SlideShare ist ein Scribd-Unternehmen logo
1 von 10
Downloaden Sie, um offline zu lesen
Republic of the Philippines
POLYTECHNIC UNIVERSITY OF THE PHILIPPINES
Sto. Tomas Branch
A CASE STUDY RELATIVE TO LOSS TIME AND MANPOWER REDUCTION
IN GLASS DELIVERY AT EPSON PRECISION (PHILIPPINES) INC.
by:
Alina, Jassfer D.
Republic of the Philippines
POLYTECHNIC UNIVERSITY OF THE PHILIPPINES
Sto. Tomas Branch
LOSS TIME AND MANPOWER REDUCTION IN GLASS DELIVERY
AT EPSON PRECISION (PHILIPPINES) INC.
I. PROBLEM BACKGROUND
The glass that will be used for RN10 models at IJ Production Scanner Sub-Assembly are
delivered at the Sub- Assembly Kitting Area to Scanner Sub- Assembly Area 5. Those glasses are
used to build a scanner assembly that is a sub component of a printer. The Warehouse
department stated that based on the audit they conducted, waiting time was observed and
currently happening, so they want to convert this loss time (waiting time) to productive time.
The processes involved for glass delivery to Scanner Sub- Assembly Area 5 production line
that can be used to address and solve the problem are as follows:
1. Get parts to the parts location.
2. Deliver the parts to the designated line.
3. Put parts in the buffer location.
4. Get empty jig in the buffer location
5. Go back to the parts location.
6. Waiting occurs.
Republic of the Philippines
POLYTECHNIC UNIVERSITY OF THE PHILIPPINES
Sto. Tomas Branch
Line Handled (3 lines)
Loss Time 4.31 hour
Working time 2.94 hour
Cycle time
Prod Dept. (Air blowers') 5.76 minutes
WHSE Dept. (Glass Delivery) 1.843 minutes
While the production operators are preparing the glass, material handlers have to wait
before they can deliver the glass in the production lines.
Table 1.a Process cycle time
Table 1.b Loss Time and Working Time per Manpower
The Production department air blowers’ process time in table 1.a is inefficient than the
process time of glass delivery of Warehouse department.
In table 1.b, the loss time of material handlers per shift occur when they finish replenishing
the parts in every station. Due to the high contribution of loss time, it is possible to reduce
manpower in the process of glass delivery.
II. PROBLEM STATEMENT
There is an existing waiting time (loss time) in the process of glass delivery at
Warehouse Department – Inkjet Printer Section.
III. OBJECTIVES OF THE STUDY
The objective of the study is to identify if there is a possibility to reduce manpower
from the glass delivery. This objective asserts the statement of the problem with the
general objectives and specific objectives which are the desired outcome of the research
process.
General Objective
The general objective of the study is to determine how to reduce manpower thru
loss time reduction in the said process.
Republic of the Philippines
POLYTECHNIC UNIVERSITY OF THE PHILIPPINES
Sto. Tomas Branch
Specific Objective
These are the following objectives that would like to achieve.
 To check if Material Handlers in glass delivery can handle additional line in
Scanner Sub-Assembly
 To improve the process of Material Handlers that can reduce loss time due to
waiting time
IV. ASSUMPTIONS AND AREAS OF CONSIDERATION
The basic assumptions that can be utilized in preparing the plan, provided by the
Warehouse Departments Inkjet Section are considered. It provides a contact person that
should be coordinated, or discontinuity responsible person for the area.
The Department of Warehouse Efficiency Group Section is the “team leader” in any
manpower budget incident. They should be notified in the event of reducing or adding of
manpower incident that occurs on the EPSON warehouse, or is reported from off- site
regarding an off-site incident. They are also the key vortex of information regarding
incidents.
The following conditions were considered during the study:
1. Cycle Time
 The preparation time for glass preparation/air blow process in production
department. .
 The glass delivery process time by the warehouse manpower to the Scanner
Sub-Assembly Area 5.
2. 2-box system
 2-box system is a system that limits the buffer stock (Work in process) in
every station of the line in EPPI.
 Implementation of 2-box system is extremely difficult to deal with,
regarding changing the line handled by the manpower.
Republic of the Philippines
POLYTECHNIC UNIVERSITY OF THE PHILIPPINES
Sto. Tomas Branch
Standard
Time
Allowance
Factor
WorkHours/
Shift
Cycle/Shift
Parts
Delivery
Line/s Target/Line
Line
Requirement
MP
Requirement
0.04hour 22.71% 7.25hour 177.52hour 40 3 2880glass 72glass 0.4056
Simulation
3. Process
 Currently, the WPS (Work Standard Procedure) for glass delivery contributes
to the high percentage of loss time in EPPI.
V. ALTERNATIVE COURSES OF ACTIONS
1. STICK WITH THE CURRENT SITUATION
For the current design process, the productive time for Material Handlers per shift
(7.25 hours) is 2.94 hours and the non-productive time (loss time) is 4.31 hours. In terms
on manpower count, currently there are 4 Material Handlers for day shift and 2 for night
shift. Each material handler handles 3 lines.
Table 2 Manpower requirement for Glass Delivery
2. ADDITIONAL LINE FOR MATERIAL HANDLERS (REDUCE MANPOWER)
Currently, the cycle time and manpower requirement for Material Handlers are shown in the table
below;
Table 3.1 Existing manpower simulation for glass delivery
TOTAL 5 Manpower 21.55 hours
Line MP Allocation Loss Time Line MP Allocation Loss Time
Line 01 Line 14
Line 02 Line 15
Line 03 Line 16
Line 04 Line 17
Line 05 Line 19
Line 06 Line 18
Line 07
Line 12
Line 13
4.31 hours
4.31 hours
Manpower Requirement
1 Manpower
1 Manpower
1 Manpower
1 Manpower
1 Manpower
Manpower Requirement
4.31 hours
4.31 hours
4.31 hours
Republic of the Philippines
POLYTECHNIC UNIVERSITY OF THE PHILIPPINES
Sto. Tomas Branch
Before After
MP Allocation MP Allocation
Line 01
Line 02
Line 03
Line 04
Line 05
Line 06
Line 07
Line 12
Line 13
Line 14
Line 15
Line 16
Line 17
Line 19
Line 18
TOTAL 5MP 4MP
1MP
1MP
1MP
1MP
1MP
1MP
Manpower Requirement
Line
1MP
1MP
1MP
In the proposed design process, the cycle time and manpower requirement for Material
Handlers are shown in the table below;
Table 3.2 Proposed manpower simulation for glass delivery
Table 3.3 Comparison between 3 lines handled vs 4 lines handled
From table 3.4, the current manpower allocation for the Glass Delivery is 5 Manpower for 15
lines in Scanner Sub-Assembly Area 5. After the study, we came up to a conclusion that the study
can reduce 1 Manpower for the said process. From the current manpower ratio 1 Manpower is to
3 Lines became 1 Manpower is to 4 lines.
Table 3.4 Manpower Allocation for Glass Delivery
TAKT TIME
ALLOWANCE
FACTOR
WORK/HOURS
/ SHIFT
CYCLE/
SHIFT
PARTS
DELIVERY
LINE/S TARGET/LINE
LINE
REQUIREMENT
MP
REQUIREMENT
.05hour 22.71% 7.25 149 40 4 3840 96 0.6454
Simulation
BEFORE AFTER
Loss Time (hours) 4.31 2.57
Working Time (hours) 2.94 4.68
Idle converted to WT 1.74
Republic of the Philippines
POLYTECHNIC UNIVERSITY OF THE PHILIPPINES
Sto. Tomas Branch
The overall problem solving process is captured with five step problem solving technique. This
is the best starting place, giving you a problem-solving overview, and a structured process to
follow. The 5 why technique fits into the analysis stage of the process.
In table 3.5 you saw a Why Table of a personal complain by the material handlers for glass
delivery. It turned out that it was because of the plant layout in Scanner sub-assembly Area 5.
Though there are several possible answers listed in Why Table to address the top problem caused
by the poor plant layout.
Why table fixed the real root cause of the failure – glass delivery problem. The plant layout is
the latent cause. It remains there waiting to trigger more troubles in future. EPPI Company will
have many problems with this layout. This is the companies own worst enemy and by default.
As the researcher of this process, it is clearly that the plant layout of Area 5 is a huge risk.
Should you come up to relay out or put it in an easy way? The latent causes are the most critical
ones to find, but they are usually the hardest to deal with and often they are embarrassing for all
involved.
Finally we get into the region of latency where individual beliefs, values lack of vital knowledge
and personal opinions breach system protection. A failure event should be traced back to its latent
factors.
Table 3.5 5 Why’s Question Worksheet for Glass Delivery
Fit the trolley to the gap
between the lines
Plant re-layout
Go to the MES, and discuss the
problems
Solution
5 Why Question Table
Date: May 12, 2014Team Members: OJT-Alina, SGL J. Federoso, SGL M. Nora
Problem Statement: Personal complain by the material handlers for glass delivery
Recommended Solution: Fit the trolley for glass delivery to the layout in Scanner Sub-Assembly Area 5
Latent Issues: The plant layout of company can cause disturbances both people and machines
Why Questions
3W2H Answers
(with what, when, where, how, how much)
Set standard weight for Jigs
Make a trolley for glass
delivery
Because the Glass and Jigs are heavy
Because the Material Handlers carry it
manually.
Because the Trolley for Glass Delivery cannot
pass/enter between the lines per station
Because the layout in Scanner Sub-Assembly is
to narrow.
Because the Manufacturing Engineering
Section (MES) was responsible for that layout.
1. Why there is a personal complain?
2. Why did the glass and jigs are heavy?
3. Why did the MH carry it manually?
4. Why trolleys cannot enter/pass?
5. Why the layout to narrow?
Republic of the Philippines
POLYTECHNIC UNIVERSITY OF THE PHILIPPINES
Sto. Tomas Branch
Dayshift Nightshift
Alternative 1 0.41 4 3 3 lines 4.31 hours 2.94 hours
Alternative 2 0.65 3 2 4 lines 2.57 hours 4.68 hours
Manpower
Requirement
Manpower Allocated Line
Handle
Loss Time
Working
Time
VI. RECOMMENDATION
Upon the evaluation of the courses of action made, alternative 2 could help in providing
solution to the problem stated.
The following recommendations are offered to the warehouse department inkjet section in
the field of efficiency.
1. Given the changing line handled by the material handlers, the potential loss time or waiting
time can be converted to productive time will be 1.74 hours.
2. From Table 4, while the current manpower ratio of one (1) Manpower to three (3) lines, it
may be advantageous to change the manpower ratio to one (1) Manpower to four (4) lines.
3. From the table 3.5, glass trolley should be fitted to the gap between the lines in Scanner
Sub-assembly to easily pass the trolley.
4. Based on the results of this study, manpower reduction will have a great positive effect to
the weekly manpower budget of the warehouse department (efficiency group)
5. 2-box system should be eliminated, to maximize the manpower requirement in every
process inside the Epson Precision (Philippines) Inc.
The glass delivery current process should remain operational until the proposed design
process and structures are implemented. The concerned departments (Training, Efficiency, and
Production and MES departments) would be adversely affected by this study. Revised processes
and structural changes in line and manpower with the detailed recommendations are contained in
this study.
Table 4 Difference between 3 lines handled to 4 lines handled
Republic of the Philippines
POLYTECHNIC UNIVERSITY OF THE PHILIPPINES
Sto. Tomas Branch
Process: GlassDelivery
Objective: Tocheckif Material Handlersinglassdeliverycanhandle additional line inScannerSub-Assembly
Purpose: Toreduce losstime due towaitingtime
No. ImplementationPlan 7-May 8-May 9-May 12-May 13-May 14-May 15-May 16-May 19-May 20-May 21-May 22-May 23-May
Remarks:On-going(8lineshasnotbeenmaterializedbecause of the 2-box system)
Plan
Actual
Remarks:On-going(4lines)
Plan
Actual
Remarks:The projecthasbeenimplemented.Material Handlerswill handle 4linesforGlassDelivery
Plan
Actual
Plan
Actual
Preparedby:
JassferAlina
Checkedby:
JasonFederoso
Approvedby:
WhSEMGRLouisaSilang
2
3
Checkingandreview of Effectiveness(Glass
Delivery)
4
May,2014
Executingthe proposedtrial.Material Handlerswill
handle 8lines
Executingthe proposedtrial.Material Handlerswill
handle 4lines
1
Discussionwiththe concernedgroupsregardingthe
proposedtrial inGlassdelivery
Plan
Actual
VII. IMPLEMENTATION PLAN
Table 5 Gantt chart for Implementation Plan
In the table 5 above, the material handlers will handle 8 lines schedule at May 8th
. The
tasks are linked, so we have set a ‘Must Start On’ constraint. But because of the 2-box system, 1
Manpower is to 8 lines was not materialize. 1
So, we come up to a solution that material handlers will handle 4 lines instead of 8 lines
that will also consider the 2 box-systems. At May 9th
, ‘Must Start On’ must set to start the trial for
6 days. May 19th
, 1 week for checking and review of the effectiveness of Material handlers that
will handle 4 lines have been materializing.
1
2box system – Only 2 buffer/stocks of replenishment per process in EPPI.
Republic of the Philippines
POLYTECHNIC UNIVERSITY OF THE PHILIPPINES
Sto. Tomas Branch
As a result of the study,
1. Monthly manpower budget reduced (manpower cost)
2. Manpower count reduced
Before After
Dayshift Nightshift Dayshift Nightshift
Manpower Count 5 5 4 4
3. Loss time (Non-productive time) reduced
Before After
Loss Time 4.31 hours 2.57 hours
Working Time 2.94 hours 4.68 hours
Idle time converted to Working time 1.75 hours
4. The Glass delivery process maximized
5. Maximized manpower allocation

Weitere Àhnliche Inhalte

Ähnlich wie Case Study-INEN3293

Joined document 24_5
Joined document 24_5Joined document 24_5
Joined document 24_5JOSEPH FRANCIS
 
Eg Lean Case Studies
Eg Lean Case StudiesEg Lean Case Studies
Eg Lean Case Studiesguestc3f47e
 
Trust Tech F119 Rapid Assessment & Hoshin Workshop Report Out
Trust Tech F119 Rapid Assessment & Hoshin Workshop Report OutTrust Tech F119 Rapid Assessment & Hoshin Workshop Report Out
Trust Tech F119 Rapid Assessment & Hoshin Workshop Report OutExerciseLeanLLC
 
Application of Lean Concepts in Molding Department
Application of Lean Concepts in Molding DepartmentApplication of Lean Concepts in Molding Department
Application of Lean Concepts in Molding DepartmentIRJET Journal
 
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...ijsrd.com
 
Work Portfolio 1
Work Portfolio 1Work Portfolio 1
Work Portfolio 1Phumzile Zungu
 
SCORE implimentation (Blue Nile PP bag).pptx
SCORE implimentation (Blue Nile PP bag).pptxSCORE implimentation (Blue Nile PP bag).pptx
SCORE implimentation (Blue Nile PP bag).pptxmolla17
 
SMC CFT 2012-13-IInd Half.
SMC CFT 2012-13-IInd Half.SMC CFT 2012-13-IInd Half.
SMC CFT 2012-13-IInd Half.Santhana Bharathi
 
Recommendation of Progrizive
Recommendation of ProgriziveRecommendation of Progrizive
Recommendation of Progrizivejeromme nastor
 
Kaizen Blitz multicoat loading area April 2005
Kaizen Blitz multicoat loading area April 2005Kaizen Blitz multicoat loading area April 2005
Kaizen Blitz multicoat loading area April 2005D9 Process Improvement
 
1D - 8D Report A
1D - 8D Report A1D - 8D Report A
1D - 8D Report ALee Kin Nan
 
TAILLON - ARTICLE
TAILLON - ARTICLETAILLON - ARTICLE
TAILLON - ARTICLEJoseph Taillon
 
Lean NMR Laboratory Layout
  Lean NMR Laboratory Layout    Lean NMR Laboratory Layout
Lean NMR Laboratory Layout Javier Siles
 
Executive Summary El
Executive Summary ElExecutive Summary El
Executive Summary ElNur El Syahira
 
Report on JIT , for Projects and Seminars
Report on JIT , for Projects and SeminarsReport on JIT , for Projects and Seminars
Report on JIT , for Projects and Seminarsomkar jagtap
 
Atos Worldline Project I Rui Zhu Telerex
Atos Worldline Project I Rui Zhu TelerexAtos Worldline Project I Rui Zhu Telerex
Atos Worldline Project I Rui Zhu TelerexRui Zhu
 

Ähnlich wie Case Study-INEN3293 (20)

Joined document 24_5
Joined document 24_5Joined document 24_5
Joined document 24_5
 
Eg Lean Case Studies
Eg Lean Case StudiesEg Lean Case Studies
Eg Lean Case Studies
 
Anand dossier 2
Anand dossier 2Anand dossier 2
Anand dossier 2
 
Trust Tech F119 Rapid Assessment & Hoshin Workshop Report Out
Trust Tech F119 Rapid Assessment & Hoshin Workshop Report OutTrust Tech F119 Rapid Assessment & Hoshin Workshop Report Out
Trust Tech F119 Rapid Assessment & Hoshin Workshop Report Out
 
Application of Lean Concepts in Molding Department
Application of Lean Concepts in Molding DepartmentApplication of Lean Concepts in Molding Department
Application of Lean Concepts in Molding Department
 
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
 
Work Portfolio 1
Work Portfolio 1Work Portfolio 1
Work Portfolio 1
 
SCORE implimentation (Blue Nile PP bag).pptx
SCORE implimentation (Blue Nile PP bag).pptxSCORE implimentation (Blue Nile PP bag).pptx
SCORE implimentation (Blue Nile PP bag).pptx
 
SMC CFT 2012-13-IInd Half.
SMC CFT 2012-13-IInd Half.SMC CFT 2012-13-IInd Half.
SMC CFT 2012-13-IInd Half.
 
Recommendation of Progrizive
Recommendation of ProgriziveRecommendation of Progrizive
Recommendation of Progrizive
 
Sps ap05
Sps ap05Sps ap05
Sps ap05
 
Kaizen Blitz multicoat loading area April 2005
Kaizen Blitz multicoat loading area April 2005Kaizen Blitz multicoat loading area April 2005
Kaizen Blitz multicoat loading area April 2005
 
1D - 8D Report A
1D - 8D Report A1D - 8D Report A
1D - 8D Report A
 
_TUBES.pptx
_TUBES.pptx_TUBES.pptx
_TUBES.pptx
 
TAILLON - ARTICLE
TAILLON - ARTICLETAILLON - ARTICLE
TAILLON - ARTICLE
 
Lean NMR Laboratory Layout
  Lean NMR Laboratory Layout    Lean NMR Laboratory Layout
Lean NMR Laboratory Layout
 
Alexa
AlexaAlexa
Alexa
 
Executive Summary El
Executive Summary ElExecutive Summary El
Executive Summary El
 
Report on JIT , for Projects and Seminars
Report on JIT , for Projects and SeminarsReport on JIT , for Projects and Seminars
Report on JIT , for Projects and Seminars
 
Atos Worldline Project I Rui Zhu Telerex
Atos Worldline Project I Rui Zhu TelerexAtos Worldline Project I Rui Zhu Telerex
Atos Worldline Project I Rui Zhu Telerex
 

Mehr von Jassfer Alina

CERTIFIED INDUSTRIAL ENGINEER
CERTIFIED INDUSTRIAL ENGINEERCERTIFIED INDUSTRIAL ENGINEER
CERTIFIED INDUSTRIAL ENGINEERJassfer Alina
 
Six Sigma Certification
Six Sigma CertificationSix Sigma Certification
Six Sigma CertificationJassfer Alina
 
Moa template2013 short
Moa template2013 shortMoa template2013 short
Moa template2013 shortJassfer Alina
 
Moa template2013 long
Moa template2013 longMoa template2013 long
Moa template2013 longJassfer Alina
 
Variable control chart
Variable control chartVariable control chart
Variable control chartJassfer Alina
 
Technical Performance Measures
Technical Performance Measures Technical Performance Measures
Technical Performance Measures Jassfer Alina
 

Mehr von Jassfer Alina (7)

CERTIFIED INDUSTRIAL ENGINEER
CERTIFIED INDUSTRIAL ENGINEERCERTIFIED INDUSTRIAL ENGINEER
CERTIFIED INDUSTRIAL ENGINEER
 
Six Sigma Certification
Six Sigma CertificationSix Sigma Certification
Six Sigma Certification
 
Moa template2013 short
Moa template2013 shortMoa template2013 short
Moa template2013 short
 
Moa template2013 long
Moa template2013 longMoa template2013 long
Moa template2013 long
 
Variable control chart
Variable control chartVariable control chart
Variable control chart
 
Technical Performance Measures
Technical Performance Measures Technical Performance Measures
Technical Performance Measures
 
Heat Transfer
Heat TransferHeat Transfer
Heat Transfer
 

KĂŒrzlich hochgeladen

🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniquesugginaramesh
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Gurgaon âœĄïž9711147426✹Call In girls Gurgaon Sector 51 escort service
Gurgaon âœĄïž9711147426✹Call In girls Gurgaon Sector 51 escort serviceGurgaon âœĄïž9711147426✹Call In girls Gurgaon Sector 51 escort service
Gurgaon âœĄïž9711147426✹Call In girls Gurgaon Sector 51 escort servicejennyeacort
 

KĂŒrzlich hochgeladen (20)

🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniques
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Gurgaon âœĄïž9711147426✹Call In girls Gurgaon Sector 51 escort service
Gurgaon âœĄïž9711147426✹Call In girls Gurgaon Sector 51 escort serviceGurgaon âœĄïž9711147426✹Call In girls Gurgaon Sector 51 escort service
Gurgaon âœĄïž9711147426✹Call In girls Gurgaon Sector 51 escort service
 

Case Study-INEN3293

  • 1. Republic of the Philippines POLYTECHNIC UNIVERSITY OF THE PHILIPPINES Sto. Tomas Branch A CASE STUDY RELATIVE TO LOSS TIME AND MANPOWER REDUCTION IN GLASS DELIVERY AT EPSON PRECISION (PHILIPPINES) INC. by: Alina, Jassfer D.
  • 2. Republic of the Philippines POLYTECHNIC UNIVERSITY OF THE PHILIPPINES Sto. Tomas Branch LOSS TIME AND MANPOWER REDUCTION IN GLASS DELIVERY AT EPSON PRECISION (PHILIPPINES) INC. I. PROBLEM BACKGROUND The glass that will be used for RN10 models at IJ Production Scanner Sub-Assembly are delivered at the Sub- Assembly Kitting Area to Scanner Sub- Assembly Area 5. Those glasses are used to build a scanner assembly that is a sub component of a printer. The Warehouse department stated that based on the audit they conducted, waiting time was observed and currently happening, so they want to convert this loss time (waiting time) to productive time. The processes involved for glass delivery to Scanner Sub- Assembly Area 5 production line that can be used to address and solve the problem are as follows: 1. Get parts to the parts location. 2. Deliver the parts to the designated line. 3. Put parts in the buffer location. 4. Get empty jig in the buffer location 5. Go back to the parts location. 6. Waiting occurs.
  • 3. Republic of the Philippines POLYTECHNIC UNIVERSITY OF THE PHILIPPINES Sto. Tomas Branch Line Handled (3 lines) Loss Time 4.31 hour Working time 2.94 hour Cycle time Prod Dept. (Air blowers') 5.76 minutes WHSE Dept. (Glass Delivery) 1.843 minutes While the production operators are preparing the glass, material handlers have to wait before they can deliver the glass in the production lines. Table 1.a Process cycle time Table 1.b Loss Time and Working Time per Manpower The Production department air blowers’ process time in table 1.a is inefficient than the process time of glass delivery of Warehouse department. In table 1.b, the loss time of material handlers per shift occur when they finish replenishing the parts in every station. Due to the high contribution of loss time, it is possible to reduce manpower in the process of glass delivery. II. PROBLEM STATEMENT There is an existing waiting time (loss time) in the process of glass delivery at Warehouse Department – Inkjet Printer Section. III. OBJECTIVES OF THE STUDY The objective of the study is to identify if there is a possibility to reduce manpower from the glass delivery. This objective asserts the statement of the problem with the general objectives and specific objectives which are the desired outcome of the research process. General Objective The general objective of the study is to determine how to reduce manpower thru loss time reduction in the said process.
  • 4. Republic of the Philippines POLYTECHNIC UNIVERSITY OF THE PHILIPPINES Sto. Tomas Branch Specific Objective These are the following objectives that would like to achieve.  To check if Material Handlers in glass delivery can handle additional line in Scanner Sub-Assembly  To improve the process of Material Handlers that can reduce loss time due to waiting time IV. ASSUMPTIONS AND AREAS OF CONSIDERATION The basic assumptions that can be utilized in preparing the plan, provided by the Warehouse Departments Inkjet Section are considered. It provides a contact person that should be coordinated, or discontinuity responsible person for the area. The Department of Warehouse Efficiency Group Section is the “team leader” in any manpower budget incident. They should be notified in the event of reducing or adding of manpower incident that occurs on the EPSON warehouse, or is reported from off- site regarding an off-site incident. They are also the key vortex of information regarding incidents. The following conditions were considered during the study: 1. Cycle Time  The preparation time for glass preparation/air blow process in production department. .  The glass delivery process time by the warehouse manpower to the Scanner Sub-Assembly Area 5. 2. 2-box system  2-box system is a system that limits the buffer stock (Work in process) in every station of the line in EPPI.  Implementation of 2-box system is extremely difficult to deal with, regarding changing the line handled by the manpower.
  • 5. Republic of the Philippines POLYTECHNIC UNIVERSITY OF THE PHILIPPINES Sto. Tomas Branch Standard Time Allowance Factor WorkHours/ Shift Cycle/Shift Parts Delivery Line/s Target/Line Line Requirement MP Requirement 0.04hour 22.71% 7.25hour 177.52hour 40 3 2880glass 72glass 0.4056 Simulation 3. Process  Currently, the WPS (Work Standard Procedure) for glass delivery contributes to the high percentage of loss time in EPPI. V. ALTERNATIVE COURSES OF ACTIONS 1. STICK WITH THE CURRENT SITUATION For the current design process, the productive time for Material Handlers per shift (7.25 hours) is 2.94 hours and the non-productive time (loss time) is 4.31 hours. In terms on manpower count, currently there are 4 Material Handlers for day shift and 2 for night shift. Each material handler handles 3 lines. Table 2 Manpower requirement for Glass Delivery 2. ADDITIONAL LINE FOR MATERIAL HANDLERS (REDUCE MANPOWER) Currently, the cycle time and manpower requirement for Material Handlers are shown in the table below; Table 3.1 Existing manpower simulation for glass delivery TOTAL 5 Manpower 21.55 hours Line MP Allocation Loss Time Line MP Allocation Loss Time Line 01 Line 14 Line 02 Line 15 Line 03 Line 16 Line 04 Line 17 Line 05 Line 19 Line 06 Line 18 Line 07 Line 12 Line 13 4.31 hours 4.31 hours Manpower Requirement 1 Manpower 1 Manpower 1 Manpower 1 Manpower 1 Manpower Manpower Requirement 4.31 hours 4.31 hours 4.31 hours
  • 6. Republic of the Philippines POLYTECHNIC UNIVERSITY OF THE PHILIPPINES Sto. Tomas Branch Before After MP Allocation MP Allocation Line 01 Line 02 Line 03 Line 04 Line 05 Line 06 Line 07 Line 12 Line 13 Line 14 Line 15 Line 16 Line 17 Line 19 Line 18 TOTAL 5MP 4MP 1MP 1MP 1MP 1MP 1MP 1MP Manpower Requirement Line 1MP 1MP 1MP In the proposed design process, the cycle time and manpower requirement for Material Handlers are shown in the table below; Table 3.2 Proposed manpower simulation for glass delivery Table 3.3 Comparison between 3 lines handled vs 4 lines handled From table 3.4, the current manpower allocation for the Glass Delivery is 5 Manpower for 15 lines in Scanner Sub-Assembly Area 5. After the study, we came up to a conclusion that the study can reduce 1 Manpower for the said process. From the current manpower ratio 1 Manpower is to 3 Lines became 1 Manpower is to 4 lines. Table 3.4 Manpower Allocation for Glass Delivery TAKT TIME ALLOWANCE FACTOR WORK/HOURS / SHIFT CYCLE/ SHIFT PARTS DELIVERY LINE/S TARGET/LINE LINE REQUIREMENT MP REQUIREMENT .05hour 22.71% 7.25 149 40 4 3840 96 0.6454 Simulation BEFORE AFTER Loss Time (hours) 4.31 2.57 Working Time (hours) 2.94 4.68 Idle converted to WT 1.74
  • 7. Republic of the Philippines POLYTECHNIC UNIVERSITY OF THE PHILIPPINES Sto. Tomas Branch The overall problem solving process is captured with five step problem solving technique. This is the best starting place, giving you a problem-solving overview, and a structured process to follow. The 5 why technique fits into the analysis stage of the process. In table 3.5 you saw a Why Table of a personal complain by the material handlers for glass delivery. It turned out that it was because of the plant layout in Scanner sub-assembly Area 5. Though there are several possible answers listed in Why Table to address the top problem caused by the poor plant layout. Why table fixed the real root cause of the failure – glass delivery problem. The plant layout is the latent cause. It remains there waiting to trigger more troubles in future. EPPI Company will have many problems with this layout. This is the companies own worst enemy and by default. As the researcher of this process, it is clearly that the plant layout of Area 5 is a huge risk. Should you come up to relay out or put it in an easy way? The latent causes are the most critical ones to find, but they are usually the hardest to deal with and often they are embarrassing for all involved. Finally we get into the region of latency where individual beliefs, values lack of vital knowledge and personal opinions breach system protection. A failure event should be traced back to its latent factors. Table 3.5 5 Why’s Question Worksheet for Glass Delivery Fit the trolley to the gap between the lines Plant re-layout Go to the MES, and discuss the problems Solution 5 Why Question Table Date: May 12, 2014Team Members: OJT-Alina, SGL J. Federoso, SGL M. Nora Problem Statement: Personal complain by the material handlers for glass delivery Recommended Solution: Fit the trolley for glass delivery to the layout in Scanner Sub-Assembly Area 5 Latent Issues: The plant layout of company can cause disturbances both people and machines Why Questions 3W2H Answers (with what, when, where, how, how much) Set standard weight for Jigs Make a trolley for glass delivery Because the Glass and Jigs are heavy Because the Material Handlers carry it manually. Because the Trolley for Glass Delivery cannot pass/enter between the lines per station Because the layout in Scanner Sub-Assembly is to narrow. Because the Manufacturing Engineering Section (MES) was responsible for that layout. 1. Why there is a personal complain? 2. Why did the glass and jigs are heavy? 3. Why did the MH carry it manually? 4. Why trolleys cannot enter/pass? 5. Why the layout to narrow?
  • 8. Republic of the Philippines POLYTECHNIC UNIVERSITY OF THE PHILIPPINES Sto. Tomas Branch Dayshift Nightshift Alternative 1 0.41 4 3 3 lines 4.31 hours 2.94 hours Alternative 2 0.65 3 2 4 lines 2.57 hours 4.68 hours Manpower Requirement Manpower Allocated Line Handle Loss Time Working Time VI. RECOMMENDATION Upon the evaluation of the courses of action made, alternative 2 could help in providing solution to the problem stated. The following recommendations are offered to the warehouse department inkjet section in the field of efficiency. 1. Given the changing line handled by the material handlers, the potential loss time or waiting time can be converted to productive time will be 1.74 hours. 2. From Table 4, while the current manpower ratio of one (1) Manpower to three (3) lines, it may be advantageous to change the manpower ratio to one (1) Manpower to four (4) lines. 3. From the table 3.5, glass trolley should be fitted to the gap between the lines in Scanner Sub-assembly to easily pass the trolley. 4. Based on the results of this study, manpower reduction will have a great positive effect to the weekly manpower budget of the warehouse department (efficiency group) 5. 2-box system should be eliminated, to maximize the manpower requirement in every process inside the Epson Precision (Philippines) Inc. The glass delivery current process should remain operational until the proposed design process and structures are implemented. The concerned departments (Training, Efficiency, and Production and MES departments) would be adversely affected by this study. Revised processes and structural changes in line and manpower with the detailed recommendations are contained in this study. Table 4 Difference between 3 lines handled to 4 lines handled
  • 9. Republic of the Philippines POLYTECHNIC UNIVERSITY OF THE PHILIPPINES Sto. Tomas Branch Process: GlassDelivery Objective: Tocheckif Material Handlersinglassdeliverycanhandle additional line inScannerSub-Assembly Purpose: Toreduce losstime due towaitingtime No. ImplementationPlan 7-May 8-May 9-May 12-May 13-May 14-May 15-May 16-May 19-May 20-May 21-May 22-May 23-May Remarks:On-going(8lineshasnotbeenmaterializedbecause of the 2-box system) Plan Actual Remarks:On-going(4lines) Plan Actual Remarks:The projecthasbeenimplemented.Material Handlerswill handle 4linesforGlassDelivery Plan Actual Plan Actual Preparedby: JassferAlina Checkedby: JasonFederoso Approvedby: WhSEMGRLouisaSilang 2 3 Checkingandreview of Effectiveness(Glass Delivery) 4 May,2014 Executingthe proposedtrial.Material Handlerswill handle 8lines Executingthe proposedtrial.Material Handlerswill handle 4lines 1 Discussionwiththe concernedgroupsregardingthe proposedtrial inGlassdelivery Plan Actual VII. IMPLEMENTATION PLAN Table 5 Gantt chart for Implementation Plan In the table 5 above, the material handlers will handle 8 lines schedule at May 8th . The tasks are linked, so we have set a ‘Must Start On’ constraint. But because of the 2-box system, 1 Manpower is to 8 lines was not materialize. 1 So, we come up to a solution that material handlers will handle 4 lines instead of 8 lines that will also consider the 2 box-systems. At May 9th , ‘Must Start On’ must set to start the trial for 6 days. May 19th , 1 week for checking and review of the effectiveness of Material handlers that will handle 4 lines have been materializing. 1 2box system – Only 2 buffer/stocks of replenishment per process in EPPI.
  • 10. Republic of the Philippines POLYTECHNIC UNIVERSITY OF THE PHILIPPINES Sto. Tomas Branch As a result of the study, 1. Monthly manpower budget reduced (manpower cost) 2. Manpower count reduced Before After Dayshift Nightshift Dayshift Nightshift Manpower Count 5 5 4 4 3. Loss time (Non-productive time) reduced Before After Loss Time 4.31 hours 2.57 hours Working Time 2.94 hours 4.68 hours Idle time converted to Working time 1.75 hours 4. The Glass delivery process maximized 5. Maximized manpower allocation