// Developing Standards for
Enterprise Schedule Quality


            Tom Polen
 Director Professional Services, Acumen


           November 2012




                            +1 512 291 6261 // info@projectacumen.com
                                          www.projectacumen.com
Table of Contents
Developing Standards for Enterprise Schedule Quality ................................................................3

A Framework for Schedule Quality ...............................................................................................3

Structuring Maturity Goals ..........................................................................................................4
  Short-Term Maturity Goals .......................................................................................................4
  Mid-Term goals ........................................................................................................................4
  Long-Term Goals ......................................................................................................................5

Practical Implementation of Scheduling Quality at the Enterprise Level .....................................5

Testing and Benchmarking..........................................................................................................7

Post-Pilot Rollout.........................................................................................................................8




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                                        2
Developing Standards for Enterprise Schedule Quality
Project-oriented organizations must approach quality from all angles—from the planning
process to execution, and ultimately, through customer satisfaction. The need for quality is a
constant, guiding force. However, as thousands, perhaps millions, of companies can attest,
while quality is not necessarily expensive in the traditional sense, it can be difficult to obtain
and an absence of quality can be costly and potentially fatal for a company.
Enterprise schedule quality refers to the soundness and reliability of a project schedule and is
essential to successful project execution. Schedule quality is a direct indicator of whether a
plan is realistic and achievable.
The Integrated Master Schedule (IMS) is the cornerstone of the planning and execution
process, and is only as strong as its weakest link. There can be many contributors to the IMS—
your own plans may involve a single company, hundreds of suppliers, or somewhere in
between. Poor quality in any area of your plan can undermine successful execution by
creating an unrealistic view. In fact, erroneous or low quality data, once present in the IMS can
immediately begin a degradation process, which ultimately obscures the true execution-
impacting events from plain sight. When truly critical activities are viewed as insignificant or
time-insensitive, predicted execution can unravel.
Ensuring quality in the IMS can be achieved through a three-step process
    1. Define quality standards for the IMS.
    2. Communicate the standards
    3. Continually ‘raise the bar’ to bring higher overall maturity
Quality in the details of project planning and execution drive the overall effectiveness of your
organization. Your company is ultimately defined by the work that you perform. Work that is
performed to high quality standards by a mature organization will be rewarded by customers in
the form of loyalty and industry recognition.

A Framework for Schedule Quality
Through a five-stage, four step process you can improve the quality of your schedule. Each
stage of this framework furthers a schedule’s maturity resulting in a schedule that is:

1. Structurally sound: well built using appropriate CPM scheduling techniques

2. Realistic: accounting for known scope as well as unknown potential risks and opportunities.

3. Optimized: thoroughly reviewed for potential cost/schedule acceleration candidates.

4. Validated: buy-in obtained from the project team, subject matter experts and
        the management team for the project.

If all four of these objectives can be achieved, then project stakeholder expectations will be
aligned, the true scope of execution understood, and an achievable target against which the
project can be tracked will be attained. In short, a sound basis of schedule will be


+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       3
accomplished thus overcoming one of the biggest project management challenges today: poor
and unrealistic planning.
    Acumen Method


    S1 //              S2 //                S3 //       S4 //              S5 //
     The Base          Critiqued              Risk      Optimized           Team
     Schedule                               Adjusted                       Aligned

                             Figure 1 - Five Stages of Schedule Maturity
Figure 1 shows the five stages of schedule maturity. The process begins with a non-validated
schedule developed using a Critical Path Method (CPM) scheduling tool. A schedule at S1 has
questionable realism and often a flawed framework.
An S2 schedule has undergone a quality analysis process and improvement. At this stage, the
project team has identified any troublesome areas of the schedule and made corrections.
Stage 3 accounts for risk and uncertainty, weighing the impact of the ‘known unknowns’ that
could arise during project execution.
S4 and S5 involve optimizing the plan to help meet stakeholder objectives and goals and
incorporating team input to ensure that they are ‘bought in’ to the new optimized schedule.
Using metrics and agreed upon standards is helpful in assessing a project’s maturity at any
stage of the framework.

Structuring Maturity Goals
Commitment to achieving higher levels of maturity must persist at all levels of the organization,
from functional positions through to the CEO and board of directors.
Maturity cannot be purchased or developed overnight. Achieving higher maturity is a long-term
strategic process. However ultimately, it will be attained through a series of short, mid, and
long-term activities.
Here are examples of short, mid, and long-term goals you may wish to consider:

Short-Term Maturity Goals
    -­‐   Start the maturity development process itself—a step toward higher maturity
    -­‐   Identify a project candidate for piloting the revised quality standards
    -­‐   Communicate the importance of higher maturity throughout the organization
    -­‐   Schedule frequent reviews to determine if the quality metrics and supporting analysis
          processes are helping to drive improved quality.

Mid-Term Maturity Goals
    -­‐   Expand the pilot to include a variety of projects, small, medium and large
    -­‐   Weigh the quality criteria of larger programs versus those of smaller programs


+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                          4
-­‐   Assure that a common quality language can be used across programs of all types and
          sizes
    -­‐   Keep senior management informed of successes, failures, and the evolution of the
          roadmap toward higher quality
    -­‐   Quantify the real financial cost of failures in quality; your real examples will become your
          own customized case study used to justify the return on the investment in quality

Long-Term Maturity Goals
    -­‐   Review accomplishments which promote higher maturity annually
    -­‐   Assess ongoing resource requirements
    -­‐   Ask yourself – Is the maturity “buzz” still in the air? What activities can keep the
          organization focused on quality and maturity?

Practical Implementation of Scheduling Quality at the Enterprise Level
Every aspect of project execution can benefit from higher quality. For this reason, quality
improvement is a multi-stakeholder exercise, requiring participation from all project
stakeholders, including customers and suppliers.
By using Acumen Fuse to create a metric template, discussions can begin as to which metrics
should be used to measure schedule and project execution quality.




                                Figure 2 - Using Metrics to Meet Goals

+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                         5
The most critical elements for mapping metrics to enterprise quality goals are:
    -­‐   Determine quality attributes – e.g., schedule quality, logic quality, float, baseline
          compliance
    -­‐   Select metrics to support the quality attributes
    -­‐   Select thresholds and scoring method
    -­‐   Group metrics in context by associated quality attribute so that the aggregate scores
          are meaningful quality indicators


Some of the most popular and prevalent quality checks are:
Missing Logic: A core schedule quality check. In theory, all activities should have at least one
predecessor and one successor associated with it. Failure to do so will impact the quality of
results derived from a time analysis as well as a risk analysis.


Negative Float: Negative float is a result of an artificially accelerated or constrained schedule.
Negative float indicates that a schedule is not possible based on the current completion dates.
Ideally, there should not be any negative float in the schedule.


Logic Density™: In theory, this value should be at least two. An average of less than two
indicates that the schedule should be reviewed and updated with additional logic links. An
upper limit of four is also recommended – logic density above this threshold indicates overly
complex logic within a schedule.


Redundancy Index™: The Redundancy Index identifies overly complex logic caused by
extraneous logic links.


Insufficient Detail™: Activities with a high duration relative to the duration of the project are
generally an indication that a plan is too high level for adequate planning and controls.
Consider further developing the schedule by adding more detailed activities.


SF Predecessors: Start-to-Finish (SF) links should be used very rarely. Having a successor
activity happens before the predecessor activity is generally a poor practice when planning.


Start Compliance: Start Compliance calculates the percentage of activities starting or that have
started outside the expected baselined period relative to the baselined activities starting or that
should have started within this period.


Finish Compliance: Finish Compliance calculates the percentage of activities finishing or that
have finished outside the expected baselined period relative to the baselined activities finishing
or that should have finished within this period.


+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       6
Risk Hot Spots: The combination of multiple successors and high criticality combined typically
result in a highly complex and risk-prone hotspot within a schedule.


Hidden Critical Paths: Hidden Paths is one of the most powerful risk exposure metrics. It
shows those activities that have a high criticality (how often the task is critical) that in absence
of risk do NOT fall on the critical path. If an activity has a high Hidden Path score, it should be
considered as important as an activity that is critical.

Testing and Benchmarking
Prior to a pilot, scenario testing may be desired to benchmark the metrics themselves. Are certain
metrics always failing the tests? Are the scores so high or low that they are not providing constructive
information for quality improvements? Metrics should be calibrated according to both the quality result
and the overall pursuit of maturity. For example, if a small company with relatively immature processes
sets the quality standards too high, they may eventually feel that the standards are unachievable and
abandon the pursuit of higher maturity. This is why goal setting for short, mid, and long-term is an
essential part of the process. The definition of goals calibrated to each specific maturity level will help
ensure that measurements will lead to near-term achievable improvements.
As the team matures and becomes satisfied with results for their current level of maturity, the
goal can be raised and the challenge increased.
Typically, a mid-size or large program may the best candidate for a pilot. With sufficient
resources, multiple concurrent pilots may be desired.
Attributes of an ideal pilot program candidate include:
    -­‐   a highly visible program;
    -­‐   a progressive, advanced project team team;
    -­‐   external contributors to the schedule –i.e., subcontractors; and,
    -­‐   a program manager and customer that are focused on quality.
A quality pilot program brings increased responsibility to the project team. If quality metrics are
properly calibrated to drive higher maturity, not all areas of the schedule will pass the quality
criteria each month. It is essential that quality breaches are treated as constructive
opportunities rather than punitive events. Recognizing areas that proactively drive quality
improvements is far more beneficial than emphasizing instances of failure. If improvement is
not celebrated and failure is punished, the quality improvement efforts will become increasingly
unpopular.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                           7
Figure 3 - The Fuse Ribbon Analyzer computes overall quality scores in any number of
  categories from a series of subcontractor schedules. The project team may decide that all
          schedules must score “Green” before they can be integrated into the IMS.

Post-Pilot Rollout
With a successful pilot, your organization may elect to roll out the quality standards gradually
to additional projects, begin all new projects with the quality standards in place, or apply them
to all active and new projects.
The most effective suppliers can differentiate themselves by applying the quality standards
across the enterprise portfolio. This assures customers that they will experience a consistently
high standard of quality whenever they do business with these suppliers.
The commitment to quality and higher maturity must be relentless. With ever-increasing
competition, these are critical differentiators. Today’s metrics and quality standards may not
meet tomorrow’s needs. Commitment, persistence, and frequent sharing of successes and
failures will cultivate the quality-oriented culture that leads to higher levels of maturity and an
improved competitive position.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       8

Weitere ähnliche Inhalte

Was ist angesagt?

Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Glen Alleman
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckSHAZEBALIKHAN1
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and AgileGlen Alleman
 
Capabilities based planning essay
Capabilities based planning essayCapabilities based planning essay
Capabilities based planning essayGlen Alleman
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growthGlen Alleman
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleGlen Alleman
 
Agile Project Management Procedures
Agile Project Management ProceduresAgile Project Management Procedures
Agile Project Management ProceduresGlen Alleman
 
Project Management Control Systems
Project Management Control SystemsProject Management Control Systems
Project Management Control Systemsskillern
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 
Assessing Enterprise Project Risk
Assessing Enterprise Project RiskAssessing Enterprise Project Risk
Assessing Enterprise Project RiskGlen Alleman
 
Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation Glen Alleman
 
Integrating risk with earned value
Integrating risk with earned valueIntegrating risk with earned value
Integrating risk with earned valueGlen Alleman
 
Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountGlen Alleman
 
Managing Deploymemt of ERP Systems in the Publishing Domain
Managing Deploymemt of ERP Systems in the Publishing DomainManaging Deploymemt of ERP Systems in the Publishing Domain
Managing Deploymemt of ERP Systems in the Publishing DomainGlen Alleman
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project managementGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
MCS Technical Article
MCS Technical ArticleMCS Technical Article
MCS Technical ArticleMartin Gough
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleGlen Alleman
 

Was ist angesagt? (20)

Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality Check
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
Capabilities based planning essay
Capabilities based planning essayCapabilities based planning essay
Capabilities based planning essay
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master Schedule
 
Agile Project Management Procedures
Agile Project Management ProceduresAgile Project Management Procedures
Agile Project Management Procedures
 
Project Management Control Systems
Project Management Control SystemsProject Management Control Systems
Project Management Control Systems
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Assessing Enterprise Project Risk
Assessing Enterprise Project RiskAssessing Enterprise Project Risk
Assessing Enterprise Project Risk
 
Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation
 
Integrating risk with earned value
Integrating risk with earned valueIntegrating risk with earned value
Integrating risk with earned value
 
Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is Paramount
 
Managing Deploymemt of ERP Systems in the Publishing Domain
Managing Deploymemt of ERP Systems in the Publishing DomainManaging Deploymemt of ERP Systems in the Publishing Domain
Managing Deploymemt of ERP Systems in the Publishing Domain
 
The 5 Immutable principles of project management
The 5 Immutable principles of project managementThe 5 Immutable principles of project management
The 5 Immutable principles of project management
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
MCS Technical Article
MCS Technical ArticleMCS Technical Article
MCS Technical Article
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 

Ähnlich wie Developing Standards for Enterprise Schedule Quality

significance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsignificance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsarah david
 
significance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsignificance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsarah david
 
significance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsignificance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsarah david
 
significance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsignificance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsarah david
 
SSCG Project Management Services
SSCG Project Management ServicesSSCG Project Management Services
SSCG Project Management ServicesEugene Nizeyimana
 
SSCG Project Management Services
SSCG Project Management ServicesSSCG Project Management Services
SSCG Project Management ServicesSSCG Consulting
 
Brochure PlanningPackage.com
Brochure PlanningPackage.comBrochure PlanningPackage.com
Brochure PlanningPackage.commkhilauria
 
P3M3 - Discovery Assessment
P3M3 - Discovery AssessmentP3M3 - Discovery Assessment
P3M3 - Discovery AssessmentProfeo
 
Building capability through maturity assessments 1.0
Building capability through maturity assessments 1.0Building capability through maturity assessments 1.0
Building capability through maturity assessments 1.0Maven
 
Project Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleProject Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleKate Pynn
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure CycleGlen Alleman
 
Building risk tolerance
Building risk toleranceBuilding risk tolerance
Building risk toleranceGlen Alleman
 
Project Management @ Ektoo
Project Management @ EktooProject Management @ Ektoo
Project Management @ Ektooshofiulalom
 
Estimation & project planning
Estimation & project planningEstimation & project planning
Estimation & project planningdia22
 
Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason Uyder
 
Tavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-FinalTavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-FinalSEKHAR KOMMURI
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAddisu15
 
Presentation by beebejan valiyakath
Presentation by beebejan valiyakathPresentation by beebejan valiyakath
Presentation by beebejan valiyakathPMI_IREP_TP
 

Ähnlich wie Developing Standards for Enterprise Schedule Quality (20)

significance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsignificance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptx
 
significance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsignificance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdf
 
significance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptxsignificance_of_test_estimating_in_the_software_development.pptx
significance_of_test_estimating_in_the_software_development.pptx
 
significance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdfsignificance_of_test_estimating_in_the_software_development.pdf
significance_of_test_estimating_in_the_software_development.pdf
 
SSCG Project Management Services
SSCG Project Management ServicesSSCG Project Management Services
SSCG Project Management Services
 
SSCG Project Management Services
SSCG Project Management ServicesSSCG Project Management Services
SSCG Project Management Services
 
Brochure PlanningPackage.com
Brochure PlanningPackage.comBrochure PlanningPackage.com
Brochure PlanningPackage.com
 
P3M3 - Discovery Assessment
P3M3 - Discovery AssessmentP3M3 - Discovery Assessment
P3M3 - Discovery Assessment
 
PMO assessment using OPM3 model
PMO assessment using OPM3 modelPMO assessment using OPM3 model
PMO assessment using OPM3 model
 
Building capability through maturity assessments 1.0
Building capability through maturity assessments 1.0Building capability through maturity assessments 1.0
Building capability through maturity assessments 1.0
 
Project Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleProject Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training Example
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure Cycle
 
Building risk tolerance
Building risk toleranceBuilding risk tolerance
Building risk tolerance
 
Project Management @ Ektoo
Project Management @ EktooProject Management @ Ektoo
Project Management @ Ektoo
 
Estimation & project planning
Estimation & project planningEstimation & project planning
Estimation & project planning
 
Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12
 
Setting up a project framework phase 1 june 20162
Setting up a project framework phase 1 june 20162Setting up a project framework phase 1 june 20162
Setting up a project framework phase 1 june 20162
 
Tavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-FinalTavant Whitepaper-MeasuringProjectSuccess-Final
Tavant Whitepaper-MeasuringProjectSuccess-Final
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdf
 
Presentation by beebejan valiyakath
Presentation by beebejan valiyakathPresentation by beebejan valiyakath
Presentation by beebejan valiyakath
 

Mehr von Acumen

Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskAcumen
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyAcumen
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Acumen
 
Meet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationMeet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationAcumen
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Acumen
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentAcumen
 
Smarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceSmarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceAcumen
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsAcumen
 
Acumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen
 
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit KeynoteAcumen
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessAcumen
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Acumen
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Acumen
 
Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute ResolutionAcumen
 
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAchieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAcumen
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Acumen
 
Fuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPCFuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPCAcumen
 
Fuse Customer Perspectives Webinar: Project Compliance
Fuse Customer Perspectives Webinar: Project ComplianceFuse Customer Perspectives Webinar: Project Compliance
Fuse Customer Perspectives Webinar: Project ComplianceAcumen
 

Mehr von Acumen (20)

Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen risk
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / Energy
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
Meet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationMeet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent Acceleration
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
 
Smarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceSmarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project Performance
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Acumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen Fuse & Customer Case Study
Acumen Fuse & Customer Case Study
 
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule Integration
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project Success
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0
 
Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute Resolution
 
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAchieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
 
Fuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPCFuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPC
 
Fuse Customer Perspectives Webinar: Project Compliance
Fuse Customer Perspectives Webinar: Project ComplianceFuse Customer Perspectives Webinar: Project Compliance
Fuse Customer Perspectives Webinar: Project Compliance
 

Developing Standards for Enterprise Schedule Quality

  • 1. // Developing Standards for Enterprise Schedule Quality Tom Polen Director Professional Services, Acumen November 2012 +1 512 291 6261 // info@projectacumen.com www.projectacumen.com
  • 2. Table of Contents Developing Standards for Enterprise Schedule Quality ................................................................3 A Framework for Schedule Quality ...............................................................................................3 Structuring Maturity Goals ..........................................................................................................4 Short-Term Maturity Goals .......................................................................................................4 Mid-Term goals ........................................................................................................................4 Long-Term Goals ......................................................................................................................5 Practical Implementation of Scheduling Quality at the Enterprise Level .....................................5 Testing and Benchmarking..........................................................................................................7 Post-Pilot Rollout.........................................................................................................................8 +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 2
  • 3. Developing Standards for Enterprise Schedule Quality Project-oriented organizations must approach quality from all angles—from the planning process to execution, and ultimately, through customer satisfaction. The need for quality is a constant, guiding force. However, as thousands, perhaps millions, of companies can attest, while quality is not necessarily expensive in the traditional sense, it can be difficult to obtain and an absence of quality can be costly and potentially fatal for a company. Enterprise schedule quality refers to the soundness and reliability of a project schedule and is essential to successful project execution. Schedule quality is a direct indicator of whether a plan is realistic and achievable. The Integrated Master Schedule (IMS) is the cornerstone of the planning and execution process, and is only as strong as its weakest link. There can be many contributors to the IMS— your own plans may involve a single company, hundreds of suppliers, or somewhere in between. Poor quality in any area of your plan can undermine successful execution by creating an unrealistic view. In fact, erroneous or low quality data, once present in the IMS can immediately begin a degradation process, which ultimately obscures the true execution- impacting events from plain sight. When truly critical activities are viewed as insignificant or time-insensitive, predicted execution can unravel. Ensuring quality in the IMS can be achieved through a three-step process 1. Define quality standards for the IMS. 2. Communicate the standards 3. Continually ‘raise the bar’ to bring higher overall maturity Quality in the details of project planning and execution drive the overall effectiveness of your organization. Your company is ultimately defined by the work that you perform. Work that is performed to high quality standards by a mature organization will be rewarded by customers in the form of loyalty and industry recognition. A Framework for Schedule Quality Through a five-stage, four step process you can improve the quality of your schedule. Each stage of this framework furthers a schedule’s maturity resulting in a schedule that is: 1. Structurally sound: well built using appropriate CPM scheduling techniques 2. Realistic: accounting for known scope as well as unknown potential risks and opportunities. 3. Optimized: thoroughly reviewed for potential cost/schedule acceleration candidates. 4. Validated: buy-in obtained from the project team, subject matter experts and the management team for the project. If all four of these objectives can be achieved, then project stakeholder expectations will be aligned, the true scope of execution understood, and an achievable target against which the project can be tracked will be attained. In short, a sound basis of schedule will be +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 3
  • 4. accomplished thus overcoming one of the biggest project management challenges today: poor and unrealistic planning. Acumen Method S1 // S2 // S3 // S4 // S5 // The Base Critiqued Risk Optimized Team Schedule Adjusted Aligned Figure 1 - Five Stages of Schedule Maturity Figure 1 shows the five stages of schedule maturity. The process begins with a non-validated schedule developed using a Critical Path Method (CPM) scheduling tool. A schedule at S1 has questionable realism and often a flawed framework. An S2 schedule has undergone a quality analysis process and improvement. At this stage, the project team has identified any troublesome areas of the schedule and made corrections. Stage 3 accounts for risk and uncertainty, weighing the impact of the ‘known unknowns’ that could arise during project execution. S4 and S5 involve optimizing the plan to help meet stakeholder objectives and goals and incorporating team input to ensure that they are ‘bought in’ to the new optimized schedule. Using metrics and agreed upon standards is helpful in assessing a project’s maturity at any stage of the framework. Structuring Maturity Goals Commitment to achieving higher levels of maturity must persist at all levels of the organization, from functional positions through to the CEO and board of directors. Maturity cannot be purchased or developed overnight. Achieving higher maturity is a long-term strategic process. However ultimately, it will be attained through a series of short, mid, and long-term activities. Here are examples of short, mid, and long-term goals you may wish to consider: Short-Term Maturity Goals -­‐ Start the maturity development process itself—a step toward higher maturity -­‐ Identify a project candidate for piloting the revised quality standards -­‐ Communicate the importance of higher maturity throughout the organization -­‐ Schedule frequent reviews to determine if the quality metrics and supporting analysis processes are helping to drive improved quality. Mid-Term Maturity Goals -­‐ Expand the pilot to include a variety of projects, small, medium and large -­‐ Weigh the quality criteria of larger programs versus those of smaller programs +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 4
  • 5. -­‐ Assure that a common quality language can be used across programs of all types and sizes -­‐ Keep senior management informed of successes, failures, and the evolution of the roadmap toward higher quality -­‐ Quantify the real financial cost of failures in quality; your real examples will become your own customized case study used to justify the return on the investment in quality Long-Term Maturity Goals -­‐ Review accomplishments which promote higher maturity annually -­‐ Assess ongoing resource requirements -­‐ Ask yourself – Is the maturity “buzz” still in the air? What activities can keep the organization focused on quality and maturity? Practical Implementation of Scheduling Quality at the Enterprise Level Every aspect of project execution can benefit from higher quality. For this reason, quality improvement is a multi-stakeholder exercise, requiring participation from all project stakeholders, including customers and suppliers. By using Acumen Fuse to create a metric template, discussions can begin as to which metrics should be used to measure schedule and project execution quality. Figure 2 - Using Metrics to Meet Goals +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 5
  • 6. The most critical elements for mapping metrics to enterprise quality goals are: -­‐ Determine quality attributes – e.g., schedule quality, logic quality, float, baseline compliance -­‐ Select metrics to support the quality attributes -­‐ Select thresholds and scoring method -­‐ Group metrics in context by associated quality attribute so that the aggregate scores are meaningful quality indicators Some of the most popular and prevalent quality checks are: Missing Logic: A core schedule quality check. In theory, all activities should have at least one predecessor and one successor associated with it. Failure to do so will impact the quality of results derived from a time analysis as well as a risk analysis. Negative Float: Negative float is a result of an artificially accelerated or constrained schedule. Negative float indicates that a schedule is not possible based on the current completion dates. Ideally, there should not be any negative float in the schedule. Logic Density™: In theory, this value should be at least two. An average of less than two indicates that the schedule should be reviewed and updated with additional logic links. An upper limit of four is also recommended – logic density above this threshold indicates overly complex logic within a schedule. Redundancy Index™: The Redundancy Index identifies overly complex logic caused by extraneous logic links. Insufficient Detail™: Activities with a high duration relative to the duration of the project are generally an indication that a plan is too high level for adequate planning and controls. Consider further developing the schedule by adding more detailed activities. SF Predecessors: Start-to-Finish (SF) links should be used very rarely. Having a successor activity happens before the predecessor activity is generally a poor practice when planning. Start Compliance: Start Compliance calculates the percentage of activities starting or that have started outside the expected baselined period relative to the baselined activities starting or that should have started within this period. Finish Compliance: Finish Compliance calculates the percentage of activities finishing or that have finished outside the expected baselined period relative to the baselined activities finishing or that should have finished within this period. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 6
  • 7. Risk Hot Spots: The combination of multiple successors and high criticality combined typically result in a highly complex and risk-prone hotspot within a schedule. Hidden Critical Paths: Hidden Paths is one of the most powerful risk exposure metrics. It shows those activities that have a high criticality (how often the task is critical) that in absence of risk do NOT fall on the critical path. If an activity has a high Hidden Path score, it should be considered as important as an activity that is critical. Testing and Benchmarking Prior to a pilot, scenario testing may be desired to benchmark the metrics themselves. Are certain metrics always failing the tests? Are the scores so high or low that they are not providing constructive information for quality improvements? Metrics should be calibrated according to both the quality result and the overall pursuit of maturity. For example, if a small company with relatively immature processes sets the quality standards too high, they may eventually feel that the standards are unachievable and abandon the pursuit of higher maturity. This is why goal setting for short, mid, and long-term is an essential part of the process. The definition of goals calibrated to each specific maturity level will help ensure that measurements will lead to near-term achievable improvements. As the team matures and becomes satisfied with results for their current level of maturity, the goal can be raised and the challenge increased. Typically, a mid-size or large program may the best candidate for a pilot. With sufficient resources, multiple concurrent pilots may be desired. Attributes of an ideal pilot program candidate include: -­‐ a highly visible program; -­‐ a progressive, advanced project team team; -­‐ external contributors to the schedule –i.e., subcontractors; and, -­‐ a program manager and customer that are focused on quality. A quality pilot program brings increased responsibility to the project team. If quality metrics are properly calibrated to drive higher maturity, not all areas of the schedule will pass the quality criteria each month. It is essential that quality breaches are treated as constructive opportunities rather than punitive events. Recognizing areas that proactively drive quality improvements is far more beneficial than emphasizing instances of failure. If improvement is not celebrated and failure is punished, the quality improvement efforts will become increasingly unpopular. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 7
  • 8. Figure 3 - The Fuse Ribbon Analyzer computes overall quality scores in any number of categories from a series of subcontractor schedules. The project team may decide that all schedules must score “Green” before they can be integrated into the IMS. Post-Pilot Rollout With a successful pilot, your organization may elect to roll out the quality standards gradually to additional projects, begin all new projects with the quality standards in place, or apply them to all active and new projects. The most effective suppliers can differentiate themselves by applying the quality standards across the enterprise portfolio. This assures customers that they will experience a consistently high standard of quality whenever they do business with these suppliers. The commitment to quality and higher maturity must be relentless. With ever-increasing competition, these are critical differentiators. Today’s metrics and quality standards may not meet tomorrow’s needs. Commitment, persistence, and frequent sharing of successes and failures will cultivate the quality-oriented culture that leads to higher levels of maturity and an improved competitive position. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 8