AUTOMATION OF ENROLLMENT PROCESS
A PROPOSAL TO: XYZ TRAINING INSTITUTION
May 29, 2011
Deborah Obasogie
PM592ON – May 2011 Sec C: Project Cost and Schedule Control
Assignment: Course Project, Part 1 (CP-1)
Table of Contents
Automation of Enrollment Process..............................................................................................................1
Executive Summary......................................................................................................................................1
Project Description.......................................................................................................................................3
Project High Level Requirements.................................................................................................................5
Functional Requirements.........................................................................................................................5
Nonfunctional Requirements...................................................................................................................5
Technical Requirements...........................................................................................................................5
Project Deliverables .................................................................................................................................6
Work Breakdown Structure .........................................................................................................................6
Cost Estimates ..............................................................................................................................................6
Advanced Cost Estimating............................................................................................................................7
Cost Assumptions.........................................................................................................................................8
Financial Analysis .........................................................................................................................................9
Schedule .......................................................................................................................................................9
Appendix A .................................................................................................................................................10
Appendix B..................................................................................................................................................14
Appendix C..................................................................................................................................................15
Appendix D .................................................................................................................................................16
Appendix E..................................................................................................................................................17
Appendix F..................................................................................................................................................18
Appendix G .................................................................................................................................................20
Appendix H .................................................................................................................................................21
Appendix I...................................................................................................................................................22
Appendix J ..................................................................................................................................................23
1/28
Automation of Enrollment Process
Executive Summary
XYZ Training Institute is a new company that provides training in subject areas including
Project Management, Microsoft Products, Java and C++. XYZ is considered a career college
and offers programs through flexible and innovative learning methods that lead to a certificate.
Traditional classroom instruction and online instruction are available.
Computer training classes are taught in a 3-floor story building in Townville, AB. XYZ
has 200 enrolled students and a 20-person staff consisting of: President, Greg Defeo; Director,
JoAnne Kline; Registrar, Jim Logan; Coordinator, Barry Rigler; Scheduler, Ann Archibald; an
Administrator, Advisor, Account Executive, Instructors (10 staff members), Marketing (1 staff
member) and 2 support staff (facilities and maintenance). Staff members will assume the roles
of Project Sponsor, Customer, and Subject Matter Experts on the project team. XYZ is
accredited by the Middle States Commission on Higher Education (MSCHE).
XYZ’s mission is to empower its students to succeed in today's dynamic world by
integrating IT training and professional skills into a sound career-focused education that provides
the life skills necessary for students to realize their full potential and career goals.
Through XYZ, nontraditional students prepare for direct entry into the workforce and
take advantage of shorter, more flexible evening schedules. XYZ also helps those currently in the
workforce obtain additional education for career advancement.
XYZ has a conglomeration of different systems and procedures (as well as hardware and
software) designed specifically for departmental needs. Employee records (including payroll,
medical and other benefits) are held by Human Resources. Financial data and processing
(including payroll computations, employee compensation, invoicing and billing for products and
1/28
2/28
services) are held by the Finance Department. Student data, from the enrollment process
(identify, retain, anticipate the needs and wants of students) are held by the Registrar Office.
Currently the Registrar Office uses MS Excel to track student enrollments. To stay
competitive in this industry, the department has identified a need for an automated system that
will streamline tracking of their student data and also be accurate and secure.
XYZ is looking to increase the efficiency and effectiveness of student data by 80% within
one year and to expand customer base by 60% by year end. In addition to a positive NPV, the
project would result in intangible benefits such as increase customer satisfaction and reliability
of student data.
The project Budget is $460,000. All funding is provided by XYZ. Solutions Consultants
will assist XYZ with this six-month implementation.
2/28
3/28
Project Description
The objective of the project is to increase the efficiency and effectiveness of student data
by 80 percent in one year and expand their customer base by 60 percent by year end. XYZ would
like to:
1. Process tracking data such as student enrollment, historic information, and student
performance.
2. Have the ability to manage courses, students, and class information.
3. Be able to perform analysis on student data.
XYZ is a new company that provides training various subject areas. They have 200
enrolled students and a staff of twenty. The Registrar Office current system is in an Excel
spreadsheet. There is no data backup leaving staff and students with no historical data tracking.
The system is unable to effectively share, manage, store, or report on student data. There are no
means to manage the data, thus data is prone to being lost and there is a high probability of data
entry errors. The current system lacks any kind of security which leaves the entire system and
users at risk.
XYZ would like to automate the enrollment process in order to stay competitive in their
industry. In order to do this they will need to upgrade the flat file system that is currently in use
to an automated system that will give them the ability to systematically perform specific and
daily functions and streamline tracking of student data.
The project will increase business for XYZ. It will do this by making it easy to provide
information to potential students about the classes being offered. This will also be accomplished
by allowing XYZ to track the demographics for students enrolled in offered courses. This will
3/28
4/28
allow marketing to be targeted more effectively by increasing the chances that potential students
will choose to enroll in courses offered.
The project will increase customer satisfaction. The primary way the project will affect
current customers is that they will enjoy a streamlined enrollment process as they take their
courses. Another source of customer satisfaction is that XYZ will be able to track courses that
are popular and those that aren’t. This will allow them to make sure that popular courses are
offered regularly and the unpopular ones are offered rarely or even completely removed from the
course offerings. The increased customer satisfaction will come from knowing that XYZ offers
courses that customers want.
The project will increase the reliability of student data. Currently the Registrar Office is
using a spreadsheet to track customers. This presents a huge risk of data loss through inadvertent
overwriting of cells in the file, accidental deletion of the file, or even a computer crash
corrupting the file. Creating a relational database system (RDBMS) will increase the data
reliability exponentially. The database can easily be backed up. In the event of a small data
issue for example, a repair could be as simple as restoring the portion of corrupted data from the
backup instead of having to restore everything such as would be the case with a spreadsheet.
The goals of the project are:
1. To make it easy to enroll students, track enrollments, and run reports to strategize the
offerings in the future.
2. To make it easy to provide information to the potential students.
3. To run reports to assist in marketing to the right audience.
Critical success factors:
1. Develop an automated system that will provide:
4/28
5/28
a. A process to enroll students and track their enrollments.
b. A process to run reports that identify “what kind of students take what classes”.
c. A process to “provide information to the potential students”.
d. A mechanism that stores and manages the student data (course, student and class
information). For specific field details of student data see Appendix A.
The new system will solve the current system problems by providing sharing and storing
of student data, reporting on student data, and management of student data (course, student, and
class information). Additionally it will provide data security, data backup and minimize data lost
and data entry errors. Making this a centralized web application will make updating and
retrieving student data easier and will increase the integrity of the data.
The project budget will be $460,000. All funding will be provided by the customer, XYZ
Training Institute.
Project High Level Requirements
Functional Requirements
For functional requirements see Appendix B.
Nonfunctional Requirements
For nonfunctional requirements see Appendix C.
Technical Requirements
For technical requirements see Appendix D. With respect to the identified technical
requirements, XYZ has proposed to use the Kuali Foundation’s open source software suite as a
basis for developing the web application. To support the use of this software, the following
software products are required as per documentation at the Kuali web site.
5/28
6/28
 Microsoft Server 2010 or Linux
 Postgres SQL 8.4
 Postgres Plus add-ons
 EnterpriseDB
 ApachePHP
 PHP BB
 PHP pg Admin
Project Deliverables
For project deliverables see Appendix E.
Work Breakdown Structure
The Work breakdown Structure (WBS) is the basic tool used in project planning. It
breaks the project down into the main components of work required to complete the project. Our
project is broken down into four major components. The Project Charter, Project Plan and the
analysis of the requirements and environment (infrastructure, hardware, software, user profiles)
are includes in the Analysis component. The largest component, Design and Build includes all
tasks meeting XYZ’s critical success factors (process to enroll students and track their
enrollments, process to run reports that identify “what kind of students take what classes”,
process to “provide information to potential students”, and mechanism that stores and manages
the student data). The third component, Test and Train includes testing and training tasks.
Deploy is responsible for installing the solution into production. For the WBS see Appendix F.
Cost Estimates
6/28
7/28
The use of historical data and expert advice is the best approach for this project.
Historical data will provide the project team with updated knowledge of the prices of parts,
services, and the development of the project schedule. Expert advice (Kuali Foundation’s staff)
will be utilized in conjunction with the development of the project schedule and with informing
XYZ during scope change requests. These techniques have been chosen because it allows the
project team to remain focus on the project itself. Also, the experts will serve as an additional
support system during meetings and throughout the project process.
The total estimated cost for the project is $458,792.00 and it can be completed anywhere
from 5 to 6 months. The code is provided by the Kuali Foundation because they have a similar
module in their software suite that accommodates most of XYZ’s functionality and screen
navigation. They will help us customize it to meet XYZ’s requirements.
Labor, materials and overhead costs are included in our $460k budget. Upfront costs
(licenses, customization, training, and implementation) will cost approximately $17,200.
Materials costs (servers, software, storage devices, etc.) required will cost approximately
$102,400. Labor will cost about $340,000. The system engineer will cost $55/hour, the database
administrator will cost $50/hour, developers (2) costs will cost $70/hour and $60/hour, the
software tester will cost $40/hour, the help desk/tech support will cost $30/hour, the trainer will
cost $35/hour, and the project manager costs will cost $100/hour; all are variable cost. The
performance will be done Monday through Friday. For costs for each task and total estimated
costs see Appendix G.
Advanced Cost Estimating
To get the cost estimates for the project, the Project Evaluation Review Technique
(PERT) is used to derive task duration estimations. Using optimistic, most likely, and
7/28
8/28
pessimistic estimates for each task, the expected duration is calculated which is then used to
calculate the estimated cost per task. For PERT analysis see Appendix H.
Cost Assumptions
Three prominent project assumptions include:
1. There is a business need to develop a student management system.
2. All courses are owned by XYZ Training Institute.
3. Research supports automation would be beneficial to XYZ Training Institute.
Although the project is utilizing both historical data and expert advice, there is no prior
historical data specific to the exact requirements identified with this effort, however, our Project
Managers are very knowledgeable and experience in software development and has generalized
costs across the board.
Time, hardware, and cost are variable, as changes are inevitable. Resource management is
more difficult in a short duration project because of the time constraint. As deliverables must be
delivered within the short period of time, it may cause the allocation of extra resources or more
over time. In addition, risks and constraints are not represented in the estimated costs, but will
identify and provide mitigation plans in the Project Charter. All of which could have an effect on
the triple constraint – score, time and cost (and quality). Arising issues impacting the project will
be presented to XYZ to review along with a revised plan for their decision to cancel or move
ahead.
Although XYZ found substantial costs reduction by adopting open source, risk includes
the absence of a formal open source policy in place and additional costs in man hours to support
system. It is assumed that XYZ has their own IT staff that will keep software updated, ensure
8/28
9/28
security patches and virus updates are done and can do maintenance updates and checks on
hardware. The project ends after deployment and cost estimates are only to that point. It is
recommended that XYZ move forward with having a formal Open Source Solution (OSS) policy
in place.
Financial Analysis
Net Present Value (NPV) is used to determine how profitable a proposed project will be
to XYZ. The results is a present value higher than the investment, a positive NPV investment
that would add value to XYZ. Cash flows represent forecasted revenues minus operating
expenses for the next five years. In addition to a positive NPV, the project would result in
intangible benefits such as increase customer satisfaction and reliability of student data.
Calculations include the initial $460,000 cost as one of the values because the payment occurs at
the end of the first period. For NPV calculations see Appendix I.
Schedule
This section depicts the WBS and the software development phases consisting of
analysis, design and build, test and train, and deploy. The schedule shows tasks, task
relationships (dependencies), task durations and resources assigned to each task. Also included is
a Gantt chart schedule showing the time line for the project. The project has 50 tasks, 147 days
durations, 6,014.4 work hours (many concurrent hours), 38 dependencies and resources (8
external (Resource Group: Solutions Consultants and Kuali) and 12 internal (resource Group:
SME)). For the schedule with Gantt chart, tasks, task relationships, task duration, and task
resources see Appendix J.
9/28
10/28
Appendix A
Data to be Held and Managed
Student Information:
Name First
Last
Address(es) Street
City
State
Zip
Social security number
Marital Status
Birthday
Phone(s)
Emails(s)
Emergency contact(s) Name
Phone
Race
Religion
Gender
Citizenship
Education(s) Degree
Major
Completion year
Institution Name
Address Street
City
State
Zip
Occupation(s)
Employer(s) Name
Address Street
City
State
Zip
Vehicle(s) Year
Make
Model
Plate state
Plate number
Certificate program
Financial aid lender
Work study employer
Student Enrollment Information:
10/28
11/28
Enrollment date(s)
Course Offerings (classes) Session Month
Year
Session Period Start date
End date
Day
Time Start time
End time
Instructor
Room
Grade(s)
Course Information:
Number
Title
Description
Prerequisite(s)
Credit hours
Instructor Information:
Name First
Last
Address(es) Street
City
State
Zip
Social security number
Marital Status
Birthday
Phone(s)
Emails(s)
Emergency contact(s) Name
Phone
Race
Religion
Gender
Citizenship
Education(s) Degree
Major
Completion year
Institution Name
Address Street
City
State
Zip
Occupation(s)
111/28
12/28
Employer(s) Name
Address Street
City
State
Zip
Facility Information:
Location Address
Street
City
State
Zip
Room number
Room capacity
Marketing Information:
Student Information:
Name First
Last
Address(es) Street
City
State
Zip
Social security number
Marital Status
Birthday
Phone(s)
Emails(s)
Emergency contact(s) Name
Phone
Race
Religion
Gender
Citizenship
Education(s) Degree
Major
Completion year
Institution Name
Address Street
City
State
Zip
Occupation(s)
Employer(s) Name
Address Street
City
12/28
13/28
State
Zip
Vehicle(s) Year
Make
Model
Plate state
Plate number
Certificate program
Financial aid lender
Work study employer
Student Enrollment Information:
Enrollment date(s)
Course Offerings (classes) Session Month
Year
Session Period Start date
End date
Day
Time Start time
End time
Instructor
Room
Grade(s)
Course Information:
Number
Title
Description
Prerequisite(s)
Credit hours
13/28
14/28
Appendix B
Functional Requirements
In Scope Out of scope
1. Tracking, historic information and analysis of student data:
a. System should enroll students and track student
enrollments.
b. System should keep and access last two years and going
forward history. History information consists of the
student, enrollment and course information listed above.
c. System should supply Marketing with the student
information for their purposes.
2. System should provide the following formatted reports:
a. Course offerings (Course Offerings Report).
b. List of students for each class (Enrollment Report).
c. List of all the classes that a student has taken and is
registered currently (Grades and Student History Reports).
 Student payments.
 Company’s vendors.
 3 other student
performance reports
(to be completed in a
separate project.)
14/28
15/28
Appendix C
Nonfunctional Requirements
In Scope Out of scope
1. Performance: System must accommodate 2500 concurrent
users.
2. Security: Every user of system must have personal login to see
and use system.
15/28
16/28
Appendix D
Technical Requirements
Technical Requirement ID Name Description
TR001 Uptime The system must maintain a 99.999% uptime rate.
TR002 Concurrent Logon The system must have the capability of allowing
multiple simultaneous logons
TR003 Auditing The system must log usage for security auditing
purposes
TR004 Open Source software Whenever possible, open source software should be
utilized to reduce licensing purchase and renewal
costs
TR005 Database software Database software should be chosen that is open
source if possible. The software must support load
balancing between multiple database servers
TR006 Web Application Server
software
Open source application server software for the web
server should be chosen where possible. This may
be impacted by the choice of programming language
for the web interface and the middleware layer of
the application
TR007 Storage A data storage solution must be chosen that is fault
tolerant
TR008 Backup A backup solution must be chosen that will allow
nightly backups of the database. The solution must
provide a portable format for offsite storage. The
source code and compiled packages for the
developed solution must be backed up and stored
offsite at initial code freeze and whenever an
enhancement is coded to the system
TR009 Server Hardware Server hardware must meet minimum requirements
for the chosen software. Ideally the hardware will
meet “recommended” requirements as per the
software documentation and allow for future
expansion.
TR010 User Hardware User machines should be capable of running current
versions of major web browsers that support the
Google Web Toolkit version 1.5
TR011 Network Hardware XYZ’s networking infrastructure must be able to
handle the increased traffic from faculty and
students accessing the web application
TR012 Network Security Applicable portions of the application will be
exposed to the Internet to allow potential students to
access content. Firewalls and other network
security features must be implemented to support
this and prevent security failures
16/28
17/28
Appendix E
Project Deliverables
Event or Deliverable Target Date Responsibility
Project charter completed June 15, 2011 Project Manager
Project charter approved June 17, 2011 Project Sponsor, Customer
Project plan completed June 22, 2011 Project Manager
Project plan approved June 24, 2011 Project Sponsor, Customer, Subject Matter
Experts
Project team assembled June 20, 2011 Project Manager
Project execution initiated June 22, 2011 Project Manager
RDBMS Data Model design July 30, 2011 Project Manager, Development team
Web GUI Interface July 30, 2011 Project Manager, Development team
Process to enroll students and
track their enrollments
Oct 12, 2011 Project Manager, Development team
Report Process that identifies
“what kind of students take
what classes”
Dec 15, 2011 Project Manager, Development tea.
Process to “provide information
to the potential students”
Dec 15, 2011 Project Manager, Development team
Mechanism to store and
manage data
Oct 15, 2011 Project Manager, Development team
Training on new system Dec 13, 2011 Project Sponsor, Customer, Subject Matter
Experts, Trainer
Project execution completed Dec 27, 2011 Project Manager
Project closed out Dec 30, 2011 Project Manager
17/28
18/28
Appendix F
WBS
WBS Task Name
1 Automate Enrollment Process
1.1 Analysis
1.1.1 Complete charter and plan
1.1.1.1 Complete and approve Project Charter
1.1.1.2 Complete and approve Project Plan
1.1.2 Analysis of requirements and environment
1.1.2.1 Analyze and set up infrastructure
1.1.2.2 Analyze and set up hardware
1.1.2.3 Analyze and set up Kuali Foundation software
1.1.2.4 Analyze and set up profile
1.2 Design and Build
1.2.1 Process to enroll students and track their enrollments
1.2.1.1 RDBMS Data Model design
1.2.1.2 Design and Build web GUI interface
1.2.1.3 Student enrollment process
1.2.2 Process to run reports that identify “what kind of students take what classes”
1.2.2.1 Design and build defined reports
1.2.2.2 Design and build analysis data
1.2.2.3 Output data for viewing
1.2.3 Process to “provide information to potential students”
1.2.3.1 Build course catalog view
1.2.3.2 Build course offerings view
1.2.3.3 Build enrollment list view
1.2.3.4 Build defined reports view
1.2.3.5 Build student history view
1.2.3.6 Build analysis data view
1.2.3.7 Build grades view
1.2.4 Mechanism that stores and manages the student data
1.2.4.1 Store and manage student information
1.2.4.2 Store and manage course information
1.2.4.3 Create course catalog
1.2.4.4 Create course offerings
1.2.4.5 Create enrollment list
1.2.4.6 Store and manage instructor information
1.2.4.7 Select class to teach
1.2.4.8 Submit student grades
1.2.4.9 Store student history
1.2.4.9.1 Store student data
1.2.4.9.2 Restore student data
1.2.4.10 Secure data with user profiles
1.3 Test and train
18/28
19/28
1.3.1 Test process to enroll students and track their enrollments
1.3.2 Test process to run reports that identify “what kind of students take what classes”
1.3.3 Test process to “provide information to potential students”
1.3.4 Test mechanism that stores and manages the student data
1.3.5 Test nonfunctional requirements
1.3.6 Test technical requirements
1.3.7 Train on new system
1.4 Deploy
1.4.1 Implement solution to production
19/28
20/28
Appendix G
Cost Estimates
Task Name Cost
Complete and approve Project Charter $4,133.33
Complete and approve Project Plan $4,000.00
Analyze and set up Infrastructure $43,620.00
Analyze and set up hardware $42,280.00
Analyze and set up Kuali Foundation software $116,300.00
Analyze and set up profile $2,200.00
RDBMS Data Model design $19,253.33
Design and Build web GUI interface $17,733.33
Student enrollment process $65,232.00
Design and build defined reports $10,800.00
Design and build analysis data $20,000.00
Output data for viewing $1,320.00
Build course catalog view $3,600.00
Build course offerings view $3,200.00
Build enrollment list view $3,600.00
Build defined reports view $3,200.00
Build student history view $3,600.00
Build analysis data view $3,200.00
Build grades view $3,600.00
Store and manage student information $4,066.67
Store and manage course information $4,000.00
Create course catalog $6,400.00
Create course offerings $7,200.00
Create enrollment list $6,400.00
Store and manage instructor information $4,000.00
Select class to teach $3,720.00
Submit student grades $3,306.67
Store student data $4,000.00
Restore student data $4,000.00
Secure data with user profiles $4,200.00
Test process to enroll students and track their enrollments $3,800.00
Test process to run reports that identify “what kind of students take what classes” $3,800.00
Test process to “provide information to potential students” $3,800.00
Test mechanism that stores and manages the student data $3,800.00
Test nonfunctional requirements $5,026.67
Test technical requirements $5,026.67
Training on new system $2,600.00
Implement solution to production $8,773.33
Total Estimated Cost: $458,792.00
20/28
21/28
Appendix H
PERT Analysis
21/28
22/28
Appendix I
NPV
22/28
23/28
Appendix J
Schedule
23/28
24/28
24/28
25/2825/28
26/2826/28

Weitere ähnliche Inhalte

Was ist angesagt?

DepEd Region 7 QAAD’s Report on Regional Monitoring, Evaluation and Plan Adju...
DepEd Region 7 QAAD’s Report on Regional Monitoring, Evaluation and Plan Adju...DepEd Region 7 QAAD’s Report on Regional Monitoring, Evaluation and Plan Adju...
DepEd Region 7 QAAD’s Report on Regional Monitoring, Evaluation and Plan Adju...Dr. Joy Kenneth Sala Biasong
 
Night Shift Differential Pay
Night Shift Differential PayNight Shift Differential Pay
Night Shift Differential PayJDP Consulting
 
Earth Science Table of Specifications .pdf
Earth Science Table of Specifications .pdfEarth Science Table of Specifications .pdf
Earth Science Table of Specifications .pdfMAHAZELTEOLOGO3
 
Example Final Defense Power Point Slide
Example Final Defense Power Point SlideExample Final Defense Power Point Slide
Example Final Defense Power Point SlideDr. Vince Bridges
 
the maternity benefit leave vs the expanded maternity law
the maternity benefit leave vs the expanded maternity lawthe maternity benefit leave vs the expanded maternity law
the maternity benefit leave vs the expanded maternity lawAngelee Mandreza
 
Thesis presentation (proposal)
Thesis presentation (proposal)Thesis presentation (proposal)
Thesis presentation (proposal)Jay Aspero
 
Universal Laws of Physics Aristotle v Galilei
Universal Laws of Physics Aristotle v GalileiUniversal Laws of Physics Aristotle v Galilei
Universal Laws of Physics Aristotle v GalileiJohn Adrian Adiaz
 
INTERNET AND ITS IMPACT ON STUDENT PERFORMANCE
INTERNET AND ITS IMPACT ON STUDENT PERFORMANCEINTERNET AND ITS IMPACT ON STUDENT PERFORMANCE
INTERNET AND ITS IMPACT ON STUDENT PERFORMANCEArshad Ahmed Saeed
 
Solicitation letters
Solicitation lettersSolicitation letters
Solicitation lettersIris Navarro
 
Intervention & innovation method
Intervention & innovation methodIntervention & innovation method
Intervention & innovation methodShiKia Carter
 
ESAT CERTIFICATE.pptx
ESAT CERTIFICATE.pptxESAT CERTIFICATE.pptx
ESAT CERTIFICATE.pptxMONMONMAMON
 
Smea presentation sept. 23
Smea presentation   sept. 23Smea presentation   sept. 23
Smea presentation sept. 23Lindy Pujante
 
Action plan yes o
Action plan yes oAction plan yes o
Action plan yes obojomariano
 
School Monitoring, Evaluation and Adjustment (SMEA): Activity Completion Report
School Monitoring, Evaluation and Adjustment (SMEA): Activity Completion ReportSchool Monitoring, Evaluation and Adjustment (SMEA): Activity Completion Report
School Monitoring, Evaluation and Adjustment (SMEA): Activity Completion ReportDr. Joy Kenneth Sala Biasong
 
Pledge of comitment
Pledge of comitmentPledge of comitment
Pledge of comitmentLive Angga
 
BE-CERTIFICATE.pptx
BE-CERTIFICATE.pptxBE-CERTIFICATE.pptx
BE-CERTIFICATE.pptxKlarisReyes1
 
Accomplishment reports in science
Accomplishment reports in scienceAccomplishment reports in science
Accomplishment reports in scienceReon Zedval
 

Was ist angesagt? (20)

DepEd Region 7 QAAD’s Report on Regional Monitoring, Evaluation and Plan Adju...
DepEd Region 7 QAAD’s Report on Regional Monitoring, Evaluation and Plan Adju...DepEd Region 7 QAAD’s Report on Regional Monitoring, Evaluation and Plan Adju...
DepEd Region 7 QAAD’s Report on Regional Monitoring, Evaluation and Plan Adju...
 
Night Shift Differential Pay
Night Shift Differential PayNight Shift Differential Pay
Night Shift Differential Pay
 
Earth Science Table of Specifications .pdf
Earth Science Table of Specifications .pdfEarth Science Table of Specifications .pdf
Earth Science Table of Specifications .pdf
 
Example Final Defense Power Point Slide
Example Final Defense Power Point SlideExample Final Defense Power Point Slide
Example Final Defense Power Point Slide
 
RPMS Re-orientation Workshop
RPMS Re-orientation WorkshopRPMS Re-orientation Workshop
RPMS Re-orientation Workshop
 
the maternity benefit leave vs the expanded maternity law
the maternity benefit leave vs the expanded maternity lawthe maternity benefit leave vs the expanded maternity law
the maternity benefit leave vs the expanded maternity law
 
Thesis presentation (proposal)
Thesis presentation (proposal)Thesis presentation (proposal)
Thesis presentation (proposal)
 
MATATAG PPT.pptx
MATATAG PPT.pptxMATATAG PPT.pptx
MATATAG PPT.pptx
 
Universal Laws of Physics Aristotle v Galilei
Universal Laws of Physics Aristotle v GalileiUniversal Laws of Physics Aristotle v Galilei
Universal Laws of Physics Aristotle v Galilei
 
INTERNET AND ITS IMPACT ON STUDENT PERFORMANCE
INTERNET AND ITS IMPACT ON STUDENT PERFORMANCEINTERNET AND ITS IMPACT ON STUDENT PERFORMANCE
INTERNET AND ITS IMPACT ON STUDENT PERFORMANCE
 
Solicitation letters
Solicitation lettersSolicitation letters
Solicitation letters
 
Intervention & innovation method
Intervention & innovation methodIntervention & innovation method
Intervention & innovation method
 
ESAT CERTIFICATE.pptx
ESAT CERTIFICATE.pptxESAT CERTIFICATE.pptx
ESAT CERTIFICATE.pptx
 
NSED 2022.docx
NSED 2022.docxNSED 2022.docx
NSED 2022.docx
 
Smea presentation sept. 23
Smea presentation   sept. 23Smea presentation   sept. 23
Smea presentation sept. 23
 
Action plan yes o
Action plan yes oAction plan yes o
Action plan yes o
 
School Monitoring, Evaluation and Adjustment (SMEA): Activity Completion Report
School Monitoring, Evaluation and Adjustment (SMEA): Activity Completion ReportSchool Monitoring, Evaluation and Adjustment (SMEA): Activity Completion Report
School Monitoring, Evaluation and Adjustment (SMEA): Activity Completion Report
 
Pledge of comitment
Pledge of comitmentPledge of comitment
Pledge of comitment
 
BE-CERTIFICATE.pptx
BE-CERTIFICATE.pptxBE-CERTIFICATE.pptx
BE-CERTIFICATE.pptx
 
Accomplishment reports in science
Accomplishment reports in scienceAccomplishment reports in science
Accomplishment reports in science
 

Andere mochten auch

Final Project 3 Document
Final Project 3  DocumentFinal Project 3  Document
Final Project 3 DocumentLinda Calkins
 
Proposal Version 5
Proposal  Version 5Proposal  Version 5
Proposal Version 5Mark Forster
 
[SIP 2015] QA Intern: Test Automation
[SIP 2015] QA Intern: Test Automation[SIP 2015] QA Intern: Test Automation
[SIP 2015] QA Intern: Test AutomationSilicon Straits
 
ENASE 2013 - SEM - (Francia) From Functional Test Scripts to Performance Test...
ENASE 2013 - SEM - (Francia) From Functional Test Scripts to Performance Test...ENASE 2013 - SEM - (Francia) From Functional Test Scripts to Performance Test...
ENASE 2013 - SEM - (Francia) From Functional Test Scripts to Performance Test...Federico Toledo
 
Online Student Registration System
Online Student Registration SystemOnline Student Registration System
Online Student Registration SystemSanjana Agarwal
 
Student result mamagement
Student result mamagementStudent result mamagement
Student result mamagementMickey
 
Course registration system dfd
Course registration system dfdCourse registration system dfd
Course registration system dfdUtsav mistry
 
Chapter 2-Realated literature and Studies
Chapter 2-Realated literature and StudiesChapter 2-Realated literature and Studies
Chapter 2-Realated literature and StudiesMercy Daracan
 
Automation testing strategy, approach & planning
Automation testing  strategy, approach & planningAutomation testing  strategy, approach & planning
Automation testing strategy, approach & planningSivaprasanthRentala1975
 

Andere mochten auch (9)

Final Project 3 Document
Final Project 3  DocumentFinal Project 3  Document
Final Project 3 Document
 
Proposal Version 5
Proposal  Version 5Proposal  Version 5
Proposal Version 5
 
[SIP 2015] QA Intern: Test Automation
[SIP 2015] QA Intern: Test Automation[SIP 2015] QA Intern: Test Automation
[SIP 2015] QA Intern: Test Automation
 
ENASE 2013 - SEM - (Francia) From Functional Test Scripts to Performance Test...
ENASE 2013 - SEM - (Francia) From Functional Test Scripts to Performance Test...ENASE 2013 - SEM - (Francia) From Functional Test Scripts to Performance Test...
ENASE 2013 - SEM - (Francia) From Functional Test Scripts to Performance Test...
 
Online Student Registration System
Online Student Registration SystemOnline Student Registration System
Online Student Registration System
 
Student result mamagement
Student result mamagementStudent result mamagement
Student result mamagement
 
Course registration system dfd
Course registration system dfdCourse registration system dfd
Course registration system dfd
 
Chapter 2-Realated literature and Studies
Chapter 2-Realated literature and StudiesChapter 2-Realated literature and Studies
Chapter 2-Realated literature and Studies
 
Automation testing strategy, approach & planning
Automation testing  strategy, approach & planningAutomation testing  strategy, approach & planning
Automation testing strategy, approach & planning
 

Ähnlich wie Proposal Automation of An Enrollment Process

Placement Management System
Placement Management SystemPlacement Management System
Placement Management SystemIRJET Journal
 
A Review on Training and Placement Management System
A Review on Training and Placement Management SystemA Review on Training and Placement Management System
A Review on Training and Placement Management SystemIRJET Journal
 
School Management System
School Management SystemSchool Management System
School Management SystemZain Basit
 
Business Intelligence
Business IntelligenceBusiness Intelligence
Business IntelligenceTing Yin
 
IRJET - Hostel Management System using Ensemble Learning
IRJET - Hostel Management System using Ensemble LearningIRJET - Hostel Management System using Ensemble Learning
IRJET - Hostel Management System using Ensemble LearningIRJET Journal
 
Project Documentation Student Management System format.pptx
Project Documentation Student Management System format.pptxProject Documentation Student Management System format.pptx
Project Documentation Student Management System format.pptxAjayPatre1
 
Running Head STUDENT RECORD KEEPING SYSTEM DATABASE PROJECT 1.docx
Running Head STUDENT RECORD KEEPING SYSTEM DATABASE PROJECT  1.docxRunning Head STUDENT RECORD KEEPING SYSTEM DATABASE PROJECT  1.docx
Running Head STUDENT RECORD KEEPING SYSTEM DATABASE PROJECT 1.docxjeanettehully
 
Student Management Program SystemFINAL PROJECT Presentation.docx
Student Management Program SystemFINAL PROJECT Presentation.docxStudent Management Program SystemFINAL PROJECT Presentation.docx
Student Management Program SystemFINAL PROJECT Presentation.docxdeanmtaylor1545
 
College Management System
College Management SystemCollege Management System
College Management SystemAsfaque Khalid
 
Guidelines in Oral Defense
Guidelines in Oral Defense Guidelines in Oral Defense
Guidelines in Oral Defense Angelito Pera
 
A New Approach of Analysis of Student Results by using MapReduce
A New Approach of Analysis of Student Results by using MapReduceA New Approach of Analysis of Student Results by using MapReduce
A New Approach of Analysis of Student Results by using MapReduceIRJET Journal
 
A Survey Paper on Leave Automation
A Survey Paper on Leave AutomationA Survey Paper on Leave Automation
A Survey Paper on Leave Automationijtsrd
 
Training and placement
Training and placementTraining and placement
Training and placementBhavesh Parmar
 
Training and placement reportmsword
Training and placement reportmswordTraining and placement reportmsword
Training and placement reportmswordBhavesh Parmar
 
Project Report on Employee Management System.docx
Project Report on Employee Management System.docxProject Report on Employee Management System.docx
Project Report on Employee Management System.docxDhineshkumarPrakasam
 

Ähnlich wie Proposal Automation of An Enrollment Process (20)

Placement Management System
Placement Management SystemPlacement Management System
Placement Management System
 
A Review on Training and Placement Management System
A Review on Training and Placement Management SystemA Review on Training and Placement Management System
A Review on Training and Placement Management System
 
K plus manual 2011 12
K plus manual 2011 12K plus manual 2011 12
K plus manual 2011 12
 
School Management System
School Management SystemSchool Management System
School Management System
 
Business Intelligence
Business IntelligenceBusiness Intelligence
Business Intelligence
 
Student acadamic system Final report
Student acadamic system Final reportStudent acadamic system Final report
Student acadamic system Final report
 
Sumer traning
Sumer traningSumer traning
Sumer traning
 
IRJET - Hostel Management System using Ensemble Learning
IRJET - Hostel Management System using Ensemble LearningIRJET - Hostel Management System using Ensemble Learning
IRJET - Hostel Management System using Ensemble Learning
 
Project Documentation Student Management System format.pptx
Project Documentation Student Management System format.pptxProject Documentation Student Management System format.pptx
Project Documentation Student Management System format.pptx
 
Running Head STUDENT RECORD KEEPING SYSTEM DATABASE PROJECT 1.docx
Running Head STUDENT RECORD KEEPING SYSTEM DATABASE PROJECT  1.docxRunning Head STUDENT RECORD KEEPING SYSTEM DATABASE PROJECT  1.docx
Running Head STUDENT RECORD KEEPING SYSTEM DATABASE PROJECT 1.docx
 
Student Management Program SystemFINAL PROJECT Presentation.docx
Student Management Program SystemFINAL PROJECT Presentation.docxStudent Management Program SystemFINAL PROJECT Presentation.docx
Student Management Program SystemFINAL PROJECT Presentation.docx
 
College Management System
College Management SystemCollege Management System
College Management System
 
Guidelines in Oral Defense
Guidelines in Oral Defense Guidelines in Oral Defense
Guidelines in Oral Defense
 
Student information system
Student information systemStudent information system
Student information system
 
Report
ReportReport
Report
 
A New Approach of Analysis of Student Results by using MapReduce
A New Approach of Analysis of Student Results by using MapReduceA New Approach of Analysis of Student Results by using MapReduce
A New Approach of Analysis of Student Results by using MapReduce
 
A Survey Paper on Leave Automation
A Survey Paper on Leave AutomationA Survey Paper on Leave Automation
A Survey Paper on Leave Automation
 
Training and placement
Training and placementTraining and placement
Training and placement
 
Training and placement reportmsword
Training and placement reportmswordTraining and placement reportmsword
Training and placement reportmsword
 
Project Report on Employee Management System.docx
Project Report on Employee Management System.docxProject Report on Employee Management System.docx
Project Report on Employee Management System.docx
 

Mehr von Deborah Obasogie

Java Technical Design Document
Java Technical Design DocumentJava Technical Design Document
Java Technical Design DocumentDeborah Obasogie
 
Technical Specification - Database
Technical Specification - DatabaseTechnical Specification - Database
Technical Specification - DatabaseDeborah Obasogie
 
requirements_traceability_matrix_sample
requirements_traceability_matrix_samplerequirements_traceability_matrix_sample
requirements_traceability_matrix_sampleDeborah Obasogie
 
Tivoli Support Documentation
Tivoli Support DocumentationTivoli Support Documentation
Tivoli Support DocumentationDeborah Obasogie
 
SoftwareRequirementSpecification.docx
SoftwareRequirementSpecification.docxSoftwareRequirementSpecification.docx
SoftwareRequirementSpecification.docxDeborah Obasogie
 
Core Skills Assessment Requirements Module 4.0
Core Skills Assessment Requirements Module 4.0Core Skills Assessment Requirements Module 4.0
Core Skills Assessment Requirements Module 4.0Deborah Obasogie
 
Governance Model - Slide Show
Governance Model - Slide ShowGovernance Model - Slide Show
Governance Model - Slide ShowDeborah Obasogie
 
Project Overview Statement (POS)
Project Overview Statement (POS)Project Overview Statement (POS)
Project Overview Statement (POS)Deborah Obasogie
 
Guidewire billing center system
Guidewire   billing center systemGuidewire   billing center system
Guidewire billing center systemDeborah Obasogie
 
Guidewire - BillingCenter System
Guidewire - BillingCenter SystemGuidewire - BillingCenter System
Guidewire - BillingCenter SystemDeborah Obasogie
 
Airlines Financial Analysis
Airlines Financial AnalysisAirlines Financial Analysis
Airlines Financial AnalysisDeborah Obasogie
 
Web Portal reporting Strategy and Recommendation
Web Portal reporting Strategy and RecommendationWeb Portal reporting Strategy and Recommendation
Web Portal reporting Strategy and RecommendationDeborah Obasogie
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisDeborah Obasogie
 

Mehr von Deborah Obasogie (20)

Scrum30Secpptx
Scrum30SecpptxScrum30Secpptx
Scrum30Secpptx
 
Java Technical Design Document
Java Technical Design DocumentJava Technical Design Document
Java Technical Design Document
 
Technical Specification - Database
Technical Specification - DatabaseTechnical Specification - Database
Technical Specification - Database
 
requirements_traceability_matrix_sample
requirements_traceability_matrix_samplerequirements_traceability_matrix_sample
requirements_traceability_matrix_sample
 
Tivoli Support Documentation
Tivoli Support DocumentationTivoli Support Documentation
Tivoli Support Documentation
 
SoftwareRequirementSpecification.docx
SoftwareRequirementSpecification.docxSoftwareRequirementSpecification.docx
SoftwareRequirementSpecification.docx
 
Core Skills Assessment Requirements Module 4.0
Core Skills Assessment Requirements Module 4.0Core Skills Assessment Requirements Module 4.0
Core Skills Assessment Requirements Module 4.0
 
SubversionGuide.docx
SubversionGuide.docxSubversionGuide.docx
SubversionGuide.docx
 
Governance Model - Slide Show
Governance Model - Slide ShowGovernance Model - Slide Show
Governance Model - Slide Show
 
Project Overview Statement (POS)
Project Overview Statement (POS)Project Overview Statement (POS)
Project Overview Statement (POS)
 
Guidewire billing center system
Guidewire   billing center systemGuidewire   billing center system
Guidewire billing center system
 
Guidewire - BillingCenter System
Guidewire - BillingCenter SystemGuidewire - BillingCenter System
Guidewire - BillingCenter System
 
Airlines Financial Analysis
Airlines Financial AnalysisAirlines Financial Analysis
Airlines Financial Analysis
 
Jira Issue Types
Jira Issue TypesJira Issue Types
Jira Issue Types
 
Web Portal reporting Strategy and Recommendation
Web Portal reporting Strategy and RecommendationWeb Portal reporting Strategy and Recommendation
Web Portal reporting Strategy and Recommendation
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value Analysis
 
Story & Estimate
Story & EstimateStory & Estimate
Story & Estimate
 
Word 2013
Word 2013Word 2013
Word 2013
 
Excel 2013
Excel 2013Excel 2013
Excel 2013
 
User Guide
User GuideUser Guide
User Guide
 

Proposal Automation of An Enrollment Process

  • 1. AUTOMATION OF ENROLLMENT PROCESS A PROPOSAL TO: XYZ TRAINING INSTITUTION May 29, 2011 Deborah Obasogie PM592ON – May 2011 Sec C: Project Cost and Schedule Control Assignment: Course Project, Part 1 (CP-1)
  • 2. Table of Contents Automation of Enrollment Process..............................................................................................................1 Executive Summary......................................................................................................................................1 Project Description.......................................................................................................................................3 Project High Level Requirements.................................................................................................................5 Functional Requirements.........................................................................................................................5 Nonfunctional Requirements...................................................................................................................5 Technical Requirements...........................................................................................................................5 Project Deliverables .................................................................................................................................6 Work Breakdown Structure .........................................................................................................................6 Cost Estimates ..............................................................................................................................................6 Advanced Cost Estimating............................................................................................................................7 Cost Assumptions.........................................................................................................................................8 Financial Analysis .........................................................................................................................................9 Schedule .......................................................................................................................................................9 Appendix A .................................................................................................................................................10 Appendix B..................................................................................................................................................14 Appendix C..................................................................................................................................................15 Appendix D .................................................................................................................................................16 Appendix E..................................................................................................................................................17 Appendix F..................................................................................................................................................18 Appendix G .................................................................................................................................................20 Appendix H .................................................................................................................................................21 Appendix I...................................................................................................................................................22 Appendix J ..................................................................................................................................................23
  • 3. 1/28 Automation of Enrollment Process Executive Summary XYZ Training Institute is a new company that provides training in subject areas including Project Management, Microsoft Products, Java and C++. XYZ is considered a career college and offers programs through flexible and innovative learning methods that lead to a certificate. Traditional classroom instruction and online instruction are available. Computer training classes are taught in a 3-floor story building in Townville, AB. XYZ has 200 enrolled students and a 20-person staff consisting of: President, Greg Defeo; Director, JoAnne Kline; Registrar, Jim Logan; Coordinator, Barry Rigler; Scheduler, Ann Archibald; an Administrator, Advisor, Account Executive, Instructors (10 staff members), Marketing (1 staff member) and 2 support staff (facilities and maintenance). Staff members will assume the roles of Project Sponsor, Customer, and Subject Matter Experts on the project team. XYZ is accredited by the Middle States Commission on Higher Education (MSCHE). XYZ’s mission is to empower its students to succeed in today's dynamic world by integrating IT training and professional skills into a sound career-focused education that provides the life skills necessary for students to realize their full potential and career goals. Through XYZ, nontraditional students prepare for direct entry into the workforce and take advantage of shorter, more flexible evening schedules. XYZ also helps those currently in the workforce obtain additional education for career advancement. XYZ has a conglomeration of different systems and procedures (as well as hardware and software) designed specifically for departmental needs. Employee records (including payroll, medical and other benefits) are held by Human Resources. Financial data and processing (including payroll computations, employee compensation, invoicing and billing for products and 1/28
  • 4. 2/28 services) are held by the Finance Department. Student data, from the enrollment process (identify, retain, anticipate the needs and wants of students) are held by the Registrar Office. Currently the Registrar Office uses MS Excel to track student enrollments. To stay competitive in this industry, the department has identified a need for an automated system that will streamline tracking of their student data and also be accurate and secure. XYZ is looking to increase the efficiency and effectiveness of student data by 80% within one year and to expand customer base by 60% by year end. In addition to a positive NPV, the project would result in intangible benefits such as increase customer satisfaction and reliability of student data. The project Budget is $460,000. All funding is provided by XYZ. Solutions Consultants will assist XYZ with this six-month implementation. 2/28
  • 5. 3/28 Project Description The objective of the project is to increase the efficiency and effectiveness of student data by 80 percent in one year and expand their customer base by 60 percent by year end. XYZ would like to: 1. Process tracking data such as student enrollment, historic information, and student performance. 2. Have the ability to manage courses, students, and class information. 3. Be able to perform analysis on student data. XYZ is a new company that provides training various subject areas. They have 200 enrolled students and a staff of twenty. The Registrar Office current system is in an Excel spreadsheet. There is no data backup leaving staff and students with no historical data tracking. The system is unable to effectively share, manage, store, or report on student data. There are no means to manage the data, thus data is prone to being lost and there is a high probability of data entry errors. The current system lacks any kind of security which leaves the entire system and users at risk. XYZ would like to automate the enrollment process in order to stay competitive in their industry. In order to do this they will need to upgrade the flat file system that is currently in use to an automated system that will give them the ability to systematically perform specific and daily functions and streamline tracking of student data. The project will increase business for XYZ. It will do this by making it easy to provide information to potential students about the classes being offered. This will also be accomplished by allowing XYZ to track the demographics for students enrolled in offered courses. This will 3/28
  • 6. 4/28 allow marketing to be targeted more effectively by increasing the chances that potential students will choose to enroll in courses offered. The project will increase customer satisfaction. The primary way the project will affect current customers is that they will enjoy a streamlined enrollment process as they take their courses. Another source of customer satisfaction is that XYZ will be able to track courses that are popular and those that aren’t. This will allow them to make sure that popular courses are offered regularly and the unpopular ones are offered rarely or even completely removed from the course offerings. The increased customer satisfaction will come from knowing that XYZ offers courses that customers want. The project will increase the reliability of student data. Currently the Registrar Office is using a spreadsheet to track customers. This presents a huge risk of data loss through inadvertent overwriting of cells in the file, accidental deletion of the file, or even a computer crash corrupting the file. Creating a relational database system (RDBMS) will increase the data reliability exponentially. The database can easily be backed up. In the event of a small data issue for example, a repair could be as simple as restoring the portion of corrupted data from the backup instead of having to restore everything such as would be the case with a spreadsheet. The goals of the project are: 1. To make it easy to enroll students, track enrollments, and run reports to strategize the offerings in the future. 2. To make it easy to provide information to the potential students. 3. To run reports to assist in marketing to the right audience. Critical success factors: 1. Develop an automated system that will provide: 4/28
  • 7. 5/28 a. A process to enroll students and track their enrollments. b. A process to run reports that identify “what kind of students take what classes”. c. A process to “provide information to the potential students”. d. A mechanism that stores and manages the student data (course, student and class information). For specific field details of student data see Appendix A. The new system will solve the current system problems by providing sharing and storing of student data, reporting on student data, and management of student data (course, student, and class information). Additionally it will provide data security, data backup and minimize data lost and data entry errors. Making this a centralized web application will make updating and retrieving student data easier and will increase the integrity of the data. The project budget will be $460,000. All funding will be provided by the customer, XYZ Training Institute. Project High Level Requirements Functional Requirements For functional requirements see Appendix B. Nonfunctional Requirements For nonfunctional requirements see Appendix C. Technical Requirements For technical requirements see Appendix D. With respect to the identified technical requirements, XYZ has proposed to use the Kuali Foundation’s open source software suite as a basis for developing the web application. To support the use of this software, the following software products are required as per documentation at the Kuali web site. 5/28
  • 8. 6/28  Microsoft Server 2010 or Linux  Postgres SQL 8.4  Postgres Plus add-ons  EnterpriseDB  ApachePHP  PHP BB  PHP pg Admin Project Deliverables For project deliverables see Appendix E. Work Breakdown Structure The Work breakdown Structure (WBS) is the basic tool used in project planning. It breaks the project down into the main components of work required to complete the project. Our project is broken down into four major components. The Project Charter, Project Plan and the analysis of the requirements and environment (infrastructure, hardware, software, user profiles) are includes in the Analysis component. The largest component, Design and Build includes all tasks meeting XYZ’s critical success factors (process to enroll students and track their enrollments, process to run reports that identify “what kind of students take what classes”, process to “provide information to potential students”, and mechanism that stores and manages the student data). The third component, Test and Train includes testing and training tasks. Deploy is responsible for installing the solution into production. For the WBS see Appendix F. Cost Estimates 6/28
  • 9. 7/28 The use of historical data and expert advice is the best approach for this project. Historical data will provide the project team with updated knowledge of the prices of parts, services, and the development of the project schedule. Expert advice (Kuali Foundation’s staff) will be utilized in conjunction with the development of the project schedule and with informing XYZ during scope change requests. These techniques have been chosen because it allows the project team to remain focus on the project itself. Also, the experts will serve as an additional support system during meetings and throughout the project process. The total estimated cost for the project is $458,792.00 and it can be completed anywhere from 5 to 6 months. The code is provided by the Kuali Foundation because they have a similar module in their software suite that accommodates most of XYZ’s functionality and screen navigation. They will help us customize it to meet XYZ’s requirements. Labor, materials and overhead costs are included in our $460k budget. Upfront costs (licenses, customization, training, and implementation) will cost approximately $17,200. Materials costs (servers, software, storage devices, etc.) required will cost approximately $102,400. Labor will cost about $340,000. The system engineer will cost $55/hour, the database administrator will cost $50/hour, developers (2) costs will cost $70/hour and $60/hour, the software tester will cost $40/hour, the help desk/tech support will cost $30/hour, the trainer will cost $35/hour, and the project manager costs will cost $100/hour; all are variable cost. The performance will be done Monday through Friday. For costs for each task and total estimated costs see Appendix G. Advanced Cost Estimating To get the cost estimates for the project, the Project Evaluation Review Technique (PERT) is used to derive task duration estimations. Using optimistic, most likely, and 7/28
  • 10. 8/28 pessimistic estimates for each task, the expected duration is calculated which is then used to calculate the estimated cost per task. For PERT analysis see Appendix H. Cost Assumptions Three prominent project assumptions include: 1. There is a business need to develop a student management system. 2. All courses are owned by XYZ Training Institute. 3. Research supports automation would be beneficial to XYZ Training Institute. Although the project is utilizing both historical data and expert advice, there is no prior historical data specific to the exact requirements identified with this effort, however, our Project Managers are very knowledgeable and experience in software development and has generalized costs across the board. Time, hardware, and cost are variable, as changes are inevitable. Resource management is more difficult in a short duration project because of the time constraint. As deliverables must be delivered within the short period of time, it may cause the allocation of extra resources or more over time. In addition, risks and constraints are not represented in the estimated costs, but will identify and provide mitigation plans in the Project Charter. All of which could have an effect on the triple constraint – score, time and cost (and quality). Arising issues impacting the project will be presented to XYZ to review along with a revised plan for their decision to cancel or move ahead. Although XYZ found substantial costs reduction by adopting open source, risk includes the absence of a formal open source policy in place and additional costs in man hours to support system. It is assumed that XYZ has their own IT staff that will keep software updated, ensure 8/28
  • 11. 9/28 security patches and virus updates are done and can do maintenance updates and checks on hardware. The project ends after deployment and cost estimates are only to that point. It is recommended that XYZ move forward with having a formal Open Source Solution (OSS) policy in place. Financial Analysis Net Present Value (NPV) is used to determine how profitable a proposed project will be to XYZ. The results is a present value higher than the investment, a positive NPV investment that would add value to XYZ. Cash flows represent forecasted revenues minus operating expenses for the next five years. In addition to a positive NPV, the project would result in intangible benefits such as increase customer satisfaction and reliability of student data. Calculations include the initial $460,000 cost as one of the values because the payment occurs at the end of the first period. For NPV calculations see Appendix I. Schedule This section depicts the WBS and the software development phases consisting of analysis, design and build, test and train, and deploy. The schedule shows tasks, task relationships (dependencies), task durations and resources assigned to each task. Also included is a Gantt chart schedule showing the time line for the project. The project has 50 tasks, 147 days durations, 6,014.4 work hours (many concurrent hours), 38 dependencies and resources (8 external (Resource Group: Solutions Consultants and Kuali) and 12 internal (resource Group: SME)). For the schedule with Gantt chart, tasks, task relationships, task duration, and task resources see Appendix J. 9/28
  • 12. 10/28 Appendix A Data to be Held and Managed Student Information: Name First Last Address(es) Street City State Zip Social security number Marital Status Birthday Phone(s) Emails(s) Emergency contact(s) Name Phone Race Religion Gender Citizenship Education(s) Degree Major Completion year Institution Name Address Street City State Zip Occupation(s) Employer(s) Name Address Street City State Zip Vehicle(s) Year Make Model Plate state Plate number Certificate program Financial aid lender Work study employer Student Enrollment Information: 10/28
  • 13. 11/28 Enrollment date(s) Course Offerings (classes) Session Month Year Session Period Start date End date Day Time Start time End time Instructor Room Grade(s) Course Information: Number Title Description Prerequisite(s) Credit hours Instructor Information: Name First Last Address(es) Street City State Zip Social security number Marital Status Birthday Phone(s) Emails(s) Emergency contact(s) Name Phone Race Religion Gender Citizenship Education(s) Degree Major Completion year Institution Name Address Street City State Zip Occupation(s) 111/28
  • 14. 12/28 Employer(s) Name Address Street City State Zip Facility Information: Location Address Street City State Zip Room number Room capacity Marketing Information: Student Information: Name First Last Address(es) Street City State Zip Social security number Marital Status Birthday Phone(s) Emails(s) Emergency contact(s) Name Phone Race Religion Gender Citizenship Education(s) Degree Major Completion year Institution Name Address Street City State Zip Occupation(s) Employer(s) Name Address Street City 12/28
  • 15. 13/28 State Zip Vehicle(s) Year Make Model Plate state Plate number Certificate program Financial aid lender Work study employer Student Enrollment Information: Enrollment date(s) Course Offerings (classes) Session Month Year Session Period Start date End date Day Time Start time End time Instructor Room Grade(s) Course Information: Number Title Description Prerequisite(s) Credit hours 13/28
  • 16. 14/28 Appendix B Functional Requirements In Scope Out of scope 1. Tracking, historic information and analysis of student data: a. System should enroll students and track student enrollments. b. System should keep and access last two years and going forward history. History information consists of the student, enrollment and course information listed above. c. System should supply Marketing with the student information for their purposes. 2. System should provide the following formatted reports: a. Course offerings (Course Offerings Report). b. List of students for each class (Enrollment Report). c. List of all the classes that a student has taken and is registered currently (Grades and Student History Reports).  Student payments.  Company’s vendors.  3 other student performance reports (to be completed in a separate project.) 14/28
  • 17. 15/28 Appendix C Nonfunctional Requirements In Scope Out of scope 1. Performance: System must accommodate 2500 concurrent users. 2. Security: Every user of system must have personal login to see and use system. 15/28
  • 18. 16/28 Appendix D Technical Requirements Technical Requirement ID Name Description TR001 Uptime The system must maintain a 99.999% uptime rate. TR002 Concurrent Logon The system must have the capability of allowing multiple simultaneous logons TR003 Auditing The system must log usage for security auditing purposes TR004 Open Source software Whenever possible, open source software should be utilized to reduce licensing purchase and renewal costs TR005 Database software Database software should be chosen that is open source if possible. The software must support load balancing between multiple database servers TR006 Web Application Server software Open source application server software for the web server should be chosen where possible. This may be impacted by the choice of programming language for the web interface and the middleware layer of the application TR007 Storage A data storage solution must be chosen that is fault tolerant TR008 Backup A backup solution must be chosen that will allow nightly backups of the database. The solution must provide a portable format for offsite storage. The source code and compiled packages for the developed solution must be backed up and stored offsite at initial code freeze and whenever an enhancement is coded to the system TR009 Server Hardware Server hardware must meet minimum requirements for the chosen software. Ideally the hardware will meet “recommended” requirements as per the software documentation and allow for future expansion. TR010 User Hardware User machines should be capable of running current versions of major web browsers that support the Google Web Toolkit version 1.5 TR011 Network Hardware XYZ’s networking infrastructure must be able to handle the increased traffic from faculty and students accessing the web application TR012 Network Security Applicable portions of the application will be exposed to the Internet to allow potential students to access content. Firewalls and other network security features must be implemented to support this and prevent security failures 16/28
  • 19. 17/28 Appendix E Project Deliverables Event or Deliverable Target Date Responsibility Project charter completed June 15, 2011 Project Manager Project charter approved June 17, 2011 Project Sponsor, Customer Project plan completed June 22, 2011 Project Manager Project plan approved June 24, 2011 Project Sponsor, Customer, Subject Matter Experts Project team assembled June 20, 2011 Project Manager Project execution initiated June 22, 2011 Project Manager RDBMS Data Model design July 30, 2011 Project Manager, Development team Web GUI Interface July 30, 2011 Project Manager, Development team Process to enroll students and track their enrollments Oct 12, 2011 Project Manager, Development team Report Process that identifies “what kind of students take what classes” Dec 15, 2011 Project Manager, Development tea. Process to “provide information to the potential students” Dec 15, 2011 Project Manager, Development team Mechanism to store and manage data Oct 15, 2011 Project Manager, Development team Training on new system Dec 13, 2011 Project Sponsor, Customer, Subject Matter Experts, Trainer Project execution completed Dec 27, 2011 Project Manager Project closed out Dec 30, 2011 Project Manager 17/28
  • 20. 18/28 Appendix F WBS WBS Task Name 1 Automate Enrollment Process 1.1 Analysis 1.1.1 Complete charter and plan 1.1.1.1 Complete and approve Project Charter 1.1.1.2 Complete and approve Project Plan 1.1.2 Analysis of requirements and environment 1.1.2.1 Analyze and set up infrastructure 1.1.2.2 Analyze and set up hardware 1.1.2.3 Analyze and set up Kuali Foundation software 1.1.2.4 Analyze and set up profile 1.2 Design and Build 1.2.1 Process to enroll students and track their enrollments 1.2.1.1 RDBMS Data Model design 1.2.1.2 Design and Build web GUI interface 1.2.1.3 Student enrollment process 1.2.2 Process to run reports that identify “what kind of students take what classes” 1.2.2.1 Design and build defined reports 1.2.2.2 Design and build analysis data 1.2.2.3 Output data for viewing 1.2.3 Process to “provide information to potential students” 1.2.3.1 Build course catalog view 1.2.3.2 Build course offerings view 1.2.3.3 Build enrollment list view 1.2.3.4 Build defined reports view 1.2.3.5 Build student history view 1.2.3.6 Build analysis data view 1.2.3.7 Build grades view 1.2.4 Mechanism that stores and manages the student data 1.2.4.1 Store and manage student information 1.2.4.2 Store and manage course information 1.2.4.3 Create course catalog 1.2.4.4 Create course offerings 1.2.4.5 Create enrollment list 1.2.4.6 Store and manage instructor information 1.2.4.7 Select class to teach 1.2.4.8 Submit student grades 1.2.4.9 Store student history 1.2.4.9.1 Store student data 1.2.4.9.2 Restore student data 1.2.4.10 Secure data with user profiles 1.3 Test and train 18/28
  • 21. 19/28 1.3.1 Test process to enroll students and track their enrollments 1.3.2 Test process to run reports that identify “what kind of students take what classes” 1.3.3 Test process to “provide information to potential students” 1.3.4 Test mechanism that stores and manages the student data 1.3.5 Test nonfunctional requirements 1.3.6 Test technical requirements 1.3.7 Train on new system 1.4 Deploy 1.4.1 Implement solution to production 19/28
  • 22. 20/28 Appendix G Cost Estimates Task Name Cost Complete and approve Project Charter $4,133.33 Complete and approve Project Plan $4,000.00 Analyze and set up Infrastructure $43,620.00 Analyze and set up hardware $42,280.00 Analyze and set up Kuali Foundation software $116,300.00 Analyze and set up profile $2,200.00 RDBMS Data Model design $19,253.33 Design and Build web GUI interface $17,733.33 Student enrollment process $65,232.00 Design and build defined reports $10,800.00 Design and build analysis data $20,000.00 Output data for viewing $1,320.00 Build course catalog view $3,600.00 Build course offerings view $3,200.00 Build enrollment list view $3,600.00 Build defined reports view $3,200.00 Build student history view $3,600.00 Build analysis data view $3,200.00 Build grades view $3,600.00 Store and manage student information $4,066.67 Store and manage course information $4,000.00 Create course catalog $6,400.00 Create course offerings $7,200.00 Create enrollment list $6,400.00 Store and manage instructor information $4,000.00 Select class to teach $3,720.00 Submit student grades $3,306.67 Store student data $4,000.00 Restore student data $4,000.00 Secure data with user profiles $4,200.00 Test process to enroll students and track their enrollments $3,800.00 Test process to run reports that identify “what kind of students take what classes” $3,800.00 Test process to “provide information to potential students” $3,800.00 Test mechanism that stores and manages the student data $3,800.00 Test nonfunctional requirements $5,026.67 Test technical requirements $5,026.67 Training on new system $2,600.00 Implement solution to production $8,773.33 Total Estimated Cost: $458,792.00 20/28