SlideShare ist ein Scribd-Unternehmen logo
1 von 19
Downloaden Sie, um offline zu lesen
 
 
Dollymount Flood Wall 
External Review 
 
Draft Report 
 
Prepared  
By 
Dr. Jimmy Murphy 
MaREI Centre, UCC 
 
February 2016 
Dollymount	Flood	Wall	– External	Review	 2016
 
2 
 
 
Table	of	Contents	
Introduction ............................................................................................................................................ 3 
Expert Reviewer Profile........................................................................................................................... 4 
Site visit. .................................................................................................................................................. 4 
Public Input ............................................................................................................................................. 4 
Design Assessment .................................................................................................................................. 4 
Extreme Water Levels ......................................................................................................................... 4 
Sea Level Rise (SLR) ............................................................................................................................. 6 
Wave Conditions ................................................................................................................................. 7 
Minimum Freeboard ......................................................................................................................... 12 
Recommended Wall Level .................................................................................................................... 12 
Alternative Wall Solutions .................................................................................................................... 12 
Demountable barriers ....................................................................................................................... 13 
Glass Walls ........................................................................................................................................ 13 
Increase Road Levels ......................................................................................................................... 14 
Water Level Control .......................................................................................................................... 14 
Modify Design Criteria ...................................................................................................................... 14 
Crest Re‐design ................................................................................................................................. 14 
Conclusion and Recommendation ........................................................................................................ 15 
Documents and correspondence reviewed .......................................................................................... 16 
Appendix 1 – Review Brief .................................................................................................................... 18 
 
 
Dollymount	Flood	Wall	– External	Review	 2016
 
3 
 
 
Introduction	
This review of the wall height of the Dollymount promenade was carried out to assess if the current 
crest level of 4.25m ODM (Ordnance Datum Malin Head) is appropriate for this location.  A number 
of documents relevant to the promenade design and the determination of extreme values for the 
Dublin  Bay  area  were  assessed  in  this  review.    A  listing  of  all  documents,  communications, 
presentations etc used in this review are listed at the end of this report.     
The basis of design of the wall was to protect against a two hundred year event in relation to water 
levels and winds in Dublin Bay and to provide a level of safety against anticipated sea level rise.  The 
final height of the wall is made up of 4 components as shown in figure 1 [7].  The initial designed 
level was 4.6m ODM however this was reduced to lessen the visual impact.  The resultant wall height 
of 4.25m ODM is considered an interim solution which may, depending on the rate of sea level rise, 
need  to  be  increased  to  the  original  designed  values  in  the  future.    In  relation  to  the  existing 
defences the new wall height ranges from being equal in height to being at a maximum 0.85m higher 
than existing defences.  The impact of the increased height is minimal to pedestrians and cyclists 
using the promenade and slightly restricts views of the lagoon from the footpath on the St Annes 
Park side.  It does however restrict views in places from standard cars travelling along the road.   
The primary issue of public concern is in relation to the height of the wall, that it is not in line with 
other flood defences in Dublin and it obscures views of Bull Island.   The analysis carried out in this 
review only considers the appropriateness of the design decisions made in terms of the wall height 
and examines other options to provide the same level of protection.  No comment is made about 
any other flood scheme in the Dublin area as that is not part of the current remit.  
  
 
Figure 1 Designed wall Configuration [7] 
Dollymount	Flood	Wall	– External	Review	 2016
 
4 
 
Expert	Reviewer	Profile	
Dr Jimmy Murphy is a senior Research Engineer in the MaREI Centre in University College Cork and 
has over 20 years experience in marine projects in relation to the design and evaluation of coastal 
and  harbour  structures.    This  work  involves  the  use  of  such  tools  as  physical  model  testing, 
numerical modelling and field measurements to optimise the layout and design of marine structures.   
He lectures in the School of Engineering in UCC on the subjects of Environmental Hydrodynamics 
and  Harbour  and  Coastal  Engineering.    In  addition  he  supervises  a  number  of  PhD  and  masters 
students and has a number of publications in the areas of coastal engineering and ocean energy.   
Site	visit.	
A site visit took place on Friday 18th
 December 2015 where in the presence of Mr. Gerard O’Connell 
from Dublin City Council (DCC) the promenade scheme and the wall design were explained.  Where 
access was available we examined the wall and drove along the section of road most affected by its 
construction.  We also visited the Bull Island biosphere via both the causeway and wooden bridge 
and generally discussed flood defence levels in the local area and the impacts of previous extreme 
events.    This  visit  clarified  the  issues  in  relation  to  the  visual  impacts  and  the  flood  defence 
requirement.    
Public	Input	
I have reviewed officially submitted documents from the public ([15] and [16]) as well as kept in 
touch with media reports ([18], [19] and [20]) while working on this review.  This has highlighted to 
me  the  importance  of  this  issue  to  the  local  community  and  the  connection  they  have  with  the 
physical environment.  Thus I feel that I am aware of the significant public concerns in relation to the 
flood wall although many issues raised are outside the remit of my review (as outlined in Appendix 
1), which focuses on the engineering justification for the current wall height.  After submission of 
this draft report it is planned that I meet with DCC and public groups and subsequently finalise the 
document.    
Design	Assessment	
This section considers each of the elements that determine the wall height.  I should state to begin 
with that even though all the relevant information was available, I did not find a clear consistent 
design document and the information provided, as used to determine the wall height, sometimes 
differed between documents, i.e. [4] and [7].   
Extreme	Water	Levels	
The  extreme  water  levels  are  the  most  dominant  component  in  terms  of  determining  the  wall 
height. In Figure 1 this has a value of 3.2m ODM (in this report I will only use Ordnance Datum Malin 
as the reference for the vertical datum) which represents the 200 year return condition.  Extreme 
water levels are made up of a combination of astronomical and meteorological (surge) components, 
the former can be predicted well in advance whilst the latter is dependent on the weather.  If the 
astronomical component is first considered it can be seen from Figure 2 (column labelled mODM) 
that the design water level for the wall is 1.21m higher than the highest astronomical tide (HAT).  
Dollymount	Flood	Wall	– External	Review	 2016
 
5 
 
This  indicates that there  is  a  high surge component to the water levels  in  Dublin Bay and this  is 
borne out by the number of extreme water levels in recent years.  The 2002 event had a water level 
of 2.97m ODM twhich was the highest ever recorded water level up to that point whilst the tide of 
3rd January 2014 reached a recorded level of 3.014m ODM at Alexandra basin in the Docklands with 
unconfirmed information of a level of , 3.047m ODM at Dollymount.  A study undertaken by Royal 
Haskoning [9] after the extreme event of 2002 showed that the 200 year event had a value of 3.13m 
ODM which differs slightly from the value indicated in Figure 1.  A re‐evaluation of extreme levels in 
2015  [5]  using  the  most  up  to  date  data  showed  that  the  magnitudes  were  largely  unchanged.  
However when taking account of sea level rise in the period between 2003‐2015 and more accurate 
tide level data there is an adjustment of the 200 year water level to 3.25m ODM.  This is stated as 
follows in [5]; 
The residual mean water level of the tidal analysis gives an indication of the changes in 
Mean  Sea  Level  (MSL)  that  have  occurred  over  the  years.  Based  on  the  additional  tide 
gauge  data,  an  increase  of  0.13m  was  observed  in  the  last  13  years  (Svasek  Hydraulics 
2015) 
Although the analysis has shown that to date in Dublin the extreme water levels are stable there is a 
risk  that  they  could  change  due  to  climate  influences.    Changes  in  storm  duration,  intensity  and 
frequency  as  well  as  sea  level  rise  can  contribute  to  surge  levels  increasing  and  this  has  been 
highlighted by the IPCC.  The text below is taken from [14].  
In summary, dynamical and statistical methods on regional scales show that it is very likely 
that there will be an increase in the occurrence of future sea level extremes in some regions by 
2100, with a likely increase in the early 21st century. The combined effects of MSL rise and 
changes in storminess will affect future extremes. There is high confidence that extremes will 
increase with MSL rise yet there is low confidence in region‐specific projections in storminess 
and storm 
Gregory [13] also concludes that  
It is very likely that there will be a significant increase in the occurrence of future sea level 
extremes. 
It is not suggested that any change be made to the extreme values due to possible future changes 
but in terms of the wall height the freeboard allowance can incorporate this risk. 
The 200 year design criterion for coastal flood defences is standard for Ireland and I am satisfied that 
the data available and methods of analysis used were satisfactory for determining the level to be 
used for the flood defence wall.  The most relevant value to use in this case would be 3.25m ODM 
and not the 3.13m ODM or the 3.2m ODM values that are indicated in some documents ([4] and [7]).      
Dollymount	Flood	Wall	– External	Review	 2016
 
6 
 
 
Figure 2 Dublin (North Wall) Tidal Levels [4] 
Sea	Level	Rise	(SLR)	
There are no fixed rules in terms of the application of a sea level rise allowance in the design of 
coastal structures in Ireland.  I have experience from various projects where values chosen range 
from 0 – 1m with the most common value used being 0.5m.  The choice is determined by what the 
client or the design engineer considers to be the most appropriate.  There is a lot of uncertainty in 
terms of the long term rate of SLR but best estimates from the IPCC research indicate that it is very 
likely  that  the  21st‐century  mean  rate  of  SLR  will  exceed  that  of  1971‐2010.    Figure  3  indicates 
possible  SLR  based  on  different  climate  parameters.    Given  that  there  is  clear  evidence  that  sea 
levels are rising and for Dublin Bay, taking land submergence into account, the rate is greater than 
4mm/year it is important that an allowance be made in any flood defence design.   
In 2011 the OPW issued guidelines whereby a sea level rise of 0.5 metres could be used when using 
Mid‐Range  Future  Scenario  (MRFS)  and  a  sea  level  rise  of  1  meter  for  High  End  Future  Scenario 
(HEFS)  [5].  In  relation  to  Dublin  Bay  the  Roughan  O  Donovan  report  [4]  base  the  sea  level  rise 
allowance  on  the  findings  from  the  Intergovernmental  Panel  on  Climate  Change  (IPCC,  2007).    A 
recommendation for sea level rise of 0.4m is used for the year 2100.  Therefore the combination of 
sea level rise and extreme water levels taken from [4] gives a value of 3.53m ODM which is lower 
than  the  value  of  3.7m  ODM  taken  from  Figure  1.    The  Royal  Haskoning  report  [5]  provide  a 
combined value of 3.76m ODM.   
My assessment for a design horizon up to 2100 and using a 200 year extreme level of 3.25m ODM 
(which  includes  SLR  up  to  2015)  is  that  a  value  of  0.4m  for  SLR  would  be  appropriate.    This 
corresponds to an average sea level rise of about 4.7mm/year which is higher than the current rate.  
Combining the extreme water level with sea level rise gives a total water level of 3.66m ODM.  This 
value is broadly in line with the value provided in Figure 1.    
 
Dollymount	Flood	Wall	– External	Review	 2016
 
7 
 
 
Figure 3 Sea Level Rise Trends [13] 
Wave	Conditions	
The analysis of wave conditions for the determination of design conditions was not fully clear so I 
carried  out  a  separate  analysis  which  will  be  presented  in  this  report.    The  Roughan  O  Donovan 
report [4] indicate that given the restricted nature of the fetch (distance over which the wind blows) 
and the shelter provided by local topography it is likely that the 1 year return significant wave height 
(Hs) values along the Dollymount frontage to be of the order of 0.47m with a potential maximum 
wave height of 0.8m .  My assessment would be that such wave magnitudes are very high in relation 
to the length of the fetch and may not consider that direction of propagation as this has a significant 
influence on how the waves interact with the flood defence.  For instance the highest waves are 
likely to be generated along the longest fetch which is orientated in a circa SW‐NE direction.  Waves 
propagating in this direction will be confined by the wall but will not break or reflect from it.  This is 
different from waves generated from easterly winds which are directly incident on the wave wall but 
are likely to be much reduced in height due to the shorter fetch.  The analysis to clarify the wave 
conditions incident on the wall used two different sets of empirical formulae for determining the Hs 
and Tp (peak wave period).  The first method is as outlined in the Coastal Engineering Manual whilst 
the second formulation was developed by Donegan and Walsh.    
Input information includes wind speed, fetch length and water depths and which this information 
the  design  wave  conditions  on  the  wave  wall  can  be  is  determined.    In  this  analysis  three  wind 
directions were considered as can be seen from figure 4‐6.  The fetch lengths used in each case are 
shown in these figures and in the analysis the average water depth over the fetch for a 3.66m ODM 
water level was chosen as 3.0m.  Also I used the same wind speeds for all directions as used by [4] 
even though there are slight variations that I considered not to be significant. I should note that 
Dollymount	Flood	Wall	– External	Review	 2016
 
8 
 
there is a high level of uncertainty regarding determining the wave conditions in such enclosed and 
restricted short fetches and some wave measurement would be very useful.   
If waves that propagate towards the wall are first considered (Table 1) then it can be seen that the 1 
year significant wave height (corresponding to the 18.2m/s wind speed) is of the order of 0.3m with 
an associated wave period of 1.7s.  These waves are relatively minor in terms of their size and do not 
represent a major loading on the wall structure.  The manner in which these waves interact with the 
wall is important as because they are low in height and short in length they will not break against the 
wall but reflect from it.  Therefore overtopping from wave breaking should not generally occur for 
this structure although it would be likely that the high wind speeds would lead to whitecapping of 
the waves.  Previous physical model testing on vertical structures that I have undertaken indicated 
whilst the waves are largely reflective occasional breaking can occur that can lead to overtopping.    
When a non breaking wave interacts with a vertical wall a standing wave can be established in front 
of the structure which means that wave oscillations at the wall increases and are doubled in many 
cases (known as clapotis).  Therefore instead of the water level oscillating around the mean level by 
0.15m (for a 0.3m wave) it now oscillates with an amplitude of 0.3m.  Therefore a minimum of 0.3m 
is required to be added to the wall height to ensure that water does not consistently overtop the 
structure.  This allowance is also sufficient to cater for waves propagating along the length of the 
lagoon as their maximum height of 0.47m (Table 3) results in an amplitude of oscillation of 0.235m.  
Table 3 also shows that the causeway experiences the largest waves generated in the lagoon.  
Therefore the recommended allowance for wave action on the wall is 0.3m    
Dollymount	Flood	Wall	– External	Review	 2016
 
9 
 
 
Figure 4 Fetch length 1 [11] 
 
Table 1 Calculated Wave Conditions for fetch 1 
CEM Donegan
Wind SpeeDepth (m)Fetch (m) Hs (m) Tp (s) Hs (m) Tp (s)
18.2 3 833 0.29 2.06 0.30 1.71
23.4 3 833 0.39 2.25 0.38 1.89
27.3 3 833 0.47 2.37 0.45 2.01
29 3 833 0.51 2.42 0.48 2.06
30.7 3 833 0.54 2.46 0.50 2.11
32.9 3 833 0.59 2.52 0.54 2.16
Dollymount	Flood	Wall	– External	Review	 2016
 
10 
 
 
Figure 5 Fetch length 2 [11] 
 
Table 2 Calculated Wave Conditions for fetch 2 
 
CEM Donegan
Wind SpeeDepth (m)Fetch (m) Hs (m) Tp (s) Hs (m) Tp (s)
18.2 3 671 0.26 2.06 0.27 1.60
23.4 3 671 0.35 2.25 0.34 1.77
27.3 3 671 0.42 2.37 0.40 1.88
29 3 671 0.46 2.42 0.43 1.93
30.7 3 671 0.49 2.46 0.45 1.97
32.9 3 671 0.53 2.52 0.48 2.03
Dollymount	Flood	Wall	– External	Review	 2016
 
11 
 
 
Figure 6 Fetch length 3 [11] 
 
 
Table 3 Calculated Wave Conditions for fetch 3 
 
CEM Donegan
Wind SpeeDepth (m)Fetch (m) Hs (m) Tp (s) Hs (m) Tp (s)
18.2 3 2040 0.45 2.06 0.47 2.23
23.4 3 2040 0.61 2.25 0.60 2.47
27.3 3 2040 0.74 2.37 0.70 2.63
29 3 2040 0.79 2.42 0.74 2.69
30.7 3 2040 0.85 2.46 0.79 2.75
32.9 3 2040 0.93 2.52 0.84 2.83
Dollymount	Flood	Wall	– External	Review	 2016
 
12 
 
Minimum	Freeboard			
Freeboard is required to provide a level of safety in the design particularly when there is uncertainty 
regarding  input  values  that  were  used.    The  application  of  safety  factors  is  standard  engineering 
practice so it is justifiable to use them for the wall design.   In this case the main uncertainty relates 
to the determination of the design wave conditions and their interaction with the wall.   Examples of 
uncertainties are provided below; 
 Given that the wind speed used to generate the wave conditions is the average hourly value 
and the short length of this fetch would indicate that the 10 minute wind speed would be 
more appropriate to use.  Therefore wave conditions are expected to be slightly higher than 
indicated.   
 The exact nature of wave interaction with the wall is dependent on a number of factors that 
cannot  be  fully  quantified.    In  this  case  field  monitoring  should  be  carried  out  and  also 
physical modelling testing in order to better understand what is happening.   
 Uncertainty regarding extreme water levels as previously outlined 
I consider a value of 0.3m freeboard as used in the design to be appropriate.  Generally in exposed 
coastal locations higher freeboards are required mainly to cater for wave action.  Given that wave 
conditions  are  benign  in  the  lagoon  and  the  type  of  wave  interaction  with  the  wall  this  level  of 
freeboard is acceptable.   
Recommended	Wall	Level	
The overall assessment of the wall height is made up of the following components 
Extreme water level (200 yr)    3.25m  
Sea Level Rise      0.4m  
Wave Action      0.3m  
Freeboard      0.3m  
Total Height Required    4.25m ODM 
Therefore  I  consider  the  selected  wall  height  of  4.25m  ODM  to  be  appropriate  in  terms  of  the 
criteria set out for the design. It is interesting that even though the components that makeup the 
wall height in this review differ from the design the overall value remains the same.   
Alternative	Wall	Solutions		
The  previous  analysis  indicates  that  the  currently  designed  wall  height  is  justified  based  on  the 
information on various analyses of the extreme conditions and the design criteria that was used.  
This section outlines possible alternative solutions that would not have the same visual impact but 
would in general provide the same level of protection from flooding.  It would be the intention that 
such solutions if implemented will be applied along a 450m section of the road where the maximum 
increase in wall height is 0.69m.  The introduction of these options is not a recommendation for their 
use as each would require full design and planning.     
Dollymount	Flood	Wall	– External	Review	 2016
 
13 
 
Demountable	barriers	
Demountable barriers are a well proven solution and have been successfully used in a number of 
flood schemes in Ireland.  There are a number of different types of solutions and a design study 
would be required to determine which would be most appropriate for this site and how it could be 
incorporated into the existing structure.  These barriers would need new planning permission and 
the  costs  would  be  relatively  high  as  they  would  need  to  include  modifying  the  existing  wall, 
purchasing  the  barriers  and  providing  a  storage  location.    Also  their  erection  would  require 
significant  resources  during  a  flood  event  from  DCC  as  this  scheme  would  double  Dublin’s  total 
length of such barriers.   
Glass	Walls	
Constructing all or part of the wall using glass panels has been suggested as a potential option to 
preserving the views from the road.  To date glass walls have been used primarily in riverine and 
sheltered  estuarine  locations  and  there  are  examples  in  Germany,  UK  and  Ireland  with  the 
Waterford City Flood Alleviation Scheme the most commonly referenced site in Ireland.  There is no 
doubt  that  glass  panels  could  be  designed  to work  for  the Dollymount  site  even  though  there  is 
limited knowledge as to how they would behaviour when subject to regular wave action.  Although 
this should not really be an issue as, if only the top 0.5m of the wall was glass then wave action at 
this level would be rare.  There are other factors that should be taken into consideration in relation 
to glass walls and these include  
 Cost  –  The  overall  cost  of  glass  panel  system  can  wary  depending  on  the  particular 
application but figures up to €5k per linear meter have been suggested.   
 Maintenance – They would require regular cleaning  
 Possible Vandalism in the form of breaking and graffiti  
 Environmental impacts – it is possible that reflections and glare from the glass may have a 
negative impact on this sensitive costal ecosystem and this would need to be investigated.    
 
Figure 7 Glass Floodwall in Waterford City [10] 
Dollymount	Flood	Wall	– External	Review	 2016
 
14 
 
Increase	Road	Levels	
This relatively simple solution would involve raising the road level such that the views from the road 
would be at least partially restored.  Given an average eye height for car drivers as being 1.1m then 
the road level would need to be above 3.15m ODM to enable views beyond the wall.  DCC state that 
this option has been already assessed at an area Committee briefing and it was estimated that it 
would cost of the order of €0.5m which was considered to be impractical.   
Water	Level	Control	
This  solution  would  involve  controlling  the  level  of  water  entering  the  Dollymount  lagoon  by 
constructing a barrier type structure at the Dollymount bridge location.  This would be  activated 
during extreme events and would prevent waters from reaching high levels in the lagoon and so 
reduce the required height of the wall.  Such a scheme would be expensive, require planning and 
potentially  be  disruptive  to  the  existing  natural  environment  so  is  unlikely  to  be  a  feasible 
alternative.    
Modify	Design	Criteria	
An important point relates to the use of the 200 year condition in the design process.   This is a very 
extreme value and a level that has never been recorded in Dublin Bay in over 90 years of records.  I 
queried DCC regarding the use of this return period in this case.  For instance the 100 year extreme 
water level is 0.1m lower and if used would have a positive impact in terms of the visual aspects.  
DCC responded by stating that their advice from the OPW is that coastal flood defence designs as 
undertaken  by  them  should  be  to  the  200  year  return  period  and  this  is  in  line  with  all  recent 
schemes  designed  in  Dublin.    Their  view  is  that  damages  from  tidal  flooding  are  generally 
significantly worse than river flooding for a number of reasons including associated wave action, salt 
water content, ground water contamination, overloading of combined sewer networks, etc. 
A  200  year  design  event  could  occur  due  to  a  number  of  different  combination  of  events  –  the 
design case chosen used the 200 year water level with the 1 year wave height as this was found to 
give the most severe loading on the structure with respect to flood risk.  But other cases studied 
included the 10 year water level with 10 year wave condition and the 50 year wave with 1 year 
water level [4].  These obviously would have a lesser impact in terms of the height of the wall but as 
is standard engineering design practice the most severe condition was chosen.  My view is that the 
water level should be the dominant criteria as wave conditions are relatively benign at this site.  The 
Roughan O Donovan report [4] does say that the design horizon of the wall is 2100 and from which 
sea level rise adjustment values were determined.   Given that this is the case it should be assessed 
whether a 100 year design condition could be used instead of the 200 year.   
The other option for modifying the design criteria is in relation to the sea level rise allowance.  Given 
that measured water levels as recent as 2014 were above 3.0m ODM there may be more scope in 
reducing the 0.4m allowance then changing the 200yr extreme level design.  Therefore if the SLR 
element of the wall height was reduced by between 0.1‐0.2m and DCC carried out frequent reviews 
based on extreme water levels and sea level rise rates then this could provide a solution.   
Crest	Re‐design	
It was stated previously that waves will not consistently overtop the wall during a storm event but it 
will occur occasionally.  The current crest design  is not optimum  for minimising overtopping  and 
Dollymount	Flood	Wall	– External	Review	 2016
 
15 
 
could be modified.  Figure 8 below shows the type of crest configuration that is often used in coastal 
structures to reduce overtopping volumes and it may be possible to shape the capping piece of the 
Dollymount  wall  in  this  manner.    This  would  improve  the  performance  of  the  wall  against  wave 
action and could delay the ultimate planned increase of the wall to 4.6m ODM.   
 
Figure 8 Example of Crest Detail for vertical wall [12] 
Conclusion	and	Recommendation	
The analysis that I have carried out show that the current wall height (4.25m ODM) is justified based 
on the design criteria used even though the components that make up this height differ slightly from 
indicated values.   
This  still  leaves  the  issue  with  regards  to  the  loss  of  visual  amenity  and  in  this  review  I  have 
suggested a number of solutions.  The majority of solutions considered have significant implications 
in terms of costs, planning requirements and environmental effects and would be unlikely to resolve 
the  immediate  issue.    Therefore  the  recommendation  that  I  would  make  is  that  DCC  review  the 
design criteria and in particular the SLR allowance included in the design.  My suggestion is that a 
value in the range of 0.2‐0.3m be used (instead of 0.4) which would mean that by current mid range 
SLR scenarios the wall height should still be sufficient to provide flood protect for at least 50 years.  
This proposed adjustment of the wall height should only be applied at locations where the visual 
amenity is most affected as agreed between DCC and local groups.  If this solution is implemented 
then DCC would need to frequently review both extreme water levels and sea level rise rates and 
have a plan in place for increasing the wall height to ensure that there is a sufficient level of flood 
protection.   
Dollymount	Flood	Wall	– External	Review	 2016
 
16 
 
Documents	and	correspondence	reviewed	
I have listed below all documentation that was made available to me by DCC plus additional items 
that I used as part of the review.  
[1] Dollymount Promenade and Flood Protection Project  ‐ Historic Evolution and Geomorphologic 
Assessment (2009) 
[2]  Dollymount  Promenade  and  Flood  Protection  Project;  Historic  Evolution  and  Geomorphologic 
Assessment, Roughan O'Donovan / Dublin City Council, 21 September 2009, Final Report 
[3]  Dollymount  Promenade  and  Flood  Protection  Project;  Hydrodynamic  Modelling  Report, 
September 2009, Final Report, 9T3615 
[4] Dollymount Promenade and Flood Protection Project ‐ Coastal and Flood Risk Engineering Design 
Criteria Report, Roughan O'Donovan / Dublin City Council, September 2009, Final Report, 9T3615 
[5] Clontarf ‐ Task1 ‐ Wave Transformation Report, Royal Haskoning, 27 August 2015, RDCR001D01,  
[6]  Dollymount  Flood  Alleviation  Project,  Briefing  Notes,  Prepared  by  Gerard  O  Connell,  29th
  Oct 
2015 
[7] S2S Cycleway & Footway Interim Works (Bull Road to Causeway Road), Presentation to Elected 
Members, 11th November 2015 
[8] Greater Dublin Strategic Drainage Study, Regional Drainage Policies – Volume 5 Climate Change, 
March 2005 
[9]  Dublin  Coastal  Flooding  Protection  Project,  Final  Report  Volume  1  ‐  Main  Report,  Royal 
Haskoning, April 2005 
[10]  Waterford  City  Flood  Alleviation  Scheme,  Gavin  O’Donovan,  BE  CEng  MIEI,  Associate,  RPS 
Consulting Engineers Ltd, (Paper first presented to Engineers Ireland on 12th Feb 2014) 
[11] Google Maps 
[12] EurOtop; Wave Overtopping of Sea Defences and Related Structures: Assessment Manual, Jan 
2007, SSN 0452‐7739, ISBN 978‐3‐8042‐1064‐6, http://www.overtopping‐manual.com/eurotop.pdf 
[13] Projections of sea level rise, Presentation by Jonathan Gregory, Lead author, Chapter 13, Sea 
level change IPCC, https://www.ipcc.ch/pdf/unfccc/cop19/3_gregory13sbsta.pdf 
[14] IPCC Report (2013) Chapter 13 Sea Level Change, 
 https://www.ipcc.ch/pdf/assessment.../WG1AR5_Chapter13_FINAL.pdf 
 
[15] Morrissey Family Letter to Dublin City Council ‐ 29th October 2015 
[16] Follow up Note to Dublin City Councillors re Sea Protection ‐ Height Survey (John Morrissey) 
[17] Frequently Asked Questions_Version 2_30th October 2015 
Dollymount	Flood	Wall	– External	Review	 2016
 
17 
 
[18]  http://www.irishtimes.com/news/environment/residents‐say‐clontarf‐sea‐wall‐construction‐
must‐be‐stopped‐1.2409083 
[19] http://www.clontarf.ie/news/sea‐wall‐update‐letter‐to‐dcc‐from‐local‐representative‐groups 
[20]  http://www.herald.ie/news/deluge‐of‐complaints‐for‐councils‐berlin‐wall‐on‐the‐clontarf‐road‐
34395037.html 
 
 
Dollymount	Flood	Wall	– External	Review	 2016
 
18 
 
Appendix	1	–	Review	Brief	
Final Draft
Re: Dollymount Flood Wall – External Expert Brief.
Following unanimous approval of a motion by Dublin City Councillors at an
emergency meeting of the Council on Wednesday 11th
November last (copy
attached) it has been decided to procure a external expert to independently
assess the height of the partially constructed and proposed new sea wall along
Clontarf Road and James Larkin Road between the Wooden Bridge and the
Causeway to Bull Island, Clontarf, Dublin 3.
Representations from members of the public who drive past this new wall
contend that it obscures their views of Bull Island thus requesting this review.
Attached are frequently asked questions and links to the City Councils web-site
which outline the history of the project so far and some of the main issues
queried by local and regional residents.
The brief for this external expert includes the following:
1. Site visit.
Meeting with Environmental Monitoring Group.
2. Review previous reports which include this section of flood defence and
the latest relevant national/international best practice documents on
climate change with a view to verifying and/or establishing relevant
design criteria. This shall include but not be limited to:-
 Greater Dublin Strategic Drainage Study (GDSDS) Climate Change
Policy Document No.5 adopted by Dublin City Council.
 Dublin Coastal Flood Protection Project.
 SAFER Project.
 Clontarf Promenade Wave Modelling Projects.
 Dublin Bay tide gauge records with particular attention to Sea level
rise noted between 2000-2014.
 An Bord Pleanala Decisions & Inspector’s Reports for this stretch of
wall.
Dollymount	Flood	Wall	– External	Review	 2016
 
19 
 
 Part 8 approval by Dublin City Council for this cycleway, watermain
and flood wall.
 National/International best practice on guidelines and
recommendations on current and future flood defence heights.
 Eastern Region CFRAMS reports and draft CFRAM floodmaps.
 Irish Coastal Flood Protection Strategy (ICFPP) – OPW.
 Review of international best practice on design of coastal
defences/flood defences and climate change.
 Other reports/analysis which the expert deems necessary.
3. Analysis and recommendation on the four main constituents which
make up the height of this flood wall.
 Static tide design level (appropriate return period and associated
level),
 global warming element (temporal allowance and appropriate sea
level rise allowance(s) for same)
 associated wave defence component (based on wave climate in lagoon
and overtopping of flood wall),
 freeboard allowance (if any required).
4. Assessment of the suitability of a glass wall option for the highest
portions of the proposed new wall.
5. Draft report in 3 weeks with final report in 4 weeks. The report will
outline all reports and studies read by the expert, his/her conclusions
from them and his/her analysis and recommendation in respect of the
height of the coastal flood defence wall required for this section of
Dublin City coastline, i.e. adequacy of the existing design or proposed
new design level.
 

Weitere ähnliche Inhalte

Was ist angesagt?

Uncertainty Reduction in Online Dating Do Satisfied Customers Communicate Mor...
Uncertainty Reduction in Online Dating Do Satisfied Customers Communicate Mor...Uncertainty Reduction in Online Dating Do Satisfied Customers Communicate Mor...
Uncertainty Reduction in Online Dating Do Satisfied Customers Communicate Mor...
Lena Frenzel
 
Contest awards-bulletin-september-2013
Contest awards-bulletin-september-2013Contest awards-bulletin-september-2013
Contest awards-bulletin-september-2013
kyffa
 
Alec new jersey
Alec new jerseyAlec new jersey
Alec new jersey
DeepDude
 

Was ist angesagt? (19)

Uncertainty Reduction in Online Dating Do Satisfied Customers Communicate Mor...
Uncertainty Reduction in Online Dating Do Satisfied Customers Communicate Mor...Uncertainty Reduction in Online Dating Do Satisfied Customers Communicate Mor...
Uncertainty Reduction in Online Dating Do Satisfied Customers Communicate Mor...
 
TOC training Keycloak RedhatSSO advanced
TOC training Keycloak RedhatSSO advancedTOC training Keycloak RedhatSSO advanced
TOC training Keycloak RedhatSSO advanced
 
FULL BOOK - Ugrin-Varga New theory - Csaba Varga
FULL BOOK - Ugrin-Varga New theory - Csaba VargaFULL BOOK - Ugrin-Varga New theory - Csaba Varga
FULL BOOK - Ugrin-Varga New theory - Csaba Varga
 
(Ximb) sustainability brewing industry
(Ximb) sustainability brewing industry(Ximb) sustainability brewing industry
(Ximb) sustainability brewing industry
 
TOC training KeyCloak Redhat SSO core
TOC training KeyCloak Redhat SSO coreTOC training KeyCloak Redhat SSO core
TOC training KeyCloak Redhat SSO core
 
Byron Schaller - Challenge 1 - Virtual Design Master
Byron Schaller - Challenge 1 - Virtual Design MasterByron Schaller - Challenge 1 - Virtual Design Master
Byron Schaller - Challenge 1 - Virtual Design Master
 
Fluid mechanics
Fluid mechanicsFluid mechanics
Fluid mechanics
 
Contest awards-bulletin-september-2013
Contest awards-bulletin-september-2013Contest awards-bulletin-september-2013
Contest awards-bulletin-september-2013
 
Srs document for college module
Srs document for college moduleSrs document for college module
Srs document for college module
 
I am the guard
I am the guardI am the guard
I am the guard
 
American Legion Post 15 Employee Handbook
American Legion Post 15 Employee HandbookAmerican Legion Post 15 Employee Handbook
American Legion Post 15 Employee Handbook
 
A4 nnlcb2
A4 nnlcb2A4 nnlcb2
A4 nnlcb2
 
Poverty paper
Poverty paperPoverty paper
Poverty paper
 
Digest of decided cses partition pdf (1) (1)
Digest of decided cses partition pdf (1) (1)Digest of decided cses partition pdf (1) (1)
Digest of decided cses partition pdf (1) (1)
 
PMOC Readiness Report Oct 2012
PMOC Readiness Report Oct 2012PMOC Readiness Report Oct 2012
PMOC Readiness Report Oct 2012
 
Netex learningCentral | Trainer Manual v4.4 [En]
Netex learningCentral | Trainer Manual v4.4 [En]Netex learningCentral | Trainer Manual v4.4 [En]
Netex learningCentral | Trainer Manual v4.4 [En]
 
Alec new jersey
Alec new jerseyAlec new jersey
Alec new jersey
 
Instruction manual | Celestron CPC Telescopes | Optics Trade
Instruction manual | Celestron CPC Telescopes | Optics TradeInstruction manual | Celestron CPC Telescopes | Optics Trade
Instruction manual | Celestron CPC Telescopes | Optics Trade
 
2002annualreport[1]
2002annualreport[1]2002annualreport[1]
2002annualreport[1]
 

Andere mochten auch

Презентация для ЛАФ 7
Презентация для ЛАФ 7Презентация для ЛАФ 7
Презентация для ЛАФ 7
Olga Kruchkova
 
Isotec_Industry_2014_WWW
Isotec_Industry_2014_WWWIsotec_Industry_2014_WWW
Isotec_Industry_2014_WWW
Daria Pepelzhi
 
О компании ЭНЕРГОАУДИТКОНТРОЛЬ
О компании ЭНЕРГОАУДИТКОНТРОЛЬО компании ЭНЕРГОАУДИТКОНТРОЛЬ
О компании ЭНЕРГОАУДИТКОНТРОЛЬ
Daria Pepelzhi
 
Jorge enrrique cardenas garcia 140920218
Jorge enrrique cardenas garcia 140920218Jorge enrrique cardenas garcia 140920218
Jorge enrrique cardenas garcia 140920218
loreinne
 

Andere mochten auch (13)

Презентация для ЛАФ 7
Презентация для ЛАФ 7Презентация для ЛАФ 7
Презентация для ЛАФ 7
 
Recovery Shake
Recovery ShakeRecovery Shake
Recovery Shake
 
High capacity nw
High capacity nwHigh capacity nw
High capacity nw
 
Lili Autismo 1[1]
Lili Autismo 1[1]Lili Autismo 1[1]
Lili Autismo 1[1]
 
Dollymount External Expert
Dollymount External ExpertDollymount External Expert
Dollymount External Expert
 
Isotec_Industry_2014_WWW
Isotec_Industry_2014_WWWIsotec_Industry_2014_WWW
Isotec_Industry_2014_WWW
 
Dollymount externalexpert ommgoc
Dollymount externalexpert ommgocDollymount externalexpert ommgoc
Dollymount externalexpert ommgoc
 
О компании ЭНЕРГОАУДИТКОНТРОЛЬ
О компании ЭНЕРГОАУДИТКОНТРОЛЬО компании ЭНЕРГОАУДИТКОНТРОЛЬ
О компании ЭНЕРГОАУДИТКОНТРОЛЬ
 
Resultados cicad 2013_presentacion_final_mesmo
Resultados cicad 2013_presentacion_final_mesmoResultados cicad 2013_presentacion_final_mesmo
Resultados cicad 2013_presentacion_final_mesmo
 
Bollywood stars on social media
Bollywood stars on social mediaBollywood stars on social media
Bollywood stars on social media
 
Aprendizaje Autónomo
Aprendizaje AutónomoAprendizaje Autónomo
Aprendizaje Autónomo
 
Jorge enrrique cardenas garcia 140920218
Jorge enrrique cardenas garcia 140920218Jorge enrrique cardenas garcia 140920218
Jorge enrrique cardenas garcia 140920218
 
milena
milenamilena
milena
 

Ähnlich wie Dollymount flood wall review feb 2016 rev2

Final Presentation
Final PresentationFinal Presentation
Final Presentation
Citrix Lad
 
Dissertation_Final_Report
Dissertation_Final_ReportDissertation_Final_Report
Dissertation_Final_Report
Tom Day
 
Outhwaite-Aaron-MASc-PEAS-August-2015
Outhwaite-Aaron-MASc-PEAS-August-2015Outhwaite-Aaron-MASc-PEAS-August-2015
Outhwaite-Aaron-MASc-PEAS-August-2015
Aaron Outhwaite
 
Ryan Fu-Sum Nanofiltration Membrane Report
Ryan Fu-Sum Nanofiltration Membrane ReportRyan Fu-Sum Nanofiltration Membrane Report
Ryan Fu-Sum Nanofiltration Membrane Report
Ryan Fu-Sum
 
Falcon Capital Partners - Physician RCM Industry Report
Falcon Capital Partners - Physician RCM Industry ReportFalcon Capital Partners - Physician RCM Industry Report
Falcon Capital Partners - Physician RCM Industry Report
Jonathan Brallier
 
Capstone jordan new award metrics for sustainability_final
Capstone jordan new award metrics for sustainability_finalCapstone jordan new award metrics for sustainability_final
Capstone jordan new award metrics for sustainability_final
Luke Statz
 
Gbr Version 060209 Addendum
Gbr Version 060209 AddendumGbr Version 060209 Addendum
Gbr Version 060209 Addendum
matthromatka
 

Ähnlich wie Dollymount flood wall review feb 2016 rev2 (20)

Final Presentation
Final PresentationFinal Presentation
Final Presentation
 
2013 march idb jamaica logistics chain study 0
2013 march idb jamaica logistics chain study 02013 march idb jamaica logistics chain study 0
2013 march idb jamaica logistics chain study 0
 
C2C Survey Report
C2C Survey ReportC2C Survey Report
C2C Survey Report
 
MSc BD China Residency Trip Official Report
MSc BD China Residency Trip Official ReportMSc BD China Residency Trip Official Report
MSc BD China Residency Trip Official Report
 
Skycranes_Report-3-2
Skycranes_Report-3-2Skycranes_Report-3-2
Skycranes_Report-3-2
 
Dissertation_Final_Report
Dissertation_Final_ReportDissertation_Final_Report
Dissertation_Final_Report
 
Outhwaite-Aaron-MASc-PEAS-August-2015
Outhwaite-Aaron-MASc-PEAS-August-2015Outhwaite-Aaron-MASc-PEAS-August-2015
Outhwaite-Aaron-MASc-PEAS-August-2015
 
SystemProposal
SystemProposalSystemProposal
SystemProposal
 
Ryan Fu-Sum Nanofiltration Membrane Report
Ryan Fu-Sum Nanofiltration Membrane ReportRyan Fu-Sum Nanofiltration Membrane Report
Ryan Fu-Sum Nanofiltration Membrane Report
 
Falcon Capital Partners - Physician RCM Industry Report
Falcon Capital Partners - Physician RCM Industry ReportFalcon Capital Partners - Physician RCM Industry Report
Falcon Capital Partners - Physician RCM Industry Report
 
Health of-the-australian-construction-industry-research-report
Health of-the-australian-construction-industry-research-reportHealth of-the-australian-construction-industry-research-report
Health of-the-australian-construction-industry-research-report
 
#VirtualDesignMaster 3 Challenge 1 - Steven Viljoen
#VirtualDesignMaster 3 Challenge 1 - Steven Viljoen#VirtualDesignMaster 3 Challenge 1 - Steven Viljoen
#VirtualDesignMaster 3 Challenge 1 - Steven Viljoen
 
Group technology.docx
Group technology.docxGroup technology.docx
Group technology.docx
 
Capstone jordan new award metrics for sustainability_final
Capstone jordan new award metrics for sustainability_finalCapstone jordan new award metrics for sustainability_final
Capstone jordan new award metrics for sustainability_final
 
15
1515
15
 
GoogleReportFlat
GoogleReportFlatGoogleReportFlat
GoogleReportFlat
 
Gbr Version 060209 Addendum
Gbr Version 060209 AddendumGbr Version 060209 Addendum
Gbr Version 060209 Addendum
 
TOC training Keycloak RedhatSSO UMA
TOC training Keycloak RedhatSSO UMATOC training Keycloak RedhatSSO UMA
TOC training Keycloak RedhatSSO UMA
 
CASE Network Report 41 - Currency Crises in Emerging Markets - Selected Compa...
CASE Network Report 41 - Currency Crises in Emerging Markets - Selected Compa...CASE Network Report 41 - Currency Crises in Emerging Markets - Selected Compa...
CASE Network Report 41 - Currency Crises in Emerging Markets - Selected Compa...
 
Ecological assesment of fauna, sindh
Ecological assesment of fauna, sindhEcological assesment of fauna, sindh
Ecological assesment of fauna, sindh
 

Mehr von Naoise

Mehr von Naoise (20)

Sk 069 - ga working drawings
Sk 069 - ga working drawingsSk 069 - ga working drawings
Sk 069 - ga working drawings
 
Clontarf to city centre cycle scheme
Clontarf to city centre cycle schemeClontarf to city centre cycle scheme
Clontarf to city centre cycle scheme
 
17203 consultative forum no 3 30112018 issue compressed
17203 consultative forum no 3 30112018 issue compressed17203 consultative forum no 3 30112018 issue compressed
17203 consultative forum no 3 30112018 issue compressed
 
Griffith Avenue SHD ncac presentation 21 01-2019
Griffith Avenue SHD ncac presentation 21 01-2019Griffith Avenue SHD ncac presentation 21 01-2019
Griffith Avenue SHD ncac presentation 21 01-2019
 
Report no. 082019 of the environment strategic policy committee changes to ...
Report no. 082019 of the environment strategic policy committee   changes to ...Report no. 082019 of the environment strategic policy committee   changes to ...
Report no. 082019 of the environment strategic policy committee changes to ...
 
Letter to An Taoiseach
Letter to An TaoiseachLetter to An Taoiseach
Letter to An Taoiseach
 
DCC CEO Report to ABP
DCC CEO Report to ABPDCC CEO Report to ABP
DCC CEO Report to ABP
 
Doc09102017 00001
Doc09102017 00001Doc09102017 00001
Doc09102017 00001
 
2017.09.07 dcc120033 cyclist safety slides
2017.09.07 dcc120033 cyclist safety slides2017.09.07 dcc120033 cyclist safety slides
2017.09.07 dcc120033 cyclist safety slides
 
2017.08.28 db ncac&cac clontarf to city centre cycle route part 8 expla...
2017.08.28 db   ncac&cac clontarf to city centre cycle route part 8 expla...2017.08.28 db   ncac&cac clontarf to city centre cycle route part 8 expla...
2017.08.28 db ncac&cac clontarf to city centre cycle route part 8 expla...
 
Abp150416
Abp150416Abp150416
Abp150416
 
DCC Dollymount Flood Defence Report
DCC Dollymount Flood Defence ReportDCC Dollymount Flood Defence Report
DCC Dollymount Flood Defence Report
 
Dollymount Flood Defence schematic
Dollymount Flood Defence schematicDollymount Flood Defence schematic
Dollymount Flood Defence schematic
 
Draft Litter Management Plan
Draft Litter Management PlanDraft Litter Management Plan
Draft Litter Management Plan
 
Proposed additional car parking facility - south of Timber Bridge
Proposed additional car parking facility  - south of Timber BridgeProposed additional car parking facility  - south of Timber Bridge
Proposed additional car parking facility - south of Timber Bridge
 
Fairview Christmas Lights Switchon
Fairview Christmas Lights SwitchonFairview Christmas Lights Switchon
Fairview Christmas Lights Switchon
 
S2S Presentation to DCC - 11th November 2015
S2S Presentation to DCC - 11th November 2015S2S Presentation to DCC - 11th November 2015
S2S Presentation to DCC - 11th November 2015
 
S2S driver eye level below Sea Wall
S2S driver eye level below Sea WallS2S driver eye level below Sea Wall
S2S driver eye level below Sea Wall
 
Item06a part8
Item06a part8Item06a part8
Item06a part8
 
Fact sheet for rockfield tennis pavilion30 oct15
Fact sheet for rockfield tennis pavilion30 oct15Fact sheet for rockfield tennis pavilion30 oct15
Fact sheet for rockfield tennis pavilion30 oct15
 

Kürzlich hochgeladen

Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
gajnagarg
 
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
MadhuKothuru
 
Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdf
ScottMeyers35
 

Kürzlich hochgeladen (20)

2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31
 
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
 
Dating Call Girls inBaloda Bazar Bhatapara 9332606886Call Girls Advance Cash...
Dating Call Girls inBaloda Bazar Bhatapara  9332606886Call Girls Advance Cash...Dating Call Girls inBaloda Bazar Bhatapara  9332606886Call Girls Advance Cash...
Dating Call Girls inBaloda Bazar Bhatapara 9332606886Call Girls Advance Cash...
 
Pakistani Call girls in Sharjah 0505086370 Sharjah Call girls
Pakistani Call girls in Sharjah 0505086370 Sharjah Call girlsPakistani Call girls in Sharjah 0505086370 Sharjah Call girls
Pakistani Call girls in Sharjah 0505086370 Sharjah Call girls
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
 
31st World Press Freedom Day Conference.
31st World Press Freedom Day Conference.31st World Press Freedom Day Conference.
31st World Press Freedom Day Conference.
 
74th Amendment of India PPT by Piyush(IC).pptx
74th Amendment of India PPT by Piyush(IC).pptx74th Amendment of India PPT by Piyush(IC).pptx
74th Amendment of India PPT by Piyush(IC).pptx
 
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
 
Panchayath circular KLC -Panchayath raj act s 169, 218
Panchayath circular KLC -Panchayath raj act s 169, 218Panchayath circular KLC -Panchayath raj act s 169, 218
Panchayath circular KLC -Panchayath raj act s 169, 218
 
AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024
 
An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCC
 
NGO working for orphan children’s education
NGO working for orphan children’s educationNGO working for orphan children’s education
NGO working for orphan children’s education
 
Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdf
 
Make a difference in a girl's life by donating to her education!
Make a difference in a girl's life by donating to her education!Make a difference in a girl's life by donating to her education!
Make a difference in a girl's life by donating to her education!
 
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
 
Just Call VIP Call Girls In Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
Just Call VIP Call Girls In  Bangalore Kr Puram ☎️ 6378878445 Independent Fem...Just Call VIP Call Girls In  Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
Just Call VIP Call Girls In Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
 
1935 CONSTITUTION REPORT IN RIPH FINALLS
1935 CONSTITUTION REPORT IN RIPH FINALLS1935 CONSTITUTION REPORT IN RIPH FINALLS
1935 CONSTITUTION REPORT IN RIPH FINALLS
 
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
 
31st World Press Freedom Day Conference in Santiago.
31st World Press Freedom Day Conference in Santiago.31st World Press Freedom Day Conference in Santiago.
31st World Press Freedom Day Conference in Santiago.
 

Dollymount flood wall review feb 2016 rev2