SlideShare ist ein Scribd-Unternehmen logo
1 von 39
Preparation of Application for 
Environmental Clearance of 
Construction Project 
Submitted By: Priyanka Singh 
M. Tech(EVS) 
Enrollment no.-A11227912005 
(AIES) 
Internal Guide- Dr. Ashotosh Tripathi 
External Guide- Neha Gupta
CONTENTS 
• Objective 
• Introduction 
• Methodology 
• Case study 
• Result 
• Present Status 
• Significance of the project
OBJECTIVE 
The main objective of this project is to prepare the proposal 
of construction project for Environmental Clearance .
INTRODUCTION 
Serial 
No. Sector 
Category 
Amendment 
in EIA 
notification 
Amendment 
in EIA 
notification 
Dated 
22/08/2013 
Amendment 
in EIA 
notification 
Dated 
Feb 2014 
A B 
8(a) 
Building and 
construction 
projects 
---- 
≥20,000 
sqm. to ≤ 
1,50,000 
sqm. of 
built-up area 
EIA Not 
Required 
EIA Not 
Required 
EIA Not 
Required 
8(b) 
Townships 
and area 
development 
projects 
---- 
≥ 1,50,000 
sqm. of 
built-up area 
EIA Required 
EIA Not 
Required EIA Required
Stages of EC process 
• Screening 
• Scoping 
• Appraisal
Methodology for Environmental Clearance
Provide the checklist of construction projects to the client 
Data will be provided by the client as per checklist 
Drawing will be provided by the project Architect 
Calculate all the required data 
Total Population 
Daily Water Requirement (Domestic + Flushing) 
Capacity of STP 
Rainwater Harvesting 
Vehicle parking 
Total solid waste 
Green area 
Fill details in FORM 1 and FORM IA and then prepare conceptual plan 
Presentation before SEAC 
Recommended Not Recommended 
SEIAA 
EC Granted EC Not Granted
Case Study
PROJECT DETAIL 
S. No. Particulars Details 
1. Name of the Project 
Vatika Urban Expression 
M/s Vatika Ltd. 
2. Activities in the Complex 
Residential Apartments, EWS Apartments, Servant 
Units, Community Building, Convenient Shopping 
and Nursery Schools 
3. Cost of Project Rs . 670 Crores approx. 
4. Total Plot Area 76,080 m2/18.80 Acres 
5. 
Permissible FAR @ 175% 1,22,394.449 m2 
Proposed FAR @ 174.898% 1,22,323.503 m2 
6. Non-FAR Area (Basement + Stilt Area) 73,896.23 + 31,409.95 = 1,05,306.18 m2 
7. Built up Area ( FAR + Non-FAR) 2,27,629.683 m2 
8. 
Permissible Ground Coverage @ 35% 24,478.890 m2 
Proposed Ground Coverage @ 17.52% 12,255.97 m2 
9. Green Area @ 32.62% 22,814.33 m2 
10. Maximum Number of Floors G + 29 (Tower detail is given at slide no. 15) 
11. Total No. of Towers 15 
12. Number of Nursery Schools 2
13. Maximum Height 97.78 meters 
14. Estimated Population 6329 persons 
15. Total Water Requirement 
Total Water Requirement: 719 KLD 
Fresh Water Requirement: 425 KLD 
Recycled Water Requirement: 294 KLD 
16. Waste Water Generation 580 KLD 
17. Capacity of STP 700 KLD 
18. Total Power Demand 
5380 KW (6725 KVA) , Source: Dakshin Haryana Bijli 
Vitaran Nigam (DHBVN). 
19. Power Back Up 
42 DG Sets of total capacity 10820 KVA (41 × 260 + 1 × 
160 KVA) 
20. Required Parking 1369 ECS 
21. Proposed Parking 1434 ECS 
22. No. of Dwelling Units 724 
23. No. of EWS Units 128 
24. No. of Servant Units 73
TOPOMAP SHOWING 500 M RADIUS OF THE AREA 
11 
S. No. Particulars Distance Direction 
Hospitals 
1. Shri Balaji Hospital & Trauma 
Center 
2.0 km SE 
2. Yash Nursing Home 2.0 km West 
Schools 
1. Government Senior Secondary 
School 
2 km West 
PROJECT 
SITE 
S. No. Particulars Distance Direction 
2. MDS Public School 2 km East 
Banks 
1. Yes Bank 2.2 km West 
2. Allahabad Bank` 3.5 km NE 
Eco-Sensitive Area 
Sultanpur Bird Sanctuary 6.4 km NW
PROJECT SITE ON MASTER PLAN 
12 
PROJECT SITE 
Nearest Highway NH-8 5 Km, South-East 
Nearest Airport IGI Airport 16 Km, North-East 
Nearest Railway Station Garhi Harsaru Railway Station 3 Km, South-West
Prospective View
DOCUMENTS REQUIRED FOR SUBMISSION 
OF ENVIRONMENT CLEARANCE 
S.No 
. Documents 
1. Form I 
2. Form I A Under the scope of Environment Consultant 
3. Conceptual Plan 
4. Annexure Under the scope of project proponent and 
project Architect
APPROVAL STATUS 
License from DTCP Granted on 26/10/2013 valid up to 25/10/2017 
Zoning Plan Approved on 28/10/2013 
NOC from AAI regarding Height Clearance Granted on 03/02/2014 valid up to 02/02/2019 
Clearance under Aravali Notification from DC Granted on 29/04/2013 
Water Assurance from HUDA Granted on 07/11/2013 
Affidavit for Non-Construction 03/10/2013
APPROVED ZONING PLAN
SITE PHOTOGRAPHS SHOWING THAT NO 
CONSTRUCTION ACTIVITY IS TAKEN IN THE PROJECT 
SITE
POPULATION CALCULATION 
S. No. Unit Type 
Dwelling 
Unit/Area 
Total Population 
1. Residential Apartment @ 5 724 3620 
2. EWS Apartment @ 5 128 640 
3. Servant Units @ 2 73 146 
4. Community Building @ 3 sqm/person 534.563 178 
5. Convenient Shopping @ 3 sqm/person 334.731 112 
6. 
Nursery School-1 @ 4 sqm/person 
Ground Floor 818.708 205 
First Floor 818.708 205 
7. 
Nursery School-2 @ 4 sqm/person 
Ground Floor 863.295 216 
First Floor 863.295 216 
Second Floor 863.295 216 
8. Visitors @ 10% of total population -- 575 
Total Population 6329 persons
CALCULATION OF DAILY WATER DEMAND 
S. 
No. 
Particulars Occupancy 
Rate of 
water 
demand 
Water Requirement (KLD) 
Domestic 
(Fresh Water) 
Flushing 
(Recycled Water) 
Total 
1. Residential Apartment 3620 135 325.80 162.90 488.70 
2. EWS Apartment 640 135 57.60 28.80 86.40 
3. Servant Units 146 135 13.14 6.57 19.71 
4. Community Building 178 45 2.67 5.34 8.01 
5. Convenient Shopping 112 45 1.68 3.36 5.04 
6. Nursery School-1 410 45 6.15 12.30 18.45 
7. Nursery School-2 648 45 9.72 19.44 29.16 
8. Visitors 575 15 3.45 5.17 8.62 
9. Horticulture 22814.33 m2 1 lit/sqm NIL NIL 23.00 (R) 
10. DG Cooling -- -- NIL NIL 27.10 (R) 
11. 
Make-up water 
requirement 
(Swimming Pool & 
Sunken Court) 
-- -- NIL NIL 5.00 (F) 
Total 
420.21 
243.88 
719.19
WATER BALANCE DIAGRAM 
Total Water Requirement 
(719 KLD) 
Fresh Water Requirement 
(425 KLD) 
Recycled/Treated Water 
(294 KLD) 
@ 80% @ 100% 
Wastewater generated 
(336 KLD) 
Wastewater 
generated 
(244 KLD) 
Wastewater 
generated 
(NIL) 
Wastewater 
generated 
(NIL) 
Domestic Water 
(420 KLD) 
Flushing 
(244 KLD) 
Horticulture 
(23 KLD) 
DG Cooling 
(27 KLD) 
Total wastewater 
generated 
(580 KLD) 
STP 
(700 KLD) 
@ 90% 
Recycled/Treated water 
(522 KLD) 
Water Tanker 
(228 KLD) 
More than 20% of wastewater 
generated 
Swimming Pool 
(5 KLD)
DUAL PLUMBING PLAN 
Treated 
water Line 
Wastewater 
Line 
Fresh 
Water Line 
STP
RAIN WATER HARVESTING CALCULATION 
22 
The Design calculations for storm water drainage and rain water harvesting pit are as follows: 
DESIGN BASIS FOR STORM WATER DRAINAGE SYSTEM: 
RUN OFF DISCHARGE 
Q = ( CIA)10-3 
S. No. Particulars Catchment Area in m2 
(A) 
Runoff Coefficient 
(C) 
Rainfall Intensity in mm 
(I) 
Discharge 
(m3/hr) 
1. Rooftop area 12255.97 0.85 45 468.79 
2. Green area 22814.33 0.20 45 205.33 
3. Paved area 34869.39 0.65 45 1019.93 
Total Runoff 69939.69 1694.05
23 
Taking 15 minutes retention time, total volume of storm water = 1370.13 × 0.25 = 423.51 m3 
Taking the effective diameter and depth of a Recharge pit 3.0 m and 3.4 m respectively, 
Volume of a single Recharge pit (πr2h) = 3.14 × 1.5 × 1.5 × 3.4 = 24.02 m3 
Hence No. of pits required = 423.51/24.02= 17.6 Say 18 Pits 
Total 18 no. of Rain Water Harvesting pits are being proposed for artificial rain water recharge within the project 
premises. 
NO. OF PITS: 18
24 
RAIN WATER HARVESTING PLAN 
RWH-6 RWH-4 RWH-3 
RWH-14 RWH-15 RWH-16 RWH-17 
RWH-5 RWH-2 RWH-1 
RWH-18
PARKING CALCULATION 
25 
VEHICLE PARKING FACILITIES 
Required Parking: 
Required parking for main unit @ 1.5 ECS/DU = 724 × 1.5 =1086 ECS 
Required parking for EWS @ 5% of total required parking = 1086 × 5 % = 54.3 say 55 ECS 
Required parking for Visitors @ 20% of total required parking = 1141 × 20 % = 228.2 say 228 ECS 
Total required parking = 1086 + 55 + 228 = 1369 ECS 
Proposed Parking: 
Area proposed for parking on surface = 1933.642 m2 
Area required for parking per ECS = 25 m2 
Proposed surface parking = 1933.642/25 = 77.3 ECS Say 77 ECS 
Area of Basement-1 = 37374.81 m2 
Area proposed for parking in Basement-1 = 29172.429 m2 
Parking Capacity of Basement-1 = 29172.429/35 m2 = 833 ECS 
Proposed parking in basement-1 = 683 ECS 
Area of Basement-2 = 36521.42 m2 
Area proposed for parking in Basement-2 = 28559.737 m2 
Parking Capacity of Basement-2 = 28559.737/35 m2 = 816 ECS 
Proposed parking in basement-2 = 674 ECS 
Total Proposed Parking =77 + 683 + 674 = 1434 ECS 
Hence, adequate space for 1434 ECS will be provided within the project premises.
26 
OPEN PARKING AND TRAFFIC CIRCULATION PLAN 
PARKING-3 
(27-50) 
PARKING-4 
(51-77) (1-PARKING-7) 
1 
PARKING-2 
(8-26) 
BUS PARKING 
(1-15) 
Required Parking: 
Required parking for main unit @ 1.5 ECS/DU = 724 × 1.5 =1086 ECS 
Required parking for EWS @ 5% of total required parking = 1086 × 5 % = 54.3 say 55 ECS 
Required parking for Visitors @ 20% of total required parking = 1141 × 20 % = 228.2 say 228 ECS 
Total required parking = 1086 + 55 + 228 = 1369 ECS 
Proposed Parking: 
Area proposed for parking on surface = 1933.642 m2 
Area required for parking per ECS = 25 m2 
Proposed surface parking = 1933.642/25 = 77.3 ECS Say 77 ECS 
Area of Basement- 1 = 37374.81 m2 
Area proposed for parking in Basement-1 = 29172.429 m2 
Parking Capacity of Basement- 1 = 29172.429/35 m2 = 833 ECS 
Proposed parking in basement- 1 = 683 ECS 
Area of Basement- 2 = 36521.42 m2 
Area proposed for parking in Basement-2 = 28559.737 m2 
Parking Capacity of Basement- 2 = 28559.737/35 m2 = 816 ECS 
Proposed parking in basement- 2 = 674 ECS 
Total Proposed Parking =77 + 683 + 674 = 1434 ECS
POWER REQUIREMENT 
Total Power Requirement : 5380 KW (6725 KVA) 
Source of Power : Dakshin Haryana Bijli Vitran Nigam 
Power back up : 42 DG sets of 10820 KVA (41×260 + 1×160 KVA) 
Fuel used in DG sets : Ultra Low Sulphur Diesel 
27 
DG set Capacity for Power Backup During Power Failure 
(KVA) 
Stack Height from Roof 
Level(m) 
260 3.2 m 
160 2.5 m
28 
SOLID WASTE MANAGEMENT
Result
LAB REPORT- WATER QUALITY 
• pH : 7.56 
• Total Hardness : 320.50mg/l 
• Iron : 0.25 mg/l 
• Chloride : 68.50 mg/l 
• TDS : 415.36 mg/l 
• Calcium : 90.50 mg/l 
• Magnesium : 23.01 mg/l 
• Alkalinity : 232.42 mg/l 
30 
Parameters of Water
31 
LAB REPORTS- AMBIENT AIR QUALITY
Results of PM2.5 adjacent to D Tower of the project site 
Sampling Location 
Concentration of PM2.5 
(μg/m3) 
Result Result Limit 
Adjacent to D Tower 33.54 34.71 60 
Sampling Location 
Results of PM10 adjacent to D Tower of the project site 
Concentration of PM 10 
(μg/m3) 
Result Result Limit 
Adjacent to D Tower 80.46 82.35 100
Results of SO2 adjacent to D Tower of the project site 
Sampling Location 
Concentration of SO2 
(μg/m3) 
Result Result Limit 
Adjacent to D Tower 12.41 13.25 80 
Sampling Location 
Results of NO2 adjacent to D Tower of the project site 
Concentration of NO2 
(μg/m3) 
Result 
(05.06.2012 to 
06.06.2012) 
Result 
(06.06.2012 to 
07.06.2012) 
Limit 
Adjacent to D Tower 25.62 26.83 80
LAB REPORT- AMBIENT NOISE 
34 
Noise Level Monitoring 
S. No. Parameters 
Test Result dB (A) 
Day Time 
(6:00 am to 
10:00 pm) 
Night Time 
(10:00 pm to 
06:00 am) 
1. Leq 51.60 44.75 
2. Lmin 46.70 41.50 
3. Lmax 57.50 50.40
LAB REPORT- SOIL QUALITY 
• Organic matter: 0.75 % 
• Density :1.32 gm/cc 
• pH : 8.4 
• Electrical Conductivity : 275 
μs/cm 
• Calcium : 1.45 mg/kg.
Present status of the Project 
• The case was done with SEAC and ToR is 
granted. 
• EIA will be submitted on 1 July in SEAC.
Significance of the project
Environmental Impact Assessment( EIA)
Environmental Impact Assessment( EIA)

Weitere ähnliche Inhalte

Was ist angesagt?

Construction and Demolition Waste Management.pptx
Construction and Demolition Waste Management.pptxConstruction and Demolition Waste Management.pptx
Construction and Demolition Waste Management.pptxSoubhagya Tripathy
 
Jaipur master plan review
Jaipur master plan reviewJaipur master plan review
Jaipur master plan reviewvikashsaini78
 
Land Use And Regulation
Land Use And RegulationLand Use And Regulation
Land Use And RegulationKetan Wadodkar
 
Eia act 2006
Eia act 2006Eia act 2006
Eia act 2006Tej Kiran
 
Le corbusiers planning concepts
Le corbusiers planning conceptsLe corbusiers planning concepts
Le corbusiers planning conceptsctlachu
 
Environmental impact assessment in nepal
Environmental impact assessment in nepalEnvironmental impact assessment in nepal
Environmental impact assessment in nepalBhim Upadhyaya
 
Environmental assessment methods
Environmental assessment methodsEnvironmental assessment methods
Environmental assessment methodsemmak781
 
Biomining of old waste dumps 2016
Biomining of old waste dumps 2016Biomining of old waste dumps 2016
Biomining of old waste dumps 2016Almitra Patel
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessmentJini Rajendran
 
Solid waste.pdf
Solid waste.pdfSolid waste.pdf
Solid waste.pdfSHBOnline
 
Site selection and justification
Site selection and justificationSite selection and justification
Site selection and justificationAnupama Krishnan
 
Part 3 - Urban planning history, theories, and concepts
Part 3 - Urban planning history, theories, and conceptsPart 3 - Urban planning history, theories, and concepts
Part 3 - Urban planning history, theories, and conceptsEnP Ragene Andrea Palma
 
Green buildings matter
Green buildings matterGreen buildings matter
Green buildings matterGRIHA India
 
3.1 development control rules
3.1 development control rules3.1 development control rules
3.1 development control rulesSachin PatiL
 
EIA for development projects
EIA for development projectsEIA for development projects
EIA for development projectsAnchal Garg
 

Was ist angesagt? (20)

Construction and Demolition Waste Management.pptx
Construction and Demolition Waste Management.pptxConstruction and Demolition Waste Management.pptx
Construction and Demolition Waste Management.pptx
 
Coastal regulation zone
Coastal regulation   zoneCoastal regulation   zone
Coastal regulation zone
 
Jaipur master plan review
Jaipur master plan reviewJaipur master plan review
Jaipur master plan review
 
Ekistics
EkisticsEkistics
Ekistics
 
Geddes theory
Geddes theoryGeddes theory
Geddes theory
 
Land Use And Regulation
Land Use And RegulationLand Use And Regulation
Land Use And Regulation
 
Eia act 2006
Eia act 2006Eia act 2006
Eia act 2006
 
Le corbusiers planning concepts
Le corbusiers planning conceptsLe corbusiers planning concepts
Le corbusiers planning concepts
 
Environmental impact assessment in nepal
Environmental impact assessment in nepalEnvironmental impact assessment in nepal
Environmental impact assessment in nepal
 
Sewage treatment plant
Sewage treatment plantSewage treatment plant
Sewage treatment plant
 
Environmental assessment methods
Environmental assessment methodsEnvironmental assessment methods
Environmental assessment methods
 
Biomining of old waste dumps 2016
Biomining of old waste dumps 2016Biomining of old waste dumps 2016
Biomining of old waste dumps 2016
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
Solid waste.pdf
Solid waste.pdfSolid waste.pdf
Solid waste.pdf
 
Site selection and justification
Site selection and justificationSite selection and justification
Site selection and justification
 
Part 3 - Urban planning history, theories, and concepts
Part 3 - Urban planning history, theories, and conceptsPart 3 - Urban planning history, theories, and concepts
Part 3 - Urban planning history, theories, and concepts
 
Green buildings matter
Green buildings matterGreen buildings matter
Green buildings matter
 
EIA
EIAEIA
EIA
 
3.1 development control rules
3.1 development control rules3.1 development control rules
3.1 development control rules
 
EIA for development projects
EIA for development projectsEIA for development projects
EIA for development projects
 

Andere mochten auch

Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...Probir Bidhan
 
Rain Water Harvesting - Indian Railways Institute of Civil Engineering
Rain Water Harvesting - Indian Railways Institute of Civil Engineering  Rain Water Harvesting - Indian Railways Institute of Civil Engineering
Rain Water Harvesting - Indian Railways Institute of Civil Engineering D6Z
 
Water balance
Water balanceWater balance
Water balancepeah13
 
Socio economic study in eia
Socio economic study in eiaSocio economic study in eia
Socio economic study in eiaArif Shaikh
 
Spa t02 solid_wastes_mgt_team_a
Spa t02 solid_wastes_mgt_team_aSpa t02 solid_wastes_mgt_team_a
Spa t02 solid_wastes_mgt_team_aAvery Cheung
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessmentIntan Ayuna
 
FinalThesis_WithTurnitin_x2
FinalThesis_WithTurnitin_x2FinalThesis_WithTurnitin_x2
FinalThesis_WithTurnitin_x2Amy Crum
 
child labor in Tamil Nadu
child labor in Tamil Naduchild labor in Tamil Nadu
child labor in Tamil Nadusujima
 
Public policy analysis on waste management
Public policy analysis on waste managementPublic policy analysis on waste management
Public policy analysis on waste managementPhIee PoeRba
 
A Study of Tamilnadu's Economy and its contribution to India's GDP
A Study of Tamilnadu's Economy and its contribution to India's GDPA Study of Tamilnadu's Economy and its contribution to India's GDP
A Study of Tamilnadu's Economy and its contribution to India's GDPUttam Satapathy
 
Jamuna Bridge & A Successful EIA-Malthus.pptx
Jamuna Bridge & A Successful EIA-Malthus.pptxJamuna Bridge & A Successful EIA-Malthus.pptx
Jamuna Bridge & A Successful EIA-Malthus.pptxMd. Mahmudor Rahman
 
Allegation-on-Padma-Bridge_Kamalendu-Das
Allegation-on-Padma-Bridge_Kamalendu-DasAllegation-on-Padma-Bridge_Kamalendu-Das
Allegation-on-Padma-Bridge_Kamalendu-DasKamalendu Das
 

Andere mochten auch (20)

EIA Methods
EIA MethodsEIA Methods
EIA Methods
 
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
 
Rain Water Harvesting - Indian Railways Institute of Civil Engineering
Rain Water Harvesting - Indian Railways Institute of Civil Engineering  Rain Water Harvesting - Indian Railways Institute of Civil Engineering
Rain Water Harvesting - Indian Railways Institute of Civil Engineering
 
EIA Report
EIA ReportEIA Report
EIA Report
 
Water balance
Water balanceWater balance
Water balance
 
Water balance diagram
Water balance diagramWater balance diagram
Water balance diagram
 
Socio economic study in eia
Socio economic study in eiaSocio economic study in eia
Socio economic study in eia
 
Eia stages
Eia stagesEia stages
Eia stages
 
The Basics of Economic Impact Analysis
The Basics of Economic Impact AnalysisThe Basics of Economic Impact Analysis
The Basics of Economic Impact Analysis
 
Socio economic impact analysis
Socio economic impact analysisSocio economic impact analysis
Socio economic impact analysis
 
Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
 
Spa t02 solid_wastes_mgt_team_a
Spa t02 solid_wastes_mgt_team_aSpa t02 solid_wastes_mgt_team_a
Spa t02 solid_wastes_mgt_team_a
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
FinalThesis_WithTurnitin_x2
FinalThesis_WithTurnitin_x2FinalThesis_WithTurnitin_x2
FinalThesis_WithTurnitin_x2
 
Location of Industries
Location of IndustriesLocation of Industries
Location of Industries
 
child labor in Tamil Nadu
child labor in Tamil Naduchild labor in Tamil Nadu
child labor in Tamil Nadu
 
Public policy analysis on waste management
Public policy analysis on waste managementPublic policy analysis on waste management
Public policy analysis on waste management
 
A Study of Tamilnadu's Economy and its contribution to India's GDP
A Study of Tamilnadu's Economy and its contribution to India's GDPA Study of Tamilnadu's Economy and its contribution to India's GDP
A Study of Tamilnadu's Economy and its contribution to India's GDP
 
Jamuna Bridge & A Successful EIA-Malthus.pptx
Jamuna Bridge & A Successful EIA-Malthus.pptxJamuna Bridge & A Successful EIA-Malthus.pptx
Jamuna Bridge & A Successful EIA-Malthus.pptx
 
Allegation-on-Padma-Bridge_Kamalendu-Das
Allegation-on-Padma-Bridge_Kamalendu-DasAllegation-on-Padma-Bridge_Kamalendu-Das
Allegation-on-Padma-Bridge_Kamalendu-Das
 

Ähnlich wie Environmental Impact Assessment( EIA)

3 BHK & 4 BHK Flats in Bandra | Flats in Bandra
 3 BHK & 4 BHK Flats in Bandra | Flats in Bandra 3 BHK & 4 BHK Flats in Bandra | Flats in Bandra
3 BHK & 4 BHK Flats in Bandra | Flats in Bandrashikhadesai1990
 
334529321 production-of-acetic-acid-pptx
334529321 production-of-acetic-acid-pptx334529321 production-of-acetic-acid-pptx
334529321 production-of-acetic-acid-pptxBatuhanKse1
 
CICC Accounting by Cebu Gov. Gwen Garcia on Feb. 26, 2009
CICC Accounting by Cebu Gov. Gwen Garcia on Feb. 26, 2009CICC Accounting by Cebu Gov. Gwen Garcia on Feb. 26, 2009
CICC Accounting by Cebu Gov. Gwen Garcia on Feb. 26, 2009Leo Lastimosa
 
Presentation Report of DC-ASR
Presentation Report of DC-ASRPresentation Report of DC-ASR
Presentation Report of DC-ASRInderjit Singh
 
Low cost solar steam generation
Low cost solar  steam generationLow cost solar  steam generation
Low cost solar steam generationSyril Thomas
 
Internship report 2015 (1)
Internship report 2015 (1)Internship report 2015 (1)
Internship report 2015 (1)Navneet Kumar
 
The watergate confidential
The watergate confidentialThe watergate confidential
The watergate confidentialHaris Memon
 
IRJET- Design and Analysis of Overhead Water Tank at Phule Nagar, Ambernath
IRJET-  	  Design and Analysis of Overhead Water Tank at Phule Nagar, AmbernathIRJET-  	  Design and Analysis of Overhead Water Tank at Phule Nagar, Ambernath
IRJET- Design and Analysis of Overhead Water Tank at Phule Nagar, AmbernathIRJET Journal
 
Farm pond anadhowapara
Farm pond anadhowaparaFarm pond anadhowapara
Farm pond anadhowaparaManashBaruah15
 
Be assignment-presentation 0
Be assignment-presentation 0Be assignment-presentation 0
Be assignment-presentation 0Jessyca Than
 

Ähnlich wie Environmental Impact Assessment( EIA) (20)

3 BHK & 4 BHK Flats in Bandra | Flats in Bandra
 3 BHK & 4 BHK Flats in Bandra | Flats in Bandra 3 BHK & 4 BHK Flats in Bandra | Flats in Bandra
3 BHK & 4 BHK Flats in Bandra | Flats in Bandra
 
SELENDRA CONDOMINIUM CONSTRUCTION ORIENTATION
SELENDRA CONDOMINIUM CONSTRUCTION ORIENTATIONSELENDRA CONDOMINIUM CONSTRUCTION ORIENTATION
SELENDRA CONDOMINIUM CONSTRUCTION ORIENTATION
 
BEST REAL ESTATE COMPANY IN PATNA
BEST REAL ESTATE COMPANY IN PATNABEST REAL ESTATE COMPANY IN PATNA
BEST REAL ESTATE COMPANY IN PATNA
 
ECA form
ECA formECA form
ECA form
 
334529321 production-of-acetic-acid-pptx
334529321 production-of-acetic-acid-pptx334529321 production-of-acetic-acid-pptx
334529321 production-of-acetic-acid-pptx
 
Final presentation
Final presentationFinal presentation
Final presentation
 
perfect project report (1)
perfect project report (1)perfect project report (1)
perfect project report (1)
 
CICC Accounting by Cebu Gov. Gwen Garcia on Feb. 26, 2009
CICC Accounting by Cebu Gov. Gwen Garcia on Feb. 26, 2009CICC Accounting by Cebu Gov. Gwen Garcia on Feb. 26, 2009
CICC Accounting by Cebu Gov. Gwen Garcia on Feb. 26, 2009
 
LGC PP-ABC Int
LGC PP-ABC IntLGC PP-ABC Int
LGC PP-ABC Int
 
Project Brief
Project BriefProject Brief
Project Brief
 
Presentation Report of DC-ASR
Presentation Report of DC-ASRPresentation Report of DC-ASR
Presentation Report of DC-ASR
 
Low cost solar steam generation
Low cost solar  steam generationLow cost solar  steam generation
Low cost solar steam generation
 
Internship report 2015 (1)
Internship report 2015 (1)Internship report 2015 (1)
Internship report 2015 (1)
 
F inal ici super project
F inal ici super projectF inal ici super project
F inal ici super project
 
Case study
Case studyCase study
Case study
 
The watergate confidential
The watergate confidentialThe watergate confidential
The watergate confidential
 
IRJET- Design and Analysis of Overhead Water Tank at Phule Nagar, Ambernath
IRJET-  	  Design and Analysis of Overhead Water Tank at Phule Nagar, AmbernathIRJET-  	  Design and Analysis of Overhead Water Tank at Phule Nagar, Ambernath
IRJET- Design and Analysis of Overhead Water Tank at Phule Nagar, Ambernath
 
Fianl Year Project.pptx
Fianl Year Project.pptxFianl Year Project.pptx
Fianl Year Project.pptx
 
Farm pond anadhowapara
Farm pond anadhowaparaFarm pond anadhowapara
Farm pond anadhowapara
 
Be assignment-presentation 0
Be assignment-presentation 0Be assignment-presentation 0
Be assignment-presentation 0
 

Kürzlich hochgeladen

Horizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben AbrahamHorizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben Abrahamssuserbb03ff
 
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...tanu pandey
 
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...ranjana rawat
 
CSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting DayCSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting DayGeorgeDiamandis11
 
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Standkumarajju5765
 
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...Cluster TWEED
 
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...SUHANI PANDEY
 
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Verified Trusted Kalyani Nagar Call Girls 8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...
Verified Trusted Kalyani Nagar Call Girls  8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...Verified Trusted Kalyani Nagar Call Girls  8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...
Verified Trusted Kalyani Nagar Call Girls 8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...tanu pandey
 
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...SUHANI PANDEY
 
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...ranjana rawat
 
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...Suhani Kapoor
 
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(ZARA) Call Girls Talegaon Dabhade ( 7001035870 ) HI-Fi Pune Escorts Service
(ZARA) Call Girls Talegaon Dabhade ( 7001035870 ) HI-Fi Pune Escorts Service(ZARA) Call Girls Talegaon Dabhade ( 7001035870 ) HI-Fi Pune Escorts Service
(ZARA) Call Girls Talegaon Dabhade ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 

Kürzlich hochgeladen (20)

Horizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben AbrahamHorizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben Abraham
 
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
 
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
 
Sustainable Packaging
Sustainable PackagingSustainable Packaging
Sustainable Packaging
 
CSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting DayCSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting Day
 
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
 
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
 
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
webinaire-green-mirror-episode-2-Smart contracts and virtual purchase agreeme...
 
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
 
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Chakan ( Pune ) Call ON 8005736733 Starting From 5K to 2...
 
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Verified Trusted Kalyani Nagar Call Girls 8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...
Verified Trusted Kalyani Nagar Call Girls  8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...Verified Trusted Kalyani Nagar Call Girls  8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...
Verified Trusted Kalyani Nagar Call Girls 8005736733 𝐈𝐍𝐃𝐄𝐏𝐄𝐍𝐃𝐄𝐍𝐓 Call 𝐆𝐈𝐑𝐋 𝐕...
 
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
 
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
 
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
 
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Budhwar Peth Call Me 7737669865 Budget Friendly No Advance Booking
 
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
 
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
 
(ZARA) Call Girls Talegaon Dabhade ( 7001035870 ) HI-Fi Pune Escorts Service
(ZARA) Call Girls Talegaon Dabhade ( 7001035870 ) HI-Fi Pune Escorts Service(ZARA) Call Girls Talegaon Dabhade ( 7001035870 ) HI-Fi Pune Escorts Service
(ZARA) Call Girls Talegaon Dabhade ( 7001035870 ) HI-Fi Pune Escorts Service
 

Environmental Impact Assessment( EIA)

  • 1. Preparation of Application for Environmental Clearance of Construction Project Submitted By: Priyanka Singh M. Tech(EVS) Enrollment no.-A11227912005 (AIES) Internal Guide- Dr. Ashotosh Tripathi External Guide- Neha Gupta
  • 2. CONTENTS • Objective • Introduction • Methodology • Case study • Result • Present Status • Significance of the project
  • 3. OBJECTIVE The main objective of this project is to prepare the proposal of construction project for Environmental Clearance .
  • 4. INTRODUCTION Serial No. Sector Category Amendment in EIA notification Amendment in EIA notification Dated 22/08/2013 Amendment in EIA notification Dated Feb 2014 A B 8(a) Building and construction projects ---- ≥20,000 sqm. to ≤ 1,50,000 sqm. of built-up area EIA Not Required EIA Not Required EIA Not Required 8(b) Townships and area development projects ---- ≥ 1,50,000 sqm. of built-up area EIA Required EIA Not Required EIA Required
  • 5. Stages of EC process • Screening • Scoping • Appraisal
  • 7. Provide the checklist of construction projects to the client Data will be provided by the client as per checklist Drawing will be provided by the project Architect Calculate all the required data Total Population Daily Water Requirement (Domestic + Flushing) Capacity of STP Rainwater Harvesting Vehicle parking Total solid waste Green area Fill details in FORM 1 and FORM IA and then prepare conceptual plan Presentation before SEAC Recommended Not Recommended SEIAA EC Granted EC Not Granted
  • 9. PROJECT DETAIL S. No. Particulars Details 1. Name of the Project Vatika Urban Expression M/s Vatika Ltd. 2. Activities in the Complex Residential Apartments, EWS Apartments, Servant Units, Community Building, Convenient Shopping and Nursery Schools 3. Cost of Project Rs . 670 Crores approx. 4. Total Plot Area 76,080 m2/18.80 Acres 5. Permissible FAR @ 175% 1,22,394.449 m2 Proposed FAR @ 174.898% 1,22,323.503 m2 6. Non-FAR Area (Basement + Stilt Area) 73,896.23 + 31,409.95 = 1,05,306.18 m2 7. Built up Area ( FAR + Non-FAR) 2,27,629.683 m2 8. Permissible Ground Coverage @ 35% 24,478.890 m2 Proposed Ground Coverage @ 17.52% 12,255.97 m2 9. Green Area @ 32.62% 22,814.33 m2 10. Maximum Number of Floors G + 29 (Tower detail is given at slide no. 15) 11. Total No. of Towers 15 12. Number of Nursery Schools 2
  • 10. 13. Maximum Height 97.78 meters 14. Estimated Population 6329 persons 15. Total Water Requirement Total Water Requirement: 719 KLD Fresh Water Requirement: 425 KLD Recycled Water Requirement: 294 KLD 16. Waste Water Generation 580 KLD 17. Capacity of STP 700 KLD 18. Total Power Demand 5380 KW (6725 KVA) , Source: Dakshin Haryana Bijli Vitaran Nigam (DHBVN). 19. Power Back Up 42 DG Sets of total capacity 10820 KVA (41 × 260 + 1 × 160 KVA) 20. Required Parking 1369 ECS 21. Proposed Parking 1434 ECS 22. No. of Dwelling Units 724 23. No. of EWS Units 128 24. No. of Servant Units 73
  • 11. TOPOMAP SHOWING 500 M RADIUS OF THE AREA 11 S. No. Particulars Distance Direction Hospitals 1. Shri Balaji Hospital & Trauma Center 2.0 km SE 2. Yash Nursing Home 2.0 km West Schools 1. Government Senior Secondary School 2 km West PROJECT SITE S. No. Particulars Distance Direction 2. MDS Public School 2 km East Banks 1. Yes Bank 2.2 km West 2. Allahabad Bank` 3.5 km NE Eco-Sensitive Area Sultanpur Bird Sanctuary 6.4 km NW
  • 12. PROJECT SITE ON MASTER PLAN 12 PROJECT SITE Nearest Highway NH-8 5 Km, South-East Nearest Airport IGI Airport 16 Km, North-East Nearest Railway Station Garhi Harsaru Railway Station 3 Km, South-West
  • 14. DOCUMENTS REQUIRED FOR SUBMISSION OF ENVIRONMENT CLEARANCE S.No . Documents 1. Form I 2. Form I A Under the scope of Environment Consultant 3. Conceptual Plan 4. Annexure Under the scope of project proponent and project Architect
  • 15. APPROVAL STATUS License from DTCP Granted on 26/10/2013 valid up to 25/10/2017 Zoning Plan Approved on 28/10/2013 NOC from AAI regarding Height Clearance Granted on 03/02/2014 valid up to 02/02/2019 Clearance under Aravali Notification from DC Granted on 29/04/2013 Water Assurance from HUDA Granted on 07/11/2013 Affidavit for Non-Construction 03/10/2013
  • 17. SITE PHOTOGRAPHS SHOWING THAT NO CONSTRUCTION ACTIVITY IS TAKEN IN THE PROJECT SITE
  • 18. POPULATION CALCULATION S. No. Unit Type Dwelling Unit/Area Total Population 1. Residential Apartment @ 5 724 3620 2. EWS Apartment @ 5 128 640 3. Servant Units @ 2 73 146 4. Community Building @ 3 sqm/person 534.563 178 5. Convenient Shopping @ 3 sqm/person 334.731 112 6. Nursery School-1 @ 4 sqm/person Ground Floor 818.708 205 First Floor 818.708 205 7. Nursery School-2 @ 4 sqm/person Ground Floor 863.295 216 First Floor 863.295 216 Second Floor 863.295 216 8. Visitors @ 10% of total population -- 575 Total Population 6329 persons
  • 19. CALCULATION OF DAILY WATER DEMAND S. No. Particulars Occupancy Rate of water demand Water Requirement (KLD) Domestic (Fresh Water) Flushing (Recycled Water) Total 1. Residential Apartment 3620 135 325.80 162.90 488.70 2. EWS Apartment 640 135 57.60 28.80 86.40 3. Servant Units 146 135 13.14 6.57 19.71 4. Community Building 178 45 2.67 5.34 8.01 5. Convenient Shopping 112 45 1.68 3.36 5.04 6. Nursery School-1 410 45 6.15 12.30 18.45 7. Nursery School-2 648 45 9.72 19.44 29.16 8. Visitors 575 15 3.45 5.17 8.62 9. Horticulture 22814.33 m2 1 lit/sqm NIL NIL 23.00 (R) 10. DG Cooling -- -- NIL NIL 27.10 (R) 11. Make-up water requirement (Swimming Pool & Sunken Court) -- -- NIL NIL 5.00 (F) Total 420.21 243.88 719.19
  • 20. WATER BALANCE DIAGRAM Total Water Requirement (719 KLD) Fresh Water Requirement (425 KLD) Recycled/Treated Water (294 KLD) @ 80% @ 100% Wastewater generated (336 KLD) Wastewater generated (244 KLD) Wastewater generated (NIL) Wastewater generated (NIL) Domestic Water (420 KLD) Flushing (244 KLD) Horticulture (23 KLD) DG Cooling (27 KLD) Total wastewater generated (580 KLD) STP (700 KLD) @ 90% Recycled/Treated water (522 KLD) Water Tanker (228 KLD) More than 20% of wastewater generated Swimming Pool (5 KLD)
  • 21. DUAL PLUMBING PLAN Treated water Line Wastewater Line Fresh Water Line STP
  • 22. RAIN WATER HARVESTING CALCULATION 22 The Design calculations for storm water drainage and rain water harvesting pit are as follows: DESIGN BASIS FOR STORM WATER DRAINAGE SYSTEM: RUN OFF DISCHARGE Q = ( CIA)10-3 S. No. Particulars Catchment Area in m2 (A) Runoff Coefficient (C) Rainfall Intensity in mm (I) Discharge (m3/hr) 1. Rooftop area 12255.97 0.85 45 468.79 2. Green area 22814.33 0.20 45 205.33 3. Paved area 34869.39 0.65 45 1019.93 Total Runoff 69939.69 1694.05
  • 23. 23 Taking 15 minutes retention time, total volume of storm water = 1370.13 × 0.25 = 423.51 m3 Taking the effective diameter and depth of a Recharge pit 3.0 m and 3.4 m respectively, Volume of a single Recharge pit (πr2h) = 3.14 × 1.5 × 1.5 × 3.4 = 24.02 m3 Hence No. of pits required = 423.51/24.02= 17.6 Say 18 Pits Total 18 no. of Rain Water Harvesting pits are being proposed for artificial rain water recharge within the project premises. NO. OF PITS: 18
  • 24. 24 RAIN WATER HARVESTING PLAN RWH-6 RWH-4 RWH-3 RWH-14 RWH-15 RWH-16 RWH-17 RWH-5 RWH-2 RWH-1 RWH-18
  • 25. PARKING CALCULATION 25 VEHICLE PARKING FACILITIES Required Parking: Required parking for main unit @ 1.5 ECS/DU = 724 × 1.5 =1086 ECS Required parking for EWS @ 5% of total required parking = 1086 × 5 % = 54.3 say 55 ECS Required parking for Visitors @ 20% of total required parking = 1141 × 20 % = 228.2 say 228 ECS Total required parking = 1086 + 55 + 228 = 1369 ECS Proposed Parking: Area proposed for parking on surface = 1933.642 m2 Area required for parking per ECS = 25 m2 Proposed surface parking = 1933.642/25 = 77.3 ECS Say 77 ECS Area of Basement-1 = 37374.81 m2 Area proposed for parking in Basement-1 = 29172.429 m2 Parking Capacity of Basement-1 = 29172.429/35 m2 = 833 ECS Proposed parking in basement-1 = 683 ECS Area of Basement-2 = 36521.42 m2 Area proposed for parking in Basement-2 = 28559.737 m2 Parking Capacity of Basement-2 = 28559.737/35 m2 = 816 ECS Proposed parking in basement-2 = 674 ECS Total Proposed Parking =77 + 683 + 674 = 1434 ECS Hence, adequate space for 1434 ECS will be provided within the project premises.
  • 26. 26 OPEN PARKING AND TRAFFIC CIRCULATION PLAN PARKING-3 (27-50) PARKING-4 (51-77) (1-PARKING-7) 1 PARKING-2 (8-26) BUS PARKING (1-15) Required Parking: Required parking for main unit @ 1.5 ECS/DU = 724 × 1.5 =1086 ECS Required parking for EWS @ 5% of total required parking = 1086 × 5 % = 54.3 say 55 ECS Required parking for Visitors @ 20% of total required parking = 1141 × 20 % = 228.2 say 228 ECS Total required parking = 1086 + 55 + 228 = 1369 ECS Proposed Parking: Area proposed for parking on surface = 1933.642 m2 Area required for parking per ECS = 25 m2 Proposed surface parking = 1933.642/25 = 77.3 ECS Say 77 ECS Area of Basement- 1 = 37374.81 m2 Area proposed for parking in Basement-1 = 29172.429 m2 Parking Capacity of Basement- 1 = 29172.429/35 m2 = 833 ECS Proposed parking in basement- 1 = 683 ECS Area of Basement- 2 = 36521.42 m2 Area proposed for parking in Basement-2 = 28559.737 m2 Parking Capacity of Basement- 2 = 28559.737/35 m2 = 816 ECS Proposed parking in basement- 2 = 674 ECS Total Proposed Parking =77 + 683 + 674 = 1434 ECS
  • 27. POWER REQUIREMENT Total Power Requirement : 5380 KW (6725 KVA) Source of Power : Dakshin Haryana Bijli Vitran Nigam Power back up : 42 DG sets of 10820 KVA (41×260 + 1×160 KVA) Fuel used in DG sets : Ultra Low Sulphur Diesel 27 DG set Capacity for Power Backup During Power Failure (KVA) Stack Height from Roof Level(m) 260 3.2 m 160 2.5 m
  • 28. 28 SOLID WASTE MANAGEMENT
  • 30. LAB REPORT- WATER QUALITY • pH : 7.56 • Total Hardness : 320.50mg/l • Iron : 0.25 mg/l • Chloride : 68.50 mg/l • TDS : 415.36 mg/l • Calcium : 90.50 mg/l • Magnesium : 23.01 mg/l • Alkalinity : 232.42 mg/l 30 Parameters of Water
  • 31. 31 LAB REPORTS- AMBIENT AIR QUALITY
  • 32. Results of PM2.5 adjacent to D Tower of the project site Sampling Location Concentration of PM2.5 (μg/m3) Result Result Limit Adjacent to D Tower 33.54 34.71 60 Sampling Location Results of PM10 adjacent to D Tower of the project site Concentration of PM 10 (μg/m3) Result Result Limit Adjacent to D Tower 80.46 82.35 100
  • 33. Results of SO2 adjacent to D Tower of the project site Sampling Location Concentration of SO2 (μg/m3) Result Result Limit Adjacent to D Tower 12.41 13.25 80 Sampling Location Results of NO2 adjacent to D Tower of the project site Concentration of NO2 (μg/m3) Result (05.06.2012 to 06.06.2012) Result (06.06.2012 to 07.06.2012) Limit Adjacent to D Tower 25.62 26.83 80
  • 34. LAB REPORT- AMBIENT NOISE 34 Noise Level Monitoring S. No. Parameters Test Result dB (A) Day Time (6:00 am to 10:00 pm) Night Time (10:00 pm to 06:00 am) 1. Leq 51.60 44.75 2. Lmin 46.70 41.50 3. Lmax 57.50 50.40
  • 35. LAB REPORT- SOIL QUALITY • Organic matter: 0.75 % • Density :1.32 gm/cc • pH : 8.4 • Electrical Conductivity : 275 μs/cm • Calcium : 1.45 mg/kg.
  • 36. Present status of the Project • The case was done with SEAC and ToR is granted. • EIA will be submitted on 1 July in SEAC.