Permission & Clearance for Real Estate Projects In Haryana
Presented by:-Pritam
Table Of Contents
► Introduction
► Approval Procedure For R.E Project In Haryana
► Approvals Required For R.E Project In Haryana
► Other Approvals required for R.E Project in Haryana
► Factor for Delay in Approval Procedure
► Comparison of Major Approvals & Time Taken
► Conclusion
► Reference
Introduction
► Haryana has seen development of real estate at scorching pace.
► Haryana has 6 administrative divisions, 22 districts, 72 sub-
divisions, 93 revenue tehsils, 50 sub-tehsils, 140 blocks.
► The Department of Town and Country Planning, Haryana is
responsible to regulate development.
 The Punjab Scheduled Roads and Controlled Areas Restriction of
Unregulated Development Act 1963
 The Haryana Development & Regulation of Urban Areas Act,1975
 The Punjab New (Capital) Periphery Control Act, 1952
► Developer have to obtain at least 35 major approvals.
► The time span for getting all relevant approvals is 4-5 years
Source:https://www.mapsofindia.com/delhi/districts/west-delhi.html
Approval Procedure For R.E Project In Haryana
Applicant submits the
CLU application online
Scrutiny of Documents
by Field Office
Report of DTP, Office
forward to Circle Office
Circle office forwards
the report with remarks
to HQ
Examination of the Field
reports at HQ
Application found in
order / Meets policy
parameters
DTCP issues LOI with
directions to applicant to
submit fees/agreement/
undertaking within 30
days
Applicant Submits LOI
compliance at HQ within
30 days
Scrutiny of Compliance
at HQ
Compliance found OK CLU Granted
1. Workflow for change of Land use (CLU) :
Land Conversion Details
Developing
Authority :
Department of
Town & Country
Planning (DTCP),
Haryana.
• Law / Regulation
under which the
approval is
sought:
• Section 8 of
Punjab Scheduled
Roads and
Controlled Areas
Restriction of
Unregulated
Development Act
1963.
• Time Limit
prescribed by the
Government:
• 3 Months.
• Time Taken for the
Clearance: At
least 6 months.
• Costs Involved: −
Scrutiny Fee @
Rs. 10/- per
Square Meter −
CLU charges vary
according to
Zone/ abutting
roads per Square
Meter which are
:Residential from
Rs. 15/- to Rs.
210/- &
Commercial from
Rs. 100/- to Rs.
1470/
• Documentations
Required:
• Revenue Map duly
signed by Patwari,
• Proof of Land
Ownership
• Proof of financial
capability like
Balance Sheet,
Income Tax
Clearance Certificate
• Survey Map, Site
Plan
• Difficulties
faced in the
documentation
:
• If the land is
jointly owned, it
gets difficult to
mutate the same
and get the
clearance from
Tehsildar
Approval Procedure For R.E Project In Haryana
2. Workflow for Building Plan & Inspection Procedure:
Applicant
submits the
application
along with
Scrutiny fee,
Labour Cess
fee, NOC of
AAI etc. &
drawing
Scrutiny of
document by
Head Office
Application
in Order
Examination
by
Concerned
Circle office,
SE HUDA,
Fire officer,
Urban Local
Bodies
Meeting of
BPAC fixed
to review the
comments
Plan review
by BPAC as
per Zoning
Plan, HBC
2017 and
NBC
Signed by
BPAC
Members
HQ verifies
validity
Licence /
CLU
permission /
pending
dues
Orders
issued for
release of
Building
Plan and
approval
conveyed
HQ - Head Quarter of Town & Country Planning
SE - Superintending Engineer
BPAC - Building Plan Approval Committee
HBC - Haryana Building Code
NBC - National Building Code
HUDA – Haryana Urban Development Authority
Approvals Required For R.E Project In Haryana
Land Purchase and Land
Papers Examination &
Feasibility for Licence
Land Conversion
Ownership Certificate
(Patta Copy/ Patta Sheet)
Non Encumbrance
Submission of Licence
Application to
Department of Town &
Country Planning (DTCP)
Demarcation / Zoning
Plan approval by DTCP
Approval of Services
Scheme & Estimates
including plan for public
health services
Approval of
electrification plan
Approval of Building
Plan
Other Statuary Clearance
(EC, AAI, Fire, SWID,
Consent to Establish &
Operate, Road Access,
Tree Cutting)
Registration of Principal
employer under Contract
Labour Act
Registration with
Building Construction
Workers Welfare Board
Building Completion
Certificate
Occupancy Certificate
Sample Copies: Conversion Certificate.PDF, Patta Copy.PDF, RG 125 DEED NO 5802 OF 13.PDF, Land Schedule.xls
Following Major approvals are applied simultaneously at this stage:
Other Approvals required for R.E Project in Haryana
Tree cutting
approval
Road Access
Ancient Monument
approval
Environment
Clearance
Consent to
Establish (CTE) &
Consent to Operate
Bore Well
Registration
Certificate
Site Office Approval
Fire fighting
scheme Approval
Lift Escalator
Installation
Approval (wherever
applicable
Electric substation
NOC
DG Sets installation
approval
Damp Proof
Certificate (DPC)
Swimming pool
operation license
(wherever
applicable)
Hoarding approval AAI Height NOC
Sample Copies: Solid Waste Disposal.PDF, Strom Water Discharge.PDF, Ground water certificate.PDF,
Treated Waste Water.PDF, Water Connection.PDF, Airport NOC.PDF
Approval Procedure For R.E Project In Haryana
Occupation Granted
Any composition fee required from Applicant
Report received from the above offices
Examination By CA(HUDA), Circle Office, District Planner Office
Application in order
Scrutiny of documents at HQ
Applicant submits the application along with Deviation & As Built Drawings, Site Photographs and other documents.
3. Workflow for Occupation Certificate & Inspection Procedure:
Submission of Licence Application to Department of Town
& Country Planning
Coloniser pays the charges, sign Agreements etc and complies with LOI & DTCP issues the Licence to the Coloniser.
DTCP issue the Letter of Intent (LOI) to the Coloniser.
The Financial Commissioner & Secretary to Govt. of Haryana approves the file & return to DTCP.
The DTCP (HR) forwards the file to The Financial Commissioner & Secretary to Govt. of Haryana for approval.
The Director Urban Estate sends Land Report to DTCP(HR)
Senior Town Planner (STP) verifies that Report & forward it to DTCP(HR)
District Town Planner (DTP) sends Site Report to Senior Town Planner (STP) of that circle.
DTCP marks it down to The Director Urban Estate for Land Report.
DTCP marks it down to District Town Planner (DTP) of local area for Site Report.
Licence application for development is applied to DTCP (HR).
Approval Procedure For Environment Clearance
Stipulated Condition Issued to proponent
SEIAA (For Checking & Recommendation)
SEAC Presentation after resubmission of any short comings (If Everything is ok forward the same to SEIAA)
SEAC (State level Expert Appraisal Committee)received the same and begins evaluation of the entire application
If Application is Ok (If No then Again from Process A)
SEIAA Scrutinises the Application at time of submission
Submission to SEIAA (State level Environmental Impact Assessment Authority)
Applicant submits Completed Application Form (Process A)
Approval Process for other Due Diligence
Ownership Certificate (Patta Copy/
Patta Sheet)- From Tehsildar
Non Encumbrance
Approving Authority: Revenue Department Registration Department
Law / Regulation under which
the approval is sought:
Punjab Land Preservation Act 1900 Indian Registration Act 1908
Time Limit prescribed by the
Govt:
No limit No limit
Time Taken for the Clearance: 3 days 3 days
Costs Involved: Rs. 100/- per document No cost
Personal Visit Required : Yes Yes
Documentations Required: Proof of Ownership Proof of ownership
Factor for Delay in Approval Procedure
The major delays in the RE approval procedures in Haryana are seen at the following levels of approvals:
1) Environment Clearance / NOC process: If the land area more than 125 Acres or Built area more than
20,000Sqmtrs then Developer has necessary obtain Environmental clearance and total time consume for these
approval is 2.5 to 3 yrs. (Declaration Letter by CSD for Bricks Sales.pdf)
2) Building Plan Approval: The present system of building plan approval involves NOC`s from different nodal
agencies like HUDA, AAI/IAF, ASI, Fire Fighting Department, Revenue Department etc. The time required could
be reduced to make the process faster by introducing single window clearance.
3) Height NOC from AAI/IAF: Structure/ Building Height Clearance take longer than the stipulated time. AAI/IAF
should issue the NOC within one month of submission of application. (AAI NOC.PDF)
Comparison of time taken for Approvals by various State
Source: FICCI Approval Process for Real Estate
Conclusion
► For every Clearance Personal visit required is essential.
► Total time required from land purchase till Grant of Licence for Development range between 14-15
months.
► Total time required for approval of Demarcation/Zoning Plan is about 5 months.
► Time required for Building Plan Approval ranges between 2-5 months.
► Total time required for Service Estimates Approval is about 6 months.
► Time required for site development works including laying of public health services and
construction of buildings is 20-24 months.
► Time required for grant of completion certificate of building and occupation permission by DTCP
including grant of no occupation permission is 6 months.
 https://tcpharyana.gov.in/FunctionAndPolicy.html (accessed on 27/3/2018)
 https://en.wikipedia.org/wiki/Haryana (accessed on 28/3/2018)
 https://www.huda.org.in/Pages/default.aspx (accessed on 28/3/2018)
 FICCI Approval Process for Real Estate Projects in Haryana.
 S.K. Mitra “Various Local Approval & Clearance Required for Large Scale Project in Metro Cities” 25th October 2013
References

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (20)

land acquisition act 2013
 land acquisition act 2013 land acquisition act 2013
land acquisition act 2013
 
Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
 
Land acquisition
Land acquisitionLand acquisition
Land acquisition
 
Land pooling policy
Land pooling policyLand pooling policy
Land pooling policy
 
Webinar on Town planning scheme
Webinar on Town planning schemeWebinar on Town planning scheme
Webinar on Town planning scheme
 
Land acquisition
Land acquisitionLand acquisition
Land acquisition
 
Maharashtra regional town planning act (1966)
Maharashtra regional town planning act (1966)Maharashtra regional town planning act (1966)
Maharashtra regional town planning act (1966)
 
Rera act 2016 ppt
Rera act 2016 pptRera act 2016 ppt
Rera act 2016 ppt
 
TDR - TRANSFER OF DEVELOPMENT RIGHTS
TDR - TRANSFER OF DEVELOPMENT RIGHTSTDR - TRANSFER OF DEVELOPMENT RIGHTS
TDR - TRANSFER OF DEVELOPMENT RIGHTS
 
HRIDAY Scheme.pptx
HRIDAY Scheme.pptxHRIDAY Scheme.pptx
HRIDAY Scheme.pptx
 
Land acquisition act 1894- 2013
Land acquisition act 1894- 2013Land acquisition act 1894- 2013
Land acquisition act 1894- 2013
 
Maha rera overview
Maha rera overviewMaha rera overview
Maha rera overview
 
Land Acquisition
Land AcquisitionLand Acquisition
Land Acquisition
 
LAND RECORDS MODERNISATION PROGRAMME
LAND RECORDS MODERNISATION PROGRAMMELAND RECORDS MODERNISATION PROGRAMME
LAND RECORDS MODERNISATION PROGRAMME
 
Land acquisition for NH under the NH act, 1956
Land acquisition for NH under the NH act, 1956Land acquisition for NH under the NH act, 1956
Land acquisition for NH under the NH act, 1956
 
Land pooling Policy of DDA TPS and Magarpatta
Land pooling   Policy of DDA TPS and MagarpattaLand pooling   Policy of DDA TPS and Magarpatta
Land pooling Policy of DDA TPS and Magarpatta
 
The Uttar Pradesh slum areas (improvement and clearance)(amendment) act 1981
The Uttar Pradesh slum areas (improvement and clearance)(amendment) act 1981The Uttar Pradesh slum areas (improvement and clearance)(amendment) act 1981
The Uttar Pradesh slum areas (improvement and clearance)(amendment) act 1981
 
Real Estate Sector of India
Real Estate Sector of IndiaReal Estate Sector of India
Real Estate Sector of India
 
Planning Legislation in India (Town Planning)
Planning Legislation in India (Town Planning)Planning Legislation in India (Town Planning)
Planning Legislation in India (Town Planning)
 
Amrut ppt
Amrut pptAmrut ppt
Amrut ppt
 

Ähnlich wie Permission & Clearance for Real Estate Projects in Haryana

Statutory Approvals For Construction Projects In India (Residential & Commerc...
Statutory Approvals For Construction Projects In India (Residential & Commerc...Statutory Approvals For Construction Projects In India (Residential & Commerc...
Statutory Approvals For Construction Projects In India (Residential & Commerc...
SSudhaVelan
 
Haryana pollution control board
Haryana pollution control boardHaryana pollution control board
Haryana pollution control board
Dewesh Singh
 
Rec framework in india
Rec framework in indiaRec framework in india
Rec framework in india
ranjeetsingh
 
DDOT Buys 2017 Presentation (September 26, 2017)
DDOT Buys 2017 Presentation (September 26, 2017)DDOT Buys 2017 Presentation (September 26, 2017)
DDOT Buys 2017 Presentation (September 26, 2017)
DC Office of Contracting & Procurement (OCP)
 

Ähnlich wie Permission & Clearance for Real Estate Projects in Haryana (20)

building plan and designing and ppt.ppt
building plan and designing and  ppt.pptbuilding plan and designing and  ppt.ppt
building plan and designing and ppt.ppt
 
Malaysian Property Development
Malaysian Property DevelopmentMalaysian Property Development
Malaysian Property Development
 
Permits and procedures generally required for construction of a real estate p...
Permits and procedures generally required for construction of a real estate p...Permits and procedures generally required for construction of a real estate p...
Permits and procedures generally required for construction of a real estate p...
 
Real estate hrm ppt final naveen shukla
Real estate hrm ppt final naveen shuklaReal estate hrm ppt final naveen shukla
Real estate hrm ppt final naveen shukla
 
Tanmay presentation
Tanmay presentationTanmay presentation
Tanmay presentation
 
bp
bpbp
bp
 
Statutory Approvals For Construction Projects In India (Residential & Commerc...
Statutory Approvals For Construction Projects In India (Residential & Commerc...Statutory Approvals For Construction Projects In India (Residential & Commerc...
Statutory Approvals For Construction Projects In India (Residential & Commerc...
 
WORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IWORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-I
 
COLD STORE PROJECT SCHEME.
COLD STORE PROJECT SCHEME.COLD STORE PROJECT SCHEME.
COLD STORE PROJECT SCHEME.
 
Haryana pollution control board
Haryana pollution control boardHaryana pollution control board
Haryana pollution control board
 
Real Estate (Regulation and Development) Act, 2017
Real Estate (Regulation and Development) Act, 2017Real Estate (Regulation and Development) Act, 2017
Real Estate (Regulation and Development) Act, 2017
 
Bihar rfp
Bihar rfpBihar rfp
Bihar rfp
 
Coastal Canal Grant Program BOCC Policy
Coastal Canal Grant Program BOCC PolicyCoastal Canal Grant Program BOCC Policy
Coastal Canal Grant Program BOCC Policy
 
What is completion certificate and how to obtain it
What is completion certificate and how to obtain itWhat is completion certificate and how to obtain it
What is completion certificate and how to obtain it
 
Application for H Street NE Small Business Capital Improvement Grant
Application for H Street NE Small Business Capital Improvement GrantApplication for H Street NE Small Business Capital Improvement Grant
Application for H Street NE Small Business Capital Improvement Grant
 
Redevelopment
RedevelopmentRedevelopment
Redevelopment
 
Rec framework in india
Rec framework in indiaRec framework in india
Rec framework in india
 
RERA - Key practical aspects and compliances - Sandeep Jhunjhunwala
RERA - Key practical aspects and compliances - Sandeep JhunjhunwalaRERA - Key practical aspects and compliances - Sandeep Jhunjhunwala
RERA - Key practical aspects and compliances - Sandeep Jhunjhunwala
 
Indirect tax judicial precedents september 2016 (1)
Indirect tax judicial precedents  september 2016 (1)Indirect tax judicial precedents  september 2016 (1)
Indirect tax judicial precedents september 2016 (1)
 
DDOT Buys 2017 Presentation (September 26, 2017)
DDOT Buys 2017 Presentation (September 26, 2017)DDOT Buys 2017 Presentation (September 26, 2017)
DDOT Buys 2017 Presentation (September 26, 2017)
 

Kürzlich hochgeladen

MEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
MEQ Mainstreet Equity Corp Q2 2024 Investor PresentationMEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
MEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
MEQ - Mainstreet Equity Corp.
 
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
ApartmentWala1
 
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
ApartmentWala1
 
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
delhi24hrs1
 
Acibadem Konaklari Uskudar - Listin Turkey
Acibadem Konaklari Uskudar - Listin TurkeyAcibadem Konaklari Uskudar - Listin Turkey
Acibadem Konaklari Uskudar - Listin Turkey
Listing Turkey
 
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
delhi24hrs1
 
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
asmaqueen5
 

Kürzlich hochgeladen (20)

Best Interior Design Services in Haldwani
Best Interior Design Services in HaldwaniBest Interior Design Services in Haldwani
Best Interior Design Services in Haldwani
 
MEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
MEQ Mainstreet Equity Corp Q2 2024 Investor PresentationMEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
MEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
 
Kohinoor Courtyard One Wakad Pune | Elegant Living Spaces
Kohinoor Courtyard One Wakad Pune | Elegant Living SpacesKohinoor Courtyard One Wakad Pune | Elegant Living Spaces
Kohinoor Courtyard One Wakad Pune | Elegant Living Spaces
 
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
 
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
 
Kalpataru Exquisite Wakad Pune E-Brochure.pdf
Kalpataru Exquisite Wakad Pune  E-Brochure.pdfKalpataru Exquisite Wakad Pune  E-Brochure.pdf
Kalpataru Exquisite Wakad Pune E-Brochure.pdf
 
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
 
Bridge & Elliot Ladner Floor Plans May 2024.pdf
Bridge & Elliot Ladner Floor Plans May 2024.pdfBridge & Elliot Ladner Floor Plans May 2024.pdf
Bridge & Elliot Ladner Floor Plans May 2024.pdf
 
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdf
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdfThe Gale at Godrej Park World Hinjewadi Pune Brochure.pdf
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdf
 
Kohinoor Teiko Hinjewadi Phase 2 Pune E-Brochure.pdf
Kohinoor Teiko Hinjewadi Phase 2 Pune  E-Brochure.pdfKohinoor Teiko Hinjewadi Phase 2 Pune  E-Brochure.pdf
Kohinoor Teiko Hinjewadi Phase 2 Pune E-Brochure.pdf
 
Retail Space for Lease - 1221 W. Main St., Sun Prairie, WI
Retail Space for Lease - 1221 W. Main St., Sun Prairie, WIRetail Space for Lease - 1221 W. Main St., Sun Prairie, WI
Retail Space for Lease - 1221 W. Main St., Sun Prairie, WI
 
Vanam At Purva Soukhyam Guduvanchery.pdf.pdf
Vanam At Purva Soukhyam Guduvanchery.pdf.pdfVanam At Purva Soukhyam Guduvanchery.pdf.pdf
Vanam At Purva Soukhyam Guduvanchery.pdf.pdf
 
Acibadem Konaklari Uskudar - Listin Turkey
Acibadem Konaklari Uskudar - Listin TurkeyAcibadem Konaklari Uskudar - Listin Turkey
Acibadem Konaklari Uskudar - Listin Turkey
 
Yashwin Enchante Uppar Kharadi Pune E-Brochue.pdf
Yashwin Enchante Uppar Kharadi Pune  E-Brochue.pdfYashwin Enchante Uppar Kharadi Pune  E-Brochue.pdf
Yashwin Enchante Uppar Kharadi Pune E-Brochue.pdf
 
Real Estate Finance and Investments (2019).pdf
Real Estate Finance and Investments (2019).pdfReal Estate Finance and Investments (2019).pdf
Real Estate Finance and Investments (2019).pdf
 
Madhugiri Boucher Managed Farmland (knx)
Madhugiri Boucher Managed Farmland (knx)Madhugiri Boucher Managed Farmland (knx)
Madhugiri Boucher Managed Farmland (knx)
 
SVN Live 5.6.24 Weekly Property Broadcast
SVN Live 5.6.24 Weekly Property BroadcastSVN Live 5.6.24 Weekly Property Broadcast
SVN Live 5.6.24 Weekly Property Broadcast
 
Parksville 96 Surrey Floor Plans May 2024
Parksville 96 Surrey Floor Plans May 2024Parksville 96 Surrey Floor Plans May 2024
Parksville 96 Surrey Floor Plans May 2024
 
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
 
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
 

Permission & Clearance for Real Estate Projects in Haryana

  • 1. Permission & Clearance for Real Estate Projects In Haryana Presented by:-Pritam
  • 2. Table Of Contents ► Introduction ► Approval Procedure For R.E Project In Haryana ► Approvals Required For R.E Project In Haryana ► Other Approvals required for R.E Project in Haryana ► Factor for Delay in Approval Procedure ► Comparison of Major Approvals & Time Taken ► Conclusion ► Reference
  • 3. Introduction ► Haryana has seen development of real estate at scorching pace. ► Haryana has 6 administrative divisions, 22 districts, 72 sub- divisions, 93 revenue tehsils, 50 sub-tehsils, 140 blocks. ► The Department of Town and Country Planning, Haryana is responsible to regulate development.  The Punjab Scheduled Roads and Controlled Areas Restriction of Unregulated Development Act 1963  The Haryana Development & Regulation of Urban Areas Act,1975  The Punjab New (Capital) Periphery Control Act, 1952 ► Developer have to obtain at least 35 major approvals. ► The time span for getting all relevant approvals is 4-5 years Source:https://www.mapsofindia.com/delhi/districts/west-delhi.html
  • 4. Approval Procedure For R.E Project In Haryana Applicant submits the CLU application online Scrutiny of Documents by Field Office Report of DTP, Office forward to Circle Office Circle office forwards the report with remarks to HQ Examination of the Field reports at HQ Application found in order / Meets policy parameters DTCP issues LOI with directions to applicant to submit fees/agreement/ undertaking within 30 days Applicant Submits LOI compliance at HQ within 30 days Scrutiny of Compliance at HQ Compliance found OK CLU Granted 1. Workflow for change of Land use (CLU) :
  • 5. Land Conversion Details Developing Authority : Department of Town & Country Planning (DTCP), Haryana. • Law / Regulation under which the approval is sought: • Section 8 of Punjab Scheduled Roads and Controlled Areas Restriction of Unregulated Development Act 1963. • Time Limit prescribed by the Government: • 3 Months. • Time Taken for the Clearance: At least 6 months. • Costs Involved: − Scrutiny Fee @ Rs. 10/- per Square Meter − CLU charges vary according to Zone/ abutting roads per Square Meter which are :Residential from Rs. 15/- to Rs. 210/- & Commercial from Rs. 100/- to Rs. 1470/ • Documentations Required: • Revenue Map duly signed by Patwari, • Proof of Land Ownership • Proof of financial capability like Balance Sheet, Income Tax Clearance Certificate • Survey Map, Site Plan • Difficulties faced in the documentation : • If the land is jointly owned, it gets difficult to mutate the same and get the clearance from Tehsildar
  • 6. Approval Procedure For R.E Project In Haryana 2. Workflow for Building Plan & Inspection Procedure: Applicant submits the application along with Scrutiny fee, Labour Cess fee, NOC of AAI etc. & drawing Scrutiny of document by Head Office Application in Order Examination by Concerned Circle office, SE HUDA, Fire officer, Urban Local Bodies Meeting of BPAC fixed to review the comments Plan review by BPAC as per Zoning Plan, HBC 2017 and NBC Signed by BPAC Members HQ verifies validity Licence / CLU permission / pending dues Orders issued for release of Building Plan and approval conveyed HQ - Head Quarter of Town & Country Planning SE - Superintending Engineer BPAC - Building Plan Approval Committee HBC - Haryana Building Code NBC - National Building Code HUDA – Haryana Urban Development Authority
  • 7. Approvals Required For R.E Project In Haryana Land Purchase and Land Papers Examination & Feasibility for Licence Land Conversion Ownership Certificate (Patta Copy/ Patta Sheet) Non Encumbrance Submission of Licence Application to Department of Town & Country Planning (DTCP) Demarcation / Zoning Plan approval by DTCP Approval of Services Scheme & Estimates including plan for public health services Approval of electrification plan Approval of Building Plan Other Statuary Clearance (EC, AAI, Fire, SWID, Consent to Establish & Operate, Road Access, Tree Cutting) Registration of Principal employer under Contract Labour Act Registration with Building Construction Workers Welfare Board Building Completion Certificate Occupancy Certificate Sample Copies: Conversion Certificate.PDF, Patta Copy.PDF, RG 125 DEED NO 5802 OF 13.PDF, Land Schedule.xls
  • 8. Following Major approvals are applied simultaneously at this stage: Other Approvals required for R.E Project in Haryana Tree cutting approval Road Access Ancient Monument approval Environment Clearance Consent to Establish (CTE) & Consent to Operate Bore Well Registration Certificate Site Office Approval Fire fighting scheme Approval Lift Escalator Installation Approval (wherever applicable Electric substation NOC DG Sets installation approval Damp Proof Certificate (DPC) Swimming pool operation license (wherever applicable) Hoarding approval AAI Height NOC Sample Copies: Solid Waste Disposal.PDF, Strom Water Discharge.PDF, Ground water certificate.PDF, Treated Waste Water.PDF, Water Connection.PDF, Airport NOC.PDF
  • 9. Approval Procedure For R.E Project In Haryana Occupation Granted Any composition fee required from Applicant Report received from the above offices Examination By CA(HUDA), Circle Office, District Planner Office Application in order Scrutiny of documents at HQ Applicant submits the application along with Deviation & As Built Drawings, Site Photographs and other documents. 3. Workflow for Occupation Certificate & Inspection Procedure:
  • 10. Submission of Licence Application to Department of Town & Country Planning Coloniser pays the charges, sign Agreements etc and complies with LOI & DTCP issues the Licence to the Coloniser. DTCP issue the Letter of Intent (LOI) to the Coloniser. The Financial Commissioner & Secretary to Govt. of Haryana approves the file & return to DTCP. The DTCP (HR) forwards the file to The Financial Commissioner & Secretary to Govt. of Haryana for approval. The Director Urban Estate sends Land Report to DTCP(HR) Senior Town Planner (STP) verifies that Report & forward it to DTCP(HR) District Town Planner (DTP) sends Site Report to Senior Town Planner (STP) of that circle. DTCP marks it down to The Director Urban Estate for Land Report. DTCP marks it down to District Town Planner (DTP) of local area for Site Report. Licence application for development is applied to DTCP (HR).
  • 11. Approval Procedure For Environment Clearance Stipulated Condition Issued to proponent SEIAA (For Checking & Recommendation) SEAC Presentation after resubmission of any short comings (If Everything is ok forward the same to SEIAA) SEAC (State level Expert Appraisal Committee)received the same and begins evaluation of the entire application If Application is Ok (If No then Again from Process A) SEIAA Scrutinises the Application at time of submission Submission to SEIAA (State level Environmental Impact Assessment Authority) Applicant submits Completed Application Form (Process A)
  • 12. Approval Process for other Due Diligence Ownership Certificate (Patta Copy/ Patta Sheet)- From Tehsildar Non Encumbrance Approving Authority: Revenue Department Registration Department Law / Regulation under which the approval is sought: Punjab Land Preservation Act 1900 Indian Registration Act 1908 Time Limit prescribed by the Govt: No limit No limit Time Taken for the Clearance: 3 days 3 days Costs Involved: Rs. 100/- per document No cost Personal Visit Required : Yes Yes Documentations Required: Proof of Ownership Proof of ownership
  • 13. Factor for Delay in Approval Procedure The major delays in the RE approval procedures in Haryana are seen at the following levels of approvals: 1) Environment Clearance / NOC process: If the land area more than 125 Acres or Built area more than 20,000Sqmtrs then Developer has necessary obtain Environmental clearance and total time consume for these approval is 2.5 to 3 yrs. (Declaration Letter by CSD for Bricks Sales.pdf) 2) Building Plan Approval: The present system of building plan approval involves NOC`s from different nodal agencies like HUDA, AAI/IAF, ASI, Fire Fighting Department, Revenue Department etc. The time required could be reduced to make the process faster by introducing single window clearance. 3) Height NOC from AAI/IAF: Structure/ Building Height Clearance take longer than the stipulated time. AAI/IAF should issue the NOC within one month of submission of application. (AAI NOC.PDF)
  • 14. Comparison of time taken for Approvals by various State Source: FICCI Approval Process for Real Estate
  • 15. Conclusion ► For every Clearance Personal visit required is essential. ► Total time required from land purchase till Grant of Licence for Development range between 14-15 months. ► Total time required for approval of Demarcation/Zoning Plan is about 5 months. ► Time required for Building Plan Approval ranges between 2-5 months. ► Total time required for Service Estimates Approval is about 6 months. ► Time required for site development works including laying of public health services and construction of buildings is 20-24 months. ► Time required for grant of completion certificate of building and occupation permission by DTCP including grant of no occupation permission is 6 months.
  • 16.  https://tcpharyana.gov.in/FunctionAndPolicy.html (accessed on 27/3/2018)  https://en.wikipedia.org/wiki/Haryana (accessed on 28/3/2018)  https://www.huda.org.in/Pages/default.aspx (accessed on 28/3/2018)  FICCI Approval Process for Real Estate Projects in Haryana.  S.K. Mitra “Various Local Approval & Clearance Required for Large Scale Project in Metro Cities” 25th October 2013 References