
  Setting the Acceleration Goal ...................................................................................... 4	
  
         Figure 1 – Defining an Acceleration Goal ............................................................. 4	
  
         Figure 2 – Project-based Acceleration Goal ......................................................... 4	
  
         Figure 3 – Activity-based Acceleration Goal ........................................................ 5	
  
  Defining Acceleration Criteria ...................................................................................... 5	
  
  Generate Scenario ....................................................................................................... 6	
  
         Figure 4 – Example of Multiple Acceleration Scenarios ........................................ 6	
  
  The Benefit and Return on Investment (ROI) of Goal-Based Acceleration .................... 7	
  
  How Does it Differ from a Monte-Carlo Simulation? ..................................................... 7	
  
  When Should Schedule Acceleration Be Carried Out? .................................................. 7	
  
  Accounting for Resources ............................................................................................ 8	
  
  Goal-based Acceleration: Faster Completion, but at What Price? ................................ 9	
  
         Figure 5 – Impact of Risk on an Accelerated Scenario ......................................... 9	
  
  Conclusion ................................................................................................................. 10	
  




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                                       2
Introduction
This white paper introduces a new, highly compelling technique for accelerating project
schedules. Unlike traditional techniques such as ‘network crashing’, goal-based schedule
acceleration results in informed acceleration decisions based on criteria that are relevant and
specific to your project. In short: targeted, meaningful changes to a schedule so as to achieve
acceleration, yet still retain realism and achievability.


What is Goal-Based Schedule Acceleration?
Goal-based schedule acceleration1 is a CPM (critical path method) based technique for
accelerating project schedules. It has been developed to solve the challenge of ensuring that a
project schedule is realistic; is aligned with stakeholder expectations; and, of course, is
executed successfully. Put forward a schedule that is too aggressive and it will not be
achieved; put forward a conservative schedule and it will not satisfy stakeholders desires to
finish earlier...

The technique builds upon the widely accepted scheduling technique known as –CPM
scheduling. CPM scheduling is a means of determining start and finish dates based upon a
sequence of activities whose durations are known. This is the underpinning of widely used
commercial scheduling tools such as MS Project and Primavera.

Goal-Based Schedule Acceleration takes this technique a step further by conducting multiple
CPM analyses in the form of a simulation incrementally adjusting pinpointed sets of activities
based upon defined criteria.

The reason why this technique is so powerful is two-fold:

       •   Firstly, it is using CPM analysis to schedule the project – it is true to the widely
           accepted, and globally used, technique for scheduling projects.
       •   Secondly, it uses criteria that are defined by project team members to make informed
           decisions as to which activities (or groups of activities) should be targeted for
           acceleration.

The technique is based upon three steps:


                 Set	
  Goal	
                   Define	
  Criteria	
               Generate	
  Scenario	
  


1
    For more information about schedule acceleration, visit http://www.projectacumen.com/products/acumen-360/features/



+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                                  3
Setting the Acceleration Goal
The acceleration goal is the target that we are trying to achieve. It can be either a project-
based target, for example, “accelerate the project as a whole by 10%” or it can be an
activity/milestone-based target e.g. “accelerate Project Sanction or First Oil by three months”.
Acceleration goals can be defined as:

    •   Percentage acceleration: e.g., accelerate by 5%
    •   Duration acceleration: e.g., reduce duration by 30 days
    •   New finish date: e.g., complete by 30 June 2015

All three acceleration goal types have one common objective: define a new target relative to
the current schedule target as a means of making an improvement or adjustment to the project
plan. Figure 1 shows an example of defining a new target date to be 50% of the original
duration. The current project completion date is February 6, 2013 and the new goal date has
been targeted at January 16, 2012.




                               Figure 1 – Defining an Acceleration Goal

In the case of accelerating a specific activity, compression or other changes needed to achieve
this acceleration are only applied to activities leading up to the targeted activity. Activities
falling after the targeted activity do not get altered; however, they may incur a date change as a
result of the knock-on effect of predecessor activities now finishing earlier. Figure 2 shows an
example of a project-based acceleration target (50% project acceleration). Figure 3 shows an
example of a specific activity being targeted with a 50% acceleration. What is unknown until
the simulation has been run is the impact on the project as a whole from the acceleration of the
targeted activity.




                             Figure 2 – Project-based Acceleration Goal




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       4
Figure 3 – Activity-based Acceleration Goal


Defining Acceleration Criteria
Once the acceleration goal has been defined, the second step is to define acceleration criteria.
Acceleration criteria are rules that the simulation adheres to when incrementally attempting to
accelerate the schedule. Criteria steps define the following:

The Action: What change should be applied during the acceleration. For example,

    •   Reduction in activity duration (e.g., reduce activity duration by up to 20%)
    •   Change in activity calendar (e.g., change from a 5 to a 6 day working week)
    •   Reduction of a lag (e.g., reduce lags by up to 50%)
    •   Removal of constraints (e.g., remove constraints on the schedule to determine the
        impact of a more free-flowing schedule)

The Target Set: which activity or groups of activities should the rule apply to? Analogous to
filter sets, the target set defines which activities receive the action e.g., “reduce engineering
durations by up to 10% with the exception of mechanical engineering.”

The Priority: when the acceleration simulation is run, emphasis is inherently around activities
that fall on or near the critical path. By definition, a project is driven by its critical (longest) path,
so only the activities on this path will actually drive a project completion. Within this set of
activities, the “action” and “target set” together pinpoint where and how in the schedule the
acceleration should be specifically aimed. Further, there is an additional layer known as
priority. Prioritization enables us to specify which of these activities is targeted first. There are
several options for prioritization:

    •   Earliest first: this results in most of the acceleration occurring in the early part of the
        project providing a front end-loaded acceleration scenario
    •   Latest first: this results in back-end activities being given focus during the acceleration
    •   Longest duration first: focuses on those activities with the longest duration first




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                        5
•   Easiest first: the topic of a separate white paper2 on “Schedule Compression
           Efficiency™,” this approach determines which activities are the best candidates for
           acceleration based on what is known as the path of least resistance.


Generate Scenario
Once the goal and criteria have been defined, the simulation can be run. A simulation consists
of hundreds or thousands of CPM analysis runs, with each iteration of the simulation applying
one or more of the criteria. What is important to note is that as each iteration is run, the
schedule incrementally accelerates until the goal is reached (or not reached, if indeed the goal
is too aggressive relative to the criteria defined).

The net result is an acceleration scenario that can be used as decision support during both
tactical and strategic project discussions regarding acceleration e.g., “how can we support a
three-month acceleration” or, “could we get back on track by focusing on construction,” or,
“can we define a stretch goal and incentivize the contractor to meet this goal.”

Figure 4 shows an example of two alternate scenarios, both using differing criteria, resulting in
two different accelerated project finish dates.




                           Figure 4 – Example of Multiple Acceleration Scenarios

There is no limit to the number of criteria or indeed the number and complexity of steps within
a criteria set. This means that a project team can develop and capture very detailed knowledge
about the project and use this as the basis for conducting the acceleration simulation.




2
    All white papers are available at http://www.projectacumen.com/resources/whitepapers.


+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                             6
The Benefit and Return on Investment (ROI) of Goal-Based Acceleration
One of the key benefits of running a goal-based acceleration is the immense time saving. The
technique runs thousands of iterations in a matter of seconds to generate a scenario that
would otherwise, in a scheduling tool, take days if not weeks to create manually.

Secondly, for those software or simulation skeptics, this approach is not taking away from the
expertise of the planner; in fact, the very opposite. By capturing the criteria as defined by the
planner, the technique is eliminating the manual process of generating alternate scenarios,
allowing them to focus instead on analyzing the results and making highly informed decisions
as to which scenario to adopt.

Thirdly, without getting into the deep mechanics of CPM scheduling, whenever a change is
made to a schedule, there is a likelihood that the critical path may not just change in length,
but even worse, the path itself may actually jump to a different set of activities. Trying to
predict or second-guess this type of impact on a schedule when making changes is nigh on
impossible. Adopting a simulation based-approach removes this complexity, again allowing the
planner to focus on making informed decisions about the scenarios generated.


How Does it Differ from a Monte-Carlo Simulation?
While this could be perceived as similar in nature to a risk-based Monte-Carlo simulation, the
technique, in reality, is very different. Risk-based simulations use ranges of durations to
determine a statistically most likely outcome. Instead, goal-based acceleration targets specific
activities using incremental duration compression based upon criteria that the project team put
forward. Further, a goal-based acceleration actually produces a deterministic end-result—that
is, an accelerated schedule that can be adopted going forward as the project plan. This output
is very different from the range-based output from a schedule risk analysis, which often causes
confusion.


When Should Schedule Acceleration Be Carried Out?
As well as having several phases (e.g., planned, in progress, complete), projects also carry
multiple “bases.” Think of a project basis as a viewpoint or perception…

Firstly there is the plan basis. Often known as a baseline, this is the agreed upon schedule for a
project that forecasts when key milestones will be completed.

Secondly there is the actual basis. This is the statused version of an in-progress schedule that
(ideally) reflects true reality. It accounts for historical completions, actual progress and delays
as well as changes made to the original plan. The actual basis all too often deviates from the


+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       7
plan basis. Comparing the differences between these two enables us to track and understand
project performance.

Thirdly there are various types of what is know as management basis. Also referred to as a
target schedule, a management basis is often driven by commercial or strategic factors such
as “time to market”, “investor requirements” and even simple factors such as “management
would like to finish by…”

It is extremely rare for a project to have perfect alignment and absence of deviation between a
plan, actual and management basis. In other words, a project essentially has three schedules
that are being worked. The further out of alignment that these are with each other, the more the
project is perceived to be slipping, failing or, “doing badly.”

In response to this alignment challenge, goal-based schedule acceleration is an ideal
technique for bringing these three forecasts back into alignment. Typical use cases include:

    •   Aligning a planned schedule to fit a management-defined completion date. e.g., “the
        schedule shows a December 2015 completion date and management are asking for a
        June 2015 completion at the latest.”
    •   Providing “what if…” scenarios when determining how a planned project can be
        accelerated. E.g., “if we were able to bring the project on-line sooner so as to benefit
        from earlier operational revenue, what would be the best scenario to achieve this?”
    •   Bringing a delayed project in execution back on track (realignment to the plan). E.g.,
        “what is the most effective means of regaining the three months of schedule slippage
        that we’ve already incurred?”
    •   Achieving schedule competitiveness. E.g., “independent benchmarking shows we
        should complete within 50 months; our schedule shows a 55 month completion—what
        is the best means of achieving this 50-month benchmark?”


Accounting for Resources
So what of the added complexity of resources within a schedule? Questions such as, “surely, if
I accelerate my schedule, don’t I need to consider the impact on resources?” The answer is
yes. If you happen to use resource-leveling when developing schedules (irrespective of
whether you are using goal-based acceleration), each time you make a change to your
schedule, you need to conduct resource leveling to determine whether the defined resource
pool can satisfy the schedule demand.

The exact same approach applies to goal-based acceleration. Develop your schedule, conduct
an acceleration, and then conduct resource leveling to determine the impact of resources on
the schedule i.e., can my resources provide for the demand of the acceleration?

+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       8
If your scheduling preference is not to use resource-leveling, then once you have conducted a
schedule acceleration, you can simply look at the change to resource usage by plotting
resource histograms and profiles in the exact same way you would using a traditional CPM
approach.


Goal-based Acceleration: Faster Completion, but at What Price?
One of the additional benefits of conducting a goal-based acceleration is to get a better
understanding of the acceleration/risk benefit. Acceleration of course comes with a price so
being able to determine the change in schedule risk exposure as a result of the acceleration is
very valuable.

An example of this is shown in Figure 5. A recent application of this technique was applied to a
project with a December 2018 completion date. A previous risk assessment had shown that
the P50 date pushed out to March 2019, a 3-month slip. The project investment group wanted
to look at faster alternatives and so a goal-based acceleration was applied resulting in an
accelerated scenario of 12 months earlier (early December 2017). A subsequent risk analysis
on this scenario showed a P50 accelerated date of May 2018.

So as a result of the simulation, 12 months acceleration was achieved but the risk exposure
increased from three months to five months. With this insight, the investment team was able to
make an informed decision about moving forward with the accelerated scenario knowing that
despite the increase in risk exposure, the new risk-adjusted accelerated date was still 7
months earlier than the original schedule date. Earlier completion with managed risk
exposure—a true win-win scenario.


                                                                       3 month
          5 month risk exposure                                          risk
                                                                       exposure




                       Figure 5 – Impact of Risk on an Accelerated Scenario




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       9
Conclusion
Goal-based schedule acceleration is a technique that combines advanced CPM simulation
with a knowledge-based approach to generate informed and realistic scenarios for project
acceleration. It acts as a highly valuable decision-support tool eliminating days of manual
“what if…” analysis and enables schedule alignment during both the planning and execution
phase.

Combined with schedule risk analysis, it is an excellent basis for determining the
cost/risk/schedule benefit of adopting a chosen accelerated scenario and equally importantly,
it is defendable given it is based on criteria as defined by the project team themselves.

Goal-based schedule acceleration has been developed by Acumen and is a core component of
the Acumen S1 > S5™ Schedule Maturity Model. Acumen 360, Acumen’s goal-based
acceleration software, integrates with both MS Project and Primavera.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       10

Weitere ähnliche Inhalte

Was ist angesagt?

Ch23-Software Engineering 9
Ch23-Software Engineering 9Ch23-Software Engineering 9
Ch23-Software Engineering 9
Ian Sommerville
 
2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)
douggillis
 

Was ist angesagt? (19)

Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Ch23-Software Engineering 9
Ch23-Software Engineering 9Ch23-Software Engineering 9
Ch23-Software Engineering 9
 
Chap007
Chap007Chap007
Chap007
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
 
CSC-1986.original
CSC-1986.originalCSC-1986.original
CSC-1986.original
 
Crtical chain m ethod ver 2
Crtical chain m ethod ver 2Crtical chain m ethod ver 2
Crtical chain m ethod ver 2
 
Project presentation
Project presentationProject presentation
Project presentation
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & Tricks
 
Rca paper
Rca paperRca paper
Rca paper
 
Communication 1
Communication 1Communication 1
Communication 1
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)
 
MS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowMS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must know
 
An Alternate Approach to Cost and Schedule Integration
An Alternate Approach to Cost and Schedule IntegrationAn Alternate Approach to Cost and Schedule Integration
An Alternate Approach to Cost and Schedule Integration
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration Estimation
 
Agile Project Management Procedures
Agile Project Management ProceduresAgile Project Management Procedures
Agile Project Management Procedures
 
Project Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions ManualProject Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions Manual
 

Ähnlich wie Faster, Yet Less Risky Projects through Goal-Based Schedule Acceleration

Info461ProjectCharterEskridgeAs08
Info461ProjectCharterEskridgeAs08Info461ProjectCharterEskridgeAs08
Info461ProjectCharterEskridgeAs08
Greg Eskridge
 
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvhdcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
WrushabhShirsat3
 
Project-Planning
Project-PlanningProject-Planning
Project-Planning
Ron Drew
 
Presentation by Rajesh Kumar Mudiakal
Presentation by Rajesh Kumar MudiakalPresentation by Rajesh Kumar Mudiakal
Presentation by Rajesh Kumar Mudiakal
PMI_IREP_TP
 
Presentation by meghna jadhav
Presentation by meghna jadhavPresentation by meghna jadhav
Presentation by meghna jadhav
PMI_IREP_TP
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Charlie Jackson
 

Ähnlich wie Faster, Yet Less Risky Projects through Goal-Based Schedule Acceleration (20)

Benchmarking Project Schedules
Benchmarking Project SchedulesBenchmarking Project Schedules
Benchmarking Project Schedules
 
Budgeting in SCRUM
Budgeting in SCRUM Budgeting in SCRUM
Budgeting in SCRUM
 
Budgeting in SCRUM
Budgeting in SCRUM Budgeting in SCRUM
Budgeting in SCRUM
 
Info461ProjectCharterEskridgeAs08
Info461ProjectCharterEskridgeAs08Info461ProjectCharterEskridgeAs08
Info461ProjectCharterEskridgeAs08
 
Project Planning
Project PlanningProject Planning
Project Planning
 
Planning.ppt
Planning.pptPlanning.ppt
Planning.ppt
 
5-ProjPlanning.ppt
5-ProjPlanning.ppt5-ProjPlanning.ppt
5-ProjPlanning.ppt
 
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvhdcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
dcvdhusdbsduvb0sdyvbsdyvbsdvysdvysdbvsydvdbvbyubdvbdvhvhvhvh
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615
 
Project-Planning
Project-PlanningProject-Planning
Project-Planning
 
Chapter 06
Chapter 06Chapter 06
Chapter 06
 
SE18_Lec 13_ Project Planning
SE18_Lec 13_ Project PlanningSE18_Lec 13_ Project Planning
SE18_Lec 13_ Project Planning
 
Presentation by Rajesh Kumar Mudiakal
Presentation by Rajesh Kumar MudiakalPresentation by Rajesh Kumar Mudiakal
Presentation by Rajesh Kumar Mudiakal
 
Presentation by meghna jadhav
Presentation by meghna jadhavPresentation by meghna jadhav
Presentation by meghna jadhav
 
Managing projects
Managing projectsManaging projects
Managing projects
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
SE_Lec 12_ Project Planning
SE_Lec 12_ Project PlanningSE_Lec 12_ Project Planning
SE_Lec 12_ Project Planning
 
Managing Project Success
Managing Project SuccessManaging Project Success
Managing Project Success
 

Mehr von Acumen

Mehr von Acumen (20)

How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us Down
 
Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen risk
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned Value
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / Energy
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
Meet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationMeet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent Acceleration
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
 
Smarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceSmarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project Performance
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Acumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen Fuse & Customer Case Study
Acumen Fuse & Customer Case Study
 
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule Integration
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project Success
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0
 
Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute Resolution
 
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAchieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
 

Kürzlich hochgeladen

+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Victor Rentea
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Victor Rentea
 

Kürzlich hochgeladen (20)

+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
 
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelMcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
 
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
AI in Action: Real World Use Cases by Anitaraj
AI in Action: Real World Use Cases by AnitarajAI in Action: Real World Use Cases by Anitaraj
AI in Action: Real World Use Cases by Anitaraj
 
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
 
Six Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal OntologySix Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal Ontology
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)
 
Introduction to use of FHIR Documents in ABDM
Introduction to use of FHIR Documents in ABDMIntroduction to use of FHIR Documents in ABDM
Introduction to use of FHIR Documents in ABDM
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistan
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
Vector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxVector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptx
 

Faster, Yet Less Risky Projects through Goal-Based Schedule Acceleration

  • 1. // Faster, Yet Less Risky Projects through Goal-Based Schedule Acceleration Dr. Dan Patterson, PMP CEO & President, Acumen November 2011 +1 512 291 6261 // info@projectacumen.com www.projectacumen.com
  • 2. Table of Contents Introduction ................................................................................................................. 3   What is Goal-Based Schedule Acceleration? ................................................................ 3   Setting the Acceleration Goal ...................................................................................... 4   Figure 1 – Defining an Acceleration Goal ............................................................. 4   Figure 2 – Project-based Acceleration Goal ......................................................... 4   Figure 3 – Activity-based Acceleration Goal ........................................................ 5   Defining Acceleration Criteria ...................................................................................... 5   Generate Scenario ....................................................................................................... 6   Figure 4 – Example of Multiple Acceleration Scenarios ........................................ 6   The Benefit and Return on Investment (ROI) of Goal-Based Acceleration .................... 7   How Does it Differ from a Monte-Carlo Simulation? ..................................................... 7   When Should Schedule Acceleration Be Carried Out? .................................................. 7   Accounting for Resources ............................................................................................ 8   Goal-based Acceleration: Faster Completion, but at What Price? ................................ 9   Figure 5 – Impact of Risk on an Accelerated Scenario ......................................... 9   Conclusion ................................................................................................................. 10   +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 2
  • 3. Introduction This white paper introduces a new, highly compelling technique for accelerating project schedules. Unlike traditional techniques such as ‘network crashing’, goal-based schedule acceleration results in informed acceleration decisions based on criteria that are relevant and specific to your project. In short: targeted, meaningful changes to a schedule so as to achieve acceleration, yet still retain realism and achievability. What is Goal-Based Schedule Acceleration? Goal-based schedule acceleration1 is a CPM (critical path method) based technique for accelerating project schedules. It has been developed to solve the challenge of ensuring that a project schedule is realistic; is aligned with stakeholder expectations; and, of course, is executed successfully. Put forward a schedule that is too aggressive and it will not be achieved; put forward a conservative schedule and it will not satisfy stakeholders desires to finish earlier... The technique builds upon the widely accepted scheduling technique known as –CPM scheduling. CPM scheduling is a means of determining start and finish dates based upon a sequence of activities whose durations are known. This is the underpinning of widely used commercial scheduling tools such as MS Project and Primavera. Goal-Based Schedule Acceleration takes this technique a step further by conducting multiple CPM analyses in the form of a simulation incrementally adjusting pinpointed sets of activities based upon defined criteria. The reason why this technique is so powerful is two-fold: • Firstly, it is using CPM analysis to schedule the project – it is true to the widely accepted, and globally used, technique for scheduling projects. • Secondly, it uses criteria that are defined by project team members to make informed decisions as to which activities (or groups of activities) should be targeted for acceleration. The technique is based upon three steps: Set  Goal   Define  Criteria   Generate  Scenario   1 For more information about schedule acceleration, visit http://www.projectacumen.com/products/acumen-360/features/ +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 3
  • 4. Setting the Acceleration Goal The acceleration goal is the target that we are trying to achieve. It can be either a project- based target, for example, “accelerate the project as a whole by 10%” or it can be an activity/milestone-based target e.g. “accelerate Project Sanction or First Oil by three months”. Acceleration goals can be defined as: • Percentage acceleration: e.g., accelerate by 5% • Duration acceleration: e.g., reduce duration by 30 days • New finish date: e.g., complete by 30 June 2015 All three acceleration goal types have one common objective: define a new target relative to the current schedule target as a means of making an improvement or adjustment to the project plan. Figure 1 shows an example of defining a new target date to be 50% of the original duration. The current project completion date is February 6, 2013 and the new goal date has been targeted at January 16, 2012. Figure 1 – Defining an Acceleration Goal In the case of accelerating a specific activity, compression or other changes needed to achieve this acceleration are only applied to activities leading up to the targeted activity. Activities falling after the targeted activity do not get altered; however, they may incur a date change as a result of the knock-on effect of predecessor activities now finishing earlier. Figure 2 shows an example of a project-based acceleration target (50% project acceleration). Figure 3 shows an example of a specific activity being targeted with a 50% acceleration. What is unknown until the simulation has been run is the impact on the project as a whole from the acceleration of the targeted activity. Figure 2 – Project-based Acceleration Goal +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 4
  • 5. Figure 3 – Activity-based Acceleration Goal Defining Acceleration Criteria Once the acceleration goal has been defined, the second step is to define acceleration criteria. Acceleration criteria are rules that the simulation adheres to when incrementally attempting to accelerate the schedule. Criteria steps define the following: The Action: What change should be applied during the acceleration. For example, • Reduction in activity duration (e.g., reduce activity duration by up to 20%) • Change in activity calendar (e.g., change from a 5 to a 6 day working week) • Reduction of a lag (e.g., reduce lags by up to 50%) • Removal of constraints (e.g., remove constraints on the schedule to determine the impact of a more free-flowing schedule) The Target Set: which activity or groups of activities should the rule apply to? Analogous to filter sets, the target set defines which activities receive the action e.g., “reduce engineering durations by up to 10% with the exception of mechanical engineering.” The Priority: when the acceleration simulation is run, emphasis is inherently around activities that fall on or near the critical path. By definition, a project is driven by its critical (longest) path, so only the activities on this path will actually drive a project completion. Within this set of activities, the “action” and “target set” together pinpoint where and how in the schedule the acceleration should be specifically aimed. Further, there is an additional layer known as priority. Prioritization enables us to specify which of these activities is targeted first. There are several options for prioritization: • Earliest first: this results in most of the acceleration occurring in the early part of the project providing a front end-loaded acceleration scenario • Latest first: this results in back-end activities being given focus during the acceleration • Longest duration first: focuses on those activities with the longest duration first +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 5
  • 6. Easiest first: the topic of a separate white paper2 on “Schedule Compression Efficiency™,” this approach determines which activities are the best candidates for acceleration based on what is known as the path of least resistance. Generate Scenario Once the goal and criteria have been defined, the simulation can be run. A simulation consists of hundreds or thousands of CPM analysis runs, with each iteration of the simulation applying one or more of the criteria. What is important to note is that as each iteration is run, the schedule incrementally accelerates until the goal is reached (or not reached, if indeed the goal is too aggressive relative to the criteria defined). The net result is an acceleration scenario that can be used as decision support during both tactical and strategic project discussions regarding acceleration e.g., “how can we support a three-month acceleration” or, “could we get back on track by focusing on construction,” or, “can we define a stretch goal and incentivize the contractor to meet this goal.” Figure 4 shows an example of two alternate scenarios, both using differing criteria, resulting in two different accelerated project finish dates. Figure 4 – Example of Multiple Acceleration Scenarios There is no limit to the number of criteria or indeed the number and complexity of steps within a criteria set. This means that a project team can develop and capture very detailed knowledge about the project and use this as the basis for conducting the acceleration simulation. 2 All white papers are available at http://www.projectacumen.com/resources/whitepapers. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 6
  • 7. The Benefit and Return on Investment (ROI) of Goal-Based Acceleration One of the key benefits of running a goal-based acceleration is the immense time saving. The technique runs thousands of iterations in a matter of seconds to generate a scenario that would otherwise, in a scheduling tool, take days if not weeks to create manually. Secondly, for those software or simulation skeptics, this approach is not taking away from the expertise of the planner; in fact, the very opposite. By capturing the criteria as defined by the planner, the technique is eliminating the manual process of generating alternate scenarios, allowing them to focus instead on analyzing the results and making highly informed decisions as to which scenario to adopt. Thirdly, without getting into the deep mechanics of CPM scheduling, whenever a change is made to a schedule, there is a likelihood that the critical path may not just change in length, but even worse, the path itself may actually jump to a different set of activities. Trying to predict or second-guess this type of impact on a schedule when making changes is nigh on impossible. Adopting a simulation based-approach removes this complexity, again allowing the planner to focus on making informed decisions about the scenarios generated. How Does it Differ from a Monte-Carlo Simulation? While this could be perceived as similar in nature to a risk-based Monte-Carlo simulation, the technique, in reality, is very different. Risk-based simulations use ranges of durations to determine a statistically most likely outcome. Instead, goal-based acceleration targets specific activities using incremental duration compression based upon criteria that the project team put forward. Further, a goal-based acceleration actually produces a deterministic end-result—that is, an accelerated schedule that can be adopted going forward as the project plan. This output is very different from the range-based output from a schedule risk analysis, which often causes confusion. When Should Schedule Acceleration Be Carried Out? As well as having several phases (e.g., planned, in progress, complete), projects also carry multiple “bases.” Think of a project basis as a viewpoint or perception… Firstly there is the plan basis. Often known as a baseline, this is the agreed upon schedule for a project that forecasts when key milestones will be completed. Secondly there is the actual basis. This is the statused version of an in-progress schedule that (ideally) reflects true reality. It accounts for historical completions, actual progress and delays as well as changes made to the original plan. The actual basis all too often deviates from the +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 7
  • 8. plan basis. Comparing the differences between these two enables us to track and understand project performance. Thirdly there are various types of what is know as management basis. Also referred to as a target schedule, a management basis is often driven by commercial or strategic factors such as “time to market”, “investor requirements” and even simple factors such as “management would like to finish by…” It is extremely rare for a project to have perfect alignment and absence of deviation between a plan, actual and management basis. In other words, a project essentially has three schedules that are being worked. The further out of alignment that these are with each other, the more the project is perceived to be slipping, failing or, “doing badly.” In response to this alignment challenge, goal-based schedule acceleration is an ideal technique for bringing these three forecasts back into alignment. Typical use cases include: • Aligning a planned schedule to fit a management-defined completion date. e.g., “the schedule shows a December 2015 completion date and management are asking for a June 2015 completion at the latest.” • Providing “what if…” scenarios when determining how a planned project can be accelerated. E.g., “if we were able to bring the project on-line sooner so as to benefit from earlier operational revenue, what would be the best scenario to achieve this?” • Bringing a delayed project in execution back on track (realignment to the plan). E.g., “what is the most effective means of regaining the three months of schedule slippage that we’ve already incurred?” • Achieving schedule competitiveness. E.g., “independent benchmarking shows we should complete within 50 months; our schedule shows a 55 month completion—what is the best means of achieving this 50-month benchmark?” Accounting for Resources So what of the added complexity of resources within a schedule? Questions such as, “surely, if I accelerate my schedule, don’t I need to consider the impact on resources?” The answer is yes. If you happen to use resource-leveling when developing schedules (irrespective of whether you are using goal-based acceleration), each time you make a change to your schedule, you need to conduct resource leveling to determine whether the defined resource pool can satisfy the schedule demand. The exact same approach applies to goal-based acceleration. Develop your schedule, conduct an acceleration, and then conduct resource leveling to determine the impact of resources on the schedule i.e., can my resources provide for the demand of the acceleration? +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 8
  • 9. If your scheduling preference is not to use resource-leveling, then once you have conducted a schedule acceleration, you can simply look at the change to resource usage by plotting resource histograms and profiles in the exact same way you would using a traditional CPM approach. Goal-based Acceleration: Faster Completion, but at What Price? One of the additional benefits of conducting a goal-based acceleration is to get a better understanding of the acceleration/risk benefit. Acceleration of course comes with a price so being able to determine the change in schedule risk exposure as a result of the acceleration is very valuable. An example of this is shown in Figure 5. A recent application of this technique was applied to a project with a December 2018 completion date. A previous risk assessment had shown that the P50 date pushed out to March 2019, a 3-month slip. The project investment group wanted to look at faster alternatives and so a goal-based acceleration was applied resulting in an accelerated scenario of 12 months earlier (early December 2017). A subsequent risk analysis on this scenario showed a P50 accelerated date of May 2018. So as a result of the simulation, 12 months acceleration was achieved but the risk exposure increased from three months to five months. With this insight, the investment team was able to make an informed decision about moving forward with the accelerated scenario knowing that despite the increase in risk exposure, the new risk-adjusted accelerated date was still 7 months earlier than the original schedule date. Earlier completion with managed risk exposure—a true win-win scenario. 3 month 5 month risk exposure risk exposure Figure 5 – Impact of Risk on an Accelerated Scenario +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 9
  • 10. Conclusion Goal-based schedule acceleration is a technique that combines advanced CPM simulation with a knowledge-based approach to generate informed and realistic scenarios for project acceleration. It acts as a highly valuable decision-support tool eliminating days of manual “what if…” analysis and enables schedule alignment during both the planning and execution phase. Combined with schedule risk analysis, it is an excellent basis for determining the cost/risk/schedule benefit of adopting a chosen accelerated scenario and equally importantly, it is defendable given it is based on criteria as defined by the project team themselves. Goal-based schedule acceleration has been developed by Acumen and is a core component of the Acumen S1 > S5™ Schedule Maturity Model. Acumen 360, Acumen’s goal-based acceleration software, integrates with both MS Project and Primavera. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 10