Factory Infrastructure for PV Manufacturing
San Francisco, July 11, 2017
Ankush Halbe
Intersolar – North America
© M+W U.S., Inc. I July 2017 2
Contents
• Company Overview
• PV Capacity Drivers
• Fab Design Concepts
• Environmental Considerations
• Safety Considerations
• Fab Statistics
• Fab Energy Management
• Summary
© M+W U.S., Inc. I July 2017 3
Advanced Technology Facilities
Global EPC Company
Semiconductor
Leading Player
With global reach
$3.05B
Annual order intake
In 30+
Countries
Renewable Energy
Research Institute Displays
1912
est. in Germany
© M+W U.S., Inc. I July 2017 4
Advanced Technology Facilities
Track Record
• >12 Gigawatts of PV Manufacturing
Capacity built
• >45 Million SF of Cleanroom Space
Delivered
• >21,000 Process Tools Installed
• >500 MW installed for C&I clients for
onsite power & utility-scale projects
• Complete solar offering from
wafering through to financing and
O&M services for PV installations
© M+W U.S., Inc. I July 2017 5
M+W International PV Projects
Europe AsiaAmericas
Representative Clients
6
© M+W U.S., Inc. I July 2017 6
Fab Engineering & Construction
Lifecycle
Site Analysis
Concept
Design
Preconstruction
Planning
Feasibility
Studies
Issued-for-
Construction
Construction
Management
Tool
Installation
Operations
Renovation New Construction
© M+W U.S., Inc. I July 2017 7
PV Capacity Drivers
Global PV Demand
Source: GTM Research
Demand for PV modules continues to grow, although at a slower, more sustainable pace (+7% YOY)
© M+W U.S., Inc. I July 2017 8
PV Capacity Drivers
Near-term Module Prices and Capacity Trends
• Module prices continue to drop to historic lows,
squeezing margins of PV manufacturers
• With excess module capacity, it is challenging
for manufacturers to spend on additional
CAPEX in 2017-18 Source: GTM Research
PERC technology
© M+W U.S., Inc. I July 2017 9
PV Capacity Drivers
PV Factory CAPEX Outlook
• Facilities typically account for ~ 20% of overall CAPEX on a new facility
• CAPEX on equipment and facilities growing at a modest pace for 2017-18
• Low utilization of existing manufacturing capacity
• Limited appetite for improving manufacturing productivity
• Limited commercial introduction of major technology innovations
Source: PV Tech, Solar Media
© M+W U.S., Inc. I July 2017 10
PV Cell Manufacturing
Process Technology Impact on Facilities Design
The function, operation and shape of any facility are primarily driven by process &
manufacturing requirements
Equipment & Automation
Production Environment
Critical Process Systems
Site Infrastructure
Building & Facility Systems
ProcessPower
DI-Water
PCW
Make-up Air
Chemicals
Specialty
Gases
Acid Pyrophoric
Solvent Exhaust
Wafer Solar Cell
Compressed
Air
Bulk
Gases
Waste Water
Heat
Exhaust
© M+W U.S., Inc. I July 2017 11
PV Cell Manufacturing
Sample Tool Utility Matrix
Utility consumption from process tools determines the type and capacity of facility systems for the
fab (e.g. for exhaust, abatement, water, bulk-gases, power, etc.)
Process
Category AF MF [kW] AF MF [kW] AF MF AF MF AF MF AF MF AF MF AF MF AF MF AF MF AF MF AF MF AF MF AF MF AF MF AF MF
Glass clean - substrate
20.00 230.00 0.5 1.0 2,500 2,500
3.0 3.0 12.2 0.50 2.00 15 50 2 10
0.50 2.00 10 30
3.0 3.0 12.2 2.00 500.00 0.50 2.00 15 50
15.80 80.00 20.00 230.00 0.5 1.0 2,500 2,500
3.0 3.0 12.2 0.50 2.00 15 50 2 10
0.50 2.00 10 30
3.0 3.0 12.2 2.00 500.00 0.50 2.00 15 50 2.00 500.00 2 10
Mo Sputter 12.0 12.0 41.8 1.00 3.00 50 250
400.00 400.00
18.5 18.5 107.4 1.00 3.00 20 80
12.0 12.0 41.8 1.00 3.00 50 250
11.0 11.0 63.9 1.00 3.00 20 80 600 600
P1-Laser 6 22 500 500
6 22 500 500
CIG Sputter 2.00 7.00 700.00 700.00 15 50 500 500
2.00 7.00 15 50 500 500
Selenization 12.00 12.00 41.8 28.00 40.00 50 80
12.00 12.00 41.8 28.00 40.00 0.06 0.12 50 80 1,000 1,000
0.06 0.12
CdS 1.00 1.00 24 70 n.a. n.a.
1.00 1.00 24 70 2.00 500.00 n.a. n.a.
1.50 1.50 28 82 2.00 500.00 n.a. n.a.
1.50 1.50 28 82 2.00 500.00 n.a. n.a.
Exhaust
PCW 1
[m3/h]
Liquids
IWD
[l/h]
Drain
CDA
Dew.P < -50°C
[Nm3/h]
SLA-D
[l/h]
Drain-OtherIndustrial Waste Drain
Electrical
CDA
Dew.P < -70°C
[Nm3/h]
NPS 220
[kVA]
General Exhaust
from Laser
N2
4.5
[Nm3/h]
Ar
5.0
[Nm3/h]
DI Water
< 10 µS/cm
[l/h]
Potable Water
[l/h]
General Exhaust
Bulkgases
GEEX
[Nm3/h]
H2S
5.0
[Nm3/h]
PCW 2
T in = 5°C (41°F)
[m3/h]
DEZ
5.0
[Nm3/h]
NPS 480
[kVA]
Laser-EX
[Nm3/h]
© M+W U.S., Inc. I July 2017 12
PV Cell Manufacturing
Conceptual Fab Layout
© M+W U.S., Inc. I July 2017 13
PV Cell Manufacturing
Conceptual Fab Layout
© M+W U.S., Inc. I July 2017 14
PV Cell Fab
Production Environment
• Si cell technologies require minimal clean space; thin-film technologies do not require
any clean space
• ISO 7/8 has regulations on airborne particulate contamination of >0.5um particulate size
• Developing a deep understanding of manufacturing process tolerances for cleanliness,
temperature, and humidity help save facilities cost
Si cell technologies – generic production environments
© M+W U.S., Inc. I July 2017 15
PV Cell Fab
Vibration Considerations
Laser & mechanical
patterning tools in
manufacturing area
typically drive any
vibration specs
SEMs, X-ray, and
other e-beam other
optical inspection
tools in FA labs
© M+W U.S., Inc. I July 2017 16
PV Manufacturing
Safety Considerations
Source: Fthenakis et al.
• Certain process chemicals and specialty gases used in the PV manufacturing industry
have safety implications
• Gaseous effluents present acute safety hazards; scrubbing is typically required
Hazardous materials used in PV cell manufacturing
© M+W U.S., Inc. I July 2017 17
Safety Considerations
Example-Silane Containment Strategies
• ICC (International code council) – CGA G13 determines storage and handling code for Silanes and
mixtures in PV facilities
• Store as minimum volumes as possible
• Store Silane cylinders separately from toxic, corrosive, flammable, oxidizing, and water-reactive
materials
• Locate scrubber for SiH4 outdoors, or in a very ventilated area
• Purge storage cabinets continuously with N2, with highly velocity airflow through several ports
• Consider explosion resistant cabinets with pads, roof, double fences, and fire protection sprinklers
• Install gas monitors, flame detectors with automatic shut-off valves at the cylinder
• Dilute the SiH4/H2 effluent from the process or the scrubber with N2 to lower the SiH4 concentration to
<0.5% before it mixes with air
• Make all exhaust lines of non-combustible material
© M+W U.S., Inc. I July 2017 18
PV Cell Fab
Fab Design Statistics
• Fab statistics consider various PV cell technology types
• Facilities infrastructure is generally similar across different PV cell technologies
Cost%
FabArea%
© M+W U.S., Inc. I July 2017 19
PV Fab
Generic Pictures
Manufacturing area Facilities Area
© M+W U.S., Inc. I July 2017 20
PV Fab
Generic Pictures
Source: PV-Tech / Tesla-SolarCity
Source: Mission Solar Energy
© M+W U.S., Inc. I July 2017 21
PV Cell Fab
Fab Construction – Cost Saving Strategies
• Pre-fab buildings
• Modular cleanrooms
• Pre-fab piping racks, equipment skids, etc.
• Process tool installation modules such as high-purity piping
Deploying the use of prefabricated construction modules helps reduce project schedules and
labor costs
© M+W U.S., Inc. I July 2017 22
Fab Energy Management
Case Study: Hi-tech Manufacturing Fab
• Energy savings strategy for a fully operational hi-tech manufacturing facility is illustrated
• Learnings are applicable to PV fabs as well
• Efficient design & management of facility systems is a “low” hanging fruit for reducing overall energy
footprint, and can have a potential ROI of <3 years
# System Changes Power Saving Power Saving Natural Gas Saving Energy Cost Saving Payback
MWh/a KW (Peak) MWh/a Years
1 Cleanroom Cleanroom Specification Change 965 150 1159 61,118$ NA
2 Make-up Air Make-up Air Supply Temperature Reduction 589 67 654 44,954$ NA
3 Chilled Water Chilled Water Supply Temperature Increase 687 TBD 40,602$ NA
4 Vacuum Temporary Shut-off 146 33 8,608$ NA
5 Cleanroom Cleanroom Air Velocity Reduction 676 77 39,936$ NA
6 Ultra Pure Water Replace Electric with Hot Water Heating 10186 1170 -11647 421,486$ 1.6
7 Exhaust Heat/Particle Exhaust Recycling 464 53 436 34,217$ 2.1
8 Hot Water Installation of VSD at Pumps 864 215 51,062$ 2.4
9 Chilled Water Installation of VSD at Pumps 1405 TBD 83,036$ 2.9
10 Make-up air Final Filter Replacements 387 44 -430 16,195$ 3.0
Total 16369 1809 -9828 801,214$
Total without risk 15504 1660 -10986 740,096$
Set-point changes
Hardware changes
© M+W U.S., Inc. I July 2017 23
PV Manufacturing Facility
Summary: Collaborative Effort to Drive Down Costs
1.0
0.5
0.0
FacilitiesandOperationCost(a.u.)
Technology
Improvement
Fab Safety
Engineering
High
Throughput
Process
Tools
Material
Supply
Chain
Process Equipment
& Technology
Safety
Purchasing
PV Manufacturer Focus M+W’s Value to PV Manufacturer
Fab Energy
Management
Lessons Learnt
Optimized
Building &
Facilities
Industrial Engineering
Energy
Efficiency
Benchmarking
www.mwgroup.net
Contact
Ankush Halbe
Ankush.Halbe@mwgroup.net
M+W U.S., Inc.
201 Fuller Road, Suite 401
Albany, NY 12210
518.450.9924
THANK YOU
Visit us at Impress Lounge (Moscone Center Rooftop)!

Weitere ähnliche Inhalte

Was ist angesagt?

One Click LCA & IES Integration
One Click LCA & IES IntegrationOne Click LCA & IES Integration
One Click LCA & IES IntegrationIES VE
 
IES & MagiCAD: Learn about the new IESVE & MagiCAD interoperability
IES & MagiCAD: Learn about the new IESVE & MagiCAD interoperabilityIES & MagiCAD: Learn about the new IESVE & MagiCAD interoperability
IES & MagiCAD: Learn about the new IESVE & MagiCAD interoperabilityIES VE
 
05 - 88 news and events update sep 2015
05 - 88 news and events update sep 201505 - 88 news and events update sep 2015
05 - 88 news and events update sep 2015nowosad88
 
TIMES-CGE-SD model coupling and data exchange mechanism for the LEDS developm...
TIMES-CGE-SD model coupling and data exchange mechanism for the LEDS developm...TIMES-CGE-SD model coupling and data exchange mechanism for the LEDS developm...
TIMES-CGE-SD model coupling and data exchange mechanism for the LEDS developm...IEA-ETSAP
 
Easme rmsummit PLATIRUS & CEBRA
Easme rmsummit PLATIRUS & CEBRAEasme rmsummit PLATIRUS & CEBRA
Easme rmsummit PLATIRUS & CEBRAJokin Hidalgo
 
Impact of technology availability on the transition to a net-zero industry
Impact of technology availability on the transition to a net-zero industryImpact of technology availability on the transition to a net-zero industry
Impact of technology availability on the transition to a net-zero industryIEA-ETSAP
 
The role of delivered performance june2009
The role of delivered performance june2009The role of delivered performance june2009
The role of delivered performance june2009Toronto 2030 District
 
Presentation Solar Technologies Leonardo Energy - ICREPQ Congress 2009
Presentation Solar Technologies   Leonardo Energy   - ICREPQ Congress 2009Presentation Solar Technologies   Leonardo Energy   - ICREPQ Congress 2009
Presentation Solar Technologies Leonardo Energy - ICREPQ Congress 2009Leonardo ENERGY
 
17nov themesession2 _seai_marren
17nov themesession2 _seai_marren17nov themesession2 _seai_marren
17nov themesession2 _seai_marrenGlobe Forum
 
Regulatory Update: Introduction to Bill 135 and Environmental Policies Impact...
Regulatory Update: Introduction to Bill 135 and Environmental Policies Impact...Regulatory Update: Introduction to Bill 135 and Environmental Policies Impact...
Regulatory Update: Introduction to Bill 135 and Environmental Policies Impact...Enercare Inc.
 
Energy Management Strategies for MURB & Commercial Buildings
Energy Management Strategies for MURB & Commercial BuildingsEnergy Management Strategies for MURB & Commercial Buildings
Energy Management Strategies for MURB & Commercial BuildingsEnercare Inc.
 
ETOGAS company presentation Dr. Karl Maria Grünauer
ETOGAS company presentation Dr. Karl Maria GrünauerETOGAS company presentation Dr. Karl Maria Grünauer
ETOGAS company presentation Dr. Karl Maria GrünauerDr. Karl Maria Grünauer
 
Energy modeling 101 (public)
Energy modeling 101 (public)Energy modeling 101 (public)
Energy modeling 101 (public)Michael Brown
 
Sustainability in Cement Industry | Rakesh Bhargava, Chief Climate & Sustaina...
Sustainability in Cement Industry | Rakesh Bhargava, Chief Climate & Sustaina...Sustainability in Cement Industry | Rakesh Bhargava, Chief Climate & Sustaina...
Sustainability in Cement Industry | Rakesh Bhargava, Chief Climate & Sustaina...Cairn India Limited
 
Money and the Role of Building Physics Software in the Valuation Chain
Money and the Role of Building Physics Software in the Valuation ChainMoney and the Role of Building Physics Software in the Valuation Chain
Money and the Role of Building Physics Software in the Valuation ChainIES VE
 
Rotor Blades: The use of composites in rotor blade design
Rotor Blades: The use of composites in rotor blade designRotor Blades: The use of composites in rotor blade design
Rotor Blades: The use of composites in rotor blade designTorben Haagh
 
Modelling Circular Economy in TIMES
Modelling Circular Economy in TIMESModelling Circular Economy in TIMES
Modelling Circular Economy in TIMESIEA-ETSAP
 
Modelling different Thermal Energy Storage (TES) options in a TIMES model
Modelling different Thermal Energy Storage (TES) options in a TIMES modelModelling different Thermal Energy Storage (TES) options in a TIMES model
Modelling different Thermal Energy Storage (TES) options in a TIMES modelIEA-ETSAP
 
Composite Wind Blade Sustainability - Compositi Magazine - 01_07_2019
Composite Wind Blade Sustainability  - Compositi Magazine - 01_07_2019Composite Wind Blade Sustainability  - Compositi Magazine - 01_07_2019
Composite Wind Blade Sustainability - Compositi Magazine - 01_07_2019Polynt Group
 

Was ist angesagt? (19)

One Click LCA & IES Integration
One Click LCA & IES IntegrationOne Click LCA & IES Integration
One Click LCA & IES Integration
 
IES & MagiCAD: Learn about the new IESVE & MagiCAD interoperability
IES & MagiCAD: Learn about the new IESVE & MagiCAD interoperabilityIES & MagiCAD: Learn about the new IESVE & MagiCAD interoperability
IES & MagiCAD: Learn about the new IESVE & MagiCAD interoperability
 
05 - 88 news and events update sep 2015
05 - 88 news and events update sep 201505 - 88 news and events update sep 2015
05 - 88 news and events update sep 2015
 
TIMES-CGE-SD model coupling and data exchange mechanism for the LEDS developm...
TIMES-CGE-SD model coupling and data exchange mechanism for the LEDS developm...TIMES-CGE-SD model coupling and data exchange mechanism for the LEDS developm...
TIMES-CGE-SD model coupling and data exchange mechanism for the LEDS developm...
 
Easme rmsummit PLATIRUS & CEBRA
Easme rmsummit PLATIRUS & CEBRAEasme rmsummit PLATIRUS & CEBRA
Easme rmsummit PLATIRUS & CEBRA
 
Impact of technology availability on the transition to a net-zero industry
Impact of technology availability on the transition to a net-zero industryImpact of technology availability on the transition to a net-zero industry
Impact of technology availability on the transition to a net-zero industry
 
The role of delivered performance june2009
The role of delivered performance june2009The role of delivered performance june2009
The role of delivered performance june2009
 
Presentation Solar Technologies Leonardo Energy - ICREPQ Congress 2009
Presentation Solar Technologies   Leonardo Energy   - ICREPQ Congress 2009Presentation Solar Technologies   Leonardo Energy   - ICREPQ Congress 2009
Presentation Solar Technologies Leonardo Energy - ICREPQ Congress 2009
 
17nov themesession2 _seai_marren
17nov themesession2 _seai_marren17nov themesession2 _seai_marren
17nov themesession2 _seai_marren
 
Regulatory Update: Introduction to Bill 135 and Environmental Policies Impact...
Regulatory Update: Introduction to Bill 135 and Environmental Policies Impact...Regulatory Update: Introduction to Bill 135 and Environmental Policies Impact...
Regulatory Update: Introduction to Bill 135 and Environmental Policies Impact...
 
Energy Management Strategies for MURB & Commercial Buildings
Energy Management Strategies for MURB & Commercial BuildingsEnergy Management Strategies for MURB & Commercial Buildings
Energy Management Strategies for MURB & Commercial Buildings
 
ETOGAS company presentation Dr. Karl Maria Grünauer
ETOGAS company presentation Dr. Karl Maria GrünauerETOGAS company presentation Dr. Karl Maria Grünauer
ETOGAS company presentation Dr. Karl Maria Grünauer
 
Energy modeling 101 (public)
Energy modeling 101 (public)Energy modeling 101 (public)
Energy modeling 101 (public)
 
Sustainability in Cement Industry | Rakesh Bhargava, Chief Climate & Sustaina...
Sustainability in Cement Industry | Rakesh Bhargava, Chief Climate & Sustaina...Sustainability in Cement Industry | Rakesh Bhargava, Chief Climate & Sustaina...
Sustainability in Cement Industry | Rakesh Bhargava, Chief Climate & Sustaina...
 
Money and the Role of Building Physics Software in the Valuation Chain
Money and the Role of Building Physics Software in the Valuation ChainMoney and the Role of Building Physics Software in the Valuation Chain
Money and the Role of Building Physics Software in the Valuation Chain
 
Rotor Blades: The use of composites in rotor blade design
Rotor Blades: The use of composites in rotor blade designRotor Blades: The use of composites in rotor blade design
Rotor Blades: The use of composites in rotor blade design
 
Modelling Circular Economy in TIMES
Modelling Circular Economy in TIMESModelling Circular Economy in TIMES
Modelling Circular Economy in TIMES
 
Modelling different Thermal Energy Storage (TES) options in a TIMES model
Modelling different Thermal Energy Storage (TES) options in a TIMES modelModelling different Thermal Energy Storage (TES) options in a TIMES model
Modelling different Thermal Energy Storage (TES) options in a TIMES model
 
Composite Wind Blade Sustainability - Compositi Magazine - 01_07_2019
Composite Wind Blade Sustainability  - Compositi Magazine - 01_07_2019Composite Wind Blade Sustainability  - Compositi Magazine - 01_07_2019
Composite Wind Blade Sustainability - Compositi Magazine - 01_07_2019
 

Ähnlich wie Factory Infrastructure for PV Manufacturing

Jonathan woolley talk
Jonathan woolley talkJonathan woolley talk
Jonathan woolley talkPhucPhamThanh
 
Chilled Water Plant Optimization
Chilled Water Plant OptimizationChilled Water Plant Optimization
Chilled Water Plant OptimizationJoePessa
 
Optimising Efficiency & Capacity Sep 04 Rev 0
Optimising Efficiency & Capacity Sep 04 Rev 0Optimising Efficiency & Capacity Sep 04 Rev 0
Optimising Efficiency & Capacity Sep 04 Rev 0Raja Ratnam
 
Barangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact SheetBarangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact SheetDeanDallwitz
 
A practical approach to pharmaceutical HVAC energy reduction
A practical approach to pharmaceutical HVAC energy reductionA practical approach to pharmaceutical HVAC energy reduction
A practical approach to pharmaceutical HVAC energy reductionEECO2
 
Now Is the Time for Energy Management
Now Is the Time for Energy ManagementNow Is the Time for Energy Management
Now Is the Time for Energy ManagementBlack & Veatch
 
Maik winges
Maik wingesMaik winges
Maik winges7391456
 
Highlights of the Kuwait HVAC&R Conference 2017
Highlights of the Kuwait HVAC&R Conference 2017Highlights of the Kuwait HVAC&R Conference 2017
Highlights of the Kuwait HVAC&R Conference 2017Swati Warang
 
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...NazrulIslam657555
 
Air conditioning if its not clean - its not green - ACT smart 4th sept 2014
Air conditioning   if its not clean - its not green - ACT smart 4th sept 2014Air conditioning   if its not clean - its not green - ACT smart 4th sept 2014
Air conditioning if its not clean - its not green - ACT smart 4th sept 2014Phil Wilkinson F.AIRAH F.IEAust M.ASHRAE
 
American Institute of Architects Committee on the Envrinment
American Institute of Architects Committee on the EnvrinmentAmerican Institute of Architects Committee on the Envrinment
American Institute of Architects Committee on the EnvrinmentCenter for Energy and Environment
 
SIKCO Engineering Services Pvt. Ltd, Navi Mumbai, Electric Products
SIKCO Engineering Services Pvt. Ltd, Navi Mumbai, Electric Products 	SIKCO Engineering Services Pvt. Ltd, Navi Mumbai, Electric Products
SIKCO Engineering Services Pvt. Ltd, Navi Mumbai, Electric Products IndiaMART InterMESH Limited
 
An introduction to EECO2-Energy Efficiency Consultancy Limited
An introduction to EECO2-Energy Efficiency Consultancy LimitedAn introduction to EECO2-Energy Efficiency Consultancy Limited
An introduction to EECO2-Energy Efficiency Consultancy LimitedEECO2
 
EECO2 GMP critical HVAC energy cost reduction
EECO2 GMP critical HVAC energy cost reductionEECO2 GMP critical HVAC energy cost reduction
EECO2 GMP critical HVAC energy cost reductionKeith Beattie
 
IRJET- Improvement of Coefficient of Performance of ICE Plant
IRJET- Improvement of Coefficient of Performance of ICE PlantIRJET- Improvement of Coefficient of Performance of ICE Plant
IRJET- Improvement of Coefficient of Performance of ICE PlantIRJET Journal
 

Ähnlich wie Factory Infrastructure for PV Manufacturing (20)

Jonathan woolley talk
Jonathan woolley talkJonathan woolley talk
Jonathan woolley talk
 
GE Hitachi. Nuclear Innovation
GE Hitachi. Nuclear InnovationGE Hitachi. Nuclear Innovation
GE Hitachi. Nuclear Innovation
 
Chilled Water Plant Optimization
Chilled Water Plant OptimizationChilled Water Plant Optimization
Chilled Water Plant Optimization
 
ESCO Contracting - CII Danfoss, Chennai Aug 2017
ESCO Contracting - CII Danfoss, Chennai Aug 2017ESCO Contracting - CII Danfoss, Chennai Aug 2017
ESCO Contracting - CII Danfoss, Chennai Aug 2017
 
Optimising Efficiency & Capacity Sep 04 Rev 0
Optimising Efficiency & Capacity Sep 04 Rev 0Optimising Efficiency & Capacity Sep 04 Rev 0
Optimising Efficiency & Capacity Sep 04 Rev 0
 
GE Hitachi. Nuclear Innovation
GE Hitachi. Nuclear InnovationGE Hitachi. Nuclear Innovation
GE Hitachi. Nuclear Innovation
 
Barangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact SheetBarangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact Sheet
 
A practical approach to pharmaceutical HVAC energy reduction
A practical approach to pharmaceutical HVAC energy reductionA practical approach to pharmaceutical HVAC energy reduction
A practical approach to pharmaceutical HVAC energy reduction
 
Now Is the Time for Energy Management
Now Is the Time for Energy ManagementNow Is the Time for Energy Management
Now Is the Time for Energy Management
 
Maik winges
Maik wingesMaik winges
Maik winges
 
ashrae 62.1
ashrae 62.1ashrae 62.1
ashrae 62.1
 
Highlights of the Kuwait HVAC&R Conference 2017
Highlights of the Kuwait HVAC&R Conference 2017Highlights of the Kuwait HVAC&R Conference 2017
Highlights of the Kuwait HVAC&R Conference 2017
 
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...
5 Steps to Achieve More CostEffective Aminebased Carbon Capture Processes at ...
 
Air conditioning if its not clean - its not green - ACT smart 4th sept 2014
Air conditioning   if its not clean - its not green - ACT smart 4th sept 2014Air conditioning   if its not clean - its not green - ACT smart 4th sept 2014
Air conditioning if its not clean - its not green - ACT smart 4th sept 2014
 
American Institute of Architects Committee on the Envrinment
American Institute of Architects Committee on the EnvrinmentAmerican Institute of Architects Committee on the Envrinment
American Institute of Architects Committee on the Envrinment
 
SIKCO Engineering Services Pvt. Ltd, Navi Mumbai, Electric Products
SIKCO Engineering Services Pvt. Ltd, Navi Mumbai, Electric Products 	SIKCO Engineering Services Pvt. Ltd, Navi Mumbai, Electric Products
SIKCO Engineering Services Pvt. Ltd, Navi Mumbai, Electric Products
 
An introduction to EECO2-Energy Efficiency Consultancy Limited
An introduction to EECO2-Energy Efficiency Consultancy LimitedAn introduction to EECO2-Energy Efficiency Consultancy Limited
An introduction to EECO2-Energy Efficiency Consultancy Limited
 
EECO2 GMP critical HVAC energy cost reduction
EECO2 GMP critical HVAC energy cost reductionEECO2 GMP critical HVAC energy cost reduction
EECO2 GMP critical HVAC energy cost reduction
 
IRJET- Improvement of Coefficient of Performance of ICE Plant
IRJET- Improvement of Coefficient of Performance of ICE PlantIRJET- Improvement of Coefficient of Performance of ICE Plant
IRJET- Improvement of Coefficient of Performance of ICE Plant
 
Introduction of CO2 Reduction Technologies in Steelworks
Introduction of  CO2 Reduction Technologies in SteelworksIntroduction of  CO2 Reduction Technologies in Steelworks
Introduction of CO2 Reduction Technologies in Steelworks
 

Kürzlich hochgeladen

HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadhamedmustafa094
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksMagic Marks
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Air Compressor reciprocating single stage
Air Compressor reciprocating single stageAir Compressor reciprocating single stage
Air Compressor reciprocating single stageAbc194748
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 

Kürzlich hochgeladen (20)

HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic Marks
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Air Compressor reciprocating single stage
Air Compressor reciprocating single stageAir Compressor reciprocating single stage
Air Compressor reciprocating single stage
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 

Factory Infrastructure for PV Manufacturing

  • 1. Factory Infrastructure for PV Manufacturing San Francisco, July 11, 2017 Ankush Halbe Intersolar – North America
  • 2. © M+W U.S., Inc. I July 2017 2 Contents • Company Overview • PV Capacity Drivers • Fab Design Concepts • Environmental Considerations • Safety Considerations • Fab Statistics • Fab Energy Management • Summary
  • 3. © M+W U.S., Inc. I July 2017 3 Advanced Technology Facilities Global EPC Company Semiconductor Leading Player With global reach $3.05B Annual order intake In 30+ Countries Renewable Energy Research Institute Displays 1912 est. in Germany
  • 4. © M+W U.S., Inc. I July 2017 4 Advanced Technology Facilities Track Record • >12 Gigawatts of PV Manufacturing Capacity built • >45 Million SF of Cleanroom Space Delivered • >21,000 Process Tools Installed • >500 MW installed for C&I clients for onsite power & utility-scale projects • Complete solar offering from wafering through to financing and O&M services for PV installations
  • 5. © M+W U.S., Inc. I July 2017 5 M+W International PV Projects Europe AsiaAmericas Representative Clients 6
  • 6. © M+W U.S., Inc. I July 2017 6 Fab Engineering & Construction Lifecycle Site Analysis Concept Design Preconstruction Planning Feasibility Studies Issued-for- Construction Construction Management Tool Installation Operations Renovation New Construction
  • 7. © M+W U.S., Inc. I July 2017 7 PV Capacity Drivers Global PV Demand Source: GTM Research Demand for PV modules continues to grow, although at a slower, more sustainable pace (+7% YOY)
  • 8. © M+W U.S., Inc. I July 2017 8 PV Capacity Drivers Near-term Module Prices and Capacity Trends • Module prices continue to drop to historic lows, squeezing margins of PV manufacturers • With excess module capacity, it is challenging for manufacturers to spend on additional CAPEX in 2017-18 Source: GTM Research PERC technology
  • 9. © M+W U.S., Inc. I July 2017 9 PV Capacity Drivers PV Factory CAPEX Outlook • Facilities typically account for ~ 20% of overall CAPEX on a new facility • CAPEX on equipment and facilities growing at a modest pace for 2017-18 • Low utilization of existing manufacturing capacity • Limited appetite for improving manufacturing productivity • Limited commercial introduction of major technology innovations Source: PV Tech, Solar Media
  • 10. © M+W U.S., Inc. I July 2017 10 PV Cell Manufacturing Process Technology Impact on Facilities Design The function, operation and shape of any facility are primarily driven by process & manufacturing requirements Equipment & Automation Production Environment Critical Process Systems Site Infrastructure Building & Facility Systems ProcessPower DI-Water PCW Make-up Air Chemicals Specialty Gases Acid Pyrophoric Solvent Exhaust Wafer Solar Cell Compressed Air Bulk Gases Waste Water Heat Exhaust
  • 11. © M+W U.S., Inc. I July 2017 11 PV Cell Manufacturing Sample Tool Utility Matrix Utility consumption from process tools determines the type and capacity of facility systems for the fab (e.g. for exhaust, abatement, water, bulk-gases, power, etc.) Process Category AF MF [kW] AF MF [kW] AF MF AF MF AF MF AF MF AF MF AF MF AF MF AF MF AF MF AF MF AF MF AF MF AF MF AF MF Glass clean - substrate 20.00 230.00 0.5 1.0 2,500 2,500 3.0 3.0 12.2 0.50 2.00 15 50 2 10 0.50 2.00 10 30 3.0 3.0 12.2 2.00 500.00 0.50 2.00 15 50 15.80 80.00 20.00 230.00 0.5 1.0 2,500 2,500 3.0 3.0 12.2 0.50 2.00 15 50 2 10 0.50 2.00 10 30 3.0 3.0 12.2 2.00 500.00 0.50 2.00 15 50 2.00 500.00 2 10 Mo Sputter 12.0 12.0 41.8 1.00 3.00 50 250 400.00 400.00 18.5 18.5 107.4 1.00 3.00 20 80 12.0 12.0 41.8 1.00 3.00 50 250 11.0 11.0 63.9 1.00 3.00 20 80 600 600 P1-Laser 6 22 500 500 6 22 500 500 CIG Sputter 2.00 7.00 700.00 700.00 15 50 500 500 2.00 7.00 15 50 500 500 Selenization 12.00 12.00 41.8 28.00 40.00 50 80 12.00 12.00 41.8 28.00 40.00 0.06 0.12 50 80 1,000 1,000 0.06 0.12 CdS 1.00 1.00 24 70 n.a. n.a. 1.00 1.00 24 70 2.00 500.00 n.a. n.a. 1.50 1.50 28 82 2.00 500.00 n.a. n.a. 1.50 1.50 28 82 2.00 500.00 n.a. n.a. Exhaust PCW 1 [m3/h] Liquids IWD [l/h] Drain CDA Dew.P < -50°C [Nm3/h] SLA-D [l/h] Drain-OtherIndustrial Waste Drain Electrical CDA Dew.P < -70°C [Nm3/h] NPS 220 [kVA] General Exhaust from Laser N2 4.5 [Nm3/h] Ar 5.0 [Nm3/h] DI Water < 10 µS/cm [l/h] Potable Water [l/h] General Exhaust Bulkgases GEEX [Nm3/h] H2S 5.0 [Nm3/h] PCW 2 T in = 5°C (41°F) [m3/h] DEZ 5.0 [Nm3/h] NPS 480 [kVA] Laser-EX [Nm3/h]
  • 12. © M+W U.S., Inc. I July 2017 12 PV Cell Manufacturing Conceptual Fab Layout
  • 13. © M+W U.S., Inc. I July 2017 13 PV Cell Manufacturing Conceptual Fab Layout
  • 14. © M+W U.S., Inc. I July 2017 14 PV Cell Fab Production Environment • Si cell technologies require minimal clean space; thin-film technologies do not require any clean space • ISO 7/8 has regulations on airborne particulate contamination of >0.5um particulate size • Developing a deep understanding of manufacturing process tolerances for cleanliness, temperature, and humidity help save facilities cost Si cell technologies – generic production environments
  • 15. © M+W U.S., Inc. I July 2017 15 PV Cell Fab Vibration Considerations Laser & mechanical patterning tools in manufacturing area typically drive any vibration specs SEMs, X-ray, and other e-beam other optical inspection tools in FA labs
  • 16. © M+W U.S., Inc. I July 2017 16 PV Manufacturing Safety Considerations Source: Fthenakis et al. • Certain process chemicals and specialty gases used in the PV manufacturing industry have safety implications • Gaseous effluents present acute safety hazards; scrubbing is typically required Hazardous materials used in PV cell manufacturing
  • 17. © M+W U.S., Inc. I July 2017 17 Safety Considerations Example-Silane Containment Strategies • ICC (International code council) – CGA G13 determines storage and handling code for Silanes and mixtures in PV facilities • Store as minimum volumes as possible • Store Silane cylinders separately from toxic, corrosive, flammable, oxidizing, and water-reactive materials • Locate scrubber for SiH4 outdoors, or in a very ventilated area • Purge storage cabinets continuously with N2, with highly velocity airflow through several ports • Consider explosion resistant cabinets with pads, roof, double fences, and fire protection sprinklers • Install gas monitors, flame detectors with automatic shut-off valves at the cylinder • Dilute the SiH4/H2 effluent from the process or the scrubber with N2 to lower the SiH4 concentration to <0.5% before it mixes with air • Make all exhaust lines of non-combustible material
  • 18. © M+W U.S., Inc. I July 2017 18 PV Cell Fab Fab Design Statistics • Fab statistics consider various PV cell technology types • Facilities infrastructure is generally similar across different PV cell technologies Cost% FabArea%
  • 19. © M+W U.S., Inc. I July 2017 19 PV Fab Generic Pictures Manufacturing area Facilities Area
  • 20. © M+W U.S., Inc. I July 2017 20 PV Fab Generic Pictures Source: PV-Tech / Tesla-SolarCity Source: Mission Solar Energy
  • 21. © M+W U.S., Inc. I July 2017 21 PV Cell Fab Fab Construction – Cost Saving Strategies • Pre-fab buildings • Modular cleanrooms • Pre-fab piping racks, equipment skids, etc. • Process tool installation modules such as high-purity piping Deploying the use of prefabricated construction modules helps reduce project schedules and labor costs
  • 22. © M+W U.S., Inc. I July 2017 22 Fab Energy Management Case Study: Hi-tech Manufacturing Fab • Energy savings strategy for a fully operational hi-tech manufacturing facility is illustrated • Learnings are applicable to PV fabs as well • Efficient design & management of facility systems is a “low” hanging fruit for reducing overall energy footprint, and can have a potential ROI of <3 years # System Changes Power Saving Power Saving Natural Gas Saving Energy Cost Saving Payback MWh/a KW (Peak) MWh/a Years 1 Cleanroom Cleanroom Specification Change 965 150 1159 61,118$ NA 2 Make-up Air Make-up Air Supply Temperature Reduction 589 67 654 44,954$ NA 3 Chilled Water Chilled Water Supply Temperature Increase 687 TBD 40,602$ NA 4 Vacuum Temporary Shut-off 146 33 8,608$ NA 5 Cleanroom Cleanroom Air Velocity Reduction 676 77 39,936$ NA 6 Ultra Pure Water Replace Electric with Hot Water Heating 10186 1170 -11647 421,486$ 1.6 7 Exhaust Heat/Particle Exhaust Recycling 464 53 436 34,217$ 2.1 8 Hot Water Installation of VSD at Pumps 864 215 51,062$ 2.4 9 Chilled Water Installation of VSD at Pumps 1405 TBD 83,036$ 2.9 10 Make-up air Final Filter Replacements 387 44 -430 16,195$ 3.0 Total 16369 1809 -9828 801,214$ Total without risk 15504 1660 -10986 740,096$ Set-point changes Hardware changes
  • 23. © M+W U.S., Inc. I July 2017 23 PV Manufacturing Facility Summary: Collaborative Effort to Drive Down Costs 1.0 0.5 0.0 FacilitiesandOperationCost(a.u.) Technology Improvement Fab Safety Engineering High Throughput Process Tools Material Supply Chain Process Equipment & Technology Safety Purchasing PV Manufacturer Focus M+W’s Value to PV Manufacturer Fab Energy Management Lessons Learnt Optimized Building & Facilities Industrial Engineering Energy Efficiency Benchmarking
  • 24. www.mwgroup.net Contact Ankush Halbe Ankush.Halbe@mwgroup.net M+W U.S., Inc. 201 Fuller Road, Suite 401 Albany, NY 12210 518.450.9924 THANK YOU Visit us at Impress Lounge (Moscone Center Rooftop)!