SlideShare ist ein Scribd-Unternehmen logo
1 von 48
Downloaden Sie, um offline zu lesen
Connoisseur Solutions
Project Procurement Management
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Project Procurement Management
Processes necessary to purchase or acquire products, services or results needed from
outside the project team.
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Procurement Management Processes
Process Process Group
Plan Procurements Planning
Conduct Procurements Executing
Control Procurements Monitoring and Controlling
Close Procurements Closing
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Plan Procurements
Plan Procurements is the process of documenting project purchasing decisions,
specifying the approach, and identifying potential sellers
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Plan Procurements
Inputs Tools and Techniques Outputs
 Project management plan
 Requirements
documentation
 Teaming agreements
 Risk Register
 Project Schedule
 Activity cost estimates
 Stakeholder register
 Enterprise Environmental
Factors
 Organizational Process
Assets
 Make or buy analysis
 Expert Judgment
 Market research
 Meetings
 Procurement
management plan
 Procurement
statements of work
 Make or buy decisions
 Procurement
documents
 Source selection
criteria
 Change requests
 Project document
updates
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Plan Procurements - Inputs
Project Management Plan - describes the need, justification, requirements, and current
boundaries for the project. It consists of Scope statement, WBS and WBS dictionary.
Requirements documentation include Important information about project
requirements that is considered during planning for procurements.
Risk Register include risk-related information such as identified risk, risk owners and risk responses
Activity resource requirements state the type and quantities of resources needed for project
activities
Project Schedule provides information on project timelines and milestones
Activity cost estimates are used to evaluate the price quoted in the bids or proposals received
from potential sellers
Stakeholder Register describes the details on the participants and their interest in the project
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Plan Procurements - Inputs
Enterprise Environmental Factors includes condition of marketplace, what product and service
are available in the market, who is the seller and what are his terms and condition
Organizational Process Assets includes policies and procedures , standards ,guidelines,
performance measurement criteria, defect management procedures, change control procedures and
historical information. Some organizations may define certain constraint on procurement decisions.
This also include the various types of contractual agreements used by the organization, All legal
contractual relationships generally fall into one of two broad families: either fixed – price or
cost reimbursable. Also, there is a third hybrid type commonly in use called the time and materials
contract.
The next slides describes the different contract types in details
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Plan Procurements -Tools and Techniques
Time & Material – T & M The seller is paid for the amount of time it
takes to accomplish the work and he is
also reimbursed for the materials used for
the project
Firm Fixed Price - FFP The seller is paid a fixed price for an
agreed upon unit of work done by him
Fixed Price Incentive Fee – FPIF The seller is paid a fixed price plus an
incentive amount for achieving pre-agreed
project metrics
Fixed Price with Economic Price
Adjustment Contracts – FP-EPA
The seller is paid a fixed price. The
contract is reviewed at pre-defined
intervals in the project for adjustments to
the contract price based on certain
parameters
Types of Contract
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Plan Procurements -Tools and Techniques
Cost Plus Fixed Fee – CPFF The contractor is reimbursed its cost plus
an additional fixed fee. Not desirable from
the buyer’s point of view
Cost Plus Incentive Fee - CPIF Seller is reimbursed for an agreed upon
performance cost along with a pre-
established fee plus an incentive bonus. In
this case, the buyer and seller share the
uncertainty to a certain degree
Cost Plus Award Fee Seller is reimbursed for an agreed upon
performance cost plus all legitimate cost
Types of Contract
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Plan Procurements -Tools and Techniques
Make or buy analysis helps project management team to decide whether it is beneficial
(in terms of cost and quality) to procure a product or service or it can be produced within
the organization.
Market Research includes examination of industry and specific vendor capabilities.
Procurement teams may leverage information gained at conferences , online reviews and
a variety of sources to identify market capabilities.
Meetings , by collaborating with potential bidders , the organization purchasing the
material or service may benefit while supplier can influence a mutually beneficial
approach or product.
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Plan Procurements - Outputs
Procurement management plan describes how the procurement process will be
managed from planning procurement to close procurement. It contains detail on
1. Types of Contracts to be used
2. Risk management issues
3. Whether independent estimates will be used and whether they are needed as
evaluation criteria
4. Standardized procurement documents, if needed
5. Process of managing multiple providers (sellers)
6. Coordination with other project aspects
7. Any constraints and assumptions that could affect planned procurements
8. Handling the long lead times to purchase certain items from sellers and
coordinating the extra time needed to procure these items with the development
of the project schedule
9. Handling make – or – buy decision and linking them to the Estimate Activity
Resources and Develop schedule process.
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Plan Procurements - Outputs
Procurement statements of work defines the products, services , or result to be
procured in details so that the seller can be sure that he can provide appropriate
products , services, or results. It is developed from the project scope baseline and
defines only that portion of the project scope that needs to be procured and stated in
the contract.
Procurement documents define the buyer’s requirements and facilitate complete
and correct response from the prospective sellers in the form of a proposal, which
aids in the selection of the seller(s). The most commonly used procurement
documents are RFP (Request for Proposal), IFB (Invitation for Bid and RFI (Request for
Information
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Plan Procurements - Outputs
Source selection criteria are the set of guidelines on the basis of which a particular
seller is selected from among the proposals received. Some of the source selection
criteria are seller’s understanding of need , overall- life-cycle cost, technical capability,
Risk, past performance of the seller, Financial capacity, Warranty etc
Make –or - Buy Decisions, A make-or- buy analysis results in a decision of whether
particular work can best be accomplished by the project team or needs to be
purchased from outside sources.
Change requests may be there during this process due to updates in the project plan
or its subsidiary plan and other components. These changes are reviewed and
approved through the integrated change control process.
Project Documents Updates that may be updated include requirement
documentation, requirements traceability matrix and risk register.
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Practicing Key Concepts
Exercise 1: Make or Buy Analysis
You’ve been contracted by a construction company to manage their contracting.
They have a choice of either buying an excavator or renting it. To buy it, the
company would have to pay $105,000, but owning it will require approximately
$10,000 in maintenance costs per year. The price to rent the excavator is $5000 per
month, with a one-time service charge of $2000. What’s the minimum number of
months the company needs to use the excavator in order for it to make sense to
buy it rather than rent?
1. 8 months
2. 16 months
3. 21 months
4. 25 months
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Exercise 2: Plan Procurements
Which document are we referring below?
1. A type of procurement document used to request proposals from
prospective sellers of products or services.
2. A type of procurement document used to request price
quotations from prospective sellers of common or standard
products or services.
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Exercise 2: Plan Procurements
Which document are we referring below?
1. A type of procurement document used to request proposals from
prospective sellers of products or services.
RFP
2. A type of procurement document used to request price
quotations from prospective sellers of common or standard
products or services.
RFQ
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Conduct Procurement
Conduct Procurements is the process of obtaining seller responses, selecting a seller,
and awarding a contract
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Conduct Procurement
Inputs Tools and Techniques Outputs
 Project Management
Plan
 Procurement
documents
 Source selection
criteria
 Seller proposals
 Project documents
 Make or buy decisions
 Teaming agreements
 Organizational Process
Assets
 Bidder conferences
 Proposal evaluation techniques
 Independent estimates
 Expert Judgment
 Advertising
 Analytical Techniques
 Procurement negotiation
 Selected sellers
 Agreements
 Resource calendars
 Change requests
 Project
management plan
updates
 Project document
updates
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Project Management Plan contains procurement management plan and this
describes how the procurement process will be managed from preparing procurement
documentation through close procurements
Procurement Documents as explained earlier provide an audit trail for contracts and
other agreements
Source Selection criteria are set of guidelines, either subjective or objective, that
are used by the performing organization to select a particular contract/ vendor (seller)
from among the proposals received.
Seller proposals are responses to the procurement document package that will be
used for selection of the sellers by the organization’s evaluation body
Conduct Procurement - Inputs
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Project documents that are important inputs to this process include risk register and
risk related contract decisions.
Make- or -buy decisions as explained earlier is based on the outcome of Make –or-
buy- Analysis. The factors that influence the decision making include , core
competencies of the organization, value delivered, risk associated with meeting the
need in a cost=effective manner and internal capability as compared to the vendor
community.
Procurement Statement of Work provides suppliers with a clearly stated set of
goals , requirements, and outcomes from which they can provide a quantifiable
response. The statement of work include
 Specifications
 Quantity desired
 Quality levels
 Performance data, period of performance, work location and other requirements
Conduct Procurement - Inputs
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Organizational Process Assets that can influence this process include listings of
prospective and previously qualified sellers and information on relevant past
experience with sellers, prior agreements
Conduct Procurement - Inputs
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Conduct Procurement – Tools and Techniques
Bidder conferences are meetings wherein the prospective supplier (sellers) are called
in to ensure that all the supplier have a clear understanding of the work defined in the
procurement documents.
Proposal evaluation techniques are used to evaluate the proposals by giving a
rating score to each proposal
Independent estimates are sometimes prepared by the procuring organization using
internal expert in estimation or an outside professional estimator
Expert Judgment includes a team of experienced and skilled experts for evaluation of
proposals under various areas of expertise as mentioned in the procurement
documents and contract
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Conduct Procurement – Tools and Techniques
Advertising is used by the performing organization to invite the potential sellers to be
Contracted
Analytical Techniques, procurements involve defining a need in such as way
that vendors can bring value through offerings. To ensure that the need can be and is
met, analytical techniques can help organizations identify the readiness of a vendor to
provide the desired end state. By examining past performance information, teams may
identify areas that may have more risk and that need to be monitored closely to
ensure success of the project
Procurement negotiations between the buyers and the potential sellers are
performed with the goal of reaching mutual agreement on the contractual terms and
conditions. The goal is to reach a win-win scenario between the buyer and seller.
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Conduct Procurements– Outputs
Selected Sellers are those who have met the evaluation criteria and negotiated a
draft contract with the buyer, which will become the actual contract when the contract
is awarded
Agreement is a formal document governing the relationship between the buyer and
the seller. The contract describes the work to be performed and perhaps the way in
which the work will be performed. An important to include with the contract is how
disputes will be resolved. Depending upon the application area, an agreement can also
be called an understanding , a contract, a subcontract, or a purchase order.
Regardless of the document complexity , a contract is a mutually binding legal
agreement that obligates the seller to provide the specific products, services, or
results and obligates the buyer to compensate the seller. The major component of
agreement are:
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Conduct Procurements– Outputs
Major components of an agreement
 Statement of work or deliverables
 Schedule baselines
 Performance reporting
 Period of performance
 Roles and responsibilities
 Seller’s place of performance
 Pricing
 Payment Terms
 Place of delivery
 Inspection and acceptance criteria
 Warranty
 Product Support
 Limitation of liability
 Fees and retainer
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Conduct Procurements– Outputs
Major components of an agreement
 Penalties
 Incentives
 Insurance and performance bonds
 Subordinate subcontractor approvals
 Change request handling and
 Termination clause and alternative dispute resolution (ADR) mechanism. The ADR
method can be decided in advance as a part of the procurement award.
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Conduct Procurements– Outputs
Resource Calendar state the availability and the quantity of contracted resource and
the project period (dates) during which the resources are active or idle
Change Requests to the project management pan, its subsidiary plans and other
components are processed for review and disposition through the Perform Integrated
Change Control process.
Project Management Plan Updates, the elements of the project management plan
that may be updated include Cost baseline, Scope baseline, Schedule baseline,
Communication management plan, and Procurement management plan.
Project Document Updates, the project documents that may be updated include,
requirement documentation, requirement traceability documentation, risk register and
stakeholder register.
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Conduct Procurements– Outputs
Selected Sellers are those who have met the evaluation criteria and negotiated a
draft contract with the buyer, which will become the actual contract when the contract
is awarded
Procurement Contract Award is a formal document governing the relationship
between the buyer and the seller. The contract describes the work to be performed
and perhaps the way in which the work will be performed. An important to include
with the contract is how disputes will be resolved.
Resource Calendar state the availability and the quantity of contracted resource and
the project period (dates) during which the resources are active or idle
Change Requests As discussed earlie
Project Management Plan Updates As discussed earlier
Project Document Updates As discussed earlier
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Control Procurements
Managing procurement relationships, monitoring contract performance and
making changes and corrections as needed.
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Control Procurement
Inputs Tools and Techniques Outputs
 Project Management
Plan
 Procurement
documents
 Agreement
 Approved change
requests
 Work Performance
reports
 Work performance
Data
 Contract change control system
 Procurement performance
reviews
 Inspections and audits
 Performance reporting
 Payment system
 Claims administration
 Records management system
•
 Work performance
information
 Change requests
 Project
management plan
updates
 Project document
updates
 Organizational
process assets update
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Project Management Plan describes how the procurement process will be managed
from developing procurement documentation through contract closure.
Procurement documents contain complete supporting records for administration of
the procurement processes; this includes procurement contract awards and the
statement of work
Agreements As Explained earlier Agreements are understanding between parties,
including understanding of the duties of each parties.
Approved change requests include modifications to the terms and condition of the
contract including the procurement statement of work, pricing and the description of
the products , services or results.
Control Procurement - Inputs
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Work Performance Reports – is a seller performance related documentation that
include
 Technical documentation. Sellers- developed technical documentation and other
deliverable information are provided in accordance with the terms of the contract.
 Work performance information. The seller’s performance reports indicate which
deliverables have been completed and which have not.
Work Performance Data includes information on a regular basis of the performance
and status of the seller’s project work activities. It includes information such as which
deliverables have been completed and which have not, whether the quality standards
defined for the project are being adhered to and the payment is being made for the
costs that have been stated in the contract.
Control Procurement - Inputs
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Control Procurement – Tools and Techniques
Contract change control system is a component of integrated change control system
and it describes the process of updating the contract
Procurement performance reviews are periodic reviews initiated by the buyer to
measure the project’s progress against the plan
Inspections and audits are done by the buyer and supported by the seller to identify
any non-compliance to the project’s process or deliverables.
Performance reporting provides information to management about how effectively
the seller is achieving his contractual objective.
Payment system helps to ensure that invoices and payments match up and that the
right amount is being invoiced for the right deliverables at the right time.
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Control Procurement – Tools and Techniques
Claims administration are basically disagreements (about scope or change request).
It is preferred that the claims should be resolved by the parties involved as per the
dispute resolution procedure . If not resolved by the parties involved, then the disputes
are resolved by the process of Arbitration whereby a third neutral party is given the
task of getting the dispute resolved.
Records management system is a part of the project management information
systems (PMIS). In addition to the documentation, it also consists of processes, control
functions, and automated tools. This system should index various documents for their
easy retrieval and archival.
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Control Procurement – Outputs
Work Performance Information provides a basis for identification of current or
potential problems to support later claims or new procurements. By reporting on the
performance of a vendor, the organization increases the knowledge of the
performance of the procurement , which supports improved forecasting , risk
management and decision making. Performance reports also assist in the event there
is a dispute with the vendor.
Change requests, changes to the project management plan, its subsidiary plans, and
other components , such as the cost baseline, schedule baseline, and procurement
management plan may result from the control procurement process.
Project management plan updates includes update to the procurement
management plan ,schedule baseline and cost baseline
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Control Procurement – Outputs
Project Documents Updates include updates to procurement documentation, it
include the procurement contract with all supporting schedules, requested unapproved
contract changes , and approved change requests. It also includes any seller
developed technical documentation and other work performance information such as
deliverable s, seller performance reports and warranties, financial documents including
invoices and payment records, and the result of contract – related inspections.
Organizational process assets updates that will be updated as a result of this
process includes documentation related to seller’s unsatisfactory performance, request
for contract changes or clarifications, payments made by the buyer to the seller and
also the documents related to seller’s performance.
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Revising Tools and Techniques
Exercise : Control Procurements
1. ___________________ involves process to change the
procurement contract. It can involve the approvals, paperwork
and the dispute resolution mechanism required for the change
control.
2. ______________ system refers to how the payments are made to
the seller.
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Revising Tools and Techniques
Answer to Exercise : Control Procurements
1. Contract Change Control System involves process to change the
procurement contract. It can involve the approvals, paperwork
and the dispute resolution mechanism required for the change
control.
2. Payment system refers to how the payments are made to the
seller.
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Close procurements
Process of completing each project procurement. It involves administrative activities
such as updating the project records with results and archiving the information for
future use and finalizing open claims in accordance with the terms and conditions
stated in the contract document
Close Procurement process closes the procurement applicable to that phase of the
project
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Close procurements
Inputs Tools and Techniques Outputs
 Project Management
Plan
 Procurement
documentation
 Procurement audits
 Procurement Negotiations
 Records management system
 Closed
procurements
 Organizational
process assets
updates
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Close procurements- Inputs
Project Management Plan Discussed Earlier
Procurement documentation includes information on contract schedule, scope,
quality and cost performance along with all contract change documentation, payment
records and inspection results. This information can be used for lessons learned
information and as a basis of evaluating contractors for future contracts.
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Close procurements- Tools and Techniques
Procurement Audits is a structured review of the procurement processes from the
plan procurements process through administer contracts process. The purpose of
procurement audit is to identify the improvement areas and the flawed procurement
processes and/ or procedure. This will assist in reusing the successful/updated
procedures in other projects.
Procurement Negotiations refers to the settlement for any outstanding issues,
claims and disputes through negotiation. Whenever the settlement cannot be achieved
through direct negotiation, some form of alternative dispute resolution(ADR) including
mediation or arbitration can be explored
Records Management System is used by the project manager to manage contract
and procurement documentation and records. Contract documents and
correspondence are archived through the records management system as part of the
close procurement process
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Close procurements- Outputs
Closed Procurements is the process in which the buyer’s contract administrator
sends formal written notice to the seller that the contract is complete.
Organizational Process Assets Updates will be updated due to modification in the
procurement files and lessons learned documentation. Also, deliverable acceptance
and rejection will be stated in the final contract documentation with supporting
reasons.
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Reviewing Associated Risks to Buyers & Sellers
Exercise 5: Contract Type
Explain the risks from buyer and seller perspective in case of the following
types of contracts
1. Firm fixed price
2. Fixed price plus incentive fee (FPIF)
3. Cost plus fixed fee
4. Cost plus award fee
5. Cost plus incentive fee
6. Time and Material (T&M)
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
 Negotiations Techniques
– Deadline: imposing a deadline to reach an agreement
– Stalling: one party may claim that an agreement cannot be finalized
because of his limited authority
– Fair and Responsible: a negotiator may claim that the price for a
product is equitable because that’s what another company is
paying.
– Delay: are useful when tempers are beginning to flare, to divert from
a subject, etc (Ex: arrival of refreshments, request for recess etc)
– Withdrawal: one party may attack an issue, then retreat
Project Procurement Management
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
 Negotiations Techniques
– Arbitration: a third party may be brought in when agreement cannot
be reached. (out of court settlement)
– Fait Accompli: a party may claim that what is being asked for has
already been accomplished and cannot be changed
Project Procurement Management
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Revising Key Terms : Complete the following
Exercise 5: Procurement Management
1. An Invitation for __________ is a document that ask sellers for
the price of work
2. The buyer selects the __________ selection criteria before
contacting potential sellers
3. The ___________contract has high risk to the seller because the
seller must cover costs that go beyond the price
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
QUIZ !
pankaj sharma, Mobile -
9810996356
Pankaj Sharma - Mobile No -919810996356

Weitere ähnliche Inhalte

Was ist angesagt?

Contract management
Contract managementContract management
Contract managementNishant Rai
 
Project management procurement
Project management  procurementProject management  procurement
Project management procurementMalcolm Peart
 
Lecture 1 Introduction to Procurement and contract Management Management - Co...
Lecture 1 Introduction to Procurement and contract Management Management - Co...Lecture 1 Introduction to Procurement and contract Management Management - Co...
Lecture 1 Introduction to Procurement and contract Management Management - Co...axmedbaasaay
 
Introduction to contract management
Introduction to contract managementIntroduction to contract management
Introduction to contract managementBerkman Solutions
 
PMP Chap 12 - Project Procurement Management Details - Part2
PMP   Chap 12 - Project Procurement Management Details - Part2PMP   Chap 12 - Project Procurement Management Details - Part2
PMP Chap 12 - Project Procurement Management Details - Part2Anand Bobade
 
Procurement
ProcurementProcurement
Procurementasim78
 
Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar Saket Bansal
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
PMP Chap 13 - Project stakeholder management Overview
PMP Chap 13 - Project stakeholder management OverviewPMP Chap 13 - Project stakeholder management Overview
PMP Chap 13 - Project stakeholder management OverviewAnand Bobade
 
Procurement system
Procurement systemProcurement system
Procurement systemAlmahi Adam
 

Was ist angesagt? (20)

Contract management
Contract managementContract management
Contract management
 
Project management procurement
Project management  procurementProject management  procurement
Project management procurement
 
PMP_Project Procurement Management
PMP_Project Procurement ManagementPMP_Project Procurement Management
PMP_Project Procurement Management
 
Procurement Management
Procurement ManagementProcurement Management
Procurement Management
 
Lecture 1 Introduction to Procurement and contract Management Management - Co...
Lecture 1 Introduction to Procurement and contract Management Management - Co...Lecture 1 Introduction to Procurement and contract Management Management - Co...
Lecture 1 Introduction to Procurement and contract Management Management - Co...
 
Procurement- Contract Management
Procurement- Contract ManagementProcurement- Contract Management
Procurement- Contract Management
 
Contract Management
Contract ManagementContract Management
Contract Management
 
Introduction to contract management
Introduction to contract managementIntroduction to contract management
Introduction to contract management
 
Procurement management
Procurement managementProcurement management
Procurement management
 
PMP Chap 12 - Project Procurement Management Details - Part2
PMP   Chap 12 - Project Procurement Management Details - Part2PMP   Chap 12 - Project Procurement Management Details - Part2
PMP Chap 12 - Project Procurement Management Details - Part2
 
Procurement
ProcurementProcurement
Procurement
 
PROCUREMENT
PROCUREMENTPROCUREMENT
PROCUREMENT
 
Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar
 
9. project procurement management
9. project procurement management9. project procurement management
9. project procurement management
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
PMP Chap 13 - Project stakeholder management Overview
PMP Chap 13 - Project stakeholder management OverviewPMP Chap 13 - Project stakeholder management Overview
PMP Chap 13 - Project stakeholder management Overview
 
Procurement system
Procurement systemProcurement system
Procurement system
 
Procurement process snippet
Procurement process snippetProcurement process snippet
Procurement process snippet
 

Andere mochten auch

Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Editionpankajsh10
 
Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5pankajsh10
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Managementpankajsh10
 
Project communications management (PMBOK 5th Edition)
Project communications management (PMBOK 5th Edition)Project communications management (PMBOK 5th Edition)
Project communications management (PMBOK 5th Edition)pankajsh10
 
Project Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th EditionProject Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th Editionpankajsh10
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Editionpankajsh10
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Editionpankajsh10
 
Project Management Framework - PMBOK 5
Project Management Framework - PMBOK 5Project Management Framework - PMBOK 5
Project Management Framework - PMBOK 5pankajsh10
 
Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5pankajsh10
 
Project Risk Management - PMBOK5
Project Risk Management - PMBOK5Project Risk Management - PMBOK5
Project Risk Management - PMBOK5pankajsh10
 
すぐに分かる!プロジェクト計画の作り方
すぐに分かる!プロジェクト計画の作り方すぐに分かる!プロジェクト計画の作り方
すぐに分かる!プロジェクト計画の作り方Eisuke Sugitani
 
JenkinsとGitで実装するGatewayCheckIn Pattern #AsianAA
JenkinsとGitで実装するGatewayCheckIn Pattern #AsianAAJenkinsとGitで実装するGatewayCheckIn Pattern #AsianAA
JenkinsとGitで実装するGatewayCheckIn Pattern #AsianAAkyon mm
 
ウォーターフォールでカンバンやってみた!
ウォーターフォールでカンバンやってみた!ウォーターフォールでカンバンやってみた!
ウォーターフォールでカンバンやってみた!尚 鈴木
 
Jenkinsを使ったコンシューマゲームでのデプロイとテスト
Jenkinsを使ったコンシューマゲームでのデプロイとテストJenkinsを使ったコンシューマゲームでのデプロイとテスト
Jenkinsを使ったコンシューマゲームでのデプロイとテストHiroyuki Tanaka
 
ようこそ!“プロジェクトマネジメント保健室”へ!
ようこそ!“プロジェクトマネジメント保健室”へ!ようこそ!“プロジェクトマネジメント保健室”へ!
ようこそ!“プロジェクトマネジメント保健室”へ!Ayako Togaeri
 
よりぬきPmbok~ゲーム開発風味~ Web02
よりぬきPmbok~ゲーム開発風味~ Web02よりぬきPmbok~ゲーム開発風味~ Web02
よりぬきPmbok~ゲーム開発風味~ Web02minamo
 
Scrum始めました
Scrum始めましたScrum始めました
Scrum始めましたminamo
 
[G-Tech2014講演資料] プロジェクト・コスト・マネジメントの核心 - グローバルナレッジ
[G-Tech2014講演資料] プロジェクト・コスト・マネジメントの核心 - グローバルナレッジ[G-Tech2014講演資料] プロジェクト・コスト・マネジメントの核心 - グローバルナレッジ
[G-Tech2014講演資料] プロジェクト・コスト・マネジメントの核心 - グローバルナレッジTrainocate Japan, Ltd.
 

Andere mochten auch (20)

Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Edition
 
Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
Project communications management (PMBOK 5th Edition)
Project communications management (PMBOK 5th Edition)Project communications management (PMBOK 5th Edition)
Project communications management (PMBOK 5th Edition)
 
Project Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th EditionProject Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th Edition
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Edition
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Edition
 
Project Management Framework - PMBOK 5
Project Management Framework - PMBOK 5Project Management Framework - PMBOK 5
Project Management Framework - PMBOK 5
 
Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5
 
Project Risk Management - PMBOK5
Project Risk Management - PMBOK5Project Risk Management - PMBOK5
Project Risk Management - PMBOK5
 
Chap12 project procurement management
Chap12 project procurement managementChap12 project procurement management
Chap12 project procurement management
 
PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP
PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACPPMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP
PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP
 
すぐに分かる!プロジェクト計画の作り方
すぐに分かる!プロジェクト計画の作り方すぐに分かる!プロジェクト計画の作り方
すぐに分かる!プロジェクト計画の作り方
 
JenkinsとGitで実装するGatewayCheckIn Pattern #AsianAA
JenkinsとGitで実装するGatewayCheckIn Pattern #AsianAAJenkinsとGitで実装するGatewayCheckIn Pattern #AsianAA
JenkinsとGitで実装するGatewayCheckIn Pattern #AsianAA
 
ウォーターフォールでカンバンやってみた!
ウォーターフォールでカンバンやってみた!ウォーターフォールでカンバンやってみた!
ウォーターフォールでカンバンやってみた!
 
Jenkinsを使ったコンシューマゲームでのデプロイとテスト
Jenkinsを使ったコンシューマゲームでのデプロイとテストJenkinsを使ったコンシューマゲームでのデプロイとテスト
Jenkinsを使ったコンシューマゲームでのデプロイとテスト
 
ようこそ!“プロジェクトマネジメント保健室”へ!
ようこそ!“プロジェクトマネジメント保健室”へ!ようこそ!“プロジェクトマネジメント保健室”へ!
ようこそ!“プロジェクトマネジメント保健室”へ!
 
よりぬきPmbok~ゲーム開発風味~ Web02
よりぬきPmbok~ゲーム開発風味~ Web02よりぬきPmbok~ゲーム開発風味~ Web02
よりぬきPmbok~ゲーム開発風味~ Web02
 
Scrum始めました
Scrum始めましたScrum始めました
Scrum始めました
 
[G-Tech2014講演資料] プロジェクト・コスト・マネジメントの核心 - グローバルナレッジ
[G-Tech2014講演資料] プロジェクト・コスト・マネジメントの核心 - グローバルナレッジ[G-Tech2014講演資料] プロジェクト・コスト・マネジメントの核心 - グローバルナレッジ
[G-Tech2014講演資料] プロジェクト・コスト・マネジメントの核心 - グローバルナレッジ
 

Ähnlich wie Project Procurement Management PMBOK 5

What is Procurement Methods and Process ITFC
What is Procurement Methods and Process ITFCWhat is Procurement Methods and Process ITFC
What is Procurement Methods and Process ITFCWalter Deagle
 
CONTEMPORARY PROJECT MANAGEMENT, 4ETimothy J. KloppenborgVit.docx
CONTEMPORARY PROJECT MANAGEMENT, 4ETimothy J. KloppenborgVit.docxCONTEMPORARY PROJECT MANAGEMENT, 4ETimothy J. KloppenborgVit.docx
CONTEMPORARY PROJECT MANAGEMENT, 4ETimothy J. KloppenborgVit.docxaidaclewer
 
Plan procurement management
Plan procurement management Plan procurement management
Plan procurement management Shereef Sabri
 
Procurement management
Procurement managementProcurement management
Procurement managementSuperstarRr
 
Procurement management by- Prateek kumar
Procurement management by- Prateek kumarProcurement management by- Prateek kumar
Procurement management by- Prateek kumarPrateek Kumar
 
The Contract And Procurement Management Process
The Contract And Procurement Management ProcessThe Contract And Procurement Management Process
The Contract And Procurement Management ProcessPamela Wright
 
Procurement ManagementImportance of Project Procurem
Procurement ManagementImportance of Project ProcuremProcurement ManagementImportance of Project Procurem
Procurement ManagementImportance of Project ProcuremDaliaCulbertson719
 
Conduct procurements
Conduct procurements Conduct procurements
Conduct procurements Shereef Sabri
 
#Procurement Strategies & strategic Sourcing : Cost Reduction - By SN Panigrahi
#Procurement Strategies & strategic Sourcing : Cost Reduction - By SN Panigrahi#Procurement Strategies & strategic Sourcing : Cost Reduction - By SN Panigrahi
#Procurement Strategies & strategic Sourcing : Cost Reduction - By SN PanigrahiSN Panigrahi, PMP
 
Pradeep Resume 30 March 2015
Pradeep Resume 30 March 2015Pradeep Resume 30 March 2015
Pradeep Resume 30 March 2015Pradeep M P
 
Purchasing & supply chain management
Purchasing & supply chain managementPurchasing & supply chain management
Purchasing & supply chain managementSajeena Justin
 
Eprocurement sourcing mro environment
Eprocurement  sourcing   mro environmentEprocurement  sourcing   mro environment
Eprocurement sourcing mro environmentUtomo Prawiro
 
Faid daoud updated cv 19 july 2016
Faid daoud updated cv 19 july 2016Faid daoud updated cv 19 july 2016
Faid daoud updated cv 19 july 2016Faid Daoud
 
Final presentation from shahida
Final presentation from shahidaFinal presentation from shahida
Final presentation from shahidashahida quraishi
 
33.1.019 Importance of Best Practices
33.1.019 Importance of Best Practices33.1.019 Importance of Best Practices
33.1.019 Importance of Best PracticesClark Cledwyn Bagaipo
 

Ähnlich wie Project Procurement Management PMBOK 5 (20)

What is Procurement Methods and Process ITFC
What is Procurement Methods and Process ITFCWhat is Procurement Methods and Process ITFC
What is Procurement Methods and Process ITFC
 
CONTEMPORARY PROJECT MANAGEMENT, 4ETimothy J. KloppenborgVit.docx
CONTEMPORARY PROJECT MANAGEMENT, 4ETimothy J. KloppenborgVit.docxCONTEMPORARY PROJECT MANAGEMENT, 4ETimothy J. KloppenborgVit.docx
CONTEMPORARY PROJECT MANAGEMENT, 4ETimothy J. KloppenborgVit.docx
 
Plan procurement management
Plan procurement management Plan procurement management
Plan procurement management
 
Procurement management
Procurement managementProcurement management
Procurement management
 
Sourcing & SRM
Sourcing & SRMSourcing & SRM
Sourcing & SRM
 
Sourcing & SRM
Sourcing & SRMSourcing & SRM
Sourcing & SRM
 
Procurement management by- Prateek kumar
Procurement management by- Prateek kumarProcurement management by- Prateek kumar
Procurement management by- Prateek kumar
 
The Contract And Procurement Management Process
The Contract And Procurement Management ProcessThe Contract And Procurement Management Process
The Contract And Procurement Management Process
 
Procurement ManagementImportance of Project Procurem
Procurement ManagementImportance of Project ProcuremProcurement ManagementImportance of Project Procurem
Procurement ManagementImportance of Project Procurem
 
Resume
ResumeResume
Resume
 
Conduct procurements
Conduct procurements Conduct procurements
Conduct procurements
 
#Procurement Strategies & strategic Sourcing : Cost Reduction - By SN Panigrahi
#Procurement Strategies & strategic Sourcing : Cost Reduction - By SN Panigrahi#Procurement Strategies & strategic Sourcing : Cost Reduction - By SN Panigrahi
#Procurement Strategies & strategic Sourcing : Cost Reduction - By SN Panigrahi
 
Pradeep Resume 30 March 2015
Pradeep Resume 30 March 2015Pradeep Resume 30 March 2015
Pradeep Resume 30 March 2015
 
16-20procurement.ppt
16-20procurement.ppt16-20procurement.ppt
16-20procurement.ppt
 
The ultimate source to pay (S2P) process guide for 2023.pptx
The ultimate source to pay (S2P) process guide for 2023.pptxThe ultimate source to pay (S2P) process guide for 2023.pptx
The ultimate source to pay (S2P) process guide for 2023.pptx
 
Purchasing & supply chain management
Purchasing & supply chain managementPurchasing & supply chain management
Purchasing & supply chain management
 
Eprocurement sourcing mro environment
Eprocurement  sourcing   mro environmentEprocurement  sourcing   mro environment
Eprocurement sourcing mro environment
 
Faid daoud updated cv 19 july 2016
Faid daoud updated cv 19 july 2016Faid daoud updated cv 19 july 2016
Faid daoud updated cv 19 july 2016
 
Final presentation from shahida
Final presentation from shahidaFinal presentation from shahida
Final presentation from shahida
 
33.1.019 Importance of Best Practices
33.1.019 Importance of Best Practices33.1.019 Importance of Best Practices
33.1.019 Importance of Best Practices
 

Kürzlich hochgeladen

A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...PsychoTech Services
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 

Kürzlich hochgeladen (20)

A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 

Project Procurement Management PMBOK 5

  • 1. Connoisseur Solutions Project Procurement Management pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 2. Connoisseur Solutions Project Procurement Management Processes necessary to purchase or acquire products, services or results needed from outside the project team. pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 3. Connoisseur Solutions Procurement Management Processes Process Process Group Plan Procurements Planning Conduct Procurements Executing Control Procurements Monitoring and Controlling Close Procurements Closing pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 4. Connoisseur Solutions Plan Procurements Plan Procurements is the process of documenting project purchasing decisions, specifying the approach, and identifying potential sellers pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 5. Connoisseur Solutions Plan Procurements Inputs Tools and Techniques Outputs  Project management plan  Requirements documentation  Teaming agreements  Risk Register  Project Schedule  Activity cost estimates  Stakeholder register  Enterprise Environmental Factors  Organizational Process Assets  Make or buy analysis  Expert Judgment  Market research  Meetings  Procurement management plan  Procurement statements of work  Make or buy decisions  Procurement documents  Source selection criteria  Change requests  Project document updates pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 6. Connoisseur Solutions Plan Procurements - Inputs Project Management Plan - describes the need, justification, requirements, and current boundaries for the project. It consists of Scope statement, WBS and WBS dictionary. Requirements documentation include Important information about project requirements that is considered during planning for procurements. Risk Register include risk-related information such as identified risk, risk owners and risk responses Activity resource requirements state the type and quantities of resources needed for project activities Project Schedule provides information on project timelines and milestones Activity cost estimates are used to evaluate the price quoted in the bids or proposals received from potential sellers Stakeholder Register describes the details on the participants and their interest in the project pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 7. Connoisseur Solutions Plan Procurements - Inputs Enterprise Environmental Factors includes condition of marketplace, what product and service are available in the market, who is the seller and what are his terms and condition Organizational Process Assets includes policies and procedures , standards ,guidelines, performance measurement criteria, defect management procedures, change control procedures and historical information. Some organizations may define certain constraint on procurement decisions. This also include the various types of contractual agreements used by the organization, All legal contractual relationships generally fall into one of two broad families: either fixed – price or cost reimbursable. Also, there is a third hybrid type commonly in use called the time and materials contract. The next slides describes the different contract types in details pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 8. Connoisseur Solutions Plan Procurements -Tools and Techniques Time & Material – T & M The seller is paid for the amount of time it takes to accomplish the work and he is also reimbursed for the materials used for the project Firm Fixed Price - FFP The seller is paid a fixed price for an agreed upon unit of work done by him Fixed Price Incentive Fee – FPIF The seller is paid a fixed price plus an incentive amount for achieving pre-agreed project metrics Fixed Price with Economic Price Adjustment Contracts – FP-EPA The seller is paid a fixed price. The contract is reviewed at pre-defined intervals in the project for adjustments to the contract price based on certain parameters Types of Contract pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 9. Connoisseur Solutions Plan Procurements -Tools and Techniques Cost Plus Fixed Fee – CPFF The contractor is reimbursed its cost plus an additional fixed fee. Not desirable from the buyer’s point of view Cost Plus Incentive Fee - CPIF Seller is reimbursed for an agreed upon performance cost along with a pre- established fee plus an incentive bonus. In this case, the buyer and seller share the uncertainty to a certain degree Cost Plus Award Fee Seller is reimbursed for an agreed upon performance cost plus all legitimate cost Types of Contract pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 10. Connoisseur Solutions Plan Procurements -Tools and Techniques Make or buy analysis helps project management team to decide whether it is beneficial (in terms of cost and quality) to procure a product or service or it can be produced within the organization. Market Research includes examination of industry and specific vendor capabilities. Procurement teams may leverage information gained at conferences , online reviews and a variety of sources to identify market capabilities. Meetings , by collaborating with potential bidders , the organization purchasing the material or service may benefit while supplier can influence a mutually beneficial approach or product. pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 11. Connoisseur Solutions Plan Procurements - Outputs Procurement management plan describes how the procurement process will be managed from planning procurement to close procurement. It contains detail on 1. Types of Contracts to be used 2. Risk management issues 3. Whether independent estimates will be used and whether they are needed as evaluation criteria 4. Standardized procurement documents, if needed 5. Process of managing multiple providers (sellers) 6. Coordination with other project aspects 7. Any constraints and assumptions that could affect planned procurements 8. Handling the long lead times to purchase certain items from sellers and coordinating the extra time needed to procure these items with the development of the project schedule 9. Handling make – or – buy decision and linking them to the Estimate Activity Resources and Develop schedule process. pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 12. Connoisseur Solutions Plan Procurements - Outputs Procurement statements of work defines the products, services , or result to be procured in details so that the seller can be sure that he can provide appropriate products , services, or results. It is developed from the project scope baseline and defines only that portion of the project scope that needs to be procured and stated in the contract. Procurement documents define the buyer’s requirements and facilitate complete and correct response from the prospective sellers in the form of a proposal, which aids in the selection of the seller(s). The most commonly used procurement documents are RFP (Request for Proposal), IFB (Invitation for Bid and RFI (Request for Information pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 13. Connoisseur Solutions Plan Procurements - Outputs Source selection criteria are the set of guidelines on the basis of which a particular seller is selected from among the proposals received. Some of the source selection criteria are seller’s understanding of need , overall- life-cycle cost, technical capability, Risk, past performance of the seller, Financial capacity, Warranty etc Make –or - Buy Decisions, A make-or- buy analysis results in a decision of whether particular work can best be accomplished by the project team or needs to be purchased from outside sources. Change requests may be there during this process due to updates in the project plan or its subsidiary plan and other components. These changes are reviewed and approved through the integrated change control process. Project Documents Updates that may be updated include requirement documentation, requirements traceability matrix and risk register. pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 14. Connoisseur Solutions Practicing Key Concepts Exercise 1: Make or Buy Analysis You’ve been contracted by a construction company to manage their contracting. They have a choice of either buying an excavator or renting it. To buy it, the company would have to pay $105,000, but owning it will require approximately $10,000 in maintenance costs per year. The price to rent the excavator is $5000 per month, with a one-time service charge of $2000. What’s the minimum number of months the company needs to use the excavator in order for it to make sense to buy it rather than rent? 1. 8 months 2. 16 months 3. 21 months 4. 25 months pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 15. Connoisseur Solutions Exercise 2: Plan Procurements Which document are we referring below? 1. A type of procurement document used to request proposals from prospective sellers of products or services. 2. A type of procurement document used to request price quotations from prospective sellers of common or standard products or services. pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 16. Connoisseur Solutions Exercise 2: Plan Procurements Which document are we referring below? 1. A type of procurement document used to request proposals from prospective sellers of products or services. RFP 2. A type of procurement document used to request price quotations from prospective sellers of common or standard products or services. RFQ pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 17. Connoisseur Solutions Conduct Procurement Conduct Procurements is the process of obtaining seller responses, selecting a seller, and awarding a contract pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 18. Connoisseur Solutions Conduct Procurement Inputs Tools and Techniques Outputs  Project Management Plan  Procurement documents  Source selection criteria  Seller proposals  Project documents  Make or buy decisions  Teaming agreements  Organizational Process Assets  Bidder conferences  Proposal evaluation techniques  Independent estimates  Expert Judgment  Advertising  Analytical Techniques  Procurement negotiation  Selected sellers  Agreements  Resource calendars  Change requests  Project management plan updates  Project document updates pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 19. Connoisseur Solutions Project Management Plan contains procurement management plan and this describes how the procurement process will be managed from preparing procurement documentation through close procurements Procurement Documents as explained earlier provide an audit trail for contracts and other agreements Source Selection criteria are set of guidelines, either subjective or objective, that are used by the performing organization to select a particular contract/ vendor (seller) from among the proposals received. Seller proposals are responses to the procurement document package that will be used for selection of the sellers by the organization’s evaluation body Conduct Procurement - Inputs pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 20. Connoisseur Solutions Project documents that are important inputs to this process include risk register and risk related contract decisions. Make- or -buy decisions as explained earlier is based on the outcome of Make –or- buy- Analysis. The factors that influence the decision making include , core competencies of the organization, value delivered, risk associated with meeting the need in a cost=effective manner and internal capability as compared to the vendor community. Procurement Statement of Work provides suppliers with a clearly stated set of goals , requirements, and outcomes from which they can provide a quantifiable response. The statement of work include  Specifications  Quantity desired  Quality levels  Performance data, period of performance, work location and other requirements Conduct Procurement - Inputs pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 21. Connoisseur Solutions Organizational Process Assets that can influence this process include listings of prospective and previously qualified sellers and information on relevant past experience with sellers, prior agreements Conduct Procurement - Inputs pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 22. Connoisseur Solutions Conduct Procurement – Tools and Techniques Bidder conferences are meetings wherein the prospective supplier (sellers) are called in to ensure that all the supplier have a clear understanding of the work defined in the procurement documents. Proposal evaluation techniques are used to evaluate the proposals by giving a rating score to each proposal Independent estimates are sometimes prepared by the procuring organization using internal expert in estimation or an outside professional estimator Expert Judgment includes a team of experienced and skilled experts for evaluation of proposals under various areas of expertise as mentioned in the procurement documents and contract pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 23. Connoisseur Solutions Conduct Procurement – Tools and Techniques Advertising is used by the performing organization to invite the potential sellers to be Contracted Analytical Techniques, procurements involve defining a need in such as way that vendors can bring value through offerings. To ensure that the need can be and is met, analytical techniques can help organizations identify the readiness of a vendor to provide the desired end state. By examining past performance information, teams may identify areas that may have more risk and that need to be monitored closely to ensure success of the project Procurement negotiations between the buyers and the potential sellers are performed with the goal of reaching mutual agreement on the contractual terms and conditions. The goal is to reach a win-win scenario between the buyer and seller. pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 24. Connoisseur Solutions Conduct Procurements– Outputs Selected Sellers are those who have met the evaluation criteria and negotiated a draft contract with the buyer, which will become the actual contract when the contract is awarded Agreement is a formal document governing the relationship between the buyer and the seller. The contract describes the work to be performed and perhaps the way in which the work will be performed. An important to include with the contract is how disputes will be resolved. Depending upon the application area, an agreement can also be called an understanding , a contract, a subcontract, or a purchase order. Regardless of the document complexity , a contract is a mutually binding legal agreement that obligates the seller to provide the specific products, services, or results and obligates the buyer to compensate the seller. The major component of agreement are: pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 25. Connoisseur Solutions Conduct Procurements– Outputs Major components of an agreement  Statement of work or deliverables  Schedule baselines  Performance reporting  Period of performance  Roles and responsibilities  Seller’s place of performance  Pricing  Payment Terms  Place of delivery  Inspection and acceptance criteria  Warranty  Product Support  Limitation of liability  Fees and retainer pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 26. Connoisseur Solutions Conduct Procurements– Outputs Major components of an agreement  Penalties  Incentives  Insurance and performance bonds  Subordinate subcontractor approvals  Change request handling and  Termination clause and alternative dispute resolution (ADR) mechanism. The ADR method can be decided in advance as a part of the procurement award. pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 27. Connoisseur Solutions Conduct Procurements– Outputs Resource Calendar state the availability and the quantity of contracted resource and the project period (dates) during which the resources are active or idle Change Requests to the project management pan, its subsidiary plans and other components are processed for review and disposition through the Perform Integrated Change Control process. Project Management Plan Updates, the elements of the project management plan that may be updated include Cost baseline, Scope baseline, Schedule baseline, Communication management plan, and Procurement management plan. Project Document Updates, the project documents that may be updated include, requirement documentation, requirement traceability documentation, risk register and stakeholder register. pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 28. Connoisseur Solutions Conduct Procurements– Outputs Selected Sellers are those who have met the evaluation criteria and negotiated a draft contract with the buyer, which will become the actual contract when the contract is awarded Procurement Contract Award is a formal document governing the relationship between the buyer and the seller. The contract describes the work to be performed and perhaps the way in which the work will be performed. An important to include with the contract is how disputes will be resolved. Resource Calendar state the availability and the quantity of contracted resource and the project period (dates) during which the resources are active or idle Change Requests As discussed earlie Project Management Plan Updates As discussed earlier Project Document Updates As discussed earlier pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 29. Connoisseur Solutions Control Procurements Managing procurement relationships, monitoring contract performance and making changes and corrections as needed. pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 30. Connoisseur Solutions Control Procurement Inputs Tools and Techniques Outputs  Project Management Plan  Procurement documents  Agreement  Approved change requests  Work Performance reports  Work performance Data  Contract change control system  Procurement performance reviews  Inspections and audits  Performance reporting  Payment system  Claims administration  Records management system •  Work performance information  Change requests  Project management plan updates  Project document updates  Organizational process assets update pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 31. Connoisseur Solutions Project Management Plan describes how the procurement process will be managed from developing procurement documentation through contract closure. Procurement documents contain complete supporting records for administration of the procurement processes; this includes procurement contract awards and the statement of work Agreements As Explained earlier Agreements are understanding between parties, including understanding of the duties of each parties. Approved change requests include modifications to the terms and condition of the contract including the procurement statement of work, pricing and the description of the products , services or results. Control Procurement - Inputs pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 32. Connoisseur Solutions Work Performance Reports – is a seller performance related documentation that include  Technical documentation. Sellers- developed technical documentation and other deliverable information are provided in accordance with the terms of the contract.  Work performance information. The seller’s performance reports indicate which deliverables have been completed and which have not. Work Performance Data includes information on a regular basis of the performance and status of the seller’s project work activities. It includes information such as which deliverables have been completed and which have not, whether the quality standards defined for the project are being adhered to and the payment is being made for the costs that have been stated in the contract. Control Procurement - Inputs pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 33. Connoisseur Solutions Control Procurement – Tools and Techniques Contract change control system is a component of integrated change control system and it describes the process of updating the contract Procurement performance reviews are periodic reviews initiated by the buyer to measure the project’s progress against the plan Inspections and audits are done by the buyer and supported by the seller to identify any non-compliance to the project’s process or deliverables. Performance reporting provides information to management about how effectively the seller is achieving his contractual objective. Payment system helps to ensure that invoices and payments match up and that the right amount is being invoiced for the right deliverables at the right time. pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 34. Connoisseur Solutions Control Procurement – Tools and Techniques Claims administration are basically disagreements (about scope or change request). It is preferred that the claims should be resolved by the parties involved as per the dispute resolution procedure . If not resolved by the parties involved, then the disputes are resolved by the process of Arbitration whereby a third neutral party is given the task of getting the dispute resolved. Records management system is a part of the project management information systems (PMIS). In addition to the documentation, it also consists of processes, control functions, and automated tools. This system should index various documents for their easy retrieval and archival. pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 35. Connoisseur Solutions Control Procurement – Outputs Work Performance Information provides a basis for identification of current or potential problems to support later claims or new procurements. By reporting on the performance of a vendor, the organization increases the knowledge of the performance of the procurement , which supports improved forecasting , risk management and decision making. Performance reports also assist in the event there is a dispute with the vendor. Change requests, changes to the project management plan, its subsidiary plans, and other components , such as the cost baseline, schedule baseline, and procurement management plan may result from the control procurement process. Project management plan updates includes update to the procurement management plan ,schedule baseline and cost baseline pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 36. Connoisseur Solutions Control Procurement – Outputs Project Documents Updates include updates to procurement documentation, it include the procurement contract with all supporting schedules, requested unapproved contract changes , and approved change requests. It also includes any seller developed technical documentation and other work performance information such as deliverable s, seller performance reports and warranties, financial documents including invoices and payment records, and the result of contract – related inspections. Organizational process assets updates that will be updated as a result of this process includes documentation related to seller’s unsatisfactory performance, request for contract changes or clarifications, payments made by the buyer to the seller and also the documents related to seller’s performance. pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 37. Connoisseur Solutions Revising Tools and Techniques Exercise : Control Procurements 1. ___________________ involves process to change the procurement contract. It can involve the approvals, paperwork and the dispute resolution mechanism required for the change control. 2. ______________ system refers to how the payments are made to the seller. pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 38. Connoisseur Solutions Revising Tools and Techniques Answer to Exercise : Control Procurements 1. Contract Change Control System involves process to change the procurement contract. It can involve the approvals, paperwork and the dispute resolution mechanism required for the change control. 2. Payment system refers to how the payments are made to the seller. pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 39. Connoisseur Solutions Close procurements Process of completing each project procurement. It involves administrative activities such as updating the project records with results and archiving the information for future use and finalizing open claims in accordance with the terms and conditions stated in the contract document Close Procurement process closes the procurement applicable to that phase of the project pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 40. Connoisseur Solutions Close procurements Inputs Tools and Techniques Outputs  Project Management Plan  Procurement documentation  Procurement audits  Procurement Negotiations  Records management system  Closed procurements  Organizational process assets updates pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 41. Connoisseur Solutions Close procurements- Inputs Project Management Plan Discussed Earlier Procurement documentation includes information on contract schedule, scope, quality and cost performance along with all contract change documentation, payment records and inspection results. This information can be used for lessons learned information and as a basis of evaluating contractors for future contracts. pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 42. Connoisseur Solutions Close procurements- Tools and Techniques Procurement Audits is a structured review of the procurement processes from the plan procurements process through administer contracts process. The purpose of procurement audit is to identify the improvement areas and the flawed procurement processes and/ or procedure. This will assist in reusing the successful/updated procedures in other projects. Procurement Negotiations refers to the settlement for any outstanding issues, claims and disputes through negotiation. Whenever the settlement cannot be achieved through direct negotiation, some form of alternative dispute resolution(ADR) including mediation or arbitration can be explored Records Management System is used by the project manager to manage contract and procurement documentation and records. Contract documents and correspondence are archived through the records management system as part of the close procurement process pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 43. Connoisseur Solutions Close procurements- Outputs Closed Procurements is the process in which the buyer’s contract administrator sends formal written notice to the seller that the contract is complete. Organizational Process Assets Updates will be updated due to modification in the procurement files and lessons learned documentation. Also, deliverable acceptance and rejection will be stated in the final contract documentation with supporting reasons. pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 44. Connoisseur Solutions Reviewing Associated Risks to Buyers & Sellers Exercise 5: Contract Type Explain the risks from buyer and seller perspective in case of the following types of contracts 1. Firm fixed price 2. Fixed price plus incentive fee (FPIF) 3. Cost plus fixed fee 4. Cost plus award fee 5. Cost plus incentive fee 6. Time and Material (T&M) pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 45. Connoisseur Solutions  Negotiations Techniques – Deadline: imposing a deadline to reach an agreement – Stalling: one party may claim that an agreement cannot be finalized because of his limited authority – Fair and Responsible: a negotiator may claim that the price for a product is equitable because that’s what another company is paying. – Delay: are useful when tempers are beginning to flare, to divert from a subject, etc (Ex: arrival of refreshments, request for recess etc) – Withdrawal: one party may attack an issue, then retreat Project Procurement Management pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 46. Connoisseur Solutions  Negotiations Techniques – Arbitration: a third party may be brought in when agreement cannot be reached. (out of court settlement) – Fait Accompli: a party may claim that what is being asked for has already been accomplished and cannot be changed Project Procurement Management pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 47. Connoisseur Solutions Revising Key Terms : Complete the following Exercise 5: Procurement Management 1. An Invitation for __________ is a document that ask sellers for the price of work 2. The buyer selects the __________ selection criteria before contacting potential sellers 3. The ___________contract has high risk to the seller because the seller must cover costs that go beyond the price pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 48. Connoisseur Solutions QUIZ ! pankaj sharma, Mobile - 9810996356 Pankaj Sharma - Mobile No -919810996356