SlideShare ist ein Scribd-Unternehmen logo
1 von 51
PROJECT MANAGEMENT 
As Per (PMI) 
PMBOK 5th Edition 
-Five Process Groups 
-Ten Knowledge Areas 
-Forty-Seven Processes 
-Inputs and Outputs 
-Tools and Techniques 
-Ethics
International Project Management Systems 
PMI: Project Management Institute was established in 
America 1984 and this is the one which will be adopted and 
taught. 
PRINCE2 : Established in UK in 1989 by information 
technology company, the system focuses on the private sector 
institutions. 
6σ: Started by Motorola 1986, focusing on the theme of 
quality for the purpose of access to quality 99.9966%, 
equivalent to 3.4 defect per million produced units. 
Agile: Used mainly in software projects and complex 
projects.
What is a PROJECT? 
A project is a temporary endeavor undertaken to 
create a unique product, service, or result. 
The temporary nature of projects indicates that a 
project has a definite beginning and end. The end 
is reached when: 
the project’s objectives have been achieved or 
when the project is terminated because its 
objectives will not or cannot be met, or when the 
need for the project no longer exists.
What is Project Management? 
Project management is the application of 
knowledge, skills, tools, and techniques to project 
activities to meet the project requirements. 
Project management is accomplished through the 
appropriate application and integration of the 47 
logically grouped project management processes, 
which are categorized into five Process Groups. 
These five Process Groups are: 
1. Initiating, 
2. Planning, 
3. Executing, 
4. Monitoring and Controlling, 
5. Closing.
Five Process Groups 
1. Initiating Process Group. Those processes performed to define a new project 
or a new phase of an existing project by obtaining authorization to start the 
project or phase. 
2. Planning Process Group. Those processes required to establish the scope of 
the project, refine the objectives, and define the course of action required to 
attain the objectives that the project was undertaken to achieve. 
3. Executing Process Group. Those processes performed to complete the work 
defined in the project management plan to satisfy the project specifications. 
4. Monitoring and Controlling Process Group. Those processes required to 
track, review, and regulate the progress and performance of the project; identify 
any areas in which changes to the plan are required; and initiate the 
corresponding changes. 
5. Closing Process Group. Those processes performed to finalize all activities 
across all Process Groups to formally close the project or phase.
Life Cycle of Phases or Entire Project
Typical Cost and Staffing Levels
Risk and uncertainty vs. Changes 
The cost of change at the early stages is low but in the late stages is 
very high. 
The risk at the early stages is high while at the late stages is low.
Process Group interact 
The Process Groups are seldom either discrete or one-time 
events; they are overlapping activities that occur throughout 
the project.
PROJECT KNOWLEDGE AREAS (KA) 
Integration 
management 
6 
4.1 
Develop 
Project 
Charter. 
4.2 
Develop 
project 
Mgmt. 
Plan 4.3 
Direct 
and 
Manage 
Project 
4.4 
work, 
Monitor 
and 
Control 
Project 
Work., 4.5 
Perform 
integrate 
d change 
control. 
4.6 Close 
Project 
or Phase. 
Scope 
management 
6 
5.1 Plan 
Scope 
Mgmt., 
5.2 
Collect 
requirem 
ents, 
5.3 
Define 
Scope 
5.4 Create 
WBS. 
5.5 
Validate 
Scope. 
5.6 Control 
Scope. 
Time 
management 
7 
6.1 Plan 
Schedule 
Mgmt., 
6.2 Define 
Activities., 
6.3 
Sequence 
Activities., 
6.4 
Estimate 
Activity 
Resources. 
, 
6.5 
Estimate 
Activity 
Durations 
6.6 
Develop 
Schedule. 
6.7 Control 
Schedule. 
Cost 
management 
4 
7.1 Plan 
Cost 
Mgmt., 
7.2 
Estimate 
Costs 
7.3 
Determi 
ne 
Budget. 
7.4 
Control 
Costs. 
Quality 
management 
3 
8.1 Plan 
Quality 
Mgmt. 
8.2 
Perform 
Quality 
Assurance. 
8.3 Control 
Quality. 
HR 
management 
4 
9.1 Plan 
HR Mgmt. 
9.2 
Acquire 
Project 
Team., 
9.3 
Develop 
Project 
Team. 
9.4 
Manage 
Project 
Team. 
Communication 
management 
3 
10.1 Plan 
Commun. 
Mgmt. 
10.2 
Manage 
Commun. 
10.3 
Control 
Commun. 
Risk 
management 
6 
11.1 Plan 
Risk 
Mgmt., 
11.2 
Identify 
Risks., 
11.3 
Perform 
Qualitativ 
e Risk 
An1a1ly.4s is. 
Perform 
Quantitati 
ve Risk 
analysis 
11.5 Plan 
Risk 
Responses. 
11.6 
Control 
Risks. 
Procurement 
management 
4 
12.1 Plan 
Procureme 
nt Mgmt. 
12.2 
Conduct 
Procureme 
nt. 
12.3 
Control 
Procureme 
nt. 
12.4 Close 
Procureme 
nt. 
Stakeholder 
management 
4 
13.1 
Identify 
Stakehold 
ers. 
13.2 Plan 
Stakehold 
ers Mgmt. 
13.3 
Manage 
Stakehold 
er 
Engageme 
nt. 
13.4 
Control 
Stakeholde 
rs 
Engageme 
nt.
47 PM Processes 
Knowledge Areas 
Process Groups 
Initiating Process Group Planning Process Group Executing Process Group 
Monitoring & Controlling 
Process Group 
Closing Process Group 
Project Integration 
management 
4.1 Develop Project Charter. 
4.2 Develop project Mgmt. 
Plan 
4.3 Direct and Manage 
Project work, 
4.4 Monitor and Control 
Project Work., 
4.6 Close Project or Phase. 
4.5 Perform integrated 
change control. 
Project Scope management 
5.1 Plan Scope Mgmt., 
5.5 Validate Scope. 
5.2 Collect requirements, 
5.3 Define Scope 
5.6 Control Scope. 
5.4 Create WBS. 
Project Time management 
6.1 Plan Schedule Mgmt., 
6.7 Control Schedule. 
6.2 Define Activities., 
6.3 Sequence Activities., 
6.4 Estimate Activity 
Resources., 
6.5 Estimate Activity 
Durations 
6.6 Develop Schedule. 
Project Cost management 
7.1 Plan Cost Mgmt., 
7.2 Estimate Costs 7.4 Control Costs. 
7.3 Determine Budget. 
Project Quality management 8.1 Plan Quality Mgmt. 
8.2 Perform Quality 
Assurance. 
8.3 Control Quality. 
Project Human Resource 
management 
9.1 Plan HR Mgmt. 
9.2 Acquire Project Team., 
9.3 Develop Project Team. 
9.4 Manage Project Team. 
Project Communication 
management 
10.1 Plan Commun. Mgmt. 10.2 Manage Commun. 10.3 Control Commun. 
Project Risk management 
11.1 Plan Risk Mgmt., 
11.6 Control Risks. 
11.2 Identify Risks., 
11.3 Perform Qualitative Risk 
Analysis. 
11.4 Perform Quantitative 
Risk analysis 
11.5 Plan Risk Responses. 
Project Procurement 
management 
12.1 Plan Procurement Mgmt. 12.2 Conduct Procurement. 12.3 Control Procurement. 12.4 Close Procurement. 
Project Stakeholder 
management 
13.1 Identify Stakeholders. 13.2 Plan Stakeholders Mgmt. 
13.3 Manage Stakeholder 
Engagement. 
13.4 Control Stakeholders 
Engagement.
1. Develop Project Charter (Initiation) 
Develop Project Charter is the process of developing a document that 
formally authorizes the existence of a project and provides the project 
manager with the authority to apply organizational resources to project 
activities. 
The key benefit of this process is a well-defined project start and project 
boundaries, creation of a formal record of the project, and a direct way for 
senior management to formally accept and commit to the project.
2. Identify Stakeholders (Initiation) 
Identify Stakeholders is the process of identifying the people, groups, 
or organizations that could impact or be impacted by a decision, 
activity, or outcome of the project, analyzing and documenting 
relevant information regarding their interests, involvement, 
interdependencies, influence, and potential impact on project success.
Cont. of Identify Stakeholders (Initiation) 
Power/ interest Grid 
•Interactive communication 
•Push communication 
•Pull communication
3. Develop Project Management Plan (Integration Planning) 
Develop Project Management Plan is the process of defining, preparing, and 
coordinating all subsidiary plans and integrating them into a comprehensive 
project management plan. The key benefit of this process is a central document 
that defines the basis of all project work.
Project Management Plan 
The project management plan is the document that describes how the project will be 
executed, monitored, and controlled. It integrates and consolidates all of the subsidiary plans 
and baselines from the planning processes. 
Project baselines include, but are not limited to: 
•Scope baseline 
•Schedule baseline 
•Cost baseline 
Subsidiary plans include, but are not limited to: 
•Scope management plan 
•Requirements management plan 
•Schedule management plan 
•Cost management plan 
•Quality management plan 
•Process improvement plan 
•Human resource management plan 
•Communications management plan 
•Risk management plan 
•Procurement management plan 
•Stakeholder management plan
Among other things, the project management plan may also include the following: 
•Life cycle selected for the project and the processes that will be applied to each 
phase; 
•Details of the tailoring decisions specified by the project management team as 
follows: 
•Project management processes selected by the project management team, 
•Level of implementation for each selected process, 
•Descriptions of the tools and techniques to be used for accomplishing those 
processes, 
•Description of how the selected processes will be used to manage the specific 
project, including the dependencies and interactions among those processes 
and the essential inputs and outputs. 
•Description of how work will be executed to accomplish the project objectives; 
•Change management plan that documents how changes will be monitored and 
controlled; 
•Configuration management plan that documents how configuration management 
will be performed; 
•Description of how the integrity of the project baselines will be maintained; 
•Requirements and techniques for communication among stakeholders; 
•Key management reviews for content, the extent of, and timing to address, open 
issues and pending decisions.
Project Management Plan VS Project Documents
4. Plan Scope Management (Scope Planning) 
Plan Scope Management is the process of creating a scope 
management plan that documents how the project scope will be 
defined, validated, and controlled. The key benefit of this process is 
that it provides guidance and direction on how scope will be 
managed throughout the project.
5. Collect requirements (Scope Planning) 
Collect Requirements is the process of determining, documenting, and 
managing stakeholder needs and requirements to meet project 
objectives. The key benefit of this process is that it provides the basis for 
defining and managing the project scope including product scope.
These classifications of requirements include: 
•Business requirements, 
•Stakeholder requirements, 
•Solution requirements, 
Solution requirements are further grouped into 
functional and nonfunctional requirements: 
•Functional requirements 
•Nonfunctional requirements 
•Project requirements, 
•Transition Requirement, “as-is” state to “to-be”. 
•Quality requirements.
6. Define Scope (Scope Planning) 
Define Scope is the process of developing a detailed description of the project 
and product. The key benefit of this process is that it describes the project, 
service, or result boundaries by defining which of the requirements collected 
will be included in and excluded from the project scope. 
During project planning, the project scope is defined and described with 
greater specificity as more information about the project is known.
7. Create WBS (Scope Planning) 
Create WBS is the process of subdividing project deliverables and 
project work into smaller, more manageable components. The key 
benefit of this process is that it provides a structured vision of what 
has to be delivered. 
The WBS organizes and defines the total scope of the project, and 
represents the work specified in the current approved project scope 
statement.
Samples of WBS (Scope Planning)
Samples of WBS (Scope Planning) 
Third 
Level 
Forth 
Level 
Second 
Level 
First 
Level
Samples of WBS (Scope Planning) 
Third 
Level 
Forth 
Level 
Second 
Level 
First 
Level
8. Plan Schedule Management(Time Planning) 
Plan Schedule Management is the process of establishing the policies, 
procedures, and documentation for planning, developing, managing, 
executing, and controlling the project schedule. The key benefit of this 
process is that it provides guidance and direction on how the project 
schedule will be managed throughout the project. 
Analytic techniques like which of these? Traditional, WBS, Pert, Project 
Diagram, MS Project, Primavera, EVM, Tracking …etc.
9. Define Activities (Time Planning) 
Define Activities is the process of identifying and documenting the 
specific actions to be performed to produce the project deliverables. The 
key benefit of this process is to break down work packages into activities 
that provide a basis for estimating, scheduling, executing, monitoring, and 
controlling the project work. 
Decomposition and Rolling wave are tools for pre or continuous planning 
depending on the nature of the project. 
Milestones are ZERO duration tasks used as reminders!
10. Sequence Activities (Time Planning) 
Sequence Activities is the process of identifying and documenting 
relationships among the project activities. The key benefit of this process 
is that it defines the logical sequence of work to obtain the greatest 
efficiency given all project constraints.
Cont. of Sequence Activities (Time Planning) 
Every activity and milestone except the first and last should 
be connected to at least one predecessor with a finish-to-start 
or start-to-start logical relationship and at least one 
successor with a finish-to-start or finish-to finish logical 
relationship. 
Logical relationships should be designed to create a realistic 
project schedule. It may be necessary to use lead or lag time 
between activities to support a realistic and achievable 
project schedule. 
Sequencing can be performed by using project management 
software or by using manual or automated techniques.
Cont. of Sequence Activities (Time Planning) 
PROJECT DIAGRAM- CRITICAL PATH METHOD (CPM) 
FW= ES+ Duration (lead-, lag +) Choose the Max. 
BW= LF- Duration (lead+, lag -) Choose the Min.
Cont. of Sequence Activities (Time Planning) 
PROJECT DIAGRAM- CRITICAL PATH METHOD (CPM) 
FW= ES+ Duration (lead-, lag +) Choose the Max. 
BW= LF- Duration (lead+, lag -) Choose the Min. 
CPM
11. Estimate Activity Resources (Time Planning) 
process of estimating the type and quantities of material, human resources, 
equipment, or supplies required to perform each activity. The key benefit of 
this process is that it identifies the type, quantity, and characteristics of 
resources required to complete the activity which allows more accurate cost 
and duration estimates.
Cont. of Estimate Activity Resources (Time Planning) 
The Estimate Activity Resources process is closely coordinated with the 
Estimate Costs process. 
For example: 
A construction project team will need to be familiar with local 
building codes. Such knowledge is often readily available from 
local sellers. However, if the local labor pool lacks experience with 
unusual or specialized construction techniques, the additional cost 
for a consultant may be the most effective way to secure 
knowledge of the local building codes. 
An automotive design team will need to be familiar with the latest 
in automated assembly techniques. 
The requisite knowledge might be obtained by hiring a consultant, 
by sending a designer to a seminar on robotics, or by including 
someone from manufacturing as a member of the project team.
12. Estimate Activity Durations (Time Planning) 
Estimate Activity Durations is the process of estimating the number of 
work periods needed to complete individual activities with estimated 
resources. The key benefit of this process is that it provides the 
amount of time each activity will take to complete, which is a major 
input into the Develop Schedule process.
Cont. of Estimate Activity Durations (Time Planning) 
•uses information on activity scope of work, required resource types, 
estimated resource quantities, and resource calendars. The inputs of the 
estimates of activity duration originate from the person (SME) or group on 
the project team who is most familiar with the nature of the work in the 
specific activity. The duration estimate is progressively elaborated, and the 
process considers the quality and availability of the input data. For example, 
as more detailed and precise data is available about the project engineering 
and design work, the accuracy of the duration estimates improves. Thus, the 
duration estimate can be assumed to be progressively more accurate and of 
better quality. 
•are used to approximate the number of work periods (activity duration) 
needed to complete the activity using the appropriate project and resource 
calendars. All data and assumptions that support duration estimating are 
documented for each estimate of activity duration.
13. Develop Schedule (Time Planning) 
Develop Schedule is the process of analyzing activity sequences, durations, 
resource requirements, and schedule constraints to create the project 
schedule model. The key benefit of this process is that by entering schedule 
activities, durations, resources, resource availabilities, and logical 
relationships into the scheduling tool, it generates a schedule model with 
planned dates for completing project activities.
Cont. of Develop Schedule (Time Planning) 
•Developing an acceptable project schedule is often an iterative 
process. The schedule model is used to determine the planned start 
and finish dates for project activities and milestones based on the 
accuracy of the inputs. 
•Schedule development can require the review and revision of 
duration estimates and resource estimates to create the project 
schedule model to establish an approved project schedule that can 
serve as a baseline to track progress. 
•Once the activity start and finish dates have been determined, it is 
common to have project staff assigned to the activities review their 
assigned activities and confirm that the start and finish dates present 
no conflict with resource calendars or assigned activities in other 
projects or tasks and thus are still valid.
14. Plan Cost Management (Cost Planning) 
the process that establishes the policies, procedures, and 
documentation for planning, managing, expending, and controlling 
project costs. The key benefit of this process is that it provides 
guidance and direction on how the project costs will be managed 
throughout the project.
15. Estimate Costs (Cost Planning) 
Estimate Costs is the process of developing an approximation of the 
monetary resources needed to complete project activities. The key 
benefit of this process is that it determines the amount of cost 
required to complete project work.
Cont. of Estimate Costs (Cost Planning) 
Cost tradeoffs and risks should be considered, such as make versus buy, 
buy versus lease, and the sharing of resources in order to achieve optimal 
costs for the project. 
Cost estimates are generally expressed in units of some currency (i.e., 
dollars, euros, yen, etc.), although in some instances other units of 
measure, such as staff hours or staff days, are used to facilitate 
comparisons by eliminating the effects of currency fluctuations. 
The accuracy of a project estimate will increase as the project progresses 
through the project life cycle. For example, a project in the initiation 
phase may have a rough order of magnitude (ROM) estimate in the range 
of −25% to +75%. Later in the project, as more information is known, 
definitive estimates could narrow the range of accuracy to -5% to +10%. 
In some organizations, there are guidelines for when such refinements 
can be made and the degree of confidence or accuracy that is expected.
Cont. of Estimate Costs (Cost Planning) 
This guideline provides an overview of estimating methods for generating 
detailed project schedules. It includes a brief description of the purpose, 
goals, and process of estimating, as well as specific estimating techniques 
for the project manager and project team. 
Methods of estimating covered in this guideline are: 
•Historical Data 
•Decomposition Process 
•Brainstorming meetings 
•Expert Judgment 
•Delphi Method 
•Network Diagrams - PERT, CPM (ADM), GERT, etc. 
•Rule of Thumb registries and charts 
•"Rolling wave" or "iterative" estimating
16. Determine Budget(Cost Planning) 
process of aggregating the estimated costs of individual activities or 
work packages to establish an authorized cost baseline. The key 
benefit of this process is that it determines the cost baseline against 
which project performance can be monitored and controlled.
Cont. of Determine Budget(Cost Planning)
Cont. of Determine Budget(Cost Planning)
18. Plan Quality Management (Quality Planning) 
the process of identifying quality requirements and/or standards for 
the project and its deliverables, and documenting how the project will 
demonstrate compliance with relevant quality requirements. 
The key benefit of this process is that it provides guidance and 
direction on how quality will be managed and validated throughout 
the project.
Cont. of Plan Quality Management (Quality Planning) 
Quality planning should be performed in parallel with the other 
planning processes. 
For example, proposed changes in the deliverables to meet 
identified quality standards may require: 
• cost or 
•schedule adjustments and 
• a detailed risk analysis of the impact to plans. 
The quality planning techniques discussed here are those used 
most frequently on projects. 
There are many others that may be useful on certain projects or 
in some application areas.
18. Plan Human Resource Management (Planning) 
the process of identifying and documenting project roles, 
responsibilities, required skills, reporting relationships, and creating a 
staffing management plan. 
The key benefit of it is establishing project roles and responsibilities, 
project organization charts, and the staffing management plan 
including the timetable for staff acquisition and release.
Cont. of Plan Human Resource Management (Planning) 
Matrix-based charts 
A responsibility assignment matrix (RAM) is a grid that shows the 
project resources assigned to each work package. This also ensures 
that there is only one person accountable for any one task. 
One example of a RAM is a RACI (responsible, accountable, consult, 
and inform) chart.
Cont. of Plan Human Resource Management (Planning) 
Resource Histogram

Weitere ähnliche Inhalte

Was ist angesagt?

PMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesPMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesMohamed Loey
 
PMBOK 2008 Map of Processes
PMBOK 2008 Map of ProcessesPMBOK 2008 Map of Processes
PMBOK 2008 Map of ProcessesMurilo Juchem
 
Discovery of Project Management profession based on PMI® PMBOK 6
Discovery of Project Management profession based on PMI® PMBOK 6Discovery of Project Management profession based on PMI® PMBOK 6
Discovery of Project Management profession based on PMI® PMBOK 6Clotilde Mbolo-Eteme, PMP
 
1.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 11.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 1reddvise
 
Pmbok flow 5_process
Pmbok flow 5_processPmbok flow 5_process
Pmbok flow 5_processPedro Arcas
 
PMBOK 5th Edition Project Management Processes and Knowledge Areas
PMBOK 5th Edition Project Management Processes and Knowledge AreasPMBOK 5th Edition Project Management Processes and Knowledge Areas
PMBOK 5th Edition Project Management Processes and Knowledge AreasMr.Sohail Amin
 
Lecture 05:Advanced Project Management PM Processes and Framework
Lecture 05:Advanced Project Management   PM Processes and FrameworkLecture 05:Advanced Project Management   PM Processes and Framework
Lecture 05:Advanced Project Management PM Processes and FrameworkFida Karim 🇵🇰
 
Pm processes, groups and k areas map and domains
Pm processes, groups and k areas map and domainsPm processes, groups and k areas map and domains
Pm processes, groups and k areas map and domainsMannay88
 
PMBoK ed.5 brief overview
PMBoK ed.5 brief overviewPMBoK ed.5 brief overview
PMBoK ed.5 brief overviewOleksiy Rudenko
 
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
PMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHICPMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHIC
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHICJonathan Donado
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementWaleed Elnaggar
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Amr Miqdadi
 
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...Tareq Al-Behairi,PMP,PMI-ACP
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 

Was ist angesagt? (20)

PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 
PMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesPMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management Processes
 
PMBOK 2008 Map of Processes
PMBOK 2008 Map of ProcessesPMBOK 2008 Map of Processes
PMBOK 2008 Map of Processes
 
Discovery of Project Management profession based on PMI® PMBOK 6
Discovery of Project Management profession based on PMI® PMBOK 6Discovery of Project Management profession based on PMI® PMBOK 6
Discovery of Project Management profession based on PMI® PMBOK 6
 
1.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 11.3 project management process groups & knowledge areas 1
1.3 project management process groups & knowledge areas 1
 
Pmbok flow 5_process
Pmbok flow 5_processPmbok flow 5_process
Pmbok flow 5_process
 
PMBOK 5th Edition Project Management Processes and Knowledge Areas
PMBOK 5th Edition Project Management Processes and Knowledge AreasPMBOK 5th Edition Project Management Processes and Knowledge Areas
PMBOK 5th Edition Project Management Processes and Knowledge Areas
 
Lecture 05:Advanced Project Management PM Processes and Framework
Lecture 05:Advanced Project Management   PM Processes and FrameworkLecture 05:Advanced Project Management   PM Processes and Framework
Lecture 05:Advanced Project Management PM Processes and Framework
 
PMP PMBOK5 project management processes
PMP PMBOK5 project management processesPMP PMBOK5 project management processes
PMP PMBOK5 project management processes
 
Pmbok 5 ed diagram
Pmbok 5 ed diagramPmbok 5 ed diagram
Pmbok 5 ed diagram
 
Pm processes, groups and k areas map and domains
Pm processes, groups and k areas map and domainsPm processes, groups and k areas map and domains
Pm processes, groups and k areas map and domains
 
PMBoK ed.5 brief overview
PMBoK ed.5 brief overviewPMBoK ed.5 brief overview
PMBoK ed.5 brief overview
 
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
PMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHICPMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHIC
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
 
Integrating project life cycle with process groups
Integrating project life cycle with process groupsIntegrating project life cycle with process groups
Integrating project life cycle with process groups
 
Pmp in summary
Pmp in summaryPmp in summary
Pmp in summary
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
 
Project Management
Project ManagementProject Management
Project Management
 

Andere mochten auch

Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...GBS PAVONE Groupware GmbH
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project managementPavan Kumar
 
PMI-PBA 商業分析讀書會 20150725
PMI-PBA 商業分析讀書會 20150725PMI-PBA 商業分析讀書會 20150725
PMI-PBA 商業分析讀書會 20150725moris lee
 
Pmp pmbok 5 updates vs pmbok 4
Pmp pmbok 5 updates vs pmbok 4Pmp pmbok 5 updates vs pmbok 4
Pmp pmbok 5 updates vs pmbok 4Hujaj Khan
 
Rohit demo sap ps_module_training
Rohit demo sap ps_module_trainingRohit demo sap ps_module_training
Rohit demo sap ps_module_trainingmultimediasunil
 
PMBOOK 5
PMBOOK 5PMBOOK 5
PMBOOK 5neleka
 
Project management
Project managementProject management
Project managementSameer Kumar
 
PMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridgePMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridgeSaket Bansal
 
Business Analysis Knowledge Areas Big Picture
Business Analysis Knowledge Areas Big PictureBusiness Analysis Knowledge Areas Big Picture
Business Analysis Knowledge Areas Big PictureMostafa Hashkil
 
Program Management Processes Flow in English - 3rd Edition - Simplified Version
Program Management Processes Flow in English - 3rd Edition - Simplified VersionProgram Management Processes Flow in English - 3rd Edition - Simplified Version
Program Management Processes Flow in English - 3rd Edition - Simplified VersionRicardo Viana Vargas
 
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaOnline PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaGlobalSkillup
 

Andere mochten auch (20)

Project Management
Project ManagementProject Management
Project Management
 
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project management
 
PMI-PBA 商業分析讀書會 20150725
PMI-PBA 商業分析讀書會 20150725PMI-PBA 商業分析讀書會 20150725
PMI-PBA 商業分析讀書會 20150725
 
Pmp pmbok 5 updates vs pmbok 4
Pmp pmbok 5 updates vs pmbok 4Pmp pmbok 5 updates vs pmbok 4
Pmp pmbok 5 updates vs pmbok 4
 
Pmp study: time
Pmp study: timePmp study: time
Pmp study: time
 
Rohit demo sap ps_module_training
Rohit demo sap ps_module_trainingRohit demo sap ps_module_training
Rohit demo sap ps_module_training
 
PMBOOK 5
PMBOOK 5PMBOOK 5
PMBOOK 5
 
Project management
Project managementProject management
Project management
 
PMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridgePMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridge
 
Business Analysis Knowledge Areas Big Picture
Business Analysis Knowledge Areas Big PictureBusiness Analysis Knowledge Areas Big Picture
Business Analysis Knowledge Areas Big Picture
 
PMP Certification for Marketers
PMP Certification for MarketersPMP Certification for Marketers
PMP Certification for Marketers
 
Program Management Processes Flow in English - 3rd Edition - Simplified Version
Program Management Processes Flow in English - 3rd Edition - Simplified VersionProgram Management Processes Flow in English - 3rd Edition - Simplified Version
Program Management Processes Flow in English - 3rd Edition - Simplified Version
 
09 project human resources management pmbok 5th
09 project human resources management pmbok 5th09 project human resources management pmbok 5th
09 project human resources management pmbok 5th
 
Pmbok
PmbokPmbok
Pmbok
 
Scrum Cheat Sheet
Scrum Cheat SheetScrum Cheat Sheet
Scrum Cheat Sheet
 
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaOnline PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
 
06 project time management m
06 project time management m06 project time management m
06 project time management m
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Requirements Management
Requirements ManagementRequirements Management
Requirements Management
 

Ähnlich wie PMBOK PROJECT MANAGEMENT GUIDE

The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Managementhatemk
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsAhmed Alageed
 
Planning process group
Planning process groupPlanning process group
Planning process groupMudassir Iqbal
 
Pm610 1103 b-02-schwappach-loren-p1-ip1
Pm610 1103 b-02-schwappach-loren-p1-ip1Pm610 1103 b-02-schwappach-loren-p1-ip1
Pm610 1103 b-02-schwappach-loren-p1-ip1Loren Schwappach
 
Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfHuyNguyen657394
 
ProjectManagementforNGOs
ProjectManagementforNGOsProjectManagementforNGOs
ProjectManagementforNGOswebuploader
 
A project portfolio management capability framework
A project portfolio management capability frameworkA project portfolio management capability framework
A project portfolio management capability frameworkRobert Greca, PMP, SA
 
3 scope Management
3 scope Management 3 scope Management
3 scope Management Qussay Karam
 
Atoha PMPPRO S1 - Foundation.pdf
Atoha PMPPRO S1 - Foundation.pdfAtoha PMPPRO S1 - Foundation.pdf
Atoha PMPPRO S1 - Foundation.pdfLe Duong
 
Project management
Project managementProject management
Project managementBiswa Prusty
 
Project Manager Interview Questions And Answers | PMP Certification Training ...
Project Manager Interview Questions And Answers | PMP Certification Training ...Project Manager Interview Questions And Answers | PMP Certification Training ...
Project Manager Interview Questions And Answers | PMP Certification Training ...Simplilearn
 
209560525-PMP-Study-Sheet.pdf
209560525-PMP-Study-Sheet.pdf209560525-PMP-Study-Sheet.pdf
209560525-PMP-Study-Sheet.pdfUmarFarooq29531
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration managementIrefuser1
 
Project management.docx
Project management.docxProject management.docx
Project management.docxHumaRazi1
 

Ähnlich wie PMBOK PROJECT MANAGEMENT GUIDE (20)

The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
 
Entra lecture6 PM1.pdf
Entra lecture6 PM1.pdfEntra lecture6 PM1.pdf
Entra lecture6 PM1.pdf
 
2) PMT & PIM.pptx
2) PMT & PIM.pptx2) PMT & PIM.pptx
2) PMT & PIM.pptx
 
Day 1 framework
Day 1 frameworkDay 1 framework
Day 1 framework
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes Groups
 
Planning process group
Planning process groupPlanning process group
Planning process group
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
 
Pm610 1103 b-02-schwappach-loren-p1-ip1
Pm610 1103 b-02-schwappach-loren-p1-ip1Pm610 1103 b-02-schwappach-loren-p1-ip1
Pm610 1103 b-02-schwappach-loren-p1-ip1
 
Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdf
 
ProjectManagementforNGOs
ProjectManagementforNGOsProjectManagementforNGOs
ProjectManagementforNGOs
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
A project portfolio management capability framework
A project portfolio management capability frameworkA project portfolio management capability framework
A project portfolio management capability framework
 
041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo
 
3 scope Management
3 scope Management 3 scope Management
3 scope Management
 
Atoha PMPPRO S1 - Foundation.pdf
Atoha PMPPRO S1 - Foundation.pdfAtoha PMPPRO S1 - Foundation.pdf
Atoha PMPPRO S1 - Foundation.pdf
 
Project management
Project managementProject management
Project management
 
Project Manager Interview Questions And Answers | PMP Certification Training ...
Project Manager Interview Questions And Answers | PMP Certification Training ...Project Manager Interview Questions And Answers | PMP Certification Training ...
Project Manager Interview Questions And Answers | PMP Certification Training ...
 
209560525-PMP-Study-Sheet.pdf
209560525-PMP-Study-Sheet.pdf209560525-PMP-Study-Sheet.pdf
209560525-PMP-Study-Sheet.pdf
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
 
Project management.docx
Project management.docxProject management.docx
Project management.docx
 

Kürzlich hochgeladen

Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...anjaliyadav012327
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 

Kürzlich hochgeladen (20)

Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 

PMBOK PROJECT MANAGEMENT GUIDE

  • 1. PROJECT MANAGEMENT As Per (PMI) PMBOK 5th Edition -Five Process Groups -Ten Knowledge Areas -Forty-Seven Processes -Inputs and Outputs -Tools and Techniques -Ethics
  • 2. International Project Management Systems PMI: Project Management Institute was established in America 1984 and this is the one which will be adopted and taught. PRINCE2 : Established in UK in 1989 by information technology company, the system focuses on the private sector institutions. 6σ: Started by Motorola 1986, focusing on the theme of quality for the purpose of access to quality 99.9966%, equivalent to 3.4 defect per million produced units. Agile: Used mainly in software projects and complex projects.
  • 3. What is a PROJECT? A project is a temporary endeavor undertaken to create a unique product, service, or result. The temporary nature of projects indicates that a project has a definite beginning and end. The end is reached when: the project’s objectives have been achieved or when the project is terminated because its objectives will not or cannot be met, or when the need for the project no longer exists.
  • 4. What is Project Management? Project management is the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements. Project management is accomplished through the appropriate application and integration of the 47 logically grouped project management processes, which are categorized into five Process Groups. These five Process Groups are: 1. Initiating, 2. Planning, 3. Executing, 4. Monitoring and Controlling, 5. Closing.
  • 5. Five Process Groups 1. Initiating Process Group. Those processes performed to define a new project or a new phase of an existing project by obtaining authorization to start the project or phase. 2. Planning Process Group. Those processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project was undertaken to achieve. 3. Executing Process Group. Those processes performed to complete the work defined in the project management plan to satisfy the project specifications. 4. Monitoring and Controlling Process Group. Those processes required to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes. 5. Closing Process Group. Those processes performed to finalize all activities across all Process Groups to formally close the project or phase.
  • 6. Life Cycle of Phases or Entire Project
  • 7. Typical Cost and Staffing Levels
  • 8. Risk and uncertainty vs. Changes The cost of change at the early stages is low but in the late stages is very high. The risk at the early stages is high while at the late stages is low.
  • 9. Process Group interact The Process Groups are seldom either discrete or one-time events; they are overlapping activities that occur throughout the project.
  • 10. PROJECT KNOWLEDGE AREAS (KA) Integration management 6 4.1 Develop Project Charter. 4.2 Develop project Mgmt. Plan 4.3 Direct and Manage Project 4.4 work, Monitor and Control Project Work., 4.5 Perform integrate d change control. 4.6 Close Project or Phase. Scope management 6 5.1 Plan Scope Mgmt., 5.2 Collect requirem ents, 5.3 Define Scope 5.4 Create WBS. 5.5 Validate Scope. 5.6 Control Scope. Time management 7 6.1 Plan Schedule Mgmt., 6.2 Define Activities., 6.3 Sequence Activities., 6.4 Estimate Activity Resources. , 6.5 Estimate Activity Durations 6.6 Develop Schedule. 6.7 Control Schedule. Cost management 4 7.1 Plan Cost Mgmt., 7.2 Estimate Costs 7.3 Determi ne Budget. 7.4 Control Costs. Quality management 3 8.1 Plan Quality Mgmt. 8.2 Perform Quality Assurance. 8.3 Control Quality. HR management 4 9.1 Plan HR Mgmt. 9.2 Acquire Project Team., 9.3 Develop Project Team. 9.4 Manage Project Team. Communication management 3 10.1 Plan Commun. Mgmt. 10.2 Manage Commun. 10.3 Control Commun. Risk management 6 11.1 Plan Risk Mgmt., 11.2 Identify Risks., 11.3 Perform Qualitativ e Risk An1a1ly.4s is. Perform Quantitati ve Risk analysis 11.5 Plan Risk Responses. 11.6 Control Risks. Procurement management 4 12.1 Plan Procureme nt Mgmt. 12.2 Conduct Procureme nt. 12.3 Control Procureme nt. 12.4 Close Procureme nt. Stakeholder management 4 13.1 Identify Stakehold ers. 13.2 Plan Stakehold ers Mgmt. 13.3 Manage Stakehold er Engageme nt. 13.4 Control Stakeholde rs Engageme nt.
  • 11. 47 PM Processes Knowledge Areas Process Groups Initiating Process Group Planning Process Group Executing Process Group Monitoring & Controlling Process Group Closing Process Group Project Integration management 4.1 Develop Project Charter. 4.2 Develop project Mgmt. Plan 4.3 Direct and Manage Project work, 4.4 Monitor and Control Project Work., 4.6 Close Project or Phase. 4.5 Perform integrated change control. Project Scope management 5.1 Plan Scope Mgmt., 5.5 Validate Scope. 5.2 Collect requirements, 5.3 Define Scope 5.6 Control Scope. 5.4 Create WBS. Project Time management 6.1 Plan Schedule Mgmt., 6.7 Control Schedule. 6.2 Define Activities., 6.3 Sequence Activities., 6.4 Estimate Activity Resources., 6.5 Estimate Activity Durations 6.6 Develop Schedule. Project Cost management 7.1 Plan Cost Mgmt., 7.2 Estimate Costs 7.4 Control Costs. 7.3 Determine Budget. Project Quality management 8.1 Plan Quality Mgmt. 8.2 Perform Quality Assurance. 8.3 Control Quality. Project Human Resource management 9.1 Plan HR Mgmt. 9.2 Acquire Project Team., 9.3 Develop Project Team. 9.4 Manage Project Team. Project Communication management 10.1 Plan Commun. Mgmt. 10.2 Manage Commun. 10.3 Control Commun. Project Risk management 11.1 Plan Risk Mgmt., 11.6 Control Risks. 11.2 Identify Risks., 11.3 Perform Qualitative Risk Analysis. 11.4 Perform Quantitative Risk analysis 11.5 Plan Risk Responses. Project Procurement management 12.1 Plan Procurement Mgmt. 12.2 Conduct Procurement. 12.3 Control Procurement. 12.4 Close Procurement. Project Stakeholder management 13.1 Identify Stakeholders. 13.2 Plan Stakeholders Mgmt. 13.3 Manage Stakeholder Engagement. 13.4 Control Stakeholders Engagement.
  • 12.
  • 13. 1. Develop Project Charter (Initiation) Develop Project Charter is the process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. The key benefit of this process is a well-defined project start and project boundaries, creation of a formal record of the project, and a direct way for senior management to formally accept and commit to the project.
  • 14. 2. Identify Stakeholders (Initiation) Identify Stakeholders is the process of identifying the people, groups, or organizations that could impact or be impacted by a decision, activity, or outcome of the project, analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success.
  • 15. Cont. of Identify Stakeholders (Initiation) Power/ interest Grid •Interactive communication •Push communication •Pull communication
  • 16. 3. Develop Project Management Plan (Integration Planning) Develop Project Management Plan is the process of defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan. The key benefit of this process is a central document that defines the basis of all project work.
  • 17. Project Management Plan The project management plan is the document that describes how the project will be executed, monitored, and controlled. It integrates and consolidates all of the subsidiary plans and baselines from the planning processes. Project baselines include, but are not limited to: •Scope baseline •Schedule baseline •Cost baseline Subsidiary plans include, but are not limited to: •Scope management plan •Requirements management plan •Schedule management plan •Cost management plan •Quality management plan •Process improvement plan •Human resource management plan •Communications management plan •Risk management plan •Procurement management plan •Stakeholder management plan
  • 18. Among other things, the project management plan may also include the following: •Life cycle selected for the project and the processes that will be applied to each phase; •Details of the tailoring decisions specified by the project management team as follows: •Project management processes selected by the project management team, •Level of implementation for each selected process, •Descriptions of the tools and techniques to be used for accomplishing those processes, •Description of how the selected processes will be used to manage the specific project, including the dependencies and interactions among those processes and the essential inputs and outputs. •Description of how work will be executed to accomplish the project objectives; •Change management plan that documents how changes will be monitored and controlled; •Configuration management plan that documents how configuration management will be performed; •Description of how the integrity of the project baselines will be maintained; •Requirements and techniques for communication among stakeholders; •Key management reviews for content, the extent of, and timing to address, open issues and pending decisions.
  • 19. Project Management Plan VS Project Documents
  • 20. 4. Plan Scope Management (Scope Planning) Plan Scope Management is the process of creating a scope management plan that documents how the project scope will be defined, validated, and controlled. The key benefit of this process is that it provides guidance and direction on how scope will be managed throughout the project.
  • 21. 5. Collect requirements (Scope Planning) Collect Requirements is the process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives. The key benefit of this process is that it provides the basis for defining and managing the project scope including product scope.
  • 22. These classifications of requirements include: •Business requirements, •Stakeholder requirements, •Solution requirements, Solution requirements are further grouped into functional and nonfunctional requirements: •Functional requirements •Nonfunctional requirements •Project requirements, •Transition Requirement, “as-is” state to “to-be”. •Quality requirements.
  • 23. 6. Define Scope (Scope Planning) Define Scope is the process of developing a detailed description of the project and product. The key benefit of this process is that it describes the project, service, or result boundaries by defining which of the requirements collected will be included in and excluded from the project scope. During project planning, the project scope is defined and described with greater specificity as more information about the project is known.
  • 24. 7. Create WBS (Scope Planning) Create WBS is the process of subdividing project deliverables and project work into smaller, more manageable components. The key benefit of this process is that it provides a structured vision of what has to be delivered. The WBS organizes and defines the total scope of the project, and represents the work specified in the current approved project scope statement.
  • 25. Samples of WBS (Scope Planning)
  • 26. Samples of WBS (Scope Planning) Third Level Forth Level Second Level First Level
  • 27. Samples of WBS (Scope Planning) Third Level Forth Level Second Level First Level
  • 28. 8. Plan Schedule Management(Time Planning) Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule. The key benefit of this process is that it provides guidance and direction on how the project schedule will be managed throughout the project. Analytic techniques like which of these? Traditional, WBS, Pert, Project Diagram, MS Project, Primavera, EVM, Tracking …etc.
  • 29. 9. Define Activities (Time Planning) Define Activities is the process of identifying and documenting the specific actions to be performed to produce the project deliverables. The key benefit of this process is to break down work packages into activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work. Decomposition and Rolling wave are tools for pre or continuous planning depending on the nature of the project. Milestones are ZERO duration tasks used as reminders!
  • 30. 10. Sequence Activities (Time Planning) Sequence Activities is the process of identifying and documenting relationships among the project activities. The key benefit of this process is that it defines the logical sequence of work to obtain the greatest efficiency given all project constraints.
  • 31. Cont. of Sequence Activities (Time Planning) Every activity and milestone except the first and last should be connected to at least one predecessor with a finish-to-start or start-to-start logical relationship and at least one successor with a finish-to-start or finish-to finish logical relationship. Logical relationships should be designed to create a realistic project schedule. It may be necessary to use lead or lag time between activities to support a realistic and achievable project schedule. Sequencing can be performed by using project management software or by using manual or automated techniques.
  • 32. Cont. of Sequence Activities (Time Planning) PROJECT DIAGRAM- CRITICAL PATH METHOD (CPM) FW= ES+ Duration (lead-, lag +) Choose the Max. BW= LF- Duration (lead+, lag -) Choose the Min.
  • 33. Cont. of Sequence Activities (Time Planning) PROJECT DIAGRAM- CRITICAL PATH METHOD (CPM) FW= ES+ Duration (lead-, lag +) Choose the Max. BW= LF- Duration (lead+, lag -) Choose the Min. CPM
  • 34. 11. Estimate Activity Resources (Time Planning) process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity. The key benefit of this process is that it identifies the type, quantity, and characteristics of resources required to complete the activity which allows more accurate cost and duration estimates.
  • 35. Cont. of Estimate Activity Resources (Time Planning) The Estimate Activity Resources process is closely coordinated with the Estimate Costs process. For example: A construction project team will need to be familiar with local building codes. Such knowledge is often readily available from local sellers. However, if the local labor pool lacks experience with unusual or specialized construction techniques, the additional cost for a consultant may be the most effective way to secure knowledge of the local building codes. An automotive design team will need to be familiar with the latest in automated assembly techniques. The requisite knowledge might be obtained by hiring a consultant, by sending a designer to a seminar on robotics, or by including someone from manufacturing as a member of the project team.
  • 36. 12. Estimate Activity Durations (Time Planning) Estimate Activity Durations is the process of estimating the number of work periods needed to complete individual activities with estimated resources. The key benefit of this process is that it provides the amount of time each activity will take to complete, which is a major input into the Develop Schedule process.
  • 37. Cont. of Estimate Activity Durations (Time Planning) •uses information on activity scope of work, required resource types, estimated resource quantities, and resource calendars. The inputs of the estimates of activity duration originate from the person (SME) or group on the project team who is most familiar with the nature of the work in the specific activity. The duration estimate is progressively elaborated, and the process considers the quality and availability of the input data. For example, as more detailed and precise data is available about the project engineering and design work, the accuracy of the duration estimates improves. Thus, the duration estimate can be assumed to be progressively more accurate and of better quality. •are used to approximate the number of work periods (activity duration) needed to complete the activity using the appropriate project and resource calendars. All data and assumptions that support duration estimating are documented for each estimate of activity duration.
  • 38. 13. Develop Schedule (Time Planning) Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model. The key benefit of this process is that by entering schedule activities, durations, resources, resource availabilities, and logical relationships into the scheduling tool, it generates a schedule model with planned dates for completing project activities.
  • 39. Cont. of Develop Schedule (Time Planning) •Developing an acceptable project schedule is often an iterative process. The schedule model is used to determine the planned start and finish dates for project activities and milestones based on the accuracy of the inputs. •Schedule development can require the review and revision of duration estimates and resource estimates to create the project schedule model to establish an approved project schedule that can serve as a baseline to track progress. •Once the activity start and finish dates have been determined, it is common to have project staff assigned to the activities review their assigned activities and confirm that the start and finish dates present no conflict with resource calendars or assigned activities in other projects or tasks and thus are still valid.
  • 40. 14. Plan Cost Management (Cost Planning) the process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs. The key benefit of this process is that it provides guidance and direction on how the project costs will be managed throughout the project.
  • 41. 15. Estimate Costs (Cost Planning) Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of this process is that it determines the amount of cost required to complete project work.
  • 42. Cont. of Estimate Costs (Cost Planning) Cost tradeoffs and risks should be considered, such as make versus buy, buy versus lease, and the sharing of resources in order to achieve optimal costs for the project. Cost estimates are generally expressed in units of some currency (i.e., dollars, euros, yen, etc.), although in some instances other units of measure, such as staff hours or staff days, are used to facilitate comparisons by eliminating the effects of currency fluctuations. The accuracy of a project estimate will increase as the project progresses through the project life cycle. For example, a project in the initiation phase may have a rough order of magnitude (ROM) estimate in the range of −25% to +75%. Later in the project, as more information is known, definitive estimates could narrow the range of accuracy to -5% to +10%. In some organizations, there are guidelines for when such refinements can be made and the degree of confidence or accuracy that is expected.
  • 43. Cont. of Estimate Costs (Cost Planning) This guideline provides an overview of estimating methods for generating detailed project schedules. It includes a brief description of the purpose, goals, and process of estimating, as well as specific estimating techniques for the project manager and project team. Methods of estimating covered in this guideline are: •Historical Data •Decomposition Process •Brainstorming meetings •Expert Judgment •Delphi Method •Network Diagrams - PERT, CPM (ADM), GERT, etc. •Rule of Thumb registries and charts •"Rolling wave" or "iterative" estimating
  • 44. 16. Determine Budget(Cost Planning) process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. The key benefit of this process is that it determines the cost baseline against which project performance can be monitored and controlled.
  • 45. Cont. of Determine Budget(Cost Planning)
  • 46. Cont. of Determine Budget(Cost Planning)
  • 47. 18. Plan Quality Management (Quality Planning) the process of identifying quality requirements and/or standards for the project and its deliverables, and documenting how the project will demonstrate compliance with relevant quality requirements. The key benefit of this process is that it provides guidance and direction on how quality will be managed and validated throughout the project.
  • 48. Cont. of Plan Quality Management (Quality Planning) Quality planning should be performed in parallel with the other planning processes. For example, proposed changes in the deliverables to meet identified quality standards may require: • cost or •schedule adjustments and • a detailed risk analysis of the impact to plans. The quality planning techniques discussed here are those used most frequently on projects. There are many others that may be useful on certain projects or in some application areas.
  • 49. 18. Plan Human Resource Management (Planning) the process of identifying and documenting project roles, responsibilities, required skills, reporting relationships, and creating a staffing management plan. The key benefit of it is establishing project roles and responsibilities, project organization charts, and the staffing management plan including the timetable for staff acquisition and release.
  • 50. Cont. of Plan Human Resource Management (Planning) Matrix-based charts A responsibility assignment matrix (RAM) is a grid that shows the project resources assigned to each work package. This also ensures that there is only one person accountable for any one task. One example of a RAM is a RACI (responsible, accountable, consult, and inform) chart.
  • 51. Cont. of Plan Human Resource Management (Planning) Resource Histogram