SlideShare ist ein Scribd-Unternehmen logo
1 von 61
Downloaden Sie, um offline zu lesen
Geotechnical Instrumentation and Monitoring for the New
MetroRail City Project, Perth, Western Australia

P.G. McGough
Instrumentation and Monitoring Manager, Leighton Kumagai Joint Venture, Perth

M. Williams
Special Contracts Manager, Leighton Kumagai Joint Venture, Perth




ABSTRACT: The New MetroRail Project involved a significant number of deep excavations within
varying soil types, as well as tunnelling under live railways and heritage buildings. From the onset of
the project, significant effort and planning was put into geotechnical instrumentation and monitoring,
with over 5200 instruments being installed during the life of the project over a length of less than 3
kilometres. This paper details the initial planning and management process, as well as the contractual
requirements, which formed the basis for more instrumentation as the project progressed. Specific
project requirements such as compensation grouting under buildings and tunnelling under live
railways at depths of less than one tunnel diameter required specific planning measures and additional
detailed monitoring which is discussed herein.

A large number of automated instruments were used to ensure cost effective and safe collection of
data. The types of instruments used on the project are discussed in detail with respect to their
applicability, accuracy, reliability, repeatability and cost effectiveness. Examples are presented to
illustrate the above points as well as highlight operational issues learnt. The process of data collection,
management and reporting is also discussed.

With construction taking place in a variety of ground conditions ranging from very soft alluvial silts
and reclaimed fill to medium dense alluvial sands and stiff clays a number of distinct response issues
were observed by the monitoring. The lessons learnt from three years of continuous monitoring of
ground and building movements, groundwater movements, and instrument vibrations are discussed
with respect to this project and future projects in Perth within similar geotechnical environments.
Detailed examples of ground, sheet pile and wall movements and strut loads with respect to excavation
design are presented, along with examples of the exceptionally low volume loss from TBM operation,
and resulting building responses to ground movement. An empirical method for predicting ground
settlement due to sheet pile extraction is also presented. Examples of ground vibrations induced by
sheet piling, construction activities and tunnelling are presented.
1    INTRODUCTION

The minimum required instrumentation for the project was specified in the contract documents
referred to as the Scope of Works and Technical Criteria (SWTC), which became the guiding
document for tendering purposes and initial estimation. To address the definition of purpose for
monitoring, a Building Protection Management Plan was created by Leighton Kumagai Joint Venture
(LKJV). The overall purpose of LKJV’s approach to instrumentation, monitoring and building
protection was summarised in the Management Plan as follows:
    “ to identify the controls to be implemented to ensure personal safety (construction and public),
    and verify design predictions to prevent damage to buildings, services and civil infrastructure as a
    result of LKJV construction activities.” [From LKJV’s “Building Protection Management Plan”]
Appropriate management methods were also created and put in place to handle the possible influences
of construction activities due to the soft Perth soils.     This included selecting “fit-for-purpose”
instrumentation that was able to be monitored safely, whilst still providing accurate and timely
feedback about construction progress. In addition to working in, with and around the construction
personnel, a key criteria was to minimise disruption to pedestrians, traffic flows, and retail business in
the CBD.


2    INITIAL PLANNING AND MANAGEMENT PROCESS

2.1 Overview
The need for protection of workers’ safety, property and the environment was foreseen by the Public
Transport Authority (PTA) in their tender scope document “Scope of Works and Technical Criteria”
(SWTC). These activities included:
    •    Monitoring the performance of deep excavations with respect to design;
    •    The need for controls to minimise the potential for damage to buildings, services, roads, rails
         and bridges from construction activities such as:
           - demolition;
           - sheet piling, bored piling or diaphragm wall construction;
           - tunnelling;
           - ground improvement activities (jet grouting, soil mixing, compensation grouting);
           - consolidation from groundwater drawdown.
    •    Determining a series of baseline condition surveys to objectively determine any damage;
    •    A process for receiving automated alerts if movement criteria were exceeded.

On consideration of the complexity of the final monitoring program, LKJV added the following
additional elements to those listed in the SWTC:
    •    An overall management process to coordinate the activities of design, construction, survey
         and monitoring crews, with geotechnical and management reviews. A single document
         (Building Protection Management Plan) was created to bring together the requirements of:
            - Geotechnical Interpretive Report;
            - Ground Settlement, Building Protection and Repair Plan, incorporating Property
               Condition Surveys and Building Protection Assessments;
            - Instrumentation and Monitoring Plan;
            - Various area-specific Method Statements and Safe Work Methods (i.e., JSA’s);
            - Feedback from the actual results generated.
    •    Visual approach to interpretation of monitoring data to allow for quick interpretation by a
         range of personnel;
•    Innovative instruments and monitoring methods such as wireless electrolevel beams and
         terrestrial photogrammetry driven by safety or minimising disruption to the public;
    •    Emergency Response procedures as part of the overall risk management plan to cover the
         event of a massive failure.

Figure 1 outlines the key elements of the building protection and monitoring process.


                                                 Geotechnical investigations



                                             Condition surveys in
                                              zone of influence

                                                                                      Detailed
                                                                                      design
                                              Assess the need for
                                              building protection



                            Install instrumentation             Protection of key
                                and monitoring                     structures       Construction
                                                                                        and
                                                                                     Tunnelling
                                                                                       works
                                                  Investigate
                                                  exceptions



                                              Post construction
                                              surveys and repair




                   Figure 1. The LKJV Building Protection and Monitoring Process

2.2 Damage criteria
After extensive preliminary geotechnical work had been undertaken, modelling of the potential zone
of influence of the project works was performed. This determined the width of the potential
subsidence zone, based on the predicted design level of induced settlement and TBM face loss.

A key point to note is that although the Ground Settlement, Building Protection and Repair Plan
determines a zone of influence based on a designed level of settlement caused by the excavations and
the TBM, the actual performance of the TBM was expected to be considerably better than this (i.e.,
less settlement). This was in demonstrated by the actual TBM operations, where up to 20mm was
designed for along William Street, but only around 3-5 mm was observed. The performance of the
TBM with respect to design is discussed in more detail later in this paper.

Once the potential zone of influence was determined, a visual Property Condition Report was prepared
for each of the following structures along or adjacent to the route of the project:
    •    88 buildings, from single storey to BankWest tower;
    •    5 bridges and footbridges, including the heritage listed Horseshoe Bridge;
    •    Sections of roads and associated furniture along and adjacent to William and Roe Streets;
    •    Around 30 water and sewer services using a CCTV camera.

The design level settlements of the TBM had the potential to cause minor damage to some buildings
along the route. An engineering assessment was made to determine whether this potential damage
would exceed the limits specified in the PTA’s SWTC. The damage criteria was based on the work of
Boscardin and Cording, 1989, which is reproduced as Table 1.
Table 1 - Building Damage Classification

                                                                                         Approx.
                    Description of                                                                       Max
        Risk                         Description of Typical Damage and Likely            Crack
                    Degree      of                                                                       Tensile
        Category                     Forms of Repair                                     width
                    Damage                                                                               Strain [%]
                                                                                         [mm]

                                                                                         Less     than   Less    than
            0       Negligible       Hairline Cracks
                                                                                         0.1             0.05

                                     Fine cracks easily treated during normal
                                     redecoration. Damage generally restricted to
                                                                                                         0.05       to
            1       Very Slight      internal wall finishes Perhaps isolated slight      0.1 to 1
                                                                                                         0.075
                                     fracture in building. Cracks in exterior
                                     brickwork visible upon close inspection.

                                     Cracks easily filled. Redecoration probably
                                     required. Recurrent cracks can be masked by
                                     suitable linings. Exterior cracks visible: some                     0.075      to
            2       Slight                                                               1 to 5
                                     repointing may be required for weather-                             0.15
                                     tightness. Doors and windows may stick
                                     slightly.

                                     Cracks may require cutting out and patching.
                                                                                         5 to 15 or a
                                     Tuck pointing and possibly replacement of a
                                                                                         number of
                                     small amount of exterior brickwork may be
            3       Moderate                                                             cracks          0.15 to 0.3
                                     required. Doors and windows sticking. Services
                                                                                         greater
                                     may be interrupted. Weathertightness often
                                                                                         than 3
                                     impaired.

                                     Extensive repair involving removal and
                                                                                         15 to 25
                                     replacement of sections of walls, especially over
                                                                                         but    also
                                     doors and windows required. Windows and door                        Greater
            4       Severe                                                               depends on
                                     frames distorted. Floor slopes noticeably. Walls                    than 0.3
                                                                                         number of
                                     lean or bulge noticeably. Some loss of bearing in
                                                                                         cracks
                                     beams. Services disrupted

                                                                                         Usually
                                     Major repair required involving partial or          greater
                                     complete reconstruction. Beams lose bearing,        than 25 but     Greater
            5       Very Severe
                                     walls lean badly and require shoring. Windows       depends on      than 0.3
                                     broken by distortion. Danger of instability.        number of
                                                                                         cracks




For each property, a Building Protection Assessment was undertaken by Airey Taylor Consulting that
considered the predicted maximum damage from the Ground Settlement Plan and the cumulative
variation from the initial damage category assessed in the Property Condition Report. The result was
the maximum damage category that could be expected. Building protection was required if the
“incremental” damage exceeded the following limits:
    •    For heritage structures – very slight (up to 1mm crack width);
    •    For other structures – slight (up to 5mm crack width).

In addition to compliance with the PTA’s SWTC, a formal Instrumentation and Monitoring Plan was
produced to detail the network of devices which would provide feedback for the following:
    •    Construction management to ensure the safety of deep excavations is maintained;
    •    TBM operators and management to control the various TBM operating parameters;
    •    Geotechnical Manager to ensure the project’s impact on the surrounding natural and built
         environments is minimised and within stated limits.
3    KEY AREAS OF MANAGEMENT FOCUS

In addition to the minimum contractually-specified arrays, there were a number of key construction
activities that needed specific management requirements:
    •   Protection of key structures: A number of structures, buildings and services needed
        special treatment due to their calculated risk category. All other structures were monitored
        according to the Instrumentation and Monitoring Plan to confirm the validity of the design
        assumptions.
    • Incident and emergency management: With the extensive array of monitoring devices,
        LKJV needed a documented process to investigate any devices that showed movement “out
        of tolerance”, plus planning for major high risk events.
These two areas are discussed in more detail in the following sections.

3.1 Protection of key structures
The main structures that needed unique building protection solutions were:
    •    Underpinning of the Wellington Building
    •    Removal of the Mitchell Façade
    •    Protection of the Horseshoe Bridge arches
    •    Compensation grouting of the buildings under which the TBM passed
    •    Perth Rail Yard, footbridge and station platforms (where tunnelling under the live railways
         was at depths of less than one tunnel diameter)
    •    Claisebrook Sewer.
These are each discussed briefly below.

3.1.1   Underpinning of the Wellington Building
The heritage-listed Wellington Building is a “classic piece of turn of the 19th century corner
architecture” under which the new station had to be constructed. As part of the permanent station
structure, the Wellington Building had an array of tubular steel and grout micropiles drilled from
within the basement. A concrete slab was then poured in the basement but not connected to the
micropiles. A series of flat jacks were placed between the top of the micropiles and the base of the
concrete slab. The slab was then clamped to the external diaphragm walls, thus forming the roof of
the new station. Excavation was then commenced in a top down method under the Wellington
Building, with the former footings removed with the first level of excavation, and the weight of the
slab and building supported by the micropiles and the diaphragm wall. The excavation was then
completed to base slab level and the tubular steel piles were then cut, and tied into the base slab of the
station providing an uplift anchor. The weight of the building then sat on the roof slab of the new
William Street Underground Station. (WSS)

To monitor the impact of the construction works, around 40 optical prisms were placed around the
building and read from robotic theodolites on the Advertising Tower at Perth Station, and the Post
Office Building in Forrest Place. This allowed for remote monitoring and interpretation of movements
across the building. Being heritage listed, the damage criteria were stricter for the Wellington
Building, which meant a much higher density of micropiles were necessary than would be required on
a purely structural basis. Additional manual monitoring such as roof and building levelling, tilt
monitoring and retro target surveying was undertaken to enhance the automated monitoring.
Figure 2 - Wellington Building, and Excavation of Exterior Brick Wall of Building Prior to Tieing
                         Basement Slab and Capping Beam to Diaphragm Wall

3.1.2   Removal of the Mitchell Façade
Only the façade of the Mitchell Building was heritage listed, but it was located very close to the
diaphragm wall alignment for the station. This combined with safety concerns over the stability of the
façade’s render meant that LKJV sought permission from the Heritage Council to remove the façade
to ensure its protection. Permission was granted and the façade was encased in a steel frame and cut
into pieces to be stored off site, as illustrated in Figure 3.




               Figure 3 - Mitchell’s Building Prior to, and during breaking up into pieces

3.1.3   Protection of the Horseshoe Bridge
LKJV’s first consideration for the Horseshoe Bridge was full underpinning through installation of jet
grout columns under the existing footings. However after more detailed analysis of the structure, the
potential for differential movement across the structure was still highly probable. It was determined
that due to the flexible nature of the steel-framed structure there would be no structural damage, but
the façade heritage features (cement render arches) were susceptible to movement and needed to be
propped with timber arches to prevent damage.

3.1.4   Compensation grouting of the “Gold Group”
The “Gold Group” buildings (named for their importance to the project) comprise the following
buildings facing William Street between Hay and Murray Street Malls: Friendlies Chemist, HBF,
Hungry Jack’s/KFC, Walsh’s Building (McDonalds, and other retail tenancies).

The route of the TBM passed either partially or wholly under these buildings, and LKJV’s Building
Protection Assessment indicated the need for protection, with a potential design movement of 20mm.
Due to various space and access constraints, LKJV determined the best option was to work
collaboratively with Keller Ground Engineering and implement a TAM compensation grouting
system. The details of this system are described in more detail in another paper contained herein by
Nobes & Williams (2007)

3.1.5   Perth Rail Station tracks and platforms
The TBM passed twice underneath the station and the live railway, which needed to be kept running at
all times. Due to the flexibility of ballasted rail, there was no structural problem should TBM
settlements reach the design limits, but such settlements may cause two operational issues. Firstly, if
tilting of the platform edge increased relative to the track there would be insufficient clearance for the
train, and secondly, if excessive cross cant was to occur it may lead to a derailment.

Due to the success of the first stage of tunnelling up William Street (maximum 5mm settlement), it
was determined that an observational approach be taken in preference to preventative measures, with
defined management methods and actions. Elements of this observational method included:
    •    Automatic electrolevel beams on the rail tracks;
    •    Automatic tilt meters on the platform faces;
    •    High density of surface, building and rail settlement points;
    •    24 hour/7 day week survey, with rail safety presence, and direct ring-by-ring contact with the
         tunnel shift engineer;
    •    Specific management measures including:
         - A purpose-written Method Statement covering survey, interpretation, tunnel operations
            and rail safety;
         - Daily coordination meetings with all parties (management, survey, geotechnical, tunnel,
            rail and client);
         - Web-based access to all monitoring information for all teams;
         - Emergency scenario workshops.

The close contact with the TBM crew allowed for parameters to be changed on a ring by ring basis on
the survey and automatic results presented. The result was that during the passage of the TBM, the
maximum final rail movement was limited to less than 10mm.

3.1.6   Claisebrook Sewer
With the footings of the century old, brick lined, Claisebrook Sewer potentially lying within 800mm
of tunnel alignment, protective measures were required. After thorough discussions with Water
Corporation, it was decided to re-line the inside of the sewer with new plastic piping. In addition to
this, LKJV determined that since a subsidence risk was still present during the passage of the TBM
due to fragile nature of the sewer, LKJV also temporarily “over-pumped” the sewer when the TBM
was within a zone of influence.

3.2 Incident and emergency management

3.2.1   Incident investigations
All instruments had the following three alert levels determined in the Ground Settlement and Building
Protection Plan:

    •    Trigger, set at say, 80% of the “design” level as an early warning;
    •    Design, equal to the predicted movement level;
    •    Allowable, set at say 120% of the “design” level and at which remedial action must be taken.
For all instruments, these alert levels were entered into the instrument database (GIMS). If a level was
exceeded, an SMS and email were sent to a nominated group of people to action as appropriate. When
alert levels were exceeded, a rigorous process was followed to ensure traceability of all decisions.
This process is shown in Figure 4. If the alert was not spurious, or a transient event, a more detailed
investigation was initiated to determine whether any changes to design or construction techniques
would be necessary.

    •    Monitoring frequencies were set for each instrument, and one full time person was dedicated
         to ensuring the instruments being read matched the progress of the construction works.
         During the peak months, a team of up to 19 people were dedicated to gathering, inputting,
         reviewing and investigating monitoring data:

3.2.2   Emergency management through desktop scenarios
Although the chance of an excavation or TBM failure (to a level requiring the assistance of emergency
services) was remote, as a key part of the LKJV’s risk management approach, a comprehensive
emergency management process was implemented. To test our management plan so that it was a
“live” document, we undertook a series of scenario workshops both internally and externally to LKJV.

On 1 December 2005, around 40 representatives from LKJV, Leighton Contractors, Leighton
Holdings, New MetroRail (client), Public Transport Authority (operations and infrastructure), City of
Perth, Fire & Emergency Services Authority, Police, Worksafe, Western Power, Alinta Gas, Water
Corporation, Telstra and Main Roads attended a workshop focussing on the bored tunnel section up
William Street. One of the key findings to come from the scenario workshops was that of the role of
the Hazard Management Authorities (HMAs) and how to use the existing Memoranda of
Understandings between the HMAs and the various government and private agencies.

Another workshop was held on 15 March 2006 with a similar range of external parties, but with more
attendance from railway operations personnel, which was the focus of the day. Also a number of
internal scenario sessions were held with teams from survey, geotechnical, tunnel and rail to ensure
coordination of activities and communication. We also checked that our communication protocols
were consistent with Leighton Contractors national approach to Crisis Management, and sought
feedback from Leighton Holdings on lessons learnt from recent crisis management activities (Lane
Cove Tunnel). Feedback from all sessions was used to make our procedures as user friendly as
possible. The aim was to ensure people knew what to do if something escalates from an incident to an
emergency.

A Building Access Checklist was also obtained for every property, which LKJV could use to raise an
alarm in the case of an emergency. Since LKJV’s monitoring and/or tunnelling teams will probably
be the first to know of any incident, we determined that having this information on hand was prudent.
BUILDING AND MONITORING INCIDENT FLOWCHART

 NEW METRORAIL CITY PROJECT


                             Legend                                                                               1                                                                         Point of Contact
                                                                                                                                                                                         Point of Contact (PC)
                                                                                                           Incident occurs                                                                    Primary           Secondary
    PC                Point of Contact                                                                                                                            Building Incident
                                                                                                                                                                                       Primary Contact Alternative Contact
                                                                                                                                                                                              Peter McGough Kate Stone
                                                                                                                                                                 Buiding Incident        Matt Williams     Kate Stone
    IM                I & M Manager                                                                                                                               Monitoring Incident Peter McGough Fugro
                                                                                                                                                                 Monitoring Incident     Peter McGough      Franco Roselli
    PD                Project Director                                                                            2
                                                                                                                                                                  Infrastructure /
                                                                                                                                                                 Infrastructure/Services      Mike Wallis       Area Manager
    CM                Construction Manager                                                                                                                        Services IncidentMichael Wallis
                                                                                                                                                                   Incident                                Relevant Area Manager
                                                                                3
    AM                Area Manager                                      No further action    No            Is investigation
    GM                Geotechnical Manager                             (Update register if                     required?                                                                                    Considerations
    DM                Design Manager                                        required)
                                                                                                                                                                                                 Establish whether incident is legitimate


                                                                                                                      Yes                                                                         Considerations
                                                                                                                                          Form W1114-CS-4018          1.    Notification to Area Manager
                                                                                                                   4                                                  2.    Safety of personnel
                                                                                                         Record Incident on
                                                                                                                                                                      3.    Structural integrity of building/infrastructure/service
                                                                                                         register and review
                                                                                                                                                                      4.    New occurrence or sudden change in trend
                                                                                                               details
                                                                                                                                                                      5.    Compare to existing condition, historical monitoring/reports
                    BUILDING INCIDENT RESPONSE                                                                                                                              and any background data
                                                                                                                              PC
                         CONTACT DETAILS                                                                                                                              6.    Review of recorded levels against control levels
LKJV M ANAGEMENT CONTACTS                        TELEPHONE      MOBILE                                                                                                7.    Visit to location and visual inspection
                                                                                                                  5
Rob Wallwork       Project Director              9424 5604   0411 259 451                                                                                             8.    Estimate of damage
                                                                                                        Conduct preliminary                                           9.    Record of construction work being undertaken at time of
Tony Cariss        Construction Manager          9424 5515   0419 932 132
                                                                                                           investigation                                                    incident
K. Akabane         Ass’t Construction Mgr        9424 5596   0421 404 984
Kate Stone         Community Relations Mgr       9424 5588   0422 001 037                                                    PC
                                                                                                                  6
F. Aikawa          Design Manager                9424 5563   0422 246 067
Simon Gegg         William Street Station Mgr    9424 5506   0402 898 627                                                                                              7
Paul Farris        Southern Area Manager         9424 5631   0422 001 235                    No                                                           Site assessment by GM to
                                                                                                          Is further action
                                                                                                                                                             agree and implement
Ashley Warner      Perth Rail Yard Manager       9228 4942   0421 144 469                                     required?
                                                                                                                                     Yes - URGENT                 action plan
LKJV TUNNELLING CONTACTS                         TELEPHONE      MOBILE
Henry Yamazaki     Tunnel Manager                9424 5654   0422 593 780
Frank Hannagan     Tunnel Superintendent                     0421 053 317                                                                                                        GM/PC
                                                                                                                      Yes
Frank Bonte        General Foreman                           0421 053 313                                         8
S. Shigemura       Senior Engineer               9424 5653   0422 653 574
M. Oshima          Senior Engineer               9424 5691   0413 197 300
                                                                                                           Are only minor
Andrew Shepherd    Shift Engineer – Tunnel       9424 5651   0411 659 546
                                                                                                  Yes     repairs required?                                                                            Special Response Team
T. Watanabe        Shift Engineer – Tunnel       9424 5651   0431 120 366
                                                                                                                                                                                                  Special Contracts Manager/Nominee
Tom Jones          Shift Engineer – Tunnel       9424 5639   0422 001 021
                                                                                                                                                                                                  Area Manager/Nominee
TBM Direct Line                                  9202 1485                                                              No                                                                        Geotechnical Manager/Nominee
LKJV MONITORING & GEOTECHNICAL CONTACTS          TELEPHONE      MOBILE                                                                                                                            LKJV geotechnical/monitoring rep
Peter McGough         Instrumentation and                                                                                                                                                         LKJV Subontractor respresentative
                                                 9424 5519   0421 053 351                                       9
                      Monitoring Manager                                                                                                                                                          PTA Representative
                                                                                                         Complete Incident
Oskar Sigl            Geotechnical Manager       9424 5514 0411 659 549                                   Form to initiate                Form W11140-CS-4019
                                                                                                                                                                                                  If available:
                                                    Intern’l: +65 9735 2522                               AMBER warning
                                                                                                                                                                                                  Construction Manager
Marc Woodward         Geotech Manager (alt)      9347 0000   0417 911 131                                                                                                                         Assistant Construction Manager
                                                                                                                             PC
Barry Hackett         Building Protection Eng.   9424 5511   0421 053 337                                                                                                                         Design Manager/Nominee
                                                                                                                   10
LKJV R AIL CONTACTS                               TELEPHONE     MOBILE                                                                                                                            Project Director
                                                                                                        Notify PTA (& insurer)
Peter Rosenbauer      Senior Project Eng’r - Rail 9424 5509 0402 894 801                                  immediately after
Vasil Calcan          Senior Rail Safety Officer            0421 635 8491                                  initiating amber
Peter Russell         Rail Safety Officer                    0407 193 915                                       warning
John Welch            Rail Safety Coordinator     9424 5541 0421 711 303                                                PC/GM                                                                  Investigation considerations
FUGRO CONTACTS (INSTRUMENTATION & MONITORING) TELEPHONE         MOBILE                                            11                                                                 1. Notification to Area Manager
Fugro Monitoring Phone                         9424 5617     0439 930 927                                Undertake detailed                                                          2. Safety of personnel
                                                                                                          investigation and                                                          3. Structural integrity of building, infrastructure, or
Ritchie Mulholland   Chief Monitoring Surveyor 9424 5617     0417 611 295
                                                                                                              formal risk                                                               service
                                                  Home:       9302 6256                                      assessment                                                              4. Review of predicted settlement and
Kent Wheeler         Monitoring Surveyor       9424 5584     0400 980 060                                            GM/PC/AM                                                           construction impact
PTA CONTACTS                                   TELEPHONE        MOBILE                                                                                 15                            5. Quantification of damage
                                                                                                                  12                                                                 6. Review protection works to determine
Richard Mann          Project Director         9326 2536     0419 964 209                                                                   Notify PTA (& insurer)
                                                                                                          Verify short term                                                             adequacy
Eric Hudson-Smith     Geotechnical Manager     9326 2060     0419 988 861                                                                      immediately after
                                                                                                          remedial action                                                            7. Undertake condition survey to determine extent
                                                                                                                                              initiating red alert
Jock Henderson        Special Projects Manager 9326 2093     0419 915 408                                    closed out                                                                 of damage
                                                                                                                                                           PD/CM/GM
INSURANCE CONTACTS                               TELEPHONE      MOBILE                                                      GM/AM                                                    8. Undertake additional monitoring (eg survey) to
Bob Perry          Marsh Ltd                     9421 5666   0414 307 247                                         13                                                                    quantity and monitor further damage
                                                                                                                                                                                     9. Complete risk assessment
EMERGENCY CONTACTS                               TELEPHONE    TELEPHONE
                                                                                                                                                       14                            10. Review of incident impact on both
PTA Urban Train Control                                       9326 2214                                     Can incident             No
                                                                                                                                             Initiate RED alert via                      temporary and permanent works design
Main Roads Traffic Operations Centre                          9428 2222                                     be resolved?                         Incident Form                           and construction
Fire and Emergency Services (FESA)                  000      1300 1300 39                                                                                 PD/CM/GM
        State Emergency Services (SES)                        9277 0555                                                                                                              Action considerations
                                                                                                                                                                                     1. Increase monitoring
        FESA and SES Operations Centre           9323 9333    9323 9322
                                                                                                                      Yes                                                            2. Continuous monitoring
WA Police                                           000       9222 1111                                                                                                              3. Review construction techniques and equipment
        Russell Armstrong (Incident Management                                                                     16
                                                 9222 1694     9222 1958                                   Verify long term                                                          4. Review emergency procedures
        Unit and LEMC)                                                                                                                                                               5. Review geotechnical control limits
                                                                                                           remedial action
Ambulance                                           000                                                                                                                              6. Determine whether amber warning or red alert
                                                                                                             closed out
        Bill Thompson                                        0415 428 617                                                                                                               required
                                                                                                                      GM/DM/CM
Worksafe                                         9327 8777   1800 678 198                                                                                                            7. Stop work where required
                                                                                                                                                                                     8. Determine urgency of repair work
City of Perth                                                 9461 3333                                          17
        Police Post at City of Perth                          9325 6000
        Bill Strong (LEMC)                       9461 5836   0418 947 908                                                           No
                                                                                                               Repairs
        Sadak Hamid                              9461 3885   0417 977 101                                     required?
Transperth                                        131 608     9325 2277
Alinta                                                         131 352
Amcom                                                        1800 222 019                                                                                                                         Considerations
                                                                                                                      Yes                                              1.    Identify scope of repair work
Optus                                                          131 344
                                                                                                                 18                                                    2.    Establish programme for repair work
Telstra                                                        132 203                                   Seek authorisation                                            3.    Obtain quotes
Water Corporation                                              131 375                                      for repairs                                                4.    Advise PTA
        George Basanovic                         9386 4952   0417 180 677                                              CM/PC                                           5.    Advise Insurers
Western Power (generation)                                     131 351                                                                                                 6.    Obtain property owner/representative approval to do work
        Shane Duryea                             9427 4257   0407 445 076                                        19
                                                                                                          Undertake repairs
Synergy (retail)
        Business Faults                           131 354                                                                    CM
        Residential Faults                        131 353                                                                                                                                    Considerations
                                                                                                                  20
                                                                                                        Final inspection and                                          1. Complete "During-construction property condition survey"
                                                                                                               sign off                                               2. Issue copy of survey and incident report to PTA and obtain
                                                                                                                        CM/PC                                            property owner/representative sign off.

                                                                                                                21
                                                                                                         Close out incident                  Form W1114-CS-4019
                                                                                                                        SCM/PC               Form W1114-CS-4018


                                                                                                                 22
                                                                                                         Notify PTA of close
                                                                                                                 out
                                                                                                                            SCM




                                                   Figure 4 - Incident Notification and Investigation Process
4   INSTRUMENTATION AND MONITORING

4.1 Instrumentation Quantities
A total of 5205 instrumentation points were installed on the New MetroRail Project to monitor the
influence of excavation, tunnelling, piling and dewatering activities. The instrumentation types, and
quantities installed over the life of the project are summarised in the following table.

                               Table 2 – Instrument Types and Quantities

                                    Instrument Type            Quantity Installed
                           Surface Settlement Pin – SSP-1            1021
                           Surface Settlement Retro – SSP- 2          451
                           Bored Settlement Point – SSP- 3            559
                           Deep Settlement Point – SSP- 4             19
                           Building Settlement Point - BSPB           449
                           Building Settlement Retro - BSPR          1403
                           Building Settlement Prism - BSPP           285
                           Tilt Meter, Manual - TILTM                 54
                           Tilt Meter, Automatic - TILTA              33
                           Crack Meters – CM                          82
                           Electro Level Beams - ELB                  150
                           Strain Gauges – SG                         174
                           Vibration Sensor - VS                      12
                           Inclinometers - INCL                       64
                           Extensometers, Magnetic - EXTM             187
                           Extensometers, Rod - EXTM                  25
                           Vibrating Wire Piezometers - VWPZ          91
                           Open Hole Piezometers - OHPZ               146
                                                                     5205


In addition to the above, a further 180 recharge and dewatering bores were drilled on the project, most
of which were also regularly monitored for water levels.

The instrumentation density installed on the project was considered to be high, with densities being
consistently higher than minimum specifications, however a large proportion of the manual settlement
points (SSP-1 and SSP-3) required replacement and thus approximately 800-1000 of this number was
likely to have been a replacement for points damaged by the construction process. Despite the high
quantity of instrumentation, costs for instrumentation and monitoring including drilling remained very
low at approximately 3-4% of the tender price.

4.2 Instrumentation Types
The 18 types of instruments used on the project could be grouped into 7 functional types as follows:
    •    Vertical Ground Movement
    •    Lateral Ground Movement
    •    Building Movement
    •    Building Tilt
    •    Structural Response
    •    Vibration
    •    Groundwater Movement
The instruments used in each of the functional groups, their suitability for purpose, reliability,
accuracy, repeatability, and cost effectiveness are discussed in detail in the following sections:

4.2.1   Vertical Ground Movement
Ground Movement, (settlement and heave) was measured using the following instruments:

    •     Settlement Pins (SSP-1), [survey nails and bridge spikes installed in roads, bridges and
          footpaths]
     • Settlement Points (SSP-3), [steel reinforcing rods grouted 800mm deep into a borehole]
     • Deep Settlement Points (SSP-4), [steel reinforcing rods grouted into borehole approximately
          1.5m above services]
     • Rod Extensometers (EXTR),
     • Magnet Extensometers (EXTM)
     • Reflective Photogrammetry Targets
     • Electrolevel Beams
     • Retro Targets
Settlement pins, settlement points and reference head on the rod extensometers were all measured by
means of digital levelling using a Leica DNA-10 Digital Level and Barcode Staff. Typically traverses
of up to several hundred metres were undertaken without control points. A misclosure limit of 3mm
was used as the acceptance criteria for these traverses. The repeatability of surveys was within +/-
1.5mm of the true or mean level as illustrated by Figure 5, which was a point sufficiently away from
all excavation and tunnelling that no settlement occurred. Vibration from pedestrian traffic and
machinery was a common problem, due to the city location, with shaking of the digital level visible
through the optical sight. This vibration occasionally resulted in gross errors, which were much
greater than +/- 1.5mm.

Raw survey data downloaded from field was adjusted via the least squares method. Data was then
“dumped” into excel spreadsheets for verification. Verified data was then exported to GIMS database
for permanent record. Contouring or cross sectioning of data was then undertaken. Whilst apparently
tedious, the above method enabled easy verification and manipulation of large quantities of data
without impacting on the integrity of the raw database. Typical examples of sectional and contoured
output are shown in Figure 6 and Figure 7.

The deep settlement points drilled into the ground (type SSP-3 and SSP-4) typically showed less
fluctuations than the smaller survey pins and spikes (type SSP-1) hammered into the ground and thus
were considered more reliable. The results on the project indicated that there was no discernible
difference in the total measured movement between points installed through road pavements (type
SSP-3) and those installed at the surface of the road (type SSP-1), inferring that the road base was
flexible enough to reflect the ground movements occurring at subgrade level, even where asphalt
thicknesses of 100-200mm were found along William Street.

An innovative drilling method was used to install settlement points in areas where coring of the upper
materials was not required. Drilling via vacuum extraction was used to install SSP-3’s and SSP-4’s in
many areas. The method simply involved the use of a pipe connected to suction truck, which
vacuumed up the sands, thus forming a hole, as illustrated in Figure 8 and Figure 9. The method is
normally used in Perth to locate and expose buried services, but we found it was ideally suited to our
purpose of forming shallow holes in a very quick and cost effective manner with no preparation or
clean up required. The shallow holes were formed within a few minutes, with the installation of the
grouted steel settlement rods occurring immediately after hole drilling, thus the whole process was
typically complete in 10-15 minutes.
13.815
                                                                                                                                                                                                                                                                  SSP_0533 Reduced Level


                          Reduced Level (mAHD)




                                                 13.805




                                                 13.795
                                                                    26-Oct-04



                                                                                             25-Dec-04



                                                                                                                 23-Feb-05



                                                                                                                                   24-Apr-05



                                                                                                                                                              23-Jun-05



                                                                                                                                                                                     22-Aug-05



                                                                                                                                                                                                    21-Oct-05



                                                                                                                                                                                                                20-Dec-05



                                                                                                                                                                                                                            18-Feb-06



                                                                                                                                                                                                                                        19-Apr-06



                                                                                                                                                                                                                                                    19-Jun-06



                                                                                                                                                                                                                                                                18-Aug-06



                                                                                                                                                                                                                                                                               17-Oct-06



                                                                                                                                                                                                                                                                                           16-Dec-06
                                                                                                                 Figure 5 – Example of Repeatability of Settlement Point

                                                                                 Ground Movement Profile Due to Tunnel 2 Excavation - CH 440 PMup
                                                                                (Chainage: 440 PMup +/- 10m, Tunnel 1, Vs = 0.00% Tunnel 2, Vs = 0.60%)


                  15.0

                  10.0

                   5.0

                   0.0
Settlement (mm)




                   -5.0

                  -10.0                                                                                                                   K=0.45
                                                                                                                                          Vloss = 0.70% (320m radius of curvature)
                                                                                                                                          (VLOSS = 0.60% if straight)
                  -15.0

                  -20.0
                                                                                                                                                                      3/08/2006 8:00
                                                                                                                                                                      4/08/2006 8:00
                  -25.0                                                                                                                                               5/08/2006 8:00
                                                 Tunnel 2 Cutter Face at CH 450 approx, 2/8/06 18:00
                                                 Tunnel 2 Cutter Face at CH 430 approx, 4/8/06 03:00                                                                  6/08/2006 8:00
                                                                                                                                                                      Design Volume Loss Curve
                  -30.0

                  -35.0
                      -50.0                             -40.0              -30.0          -20.0          -10.0               0.0   10.0                20.0               30.0           40.0    50.0
                                                                                                                  Chainage (m)




                   Figure 6 –Example Cross Sectional Display of                                                                                                                                                  Figure 7 –Example Contoured Output of
                           Tunnel Settlement with Time                                                                                                                                                          Settlement Data Around Major Excavation




                                                                Figure 8 – Vacuum Extraction Drilling                                                                                                           Figure 9 – Vacuum Extraction Unit
Rod extensometers used on the project were the multiple head grouted anchor type supplied by Slope
Indicator Company (SINCO). The heads were typically grouted 1.5 and 4.5 metres above the tunnel
crown, and during tunnel passage the differential movement of the rods relative to the fixed head was
measured manually with micrometer. The results obtained were consistent with tunnel activities and
show that micrometer repeatability was approximately +/- 0.25mm, as illustrated in Figure 10, but
calculated total movements were limited by the head levelling repeatability of +/- 1.5mm.

The installation of the rod extensometers was a prescribed requirement on the project, with the benefit
of the installed rod extensometers being questionable as the results confirmed the knowledge that
relatively greater settlements occur at depth than at the surface. The density of the extensometers
installed (1 per 200m) served no other benefit than to confirm this fact, with the higher density of
surface monitoring providing a better warning of face loss or heave.
                                           Rod 1 - Diff. from Original (mm)                                 Rod 2 - Diff. from Original (mm)
                                           Rod Head - Diff from original (mm)                               Surface Movement at SSP 3023

                            5.00




                           4.00




                           3.00
                                                                                                   Heave from
                                                                                                   tail void
                                                                                Tunnel
                           2.00                                                                    grouting
                                                                                Induced
                                                                                                   (point 1.5m
Diff. from Original (mm)




                                                                                Settlement
                                                                                                   from crown)
                            1.00




                           0.00




                           -1.00




                           -2.00




                           -3.00

                                                                                                  No heave at
                                                                                                  surface
                           -4.00




                           -5.00
                             01/ Jan/ 06              08/ Jan/ 06                    15/ Jan/06                        22/ Jan/ 06             29/ Jan/ 06

                                                                                     Date




Figure 10 - Typical Example of Rod Extensometer                                                                                                              Figure 11 - Typical Example of Magnet
                  Output Data                                                                                                                                          Extensometer Data
Magnet extensometers were used adjacent to excavations in preference to rod extensometers. The
type of magnets used on the project consisted of magnetic strips attached to corrugated plastic pipe,
which slid over standard inclinometer piping. The magnets were installed at intervals of 3-5m down
the inclinometer hole. The inclinometer and magnet were then grouted into place, initial readings
taken; a period of equalisation (~30 days) was then foregone before secondary readings were taken.
Readings were taken via lowering a probe down the centre of the inclinometer pipe until it reaches the
bottom magnet position. The tape is then pulled up and as it passes each magnet, two beeps are heard;
the depth at which the second beep is heard is recorded for each magnet. The method is prone to gross
errors. The repeatability of the measurements is approximately +/- 5mm as illustrated in Figure 11,
with gross movements with depth clearly visible once excavation induced settlement commences. The
settlement of the top of the inclinometer was also checked via regular levelling and compared to the
observed results. The magnet extensometers were considered highly suitable for the intended purpose
of measuring large movements where accuracies of +/- 5mm were acceptable. Magnet extensometers
provided a cost effective solution without the need for multiple boreholes or expensive rod
extensometers, or alternatively they provided additional information at minimal cost from an existing
planned inclinometer. Experience from this project would suggest that at least 5 readings be taken to
establish an average baseline value before any excavation or external loading commences.

Settlement monitoring was also undertaken with retro reflective targets located on rail tracks or survey
spikes in areas where access for regular levelling was not possible. This method of survey was
undertaken using Leica Total Stations and was slightly less repeatable than digital levelling, with
higher degrees of scatter in the measured results. Repeatability using this method was in the range of
+/-2mm. This reduced repeatability is likely to be a result of human error as the surveyor focuses on
the centre of the target to get the correct result. As discussed later in the building monitoring section,
the effect of one or two face readings is also likely to have impacted on the repeatability of the results
obtained from this type levelling.

Due to the need to focus on the target, the resulting retro target survey is slower than compared to
digital levelling. However as this method only requires one surveyor for the majority of the survey,
the operational costs incurred can be less than or equal to digital levelling in many cases. Experience
on the project indicates that using retro targets for long term settlement monitoring should only be
considered where access is limited for level surveys, or where automated instrumentation cannot be
installed. In contrast, for short term high density monitoring of restricted access areas, retro targets
would provide a cost effective solution as they only cost a few dollars each to supply and install, and
the degree of repeatability can be negated by small traverse lengths and high frequencies of
monitoring.




 Figure 12 - EL Beams installed along centreline of    Figure 13 - Proximity of Retrieval Box Excavation
                  active rail line                                    to Active Rail Line
Automated Electro-Level (EL) Beam monitoring was also used to monitor settlement of the train
tracks as excavation and tunnelling occurred in the Perth Rail Station and Perth Rail Yard. EL Beams
were required as access to the active rail area was limited with trains operating 18-20 hours per day,
and excavation was occurring within 1m of active tracks (Figure 12 and Figure 13), and tunnelling
occurred directly below the active train lines of Perth Train Station. Chains of EL beams were used to
obtain settlement profiles along the centreline of rail tracks, and transverse movements were also
measured every few metres. The ends of each EL beam chain were regularly verified via levelling and
settlement profiles adjusted for end settlement if applicable. Some EL Beams were in place for almost
2 years, and despite the vibrations from regular train traffic (every 2-30 minutes), extreme heat, and
weather, the EL beams showed no creep effects, with the repeatability of the entire chain remaining in
the range +/- 1.0mm of a mean value. A typical settlement profile and the fluctuation in the readings
observed over a 6 hour period where no construction activity was occurring is shown in Figure 14,
illustrating the high degree of repeatability.

The EL beam results were also consistent with excavation and tunnelling activities, with retro target
monitoring undertaken during tunnelling confirming the accuracy of the individual EL Beams as
shown in Figure 15, as well as highlighting the immediate response of the ground/rail as the TBM
passed underneath the beam shown. The sub millimetre accuracy of individual EL beams was
highlighted in their ability to resolve the daily 2mm variation in track height due to thermal effects.
As a result of this EL beam monitoring, there was continuous train operation throughout the 3 years of
the project, even with excavations within 1m of active trains as illustrated in Figure 13.

An innovative method of settlement monitoring using photogrammetry and auto target recognition
software was trialled on the project. Reflective targets mounted on the sides of “Cat’s Eyes” on the
road above the tunnel, on kerbs and on buildings, were monitored for movement. The aim of the
photogrammetry was to reduce the time the surveyors were spending on William Street, which was a
busy one way street through the centre of Perth CBD. By using photogrammetry, thus reducing the
survey time on the road, the risk of injury to our surveyors was reduced significantly as normal survey
required a moving method of traffic management (cars with flashing arrow boards and surveyors
working in front) in order to maintain traffic flow. In addition to the safety risks, the reduced cost of
traffic management and survey time was a benefit of this method of monitoring.
Figure 14 - Typical Repeatability of EL Beam Located on the Railway (15min readings over 6 hr period)

                                                                                         Longitudinal Settlement - EL_001_5L01 at CH 23.143m
                             10

                              8

                              6
  Cumilative Movement (mm)




                              4

                              2

                              0

                              -2

                              -4

                              -6

                              -8

                             -10
                                   12-May-06




                                               13-May-06




                                                                 14-May-06




                                                                             15-May-06




                                                                                              16-May-06




                                                                                                          17-May-06




                                                                                                                           18-May-06




                                                                                                                                         19-May-06




                                                                                                                                                              20-May-06




                                                                                                                                                                          21-May-06




                                                                                                                                                                                      22-May-06




                                                                                                                                                                                                  23-May-06




                                                                                                                                                                                                              24-May-06
                                                                                                                Cumilative Date EB 527               EB 526



                                                           Figure 15 - Comparison of EL Beam Data with Retro Target Surveying

The reflective targets were typically 15-20mm in diameter and glued to the side of the “Cat’s Eyes” as
shown in Figure 16. Additional points were also installed on the adjacent kerbs and buildings, as
illustrated in Figure 17. Once an initial photo model was generated (from multiple photos), software
automatically determined the location and change in movement of each reflective point in subsequent
photos, with each model only requiring four control points. The photogrammetry software used was
3DM Calib Cam by Adam Technology, with an example model with automated target points
recognised and labelled shown in Figure 18. Typically two photogrammetry surveys per day were
run, with greater than 100m of tunnel coverage in each photo model.

There was good correlation with manual level surveys as illustrated in Figure 19 (Note: SSP 3005 =
manual level, SSP 2317 – 2319 = Photogrammetry Level), however due to the low levels of tunnel
deformation in the study area there was insufficient data to confirm the repeatability of the system
relative to levelling. The system proved to be fit for purpose and has numerous applications for
monitoring of buildings and structures at low cost. The safety benefits of the system cannot be
understated as it significantly reduced the period the surveyors were exposed to life threatening
injuries such as being hit by a car. If adopted at the start of a project the quantities of building and
settlement monitoring surveys would be reduced significantly thus saving hundreds of thousands of
dollars annually to similar projects of this type.
Figure 16 - Reflective Target on Cat’s Eyes           Figure 17 - Reflective Targets on Kerbs/Buildings




                      Figure 18 - Photogrammetry Model with Automatic Target Recognition Generated from Figure 17

                                                                                                                                       432
                       4


                                                                                                                                       434
                       2
                                                                                             Photogrammetry
                                                                                                  Points
                       0                                                                                                               436
S ettlem ent [m m ]




                       -2
                                                                                                                                       438

                       -4

                                                                                                             Levelling                 440
                       -6                                                                                      Point

                                                                                                                                       442
                       -8



                      -10                                                                                                              444
                      13/11/05      23/11/05        3/12/05     13/12/05          23/12/05         2/01/06      12/01/06          22/01/06
                                                                           Date


                        SSP_3005               SSP_2317              SSP_2318                    SSP_2319                  #N/A


                                   Figure 19 - Comparison of Photogrammetry Surveys with Level Surveys
Settlement monitoring was the most time consuming and costly exercise on the project. The cost of a
surveyor and assistant was approximately A$1500 per day over 2.5 years (approximately A$500,000
per annum per survey crew), and 2-3 crews were operating at most times throughout the project. In
addition to this, daily traffic control at A$1000-A$2000 per day was also required when surveying
above the tunnels, and on highly trafficked streets where excavation induced settlement was occurring.
Experience shows that substantial cost savings in survey would have been possibly gained in using
automated EL beams mounted below footpaths and roads given that each EL beam costs in the order
of A$2500-A$3000 for a 3m beam length.

The use of automated instruments would also have reduced the quantity of engineer supervision on the
project whilst providing highly desirable continuous information to tunnelling and construction
personnel. The density of EL Beam readings would also have benefited the end users, as readings
would be spaced at 3-5m intervals rather than the 12-25m centreline spacing than was only possible
with manual monitoring.

4.2.2   Lateral Ground Movement
Lateral ground movement was measured primarily through inclinometers installed adjacent
excavations and between tunnels. The lateral movement of several sheet piled structures and rail lines
was also measured using retro targets.

The inclinometers and casing used on the project were supplied by SINCO and were found to be
extremely reliable with approximately 8km of readings (spaced at 0.5m intervals) being undertaken
each week, or more impressively approximately 800,000 readings per year totalling over 400km.
During the 2.5 year monitoring period, only the wheels and springs required replacement once.
Repeatability of measurements in holes up to 40m deep was found to be less than +/-1mm over the
40m, and did not change throughout the project. The results obtained were consistent with
expectations, with the development lateral ground movements and ongoing creep consistent with
excavation activities.

Given the quantity of readings obtained by monitoring personnel and the high potential for back
injury, a simple extension piece which fitted over the quick connect collar of the casing was developed
at the start of the project. The purpose of the extension piece was to extend the reading height to
approximately waist height (as shown in Figure 20) reducing the need for bending over the hole
continuously as is the common procedure (as shown in Figure 21). As a result there were no recorded
back injuries or complaints from monitoring personnel over the life of the project despite the millions
of readings taken.




   Figure 20 - Inclinometer Measurement with        Figure 21 - “Normal” Inclinometer Measurement
        Extension Piece to Waist Height             requiring bending over the borehole

Automated Inclinometers (IPI’s) were also used on the project in high traffic areas where access for
periods greater than 5 minutes was not possible, or posed an unacceptable risk to monitoring personnel
safety. The IPI’s were used to monitor ground deformations between the two tunnels along William
Street, and in a bus lane adjacent a bridge founded on stone columns. The IPI’s generally performed
very well and produced excellent results, and were stable for periods of more than 1 year. The
response of individual sensors was excellent, with a repeatability less than +/-0.2mm as illustrated in
Figure 22 below, with the overall accuracy of a 24m chain approximately +/- 0.5mm as illustrated in
Figure 23. There was a small proportion of sensors that showed minor creep movements, however
these were replaced by the supplier under warranty. It should be noted that in Figure 23, the
temperature sensors recorded increased temperatures after the tunnel passed which was possibly linked
to the exothermic heat generated during curing of the tail void grout.

                                                                                    Sensor 1 Relative Movement From Bottom of Hole
                                                                                            (RL From -12.985mAHD to -9.985AHD)

                           5.0                                                                                                                                   24
                                                                           Temperature Increase after Tunnel Passage
                           4.0                                                                                                                                   23

                           3.0                                                                                                                                   22
  Relative Movement (mm)




                           2.0                                                                                                                                   21




                                                                                                                                                                      Temperature (0C)
                           1.0                                                                                                                                   20

                           0.0                                                                                                                                   19

                           -1.0                                                                                                                                  18
                                                                                                                Response to Tunnelling
                           -2.0                                                                                                                                  17

                           -3.0                                                                                                                                  16

                           -4.0                                                                                                                                  15

                           -5.0                                                                                                                                  14
                                04-    05-    06-    07-    08-    09-    10-    11-    12-    13-    14-    15-    16-    17-    18-    19-    20-
                              Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06
7Pt Moving Average Trendlines fitted to Data                                                            Date / Time



                                                                        Figure 22 - Typical Repeatability of Individual IPI Sensor


                                                                                        BH 2178 A-Axis From Initial
                                                                                                                                                     20/01/2006 7:30
                                                                                              Chainage 261.57
                                                         15
                                                                                                                                                     18/01/2006 6:00


                                                         10                                                                                          16/01/2006 6:00


                                                                                                                                                     14/01/2006 6:00
                                  Reduced Level (mAHD)




                                                          5

                                                                                                                                                     13/01/2006 6:00

                                                          0
                                                                                                                                                     12/01/2006 6:00

                                                                      Bored Tunnel Level                                                             11/01/2006 6:00
                                                          -5

                                                                                                                                                     9/01/2006 6:00
                                                         -10
                                                                                                                                                     7/01/2006 6:00


                                                         -15                                                                                         4/01/2006 6:00
                                                               -10             -5                   0                    5                10
                                                               West                                                                      East   Created: 20/01/2006 7:30
                                                                            7Pt Average Cummulative Displacement (mm)



                                        Figure 23 - Typical Repeatability of IPI Chain (for 16 day period shown in Figure 22)
Whilst expensive to install, the IPI’s are recommended for where long term monitoring of large
excavations is required in developed countries (i.e. cost of manpower is expensive). A typical 30
metre IPI and datalogging system may cost approximately A$20,000-A$25,000 to purchase, however
if that instrument is logged every two days over a period of 1 year, the cost of two monitoring
personnel to undertake the same manual inclinometer surveys would also cost in the region of
A$20,000 or more. Whilst the cost benefits are neutral over 1 year, the benefits lie in the continuous
information gained and ability to warn of impending failures at any time. Additional benefits are that
construction personnel can have unrestricted site access, allowing continuous traffic/machinery flow
above (assuming the instruments are located under 1m of fill), and importantly the IPI’s can be
retrieved and re-used at other locations thus reducing the overall cost for longer and larger projects.

The IPI’s were located in highly trafficked areas, and hence restrictions on installation time and area
available for drilling were present, so a drilling technique new to Australia; sonic drilling, was utilised.
Sonic drilling allowed rapid dry coring of the borehole from the surface, through 100-200mm of
asphalt, to depths of approximately 30 metres in one night. The continuous coring was of great benefit
in geological logging, whilst the dry drilling method was very beneficial environmentally as no sumps
or mud tanks were required to contain wash cuttings, thus also saving valuable clean up time. The
machine used was also compact and thus traffic management was confined to two lanes, and the IPI
installation was completed in one night. The cost savings compared to traditional rotary methods were
substantial. The sonic core method was also used to drill and install SSP-3’s and Rod Extensometers
above the tunnel centreline, and to sample jet grout and soil mix columns. The method allowed rapid
coring (in the order of a few minutes) through the thick surface asphalt and crushed rock road base
into the subgrade, with the machine quickly mobilised to the next drill location in 5-15minutes.




   Figure 24 – Sonic Drill Rig in William Street        Figure 25 – Sonic Rig Showing Coring Barrel and
                                                            Catch Tray for Water from Core Barrel

4.2.3    Building Movement
Building movement (settlement and heave) was monitored using the following instruments:
     •    Building Settlement Points (BSP), [bolts installed into buildings, bridges and structures]
     •    Retro-Reflective Targets (BSPR)
     •    Optical Prisms (BSPP)
     •    Reflective Photogrammetry Targets
     •    Electrolevel Beams
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia
Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia

Weitere ähnliche Inhalte

Ähnlich wie Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia

Rapid visual screening of critical facilities in the Kingston Metropolit
Rapid visual screening of critical facilities in the Kingston MetropolitRapid visual screening of critical facilities in the Kingston Metropolit
Rapid visual screening of critical facilities in the Kingston MetropolitChristopher Gayle M.Eng
 
IRJET- A Case Study on Rehabilitation and Retrofitting of Cheetal Marriage Ac...
IRJET- A Case Study on Rehabilitation and Retrofitting of Cheetal Marriage Ac...IRJET- A Case Study on Rehabilitation and Retrofitting of Cheetal Marriage Ac...
IRJET- A Case Study on Rehabilitation and Retrofitting of Cheetal Marriage Ac...IRJET Journal
 
IRJET- To Study and Analyze the Various Structures by the Structural Audit
IRJET- To Study and Analyze the Various Structures by the Structural AuditIRJET- To Study and Analyze the Various Structures by the Structural Audit
IRJET- To Study and Analyze the Various Structures by the Structural AuditIRJET Journal
 
Why You Need Site Surveying for Your Construction Project?
Why You Need Site Surveying for Your Construction Project?Why You Need Site Surveying for Your Construction Project?
Why You Need Site Surveying for Your Construction Project?Aussie Hydro-Vac Services
 
Presentation1
Presentation1Presentation1
Presentation1premcivil
 
IRJET- Investigation of Damage Level and Study on Load Deflection Charact...
IRJET-  	  Investigation of Damage Level and Study on Load Deflection Charact...IRJET-  	  Investigation of Damage Level and Study on Load Deflection Charact...
IRJET- Investigation of Damage Level and Study on Load Deflection Charact...IRJET Journal
 
IRJET- Analysis and Design of Multi Storey Building Subjected to Seismic Load...
IRJET- Analysis and Design of Multi Storey Building Subjected to Seismic Load...IRJET- Analysis and Design of Multi Storey Building Subjected to Seismic Load...
IRJET- Analysis and Design of Multi Storey Building Subjected to Seismic Load...IRJET Journal
 
IRJET- Review on Restrengthening of Existing R.C Structure with Considera...
IRJET-  	  Review on Restrengthening of Existing R.C Structure with Considera...IRJET-  	  Review on Restrengthening of Existing R.C Structure with Considera...
IRJET- Review on Restrengthening of Existing R.C Structure with Considera...IRJET Journal
 
IRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case StudyIRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case StudyIRJET Journal
 
ANALYSIS AND DESIGN OF MULTISTORIED EARTHQUAKE RESISTANT BUILDING. “G+25”
ANALYSIS AND DESIGN OF MULTISTORIED EARTHQUAKE RESISTANT BUILDING. “G+25”ANALYSIS AND DESIGN OF MULTISTORIED EARTHQUAKE RESISTANT BUILDING. “G+25”
ANALYSIS AND DESIGN OF MULTISTORIED EARTHQUAKE RESISTANT BUILDING. “G+25”IRJET Journal
 
Construction Planning of an Offshore Petroleum Platform
Construction Planning of an Offshore Petroleum PlatformConstruction Planning of an Offshore Petroleum Platform
Construction Planning of an Offshore Petroleum PlatformProfessor Kabir Sadeghi
 
internship review .pdf
internship review .pdfinternship review .pdf
internship review .pdfPAYALINAMDAR
 
Structural Diagnosis, Repair and Retrofitting of RCC Structure
Structural Diagnosis, Repair and Retrofitting of RCC StructureStructural Diagnosis, Repair and Retrofitting of RCC Structure
Structural Diagnosis, Repair and Retrofitting of RCC StructureIRJET Journal
 
Response Spectrum and Time History Analysis of a Multistorey Building
Response Spectrum and Time History Analysis of a Multistorey BuildingResponse Spectrum and Time History Analysis of a Multistorey Building
Response Spectrum and Time History Analysis of a Multistorey BuildingIRJET Journal
 
Blast Resistant Buildings
Blast Resistant BuildingsBlast Resistant Buildings
Blast Resistant BuildingsIRJET Journal
 
Performance Based Approach for Seismic Design of Tall Building Diaphragms
Performance Based Approach for Seismic Design of Tall Building DiaphragmsPerformance Based Approach for Seismic Design of Tall Building Diaphragms
Performance Based Approach for Seismic Design of Tall Building DiaphragmsIRJET Journal
 
Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Khalid Abdel Naser Abdel Rahim
 

Ähnlich wie Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia (20)

Rapid visual screening of critical facilities in the Kingston Metropolit
Rapid visual screening of critical facilities in the Kingston MetropolitRapid visual screening of critical facilities in the Kingston Metropolit
Rapid visual screening of critical facilities in the Kingston Metropolit
 
IRJET- A Case Study on Rehabilitation and Retrofitting of Cheetal Marriage Ac...
IRJET- A Case Study on Rehabilitation and Retrofitting of Cheetal Marriage Ac...IRJET- A Case Study on Rehabilitation and Retrofitting of Cheetal Marriage Ac...
IRJET- A Case Study on Rehabilitation and Retrofitting of Cheetal Marriage Ac...
 
IRJET- To Study and Analyze the Various Structures by the Structural Audit
IRJET- To Study and Analyze the Various Structures by the Structural AuditIRJET- To Study and Analyze the Various Structures by the Structural Audit
IRJET- To Study and Analyze the Various Structures by the Structural Audit
 
Why You Need Site Surveying for Your Construction Project?
Why You Need Site Surveying for Your Construction Project?Why You Need Site Surveying for Your Construction Project?
Why You Need Site Surveying for Your Construction Project?
 
Presentation1
Presentation1Presentation1
Presentation1
 
IRJET- Investigation of Damage Level and Study on Load Deflection Charact...
IRJET-  	  Investigation of Damage Level and Study on Load Deflection Charact...IRJET-  	  Investigation of Damage Level and Study on Load Deflection Charact...
IRJET- Investigation of Damage Level and Study on Load Deflection Charact...
 
IRJET- Analysis and Design of Multi Storey Building Subjected to Seismic Load...
IRJET- Analysis and Design of Multi Storey Building Subjected to Seismic Load...IRJET- Analysis and Design of Multi Storey Building Subjected to Seismic Load...
IRJET- Analysis and Design of Multi Storey Building Subjected to Seismic Load...
 
IRJET- Review on Restrengthening of Existing R.C Structure with Considera...
IRJET-  	  Review on Restrengthening of Existing R.C Structure with Considera...IRJET-  	  Review on Restrengthening of Existing R.C Structure with Considera...
IRJET- Review on Restrengthening of Existing R.C Structure with Considera...
 
Indian standards on earthquake engineerin gkk
Indian standards on earthquake engineerin gkkIndian standards on earthquake engineerin gkk
Indian standards on earthquake engineerin gkk
 
IRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case StudyIRJET - Failure in Commercial Building and Management - Case Study
IRJET - Failure in Commercial Building and Management - Case Study
 
Iw3315041514
Iw3315041514Iw3315041514
Iw3315041514
 
ANALYSIS AND DESIGN OF MULTISTORIED EARTHQUAKE RESISTANT BUILDING. “G+25”
ANALYSIS AND DESIGN OF MULTISTORIED EARTHQUAKE RESISTANT BUILDING. “G+25”ANALYSIS AND DESIGN OF MULTISTORIED EARTHQUAKE RESISTANT BUILDING. “G+25”
ANALYSIS AND DESIGN OF MULTISTORIED EARTHQUAKE RESISTANT BUILDING. “G+25”
 
Construction Planning of an Offshore Petroleum Platform
Construction Planning of an Offshore Petroleum PlatformConstruction Planning of an Offshore Petroleum Platform
Construction Planning of an Offshore Petroleum Platform
 
internship review .pdf
internship review .pdfinternship review .pdf
internship review .pdf
 
Vibrations generated by rail infrastructure
Vibrations generated by rail infrastructureVibrations generated by rail infrastructure
Vibrations generated by rail infrastructure
 
Structural Diagnosis, Repair and Retrofitting of RCC Structure
Structural Diagnosis, Repair and Retrofitting of RCC StructureStructural Diagnosis, Repair and Retrofitting of RCC Structure
Structural Diagnosis, Repair and Retrofitting of RCC Structure
 
Response Spectrum and Time History Analysis of a Multistorey Building
Response Spectrum and Time History Analysis of a Multistorey BuildingResponse Spectrum and Time History Analysis of a Multistorey Building
Response Spectrum and Time History Analysis of a Multistorey Building
 
Blast Resistant Buildings
Blast Resistant BuildingsBlast Resistant Buildings
Blast Resistant Buildings
 
Performance Based Approach for Seismic Design of Tall Building Diaphragms
Performance Based Approach for Seismic Design of Tall Building DiaphragmsPerformance Based Approach for Seismic Design of Tall Building Diaphragms
Performance Based Approach for Seismic Design of Tall Building Diaphragms
 
Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...
 

Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia

  • 1. Geotechnical Instrumentation and Monitoring for the New MetroRail City Project, Perth, Western Australia P.G. McGough Instrumentation and Monitoring Manager, Leighton Kumagai Joint Venture, Perth M. Williams Special Contracts Manager, Leighton Kumagai Joint Venture, Perth ABSTRACT: The New MetroRail Project involved a significant number of deep excavations within varying soil types, as well as tunnelling under live railways and heritage buildings. From the onset of the project, significant effort and planning was put into geotechnical instrumentation and monitoring, with over 5200 instruments being installed during the life of the project over a length of less than 3 kilometres. This paper details the initial planning and management process, as well as the contractual requirements, which formed the basis for more instrumentation as the project progressed. Specific project requirements such as compensation grouting under buildings and tunnelling under live railways at depths of less than one tunnel diameter required specific planning measures and additional detailed monitoring which is discussed herein. A large number of automated instruments were used to ensure cost effective and safe collection of data. The types of instruments used on the project are discussed in detail with respect to their applicability, accuracy, reliability, repeatability and cost effectiveness. Examples are presented to illustrate the above points as well as highlight operational issues learnt. The process of data collection, management and reporting is also discussed. With construction taking place in a variety of ground conditions ranging from very soft alluvial silts and reclaimed fill to medium dense alluvial sands and stiff clays a number of distinct response issues were observed by the monitoring. The lessons learnt from three years of continuous monitoring of ground and building movements, groundwater movements, and instrument vibrations are discussed with respect to this project and future projects in Perth within similar geotechnical environments. Detailed examples of ground, sheet pile and wall movements and strut loads with respect to excavation design are presented, along with examples of the exceptionally low volume loss from TBM operation, and resulting building responses to ground movement. An empirical method for predicting ground settlement due to sheet pile extraction is also presented. Examples of ground vibrations induced by sheet piling, construction activities and tunnelling are presented.
  • 2. 1 INTRODUCTION The minimum required instrumentation for the project was specified in the contract documents referred to as the Scope of Works and Technical Criteria (SWTC), which became the guiding document for tendering purposes and initial estimation. To address the definition of purpose for monitoring, a Building Protection Management Plan was created by Leighton Kumagai Joint Venture (LKJV). The overall purpose of LKJV’s approach to instrumentation, monitoring and building protection was summarised in the Management Plan as follows: “ to identify the controls to be implemented to ensure personal safety (construction and public), and verify design predictions to prevent damage to buildings, services and civil infrastructure as a result of LKJV construction activities.” [From LKJV’s “Building Protection Management Plan”] Appropriate management methods were also created and put in place to handle the possible influences of construction activities due to the soft Perth soils. This included selecting “fit-for-purpose” instrumentation that was able to be monitored safely, whilst still providing accurate and timely feedback about construction progress. In addition to working in, with and around the construction personnel, a key criteria was to minimise disruption to pedestrians, traffic flows, and retail business in the CBD. 2 INITIAL PLANNING AND MANAGEMENT PROCESS 2.1 Overview The need for protection of workers’ safety, property and the environment was foreseen by the Public Transport Authority (PTA) in their tender scope document “Scope of Works and Technical Criteria” (SWTC). These activities included: • Monitoring the performance of deep excavations with respect to design; • The need for controls to minimise the potential for damage to buildings, services, roads, rails and bridges from construction activities such as: - demolition; - sheet piling, bored piling or diaphragm wall construction; - tunnelling; - ground improvement activities (jet grouting, soil mixing, compensation grouting); - consolidation from groundwater drawdown. • Determining a series of baseline condition surveys to objectively determine any damage; • A process for receiving automated alerts if movement criteria were exceeded. On consideration of the complexity of the final monitoring program, LKJV added the following additional elements to those listed in the SWTC: • An overall management process to coordinate the activities of design, construction, survey and monitoring crews, with geotechnical and management reviews. A single document (Building Protection Management Plan) was created to bring together the requirements of: - Geotechnical Interpretive Report; - Ground Settlement, Building Protection and Repair Plan, incorporating Property Condition Surveys and Building Protection Assessments; - Instrumentation and Monitoring Plan; - Various area-specific Method Statements and Safe Work Methods (i.e., JSA’s); - Feedback from the actual results generated. • Visual approach to interpretation of monitoring data to allow for quick interpretation by a range of personnel;
  • 3. Innovative instruments and monitoring methods such as wireless electrolevel beams and terrestrial photogrammetry driven by safety or minimising disruption to the public; • Emergency Response procedures as part of the overall risk management plan to cover the event of a massive failure. Figure 1 outlines the key elements of the building protection and monitoring process. Geotechnical investigations Condition surveys in zone of influence Detailed design Assess the need for building protection Install instrumentation Protection of key and monitoring structures Construction and Tunnelling works Investigate exceptions Post construction surveys and repair Figure 1. The LKJV Building Protection and Monitoring Process 2.2 Damage criteria After extensive preliminary geotechnical work had been undertaken, modelling of the potential zone of influence of the project works was performed. This determined the width of the potential subsidence zone, based on the predicted design level of induced settlement and TBM face loss. A key point to note is that although the Ground Settlement, Building Protection and Repair Plan determines a zone of influence based on a designed level of settlement caused by the excavations and the TBM, the actual performance of the TBM was expected to be considerably better than this (i.e., less settlement). This was in demonstrated by the actual TBM operations, where up to 20mm was designed for along William Street, but only around 3-5 mm was observed. The performance of the TBM with respect to design is discussed in more detail later in this paper. Once the potential zone of influence was determined, a visual Property Condition Report was prepared for each of the following structures along or adjacent to the route of the project: • 88 buildings, from single storey to BankWest tower; • 5 bridges and footbridges, including the heritage listed Horseshoe Bridge; • Sections of roads and associated furniture along and adjacent to William and Roe Streets; • Around 30 water and sewer services using a CCTV camera. The design level settlements of the TBM had the potential to cause minor damage to some buildings along the route. An engineering assessment was made to determine whether this potential damage would exceed the limits specified in the PTA’s SWTC. The damage criteria was based on the work of Boscardin and Cording, 1989, which is reproduced as Table 1.
  • 4. Table 1 - Building Damage Classification Approx. Description of Max Risk Description of Typical Damage and Likely Crack Degree of Tensile Category Forms of Repair width Damage Strain [%] [mm] Less than Less than 0 Negligible Hairline Cracks 0.1 0.05 Fine cracks easily treated during normal redecoration. Damage generally restricted to 0.05 to 1 Very Slight internal wall finishes Perhaps isolated slight 0.1 to 1 0.075 fracture in building. Cracks in exterior brickwork visible upon close inspection. Cracks easily filled. Redecoration probably required. Recurrent cracks can be masked by suitable linings. Exterior cracks visible: some 0.075 to 2 Slight 1 to 5 repointing may be required for weather- 0.15 tightness. Doors and windows may stick slightly. Cracks may require cutting out and patching. 5 to 15 or a Tuck pointing and possibly replacement of a number of small amount of exterior brickwork may be 3 Moderate cracks 0.15 to 0.3 required. Doors and windows sticking. Services greater may be interrupted. Weathertightness often than 3 impaired. Extensive repair involving removal and 15 to 25 replacement of sections of walls, especially over but also doors and windows required. Windows and door Greater 4 Severe depends on frames distorted. Floor slopes noticeably. Walls than 0.3 number of lean or bulge noticeably. Some loss of bearing in cracks beams. Services disrupted Usually Major repair required involving partial or greater complete reconstruction. Beams lose bearing, than 25 but Greater 5 Very Severe walls lean badly and require shoring. Windows depends on than 0.3 broken by distortion. Danger of instability. number of cracks For each property, a Building Protection Assessment was undertaken by Airey Taylor Consulting that considered the predicted maximum damage from the Ground Settlement Plan and the cumulative variation from the initial damage category assessed in the Property Condition Report. The result was the maximum damage category that could be expected. Building protection was required if the “incremental” damage exceeded the following limits: • For heritage structures – very slight (up to 1mm crack width); • For other structures – slight (up to 5mm crack width). In addition to compliance with the PTA’s SWTC, a formal Instrumentation and Monitoring Plan was produced to detail the network of devices which would provide feedback for the following: • Construction management to ensure the safety of deep excavations is maintained; • TBM operators and management to control the various TBM operating parameters; • Geotechnical Manager to ensure the project’s impact on the surrounding natural and built environments is minimised and within stated limits.
  • 5. 3 KEY AREAS OF MANAGEMENT FOCUS In addition to the minimum contractually-specified arrays, there were a number of key construction activities that needed specific management requirements: • Protection of key structures: A number of structures, buildings and services needed special treatment due to their calculated risk category. All other structures were monitored according to the Instrumentation and Monitoring Plan to confirm the validity of the design assumptions. • Incident and emergency management: With the extensive array of monitoring devices, LKJV needed a documented process to investigate any devices that showed movement “out of tolerance”, plus planning for major high risk events. These two areas are discussed in more detail in the following sections. 3.1 Protection of key structures The main structures that needed unique building protection solutions were: • Underpinning of the Wellington Building • Removal of the Mitchell Façade • Protection of the Horseshoe Bridge arches • Compensation grouting of the buildings under which the TBM passed • Perth Rail Yard, footbridge and station platforms (where tunnelling under the live railways was at depths of less than one tunnel diameter) • Claisebrook Sewer. These are each discussed briefly below. 3.1.1 Underpinning of the Wellington Building The heritage-listed Wellington Building is a “classic piece of turn of the 19th century corner architecture” under which the new station had to be constructed. As part of the permanent station structure, the Wellington Building had an array of tubular steel and grout micropiles drilled from within the basement. A concrete slab was then poured in the basement but not connected to the micropiles. A series of flat jacks were placed between the top of the micropiles and the base of the concrete slab. The slab was then clamped to the external diaphragm walls, thus forming the roof of the new station. Excavation was then commenced in a top down method under the Wellington Building, with the former footings removed with the first level of excavation, and the weight of the slab and building supported by the micropiles and the diaphragm wall. The excavation was then completed to base slab level and the tubular steel piles were then cut, and tied into the base slab of the station providing an uplift anchor. The weight of the building then sat on the roof slab of the new William Street Underground Station. (WSS) To monitor the impact of the construction works, around 40 optical prisms were placed around the building and read from robotic theodolites on the Advertising Tower at Perth Station, and the Post Office Building in Forrest Place. This allowed for remote monitoring and interpretation of movements across the building. Being heritage listed, the damage criteria were stricter for the Wellington Building, which meant a much higher density of micropiles were necessary than would be required on a purely structural basis. Additional manual monitoring such as roof and building levelling, tilt monitoring and retro target surveying was undertaken to enhance the automated monitoring.
  • 6. Figure 2 - Wellington Building, and Excavation of Exterior Brick Wall of Building Prior to Tieing Basement Slab and Capping Beam to Diaphragm Wall 3.1.2 Removal of the Mitchell Façade Only the façade of the Mitchell Building was heritage listed, but it was located very close to the diaphragm wall alignment for the station. This combined with safety concerns over the stability of the façade’s render meant that LKJV sought permission from the Heritage Council to remove the façade to ensure its protection. Permission was granted and the façade was encased in a steel frame and cut into pieces to be stored off site, as illustrated in Figure 3. Figure 3 - Mitchell’s Building Prior to, and during breaking up into pieces 3.1.3 Protection of the Horseshoe Bridge LKJV’s first consideration for the Horseshoe Bridge was full underpinning through installation of jet grout columns under the existing footings. However after more detailed analysis of the structure, the potential for differential movement across the structure was still highly probable. It was determined that due to the flexible nature of the steel-framed structure there would be no structural damage, but the façade heritage features (cement render arches) were susceptible to movement and needed to be propped with timber arches to prevent damage. 3.1.4 Compensation grouting of the “Gold Group” The “Gold Group” buildings (named for their importance to the project) comprise the following buildings facing William Street between Hay and Murray Street Malls: Friendlies Chemist, HBF, Hungry Jack’s/KFC, Walsh’s Building (McDonalds, and other retail tenancies). The route of the TBM passed either partially or wholly under these buildings, and LKJV’s Building Protection Assessment indicated the need for protection, with a potential design movement of 20mm.
  • 7. Due to various space and access constraints, LKJV determined the best option was to work collaboratively with Keller Ground Engineering and implement a TAM compensation grouting system. The details of this system are described in more detail in another paper contained herein by Nobes & Williams (2007) 3.1.5 Perth Rail Station tracks and platforms The TBM passed twice underneath the station and the live railway, which needed to be kept running at all times. Due to the flexibility of ballasted rail, there was no structural problem should TBM settlements reach the design limits, but such settlements may cause two operational issues. Firstly, if tilting of the platform edge increased relative to the track there would be insufficient clearance for the train, and secondly, if excessive cross cant was to occur it may lead to a derailment. Due to the success of the first stage of tunnelling up William Street (maximum 5mm settlement), it was determined that an observational approach be taken in preference to preventative measures, with defined management methods and actions. Elements of this observational method included: • Automatic electrolevel beams on the rail tracks; • Automatic tilt meters on the platform faces; • High density of surface, building and rail settlement points; • 24 hour/7 day week survey, with rail safety presence, and direct ring-by-ring contact with the tunnel shift engineer; • Specific management measures including: - A purpose-written Method Statement covering survey, interpretation, tunnel operations and rail safety; - Daily coordination meetings with all parties (management, survey, geotechnical, tunnel, rail and client); - Web-based access to all monitoring information for all teams; - Emergency scenario workshops. The close contact with the TBM crew allowed for parameters to be changed on a ring by ring basis on the survey and automatic results presented. The result was that during the passage of the TBM, the maximum final rail movement was limited to less than 10mm. 3.1.6 Claisebrook Sewer With the footings of the century old, brick lined, Claisebrook Sewer potentially lying within 800mm of tunnel alignment, protective measures were required. After thorough discussions with Water Corporation, it was decided to re-line the inside of the sewer with new plastic piping. In addition to this, LKJV determined that since a subsidence risk was still present during the passage of the TBM due to fragile nature of the sewer, LKJV also temporarily “over-pumped” the sewer when the TBM was within a zone of influence. 3.2 Incident and emergency management 3.2.1 Incident investigations All instruments had the following three alert levels determined in the Ground Settlement and Building Protection Plan: • Trigger, set at say, 80% of the “design” level as an early warning; • Design, equal to the predicted movement level; • Allowable, set at say 120% of the “design” level and at which remedial action must be taken.
  • 8. For all instruments, these alert levels were entered into the instrument database (GIMS). If a level was exceeded, an SMS and email were sent to a nominated group of people to action as appropriate. When alert levels were exceeded, a rigorous process was followed to ensure traceability of all decisions. This process is shown in Figure 4. If the alert was not spurious, or a transient event, a more detailed investigation was initiated to determine whether any changes to design or construction techniques would be necessary. • Monitoring frequencies were set for each instrument, and one full time person was dedicated to ensuring the instruments being read matched the progress of the construction works. During the peak months, a team of up to 19 people were dedicated to gathering, inputting, reviewing and investigating monitoring data: 3.2.2 Emergency management through desktop scenarios Although the chance of an excavation or TBM failure (to a level requiring the assistance of emergency services) was remote, as a key part of the LKJV’s risk management approach, a comprehensive emergency management process was implemented. To test our management plan so that it was a “live” document, we undertook a series of scenario workshops both internally and externally to LKJV. On 1 December 2005, around 40 representatives from LKJV, Leighton Contractors, Leighton Holdings, New MetroRail (client), Public Transport Authority (operations and infrastructure), City of Perth, Fire & Emergency Services Authority, Police, Worksafe, Western Power, Alinta Gas, Water Corporation, Telstra and Main Roads attended a workshop focussing on the bored tunnel section up William Street. One of the key findings to come from the scenario workshops was that of the role of the Hazard Management Authorities (HMAs) and how to use the existing Memoranda of Understandings between the HMAs and the various government and private agencies. Another workshop was held on 15 March 2006 with a similar range of external parties, but with more attendance from railway operations personnel, which was the focus of the day. Also a number of internal scenario sessions were held with teams from survey, geotechnical, tunnel and rail to ensure coordination of activities and communication. We also checked that our communication protocols were consistent with Leighton Contractors national approach to Crisis Management, and sought feedback from Leighton Holdings on lessons learnt from recent crisis management activities (Lane Cove Tunnel). Feedback from all sessions was used to make our procedures as user friendly as possible. The aim was to ensure people knew what to do if something escalates from an incident to an emergency. A Building Access Checklist was also obtained for every property, which LKJV could use to raise an alarm in the case of an emergency. Since LKJV’s monitoring and/or tunnelling teams will probably be the first to know of any incident, we determined that having this information on hand was prudent.
  • 9. BUILDING AND MONITORING INCIDENT FLOWCHART NEW METRORAIL CITY PROJECT Legend 1 Point of Contact Point of Contact (PC) Incident occurs Primary Secondary PC Point of Contact Building Incident Primary Contact Alternative Contact Peter McGough Kate Stone Buiding Incident Matt Williams Kate Stone IM I & M Manager Monitoring Incident Peter McGough Fugro Monitoring Incident Peter McGough Franco Roselli PD Project Director 2 Infrastructure / Infrastructure/Services Mike Wallis Area Manager CM Construction Manager Services IncidentMichael Wallis Incident Relevant Area Manager 3 AM Area Manager No further action No Is investigation GM Geotechnical Manager (Update register if required? Considerations DM Design Manager required) Establish whether incident is legitimate Yes Considerations Form W1114-CS-4018 1. Notification to Area Manager 4 2. Safety of personnel Record Incident on 3. Structural integrity of building/infrastructure/service register and review 4. New occurrence or sudden change in trend details 5. Compare to existing condition, historical monitoring/reports BUILDING INCIDENT RESPONSE and any background data PC CONTACT DETAILS 6. Review of recorded levels against control levels LKJV M ANAGEMENT CONTACTS TELEPHONE MOBILE 7. Visit to location and visual inspection 5 Rob Wallwork Project Director 9424 5604 0411 259 451 8. Estimate of damage Conduct preliminary 9. Record of construction work being undertaken at time of Tony Cariss Construction Manager 9424 5515 0419 932 132 investigation incident K. Akabane Ass’t Construction Mgr 9424 5596 0421 404 984 Kate Stone Community Relations Mgr 9424 5588 0422 001 037 PC 6 F. Aikawa Design Manager 9424 5563 0422 246 067 Simon Gegg William Street Station Mgr 9424 5506 0402 898 627 7 Paul Farris Southern Area Manager 9424 5631 0422 001 235 No Site assessment by GM to Is further action agree and implement Ashley Warner Perth Rail Yard Manager 9228 4942 0421 144 469 required? Yes - URGENT action plan LKJV TUNNELLING CONTACTS TELEPHONE MOBILE Henry Yamazaki Tunnel Manager 9424 5654 0422 593 780 Frank Hannagan Tunnel Superintendent 0421 053 317 GM/PC Yes Frank Bonte General Foreman 0421 053 313 8 S. Shigemura Senior Engineer 9424 5653 0422 653 574 M. Oshima Senior Engineer 9424 5691 0413 197 300 Are only minor Andrew Shepherd Shift Engineer – Tunnel 9424 5651 0411 659 546 Yes repairs required? Special Response Team T. Watanabe Shift Engineer – Tunnel 9424 5651 0431 120 366 Special Contracts Manager/Nominee Tom Jones Shift Engineer – Tunnel 9424 5639 0422 001 021 Area Manager/Nominee TBM Direct Line 9202 1485 No Geotechnical Manager/Nominee LKJV MONITORING & GEOTECHNICAL CONTACTS TELEPHONE MOBILE LKJV geotechnical/monitoring rep Peter McGough Instrumentation and LKJV Subontractor respresentative 9424 5519 0421 053 351 9 Monitoring Manager PTA Representative Complete Incident Oskar Sigl Geotechnical Manager 9424 5514 0411 659 549 Form to initiate Form W11140-CS-4019 If available: Intern’l: +65 9735 2522 AMBER warning Construction Manager Marc Woodward Geotech Manager (alt) 9347 0000 0417 911 131 Assistant Construction Manager PC Barry Hackett Building Protection Eng. 9424 5511 0421 053 337 Design Manager/Nominee 10 LKJV R AIL CONTACTS TELEPHONE MOBILE Project Director Notify PTA (& insurer) Peter Rosenbauer Senior Project Eng’r - Rail 9424 5509 0402 894 801 immediately after Vasil Calcan Senior Rail Safety Officer 0421 635 8491 initiating amber Peter Russell Rail Safety Officer 0407 193 915 warning John Welch Rail Safety Coordinator 9424 5541 0421 711 303 PC/GM Investigation considerations FUGRO CONTACTS (INSTRUMENTATION & MONITORING) TELEPHONE MOBILE 11 1. Notification to Area Manager Fugro Monitoring Phone 9424 5617 0439 930 927 Undertake detailed 2. Safety of personnel investigation and 3. Structural integrity of building, infrastructure, or Ritchie Mulholland Chief Monitoring Surveyor 9424 5617 0417 611 295 formal risk service Home: 9302 6256 assessment 4. Review of predicted settlement and Kent Wheeler Monitoring Surveyor 9424 5584 0400 980 060 GM/PC/AM construction impact PTA CONTACTS TELEPHONE MOBILE 15 5. Quantification of damage 12 6. Review protection works to determine Richard Mann Project Director 9326 2536 0419 964 209 Notify PTA (& insurer) Verify short term adequacy Eric Hudson-Smith Geotechnical Manager 9326 2060 0419 988 861 immediately after remedial action 7. Undertake condition survey to determine extent initiating red alert Jock Henderson Special Projects Manager 9326 2093 0419 915 408 closed out of damage PD/CM/GM INSURANCE CONTACTS TELEPHONE MOBILE GM/AM 8. Undertake additional monitoring (eg survey) to Bob Perry Marsh Ltd 9421 5666 0414 307 247 13 quantity and monitor further damage 9. Complete risk assessment EMERGENCY CONTACTS TELEPHONE TELEPHONE 14 10. Review of incident impact on both PTA Urban Train Control 9326 2214 Can incident No Initiate RED alert via temporary and permanent works design Main Roads Traffic Operations Centre 9428 2222 be resolved? Incident Form and construction Fire and Emergency Services (FESA) 000 1300 1300 39 PD/CM/GM State Emergency Services (SES) 9277 0555 Action considerations 1. Increase monitoring FESA and SES Operations Centre 9323 9333 9323 9322 Yes 2. Continuous monitoring WA Police 000 9222 1111 3. Review construction techniques and equipment Russell Armstrong (Incident Management 16 9222 1694 9222 1958 Verify long term 4. Review emergency procedures Unit and LEMC) 5. Review geotechnical control limits remedial action Ambulance 000 6. Determine whether amber warning or red alert closed out Bill Thompson 0415 428 617 required GM/DM/CM Worksafe 9327 8777 1800 678 198 7. Stop work where required 8. Determine urgency of repair work City of Perth 9461 3333 17 Police Post at City of Perth 9325 6000 Bill Strong (LEMC) 9461 5836 0418 947 908 No Repairs Sadak Hamid 9461 3885 0417 977 101 required? Transperth 131 608 9325 2277 Alinta 131 352 Amcom 1800 222 019 Considerations Yes 1. Identify scope of repair work Optus 131 344 18 2. Establish programme for repair work Telstra 132 203 Seek authorisation 3. Obtain quotes Water Corporation 131 375 for repairs 4. Advise PTA George Basanovic 9386 4952 0417 180 677 CM/PC 5. Advise Insurers Western Power (generation) 131 351 6. Obtain property owner/representative approval to do work Shane Duryea 9427 4257 0407 445 076 19 Undertake repairs Synergy (retail) Business Faults 131 354 CM Residential Faults 131 353 Considerations 20 Final inspection and 1. Complete "During-construction property condition survey" sign off 2. Issue copy of survey and incident report to PTA and obtain CM/PC property owner/representative sign off. 21 Close out incident Form W1114-CS-4019 SCM/PC Form W1114-CS-4018 22 Notify PTA of close out SCM Figure 4 - Incident Notification and Investigation Process
  • 10. 4 INSTRUMENTATION AND MONITORING 4.1 Instrumentation Quantities A total of 5205 instrumentation points were installed on the New MetroRail Project to monitor the influence of excavation, tunnelling, piling and dewatering activities. The instrumentation types, and quantities installed over the life of the project are summarised in the following table. Table 2 – Instrument Types and Quantities Instrument Type Quantity Installed Surface Settlement Pin – SSP-1 1021 Surface Settlement Retro – SSP- 2 451 Bored Settlement Point – SSP- 3 559 Deep Settlement Point – SSP- 4 19 Building Settlement Point - BSPB 449 Building Settlement Retro - BSPR 1403 Building Settlement Prism - BSPP 285 Tilt Meter, Manual - TILTM 54 Tilt Meter, Automatic - TILTA 33 Crack Meters – CM 82 Electro Level Beams - ELB 150 Strain Gauges – SG 174 Vibration Sensor - VS 12 Inclinometers - INCL 64 Extensometers, Magnetic - EXTM 187 Extensometers, Rod - EXTM 25 Vibrating Wire Piezometers - VWPZ 91 Open Hole Piezometers - OHPZ 146 5205 In addition to the above, a further 180 recharge and dewatering bores were drilled on the project, most of which were also regularly monitored for water levels. The instrumentation density installed on the project was considered to be high, with densities being consistently higher than minimum specifications, however a large proportion of the manual settlement points (SSP-1 and SSP-3) required replacement and thus approximately 800-1000 of this number was likely to have been a replacement for points damaged by the construction process. Despite the high quantity of instrumentation, costs for instrumentation and monitoring including drilling remained very low at approximately 3-4% of the tender price. 4.2 Instrumentation Types The 18 types of instruments used on the project could be grouped into 7 functional types as follows: • Vertical Ground Movement • Lateral Ground Movement • Building Movement • Building Tilt • Structural Response • Vibration • Groundwater Movement
  • 11. The instruments used in each of the functional groups, their suitability for purpose, reliability, accuracy, repeatability, and cost effectiveness are discussed in detail in the following sections: 4.2.1 Vertical Ground Movement Ground Movement, (settlement and heave) was measured using the following instruments: • Settlement Pins (SSP-1), [survey nails and bridge spikes installed in roads, bridges and footpaths] • Settlement Points (SSP-3), [steel reinforcing rods grouted 800mm deep into a borehole] • Deep Settlement Points (SSP-4), [steel reinforcing rods grouted into borehole approximately 1.5m above services] • Rod Extensometers (EXTR), • Magnet Extensometers (EXTM) • Reflective Photogrammetry Targets • Electrolevel Beams • Retro Targets Settlement pins, settlement points and reference head on the rod extensometers were all measured by means of digital levelling using a Leica DNA-10 Digital Level and Barcode Staff. Typically traverses of up to several hundred metres were undertaken without control points. A misclosure limit of 3mm was used as the acceptance criteria for these traverses. The repeatability of surveys was within +/- 1.5mm of the true or mean level as illustrated by Figure 5, which was a point sufficiently away from all excavation and tunnelling that no settlement occurred. Vibration from pedestrian traffic and machinery was a common problem, due to the city location, with shaking of the digital level visible through the optical sight. This vibration occasionally resulted in gross errors, which were much greater than +/- 1.5mm. Raw survey data downloaded from field was adjusted via the least squares method. Data was then “dumped” into excel spreadsheets for verification. Verified data was then exported to GIMS database for permanent record. Contouring or cross sectioning of data was then undertaken. Whilst apparently tedious, the above method enabled easy verification and manipulation of large quantities of data without impacting on the integrity of the raw database. Typical examples of sectional and contoured output are shown in Figure 6 and Figure 7. The deep settlement points drilled into the ground (type SSP-3 and SSP-4) typically showed less fluctuations than the smaller survey pins and spikes (type SSP-1) hammered into the ground and thus were considered more reliable. The results on the project indicated that there was no discernible difference in the total measured movement between points installed through road pavements (type SSP-3) and those installed at the surface of the road (type SSP-1), inferring that the road base was flexible enough to reflect the ground movements occurring at subgrade level, even where asphalt thicknesses of 100-200mm were found along William Street. An innovative drilling method was used to install settlement points in areas where coring of the upper materials was not required. Drilling via vacuum extraction was used to install SSP-3’s and SSP-4’s in many areas. The method simply involved the use of a pipe connected to suction truck, which vacuumed up the sands, thus forming a hole, as illustrated in Figure 8 and Figure 9. The method is normally used in Perth to locate and expose buried services, but we found it was ideally suited to our purpose of forming shallow holes in a very quick and cost effective manner with no preparation or clean up required. The shallow holes were formed within a few minutes, with the installation of the grouted steel settlement rods occurring immediately after hole drilling, thus the whole process was typically complete in 10-15 minutes.
  • 12. 13.815 SSP_0533 Reduced Level Reduced Level (mAHD) 13.805 13.795 26-Oct-04 25-Dec-04 23-Feb-05 24-Apr-05 23-Jun-05 22-Aug-05 21-Oct-05 20-Dec-05 18-Feb-06 19-Apr-06 19-Jun-06 18-Aug-06 17-Oct-06 16-Dec-06 Figure 5 – Example of Repeatability of Settlement Point Ground Movement Profile Due to Tunnel 2 Excavation - CH 440 PMup (Chainage: 440 PMup +/- 10m, Tunnel 1, Vs = 0.00% Tunnel 2, Vs = 0.60%) 15.0 10.0 5.0 0.0 Settlement (mm) -5.0 -10.0 K=0.45 Vloss = 0.70% (320m radius of curvature) (VLOSS = 0.60% if straight) -15.0 -20.0 3/08/2006 8:00 4/08/2006 8:00 -25.0 5/08/2006 8:00 Tunnel 2 Cutter Face at CH 450 approx, 2/8/06 18:00 Tunnel 2 Cutter Face at CH 430 approx, 4/8/06 03:00 6/08/2006 8:00 Design Volume Loss Curve -30.0 -35.0 -50.0 -40.0 -30.0 -20.0 -10.0 0.0 10.0 20.0 30.0 40.0 50.0 Chainage (m) Figure 6 –Example Cross Sectional Display of Figure 7 –Example Contoured Output of Tunnel Settlement with Time Settlement Data Around Major Excavation Figure 8 – Vacuum Extraction Drilling Figure 9 – Vacuum Extraction Unit Rod extensometers used on the project were the multiple head grouted anchor type supplied by Slope Indicator Company (SINCO). The heads were typically grouted 1.5 and 4.5 metres above the tunnel
  • 13. crown, and during tunnel passage the differential movement of the rods relative to the fixed head was measured manually with micrometer. The results obtained were consistent with tunnel activities and show that micrometer repeatability was approximately +/- 0.25mm, as illustrated in Figure 10, but calculated total movements were limited by the head levelling repeatability of +/- 1.5mm. The installation of the rod extensometers was a prescribed requirement on the project, with the benefit of the installed rod extensometers being questionable as the results confirmed the knowledge that relatively greater settlements occur at depth than at the surface. The density of the extensometers installed (1 per 200m) served no other benefit than to confirm this fact, with the higher density of surface monitoring providing a better warning of face loss or heave. Rod 1 - Diff. from Original (mm) Rod 2 - Diff. from Original (mm) Rod Head - Diff from original (mm) Surface Movement at SSP 3023 5.00 4.00 3.00 Heave from tail void Tunnel 2.00 grouting Induced (point 1.5m Diff. from Original (mm) Settlement from crown) 1.00 0.00 -1.00 -2.00 -3.00 No heave at surface -4.00 -5.00 01/ Jan/ 06 08/ Jan/ 06 15/ Jan/06 22/ Jan/ 06 29/ Jan/ 06 Date Figure 10 - Typical Example of Rod Extensometer Figure 11 - Typical Example of Magnet Output Data Extensometer Data Magnet extensometers were used adjacent to excavations in preference to rod extensometers. The type of magnets used on the project consisted of magnetic strips attached to corrugated plastic pipe, which slid over standard inclinometer piping. The magnets were installed at intervals of 3-5m down the inclinometer hole. The inclinometer and magnet were then grouted into place, initial readings taken; a period of equalisation (~30 days) was then foregone before secondary readings were taken. Readings were taken via lowering a probe down the centre of the inclinometer pipe until it reaches the bottom magnet position. The tape is then pulled up and as it passes each magnet, two beeps are heard; the depth at which the second beep is heard is recorded for each magnet. The method is prone to gross errors. The repeatability of the measurements is approximately +/- 5mm as illustrated in Figure 11, with gross movements with depth clearly visible once excavation induced settlement commences. The settlement of the top of the inclinometer was also checked via regular levelling and compared to the observed results. The magnet extensometers were considered highly suitable for the intended purpose of measuring large movements where accuracies of +/- 5mm were acceptable. Magnet extensometers provided a cost effective solution without the need for multiple boreholes or expensive rod extensometers, or alternatively they provided additional information at minimal cost from an existing planned inclinometer. Experience from this project would suggest that at least 5 readings be taken to establish an average baseline value before any excavation or external loading commences. Settlement monitoring was also undertaken with retro reflective targets located on rail tracks or survey spikes in areas where access for regular levelling was not possible. This method of survey was undertaken using Leica Total Stations and was slightly less repeatable than digital levelling, with higher degrees of scatter in the measured results. Repeatability using this method was in the range of +/-2mm. This reduced repeatability is likely to be a result of human error as the surveyor focuses on the centre of the target to get the correct result. As discussed later in the building monitoring section, the effect of one or two face readings is also likely to have impacted on the repeatability of the results obtained from this type levelling. Due to the need to focus on the target, the resulting retro target survey is slower than compared to digital levelling. However as this method only requires one surveyor for the majority of the survey, the operational costs incurred can be less than or equal to digital levelling in many cases. Experience
  • 14. on the project indicates that using retro targets for long term settlement monitoring should only be considered where access is limited for level surveys, or where automated instrumentation cannot be installed. In contrast, for short term high density monitoring of restricted access areas, retro targets would provide a cost effective solution as they only cost a few dollars each to supply and install, and the degree of repeatability can be negated by small traverse lengths and high frequencies of monitoring. Figure 12 - EL Beams installed along centreline of Figure 13 - Proximity of Retrieval Box Excavation active rail line to Active Rail Line Automated Electro-Level (EL) Beam monitoring was also used to monitor settlement of the train tracks as excavation and tunnelling occurred in the Perth Rail Station and Perth Rail Yard. EL Beams were required as access to the active rail area was limited with trains operating 18-20 hours per day, and excavation was occurring within 1m of active tracks (Figure 12 and Figure 13), and tunnelling occurred directly below the active train lines of Perth Train Station. Chains of EL beams were used to obtain settlement profiles along the centreline of rail tracks, and transverse movements were also measured every few metres. The ends of each EL beam chain were regularly verified via levelling and settlement profiles adjusted for end settlement if applicable. Some EL Beams were in place for almost 2 years, and despite the vibrations from regular train traffic (every 2-30 minutes), extreme heat, and weather, the EL beams showed no creep effects, with the repeatability of the entire chain remaining in the range +/- 1.0mm of a mean value. A typical settlement profile and the fluctuation in the readings observed over a 6 hour period where no construction activity was occurring is shown in Figure 14, illustrating the high degree of repeatability. The EL beam results were also consistent with excavation and tunnelling activities, with retro target monitoring undertaken during tunnelling confirming the accuracy of the individual EL Beams as shown in Figure 15, as well as highlighting the immediate response of the ground/rail as the TBM passed underneath the beam shown. The sub millimetre accuracy of individual EL beams was highlighted in their ability to resolve the daily 2mm variation in track height due to thermal effects. As a result of this EL beam monitoring, there was continuous train operation throughout the 3 years of the project, even with excavations within 1m of active trains as illustrated in Figure 13. An innovative method of settlement monitoring using photogrammetry and auto target recognition software was trialled on the project. Reflective targets mounted on the sides of “Cat’s Eyes” on the road above the tunnel, on kerbs and on buildings, were monitored for movement. The aim of the photogrammetry was to reduce the time the surveyors were spending on William Street, which was a busy one way street through the centre of Perth CBD. By using photogrammetry, thus reducing the survey time on the road, the risk of injury to our surveyors was reduced significantly as normal survey required a moving method of traffic management (cars with flashing arrow boards and surveyors working in front) in order to maintain traffic flow. In addition to the safety risks, the reduced cost of traffic management and survey time was a benefit of this method of monitoring.
  • 15. Figure 14 - Typical Repeatability of EL Beam Located on the Railway (15min readings over 6 hr period) Longitudinal Settlement - EL_001_5L01 at CH 23.143m 10 8 6 Cumilative Movement (mm) 4 2 0 -2 -4 -6 -8 -10 12-May-06 13-May-06 14-May-06 15-May-06 16-May-06 17-May-06 18-May-06 19-May-06 20-May-06 21-May-06 22-May-06 23-May-06 24-May-06 Cumilative Date EB 527 EB 526 Figure 15 - Comparison of EL Beam Data with Retro Target Surveying The reflective targets were typically 15-20mm in diameter and glued to the side of the “Cat’s Eyes” as shown in Figure 16. Additional points were also installed on the adjacent kerbs and buildings, as illustrated in Figure 17. Once an initial photo model was generated (from multiple photos), software automatically determined the location and change in movement of each reflective point in subsequent photos, with each model only requiring four control points. The photogrammetry software used was 3DM Calib Cam by Adam Technology, with an example model with automated target points recognised and labelled shown in Figure 18. Typically two photogrammetry surveys per day were run, with greater than 100m of tunnel coverage in each photo model. There was good correlation with manual level surveys as illustrated in Figure 19 (Note: SSP 3005 = manual level, SSP 2317 – 2319 = Photogrammetry Level), however due to the low levels of tunnel deformation in the study area there was insufficient data to confirm the repeatability of the system relative to levelling. The system proved to be fit for purpose and has numerous applications for monitoring of buildings and structures at low cost. The safety benefits of the system cannot be understated as it significantly reduced the period the surveyors were exposed to life threatening injuries such as being hit by a car. If adopted at the start of a project the quantities of building and settlement monitoring surveys would be reduced significantly thus saving hundreds of thousands of dollars annually to similar projects of this type.
  • 16. Figure 16 - Reflective Target on Cat’s Eyes Figure 17 - Reflective Targets on Kerbs/Buildings Figure 18 - Photogrammetry Model with Automatic Target Recognition Generated from Figure 17 432 4 434 2 Photogrammetry Points 0 436 S ettlem ent [m m ] -2 438 -4 Levelling 440 -6 Point 442 -8 -10 444 13/11/05 23/11/05 3/12/05 13/12/05 23/12/05 2/01/06 12/01/06 22/01/06 Date SSP_3005 SSP_2317 SSP_2318 SSP_2319 #N/A Figure 19 - Comparison of Photogrammetry Surveys with Level Surveys
  • 17. Settlement monitoring was the most time consuming and costly exercise on the project. The cost of a surveyor and assistant was approximately A$1500 per day over 2.5 years (approximately A$500,000 per annum per survey crew), and 2-3 crews were operating at most times throughout the project. In addition to this, daily traffic control at A$1000-A$2000 per day was also required when surveying above the tunnels, and on highly trafficked streets where excavation induced settlement was occurring. Experience shows that substantial cost savings in survey would have been possibly gained in using automated EL beams mounted below footpaths and roads given that each EL beam costs in the order of A$2500-A$3000 for a 3m beam length. The use of automated instruments would also have reduced the quantity of engineer supervision on the project whilst providing highly desirable continuous information to tunnelling and construction personnel. The density of EL Beam readings would also have benefited the end users, as readings would be spaced at 3-5m intervals rather than the 12-25m centreline spacing than was only possible with manual monitoring. 4.2.2 Lateral Ground Movement Lateral ground movement was measured primarily through inclinometers installed adjacent excavations and between tunnels. The lateral movement of several sheet piled structures and rail lines was also measured using retro targets. The inclinometers and casing used on the project were supplied by SINCO and were found to be extremely reliable with approximately 8km of readings (spaced at 0.5m intervals) being undertaken each week, or more impressively approximately 800,000 readings per year totalling over 400km. During the 2.5 year monitoring period, only the wheels and springs required replacement once. Repeatability of measurements in holes up to 40m deep was found to be less than +/-1mm over the 40m, and did not change throughout the project. The results obtained were consistent with expectations, with the development lateral ground movements and ongoing creep consistent with excavation activities. Given the quantity of readings obtained by monitoring personnel and the high potential for back injury, a simple extension piece which fitted over the quick connect collar of the casing was developed at the start of the project. The purpose of the extension piece was to extend the reading height to approximately waist height (as shown in Figure 20) reducing the need for bending over the hole continuously as is the common procedure (as shown in Figure 21). As a result there were no recorded back injuries or complaints from monitoring personnel over the life of the project despite the millions of readings taken. Figure 20 - Inclinometer Measurement with Figure 21 - “Normal” Inclinometer Measurement Extension Piece to Waist Height requiring bending over the borehole Automated Inclinometers (IPI’s) were also used on the project in high traffic areas where access for periods greater than 5 minutes was not possible, or posed an unacceptable risk to monitoring personnel safety. The IPI’s were used to monitor ground deformations between the two tunnels along William
  • 18. Street, and in a bus lane adjacent a bridge founded on stone columns. The IPI’s generally performed very well and produced excellent results, and were stable for periods of more than 1 year. The response of individual sensors was excellent, with a repeatability less than +/-0.2mm as illustrated in Figure 22 below, with the overall accuracy of a 24m chain approximately +/- 0.5mm as illustrated in Figure 23. There was a small proportion of sensors that showed minor creep movements, however these were replaced by the supplier under warranty. It should be noted that in Figure 23, the temperature sensors recorded increased temperatures after the tunnel passed which was possibly linked to the exothermic heat generated during curing of the tail void grout. Sensor 1 Relative Movement From Bottom of Hole (RL From -12.985mAHD to -9.985AHD) 5.0 24 Temperature Increase after Tunnel Passage 4.0 23 3.0 22 Relative Movement (mm) 2.0 21 Temperature (0C) 1.0 20 0.0 19 -1.0 18 Response to Tunnelling -2.0 17 -3.0 16 -4.0 15 -5.0 14 04- 05- 06- 07- 08- 09- 10- 11- 12- 13- 14- 15- 16- 17- 18- 19- 20- Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 Jan-06 7Pt Moving Average Trendlines fitted to Data Date / Time Figure 22 - Typical Repeatability of Individual IPI Sensor BH 2178 A-Axis From Initial 20/01/2006 7:30 Chainage 261.57 15 18/01/2006 6:00 10 16/01/2006 6:00 14/01/2006 6:00 Reduced Level (mAHD) 5 13/01/2006 6:00 0 12/01/2006 6:00 Bored Tunnel Level 11/01/2006 6:00 -5 9/01/2006 6:00 -10 7/01/2006 6:00 -15 4/01/2006 6:00 -10 -5 0 5 10 West East Created: 20/01/2006 7:30 7Pt Average Cummulative Displacement (mm) Figure 23 - Typical Repeatability of IPI Chain (for 16 day period shown in Figure 22)
  • 19. Whilst expensive to install, the IPI’s are recommended for where long term monitoring of large excavations is required in developed countries (i.e. cost of manpower is expensive). A typical 30 metre IPI and datalogging system may cost approximately A$20,000-A$25,000 to purchase, however if that instrument is logged every two days over a period of 1 year, the cost of two monitoring personnel to undertake the same manual inclinometer surveys would also cost in the region of A$20,000 or more. Whilst the cost benefits are neutral over 1 year, the benefits lie in the continuous information gained and ability to warn of impending failures at any time. Additional benefits are that construction personnel can have unrestricted site access, allowing continuous traffic/machinery flow above (assuming the instruments are located under 1m of fill), and importantly the IPI’s can be retrieved and re-used at other locations thus reducing the overall cost for longer and larger projects. The IPI’s were located in highly trafficked areas, and hence restrictions on installation time and area available for drilling were present, so a drilling technique new to Australia; sonic drilling, was utilised. Sonic drilling allowed rapid dry coring of the borehole from the surface, through 100-200mm of asphalt, to depths of approximately 30 metres in one night. The continuous coring was of great benefit in geological logging, whilst the dry drilling method was very beneficial environmentally as no sumps or mud tanks were required to contain wash cuttings, thus also saving valuable clean up time. The machine used was also compact and thus traffic management was confined to two lanes, and the IPI installation was completed in one night. The cost savings compared to traditional rotary methods were substantial. The sonic core method was also used to drill and install SSP-3’s and Rod Extensometers above the tunnel centreline, and to sample jet grout and soil mix columns. The method allowed rapid coring (in the order of a few minutes) through the thick surface asphalt and crushed rock road base into the subgrade, with the machine quickly mobilised to the next drill location in 5-15minutes. Figure 24 – Sonic Drill Rig in William Street Figure 25 – Sonic Rig Showing Coring Barrel and Catch Tray for Water from Core Barrel 4.2.3 Building Movement Building movement (settlement and heave) was monitored using the following instruments: • Building Settlement Points (BSP), [bolts installed into buildings, bridges and structures] • Retro-Reflective Targets (BSPR) • Optical Prisms (BSPP) • Reflective Photogrammetry Targets • Electrolevel Beams