3P 
RAPIDLY 
DESIGN A LEAN 
MANUFACTURING 
PROCESS 
(Overview)
It All Starts With a Great Idea for a 
New Product
However After Launch…… 
• Capital Investments & 
Operating Costs - Over Budget 
• Poor Customer Service & Long 
Lead-Times 
• Batch Processing - No Flow 
• Rework Loops Everywhere 
• Environmental, Ergonomic & 
Safety Issues 
• “Thrown Over Wall”: All key 
Members Upset They Were 
Not Involved in Process Design
PRO-ACTIVE SOLUTION 
Production Preparation Process
WHAT IS 3P? 
 Intense 3-5 Day Event 
 A Focus on Developing a Waste-Free System 
Concentrating on Flow of Material & Information 
 Cross-Functional Collaboration (Engineering, 
Operations, Facilities, Planning, Finance….) 
 Try-storming using Rapid Prototyping & Testing 
 Numerous Alternatives are Developed for Each 
Process Step and Overall System. 
 Team is encouraged to Fail Quick & Often 
Through Continuous PDCA for Rapid Learning 
 Great way to begin the Journey of Operational 
Excellence
WHEN TO USE 3P 
 New Product or a New Business Line 
 Design Changes in an Existing Product 
 Changes In Demand: Increase or Decrease 
 New Technology or Equipment 
 Relocation of Process (Internally or Externally) 
 Current Process Just Needs a Complete Overhaul 
Should be performed concurrently with the 
Product Design Process
3P 
Phases 
5. On-Going 
Continuous 
Improvement 
1. Info Gathering 
(Pre-Event) 
2. Creative 
3. Capture 
4.Implementation 
(Post Event)
PHASE 1  Customer Requirements 
INFORMATION 
GATHERING 
Pre-Event 
 Projected Volumes & Ramp Up 
Schedule 
 Variations of Product/Part #’s 
 Product Drawings & Details 
 Samples: Raw, Components & 
Finished Product 
 Environmental, Health, & 
Safety Considerations 
 Initial Process Map 
 Information on Any Pre- 
Selected Equipment or Shared 
Resources 
 _________________________
PHASE 2 
CREATIVE 
PHASE 
3-5 Day Event 
 “Designing a Lean Process” 
Training (Can be provided before the event) 
 Development of Selection 
Criteria 
 Teams Divided into Small 
Groups 
 Min. of 7 Alternatives Designed 
thru Try-Storming for Each Step 
 Identify Error Proofing 
Solutions: “Build Quality In” 
 Ideas Developed and Tested 
Quickly (Fail Quick and Learn 
Rapidly) 
 Create a Full Scale Mock-Up of 
Overall System
Try-Storming 
Develop Prototypes of Workstations, Equipment, fixtures, Conveyance, 
etc…Quickly so they can be tested. 
They do not have to be exact – Just good enough so you can quickly see 
the concept. (Remember to identify any Mistake-Proofing 
Opportunities/Solutions.) 
Teams explore thru hands-on creativity. Prototype Mock-Ups can be 
Small Scaled or Large Actual-Size. Sketches can also be made on Large 
Post Cards or Flip Chart Paper. 
Potential Materials 
 PVC Piping 
 3D Paper models 
 Cardboard 
 Building Blocks 
 Wood 
 Popsicle Sticks 
 Items From Your Garage 
 Flip Chart Paper 
 Different Colored Paper 
 Plenty of Packing tape or duct tape
PHASE 3 Document the New Process 
CAPTURE 
PHASE 
3-5 DAY Event 
 New Process Flow/ VSM 
 Takt-Time/Cycle Time 
 Process Capacity 
 Standard Work Sheets 
 Pictures and Video 
 Layout 
 Implementation Plan (Present results 
of event & plan with all team members that were unable 
to attend Event) 
 Follow-Up Meeting Schedule
PHASE 4 
IMPLEMENTATION 
PHASE 
Post Event 
 Turn Concept into reality 
 Team Meetings Held 
Weekly or Bi-weekly to 
Review Status and 
Communicate Challenges 
or Modifications
PHASE 5 A 3P Event is a great process to 
CONTINUOUS 
IMPROVEMENT 
Post Event 
begin your journey for 
“Operational Excellence” 
 Team Collaboration 
 Empowerment 
 Waste Id. & Elimination 
 Problem Solving 
 Challenge Status Quo 
 Fail Quick and Learn Rapidly
WHAT ARE THE 
BENEFITS OF 3P? 
 Launch Time Quicker, Reduced Cost, Built in Quality 
& Higher ROI 
 Customer Focused Process 
 Gives Team a Deeper Hands-On Understanding 
Lean Methodology and Operational Excellence 
 Cross-Functional Collaboration 
 Teaches Team about Rapid Learning through 
Continuous PDCA 
 Gives a Connection & Deep Understanding of the 
New Manufacturing Process for All Team Members
OpEx Creative is a lean process design company. We utilize Lean & Six Sigma 
to help organizations of all sizes and industries to develop, transform, and 
bring to market new business lines & improve performance of existing lines. 
 We partner with start-ups to design processes that support new product 
opportunities. 
 We provide public & in-house workshops for lean office & services , 3P 
for services and manufacturing & team problem solving skills. 
 We help organizations to build the capabilities required to sustain 
growth. 
To schedule a 3P event, training, or just give us a call with any questions. 
Visit us at: opexcreative.com 
Free 30 minute Initial Consultation 
©2014 OpEx Creative 
Most Photos from www.pexels.com

Weitere ähnliche Inhalte

Was ist angesagt?

Lean Six Sigma Green Belt roadmap poster
Lean Six Sigma Green Belt roadmap posterLean Six Sigma Green Belt roadmap poster
Lean Six Sigma Green Belt roadmap poster
Francisco Pulgar-Vidal, MBA, Lean Six Sigma MBB
 

Was ist angesagt? (20)

Value stream mapping study with example
Value stream mapping study with exampleValue stream mapping study with example
Value stream mapping study with example
 
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
 
Lean Concepts "8 Forms of Waste Cause & Effect : How to Eliminate / Reduce Wa...
Lean Concepts "8 Forms of Waste Cause & Effect : How to Eliminate / Reduce Wa...Lean Concepts "8 Forms of Waste Cause & Effect : How to Eliminate / Reduce Wa...
Lean Concepts "8 Forms of Waste Cause & Effect : How to Eliminate / Reduce Wa...
 
13. value stream mapping
13. value stream mapping13. value stream mapping
13. value stream mapping
 
Dmaic
DmaicDmaic
Dmaic
 
Lean Six Sigma Green Belt roadmap poster
Lean Six Sigma Green Belt roadmap posterLean Six Sigma Green Belt roadmap poster
Lean Six Sigma Green Belt roadmap poster
 
Lean Transformation ~ A Journey
Lean Transformation ~ A JourneyLean Transformation ~ A Journey
Lean Transformation ~ A Journey
 
Bill Stankeiwicz Copy Scope 2010 Pentair Company
Bill Stankeiwicz Copy Scope 2010 Pentair CompanyBill Stankeiwicz Copy Scope 2010 Pentair Company
Bill Stankeiwicz Copy Scope 2010 Pentair Company
 
Lean Paper Airplane Folding Game
Lean Paper Airplane Folding GameLean Paper Airplane Folding Game
Lean Paper Airplane Folding Game
 
Six Sigma Yellow Belt Training
Six Sigma Yellow Belt TrainingSix Sigma Yellow Belt Training
Six Sigma Yellow Belt Training
 
Kaizen – Forms & Checklists
Kaizen – Forms & ChecklistsKaizen – Forms & Checklists
Kaizen – Forms & Checklists
 
3 MU
3 MU3 MU
3 MU
 
Value Stream Mapping
Value Stream MappingValue Stream Mapping
Value Stream Mapping
 
Lean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleLean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation Sample
 
Spaghetti Diagrams
Spaghetti DiagramsSpaghetti Diagrams
Spaghetti Diagrams
 
Lean Six Sigma: DMAIC In-Depth
Lean Six Sigma: DMAIC In-DepthLean Six Sigma: DMAIC In-Depth
Lean Six Sigma: DMAIC In-Depth
 
Lean Kanban Systems Training Module
Lean Kanban Systems Training ModuleLean Kanban Systems Training Module
Lean Kanban Systems Training Module
 
How to implement lean - Executive overview
How to implement lean - Executive overviewHow to implement lean - Executive overview
How to implement lean - Executive overview
 
Core Lean Tools
Core Lean ToolsCore Lean Tools
Core Lean Tools
 
Value Stream Mapping: From Tool to Management Practice
Value Stream Mapping: From Tool to Management PracticeValue Stream Mapping: From Tool to Management Practice
Value Stream Mapping: From Tool to Management Practice
 

Ähnlich wie 3P Production Preparation Process Overview

CAI - Agile Scrum Development Presentation
CAI - Agile Scrum Development PresentationCAI - Agile Scrum Development Presentation
CAI - Agile Scrum Development Presentation
deyoepw
 
Atmosphere 2016 - Berk Dulger - DevOps Tactical Adoption Theory
Atmosphere 2016 - Berk Dulger  - DevOps Tactical Adoption TheoryAtmosphere 2016 - Berk Dulger  - DevOps Tactical Adoption Theory
Atmosphere 2016 - Berk Dulger - DevOps Tactical Adoption Theory
PROIDEA
 

Ähnlich wie 3P Production Preparation Process Overview (20)

2015 06-24 innovation in the large enterprise final-v2
2015 06-24 innovation in the large enterprise final-v22015 06-24 innovation in the large enterprise final-v2
2015 06-24 innovation in the large enterprise final-v2
 
Agile Pmi 102108 Final
Agile Pmi 102108 FinalAgile Pmi 102108 Final
Agile Pmi 102108 Final
 
ADDO19 - Automate or not from the beginning that is the question
ADDO19 - Automate or not from the beginning that is the questionADDO19 - Automate or not from the beginning that is the question
ADDO19 - Automate or not from the beginning that is the question
 
2012 lean toolbox_4 asq
2012 lean toolbox_4 asq2012 lean toolbox_4 asq
2012 lean toolbox_4 asq
 
Design sprint
Design sprintDesign sprint
Design sprint
 
Best Practices When Moving To Agile Project Management
Best Practices When Moving To Agile Project ManagementBest Practices When Moving To Agile Project Management
Best Practices When Moving To Agile Project Management
 
Agile transformation approach by first consulting
Agile transformation approach by first consultingAgile transformation approach by first consulting
Agile transformation approach by first consulting
 
Agile transformation approach by First Consulting
Agile transformation approach by First ConsultingAgile transformation approach by First Consulting
Agile transformation approach by First Consulting
 
CAI - Agile Scrum Development Presentation
CAI - Agile Scrum Development PresentationCAI - Agile Scrum Development Presentation
CAI - Agile Scrum Development Presentation
 
Webinar - Design Thinking for Platform Engineering
Webinar - Design Thinking for Platform EngineeringWebinar - Design Thinking for Platform Engineering
Webinar - Design Thinking for Platform Engineering
 
Process Evolution and Product Maturity
Process Evolution and Product MaturityProcess Evolution and Product Maturity
Process Evolution and Product Maturity
 
Lean Principles for Agile Teams
Lean Principles for Agile TeamsLean Principles for Agile Teams
Lean Principles for Agile Teams
 
Conducting Kaizen Events
Conducting Kaizen EventsConducting Kaizen Events
Conducting Kaizen Events
 
Atmosphere 2016 - Berk Dulger - DevOps Tactical Adoption Theory
Atmosphere 2016 - Berk Dulger  - DevOps Tactical Adoption TheoryAtmosphere 2016 - Berk Dulger  - DevOps Tactical Adoption Theory
Atmosphere 2016 - Berk Dulger - DevOps Tactical Adoption Theory
 
Lean UX
Lean UXLean UX
Lean UX
 
Alternate Hourly Lean Introduction
Alternate Hourly Lean IntroductionAlternate Hourly Lean Introduction
Alternate Hourly Lean Introduction
 
Waterfall vs agile approach scrum framework and best practices in software d...
Waterfall vs agile approach  scrum framework and best practices in software d...Waterfall vs agile approach  scrum framework and best practices in software d...
Waterfall vs agile approach scrum framework and best practices in software d...
 
Top tools process_excellence
Top tools process_excellenceTop tools process_excellence
Top tools process_excellence
 
Tp88 pub45
Tp88 pub45Tp88 pub45
Tp88 pub45
 
DevOps: Why Should We Care?
DevOps: Why Should We Care?DevOps: Why Should We Care?
DevOps: Why Should We Care?
 

Kürzlich hochgeladen

Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 

Kürzlich hochgeladen (20)

Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 

3P Production Preparation Process Overview

  • 1. 3P RAPIDLY DESIGN A LEAN MANUFACTURING PROCESS (Overview)
  • 2. It All Starts With a Great Idea for a New Product
  • 3. However After Launch…… • Capital Investments & Operating Costs - Over Budget • Poor Customer Service & Long Lead-Times • Batch Processing - No Flow • Rework Loops Everywhere • Environmental, Ergonomic & Safety Issues • “Thrown Over Wall”: All key Members Upset They Were Not Involved in Process Design
  • 4. PRO-ACTIVE SOLUTION Production Preparation Process
  • 5. WHAT IS 3P?  Intense 3-5 Day Event  A Focus on Developing a Waste-Free System Concentrating on Flow of Material & Information  Cross-Functional Collaboration (Engineering, Operations, Facilities, Planning, Finance….)  Try-storming using Rapid Prototyping & Testing  Numerous Alternatives are Developed for Each Process Step and Overall System.  Team is encouraged to Fail Quick & Often Through Continuous PDCA for Rapid Learning  Great way to begin the Journey of Operational Excellence
  • 6. WHEN TO USE 3P  New Product or a New Business Line  Design Changes in an Existing Product  Changes In Demand: Increase or Decrease  New Technology or Equipment  Relocation of Process (Internally or Externally)  Current Process Just Needs a Complete Overhaul Should be performed concurrently with the Product Design Process
  • 7. 3P Phases 5. On-Going Continuous Improvement 1. Info Gathering (Pre-Event) 2. Creative 3. Capture 4.Implementation (Post Event)
  • 8. PHASE 1  Customer Requirements INFORMATION GATHERING Pre-Event  Projected Volumes & Ramp Up Schedule  Variations of Product/Part #’s  Product Drawings & Details  Samples: Raw, Components & Finished Product  Environmental, Health, & Safety Considerations  Initial Process Map  Information on Any Pre- Selected Equipment or Shared Resources  _________________________
  • 9. PHASE 2 CREATIVE PHASE 3-5 Day Event  “Designing a Lean Process” Training (Can be provided before the event)  Development of Selection Criteria  Teams Divided into Small Groups  Min. of 7 Alternatives Designed thru Try-Storming for Each Step  Identify Error Proofing Solutions: “Build Quality In”  Ideas Developed and Tested Quickly (Fail Quick and Learn Rapidly)  Create a Full Scale Mock-Up of Overall System
  • 10. Try-Storming Develop Prototypes of Workstations, Equipment, fixtures, Conveyance, etc…Quickly so they can be tested. They do not have to be exact – Just good enough so you can quickly see the concept. (Remember to identify any Mistake-Proofing Opportunities/Solutions.) Teams explore thru hands-on creativity. Prototype Mock-Ups can be Small Scaled or Large Actual-Size. Sketches can also be made on Large Post Cards or Flip Chart Paper. Potential Materials  PVC Piping  3D Paper models  Cardboard  Building Blocks  Wood  Popsicle Sticks  Items From Your Garage  Flip Chart Paper  Different Colored Paper  Plenty of Packing tape or duct tape
  • 11. PHASE 3 Document the New Process CAPTURE PHASE 3-5 DAY Event  New Process Flow/ VSM  Takt-Time/Cycle Time  Process Capacity  Standard Work Sheets  Pictures and Video  Layout  Implementation Plan (Present results of event & plan with all team members that were unable to attend Event)  Follow-Up Meeting Schedule
  • 12. PHASE 4 IMPLEMENTATION PHASE Post Event  Turn Concept into reality  Team Meetings Held Weekly or Bi-weekly to Review Status and Communicate Challenges or Modifications
  • 13. PHASE 5 A 3P Event is a great process to CONTINUOUS IMPROVEMENT Post Event begin your journey for “Operational Excellence”  Team Collaboration  Empowerment  Waste Id. & Elimination  Problem Solving  Challenge Status Quo  Fail Quick and Learn Rapidly
  • 14. WHAT ARE THE BENEFITS OF 3P?  Launch Time Quicker, Reduced Cost, Built in Quality & Higher ROI  Customer Focused Process  Gives Team a Deeper Hands-On Understanding Lean Methodology and Operational Excellence  Cross-Functional Collaboration  Teaches Team about Rapid Learning through Continuous PDCA  Gives a Connection & Deep Understanding of the New Manufacturing Process for All Team Members
  • 15. OpEx Creative is a lean process design company. We utilize Lean & Six Sigma to help organizations of all sizes and industries to develop, transform, and bring to market new business lines & improve performance of existing lines.  We partner with start-ups to design processes that support new product opportunities.  We provide public & in-house workshops for lean office & services , 3P for services and manufacturing & team problem solving skills.  We help organizations to build the capabilities required to sustain growth. To schedule a 3P event, training, or just give us a call with any questions. Visit us at: opexcreative.com Free 30 minute Initial Consultation ©2014 OpEx Creative Most Photos from www.pexels.com