Project Name : Samsung Naffora Techno Valley Project   Inquiry No. NB2231-PR-ITB-223
Job No.: NB2231




                   INSTRUCTION TO BIDDERS
Project Name : Samsung Naffora Techno Valley Project    Inquiry No. NB2231-PR-ITB-223
Job No.: NB2231




                              INSTRUCTION TO BIDDERS


                                           INDEX



    1.   GENERAL

    2.   SUBMISSION OF PROPOSAL

    3.   COMMUNICATION

    4.   SCOPE OF WORK

    5.   TERMS OF PAYMENT

    6.   DEVIATION FROM INQUIRY DOCUMENTS

    7.   EVALUATION OF PROPOSAL

    8.   FAMILIARIZATION WITH WORKING CONDITIONS

    9.   CLARIFICATION

    10. PROPOSED PRICE

    11. CONTENTS OF PROPOSAL

    12. COSTS OF PREPARATION OF THE BIDDER'S PROPOSAL

    13. CONFIDENTIAL DATA AND INFORMATION

    14. TAXES AND DUTIES

    15. BILLS OF QUANTITIES


     Attachment-1 :         Project Summary

     Attachment-2 :         Technical Specifications

    Attachment-3 :          Bill of Quantities


                                          Page 1 of 9
Project Name : Samsung Naffora Techno Valley Project    Inquiry No. NB2231-PR-ITB-223
Job No.: NB2231




  1. GENERAL

     The Bidder is requested to submit to Samsung Saudi Arabia Ltd. (hereinafter called
     "SSA") a proposal based on the Inquiry Documents for the work as detailed in the Scope
     of Work and Supply attached thereto.

     The Bidder's proposal must comply with all Inquiry Documents in all respects.

     The Inquiry Documents consist of:

     (1)   Invitation to Bid
     (2)   Instruction to Bidders
     (3)   Requisition Sheets

     The Bidder is requested to confirm that all applicable documents stated herein are in his
     possession, and if any of them prove to be missing, to inform SSA promptly in order to
     obtain the same.

  2. SUBMISSION OF PROPOSAL

     1)    Number of copies and addressee

           One(1) original and two (2) copies of the Bidder's proposal duly signed by the
           Bidder's executive shall be submitted to the addressee given in Clause 3 below.
           Also one (1) soft copy of CD should be included (one original and two copy of
           proposal documents and CD copy must be sealed with your company envelopes)


     2)    Bid closing date

           The Bidder is requested to submit a proposal on or before the bid closing date
           specified in the Invitation to Bid.


     3)    Language

           The proposal and all related documents, including, such items as reports, studies,
           correspondence, and drawings, shall be in the English language.


     4)    Return of Inquiry Documents

           The unsuccessful Bidder shall immediately, upon receipt of SSA's notice, return to
           SSA all Inquiry Documents.


  3. COMMUNICATION

                                          Page 2 of 9
Project Name : Samsung Naffora Techno Valley Project      Inquiry No. NB2231-PR-ITB-223
Job No.: NB2231

     All communications shall be addressed as follows:

     1)    Address for Proposal Submission / Questionnaire / Clarification;
           (1 original and 2 copy to Samsung Saudi Arabia Co.LTD)

    Samsung Naffora Techno Valley Project.
    Samsung Engineering Co., Ltd.
    P.O. Box 35816 - Tareeg 120/207 Jubail Ind. City 31961 –
    Kingdom of Saudi Arabia

    Telephone No. : 966-3-340-8981 (Ext.127)
    Facsimile No. : 966-3-340-8984
    E-Mail: chulgoo.lee@samsung.com

  4. SCOPE OF WORK

     The Scope of Work will be as per the Drawings (Appendix 1), Technical Specifications
     (Attachment 2) and BOQ (Attachment 3).


  5. TERMS OF PAYMENT

     1)   Advance Payment (A/P)

              10 % of Contract Price subject to submission for equivalent amount of
             Bank Guarantee.
             Payment to be released within 45 calendar days of having received
             from the subcontractor the Advance Payment Bond, and the Performance Bond.

     2)   Monthly Progress Payment

              90 % of Contract Price based on monthly progress approved by SSA.
              (Deducting 10 % A/P and 10 % Retention Price from the Total Progress of work)
             Payment to be released within 45 calendar days following acceptance of
             relevant invoice.

     3)   Retention

               10     % of Contract Price

              Retention amounting to be applied to monthly progress payment

              Retention amount to be released to the contractor within 45 days from the initial
              Acceptance Date after receiving Warranty bond

     4)   Bond

          4-1)1. Advance Payment Bond (A/B)


                                            Page 3 of 9
Project Name : Samsung Naffora Techno Valley Project         Inquiry No. NB2231-PR-ITB-223
Job No.: NB2231

                10 % of Contract Price, and furnish within     14   days from the date of Contract
               signing

               A/B shall remain valid until the date of the initial Acceptance Date.

               A/B to be released to the contractor within 30 days after the initial Acceptance
               Date.
               .


            4-1)2. Performance Bond (P/B)

               10 % of Contract price, and furnish within 14 days from the date of Contract
               signing

               P/B shall remain valid until the initial Acceptance Date including punch work.

               P/B to be released within 30 days after the initial Acceptance Date.


            4-1)3. Warranty Bond (W/B)

                 10 % of the final, adjusted Contract price prior to receiving the Certificate of
                initial Acceptance

               W/B shall remain valid until expiration date of the Warranty Period

               W/B to be released within 30 days after issue of the Certificate of final
               Acceptance.

       5)    Warranty Period

                 15   Months from the initial Acceptance Date

       6)   Liquidated Damage

               Max 10 % of Contract Price
               0.01 % of Contract Price for each day delayed

       7)   Bank charge
            Any and all bank charge to be incurred for the receipt of any payments under the
            Bidder shall be at the Bidder’s account.


  6.        DEVIATION FROM INQUIRY DOCUMENTS

       1) In the event that the Bidder wishes to submit an alternative proposal, the Bidder shall
          firstly prepare his basic proposal strictly in accordance with the requirements and
          conditions hereof. In addition to the basic proposal, the Bidder may prepare an
          alternative proposal clearly indicating (1) technical reasons, (2) effects on price and
          (3) effects on the time schedule of works of the basic proposal.
                                            Page 4 of 9
Project Name : Samsung Naffora Techno Valley Project      Inquiry No. NB2231-PR-ITB-223
Job No.: NB2231


          SSA reserves the right to accept either the basic proposal or the alternative proposal
          but in the event that the basic proposal is accepted, the requirements and conditions
          of the Inquiry Documents shall be deemed to have been accepted by the Bidder. In
          the event of submission of an alternative proposal by the Bidder, the requirements
          and conditions of the Inquiry Documents to which no amendments and alternatives /
          deviations have been proposed by the Bidder at the time of the submission of the
          alternative proposal shall be deemed to have been accepted fully by the Bidder.


     2)    Any deviation and / or alterations from the inquiry conditions (commercial and
           technical) must be clearly and specifically stated in one section (to be titled
           "Deviations") of the proposal. SSA has no obligation to search for any deviations
           in other parts than the said "Deviation" section. In the event that the Bidder is
           awarded the contract, it will be on the basis only of those deviations and alterations
           included in such separate "Deviations" section and accepted by SSA.


  7. EVALUATION OF PROPOSAL

     The evaluation of the Bidder's proposal will not be limited to price but also take into
     account technical capability, working experienced in the related field, time schedule of
     works, reliability of execution plan, etc. It is therefore essential importance that all the
     information requested in "Requisition Sheets" herein below be constrained in the Bidder's
     proposal. The evaluation will be conducted under SSA's sole discretion and judgment.

  8. FAMILIARIZATION WITH WORKING CONDITIONS

     It is the Bidder's responsibility to familiarize himself with the Work to be performed in
     accordance with the Inquiry Documents, including but not limited to working conditions,
     location of work, and all other requirements, such as local conditions, applicable laws
     and regulations, labor condition, environmental aspects, etc., in order to submit a firm
     and comprehensive proposal. The Bidder shall also check and verify the local information
     contained in the Inquiry Documents and is expected to have fully satisfied himself
     thereon before submitting his proposal.

     The Bidder shall make his own arrangements and inquiries with regard to the loading,
     unloading and transport of all construction equipment and material required for the works.
     The Bidder shall make all necessary investigations as to the heaviest loads that can be
     handled at ports or transported to the work site by road, railway or river, in particular with
     regard to the weight-bearing capacity or all bridges and culverts, and the Bidder shall
     comply with all relevant regulations of the governmental departments in connection
     therewith.

  9. CLARIFICATION

     For clarification of or any query in respect of any part of the Inquiry Documents, the Bidder
     may contact SSA by e-mail or facsimile. Any clarification or reply by SSA will be advised
     to all Bidders as necessary for fair bid from all Bidders and shall not be valid or binding
     unless made in writing including e-mail or facsimile.

                                          Page 5 of 9
Project Name : Samsung Naffora Techno Valley Project       Inquiry No. NB2231-PR-ITB-223
Job No.: NB2231


  10. PROPOSED PRICE

     1)    Unit rates

           The Bidder shall propose unit rates for work by filling in the blanks of all tables
           contained in "Bill of Quantities (Attachment-3). An amount to absorb fluctuations
           in the costs of labor, construction equipment, materials and consumable shall be
           estimated and will be the Bidder's responsibility.

     2)    Currencies

           The Bidder shall quote all prices in the currencies of Saudi Arabia Riyal (SAR)

  11. CONTENTS OF PROPOSAL

     The contents of the Bidder's proposal should be explicit so that SSA can fully analyze the
     essence of the technical and commercial aspects. The Bidder's proposal shall include,
     without limitation, the data and information set out below.

     1)    Prices

           The Bidder shall fill in the blanks of "Bill of Quantities (Attachment-3)”.

     2)    Work organization chart

            The Bidder shall submit an organization chart for construction activities. The
            organization chart shall be accompanied by:

           -     A short description of responsibilities and scope of authority of various
                 personnel functions shall be shown

           -   Safety, quality assurance, and environmental protection functions shall be
               clearly shown.

     3)    Detailed construction schedule

           The Bidder is requested to submit his detailed construction schedule including all
           kind of works described in this Inquiry Document.

     4)    Manpower mobilization schedule

           The Bidder shall submit a manpower schedule for the work, which shall be
           accompanied by:

           -     Management & Supervisory Staff

                 The scheduled duration of assignment to site supervision for each member
                 describing local or foreigner shown in the Bidder's proposed organization
                 chart shall be shown in bar chart form.
                                           Page 6 of 9
Project Name : Samsung Naffora Techno Valley Project          Inquiry No. NB2231-PR-ITB-223
    Job No.: NB2231


                  -     Direct Labor/ Indirect Labor

                        The numbers of personnel identifying local or foreigner, up to and including
                        foreman level, which will be employed monthly shall be shown in tabulated
                        form.

                  The Bidder shall execute his work on the basis that all activity shall be performed
                  during ten (10) hours per working day and six (6) days per week.


            5)    Temporary facilities plan

                  The Bidder shall submit a layout plan including required surface area, descriptions
                  and capacities of all temporary facilities to be constructed by the Bidder. In
                  addition, Bidder is requested to present his plan for labor accommodation
                  especially for the necessity of camp and it’s operation.

                  In case of camp operation, Bidder shall provide the camp and related utilities for his
                  labors and these costs should be included in the unit rates quoted in the Bill of
                  Quantities (Attachment-3).
.

            6)    Experience on similar job

                  The Bidder shall submit a list of similar jobs executed by the Bidder for the past
                  years, indicating project name, location, Owner, value and period of work, also
                  stating clearly whether the Bidder carry out those job as a contractor or a
                  Subcontractor.

            7)    Information on the Bidder's volume of work in progress and current commitments

                   The Bidder shall submit an analysis of the Bidder's projected workload for all
                   construction works in progress and in future. These construction works shall be
                   individually identified by project, location and Owner.


            8)    QA / QC management

                  The Bidder shall submit his policy and management system established for
                  Company's QA / QC as well as the virtual practice in the project site.


      12.        COSTS OF PREPARATION OF THE CONTRACTOR'S PROPOSAL

                 The Bidder shall bear all necessary costs and expenses required for or in connection
                 with the preparation of the proposal and subsequent actions to be taken by the
                 Bidder up to the conclusion of the contract including site visits, clarifications of the
                 proposal and negotiations of the contract.


                                                 Page 7 of 9
Project Name : Samsung Naffora Techno Valley Project     Inquiry No. NB2231-PR-ITB-223
Job No.: NB2231


  13.    CONFIDENTIAL DATA AND INFORMATION

         The Bidder shall keep the data and information contained in the Inquiry Documents
         supplied by SSA strictly confidential.

  14.    TAXES AND DUTIES

         The Bidder will be required to fully comply with the local tax laws and regulations. To
         that end the Bidder is required to acquaint himself with the relevant laws and
         regulations relating to the importation of materials, corporate taxes and personal
         income taxes, etc.

  15.    BILL OF QUANTITIES

         The items of Work and their respective descriptions and quantities (hereinafter
         collectively referred to as “The Quantities”) contained in the Bill of Quantities have
         generally been measured drawings, the Standards manual and Specifications and
         have been included to assist the Tenderer in the preparation of his Tender. The
         accuracy of the Bill of Quantities is not guaranteed and Tenderers are strongly
         advised to check the quantities for themselves and to allow in their submitted rates
         and include items resulting from their design as they consider necessary for any
         errors or omissions.

         The quantities shown in the Bill of Quantities may be altered during tendering.
         However, since the intention of the Conditions of Contract is that no work will be
         remeasured, Contractor to consider BOQ quantities (quantities to be based on the
         drawings) as actual and correct and any error or omission from the BOQ provides no
         grounds to adjust the contract price. The contractor is required to execute the item of
         work as per the quantities based on the drawings, irrespective of the quantities
         mentioned in the BOQ for the corresponding item. Each item of work in the Bill of
         Quantities must be individually priced in the rate column, extended and brought to the
         total for the appropriate page (Summary Sheet “Attachment-3”). Failure to comply
         with these requirements may render the Tender null and void.




                                          Page 8 of 9

Weitere Àhnliche Inhalte

Was ist angesagt?

Civil construction draft contarct document
Civil construction draft contarct documentCivil construction draft contarct document
Civil construction draft contarct document
Haftamu Tekle
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
DarrenTofu
 
Big Ideas for Small Business: Chapter 188
Big Ideas for Small Business: Chapter 188Big Ideas for Small Business: Chapter 188
Big Ideas for Small Business: Chapter 188
CleEconomicDevelopment
 
PROJ CONSULTANCY- agreement - general-010415
PROJ CONSULTANCY- agreement - general-010415PROJ CONSULTANCY- agreement - general-010415
PROJ CONSULTANCY- agreement - general-010415
burhaan taskeen azad
 

Was ist angesagt? (20)

Contract lecture Note
 Contract  lecture Note Contract  lecture Note
Contract lecture Note
 
Civil construction draft contarct document
Civil construction draft contarct documentCivil construction draft contarct document
Civil construction draft contarct document
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Cl compilation
Cl compilationCl compilation
Cl compilation
 
Formation
FormationFormation
Formation
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
 
MEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONMEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATION
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
 
Big Ideas for Small Business: Chapter 188
Big Ideas for Small Business: Chapter 188Big Ideas for Small Business: Chapter 188
Big Ideas for Small Business: Chapter 188
 
Defects liability
Defects liabilityDefects liability
Defects liability
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
Dbc cdl 34 oc-crs_punaf1
Dbc cdl 34 oc-crs_punaf1Dbc cdl 34 oc-crs_punaf1
Dbc cdl 34 oc-crs_punaf1
 
Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final Report
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
 
Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1
 
PROJ CONSULTANCY- agreement - general-010415
PROJ CONSULTANCY- agreement - general-010415PROJ CONSULTANCY- agreement - general-010415
PROJ CONSULTANCY- agreement - general-010415
 
Procurement of work ICTAD sbd 01 2007
Procurement of work ICTAD sbd 01 2007Procurement of work ICTAD sbd 01 2007
Procurement of work ICTAD sbd 01 2007
 

Ähnlich wie (Interior const) instruction to bidders

Itt provision of wi fi network design and implementation services
Itt   provision of wi fi network design and implementation servicesItt   provision of wi fi network design and implementation services
Itt provision of wi fi network design and implementation services
abenyeung1
 
Document samples
Document samplesDocument samples
Document samples
Arthur Wilson
 
ZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docxZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docx
FairFASST
 
CE 444 Contracts and SpecificationsAssignment 7 - Conduct a 95
CE 444 Contracts and SpecificationsAssignment 7 -  Conduct a 95CE 444 Contracts and SpecificationsAssignment 7 -  Conduct a 95
CE 444 Contracts and SpecificationsAssignment 7 - Conduct a 95
MaximaSheffield592
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
Arvind Solanki
 
Contract Agreement - Longhaul Backbone Project
Contract Agreement - Longhaul Backbone ProjectContract Agreement - Longhaul Backbone Project
Contract Agreement - Longhaul Backbone Project
Khurram Shafique
 
Tendernotice_1 (1).pdf
Tendernotice_1 (1).pdfTendernotice_1 (1).pdf
Tendernotice_1 (1).pdf
ssusera91051
 

Ähnlich wie (Interior const) instruction to bidders (20)

Itt provision of wi fi network design and implementation services
Itt   provision of wi fi network design and implementation servicesItt   provision of wi fi network design and implementation services
Itt provision of wi fi network design and implementation services
 
1545313910708_TENDER_NOTICE_LAD.pdf
1545313910708_TENDER_NOTICE_LAD.pdf1545313910708_TENDER_NOTICE_LAD.pdf
1545313910708_TENDER_NOTICE_LAD.pdf
 
Document samples
Document samplesDocument samples
Document samples
 
Ms.jkr.20800.2005
Ms.jkr.20800.2005Ms.jkr.20800.2005
Ms.jkr.20800.2005
 
Cpm ch 2tender
Cpm ch 2tenderCpm ch 2tender
Cpm ch 2tender
 
tendering
 tendering tendering
tendering
 
scope - CCTV Tender.pdf
scope - CCTV Tender.pdfscope - CCTV Tender.pdf
scope - CCTV Tender.pdf
 
Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practice
 
STANDARD SPECIFICATIONS FOR BUILDING WORKS.pdf
STANDARD SPECIFICATIONS FOR BUILDING WORKS.pdfSTANDARD SPECIFICATIONS FOR BUILDING WORKS.pdf
STANDARD SPECIFICATIONS FOR BUILDING WORKS.pdf
 
Standard specifications for_building_wor
Standard specifications for_building_worStandard specifications for_building_wor
Standard specifications for_building_wor
 
MSP
MSPMSP
MSP
 
Tender
TenderTender
Tender
 
ZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docxZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docx
 
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
 
Bid document reverse tendering
Bid document reverse tenderingBid document reverse tendering
Bid document reverse tendering
 
Cl report final
Cl report finalCl report final
Cl report final
 
CE 444 Contracts and SpecificationsAssignment 7 - Conduct a 95
CE 444 Contracts and SpecificationsAssignment 7 -  Conduct a 95CE 444 Contracts and SpecificationsAssignment 7 -  Conduct a 95
CE 444 Contracts and SpecificationsAssignment 7 - Conduct a 95
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
Contract Agreement - Longhaul Backbone Project
Contract Agreement - Longhaul Backbone ProjectContract Agreement - Longhaul Backbone Project
Contract Agreement - Longhaul Backbone Project
 
Tendernotice_1 (1).pdf
Tendernotice_1 (1).pdfTendernotice_1 (1).pdf
Tendernotice_1 (1).pdf
 

KĂŒrzlich hochgeladen

CYTOTEC DUBAI ☎ +966572737505 } Abortion pills in Abu dhabi,get misoprostal ...
CYTOTEC DUBAI ☎ +966572737505 } Abortion pills in Abu dhabi,get misoprostal ...CYTOTEC DUBAI ☎ +966572737505 } Abortion pills in Abu dhabi,get misoprostal ...
CYTOTEC DUBAI ☎ +966572737505 } Abortion pills in Abu dhabi,get misoprostal ...
Abortion pills in Riyadh +966572737505 get cytotec
 
Sample sample sample sample sample sample
Sample sample sample sample sample sampleSample sample sample sample sample sample
Sample sample sample sample sample sample
Casey Keith
 
Visa Consultant in Lahore || 📞03094429236
Visa Consultant in Lahore || 📞03094429236Visa Consultant in Lahore || 📞03094429236
Visa Consultant in Lahore || 📞03094429236
Sherazi Tours
 
sample sample sample sample sample sample
sample sample sample sample sample samplesample sample sample sample sample sample
sample sample sample sample sample sample
Casey Keith
 
💕đŸ“Č09602870969💓Girl Escort Services Udaipur Call Girls in Chittorgarh Haldighati
💕đŸ“Č09602870969💓Girl Escort Services Udaipur Call Girls in Chittorgarh Haldighati💕đŸ“Č09602870969💓Girl Escort Services Udaipur Call Girls in Chittorgarh Haldighati
💕đŸ“Č09602870969💓Girl Escort Services Udaipur Call Girls in Chittorgarh Haldighati
Apsara Of India
 
Study Consultants in Lahore || 📞03094429236
Study Consultants in Lahore || 📞03094429236Study Consultants in Lahore || 📞03094429236
Study Consultants in Lahore || 📞03094429236
Sherazi Tours
 

KĂŒrzlich hochgeladen (20)

WhatsApp Chat: 📞 8617697112 Independent Call Girls in Darjeeling
WhatsApp Chat: 📞 8617697112 Independent Call Girls in DarjeelingWhatsApp Chat: 📞 8617697112 Independent Call Girls in Darjeeling
WhatsApp Chat: 📞 8617697112 Independent Call Girls in Darjeeling
 
CYTOTEC DUBAI ☎ +966572737505 } Abortion pills in Abu dhabi,get misoprostal ...
CYTOTEC DUBAI ☎ +966572737505 } Abortion pills in Abu dhabi,get misoprostal ...CYTOTEC DUBAI ☎ +966572737505 } Abortion pills in Abu dhabi,get misoprostal ...
CYTOTEC DUBAI ☎ +966572737505 } Abortion pills in Abu dhabi,get misoprostal ...
 
Genuine 9332606886 Hot and Beautiful 💕 Bilaspur Escorts call Girls
Genuine 9332606886 Hot and Beautiful 💕 Bilaspur Escorts call GirlsGenuine 9332606886 Hot and Beautiful 💕 Bilaspur Escorts call Girls
Genuine 9332606886 Hot and Beautiful 💕 Bilaspur Escorts call Girls
 
Genuine 8250077686 Hot and Beautiful 💕 Visakhapatnam Escorts call Girls
Genuine 8250077686 Hot and Beautiful 💕 Visakhapatnam Escorts call GirlsGenuine 8250077686 Hot and Beautiful 💕 Visakhapatnam Escorts call Girls
Genuine 8250077686 Hot and Beautiful 💕 Visakhapatnam Escorts call Girls
 
Sample sample sample sample sample sample
Sample sample sample sample sample sampleSample sample sample sample sample sample
Sample sample sample sample sample sample
 
Visa Consultant in Lahore || 📞03094429236
Visa Consultant in Lahore || 📞03094429236Visa Consultant in Lahore || 📞03094429236
Visa Consultant in Lahore || 📞03094429236
 
Night 7k to 12k Lahaul and Spiti Call Girls 👉👉 8617697112⭐⭐ 100% Genuine Esco...
Night 7k to 12k Lahaul and Spiti Call Girls 👉👉 8617697112⭐⭐ 100% Genuine Esco...Night 7k to 12k Lahaul and Spiti Call Girls 👉👉 8617697112⭐⭐ 100% Genuine Esco...
Night 7k to 12k Lahaul and Spiti Call Girls 👉👉 8617697112⭐⭐ 100% Genuine Esco...
 
Hire 8617697112 Call Girls Udhampur For an Amazing Night
Hire 8617697112 Call Girls Udhampur For an Amazing NightHire 8617697112 Call Girls Udhampur For an Amazing Night
Hire 8617697112 Call Girls Udhampur For an Amazing Night
 
Ooty call girls 📞 8617697112 At Low Cost Cash Payment Booking
Ooty call girls 📞 8617697112 At Low Cost Cash Payment BookingOoty call girls 📞 8617697112 At Low Cost Cash Payment Booking
Ooty call girls 📞 8617697112 At Low Cost Cash Payment Booking
 
ITALY - Visa Options for expats and digital nomads
ITALY - Visa Options for expats and digital nomadsITALY - Visa Options for expats and digital nomads
ITALY - Visa Options for expats and digital nomads
 
Night 7k to 12k Daman Call Girls 👉👉 8617697112⭐⭐ 100% Genuine Escort Service ...
Night 7k to 12k Daman Call Girls 👉👉 8617697112⭐⭐ 100% Genuine Escort Service ...Night 7k to 12k Daman Call Girls 👉👉 8617697112⭐⭐ 100% Genuine Escort Service ...
Night 7k to 12k Daman Call Girls 👉👉 8617697112⭐⭐ 100% Genuine Escort Service ...
 
Kolkata Call Girls - 📞 8617697112 🔝 Top Class Call Girls Service Available
Kolkata Call Girls - 📞 8617697112 🔝 Top Class Call Girls Service AvailableKolkata Call Girls - 📞 8617697112 🔝 Top Class Call Girls Service Available
Kolkata Call Girls - 📞 8617697112 🔝 Top Class Call Girls Service Available
 
WhatsApp Chat: 📞 8617697112 Hire Call Girls Cooch Behar For a Sensual Sex Exp...
WhatsApp Chat: 📞 8617697112 Hire Call Girls Cooch Behar For a Sensual Sex Exp...WhatsApp Chat: 📞 8617697112 Hire Call Girls Cooch Behar For a Sensual Sex Exp...
WhatsApp Chat: 📞 8617697112 Hire Call Girls Cooch Behar For a Sensual Sex Exp...
 
sample sample sample sample sample sample
sample sample sample sample sample samplesample sample sample sample sample sample
sample sample sample sample sample sample
 
Kanpur Call Girls Service ☎ 82500–77686 ☎ Enjoy 24/7 Escort Service
Kanpur Call Girls Service ☎ 82500–77686 ☎ Enjoy 24/7 Escort ServiceKanpur Call Girls Service ☎ 82500–77686 ☎ Enjoy 24/7 Escort Service
Kanpur Call Girls Service ☎ 82500–77686 ☎ Enjoy 24/7 Escort Service
 
💕đŸ“Č09602870969💓Girl Escort Services Udaipur Call Girls in Chittorgarh Haldighati
💕đŸ“Č09602870969💓Girl Escort Services Udaipur Call Girls in Chittorgarh Haldighati💕đŸ“Č09602870969💓Girl Escort Services Udaipur Call Girls in Chittorgarh Haldighati
💕đŸ“Č09602870969💓Girl Escort Services Udaipur Call Girls in Chittorgarh Haldighati
 
08448380779 Call Girls In Chirag Enclave Women Seeking Men
08448380779 Call Girls In Chirag Enclave Women Seeking Men08448380779 Call Girls In Chirag Enclave Women Seeking Men
08448380779 Call Girls In Chirag Enclave Women Seeking Men
 
Hire 💕 8617697112 Reckong Peo Call Girls Service Call Girls Agency
Hire 💕 8617697112 Reckong Peo Call Girls Service Call Girls AgencyHire 💕 8617697112 Reckong Peo Call Girls Service Call Girls Agency
Hire 💕 8617697112 Reckong Peo Call Girls Service Call Girls Agency
 
❀Personal Contact Number Mcleodganj Call Girls 8617697112💩✅.
❀Personal Contact Number Mcleodganj Call Girls 8617697112💩✅.❀Personal Contact Number Mcleodganj Call Girls 8617697112💩✅.
❀Personal Contact Number Mcleodganj Call Girls 8617697112💩✅.
 
Study Consultants in Lahore || 📞03094429236
Study Consultants in Lahore || 📞03094429236Study Consultants in Lahore || 📞03094429236
Study Consultants in Lahore || 📞03094429236
 

(Interior const) instruction to bidders

  • 1. Project Name : Samsung Naffora Techno Valley Project Inquiry No. NB2231-PR-ITB-223 Job No.: NB2231 INSTRUCTION TO BIDDERS
  • 2. Project Name : Samsung Naffora Techno Valley Project Inquiry No. NB2231-PR-ITB-223 Job No.: NB2231 INSTRUCTION TO BIDDERS INDEX 1. GENERAL 2. SUBMISSION OF PROPOSAL 3. COMMUNICATION 4. SCOPE OF WORK 5. TERMS OF PAYMENT 6. DEVIATION FROM INQUIRY DOCUMENTS 7. EVALUATION OF PROPOSAL 8. FAMILIARIZATION WITH WORKING CONDITIONS 9. CLARIFICATION 10. PROPOSED PRICE 11. CONTENTS OF PROPOSAL 12. COSTS OF PREPARATION OF THE BIDDER'S PROPOSAL 13. CONFIDENTIAL DATA AND INFORMATION 14. TAXES AND DUTIES 15. BILLS OF QUANTITIES Attachment-1 : Project Summary Attachment-2 : Technical Specifications Attachment-3 : Bill of Quantities Page 1 of 9
  • 3. Project Name : Samsung Naffora Techno Valley Project Inquiry No. NB2231-PR-ITB-223 Job No.: NB2231 1. GENERAL The Bidder is requested to submit to Samsung Saudi Arabia Ltd. (hereinafter called "SSA") a proposal based on the Inquiry Documents for the work as detailed in the Scope of Work and Supply attached thereto. The Bidder's proposal must comply with all Inquiry Documents in all respects. The Inquiry Documents consist of: (1) Invitation to Bid (2) Instruction to Bidders (3) Requisition Sheets The Bidder is requested to confirm that all applicable documents stated herein are in his possession, and if any of them prove to be missing, to inform SSA promptly in order to obtain the same. 2. SUBMISSION OF PROPOSAL 1) Number of copies and addressee One(1) original and two (2) copies of the Bidder's proposal duly signed by the Bidder's executive shall be submitted to the addressee given in Clause 3 below. Also one (1) soft copy of CD should be included (one original and two copy of proposal documents and CD copy must be sealed with your company envelopes) 2) Bid closing date The Bidder is requested to submit a proposal on or before the bid closing date specified in the Invitation to Bid. 3) Language The proposal and all related documents, including, such items as reports, studies, correspondence, and drawings, shall be in the English language. 4) Return of Inquiry Documents The unsuccessful Bidder shall immediately, upon receipt of SSA's notice, return to SSA all Inquiry Documents. 3. COMMUNICATION Page 2 of 9
  • 4. Project Name : Samsung Naffora Techno Valley Project Inquiry No. NB2231-PR-ITB-223 Job No.: NB2231 All communications shall be addressed as follows: 1) Address for Proposal Submission / Questionnaire / Clarification; (1 original and 2 copy to Samsung Saudi Arabia Co.LTD) Samsung Naffora Techno Valley Project. Samsung Engineering Co., Ltd. P.O. Box 35816 - Tareeg 120/207 Jubail Ind. City 31961 – Kingdom of Saudi Arabia Telephone No. : 966-3-340-8981 (Ext.127) Facsimile No. : 966-3-340-8984 E-Mail: chulgoo.lee@samsung.com 4. SCOPE OF WORK The Scope of Work will be as per the Drawings (Appendix 1), Technical Specifications (Attachment 2) and BOQ (Attachment 3). 5. TERMS OF PAYMENT 1) Advance Payment (A/P) 10 % of Contract Price subject to submission for equivalent amount of Bank Guarantee. Payment to be released within 45 calendar days of having received from the subcontractor the Advance Payment Bond, and the Performance Bond. 2) Monthly Progress Payment 90 % of Contract Price based on monthly progress approved by SSA. (Deducting 10 % A/P and 10 % Retention Price from the Total Progress of work) Payment to be released within 45 calendar days following acceptance of relevant invoice. 3) Retention 10 % of Contract Price Retention amounting to be applied to monthly progress payment Retention amount to be released to the contractor within 45 days from the initial Acceptance Date after receiving Warranty bond 4) Bond 4-1)1. Advance Payment Bond (A/B) Page 3 of 9
  • 5. Project Name : Samsung Naffora Techno Valley Project Inquiry No. NB2231-PR-ITB-223 Job No.: NB2231 10 % of Contract Price, and furnish within 14 days from the date of Contract signing A/B shall remain valid until the date of the initial Acceptance Date. A/B to be released to the contractor within 30 days after the initial Acceptance Date. . 4-1)2. Performance Bond (P/B) 10 % of Contract price, and furnish within 14 days from the date of Contract signing P/B shall remain valid until the initial Acceptance Date including punch work. P/B to be released within 30 days after the initial Acceptance Date. 4-1)3. Warranty Bond (W/B) 10 % of the final, adjusted Contract price prior to receiving the Certificate of initial Acceptance W/B shall remain valid until expiration date of the Warranty Period W/B to be released within 30 days after issue of the Certificate of final Acceptance. 5) Warranty Period 15 Months from the initial Acceptance Date 6) Liquidated Damage Max 10 % of Contract Price 0.01 % of Contract Price for each day delayed 7) Bank charge Any and all bank charge to be incurred for the receipt of any payments under the Bidder shall be at the Bidder’s account. 6. DEVIATION FROM INQUIRY DOCUMENTS 1) In the event that the Bidder wishes to submit an alternative proposal, the Bidder shall firstly prepare his basic proposal strictly in accordance with the requirements and conditions hereof. In addition to the basic proposal, the Bidder may prepare an alternative proposal clearly indicating (1) technical reasons, (2) effects on price and (3) effects on the time schedule of works of the basic proposal. Page 4 of 9
  • 6. Project Name : Samsung Naffora Techno Valley Project Inquiry No. NB2231-PR-ITB-223 Job No.: NB2231 SSA reserves the right to accept either the basic proposal or the alternative proposal but in the event that the basic proposal is accepted, the requirements and conditions of the Inquiry Documents shall be deemed to have been accepted by the Bidder. In the event of submission of an alternative proposal by the Bidder, the requirements and conditions of the Inquiry Documents to which no amendments and alternatives / deviations have been proposed by the Bidder at the time of the submission of the alternative proposal shall be deemed to have been accepted fully by the Bidder. 2) Any deviation and / or alterations from the inquiry conditions (commercial and technical) must be clearly and specifically stated in one section (to be titled "Deviations") of the proposal. SSA has no obligation to search for any deviations in other parts than the said "Deviation" section. In the event that the Bidder is awarded the contract, it will be on the basis only of those deviations and alterations included in such separate "Deviations" section and accepted by SSA. 7. EVALUATION OF PROPOSAL The evaluation of the Bidder's proposal will not be limited to price but also take into account technical capability, working experienced in the related field, time schedule of works, reliability of execution plan, etc. It is therefore essential importance that all the information requested in "Requisition Sheets" herein below be constrained in the Bidder's proposal. The evaluation will be conducted under SSA's sole discretion and judgment. 8. FAMILIARIZATION WITH WORKING CONDITIONS It is the Bidder's responsibility to familiarize himself with the Work to be performed in accordance with the Inquiry Documents, including but not limited to working conditions, location of work, and all other requirements, such as local conditions, applicable laws and regulations, labor condition, environmental aspects, etc., in order to submit a firm and comprehensive proposal. The Bidder shall also check and verify the local information contained in the Inquiry Documents and is expected to have fully satisfied himself thereon before submitting his proposal. The Bidder shall make his own arrangements and inquiries with regard to the loading, unloading and transport of all construction equipment and material required for the works. The Bidder shall make all necessary investigations as to the heaviest loads that can be handled at ports or transported to the work site by road, railway or river, in particular with regard to the weight-bearing capacity or all bridges and culverts, and the Bidder shall comply with all relevant regulations of the governmental departments in connection therewith. 9. CLARIFICATION For clarification of or any query in respect of any part of the Inquiry Documents, the Bidder may contact SSA by e-mail or facsimile. Any clarification or reply by SSA will be advised to all Bidders as necessary for fair bid from all Bidders and shall not be valid or binding unless made in writing including e-mail or facsimile. Page 5 of 9
  • 7. Project Name : Samsung Naffora Techno Valley Project Inquiry No. NB2231-PR-ITB-223 Job No.: NB2231 10. PROPOSED PRICE 1) Unit rates The Bidder shall propose unit rates for work by filling in the blanks of all tables contained in "Bill of Quantities (Attachment-3). An amount to absorb fluctuations in the costs of labor, construction equipment, materials and consumable shall be estimated and will be the Bidder's responsibility. 2) Currencies The Bidder shall quote all prices in the currencies of Saudi Arabia Riyal (SAR) 11. CONTENTS OF PROPOSAL The contents of the Bidder's proposal should be explicit so that SSA can fully analyze the essence of the technical and commercial aspects. The Bidder's proposal shall include, without limitation, the data and information set out below. 1) Prices The Bidder shall fill in the blanks of "Bill of Quantities (Attachment-3)”. 2) Work organization chart The Bidder shall submit an organization chart for construction activities. The organization chart shall be accompanied by: - A short description of responsibilities and scope of authority of various personnel functions shall be shown - Safety, quality assurance, and environmental protection functions shall be clearly shown. 3) Detailed construction schedule The Bidder is requested to submit his detailed construction schedule including all kind of works described in this Inquiry Document. 4) Manpower mobilization schedule The Bidder shall submit a manpower schedule for the work, which shall be accompanied by: - Management & Supervisory Staff The scheduled duration of assignment to site supervision for each member describing local or foreigner shown in the Bidder's proposed organization chart shall be shown in bar chart form. Page 6 of 9
  • 8. Project Name : Samsung Naffora Techno Valley Project Inquiry No. NB2231-PR-ITB-223 Job No.: NB2231 - Direct Labor/ Indirect Labor The numbers of personnel identifying local or foreigner, up to and including foreman level, which will be employed monthly shall be shown in tabulated form. The Bidder shall execute his work on the basis that all activity shall be performed during ten (10) hours per working day and six (6) days per week. 5) Temporary facilities plan The Bidder shall submit a layout plan including required surface area, descriptions and capacities of all temporary facilities to be constructed by the Bidder. In addition, Bidder is requested to present his plan for labor accommodation especially for the necessity of camp and it’s operation. In case of camp operation, Bidder shall provide the camp and related utilities for his labors and these costs should be included in the unit rates quoted in the Bill of Quantities (Attachment-3). . 6) Experience on similar job The Bidder shall submit a list of similar jobs executed by the Bidder for the past years, indicating project name, location, Owner, value and period of work, also stating clearly whether the Bidder carry out those job as a contractor or a Subcontractor. 7) Information on the Bidder's volume of work in progress and current commitments The Bidder shall submit an analysis of the Bidder's projected workload for all construction works in progress and in future. These construction works shall be individually identified by project, location and Owner. 8) QA / QC management The Bidder shall submit his policy and management system established for Company's QA / QC as well as the virtual practice in the project site. 12. COSTS OF PREPARATION OF THE CONTRACTOR'S PROPOSAL The Bidder shall bear all necessary costs and expenses required for or in connection with the preparation of the proposal and subsequent actions to be taken by the Bidder up to the conclusion of the contract including site visits, clarifications of the proposal and negotiations of the contract. Page 7 of 9
  • 9. Project Name : Samsung Naffora Techno Valley Project Inquiry No. NB2231-PR-ITB-223 Job No.: NB2231 13. CONFIDENTIAL DATA AND INFORMATION The Bidder shall keep the data and information contained in the Inquiry Documents supplied by SSA strictly confidential. 14. TAXES AND DUTIES The Bidder will be required to fully comply with the local tax laws and regulations. To that end the Bidder is required to acquaint himself with the relevant laws and regulations relating to the importation of materials, corporate taxes and personal income taxes, etc. 15. BILL OF QUANTITIES The items of Work and their respective descriptions and quantities (hereinafter collectively referred to as “The Quantities”) contained in the Bill of Quantities have generally been measured drawings, the Standards manual and Specifications and have been included to assist the Tenderer in the preparation of his Tender. The accuracy of the Bill of Quantities is not guaranteed and Tenderers are strongly advised to check the quantities for themselves and to allow in their submitted rates and include items resulting from their design as they consider necessary for any errors or omissions. The quantities shown in the Bill of Quantities may be altered during tendering. However, since the intention of the Conditions of Contract is that no work will be remeasured, Contractor to consider BOQ quantities (quantities to be based on the drawings) as actual and correct and any error or omission from the BOQ provides no grounds to adjust the contract price. The contractor is required to execute the item of work as per the quantities based on the drawings, irrespective of the quantities mentioned in the BOQ for the corresponding item. Each item of work in the Bill of Quantities must be individually priced in the rate column, extended and brought to the total for the appropriate page (Summary Sheet “Attachment-3”). Failure to comply with these requirements may render the Tender null and void. Page 8 of 9