National Solid Waste
Management Program
In Sri Lanka
Central Environmental Authority
• Government of sri lanka Launched
Pilisaru project -2008
The theme of the project
YEAR 2018 WASTE FREE SRI LANKA
Waste Generation per day 7500 MT
Daily Waste collection per day 3500 MT
Local Authorities
Waste composition in Sri Lanka
Type of Local Authority Quantity by person(Kg/day)
Colombo Municipal Council 0.80
Municipal Councils 0.75
Urban Councils 0.60
Pradeshiya Sabas 0.40
Per capita daily generation of solid waste
Western Province 58.5%
Eastern Province 8.5%
Central Province 8%
Southern Province 7%
NW Province 6%
Northern Province 3.3%
Sabaragamuwa Province 3.2%
Uva Province 3%
NC Province 2.5%
Percentage of Solid Waste collected by the LAS
Objectives of the Pilisaru Project
• Preparation of national policy on Solid Waste
management.
• Preparation of strategies for the solid waste
management.
• Provision of training on effective solid waste
management including education and awareness for
relevant officers.
• Provision of necessary facilities for implementation of
solid waste management projects and programs.
• Strengthening the legal framework for solid waste
management.
Activities of the Pilisaru project
1. Provision of Proper Waste Management Facilities for
Local Authorities
2. Installments of Bio Gas plants for hospitals and other
government institutions
3. Provision of necessary instruments /equipments for
Local Authorities where compost sites are being
operated
4. Provision of Compost bins at low cost for local
authorities
5. Conduct Education and awareness programms
6. Awareness program on waste segregation at LA level
7. Project Coordination, Monitoring and Evaluation
Sri Lanka
Waste
(Mt/Day)
No of
District
No. of
LAs
No. of
Com.
Plant
No of
District
Target
Waste(Mt/D)
%
3424 25 335 119 20 656.75 19.18
Northern Province
District Waste
(Mt/Day)
No of LAs No. of
Com.
Plant
Target
Waste
Mt/Day)
%
Jaffna 78.5 17 03 11 14.01
North central Province
District Waste
(Mt/Day)
No of
LAs
No. of Com. Plant Target
Waste
Mt/Day)
%
Anuradapura 64.7 19 14 (Camp - 3) 46.5 71.87
Polonnaruwa 17.5 07 02 12 68.57
Total 82.2 26 16 58.5 71.16
Northwestern Province
District Waste
(Mt/Day)
No
of
LAs
No. of
Com.
Plant
Target
Waste
Mt/Day)
%
Kurunegala 113 21 16 88 77.87
Puttalam 87.9 12 05 30 34.12
Total 200.9 33 21 118 58.73
Central Province
District Waste
(Mt/Day)
No of
LAs
No. of
Com.
Plant
Target
Waste
(Mt/Day)
%
Kandy 209.5 22 04 17 8.11
Matale 47.3 13 04 08 16.91
NuwaraEliya 58 08 02 05 8.62
Total 314.8 43 10 30 9.53
Western Province
District Waste
(Mt/Da
y)
No of
LAs
No. of
Com. Plant
Target Waste
Mt/Day)
%
Colombo 1284 13 02(School 2
Camp 1)
7.25 0.56
Kalutara 126.5 16 07 69 54.55
Gampaha 372.5 19 08 40.5 10.87
Total 1783 48 17 116.75 6.55
Southern Province
District Waste
(Mt/Day
)
No of
LAs
No. of
Com.
Plant
Target
Waste
Mt/Day)
%
Hambantota 50 12 08 30 60.00
Matara 92 17 07 51 55.43
Galle 107.5 20 09 13 12.09
Total 249.5 49 24 94 37.68
Sabaragamuwa Province
District Waste
(Mt/Day)
No of
LAs
No. of
Com.
Plant
Target
Waste
Mt/Day)
%
Kegalle 65.5 12 06 34 51.91
Ratnapura 88 17 02 02 2.27
Total 153.5 29 08 36 23.45
Uva Province
District Waste
(Mt/Day)
No of LAs No. of
Com.
Plant
Target
Waste
(Mt/Day)
%
Badulla 75.6 17 (Camp 1) 05 52 68.78
Monaragala 35 10 02 04 11.43
Total 110.6 27 07 56 50.63
Eastern Province
District Waste
(Mt/Day)
No of
LAs
No. of
Com.
Plant
Target
Waste
(Mt/Day)
%
Ampara 142.5 20 05 13 9.12
Batticaloa 136 12 01 09 6.62
Total 278.5 32 06 22 7.90
Site Locations
Present status – 120 compost sites (2008 -
2014)
• Number of compost plants being
in operation - 94
• Construction finished but compost production
to be started, Problem with Electricity, water &
access road) - 07
• Construction ongoing - 17
• Sites in which construction stopped( Legal Matters
Gallenbidunuwewa PS, Kalawana PS) - 02
Medium and Small scale Compost Plants (2008 -2014)
Alawwa PS compost plant Pannala PS compost plant
Kaduwela MC compost plant Balangoda UC compost plant
Compost plants established for the
government institutions (2008 – 2014)
Ragama Medical faculty compost plant Royal Collage compost plant
Ekala Air-force camp compost plant Galkulama Armed Camp compost plant
Thank You
Major compost plants
Galle - Monroviyawaththa compost
site - 2012
Kurunegala - Sundarapola compost site - 2012
Kaluthara -Pohorawaththa compost site - 2010
A’pura – Nuwaragam palatha compost site - 2009
1). Provision of Proper Waste Management Facilities - compost sites
2008 -2014
2) Installments of 22 Bio Gas plants for hospitals and
other government institutions (2008 – 2014)
Trinco Hospital General Hospital Polonnaruwa
Cancer Hospital Maharagama Gampaha Hospital
3). Provision of necessary
instruments/ equipments for Local
Authorities where compost sites are
being operated
2008 - 2014
Shiver machines - 54
Skid steer loaders - 21
Tractor - 151
Compactors - 04
Tractor tailors - 161
Wheel loader - 01
Excavator - 01
4). Provision of Compost bins at low
cost for local authorities (2008 – 2014)
• Implementation of compost bin production
center at CEA premises from 01 /08/2014
5). Conduct Education and awareness programms (2008 –
2014)
Mass Scale Awareness program
trough TV, Radio, News papers , posters,
leaflets
6). Awareness program on waste segregation at LA level
6.1) Implemented first program in the Kaduwela MC and continued.
6.2 )Scheduled to implement in rest of LAs where compost production
take place
6.3 )To encourage the household dwellers for waste separation, 15000 bins
will be provided at LA level
6.4 )Inclusion of waste management subject for school curricular
6.5) Discussions held with NIE to include this to 6 subjects from years 6 to 9
7). Project Coordination, Monitoring and Evaluation
7.1) Reviewing the progress of all compost sites at
provincial/district level
Covered three provinces and identified shortcomings in compost
sites and requests received through CLGs being processed.
7.2) All compost sites are being monitored monthly through
divisional environmental officers in CEA district offices
7.3) Inter-agency coordination meetings scheduled to hold with
ministry of local government and provincial council and waste
management authority in Western Provincial council
Kotawila Waste Management project 2014 - 2015
Central Environmental Authority Matara Municipality
Total Cost – Rs. 249 million
CEA – Rs. 126 million
Bio Green – Rs. 123 million
The dumping site as at 16th September 2014
View of capping from semi engineering landfill site.
The dumping site as at 16th September 2014
Work on the semi engineered landfill in progress
(change instructed as at last site visit has been incorporated)
The dumping site as at 18th September 2014
View of the capped area
Construction in progress – as at 26th Oct.
Platform for conveyors been constructed & compacted
Completed Platform – as at 21st Nov.
Completed platform with conveyor frames been fitted
Construction in progress – 26th Oct.
Preparations and construction of retaining wall
Construction in progress – as at 21st Nov.
Columns completed & Trusses been fitted
Digester tank work in progress – as at 22nd Dec
Work in progress at site
Construction in progress
Design drawing of the fully enclosed buildings
Financial Status
Year Total Allocation
(Rs. Million)
Total Expenditure (Rs.
Million)
Percentage
2008 558 107.5 19%
2009 817 252.7 31%
2010 695 410.2 60%
2011 640 500.2 78%
2012 546 410.2 75%
2013 200 192.8 96%
2014 459 342 75%
2015 300
0
100
200
300
400
500
600
700
800
900
2008 2009 2010 2011 2012 2013 2014
Financial Status
Total Allocation (Rs. Million) Total Expenditure (Rs. Million)
THANK YOU…!

Weitere ähnliche Inhalte

Ähnlich wie 6 cea

WASTE MGT STRATEGY TIWAN.pptx
WASTE MGT STRATEGY TIWAN.pptxWASTE MGT STRATEGY TIWAN.pptx
WASTE MGT STRATEGY TIWAN.pptxendurancechery
 
Project Completion Review of Food Security Livelihood Improvement and Climate...
Project Completion Review of Food Security Livelihood Improvement and Climate...Project Completion Review of Food Security Livelihood Improvement and Climate...
Project Completion Review of Food Security Livelihood Improvement and Climate...BijayaUpadhya
 
Waste to energy india
Waste to energy indiaWaste to energy india
Waste to energy indiaKishlay Kumar
 
Victorias Waste Infrastructure Planning Framework
Victorias Waste Infrastructure Planning FrameworkVictorias Waste Infrastructure Planning Framework
Victorias Waste Infrastructure Planning FrameworkCircular Economy Asia
 
Transformation Towards Sustainability at Chulalongkorn University, Korb Limsu...
Transformation Towards Sustainability at Chulalongkorn University, Korb Limsu...Transformation Towards Sustainability at Chulalongkorn University, Korb Limsu...
Transformation Towards Sustainability at Chulalongkorn University, Korb Limsu...ESD UNU-IAS
 
Dunedin presentation.pptx[14276]
Dunedin presentation.pptx[14276]Dunedin presentation.pptx[14276]
Dunedin presentation.pptx[14276]Patrick Murphy
 
ASEAN’s Energy Situation and Growing Effort on CDM
ASEAN’s Energy Situation and Growing Effort on CDMASEAN’s Energy Situation and Growing Effort on CDM
ASEAN’s Energy Situation and Growing Effort on CDMbenisuryadi
 
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEF
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEFRenewable Energy status and road-map of Bangladesh and support of UNDP-GEF
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEFDr. Md. Taibur Rahman
 
1 - Memon - ISWM.pdf
1 - Memon - ISWM.pdf1 - Memon - ISWM.pdf
1 - Memon - ISWM.pdfprincypandey6
 
Synergy GIZ and Counterparts
Synergy GIZ and CounterpartsSynergy GIZ and Counterparts
Synergy GIZ and CounterpartsRio Wicaksono
 
Solid Waste Management of Dhaka City Corporation
Solid Waste Management of Dhaka City CorporationSolid Waste Management of Dhaka City Corporation
Solid Waste Management of Dhaka City CorporationMosfiqur Rahman Saikat
 
2. aung khaing nyi shwetaung cement esia process taunggyi
2. aung khaing nyi shwetaung cement esia process taunggyi2. aung khaing nyi shwetaung cement esia process taunggyi
2. aung khaing nyi shwetaung cement esia process taunggyiEthical Sector
 
Minister of Roads and Highways, Mr Kwasi Amoako-Attah on Ghana Roads
Minister of Roads and Highways, Mr Kwasi Amoako-Attah on Ghana RoadsMinister of Roads and Highways, Mr Kwasi Amoako-Attah on Ghana Roads
Minister of Roads and Highways, Mr Kwasi Amoako-Attah on Ghana RoadsKweku Zurek
 
Presentation ICEED2013
Presentation ICEED2013Presentation ICEED2013
Presentation ICEED2013Marcel Gakuba
 

Ähnlich wie 6 cea (20)

WASTE MGT STRATEGY TIWAN.pptx
WASTE MGT STRATEGY TIWAN.pptxWASTE MGT STRATEGY TIWAN.pptx
WASTE MGT STRATEGY TIWAN.pptx
 
Project Completion Review of Food Security Livelihood Improvement and Climate...
Project Completion Review of Food Security Livelihood Improvement and Climate...Project Completion Review of Food Security Livelihood Improvement and Climate...
Project Completion Review of Food Security Livelihood Improvement and Climate...
 
Waste to energy india
Waste to energy indiaWaste to energy india
Waste to energy india
 
PRESENTATION-SBM
PRESENTATION-SBMPRESENTATION-SBM
PRESENTATION-SBM
 
Victorias Waste Infrastructure Planning Framework
Victorias Waste Infrastructure Planning FrameworkVictorias Waste Infrastructure Planning Framework
Victorias Waste Infrastructure Planning Framework
 
Transformation Towards Sustainability at Chulalongkorn University, Korb Limsu...
Transformation Towards Sustainability at Chulalongkorn University, Korb Limsu...Transformation Towards Sustainability at Chulalongkorn University, Korb Limsu...
Transformation Towards Sustainability at Chulalongkorn University, Korb Limsu...
 
10 Local Authority Water and Communities Office. Matt Shortt
10 Local Authority Water and Communities Office. Matt Shortt10 Local Authority Water and Communities Office. Matt Shortt
10 Local Authority Water and Communities Office. Matt Shortt
 
Dunedin presentation.pptx[14276]
Dunedin presentation.pptx[14276]Dunedin presentation.pptx[14276]
Dunedin presentation.pptx[14276]
 
ASEAN’s Energy Situation and Growing Effort on CDM
ASEAN’s Energy Situation and Growing Effort on CDMASEAN’s Energy Situation and Growing Effort on CDM
ASEAN’s Energy Situation and Growing Effort on CDM
 
B04640813
B04640813B04640813
B04640813
 
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEF
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEFRenewable Energy status and road-map of Bangladesh and support of UNDP-GEF
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEF
 
1 - Memon - ISWM.pdf
1 - Memon - ISWM.pdf1 - Memon - ISWM.pdf
1 - Memon - ISWM.pdf
 
CRT/N Introduction - RTKC Milestones
CRT/N  Introduction - RTKC MilestonesCRT/N  Introduction - RTKC Milestones
CRT/N Introduction - RTKC Milestones
 
IndianRhinos1
IndianRhinos1IndianRhinos1
IndianRhinos1
 
Synergy GIZ and Counterparts
Synergy GIZ and CounterpartsSynergy GIZ and Counterparts
Synergy GIZ and Counterparts
 
Solid Waste Management of Dhaka City Corporation
Solid Waste Management of Dhaka City CorporationSolid Waste Management of Dhaka City Corporation
Solid Waste Management of Dhaka City Corporation
 
Rids
RidsRids
Rids
 
2. aung khaing nyi shwetaung cement esia process taunggyi
2. aung khaing nyi shwetaung cement esia process taunggyi2. aung khaing nyi shwetaung cement esia process taunggyi
2. aung khaing nyi shwetaung cement esia process taunggyi
 
Minister of Roads and Highways, Mr Kwasi Amoako-Attah on Ghana Roads
Minister of Roads and Highways, Mr Kwasi Amoako-Attah on Ghana RoadsMinister of Roads and Highways, Mr Kwasi Amoako-Attah on Ghana Roads
Minister of Roads and Highways, Mr Kwasi Amoako-Attah on Ghana Roads
 
Presentation ICEED2013
Presentation ICEED2013Presentation ICEED2013
Presentation ICEED2013
 

Kürzlich hochgeladen

💞 Safe And Secure Call Girls gaya 🧿 9332606886 🧿 High Class Call Girl Service...
💞 Safe And Secure Call Girls gaya 🧿 9332606886 🧿 High Class Call Girl Service...💞 Safe And Secure Call Girls gaya 🧿 9332606886 🧿 High Class Call Girl Service...
💞 Safe And Secure Call Girls gaya 🧿 9332606886 🧿 High Class Call Girl Service...India Call Girls
 
❤️Amritsar Escort Service☎️98151-129OO☎️ Call Girl service in Amritsar☎️ Amri...
❤️Amritsar Escort Service☎️98151-129OO☎️ Call Girl service in Amritsar☎️ Amri...❤️Amritsar Escort Service☎️98151-129OO☎️ Call Girl service in Amritsar☎️ Amri...
❤️Amritsar Escort Service☎️98151-129OO☎️ Call Girl service in Amritsar☎️ Amri...shallyentertainment1
 
💸Cash Payment No Advance Call Girls Kanpur 🧿 9332606886 🧿 High Class Call Gir...
💸Cash Payment No Advance Call Girls Kanpur 🧿 9332606886 🧿 High Class Call Gir...💸Cash Payment No Advance Call Girls Kanpur 🧿 9332606886 🧿 High Class Call Gir...
💸Cash Payment No Advance Call Girls Kanpur 🧿 9332606886 🧿 High Class Call Gir...India Call Girls
 
💸Cash Payment No Advance Call Girls Nagpur 🧿 9332606886 🧿 High Class Call Gir...
💸Cash Payment No Advance Call Girls Nagpur 🧿 9332606886 🧿 High Class Call Gir...💸Cash Payment No Advance Call Girls Nagpur 🧿 9332606886 🧿 High Class Call Gir...
💸Cash Payment No Advance Call Girls Nagpur 🧿 9332606886 🧿 High Class Call Gir...India Call Girls
 
2024 PCP #IMPerative Updates in Rheumatology
2024 PCP #IMPerative Updates in Rheumatology2024 PCP #IMPerative Updates in Rheumatology
2024 PCP #IMPerative Updates in RheumatologySidney Erwin Manahan
 
❤️ Call Girls service In Panchkula☎️9815457724☎️ Call Girl service in Panchku...
❤️ Call Girls service In Panchkula☎️9815457724☎️ Call Girl service in Panchku...❤️ Call Girls service In Panchkula☎️9815457724☎️ Call Girl service in Panchku...
❤️ Call Girls service In Panchkula☎️9815457724☎️ Call Girl service in Panchku...Rashmi Entertainment
 
🍑👄Ludhiana Escorts Service☎️98157-77685🍑👄 Call Girl service in Ludhiana☎️Ludh...
🍑👄Ludhiana Escorts Service☎️98157-77685🍑👄 Call Girl service in Ludhiana☎️Ludh...🍑👄Ludhiana Escorts Service☎️98157-77685🍑👄 Call Girl service in Ludhiana☎️Ludh...
🍑👄Ludhiana Escorts Service☎️98157-77685🍑👄 Call Girl service in Ludhiana☎️Ludh...dilpreetentertainmen
 
❤️ Zirakpur Call Girl Service ☎️9878799926☎️ Call Girl service in Zirakpur ☎...
❤️ Zirakpur Call Girl Service  ☎️9878799926☎️ Call Girl service in Zirakpur ☎...❤️ Zirakpur Call Girl Service  ☎️9878799926☎️ Call Girl service in Zirakpur ☎...
❤️ Zirakpur Call Girl Service ☎️9878799926☎️ Call Girl service in Zirakpur ☎...daljeetkaur2026
 
💸Cash Payment No Advance Call Girls Pune 🧿 9332606886 🧿 High Class Call Girl ...
💸Cash Payment No Advance Call Girls Pune 🧿 9332606886 🧿 High Class Call Girl ...💸Cash Payment No Advance Call Girls Pune 🧿 9332606886 🧿 High Class Call Girl ...
💸Cash Payment No Advance Call Girls Pune 🧿 9332606886 🧿 High Class Call Girl ...India Call Girls
 
❤️Chandigarh Escort Service☎️9815457724☎️ Call Girl service in Chandigarh☎️ C...
❤️Chandigarh Escort Service☎️9815457724☎️ Call Girl service in Chandigarh☎️ C...❤️Chandigarh Escort Service☎️9815457724☎️ Call Girl service in Chandigarh☎️ C...
❤️Chandigarh Escort Service☎️9815457724☎️ Call Girl service in Chandigarh☎️ C...Rashmi Entertainment
 
💸Cash Payment No Advance Call Girls Surat 🧿 9332606886 🧿 High Class Call Girl...
💸Cash Payment No Advance Call Girls Surat 🧿 9332606886 🧿 High Class Call Girl...💸Cash Payment No Advance Call Girls Surat 🧿 9332606886 🧿 High Class Call Girl...
💸Cash Payment No Advance Call Girls Surat 🧿 9332606886 🧿 High Class Call Girl...India Call Girls
 
❤️ Chandigarh Call Girls Service☎️9878799926☎️ Call Girl service in Chandigar...
❤️ Chandigarh Call Girls Service☎️9878799926☎️ Call Girl service in Chandigar...❤️ Chandigarh Call Girls Service☎️9878799926☎️ Call Girl service in Chandigar...
❤️ Chandigarh Call Girls Service☎️9878799926☎️ Call Girl service in Chandigar...daljeetkaur2026
 
💸Cash Payment No Advance Call Girls Kolkata 🧿 9332606886 🧿 High Class Call Gi...
💸Cash Payment No Advance Call Girls Kolkata 🧿 9332606886 🧿 High Class Call Gi...💸Cash Payment No Advance Call Girls Kolkata 🧿 9332606886 🧿 High Class Call Gi...
💸Cash Payment No Advance Call Girls Kolkata 🧿 9332606886 🧿 High Class Call Gi...India Call Girls
 
👉Bangalore Call Girl Service👉📞 6378878445 👉📞 Just📲 Call Manisha Call Girls Se...
👉Bangalore Call Girl Service👉📞 6378878445 👉📞 Just📲 Call Manisha Call Girls Se...👉Bangalore Call Girl Service👉📞 6378878445 👉📞 Just📲 Call Manisha Call Girls Se...
👉Bangalore Call Girl Service👉📞 6378878445 👉📞 Just📲 Call Manisha Call Girls Se...dharampalsingh2210
 
💞 Safe And Secure Call Girls Coimbatore 🧿 9332606886 🧿 High Class Call Girl S...
💞 Safe And Secure Call Girls Coimbatore 🧿 9332606886 🧿 High Class Call Girl S...💞 Safe And Secure Call Girls Coimbatore 🧿 9332606886 🧿 High Class Call Girl S...
💞 Safe And Secure Call Girls Coimbatore 🧿 9332606886 🧿 High Class Call Girl S...India Call Girls
 
The Events of Cardiac Cycle - Wigger's Diagram
The Events of Cardiac Cycle - Wigger's DiagramThe Events of Cardiac Cycle - Wigger's Diagram
The Events of Cardiac Cycle - Wigger's DiagramMedicoseAcademics
 
💸Cash Payment No Advance Call Girls Hyderabad 🧿 9332606886 🧿 High Class Call ...
💸Cash Payment No Advance Call Girls Hyderabad 🧿 9332606886 🧿 High Class Call ...💸Cash Payment No Advance Call Girls Hyderabad 🧿 9332606886 🧿 High Class Call ...
💸Cash Payment No Advance Call Girls Hyderabad 🧿 9332606886 🧿 High Class Call ...India Call Girls
 
💞 Safe And Secure Call Girls Mysore 🧿 9332606886 🧿 High Class Call Girl Servi...
💞 Safe And Secure Call Girls Mysore 🧿 9332606886 🧿 High Class Call Girl Servi...💞 Safe And Secure Call Girls Mysore 🧿 9332606886 🧿 High Class Call Girl Servi...
💞 Safe And Secure Call Girls Mysore 🧿 9332606886 🧿 High Class Call Girl Servi...India Call Girls
 

Kürzlich hochgeladen (18)

💞 Safe And Secure Call Girls gaya 🧿 9332606886 🧿 High Class Call Girl Service...
💞 Safe And Secure Call Girls gaya 🧿 9332606886 🧿 High Class Call Girl Service...💞 Safe And Secure Call Girls gaya 🧿 9332606886 🧿 High Class Call Girl Service...
💞 Safe And Secure Call Girls gaya 🧿 9332606886 🧿 High Class Call Girl Service...
 
❤️Amritsar Escort Service☎️98151-129OO☎️ Call Girl service in Amritsar☎️ Amri...
❤️Amritsar Escort Service☎️98151-129OO☎️ Call Girl service in Amritsar☎️ Amri...❤️Amritsar Escort Service☎️98151-129OO☎️ Call Girl service in Amritsar☎️ Amri...
❤️Amritsar Escort Service☎️98151-129OO☎️ Call Girl service in Amritsar☎️ Amri...
 
💸Cash Payment No Advance Call Girls Kanpur 🧿 9332606886 🧿 High Class Call Gir...
💸Cash Payment No Advance Call Girls Kanpur 🧿 9332606886 🧿 High Class Call Gir...💸Cash Payment No Advance Call Girls Kanpur 🧿 9332606886 🧿 High Class Call Gir...
💸Cash Payment No Advance Call Girls Kanpur 🧿 9332606886 🧿 High Class Call Gir...
 
💸Cash Payment No Advance Call Girls Nagpur 🧿 9332606886 🧿 High Class Call Gir...
💸Cash Payment No Advance Call Girls Nagpur 🧿 9332606886 🧿 High Class Call Gir...💸Cash Payment No Advance Call Girls Nagpur 🧿 9332606886 🧿 High Class Call Gir...
💸Cash Payment No Advance Call Girls Nagpur 🧿 9332606886 🧿 High Class Call Gir...
 
2024 PCP #IMPerative Updates in Rheumatology
2024 PCP #IMPerative Updates in Rheumatology2024 PCP #IMPerative Updates in Rheumatology
2024 PCP #IMPerative Updates in Rheumatology
 
❤️ Call Girls service In Panchkula☎️9815457724☎️ Call Girl service in Panchku...
❤️ Call Girls service In Panchkula☎️9815457724☎️ Call Girl service in Panchku...❤️ Call Girls service In Panchkula☎️9815457724☎️ Call Girl service in Panchku...
❤️ Call Girls service In Panchkula☎️9815457724☎️ Call Girl service in Panchku...
 
🍑👄Ludhiana Escorts Service☎️98157-77685🍑👄 Call Girl service in Ludhiana☎️Ludh...
🍑👄Ludhiana Escorts Service☎️98157-77685🍑👄 Call Girl service in Ludhiana☎️Ludh...🍑👄Ludhiana Escorts Service☎️98157-77685🍑👄 Call Girl service in Ludhiana☎️Ludh...
🍑👄Ludhiana Escorts Service☎️98157-77685🍑👄 Call Girl service in Ludhiana☎️Ludh...
 
❤️ Zirakpur Call Girl Service ☎️9878799926☎️ Call Girl service in Zirakpur ☎...
❤️ Zirakpur Call Girl Service  ☎️9878799926☎️ Call Girl service in Zirakpur ☎...❤️ Zirakpur Call Girl Service  ☎️9878799926☎️ Call Girl service in Zirakpur ☎...
❤️ Zirakpur Call Girl Service ☎️9878799926☎️ Call Girl service in Zirakpur ☎...
 
💸Cash Payment No Advance Call Girls Pune 🧿 9332606886 🧿 High Class Call Girl ...
💸Cash Payment No Advance Call Girls Pune 🧿 9332606886 🧿 High Class Call Girl ...💸Cash Payment No Advance Call Girls Pune 🧿 9332606886 🧿 High Class Call Girl ...
💸Cash Payment No Advance Call Girls Pune 🧿 9332606886 🧿 High Class Call Girl ...
 
❤️Chandigarh Escort Service☎️9815457724☎️ Call Girl service in Chandigarh☎️ C...
❤️Chandigarh Escort Service☎️9815457724☎️ Call Girl service in Chandigarh☎️ C...❤️Chandigarh Escort Service☎️9815457724☎️ Call Girl service in Chandigarh☎️ C...
❤️Chandigarh Escort Service☎️9815457724☎️ Call Girl service in Chandigarh☎️ C...
 
💸Cash Payment No Advance Call Girls Surat 🧿 9332606886 🧿 High Class Call Girl...
💸Cash Payment No Advance Call Girls Surat 🧿 9332606886 🧿 High Class Call Girl...💸Cash Payment No Advance Call Girls Surat 🧿 9332606886 🧿 High Class Call Girl...
💸Cash Payment No Advance Call Girls Surat 🧿 9332606886 🧿 High Class Call Girl...
 
❤️ Chandigarh Call Girls Service☎️9878799926☎️ Call Girl service in Chandigar...
❤️ Chandigarh Call Girls Service☎️9878799926☎️ Call Girl service in Chandigar...❤️ Chandigarh Call Girls Service☎️9878799926☎️ Call Girl service in Chandigar...
❤️ Chandigarh Call Girls Service☎️9878799926☎️ Call Girl service in Chandigar...
 
💸Cash Payment No Advance Call Girls Kolkata 🧿 9332606886 🧿 High Class Call Gi...
💸Cash Payment No Advance Call Girls Kolkata 🧿 9332606886 🧿 High Class Call Gi...💸Cash Payment No Advance Call Girls Kolkata 🧿 9332606886 🧿 High Class Call Gi...
💸Cash Payment No Advance Call Girls Kolkata 🧿 9332606886 🧿 High Class Call Gi...
 
👉Bangalore Call Girl Service👉📞 6378878445 👉📞 Just📲 Call Manisha Call Girls Se...
👉Bangalore Call Girl Service👉📞 6378878445 👉📞 Just📲 Call Manisha Call Girls Se...👉Bangalore Call Girl Service👉📞 6378878445 👉📞 Just📲 Call Manisha Call Girls Se...
👉Bangalore Call Girl Service👉📞 6378878445 👉📞 Just📲 Call Manisha Call Girls Se...
 
💞 Safe And Secure Call Girls Coimbatore 🧿 9332606886 🧿 High Class Call Girl S...
💞 Safe And Secure Call Girls Coimbatore 🧿 9332606886 🧿 High Class Call Girl S...💞 Safe And Secure Call Girls Coimbatore 🧿 9332606886 🧿 High Class Call Girl S...
💞 Safe And Secure Call Girls Coimbatore 🧿 9332606886 🧿 High Class Call Girl S...
 
The Events of Cardiac Cycle - Wigger's Diagram
The Events of Cardiac Cycle - Wigger's DiagramThe Events of Cardiac Cycle - Wigger's Diagram
The Events of Cardiac Cycle - Wigger's Diagram
 
💸Cash Payment No Advance Call Girls Hyderabad 🧿 9332606886 🧿 High Class Call ...
💸Cash Payment No Advance Call Girls Hyderabad 🧿 9332606886 🧿 High Class Call ...💸Cash Payment No Advance Call Girls Hyderabad 🧿 9332606886 🧿 High Class Call ...
💸Cash Payment No Advance Call Girls Hyderabad 🧿 9332606886 🧿 High Class Call ...
 
💞 Safe And Secure Call Girls Mysore 🧿 9332606886 🧿 High Class Call Girl Servi...
💞 Safe And Secure Call Girls Mysore 🧿 9332606886 🧿 High Class Call Girl Servi...💞 Safe And Secure Call Girls Mysore 🧿 9332606886 🧿 High Class Call Girl Servi...
💞 Safe And Secure Call Girls Mysore 🧿 9332606886 🧿 High Class Call Girl Servi...
 

6 cea

  • 1. National Solid Waste Management Program In Sri Lanka Central Environmental Authority
  • 2. • Government of sri lanka Launched Pilisaru project -2008 The theme of the project YEAR 2018 WASTE FREE SRI LANKA
  • 3. Waste Generation per day 7500 MT Daily Waste collection per day 3500 MT Local Authorities
  • 5. Type of Local Authority Quantity by person(Kg/day) Colombo Municipal Council 0.80 Municipal Councils 0.75 Urban Councils 0.60 Pradeshiya Sabas 0.40 Per capita daily generation of solid waste
  • 6. Western Province 58.5% Eastern Province 8.5% Central Province 8% Southern Province 7% NW Province 6% Northern Province 3.3% Sabaragamuwa Province 3.2% Uva Province 3% NC Province 2.5% Percentage of Solid Waste collected by the LAS
  • 7. Objectives of the Pilisaru Project • Preparation of national policy on Solid Waste management. • Preparation of strategies for the solid waste management. • Provision of training on effective solid waste management including education and awareness for relevant officers. • Provision of necessary facilities for implementation of solid waste management projects and programs. • Strengthening the legal framework for solid waste management.
  • 8. Activities of the Pilisaru project 1. Provision of Proper Waste Management Facilities for Local Authorities 2. Installments of Bio Gas plants for hospitals and other government institutions 3. Provision of necessary instruments /equipments for Local Authorities where compost sites are being operated 4. Provision of Compost bins at low cost for local authorities 5. Conduct Education and awareness programms 6. Awareness program on waste segregation at LA level 7. Project Coordination, Monitoring and Evaluation
  • 9. Sri Lanka Waste (Mt/Day) No of District No. of LAs No. of Com. Plant No of District Target Waste(Mt/D) % 3424 25 335 119 20 656.75 19.18
  • 10. Northern Province District Waste (Mt/Day) No of LAs No. of Com. Plant Target Waste Mt/Day) % Jaffna 78.5 17 03 11 14.01
  • 11. North central Province District Waste (Mt/Day) No of LAs No. of Com. Plant Target Waste Mt/Day) % Anuradapura 64.7 19 14 (Camp - 3) 46.5 71.87 Polonnaruwa 17.5 07 02 12 68.57 Total 82.2 26 16 58.5 71.16
  • 12. Northwestern Province District Waste (Mt/Day) No of LAs No. of Com. Plant Target Waste Mt/Day) % Kurunegala 113 21 16 88 77.87 Puttalam 87.9 12 05 30 34.12 Total 200.9 33 21 118 58.73
  • 13. Central Province District Waste (Mt/Day) No of LAs No. of Com. Plant Target Waste (Mt/Day) % Kandy 209.5 22 04 17 8.11 Matale 47.3 13 04 08 16.91 NuwaraEliya 58 08 02 05 8.62 Total 314.8 43 10 30 9.53
  • 14. Western Province District Waste (Mt/Da y) No of LAs No. of Com. Plant Target Waste Mt/Day) % Colombo 1284 13 02(School 2 Camp 1) 7.25 0.56 Kalutara 126.5 16 07 69 54.55 Gampaha 372.5 19 08 40.5 10.87 Total 1783 48 17 116.75 6.55
  • 15. Southern Province District Waste (Mt/Day ) No of LAs No. of Com. Plant Target Waste Mt/Day) % Hambantota 50 12 08 30 60.00 Matara 92 17 07 51 55.43 Galle 107.5 20 09 13 12.09 Total 249.5 49 24 94 37.68
  • 16. Sabaragamuwa Province District Waste (Mt/Day) No of LAs No. of Com. Plant Target Waste Mt/Day) % Kegalle 65.5 12 06 34 51.91 Ratnapura 88 17 02 02 2.27 Total 153.5 29 08 36 23.45
  • 17. Uva Province District Waste (Mt/Day) No of LAs No. of Com. Plant Target Waste (Mt/Day) % Badulla 75.6 17 (Camp 1) 05 52 68.78 Monaragala 35 10 02 04 11.43 Total 110.6 27 07 56 50.63
  • 18. Eastern Province District Waste (Mt/Day) No of LAs No. of Com. Plant Target Waste (Mt/Day) % Ampara 142.5 20 05 13 9.12 Batticaloa 136 12 01 09 6.62 Total 278.5 32 06 22 7.90
  • 20. Present status – 120 compost sites (2008 - 2014) • Number of compost plants being in operation - 94 • Construction finished but compost production to be started, Problem with Electricity, water & access road) - 07 • Construction ongoing - 17 • Sites in which construction stopped( Legal Matters Gallenbidunuwewa PS, Kalawana PS) - 02
  • 21. Medium and Small scale Compost Plants (2008 -2014) Alawwa PS compost plant Pannala PS compost plant Kaduwela MC compost plant Balangoda UC compost plant
  • 22. Compost plants established for the government institutions (2008 – 2014) Ragama Medical faculty compost plant Royal Collage compost plant Ekala Air-force camp compost plant Galkulama Armed Camp compost plant
  • 24. Major compost plants Galle - Monroviyawaththa compost site - 2012 Kurunegala - Sundarapola compost site - 2012 Kaluthara -Pohorawaththa compost site - 2010 A’pura – Nuwaragam palatha compost site - 2009 1). Provision of Proper Waste Management Facilities - compost sites 2008 -2014
  • 25. 2) Installments of 22 Bio Gas plants for hospitals and other government institutions (2008 – 2014) Trinco Hospital General Hospital Polonnaruwa Cancer Hospital Maharagama Gampaha Hospital
  • 26. 3). Provision of necessary instruments/ equipments for Local Authorities where compost sites are being operated 2008 - 2014
  • 27. Shiver machines - 54 Skid steer loaders - 21 Tractor - 151 Compactors - 04 Tractor tailors - 161
  • 28. Wheel loader - 01 Excavator - 01
  • 29. 4). Provision of Compost bins at low cost for local authorities (2008 – 2014) • Implementation of compost bin production center at CEA premises from 01 /08/2014
  • 30. 5). Conduct Education and awareness programms (2008 – 2014) Mass Scale Awareness program trough TV, Radio, News papers , posters, leaflets
  • 31. 6). Awareness program on waste segregation at LA level 6.1) Implemented first program in the Kaduwela MC and continued. 6.2 )Scheduled to implement in rest of LAs where compost production take place 6.3 )To encourage the household dwellers for waste separation, 15000 bins will be provided at LA level 6.4 )Inclusion of waste management subject for school curricular 6.5) Discussions held with NIE to include this to 6 subjects from years 6 to 9
  • 32.
  • 33. 7). Project Coordination, Monitoring and Evaluation 7.1) Reviewing the progress of all compost sites at provincial/district level Covered three provinces and identified shortcomings in compost sites and requests received through CLGs being processed. 7.2) All compost sites are being monitored monthly through divisional environmental officers in CEA district offices 7.3) Inter-agency coordination meetings scheduled to hold with ministry of local government and provincial council and waste management authority in Western Provincial council
  • 34. Kotawila Waste Management project 2014 - 2015 Central Environmental Authority Matara Municipality Total Cost – Rs. 249 million CEA – Rs. 126 million Bio Green – Rs. 123 million
  • 35. The dumping site as at 16th September 2014 View of capping from semi engineering landfill site.
  • 36. The dumping site as at 16th September 2014 Work on the semi engineered landfill in progress (change instructed as at last site visit has been incorporated)
  • 37. The dumping site as at 18th September 2014 View of the capped area
  • 38. Construction in progress – as at 26th Oct. Platform for conveyors been constructed & compacted
  • 39. Completed Platform – as at 21st Nov. Completed platform with conveyor frames been fitted
  • 40. Construction in progress – 26th Oct. Preparations and construction of retaining wall
  • 41. Construction in progress – as at 21st Nov. Columns completed & Trusses been fitted
  • 42. Digester tank work in progress – as at 22nd Dec Work in progress at site
  • 43. Construction in progress Design drawing of the fully enclosed buildings
  • 44. Financial Status Year Total Allocation (Rs. Million) Total Expenditure (Rs. Million) Percentage 2008 558 107.5 19% 2009 817 252.7 31% 2010 695 410.2 60% 2011 640 500.2 78% 2012 546 410.2 75% 2013 200 192.8 96% 2014 459 342 75% 2015 300
  • 45. 0 100 200 300 400 500 600 700 800 900 2008 2009 2010 2011 2012 2013 2014 Financial Status Total Allocation (Rs. Million) Total Expenditure (Rs. Million)
  • 46.
  • 47.