• Methods to solve LPP :
1. Graphical Method - for only two variables.
2. Simplex Method - Universal method.
3. Assignment Method - Special method.
4. Transportation Method - Special method.
Note : Methods (2), (3) and (4) are iterative
methods.
Assignment Method
(Special Method)
• Assignment Problems
and
• Methods to solve such
problems
C11 C12 . . C1n
C21 C22 . . C2n
. . . . .
. . . . .
Cm1 . . . Cmn
Jobs (Activities)
1 2 . . n
1
2
.
.
m
Persons(Resources)
CasesCases
• m = n
• m ≠ n
• Cij
• Pij
• Cij = Cost associated with assigning ith
resource to jth
activity
Assignment ProblemAssignment Problem
A. Balanced Minimization → m = n with Cij
B. Unbalanced Minimization →m ≠ n with Cij
C. Balanced Maximization → m = n with Pij
D. Unbalanced Maximization →m ≠ n with Pij
Categories of Assignment ProblemsCategories of Assignment Problems
C11 C12 . . C1n
C21 C22 . . C2n
. . . . .
. . . . .
Cn1 . . . Cnn
Jobs (Activities)
1 2 . . n
1
2
.
.
n
Persons(Resources)
• Xij = assignment of ith
resource to jth
activity
• Assignments are made on one to one basis
A.A. Balanced Minimization ProblemBalanced Minimization Problem
Formulation of Assignment Problem as LPP
1 1
.
n n
i j
Min Z Cij Xij
= =
= ∑∑
1
/ 1 ( )
n
j
s t Xij for all i I
=
= −∑
1
1 ( )
n
i
Xij for all j II
=
= −∑
0 1 & .All Xij or for all i j=
Methods to solve Assignment ProblemsMethods to solve Assignment Problems
4. Hungarian Method
1. Enumeration Method
2. Integer Programming Method
3. Transportation Method
C11 C12
C21 C22
1 2
1
2
1.1. Enumeration MethodEnumeration Method
• For n x n Problem---- n!
2! (=2)• No. of Possible solutions =
• P1J1 , P2J2 OR P1J2 , P2J1
• For 4 x 4 Problem---- 4! = 24
• For 5 x 5 Problem----5! = 120
• All Xij = 0 or 1 → 0-1 Integer programming.
2.2. Integer Programming MethodInteger Programming Method
• Difficult to solve manually.
• For n x n Problem → Variables = n x n.
Constraints = n+n = 2n
• For 5 x 5 Problem → Variables = 25
Constraints = 10
• Formulate the problem in Transportation
Problem format.
3.3. Transportation MethodTransportation Method
C11 C12 . . C1n
C21 C22 . . C2n
. . . . .
. . . . .
Cn1 . . . Cnn
1 2 . . n
1
2
.
.
n
1
1
.
1
1 1 . . 1
4.4. Hungarian MethodHungarian Method
1. Row Deduction
2. Column Deduction
3. Assign zeros-If all assignments are over,
Then STOP
Else Go To Step 4
4. Adopt Tick Marking Procedure
5. Modify Cij and Go To Step 3
(Mr. D. Konig - A Hungarian Mathematician)
Steps :Steps :
1 2 3
1
2
3
Prob. 1Prob. 1 Balanced Minimization ProblemBalanced Minimization Problem
Perform Row DeductionPerform Row Deduction
19 28 31
11 17 16
12 15 13
0 9 12
0 6 5
0 3 1
1 2 3
1
2
3
Row DeductionRow Deduction
• Perform Column DeductionPerform Column Deduction
0 6 11
0 3 4
0 0 0
1 2 3
1
2
3
Column DeductionColumn Deduction
• Minimum uncrossed no = 3.
• Modify Numbers
Assign ZerosAssign Zeros
Adopt Tick MarkingAdopt Tick Marking
0 3 8
0 0 1
3 0 0
1 2 3
1
2
3
• Hence optimal solution is
P1J1, P2J2, P3J3 giving Z = 19+17+13 = 49
Procedure of Assigning ZerosProcedure of Assigning Zeros
Steps to be followed, after getting at-least one zero in each row &
each column.
1. Start with 1st row. If there is only one uncrossed, unassigned
zero, assign it & cross other zeros in respective column (of
assigned zero), if they exits, else go to next row. Repeat this for
next all other rows.
2. If still uncrossed, unassigned zeros are available, start with first
column. If there is only one uncrossed, unassigned zero, assign it
and cross other zeros in respective row of assigned zero, if they
exit, else go to next column. Repeat this for next all other columns.
3. Repeat 1 & 2 until single uncrossed, unassigned zeros are
available, while going through rows & columns.
4. If still multiple uncrossed, unassigned zeros are available while
going through rows & columns, it indicates that multiple
(alternative) optimal solutions are possible.
Assign any one remaining uncrossed, unassigned zero & cross
remaining zeros in respective row & column of assigned zero.
Then go to 1.
5. If required assignments are completed then STOP, else perform
“Tick Marking Procedure”. Modify numbers & go to 1.
Tick marking ProcedureTick marking Procedure
(To draw minimum number of lines through zeros.)
1. Tick marks row/rows where there is no assigned zero.
2. Tick mark column/columns w.r.t. crossed zero/zeros in
marked row/rows.
3. Tick mark row/rows w.r.t. assigned zero in marked
column/columns.
4. Go to to step 2 and repeat the procedure until no zero is
available for tick marking.
Then
5. Draw lines through unmarked rows and marked columns
(Check no. of lines = No. of assigned
zeros)
Tick marking ProcedureTick marking Procedure
(Continue)(Continue)
How to Modify numbers ?
Find minimum number out of uncrossed numbers.
1. Add this minimum number to crossings.
2. Deduct this number from all uncrossed numbers one by one.
3. Keep crossed numbers, on horizontal & vertical lines,
except on crossing, same
C11 C12 C13
C21 C22 C23
. . .
. . .
C51 C52 C53
Jobs (Activities)
1 2 3
1
2
3
4
5
Persons(Resources)
• D1 and D2 Dummy Jobs are to be
introduced to balance the problem
B. Unbalanced Minimization ProblemB. Unbalanced Minimization Problem
C11 C12 C13 0 0
C21 C22 C23 0 0
. . . 0 0
. . . 0 0
C51 C52 C53 0 0
Jobs (Activities)
1 2 3 D1 D2
1
2
3
4
5
Persons(Resources)
• D1 and D2 are Dummy Jobs : Cij = 0
Prob. 2 The personnel manager of ABC Company wants
to assign Mr. X, Mr. Y and Mr. Z to regional offices. But the
firm also has an opening in its Chennai office and would send
one of the three to that branch, if it were more economical
than a move to Delhi, Mumbai or Kolkata. It will cost Rs.
2,000 to relocate Mr. X to Chennai, Rs. 1,600 to reallocate
Mr. Y there, and Rs. 3,000 to move Mr. Z. What is the
optimal assignment of personnel to offices ?
Office
Delhi Mumbai Kolkata
Personnel
Mr. X 1,600 2,200 2,400
Mr. Y 1,000 3,200 2,600
Mr. Z 1,000 2,000 4,600
UBMin (AP), after adding Chennai :
Delhi Mumbai Kolkata Chennai
Mr. X 1,600 2,200 2,400 2,000
Mr. Y 1,000 3,200 2,600 1,600
Mr. Z 1,000 2,000 4,600 3,000
BMin (AP), after adding Dummy Row
:
Delhi Mumbai Kolkata Chennai
Mr. X 1,600 2,200 2,400 2,000
Mr. Y 1,000 3,200 2,600 1,600
Mr. Z 1,000 2,000 4,600 3,000
Dummy 0 0 0 0
After Row Deduction :
D M K Ch
X 0 600 800 400
Y 0 2,200 1,600 600
Z 0 1,000 3,600 2,000
Dm 0 0 0 0
Modified Matrix and Assignment :
D M K Ch
X 0 200 400 0
Y 0 1,800 1,200 200
Z 0 600 3,200 1,600
Dm 0 0 0 0
Modified Matrix and Assignment :
D M K Ch
X 200 200 400 0
Y 0 1,600 1,000 0
Z 0 400 3,000 1,400
Dm 400 0 0 0
Modified Matrix and Assignment :
D M K Ch
X 200 0 200 0
Y 0 1,400 800 0
Z 0 200 2,800 1,400
Dm 6 00 0 0 200
Hence, Optimal Solution is : XM, YCh, ZD
Giving Z = 2,200 + 1,600 + 1,000 = 4,800
Hence, it is economical to move Y to Chennai
Jobs (Activities)
1 2 3 4 5
1
2
3
4
5
Persons(Resources)
• Convert Profit Matrix into Relative Cost
Matrix
C. Balanced Maximization ProblemC. Balanced Maximization Problem
Pij
• How to Convert Profit Matrix into
Relative Cost Matrix ?
3. (Pij)max - Pij = RCij
1. (Pij) (-1) = RCij
2. 1/Pij = RCij
Prob. 3 Balanced Maximization Problem :Prob. 3 Balanced Maximization Problem :
C1 C2 C3 C4
P1 60 100 90 95
P2 93 60 70 60
P3 75 85 60 90
P4 95 89 65 60
Balanced RC Matrix :Balanced RC Matrix :
C1 C2 C3 C4
P1 40 0 10 5
P2 7 40 30 40
P3 25 15 40 10
P4 5 11 35 40
After Row Deduction :After Row Deduction :
C1 C2 C3 C4
P1 40 0 10 5
P2 0 33 23 33
P3 15 5 30 0
P4 0 6 30 35
After Column Deduction :After Column Deduction :
C1 C2 C3 C4
P1 40 0 0 5
P2 0 33 13 33
P3 15 5 20 0
P4 0 6 20 35
Assigning :Assigning :
C1 C2 C3 C4
P1 40 0 0 5
P2 0 33 13 33
P3 15 5 20 0
P4 0 6 20 35
Modified Matrix and Assigning :Modified Matrix and Assigning :
C1 C2 C3 C4
P1 46 0 0 5
P2 0 27 7 27
P3 21 5 20 0
P4 0 0 14 29
Hence, Optimal Solution is : P1C3, P2C1, P3C4, P4C2
Giving Z = 90 + 93 + 90 + 89 = 362
Jobs (Activities)
1 2 3
1
2
3
4
5
Persons(Resources)
• Convert Unbalanced Profit Matrix into
Unbalanced Relative Cost Matrix
D. Unbalanced Maximization ProblemD. Unbalanced Maximization Problem
Pij
• Then Balance the matrix and solve
Prob. 4 Unbalanced Maximization Problem :Prob. 4 Unbalanced Maximization Problem :
J1 J2 J3 J4
P1 62 78 50 101
P2 71 84 61 73
P3 87 111 92 71
Unbalanced RC Matrix :Unbalanced RC Matrix :
J1 J2 J3 J4
P1 49 33 61 10
P2 40 27 50 38
P3 24 0 19 40
Balanced RC Matrix :Balanced RC Matrix :
J1 J2 J3 J4
P1 49 33 61 10
P2 40 27 50 38
P3 24 0 19 40
D 0 0 0 0
After Row Deduction :After Row Deduction :
J1 J2 J3 J4
P1 39 23 51 0
P2 13 0 23 11
P3 24 0 19 40
D 0 0 0 0
Assigning :Assigning :
J1 J2 J3 J4
P1 39 23 51 0
P2 13 0 23 11
P3 24 0 19 40
D 0 0 0 0
Modified Matrix and Assigning :Modified Matrix and Assigning :
J1 J2 J3 J4
P1 39 34 51 0
P2 2 0 12 0
P3 13 0 8 29
D 0 11 0 0
Modified Matrix and Assigning :Modified Matrix and Assigning :
J1 J2 J3 J4
P1 37 34 49 0
P2 0 0 10 0
P3 11 0 6 29
D 0 13 0 2
Hence, Optimal Solution is : P1J4, P2J1, P3J2
Giving Z = 101 + 71 + 111 = 283
10 5 13 15 16
3 9 18 13 6
10 7 3 2 2
7 11 9 7 12
7 9 10 4 12
Jobs (Activities)
1 2 3 4 5
1
2
3
4
5
Persons(Resources)Prob. 5 Practice Problem (Minimization)Prob. 5 Practice Problem (Minimization)
5 0 8 10 11
0 6 15 10 3
8 5 1 0 0
0 4 2 0 5
3 5 6 0 8
Jobs (Activities)
1 2 3 4 5
1
2
3
4
5
Persons(Resources)
5 0 7 10 11
0 6 14 10 3
8 5 0 0 0
0 4 1 0 5
3 5 5 0 8
Jobs (Activities)
1 2 3 4 5
1
2
3
4
5
Persons(Resources) • Minimum uncrossed Number = 1.
6 0 7 11 11
0 5 13 10 2
9 5 0 1 0
0 3 0 0 4
3 4 4 0 7
Jobs (Activities)
1 2 3 4 5
1
2
3
4
5
Persons(Resources)
• Hence optimal solution is
P1J2, P2J1, P3J5, P4J3, P5J4 giving Z = 5+3+2+9+4 =
23
4 7 5 6
− 8 7 4
3 − 5 3
6 6 4 2
Jobs (Activities)
1 2 3 4
1
2
3
4
Persons(Resources)
Prob. 6Prob. 6
Problem for Alternative / Multiple Optimal Solutions :
0 3 1 2
Μ 4 3 0
0 Μ 2 0
4 4 2 0
Jobs (Activities)
1 2 3 4
1
2
3
4
Persons(Resources)
After Row deduction 
0 0 0 2
Μ 1 2 0
0 Μ 1 0
4 1 1 0
Jobs (Activities)
1 2 3 4
1
2
3
4
Persons(Resources)
After Column deduction 
Now modified matrix will be :
0 0 0 3
Μ 0 1 0
0 Μ 1 1
3 0 0 0
Jobs (Activities)
1 2 3 4
1
2
3
4
Persons(Resources)
• Hence, this is a case of alternative optimal solutions.
• Assign any one remaining zero and cross existing zeros
in respective row and column, then apply assigning
procedure.
• Hence, one of the optimal solutions is P1J2, P2J4, P3J1,
P4J3 giving Z = 7+4+3+4 = 18
0 0 0 3
Μ 0 1 0
0 Μ 1 1
3 0 0 0
Jobs (Activities)
1 2 3 4
1
2
3
4
Persons(Resources)
• Hence, another optimal solution is P1J3, P2J2, P3J1,
P4J4 giving Z = 5+8+3+2 = 18
To get another optimal solution, assign another remaining zero.
P1J3 can not be assigned, as it is already assigned before.
. Restriction in Assignment.
e.g. Assignment of P3 to J4 is not possible.
Then C34 = M (Big Number)
. Alternative Optimal Solution Possibility
-Already considered.
. Particular assignment is prefixed.
e.g. If P3 & J4 prefixed
Then Row3 & Column4 are deleted.
Typical Cases in Assignment ProblemsTypical Cases in Assignment Problems
Typical
Questions
Que. Answer each of the following questions in brief.
[ 1 ] What are the methods to solve Assignment Problems ?
Ans. : (1) Enumeration Method
(2) Integer Programming Method
(3) Transportation Method
(4) Hungarian Method
[ 2 ] How can you identify a function as Linear ?
Ans. : Power of each variable = only 1.
No multiplication of variables.
[ 3 ] What is the purpose of “Tick Marking Procedure” in a
method of solving Assignment Problems ?
Ans. : The purpose of “Tick Marking” procedure is to
draw minimum number of lines covering zeros.
[ 4 ] What is significance of name “Hungarian Method” ?
Ans. : It is because of D. Konig of Hungary.
[ 5 ] Following is Minimization Assignment Problem.
(i) Write objective equation.
(ii) Write all possible constraints.
(iii) State “Non-Negativity” conditions for this problem.
(iv) State Optimal Solution. Is it unique optimal ?
X Y
A 3 2
B 4 5
Ans. : ( i ) Min Z = 3x11 + 2x12 + 4x21 + 5x22
( ii ) x11 + x12 = 1
x21 + x22 = 1
x11 + x21 = 1
x12 + x22 = 1
( iii ) All xij = 0 or 1 OR x11, x12, x21, x22 = 0 or 1
( iv ) Optimal solution is AY, BX giving Z = 6 (unique)
[ 6 ] Get Optimal Solution of following Minimization
Assignment Problem. How many Optimal Solutions are
existing for this problem ?
X Y Z
A 3 2 2
B 6 5 5
C 6 1 1
X Y Z
A 3 2 2
B 6 5 5
C 6 1 1
X Y Z
A 1 0 0
B 1 0 0
C 5 0 0
X Y Z
A 0 0 0
B 0 0 0
C 4 0 0
X Y Z
A 0 0 0
B 0 0 0
C 4 0 0
X Y Z
A 0 0 0
B 0 0 0
C 4 0 0
X Y Z
A 0 0 0
B 0 0 0
C 4 0 0
There are 4 Optimal Solutions.
RecapitulateRecapitulate
• Methods to solve Assignment
Problem
• Hungarian Method
• Typical cases of Assignment
Problems
Home Assignments :
[ 1 ] Answer the following in brief :
( a ) What is the purpose of “Tick Marking”
procedure in solving Assignment Problem ?
( b ) What is significance of name “Hungarian”
method ?
[ 2 ] For the following Minimization Assignment
Problem, answer the question given below.
J1
J2
J3
P1 2 4 3
P2 5 6 6
( a ) Formulate this problem as LPP.
( b ) Get all possible Optimal Solutions.
[ 3 ] ( i ) State possible methods of solving
“Assignment Problem”.
( ii ) State possible methods of converting
“Profit Matrix” into “Relative Cost Matrix”.
[ 4 ] Formulate following Assignment Problem as :
( i ) LPP
( ii ) Transportation Problem
P Q
A 2 5
B 6 4
[ 5 ] Find optimal assignments for following
“Minimization Assignment Problem”.
J1
J2
J3
P1 −10 −10 −12
P2 −18 −6 −14
P3 −6 −2 −2
[ 6 ] Average time taken by operators on 4 old
machines and a new machine are tabulated below.
Management is considering to replace one of the old
machines by a new machine. Is it advantageous to
replace new machine with an old machine ? Why ?
M1
M2
M3
M4 New
O1 10 12 8 10 11
O2 9 10 8 7 10
O3 8 7 8 8 8
O4 12 13 14 14 11
[ 7 ] Consider the problem of assigning four operators
to four machines. The assignment costs are given
in Rupees. Operator 1 cannot be assigned to
machine 3. Also operator 3 cannot be assigned to
machine 4. Find the optimal assignment.
M1 M2 M3 M4
1 5 5 − 2
2 7 4 2 3
3 9 3 5 −
4 7 2 6 7
If 5th Machine is made available and the
respective costs to the four operators are Rs. 2, 1,
2 and 8. Find whether it is economical to replace
any of the four existing machines. If so, which ?
[ 8 ] There are four batsman P, Q, R, & S. The
batsman are to be selected for first three
positions P1, P2 and P3. The expected score by
these batsman at three different positions are
given as below. Decide the optimal batsman for
these three positions.
P1
P2
P3
P 42 16 27
Q 48 40 25
R 50 18 36
S 58 38 60
[ 9 ]
J1 J2 J3 J4
P1 20 22 28 15
P2 16 20 12 13
P3 19 23 14 25
P4 10 16 12 10
Minimization Problem :
[ 10 ]
J1 J2 J3 J4
P1 10 24 30 15
P2 16 22 28 12
P3 12 20 32 10
P4 9 26 34 16
Minimization Problem :
Thank youThank you
For any Query or suggestion :
Contact :
Dr. D. B. Naik
Professor & Head, Training & Placement (T&P)
S. V. National Institute of Technology (SVNIT),
Ichchhanath, Surat – 395 007 (Gujarat) INDIA.
Email ID : dbnaik@gmail.com
dbnaik@svnit.ac.in
dbnaik_svr@yahoo.com
Phone No. : 0261-2201540 (D), 2255225 (O)

Weitere ähnliche Inhalte

Was ist angesagt?

Travelling salesman problem
Travelling salesman problemTravelling salesman problem
Travelling salesman problemShivji Dangar
 
Transportation Problem in Operational Research
Transportation Problem in Operational ResearchTransportation Problem in Operational Research
Transportation Problem in Operational ResearchNeha Sharma
 
Operation research complete note
Operation research  complete noteOperation research  complete note
Operation research complete notekabul university
 
Duality in Linear Programming
Duality in Linear ProgrammingDuality in Linear Programming
Duality in Linear Programmingjyothimonc
 
Special Cases in Simplex Method
Special Cases in Simplex MethodSpecial Cases in Simplex Method
Special Cases in Simplex MethodDivyansh Verma
 
Simulation in Operation Research
Simulation in Operation ResearchSimulation in Operation Research
Simulation in Operation ResearchYamini Kahaliya
 
LP special cases and Duality.pptx
LP special cases and Duality.pptxLP special cases and Duality.pptx
LP special cases and Duality.pptxSnehal Athawale
 
MODI Method (Operations Research)
MODI Method (Operations Research) MODI Method (Operations Research)
MODI Method (Operations Research) Nilraj Vasandia
 
NORTH WEST CORNER METHOD
NORTH WEST CORNER METHODNORTH WEST CORNER METHOD
NORTH WEST CORNER METHODRashiPandey16
 
Assignment problem
Assignment problemAssignment problem
Assignment problemAbu Bashar
 
Transportation and transshipment problems
Transportation  and transshipment problemsTransportation  and transshipment problems
Transportation and transshipment problemsDr. Adinath Damale
 
Dynamic Programming
Dynamic ProgrammingDynamic Programming
Dynamic Programmingcontact2kazi
 
Operations Research
Operations ResearchOperations Research
Operations Researchajithsrc
 

Was ist angesagt? (20)

Linear programming
Linear programmingLinear programming
Linear programming
 
Travelling salesman problem
Travelling salesman problemTravelling salesman problem
Travelling salesman problem
 
linear programming
linear programminglinear programming
linear programming
 
Transportation Problem in Operational Research
Transportation Problem in Operational ResearchTransportation Problem in Operational Research
Transportation Problem in Operational Research
 
Decision theory
Decision theoryDecision theory
Decision theory
 
Operation research complete note
Operation research  complete noteOperation research  complete note
Operation research complete note
 
Duality in Linear Programming
Duality in Linear ProgrammingDuality in Linear Programming
Duality in Linear Programming
 
L20 Simplex Method
L20 Simplex MethodL20 Simplex Method
L20 Simplex Method
 
Goal programming
Goal programmingGoal programming
Goal programming
 
Goal Programming
Goal ProgrammingGoal Programming
Goal Programming
 
Special Cases in Simplex Method
Special Cases in Simplex MethodSpecial Cases in Simplex Method
Special Cases in Simplex Method
 
Simulation in Operation Research
Simulation in Operation ResearchSimulation in Operation Research
Simulation in Operation Research
 
LP special cases and Duality.pptx
LP special cases and Duality.pptxLP special cases and Duality.pptx
LP special cases and Duality.pptx
 
MODI Method (Operations Research)
MODI Method (Operations Research) MODI Method (Operations Research)
MODI Method (Operations Research)
 
NORTH WEST CORNER METHOD
NORTH WEST CORNER METHODNORTH WEST CORNER METHOD
NORTH WEST CORNER METHOD
 
Assignment problem
Assignment problemAssignment problem
Assignment problem
 
Transportation and transshipment problems
Transportation  and transshipment problemsTransportation  and transshipment problems
Transportation and transshipment problems
 
Vam
VamVam
Vam
 
Dynamic Programming
Dynamic ProgrammingDynamic Programming
Dynamic Programming
 
Operations Research
Operations ResearchOperations Research
Operations Research
 

Andere mochten auch

Lesson 33: The Assignment Problem
Lesson 33: The Assignment  ProblemLesson 33: The Assignment  Problem
Lesson 33: The Assignment ProblemMatthew Leingang
 
assignment problem
assignment problemassignment problem
assignment problemSwarit Yadav
 
Linear programming Cost Minimization
Linear programming Cost MinimizationLinear programming Cost Minimization
Linear programming Cost MinimizationKhushbu :-)
 
Assgnment=hungarian method
Assgnment=hungarian methodAssgnment=hungarian method
Assgnment=hungarian methodJoseph Konnully
 
Transportation and Assignment
Transportation and AssignmentTransportation and Assignment
Transportation and AssignmentLokesh Payasi
 
Assignment problem ppt
Assignment problem ppt Assignment problem ppt
Assignment problem ppt Babasab Patil
 
Art characteristics and assignment
Art characteristics and assignmentArt characteristics and assignment
Art characteristics and assignmentMark Taylor
 
2014 IEEE JAVA PARALLEL DISTRIBUTED PROJECT The client assignment problem for...
2014 IEEE JAVA PARALLEL DISTRIBUTED PROJECT The client assignment problem for...2014 IEEE JAVA PARALLEL DISTRIBUTED PROJECT The client assignment problem for...
2014 IEEE JAVA PARALLEL DISTRIBUTED PROJECT The client assignment problem for...IEEEGLOBALSOFTSTUDENTSPROJECTS
 
6 Steps To Assignment Success Snr
6 Steps To Assignment Success Snr6 Steps To Assignment Success Snr
6 Steps To Assignment Success SnrLLeida
 
Loading jobs and methods definitivo
Loading jobs and methods definitivo Loading jobs and methods definitivo
Loading jobs and methods definitivo Jorge Fuentes
 
ITFT - Assignment problem
ITFT - Assignment problemITFT - Assignment problem
ITFT - Assignment problemJasmineKaur29
 
Baroque Art of Northern Europe
Baroque Art of Northern EuropeBaroque Art of Northern Europe
Baroque Art of Northern EuropeGary Freeman
 
DAM assignment - LPP formulation, Graphical solution and Simplex Method
DAM assignment - LPP formulation, Graphical solution and Simplex MethodDAM assignment - LPP formulation, Graphical solution and Simplex Method
DAM assignment - LPP formulation, Graphical solution and Simplex MethodNeha Kumar
 
Automating performance based tests
Automating performance based testsAutomating performance based tests
Automating performance based testsfrancelvcg1161997
 

Andere mochten auch (20)

Lesson 33: The Assignment Problem
Lesson 33: The Assignment  ProblemLesson 33: The Assignment  Problem
Lesson 33: The Assignment Problem
 
Assignment Problem
Assignment ProblemAssignment Problem
Assignment Problem
 
assignment problem
assignment problemassignment problem
assignment problem
 
Assignment problem
Assignment problemAssignment problem
Assignment problem
 
Assignment Problem
Assignment ProblemAssignment Problem
Assignment Problem
 
Linear programming Cost Minimization
Linear programming Cost MinimizationLinear programming Cost Minimization
Linear programming Cost Minimization
 
Assgnment=hungarian method
Assgnment=hungarian methodAssgnment=hungarian method
Assgnment=hungarian method
 
Transportation and Assignment
Transportation and AssignmentTransportation and Assignment
Transportation and Assignment
 
Assignment problem
Assignment problemAssignment problem
Assignment problem
 
Assignment problem ppt
Assignment problem ppt Assignment problem ppt
Assignment problem ppt
 
Art characteristics and assignment
Art characteristics and assignmentArt characteristics and assignment
Art characteristics and assignment
 
2014 IEEE JAVA PARALLEL DISTRIBUTED PROJECT The client assignment problem for...
2014 IEEE JAVA PARALLEL DISTRIBUTED PROJECT The client assignment problem for...2014 IEEE JAVA PARALLEL DISTRIBUTED PROJECT The client assignment problem for...
2014 IEEE JAVA PARALLEL DISTRIBUTED PROJECT The client assignment problem for...
 
6 Steps To Assignment Success Snr
6 Steps To Assignment Success Snr6 Steps To Assignment Success Snr
6 Steps To Assignment Success Snr
 
Loading jobs and methods definitivo
Loading jobs and methods definitivo Loading jobs and methods definitivo
Loading jobs and methods definitivo
 
ITFT - Assignment problem
ITFT - Assignment problemITFT - Assignment problem
ITFT - Assignment problem
 
Assignment
AssignmentAssignment
Assignment
 
Baroque Art of Northern Europe
Baroque Art of Northern EuropeBaroque Art of Northern Europe
Baroque Art of Northern Europe
 
DAM assignment - LPP formulation, Graphical solution and Simplex Method
DAM assignment - LPP formulation, Graphical solution and Simplex MethodDAM assignment - LPP formulation, Graphical solution and Simplex Method
DAM assignment - LPP formulation, Graphical solution and Simplex Method
 
Automating performance based tests
Automating performance based testsAutomating performance based tests
Automating performance based tests
 
21122351 henry-fayol
21122351 henry-fayol21122351 henry-fayol
21122351 henry-fayol
 

Ähnlich wie Ap for b.tech. (mechanical) Assignment Problem

dynamic programming complete by Mumtaz Ali (03154103173)
dynamic programming complete by Mumtaz Ali (03154103173)dynamic programming complete by Mumtaz Ali (03154103173)
dynamic programming complete by Mumtaz Ali (03154103173)Mumtaz Ali
 
04-Unit Four - OR.pptx
04-Unit Four - OR.pptx04-Unit Four - OR.pptx
04-Unit Four - OR.pptxAbdiMuceeTube
 
Linear Programing.pptx
Linear Programing.pptxLinear Programing.pptx
Linear Programing.pptxAdnanHaleem
 
Linear programming manzoor nabi
Linear programming  manzoor nabiLinear programming  manzoor nabi
Linear programming manzoor nabiManzoor Wani
 
Insider mathematical
Insider   mathematicalInsider   mathematical
Insider mathematicalAditi Saxena
 
Dynamic Programming Matrix Chain Multiplication
Dynamic Programming Matrix Chain MultiplicationDynamic Programming Matrix Chain Multiplication
Dynamic Programming Matrix Chain MultiplicationKrishnakoumarC
 
Backtracking & branch and bound
Backtracking & branch and boundBacktracking & branch and bound
Backtracking & branch and boundVipul Chauhan
 
Decision Science.pdf
Decision Science.pdfDecision Science.pdf
Decision Science.pdfpandeyaman577
 
Integer Linear Programming
Integer Linear ProgrammingInteger Linear Programming
Integer Linear ProgrammingSukhpalRamanand
 
Operations Research Problem
Operations Research  ProblemOperations Research  Problem
Operations Research ProblemTaslima Mujawar
 
LPP, Duality and Game Theory
LPP, Duality and Game TheoryLPP, Duality and Game Theory
LPP, Duality and Game TheoryPurnima Pandit
 
Optimization Techniques.pdf
Optimization Techniques.pdfOptimization Techniques.pdf
Optimization Techniques.pdfanandsimple
 
Integer Programming PPt.ernxzamnbmbmspdf
Integer Programming PPt.ernxzamnbmbmspdfInteger Programming PPt.ernxzamnbmbmspdf
Integer Programming PPt.ernxzamnbmbmspdfRaja Manyam
 
Numerical analysis simplex method 1
Numerical analysis  simplex method 1Numerical analysis  simplex method 1
Numerical analysis simplex method 1SHAMJITH KM
 

Ähnlich wie Ap for b.tech. (mechanical) Assignment Problem (20)

dynamic programming complete by Mumtaz Ali (03154103173)
dynamic programming complete by Mumtaz Ali (03154103173)dynamic programming complete by Mumtaz Ali (03154103173)
dynamic programming complete by Mumtaz Ali (03154103173)
 
04-Unit Four - OR.pptx
04-Unit Four - OR.pptx04-Unit Four - OR.pptx
04-Unit Four - OR.pptx
 
Lp graphical and simplexx892
Lp graphical and simplexx892Lp graphical and simplexx892
Lp graphical and simplexx892
 
Assignment
AssignmentAssignment
Assignment
 
Linear Programing.pptx
Linear Programing.pptxLinear Programing.pptx
Linear Programing.pptx
 
Linear programming manzoor nabi
Linear programming  manzoor nabiLinear programming  manzoor nabi
Linear programming manzoor nabi
 
Insider mathematical
Insider   mathematicalInsider   mathematical
Insider mathematical
 
Daa chapter 3
Daa chapter 3Daa chapter 3
Daa chapter 3
 
Dynamic Programming Matrix Chain Multiplication
Dynamic Programming Matrix Chain MultiplicationDynamic Programming Matrix Chain Multiplication
Dynamic Programming Matrix Chain Multiplication
 
Backtracking & branch and bound
Backtracking & branch and boundBacktracking & branch and bound
Backtracking & branch and bound
 
MFCS2-Module1.pptx
MFCS2-Module1.pptxMFCS2-Module1.pptx
MFCS2-Module1.pptx
 
Decision Science.pdf
Decision Science.pdfDecision Science.pdf
Decision Science.pdf
 
Assignment model
Assignment modelAssignment model
Assignment model
 
Integer Linear Programming
Integer Linear ProgrammingInteger Linear Programming
Integer Linear Programming
 
Operations Research Problem
Operations Research  ProblemOperations Research  Problem
Operations Research Problem
 
2.ppt
2.ppt2.ppt
2.ppt
 
LPP, Duality and Game Theory
LPP, Duality and Game TheoryLPP, Duality and Game Theory
LPP, Duality and Game Theory
 
Optimization Techniques.pdf
Optimization Techniques.pdfOptimization Techniques.pdf
Optimization Techniques.pdf
 
Integer Programming PPt.ernxzamnbmbmspdf
Integer Programming PPt.ernxzamnbmbmspdfInteger Programming PPt.ernxzamnbmbmspdf
Integer Programming PPt.ernxzamnbmbmspdf
 
Numerical analysis simplex method 1
Numerical analysis  simplex method 1Numerical analysis  simplex method 1
Numerical analysis simplex method 1
 

Kürzlich hochgeladen

The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 

Kürzlich hochgeladen (20)

The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 

Ap for b.tech. (mechanical) Assignment Problem

  • 1. • Methods to solve LPP : 1. Graphical Method - for only two variables. 2. Simplex Method - Universal method. 3. Assignment Method - Special method. 4. Transportation Method - Special method. Note : Methods (2), (3) and (4) are iterative methods.
  • 3. • Assignment Problems and • Methods to solve such problems
  • 4. C11 C12 . . C1n C21 C22 . . C2n . . . . . . . . . . Cm1 . . . Cmn Jobs (Activities) 1 2 . . n 1 2 . . m Persons(Resources) CasesCases • m = n • m ≠ n • Cij • Pij • Cij = Cost associated with assigning ith resource to jth activity Assignment ProblemAssignment Problem
  • 5. A. Balanced Minimization → m = n with Cij B. Unbalanced Minimization →m ≠ n with Cij C. Balanced Maximization → m = n with Pij D. Unbalanced Maximization →m ≠ n with Pij Categories of Assignment ProblemsCategories of Assignment Problems
  • 6. C11 C12 . . C1n C21 C22 . . C2n . . . . . . . . . . Cn1 . . . Cnn Jobs (Activities) 1 2 . . n 1 2 . . n Persons(Resources) • Xij = assignment of ith resource to jth activity • Assignments are made on one to one basis A.A. Balanced Minimization ProblemBalanced Minimization Problem
  • 7. Formulation of Assignment Problem as LPP 1 1 . n n i j Min Z Cij Xij = = = ∑∑ 1 / 1 ( ) n j s t Xij for all i I = = −∑ 1 1 ( ) n i Xij for all j II = = −∑ 0 1 & .All Xij or for all i j=
  • 8. Methods to solve Assignment ProblemsMethods to solve Assignment Problems 4. Hungarian Method 1. Enumeration Method 2. Integer Programming Method 3. Transportation Method
  • 9. C11 C12 C21 C22 1 2 1 2 1.1. Enumeration MethodEnumeration Method • For n x n Problem---- n! 2! (=2)• No. of Possible solutions = • P1J1 , P2J2 OR P1J2 , P2J1 • For 4 x 4 Problem---- 4! = 24 • For 5 x 5 Problem----5! = 120
  • 10. • All Xij = 0 or 1 → 0-1 Integer programming. 2.2. Integer Programming MethodInteger Programming Method • Difficult to solve manually. • For n x n Problem → Variables = n x n. Constraints = n+n = 2n • For 5 x 5 Problem → Variables = 25 Constraints = 10
  • 11. • Formulate the problem in Transportation Problem format. 3.3. Transportation MethodTransportation Method C11 C12 . . C1n C21 C22 . . C2n . . . . . . . . . . Cn1 . . . Cnn 1 2 . . n 1 2 . . n 1 1 . 1 1 1 . . 1
  • 12. 4.4. Hungarian MethodHungarian Method 1. Row Deduction 2. Column Deduction 3. Assign zeros-If all assignments are over, Then STOP Else Go To Step 4 4. Adopt Tick Marking Procedure 5. Modify Cij and Go To Step 3 (Mr. D. Konig - A Hungarian Mathematician) Steps :Steps :
  • 13. 1 2 3 1 2 3 Prob. 1Prob. 1 Balanced Minimization ProblemBalanced Minimization Problem Perform Row DeductionPerform Row Deduction 19 28 31 11 17 16 12 15 13
  • 14. 0 9 12 0 6 5 0 3 1 1 2 3 1 2 3 Row DeductionRow Deduction • Perform Column DeductionPerform Column Deduction
  • 15. 0 6 11 0 3 4 0 0 0 1 2 3 1 2 3 Column DeductionColumn Deduction • Minimum uncrossed no = 3. • Modify Numbers Assign ZerosAssign Zeros Adopt Tick MarkingAdopt Tick Marking
  • 16. 0 3 8 0 0 1 3 0 0 1 2 3 1 2 3 • Hence optimal solution is P1J1, P2J2, P3J3 giving Z = 19+17+13 = 49
  • 17. Procedure of Assigning ZerosProcedure of Assigning Zeros Steps to be followed, after getting at-least one zero in each row & each column. 1. Start with 1st row. If there is only one uncrossed, unassigned zero, assign it & cross other zeros in respective column (of assigned zero), if they exits, else go to next row. Repeat this for next all other rows. 2. If still uncrossed, unassigned zeros are available, start with first column. If there is only one uncrossed, unassigned zero, assign it and cross other zeros in respective row of assigned zero, if they exit, else go to next column. Repeat this for next all other columns. 3. Repeat 1 & 2 until single uncrossed, unassigned zeros are available, while going through rows & columns. 4. If still multiple uncrossed, unassigned zeros are available while going through rows & columns, it indicates that multiple (alternative) optimal solutions are possible. Assign any one remaining uncrossed, unassigned zero & cross remaining zeros in respective row & column of assigned zero. Then go to 1. 5. If required assignments are completed then STOP, else perform “Tick Marking Procedure”. Modify numbers & go to 1.
  • 18. Tick marking ProcedureTick marking Procedure (To draw minimum number of lines through zeros.) 1. Tick marks row/rows where there is no assigned zero. 2. Tick mark column/columns w.r.t. crossed zero/zeros in marked row/rows. 3. Tick mark row/rows w.r.t. assigned zero in marked column/columns. 4. Go to to step 2 and repeat the procedure until no zero is available for tick marking. Then 5. Draw lines through unmarked rows and marked columns (Check no. of lines = No. of assigned zeros)
  • 19. Tick marking ProcedureTick marking Procedure (Continue)(Continue) How to Modify numbers ? Find minimum number out of uncrossed numbers. 1. Add this minimum number to crossings. 2. Deduct this number from all uncrossed numbers one by one. 3. Keep crossed numbers, on horizontal & vertical lines, except on crossing, same
  • 20. C11 C12 C13 C21 C22 C23 . . . . . . C51 C52 C53 Jobs (Activities) 1 2 3 1 2 3 4 5 Persons(Resources) • D1 and D2 Dummy Jobs are to be introduced to balance the problem B. Unbalanced Minimization ProblemB. Unbalanced Minimization Problem
  • 21. C11 C12 C13 0 0 C21 C22 C23 0 0 . . . 0 0 . . . 0 0 C51 C52 C53 0 0 Jobs (Activities) 1 2 3 D1 D2 1 2 3 4 5 Persons(Resources) • D1 and D2 are Dummy Jobs : Cij = 0
  • 22. Prob. 2 The personnel manager of ABC Company wants to assign Mr. X, Mr. Y and Mr. Z to regional offices. But the firm also has an opening in its Chennai office and would send one of the three to that branch, if it were more economical than a move to Delhi, Mumbai or Kolkata. It will cost Rs. 2,000 to relocate Mr. X to Chennai, Rs. 1,600 to reallocate Mr. Y there, and Rs. 3,000 to move Mr. Z. What is the optimal assignment of personnel to offices ? Office Delhi Mumbai Kolkata Personnel Mr. X 1,600 2,200 2,400 Mr. Y 1,000 3,200 2,600 Mr. Z 1,000 2,000 4,600
  • 23. UBMin (AP), after adding Chennai : Delhi Mumbai Kolkata Chennai Mr. X 1,600 2,200 2,400 2,000 Mr. Y 1,000 3,200 2,600 1,600 Mr. Z 1,000 2,000 4,600 3,000
  • 24. BMin (AP), after adding Dummy Row : Delhi Mumbai Kolkata Chennai Mr. X 1,600 2,200 2,400 2,000 Mr. Y 1,000 3,200 2,600 1,600 Mr. Z 1,000 2,000 4,600 3,000 Dummy 0 0 0 0
  • 25. After Row Deduction : D M K Ch X 0 600 800 400 Y 0 2,200 1,600 600 Z 0 1,000 3,600 2,000 Dm 0 0 0 0
  • 26. Modified Matrix and Assignment : D M K Ch X 0 200 400 0 Y 0 1,800 1,200 200 Z 0 600 3,200 1,600 Dm 0 0 0 0
  • 27. Modified Matrix and Assignment : D M K Ch X 200 200 400 0 Y 0 1,600 1,000 0 Z 0 400 3,000 1,400 Dm 400 0 0 0
  • 28. Modified Matrix and Assignment : D M K Ch X 200 0 200 0 Y 0 1,400 800 0 Z 0 200 2,800 1,400 Dm 6 00 0 0 200 Hence, Optimal Solution is : XM, YCh, ZD Giving Z = 2,200 + 1,600 + 1,000 = 4,800 Hence, it is economical to move Y to Chennai
  • 29. Jobs (Activities) 1 2 3 4 5 1 2 3 4 5 Persons(Resources) • Convert Profit Matrix into Relative Cost Matrix C. Balanced Maximization ProblemC. Balanced Maximization Problem Pij
  • 30. • How to Convert Profit Matrix into Relative Cost Matrix ? 3. (Pij)max - Pij = RCij 1. (Pij) (-1) = RCij 2. 1/Pij = RCij
  • 31. Prob. 3 Balanced Maximization Problem :Prob. 3 Balanced Maximization Problem : C1 C2 C3 C4 P1 60 100 90 95 P2 93 60 70 60 P3 75 85 60 90 P4 95 89 65 60
  • 32. Balanced RC Matrix :Balanced RC Matrix : C1 C2 C3 C4 P1 40 0 10 5 P2 7 40 30 40 P3 25 15 40 10 P4 5 11 35 40
  • 33. After Row Deduction :After Row Deduction : C1 C2 C3 C4 P1 40 0 10 5 P2 0 33 23 33 P3 15 5 30 0 P4 0 6 30 35
  • 34. After Column Deduction :After Column Deduction : C1 C2 C3 C4 P1 40 0 0 5 P2 0 33 13 33 P3 15 5 20 0 P4 0 6 20 35
  • 35. Assigning :Assigning : C1 C2 C3 C4 P1 40 0 0 5 P2 0 33 13 33 P3 15 5 20 0 P4 0 6 20 35
  • 36. Modified Matrix and Assigning :Modified Matrix and Assigning : C1 C2 C3 C4 P1 46 0 0 5 P2 0 27 7 27 P3 21 5 20 0 P4 0 0 14 29 Hence, Optimal Solution is : P1C3, P2C1, P3C4, P4C2 Giving Z = 90 + 93 + 90 + 89 = 362
  • 37. Jobs (Activities) 1 2 3 1 2 3 4 5 Persons(Resources) • Convert Unbalanced Profit Matrix into Unbalanced Relative Cost Matrix D. Unbalanced Maximization ProblemD. Unbalanced Maximization Problem Pij • Then Balance the matrix and solve
  • 38. Prob. 4 Unbalanced Maximization Problem :Prob. 4 Unbalanced Maximization Problem : J1 J2 J3 J4 P1 62 78 50 101 P2 71 84 61 73 P3 87 111 92 71
  • 39. Unbalanced RC Matrix :Unbalanced RC Matrix : J1 J2 J3 J4 P1 49 33 61 10 P2 40 27 50 38 P3 24 0 19 40
  • 40. Balanced RC Matrix :Balanced RC Matrix : J1 J2 J3 J4 P1 49 33 61 10 P2 40 27 50 38 P3 24 0 19 40 D 0 0 0 0
  • 41. After Row Deduction :After Row Deduction : J1 J2 J3 J4 P1 39 23 51 0 P2 13 0 23 11 P3 24 0 19 40 D 0 0 0 0
  • 42. Assigning :Assigning : J1 J2 J3 J4 P1 39 23 51 0 P2 13 0 23 11 P3 24 0 19 40 D 0 0 0 0
  • 43. Modified Matrix and Assigning :Modified Matrix and Assigning : J1 J2 J3 J4 P1 39 34 51 0 P2 2 0 12 0 P3 13 0 8 29 D 0 11 0 0
  • 44. Modified Matrix and Assigning :Modified Matrix and Assigning : J1 J2 J3 J4 P1 37 34 49 0 P2 0 0 10 0 P3 11 0 6 29 D 0 13 0 2 Hence, Optimal Solution is : P1J4, P2J1, P3J2 Giving Z = 101 + 71 + 111 = 283
  • 45. 10 5 13 15 16 3 9 18 13 6 10 7 3 2 2 7 11 9 7 12 7 9 10 4 12 Jobs (Activities) 1 2 3 4 5 1 2 3 4 5 Persons(Resources)Prob. 5 Practice Problem (Minimization)Prob. 5 Practice Problem (Minimization)
  • 46. 5 0 8 10 11 0 6 15 10 3 8 5 1 0 0 0 4 2 0 5 3 5 6 0 8 Jobs (Activities) 1 2 3 4 5 1 2 3 4 5 Persons(Resources)
  • 47. 5 0 7 10 11 0 6 14 10 3 8 5 0 0 0 0 4 1 0 5 3 5 5 0 8 Jobs (Activities) 1 2 3 4 5 1 2 3 4 5 Persons(Resources) • Minimum uncrossed Number = 1.
  • 48. 6 0 7 11 11 0 5 13 10 2 9 5 0 1 0 0 3 0 0 4 3 4 4 0 7 Jobs (Activities) 1 2 3 4 5 1 2 3 4 5 Persons(Resources) • Hence optimal solution is P1J2, P2J1, P3J5, P4J3, P5J4 giving Z = 5+3+2+9+4 = 23
  • 49. 4 7 5 6 − 8 7 4 3 − 5 3 6 6 4 2 Jobs (Activities) 1 2 3 4 1 2 3 4 Persons(Resources) Prob. 6Prob. 6 Problem for Alternative / Multiple Optimal Solutions :
  • 50. 0 3 1 2 Μ 4 3 0 0 Μ 2 0 4 4 2 0 Jobs (Activities) 1 2 3 4 1 2 3 4 Persons(Resources) After Row deduction 
  • 51. 0 0 0 2 Μ 1 2 0 0 Μ 1 0 4 1 1 0 Jobs (Activities) 1 2 3 4 1 2 3 4 Persons(Resources) After Column deduction  Now modified matrix will be :
  • 52. 0 0 0 3 Μ 0 1 0 0 Μ 1 1 3 0 0 0 Jobs (Activities) 1 2 3 4 1 2 3 4 Persons(Resources) • Hence, this is a case of alternative optimal solutions. • Assign any one remaining zero and cross existing zeros in respective row and column, then apply assigning procedure. • Hence, one of the optimal solutions is P1J2, P2J4, P3J1, P4J3 giving Z = 7+4+3+4 = 18
  • 53. 0 0 0 3 Μ 0 1 0 0 Μ 1 1 3 0 0 0 Jobs (Activities) 1 2 3 4 1 2 3 4 Persons(Resources) • Hence, another optimal solution is P1J3, P2J2, P3J1, P4J4 giving Z = 5+8+3+2 = 18 To get another optimal solution, assign another remaining zero. P1J3 can not be assigned, as it is already assigned before.
  • 54. . Restriction in Assignment. e.g. Assignment of P3 to J4 is not possible. Then C34 = M (Big Number) . Alternative Optimal Solution Possibility -Already considered. . Particular assignment is prefixed. e.g. If P3 & J4 prefixed Then Row3 & Column4 are deleted. Typical Cases in Assignment ProblemsTypical Cases in Assignment Problems
  • 56. Que. Answer each of the following questions in brief. [ 1 ] What are the methods to solve Assignment Problems ? Ans. : (1) Enumeration Method (2) Integer Programming Method (3) Transportation Method (4) Hungarian Method [ 2 ] How can you identify a function as Linear ? Ans. : Power of each variable = only 1. No multiplication of variables.
  • 57. [ 3 ] What is the purpose of “Tick Marking Procedure” in a method of solving Assignment Problems ? Ans. : The purpose of “Tick Marking” procedure is to draw minimum number of lines covering zeros. [ 4 ] What is significance of name “Hungarian Method” ? Ans. : It is because of D. Konig of Hungary.
  • 58. [ 5 ] Following is Minimization Assignment Problem. (i) Write objective equation. (ii) Write all possible constraints. (iii) State “Non-Negativity” conditions for this problem. (iv) State Optimal Solution. Is it unique optimal ? X Y A 3 2 B 4 5 Ans. : ( i ) Min Z = 3x11 + 2x12 + 4x21 + 5x22 ( ii ) x11 + x12 = 1 x21 + x22 = 1 x11 + x21 = 1 x12 + x22 = 1 ( iii ) All xij = 0 or 1 OR x11, x12, x21, x22 = 0 or 1 ( iv ) Optimal solution is AY, BX giving Z = 6 (unique)
  • 59. [ 6 ] Get Optimal Solution of following Minimization Assignment Problem. How many Optimal Solutions are existing for this problem ? X Y Z A 3 2 2 B 6 5 5 C 6 1 1 X Y Z A 3 2 2 B 6 5 5 C 6 1 1 X Y Z A 1 0 0 B 1 0 0 C 5 0 0
  • 60. X Y Z A 0 0 0 B 0 0 0 C 4 0 0 X Y Z A 0 0 0 B 0 0 0 C 4 0 0 X Y Z A 0 0 0 B 0 0 0 C 4 0 0 X Y Z A 0 0 0 B 0 0 0 C 4 0 0 There are 4 Optimal Solutions.
  • 61. RecapitulateRecapitulate • Methods to solve Assignment Problem • Hungarian Method • Typical cases of Assignment Problems
  • 63. [ 1 ] Answer the following in brief : ( a ) What is the purpose of “Tick Marking” procedure in solving Assignment Problem ? ( b ) What is significance of name “Hungarian” method ?
  • 64. [ 2 ] For the following Minimization Assignment Problem, answer the question given below. J1 J2 J3 P1 2 4 3 P2 5 6 6 ( a ) Formulate this problem as LPP. ( b ) Get all possible Optimal Solutions.
  • 65. [ 3 ] ( i ) State possible methods of solving “Assignment Problem”. ( ii ) State possible methods of converting “Profit Matrix” into “Relative Cost Matrix”. [ 4 ] Formulate following Assignment Problem as : ( i ) LPP ( ii ) Transportation Problem P Q A 2 5 B 6 4
  • 66. [ 5 ] Find optimal assignments for following “Minimization Assignment Problem”. J1 J2 J3 P1 −10 −10 −12 P2 −18 −6 −14 P3 −6 −2 −2
  • 67. [ 6 ] Average time taken by operators on 4 old machines and a new machine are tabulated below. Management is considering to replace one of the old machines by a new machine. Is it advantageous to replace new machine with an old machine ? Why ? M1 M2 M3 M4 New O1 10 12 8 10 11 O2 9 10 8 7 10 O3 8 7 8 8 8 O4 12 13 14 14 11
  • 68. [ 7 ] Consider the problem of assigning four operators to four machines. The assignment costs are given in Rupees. Operator 1 cannot be assigned to machine 3. Also operator 3 cannot be assigned to machine 4. Find the optimal assignment. M1 M2 M3 M4 1 5 5 − 2 2 7 4 2 3 3 9 3 5 − 4 7 2 6 7 If 5th Machine is made available and the respective costs to the four operators are Rs. 2, 1, 2 and 8. Find whether it is economical to replace any of the four existing machines. If so, which ?
  • 69. [ 8 ] There are four batsman P, Q, R, & S. The batsman are to be selected for first three positions P1, P2 and P3. The expected score by these batsman at three different positions are given as below. Decide the optimal batsman for these three positions. P1 P2 P3 P 42 16 27 Q 48 40 25 R 50 18 36 S 58 38 60
  • 70. [ 9 ] J1 J2 J3 J4 P1 20 22 28 15 P2 16 20 12 13 P3 19 23 14 25 P4 10 16 12 10 Minimization Problem :
  • 71. [ 10 ] J1 J2 J3 J4 P1 10 24 30 15 P2 16 22 28 12 P3 12 20 32 10 P4 9 26 34 16 Minimization Problem :
  • 72. Thank youThank you For any Query or suggestion : Contact : Dr. D. B. Naik Professor & Head, Training & Placement (T&P) S. V. National Institute of Technology (SVNIT), Ichchhanath, Surat – 395 007 (Gujarat) INDIA. Email ID : dbnaik@gmail.com dbnaik@svnit.ac.in dbnaik_svr@yahoo.com Phone No. : 0261-2201540 (D), 2255225 (O)