SERI INTAN APARTMENT TYPE B - INTERMEDIATE
LEE PEI GIE
TIMBER LOUVRED WINDOW 16 /11 / 2015
A
B
C
D
E
F
G
Precast Concrete Lintel
115 mm x 150mm depth precastconcrete grade 20
lintel reinforced with 2 nos 12mm diameter high tensile
bars and 6mm mild steel stirrup at150mm centre and
bedded in cementand sand (1:3) mortar.
Packing Piece
75mm x 20mm sawn pressure treated Grade B timber
guard fixed to brickwork & concrete work.
Purpose made window and frame
585mm x 940mm Grade B hardwood timber window
frames all as per manufacture detail.
Aluminium Adjustable Louvre Window
Pair single control aluminium adjustable louvre stiles
880mm high each with clips for 7 nos 150mm wide
glass louvred & screwed to timber frame.
Glazing
512mm x 150mm x6mm thick clear glass and fix into
clips of louvred stiles.
Painting
Prepare and apply one coat of Nippon Hydro Primer or
other approved equivalentprimer paints as described
on:
General surface of timber not exceeding 150mm girth
Knotting, stopping and applyone coat of Nippon Hydro
Primer,one Nippon Odourlite Undercoatand two
finishing coats ofNippon Odourlite or other approved
equivalentgloss paintas described on:
Glasslouvredwindow
M
M
NO
NO
NO
M
M²
2
6
2
2
14
13
2
TO COLLECTION (RM)
LEE PEI GIE
SERI INTAN APARTMENT TYPE B - INTERMEDIATE
TIMBER FRAME DOOR 16 /11 / 2015
A
B
C
D
E
F
G
H
I
Precast Concrete Lintel
115 mm x 150mm depth precastconcrete grade 20
lintel reinforced with 2 nos 12mm diameter high tensile
bars and 6mm mild steel stirrup at150mm centre and
bedded in cementand sand (1:3) mortar.
Packing Piece
75mm x 20mm sawn pressure treated Grade B timber
guard fixed to brickwork & concrete work.
Timber Door Frame
115mmx60mm grade B wrot pressure treated timber
rebated head & jambs screwed to packing piece.
Timber Door Leaf
780mm x 2070mm x35mm thick Grade B hardwood
timber flush door all as per manufacture details.
Ironmongeries
Supply and fix the following or other
equal and approved ironmongerycomplete
with requisite matching screws:-
Allgood 100mm 2 steel butt hinges and fix to door leaf.
Dexter by Schlage J54CNA630 stainless steel cylinder
lockset.
Painting
Prepare and apply one coat of Nippon Hydro Primer or
other approved equivalent primer paints as described
on:
Timber guard and timber frame not exceeding
150mm girth
Knotting, stopping and applyone coat of Nippon Hydro
Primer,one Nippon Odourlite Undercoatand two
finishing coats of Nippon Odourlite or other approved
equivalentgloss enamel paint as desribed on:
Timber door frame,exceeding 150mm butnot
exceeding 300mm
Knotting, stopping and applyone coat of Nippon Hydro
Primer,one Nippon Odourlite Undercoatand two
finishing coats of Nippon Odourlite or other approved
equivalentgloss paint as desribed on:
Timberpanel doorleaf,over300mm girth
M
M
M
NO
NO
NO
M
M
M²
1
5
5
1
3
1
10
5
3
TO COLLECTION (RM)

Weitere ähnliche Inhalte

Was ist angesagt?

Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of QuantityArissa Loh
 
5) int walls finishes bq
5) int walls finishes bq5) int walls finishes bq
5) int walls finishes bqJeanne Hoo
 
Measurement III:Doors & Windows
Measurement III:Doors & WindowsMeasurement III:Doors & Windows
Measurement III:Doors & Windows마 이환
 
M3 EG BQ steel struture
M3 EG BQ steel strutureM3 EG BQ steel struture
M3 EG BQ steel strutureEst
 
10) int floor-finishes-1-query-list
10) int floor-finishes-1-query-list10) int floor-finishes-1-query-list
10) int floor-finishes-1-query-listJeanne Hoo
 
How do you takeoff a staircase?
How do you takeoff a staircase?How do you takeoff a staircase?
How do you takeoff a staircase?Duc Tran Xuan
 
Bq preamble
Bq preambleBq preamble
Bq preambleaizat76
 
PORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsPORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsGrace Henry
 
Exterior and interior Finishes- Building Construction
Exterior and interior Finishes- Building ConstructionExterior and interior Finishes- Building Construction
Exterior and interior Finishes- Building ConstructionTaha Padrawala
 
Long span structures in Concrete and Steel
Long span structures in Concrete and SteelLong span structures in Concrete and Steel
Long span structures in Concrete and SteelRithika Ravishankar
 
Building Technology 1 (Project 1)
Building Technology 1 (Project 1)Building Technology 1 (Project 1)
Building Technology 1 (Project 1)Soh Shing
 
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYTHUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYSSudhaVelan
 

Was ist angesagt? (20)

Bill Of Quantities
Bill Of QuantitiesBill Of Quantities
Bill Of Quantities
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of Quantity
 
long span roof
long span rooflong span roof
long span roof
 
5) int walls finishes bq
5) int walls finishes bq5) int walls finishes bq
5) int walls finishes bq
 
Measurement III:Doors & Windows
Measurement III:Doors & WindowsMeasurement III:Doors & Windows
Measurement III:Doors & Windows
 
M3 EG BQ steel struture
M3 EG BQ steel strutureM3 EG BQ steel struture
M3 EG BQ steel struture
 
10) int floor-finishes-1-query-list
10) int floor-finishes-1-query-list10) int floor-finishes-1-query-list
10) int floor-finishes-1-query-list
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 
How do you takeoff a staircase?
How do you takeoff a staircase?How do you takeoff a staircase?
How do you takeoff a staircase?
 
Car park bq
Car park bqCar park bq
Car park bq
 
Bq preamble
Bq preambleBq preamble
Bq preamble
 
PORTAL FRAME- Structural systems
PORTAL FRAME- Structural systemsPORTAL FRAME- Structural systems
PORTAL FRAME- Structural systems
 
R.C.C. STAIRS
R.C.C. STAIRSR.C.C. STAIRS
R.C.C. STAIRS
 
Exterior and interior Finishes- Building Construction
Exterior and interior Finishes- Building ConstructionExterior and interior Finishes- Building Construction
Exterior and interior Finishes- Building Construction
 
Long span structures in Concrete and Steel
Long span structures in Concrete and SteelLong span structures in Concrete and Steel
Long span structures in Concrete and Steel
 
Floor finishes
Floor finishesFloor finishes
Floor finishes
 
Building Technology 1 (Project 1)
Building Technology 1 (Project 1)Building Technology 1 (Project 1)
Building Technology 1 (Project 1)
 
Aluminium doors and Windows
Aluminium doors and WindowsAluminium doors and Windows
Aluminium doors and Windows
 
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYTHUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
 
Wall finishes
Wall finishesWall finishes
Wall finishes
 

Andere mochten auch

Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantitiesBt Lee
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second editionBt Lee
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantitiesalanchong88
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantityhlksd
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and materialALI HYDER GADHI
 
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATESGeneral notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATESR.R.G.S Bandara
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationHarish Mahavar
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
 
Excavation2014a-Lecture1
Excavation2014a-Lecture1Excavation2014a-Lecture1
Excavation2014a-Lecture1Anne Allan
 
Quantity surveying course
Quantity surveying courseQuantity surveying course
Quantity surveying courseJavid Hussain
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveyingsooricivil
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYINGlizwi nyandu
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveyingAwanish Shukla
 
Measurment 3 (qsb 60304) module outline - 28 march 2016
Measurment 3 (qsb 60304)   module outline - 28 march 2016Measurment 3 (qsb 60304)   module outline - 28 march 2016
Measurment 3 (qsb 60304) module outline - 28 march 2016Est
 
Measurement assignment 2 (group)
Measurement assignment 2 (group)Measurement assignment 2 (group)
Measurement assignment 2 (group)Syafiq Zariful
 
Measurement 4 Assignment Presentation
Measurement 4 Assignment PresentationMeasurement 4 Assignment Presentation
Measurement 4 Assignment PresentationHaziq1511
 
KA6564 Assignment 1
KA6564 Assignment 1KA6564 Assignment 1
KA6564 Assignment 1armada7000
 
Concrete 2014a-Lecture7
Concrete 2014a-Lecture7Concrete 2014a-Lecture7
Concrete 2014a-Lecture7Anne Allan
 
Quantity surveyor (ici+itd)
Quantity surveyor (ici+itd)Quantity surveyor (ici+itd)
Quantity surveyor (ici+itd)ALISON TANG
 

Andere mochten auch (20)

Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second edition
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantity
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATESGeneral notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATES
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
Excavation2014a-Lecture1
Excavation2014a-Lecture1Excavation2014a-Lecture1
Excavation2014a-Lecture1
 
Quantity surveying course
Quantity surveying courseQuantity surveying course
Quantity surveying course
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
 
Measurment 3 (qsb 60304) module outline - 28 march 2016
Measurment 3 (qsb 60304)   module outline - 28 march 2016Measurment 3 (qsb 60304)   module outline - 28 march 2016
Measurment 3 (qsb 60304) module outline - 28 march 2016
 
Measurement assignment 2 (group)
Measurement assignment 2 (group)Measurement assignment 2 (group)
Measurement assignment 2 (group)
 
Measurement 4 Assignment Presentation
Measurement 4 Assignment PresentationMeasurement 4 Assignment Presentation
Measurement 4 Assignment Presentation
 
How to pour concrete
How to pour concreteHow to pour concrete
How to pour concrete
 
KA6564 Assignment 1
KA6564 Assignment 1KA6564 Assignment 1
KA6564 Assignment 1
 
Concrete 2014a-Lecture7
Concrete 2014a-Lecture7Concrete 2014a-Lecture7
Concrete 2014a-Lecture7
 
Quantity surveyor (ici+itd)
Quantity surveyor (ici+itd)Quantity surveyor (ici+itd)
Quantity surveyor (ici+itd)
 

Ähnlich wie Bill of Quantities ( Door and Window )

Supplier's rates updated
Supplier's rates updatedSupplier's rates updated
Supplier's rates updatedArthur Wilson
 
Freelance project management case studies - residential
Freelance project management case studies - residentialFreelance project management case studies - residential
Freelance project management case studies - residentialgrahamelanders
 
Freelance project management residential
Freelance project management residentialFreelance project management residential
Freelance project management residentialgrahamelanders
 
Freelance project management residential
Freelance project management residentialFreelance project management residential
Freelance project management residentialgrahamelanders
 
Lynca Meats - Pork Factory - Meyerton - Details 02
Lynca Meats - Pork Factory - Meyerton - Details 02Lynca Meats - Pork Factory - Meyerton - Details 02
Lynca Meats - Pork Factory - Meyerton - Details 02Trevain Bechan
 
Kitsen K100 Detailed Pictures (components, packaging & loading and projects)
Kitsen K100 Detailed Pictures (components, packaging & loading and projects)Kitsen K100 Detailed Pictures (components, packaging & loading and projects)
Kitsen K100 Detailed Pictures (components, packaging & loading and projects)AshleyLiKITSEN
 
Jack_Lambourne - Portfolio
Jack_Lambourne - PortfolioJack_Lambourne - Portfolio
Jack_Lambourne - PortfolioJack Lambourne
 
Lynca Meats - Pork Factory - Meyerton - Details 01
Lynca Meats - Pork Factory - Meyerton - Details 01Lynca Meats - Pork Factory - Meyerton - Details 01
Lynca Meats - Pork Factory - Meyerton - Details 01Trevain Bechan
 
Design Portfolio by Aaron Kaira
Design Portfolio by Aaron KairaDesign Portfolio by Aaron Kaira
Design Portfolio by Aaron KairaAaron Kaira
 
Porta Cabin Presentation
Porta Cabin PresentationPorta Cabin Presentation
Porta Cabin Presentationamcoengg
 
Catalog - pvc panel
Catalog - pvc panelCatalog - pvc panel
Catalog - pvc panelJustin Guo
 
Warmline range Data Sheets
Warmline range  Data SheetsWarmline range  Data Sheets
Warmline range Data SheetsMarcus Maher
 
Revit project No. 3 Thesis - Exhibition posters
 Revit project No. 3 Thesis - Exhibition posters Revit project No. 3 Thesis - Exhibition posters
Revit project No. 3 Thesis - Exhibition postersTej Raj Upreti
 
Tech_Brochure_Cladding_Remake_Booklet_LQ_Email
Tech_Brochure_Cladding_Remake_Booklet_LQ_EmailTech_Brochure_Cladding_Remake_Booklet_LQ_Email
Tech_Brochure_Cladding_Remake_Booklet_LQ_EmailMiddle East Insulation LLC
 

Ähnlich wie Bill of Quantities ( Door and Window ) (20)

Supplier's rates updated
Supplier's rates updatedSupplier's rates updated
Supplier's rates updated
 
Item
ItemItem
Item
 
Freelance project management case studies - residential
Freelance project management case studies - residentialFreelance project management case studies - residential
Freelance project management case studies - residential
 
Freelance project management residential
Freelance project management residentialFreelance project management residential
Freelance project management residential
 
Freelance project management residential
Freelance project management residentialFreelance project management residential
Freelance project management residential
 
Lynca Meats - Pork Factory - Meyerton - Details 02
Lynca Meats - Pork Factory - Meyerton - Details 02Lynca Meats - Pork Factory - Meyerton - Details 02
Lynca Meats - Pork Factory - Meyerton - Details 02
 
Kitsen K100 Detailed Pictures (components, packaging & loading and projects)
Kitsen K100 Detailed Pictures (components, packaging & loading and projects)Kitsen K100 Detailed Pictures (components, packaging & loading and projects)
Kitsen K100 Detailed Pictures (components, packaging & loading and projects)
 
Jack_Lambourne - Portfolio
Jack_Lambourne - PortfolioJack_Lambourne - Portfolio
Jack_Lambourne - Portfolio
 
Lynca Meats - Pork Factory - Meyerton - Details 01
Lynca Meats - Pork Factory - Meyerton - Details 01Lynca Meats - Pork Factory - Meyerton - Details 01
Lynca Meats - Pork Factory - Meyerton - Details 01
 
Design Portfolio by Aaron Kaira
Design Portfolio by Aaron KairaDesign Portfolio by Aaron Kaira
Design Portfolio by Aaron Kaira
 
Porta Cabin Presentation
Porta Cabin PresentationPorta Cabin Presentation
Porta Cabin Presentation
 
Branddeur
Branddeur Branddeur
Branddeur
 
7545 102 final elevations as proposed
7545 102 final elevations as proposed7545 102 final elevations as proposed
7545 102 final elevations as proposed
 
Steel Siding 101
Steel Siding 101Steel Siding 101
Steel Siding 101
 
Partitions
PartitionsPartitions
Partitions
 
WOODlife Eco Decking
WOODlife Eco DeckingWOODlife Eco Decking
WOODlife Eco Decking
 
Catalog - pvc panel
Catalog - pvc panelCatalog - pvc panel
Catalog - pvc panel
 
Warmline range Data Sheets
Warmline range  Data SheetsWarmline range  Data Sheets
Warmline range Data Sheets
 
Revit project No. 3 Thesis - Exhibition posters
 Revit project No. 3 Thesis - Exhibition posters Revit project No. 3 Thesis - Exhibition posters
Revit project No. 3 Thesis - Exhibition posters
 
Tech_Brochure_Cladding_Remake_Booklet_LQ_Email
Tech_Brochure_Cladding_Remake_Booklet_LQ_EmailTech_Brochure_Cladding_Remake_Booklet_LQ_Email
Tech_Brochure_Cladding_Remake_Booklet_LQ_Email
 

Mehr von Lee Pei Gie

ECA Presentation
ECA PresentationECA Presentation
ECA PresentationLee Pei Gie
 
Software application
Software application Software application
Software application Lee Pei Gie
 
Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Lee Pei Gie
 
Software Application Presentation Slide
Software Application Presentation SlideSoftware Application Presentation Slide
Software Application Presentation SlideLee Pei Gie
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 
Strategic Proposal
Strategic ProposalStrategic Proposal
Strategic ProposalLee Pei Gie
 
Strategic Proposal
Strategic ProposalStrategic Proposal
Strategic ProposalLee Pei Gie
 
Building Services System in PKNS Complex, Shah Alam
Building Services System in PKNS Complex, Shah AlamBuilding Services System in PKNS Complex, Shah Alam
Building Services System in PKNS Complex, Shah AlamLee Pei Gie
 
Storm water management
Storm water managementStorm water management
Storm water managementLee Pei Gie
 
Management Process
Management ProcessManagement Process
Management ProcessLee Pei Gie
 
Charity Drive Report
Charity Drive ReportCharity Drive Report
Charity Drive ReportLee Pei Gie
 
A Tale of Two Businesses
A Tale of Two BusinessesA Tale of Two Businesses
A Tale of Two BusinessesLee Pei Gie
 
Account Ratio Analysis
Account Ratio AnalysisAccount Ratio Analysis
Account Ratio AnalysisLee Pei Gie
 
Mathematics survey on gym
Mathematics survey on gymMathematics survey on gym
Mathematics survey on gymLee Pei Gie
 

Mehr von Lee Pei Gie (14)

ECA Presentation
ECA PresentationECA Presentation
ECA Presentation
 
Software application
Software application Software application
Software application
 
Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Tender Presentation ( Estimating )
Tender Presentation ( Estimating )
 
Software Application Presentation Slide
Software Application Presentation SlideSoftware Application Presentation Slide
Software Application Presentation Slide
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Strategic Proposal
Strategic ProposalStrategic Proposal
Strategic Proposal
 
Strategic Proposal
Strategic ProposalStrategic Proposal
Strategic Proposal
 
Building Services System in PKNS Complex, Shah Alam
Building Services System in PKNS Complex, Shah AlamBuilding Services System in PKNS Complex, Shah Alam
Building Services System in PKNS Complex, Shah Alam
 
Storm water management
Storm water managementStorm water management
Storm water management
 
Management Process
Management ProcessManagement Process
Management Process
 
Charity Drive Report
Charity Drive ReportCharity Drive Report
Charity Drive Report
 
A Tale of Two Businesses
A Tale of Two BusinessesA Tale of Two Businesses
A Tale of Two Businesses
 
Account Ratio Analysis
Account Ratio AnalysisAccount Ratio Analysis
Account Ratio Analysis
 
Mathematics survey on gym
Mathematics survey on gymMathematics survey on gym
Mathematics survey on gym
 

Kürzlich hochgeladen

Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptxPoojaSen20
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 

Kürzlich hochgeladen (20)

Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptx
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 

Bill of Quantities ( Door and Window )

  • 1. SERI INTAN APARTMENT TYPE B - INTERMEDIATE LEE PEI GIE TIMBER LOUVRED WINDOW 16 /11 / 2015 A B C D E F G Precast Concrete Lintel 115 mm x 150mm depth precastconcrete grade 20 lintel reinforced with 2 nos 12mm diameter high tensile bars and 6mm mild steel stirrup at150mm centre and bedded in cementand sand (1:3) mortar. Packing Piece 75mm x 20mm sawn pressure treated Grade B timber guard fixed to brickwork & concrete work. Purpose made window and frame 585mm x 940mm Grade B hardwood timber window frames all as per manufacture detail. Aluminium Adjustable Louvre Window Pair single control aluminium adjustable louvre stiles 880mm high each with clips for 7 nos 150mm wide glass louvred & screwed to timber frame. Glazing 512mm x 150mm x6mm thick clear glass and fix into clips of louvred stiles. Painting Prepare and apply one coat of Nippon Hydro Primer or other approved equivalentprimer paints as described on: General surface of timber not exceeding 150mm girth Knotting, stopping and applyone coat of Nippon Hydro Primer,one Nippon Odourlite Undercoatand two finishing coats ofNippon Odourlite or other approved equivalentgloss paintas described on: Glasslouvredwindow M M NO NO NO M M² 2 6 2 2 14 13 2 TO COLLECTION (RM)
  • 2. LEE PEI GIE SERI INTAN APARTMENT TYPE B - INTERMEDIATE TIMBER FRAME DOOR 16 /11 / 2015 A B C D E F G H I Precast Concrete Lintel 115 mm x 150mm depth precastconcrete grade 20 lintel reinforced with 2 nos 12mm diameter high tensile bars and 6mm mild steel stirrup at150mm centre and bedded in cementand sand (1:3) mortar. Packing Piece 75mm x 20mm sawn pressure treated Grade B timber guard fixed to brickwork & concrete work. Timber Door Frame 115mmx60mm grade B wrot pressure treated timber rebated head & jambs screwed to packing piece. Timber Door Leaf 780mm x 2070mm x35mm thick Grade B hardwood timber flush door all as per manufacture details. Ironmongeries Supply and fix the following or other equal and approved ironmongerycomplete with requisite matching screws:- Allgood 100mm 2 steel butt hinges and fix to door leaf. Dexter by Schlage J54CNA630 stainless steel cylinder lockset. Painting Prepare and apply one coat of Nippon Hydro Primer or other approved equivalent primer paints as described on: Timber guard and timber frame not exceeding 150mm girth Knotting, stopping and applyone coat of Nippon Hydro Primer,one Nippon Odourlite Undercoatand two finishing coats of Nippon Odourlite or other approved equivalentgloss enamel paint as desribed on: Timber door frame,exceeding 150mm butnot exceeding 300mm Knotting, stopping and applyone coat of Nippon Hydro Primer,one Nippon Odourlite Undercoatand two finishing coats of Nippon Odourlite or other approved equivalentgloss paint as desribed on: Timberpanel doorleaf,over300mm girth M M M NO NO NO M M M² 1 5 5 1 3 1 10 5 3 TO COLLECTION (RM)