SlideShare ist ein Scribd-Unternehmen logo
1 von 18
Project Planning and Earned Value Management
Contents Objective Fact about Earned Value Management  Earned Value definitions & descriptions How to Produce Earned Value Introduction to the “Project Planning Approach” utilizing the top level down & bottom level up mechanism for planning a T24 project.  - Two screenshots showing how the lower deliverables can be 		  managed more effectively in Microsoft Sharepoint 	- Microsoft Project and how Earned Value is derived. 	- Weekly Earned Value analytical graph. 	- Earned Value trend analysis across the T24 project. Introduction to the planning process and how it was integrated into the T24 project.  	- Example of a High Level Work Breakdown Structure For a T24 Methodology 		- The planning process 		- The control process Overview of Microsoft Sharepoint T24 Project Dashboard
Objective The objective of this slideshow is to provide the audience with the following: A high level overview of Earned Value Analysis and the benefits of using this analytical method to measure a projects progress. How Earned Value Management enhances  project performance by allowing the project audience to exhume levels of detail from any project and retrieve statistics that can be measured against the baseline under project control. A detailed overview of one specific phase from the project which will define how to approach project planning for this type of project, using combined solutions of both Microsoft Sharepoint Services and Microsoft Project 2007. Define and show how the iterative project planning process works within the Hub T24 project and how the best practice of maintaining and enforcing this process within a project of this magnitude. Review of the project dashboard – Implemented a one stop solution for visual knowledge about the project for senior management.
Facts About Earned Value Organisations often want to know some of the following questions when Considering using the Earned Value Technique  What is EVM? It’s a metric devised to achieve meaningful comparisons between planned and completed work.  Earned Value allows projects to show early indications of cost and schedule overruns within a project by using controlled mechanisms that are enforced before the baseline of the project.  	The three basic main elements of EVT are PV, EV, and AC. These are the core analytical 	acronyms that are used to produce the statistics for EVA.  Why should we adopt the EVT within our organisation and what are the benefits to using EVA within a project? The EVM technique integrates the triple constraints of scope, time and cost and is becoming a wide spread form of tracking mechanism for projects. It evaluates progress analytically and this been known for its proven and established efficiencies it brings to any project.  EVT allows you to have more control and management of the project. Coupled with good planning and effective use of EVM will reduce the impact to a significant number of project issues which are due to schedule and cost overrun.  EVM also aids in negotiations with the end customers about scope increase, because cost and schedule increases nearly always occur due to scope creep and this will be quite evident to stakeholders.   EVM also provides statistics to stakeholders when reporting on project performance because EVM can show past, current and predicted forecast performance and this shows a greater level of detail.
EV Definitions & Descriptions
How To Produce EV The EVT is produced using the built in reporting tool within MPP.  The skill is knowing how to use the tool, and also how to calculate the algebraic equations, so that accurate statistics are collated.  The key to using EV is making sure the planner utilizes the strict controls procedure .When the tolerance margins move outside the threshold .10% the planner must initiate and detect early signs of deviation before the tolerances are breached.  Before a plan can be produced it is common to have all the deliverables in the form of a WBS.  Once the planner has consolidated the deliverables  with thestream lead, who is the owner of the designated phase, then and only then can an MPP plan can be produced.  The following tasks have to be completed before producing a base-lined plan that forms the basis of planned value (PV) ,[object Object],This means that all of the belowdata has to be retrieved and input into the plan.  To do this the following basic fundamentals have to be achieved: ,[object Object]
The dependencies are built upon the independency relationships that is scaled out from the WBS and these are done in either the project plan itself or in a integrated solution that has been designed within MSP.
You also need a list of assumed or available resources including their costs and the designated tasks they have been delegated to own.
Finally export the plan into MSP so that the progress of the work can be tracked by the stream lead. This gives the planner a overview of all of the deliverables, timelines and work to be completed within the project. The planner must track the progress and try to maintain stability and consistency for each of the deliverables. The planner does this by tracking the alerts and reviewing the reports from MSP in real-time. This allows for clear transparency to the project products being delivered and this also allows senior management to have a top level down and bottom level up view of the project. ,[object Object],The planner will then input the statistics from the reports into MPP and the EVM reports are generated. This tool has been used as a KPI to any level of detail within the project and has been a fundamental means of communication without human intervention.
Project Planning Approach A combination of a top level down and a bottom level up approach was used to track and measure the deliverables of the project.   This provides senior management with the ability to view the project from a high level financially and at the lower level products. Products like MPP and MSP where used to store, maintain and effectively manage the project and to provide advanced dynamic reporting to the stakeholders.  The following slides are document outputs from MSP and MPP showing the planning solutions that were used for the T24 project at KBL bank, which includes an example of a T24 WBS methodology.
High Level WBS For A T24 Project Including the Methodology START Gap Analysis Functional Design DST based Development System Testing Functional Catalogue Local Code Conversion Migration Testing Migration Design Technical Design Non Functional Testing Architecture Unit Testing Build Team UAT Testing Business Process  Testing Dress Rehearsal Implementation   Migration Cutover Training END BPT & UAT Testing Team Implementation Team
MSP Lower Level Deliverables
MSP With Gantt Chart
Microsoft Project With Earned Value The below example is a screen shot showing the high level deliverables of the securities areasituated within the design & analysis phase of the project. This report allows seniormanagement to view the project at phase level. The below screenshot shows how we retrievethe Earned Value statistics.
Analytical Earned Value Graph
Overall T24 Project EV Report
Introduction To The Planning Process A vital part to achieving the T24 implementation is to have strategic plan for how every piece of the project. To do this multiple solutions were needed to maintain, administer, and utilise within the project. To maintain an efficient and fluid system for integrating and maintaining project plans you should break the planning process down into two parts. ,[object Object]
The Control ProcessThe Planning Processis a high level overview that provides a detailed analysis and breakdown of each work stream in the T24 program.  The goal of the planning phase is to have clear timeframes driven by concrete milestones, by which the project can be measured against. The Control Process is where you should monitor the progress and constantly review the SPI and CPI for the project, so that the tolerance thresholds are controlled. If you exceed a project tolerance then actions are invoked to allow senior management to review the relevant work stream and implement corrective action to reduce or eradicate the issue at an early stage.  The breakdown of the high level solutions for the planning and control processes can be seen in the next slides.

Weitere ähnliche Inhalte

Was ist angesagt?

EA as an Actionable Architecture
EA as an Actionable ArchitectureEA as an Actionable Architecture
EA as an Actionable ArchitectureJerald Burget
 
Customer-centric innovation enabled by cloud
 Customer-centric innovation enabled by cloud Customer-centric innovation enabled by cloud
Customer-centric innovation enabled by cloudThoughtworks
 
Avoiding the Pitfalls of Capitalizing Software in an Agile World
Avoiding the Pitfalls of Capitalizing Software in an Agile WorldAvoiding the Pitfalls of Capitalizing Software in an Agile World
Avoiding the Pitfalls of Capitalizing Software in an Agile WorldLeadingAgile
 
Modernize Your Banking Platform with Temenos and NuoDB
Modernize Your Banking Platform with Temenos and NuoDBModernize Your Banking Platform with Temenos and NuoDB
Modernize Your Banking Platform with Temenos and NuoDBNuoDB
 
IT Infrastructure Management Powerpoint Presentation Slides
IT Infrastructure Management Powerpoint Presentation SlidesIT Infrastructure Management Powerpoint Presentation Slides
IT Infrastructure Management Powerpoint Presentation SlidesSlideTeam
 
OSS/BSS Landscape
OSS/BSS LandscapeOSS/BSS Landscape
OSS/BSS Landscapeanandbajaj
 
Driving the Telecom Digital Transformation through Open Digital Architecture
Driving the Telecom Digital Transformation through Open Digital ArchitectureDriving the Telecom Digital Transformation through Open Digital Architecture
Driving the Telecom Digital Transformation through Open Digital ArchitectureSanjeewaRavi
 
eTOM framework as key component of process reengineering during implementatio...
eTOM framework as key component of process reengineering during implementatio...eTOM framework as key component of process reengineering during implementatio...
eTOM framework as key component of process reengineering during implementatio...Comarch
 
Effective portfolio management
Effective portfolio managementEffective portfolio management
Effective portfolio managementDave Angelow
 
Implementing agile iterative project delivery approach and achieving business...
Implementing agile iterative project delivery approach and achieving business...Implementing agile iterative project delivery approach and achieving business...
Implementing agile iterative project delivery approach and achieving business...Alan McSweeney
 
Learn Togaf 9.1 in 100 slides!
Learn Togaf 9.1 in 100 slides!Learn Togaf 9.1 in 100 slides!
Learn Togaf 9.1 in 100 slides!Sam Mandebvu
 
The First 100 Days for a New CIO - Using the Innovation Value Institute IT Ca...
The First 100 Days for a New CIO - Using the Innovation Value Institute IT Ca...The First 100 Days for a New CIO - Using the Innovation Value Institute IT Ca...
The First 100 Days for a New CIO - Using the Innovation Value Institute IT Ca...Alan McSweeney
 
SaaS Companies: What Costs Should Be Capitalized?
SaaS Companies: What Costs Should Be Capitalized?SaaS Companies: What Costs Should Be Capitalized?
SaaS Companies: What Costs Should Be Capitalized?Armanino LLP
 
Kafka for Live Commerce to Transform the Retail and Shopping Metaverse
Kafka for Live Commerce to Transform the Retail and Shopping MetaverseKafka for Live Commerce to Transform the Retail and Shopping Metaverse
Kafka for Live Commerce to Transform the Retail and Shopping MetaverseKai Wähner
 
Eugenio Mauri: présentation de TOGAF
Eugenio Mauri: présentation de TOGAFEugenio Mauri: présentation de TOGAF
Eugenio Mauri: présentation de TOGAFEugenio Mauri
 
Enterprise Architecture Implementation And The Open Group Architecture Framew...
Enterprise Architecture Implementation And The Open Group Architecture Framew...Enterprise Architecture Implementation And The Open Group Architecture Framew...
Enterprise Architecture Implementation And The Open Group Architecture Framew...Alan McSweeney
 
Webinar: Monitoring & Orchestrating Your Microservices Landscape using Workfl...
Webinar: Monitoring & Orchestrating Your Microservices Landscape using Workfl...Webinar: Monitoring & Orchestrating Your Microservices Landscape using Workfl...
Webinar: Monitoring & Orchestrating Your Microservices Landscape using Workfl...camunda services GmbH
 
Next generation OSS/BSS architecture
Next generation OSS/BSS architectureNext generation OSS/BSS architecture
Next generation OSS/BSS architectureEricsson
 

Was ist angesagt? (20)

EA as an Actionable Architecture
EA as an Actionable ArchitectureEA as an Actionable Architecture
EA as an Actionable Architecture
 
Customer-centric innovation enabled by cloud
 Customer-centric innovation enabled by cloud Customer-centric innovation enabled by cloud
Customer-centric innovation enabled by cloud
 
TOGAF in 8 Steps
TOGAF in 8 StepsTOGAF in 8 Steps
TOGAF in 8 Steps
 
Avoiding the Pitfalls of Capitalizing Software in an Agile World
Avoiding the Pitfalls of Capitalizing Software in an Agile WorldAvoiding the Pitfalls of Capitalizing Software in an Agile World
Avoiding the Pitfalls of Capitalizing Software in an Agile World
 
Modernize Your Banking Platform with Temenos and NuoDB
Modernize Your Banking Platform with Temenos and NuoDBModernize Your Banking Platform with Temenos and NuoDB
Modernize Your Banking Platform with Temenos and NuoDB
 
Network Operations Center
Network Operations Center  Network Operations Center
Network Operations Center
 
IT Infrastructure Management Powerpoint Presentation Slides
IT Infrastructure Management Powerpoint Presentation SlidesIT Infrastructure Management Powerpoint Presentation Slides
IT Infrastructure Management Powerpoint Presentation Slides
 
OSS/BSS Landscape
OSS/BSS LandscapeOSS/BSS Landscape
OSS/BSS Landscape
 
Driving the Telecom Digital Transformation through Open Digital Architecture
Driving the Telecom Digital Transformation through Open Digital ArchitectureDriving the Telecom Digital Transformation through Open Digital Architecture
Driving the Telecom Digital Transformation through Open Digital Architecture
 
eTOM framework as key component of process reengineering during implementatio...
eTOM framework as key component of process reengineering during implementatio...eTOM framework as key component of process reengineering during implementatio...
eTOM framework as key component of process reengineering during implementatio...
 
Effective portfolio management
Effective portfolio managementEffective portfolio management
Effective portfolio management
 
Implementing agile iterative project delivery approach and achieving business...
Implementing agile iterative project delivery approach and achieving business...Implementing agile iterative project delivery approach and achieving business...
Implementing agile iterative project delivery approach and achieving business...
 
Learn Togaf 9.1 in 100 slides!
Learn Togaf 9.1 in 100 slides!Learn Togaf 9.1 in 100 slides!
Learn Togaf 9.1 in 100 slides!
 
The First 100 Days for a New CIO - Using the Innovation Value Institute IT Ca...
The First 100 Days for a New CIO - Using the Innovation Value Institute IT Ca...The First 100 Days for a New CIO - Using the Innovation Value Institute IT Ca...
The First 100 Days for a New CIO - Using the Innovation Value Institute IT Ca...
 
SaaS Companies: What Costs Should Be Capitalized?
SaaS Companies: What Costs Should Be Capitalized?SaaS Companies: What Costs Should Be Capitalized?
SaaS Companies: What Costs Should Be Capitalized?
 
Kafka for Live Commerce to Transform the Retail and Shopping Metaverse
Kafka for Live Commerce to Transform the Retail and Shopping MetaverseKafka for Live Commerce to Transform the Retail and Shopping Metaverse
Kafka for Live Commerce to Transform the Retail and Shopping Metaverse
 
Eugenio Mauri: présentation de TOGAF
Eugenio Mauri: présentation de TOGAFEugenio Mauri: présentation de TOGAF
Eugenio Mauri: présentation de TOGAF
 
Enterprise Architecture Implementation And The Open Group Architecture Framew...
Enterprise Architecture Implementation And The Open Group Architecture Framew...Enterprise Architecture Implementation And The Open Group Architecture Framew...
Enterprise Architecture Implementation And The Open Group Architecture Framew...
 
Webinar: Monitoring & Orchestrating Your Microservices Landscape using Workfl...
Webinar: Monitoring & Orchestrating Your Microservices Landscape using Workfl...Webinar: Monitoring & Orchestrating Your Microservices Landscape using Workfl...
Webinar: Monitoring & Orchestrating Your Microservices Landscape using Workfl...
 
Next generation OSS/BSS architecture
Next generation OSS/BSS architectureNext generation OSS/BSS architecture
Next generation OSS/BSS architecture
 

Ähnlich wie T24 Temenos Earned Value Management & Project Planning Presentation

iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...IRJET Journal
 
Integrated Performance Management Scorecard
Integrated Performance Management ScorecardIntegrated Performance Management Scorecard
Integrated Performance Management ScorecardSaravanan Veeraiyan
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement ignitetribes
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
project management plan.pptx
project management plan.pptxproject management plan.pptx
project management plan.pptxNimra zaman
 
Project Management Plan Templatewww.ProjectManagementDocs.com.docx
Project Management Plan Templatewww.ProjectManagementDocs.com.docxProject Management Plan Templatewww.ProjectManagementDocs.com.docx
Project Management Plan Templatewww.ProjectManagementDocs.com.docxwkyra78
 
The Business of Projects
The Business of ProjectsThe Business of Projects
The Business of ProjectsUnanet
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part twoHossam Maghrabi
 
Software project management- Software Engineering
Software project management- Software EngineeringSoftware project management- Software Engineering
Software project management- Software EngineeringMuhammad Yousuf Abdul Qadir
 
PMO (Project Management Office)
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)Dilawar Abbas
 
Project Management Plan Templatewww.ProjectManagementDocs.com.docx
Project Management Plan Templatewww.ProjectManagementDocs.com.docxProject Management Plan Templatewww.ProjectManagementDocs.com.docx
Project Management Plan Templatewww.ProjectManagementDocs.com.docxbriancrawford30935
 
unit-vpart-2.ppt
unit-vpart-2.pptunit-vpart-2.ppt
unit-vpart-2.pptTejaTeja57
 
PMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best PracticesPMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best PracticesRicardo Leite
 
Northern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentNorthern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentSiwawong Wuttipongprasert
 
Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfVarunSubramanyam
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1ghulam MUSTAFA
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.pptAlfredoArturoGranado
 

Ähnlich wie T24 Temenos Earned Value Management & Project Planning Presentation (20)

formation.docx
formation.docxformation.docx
formation.docx
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
 
Integrated Performance Management Scorecard
Integrated Performance Management ScorecardIntegrated Performance Management Scorecard
Integrated Performance Management Scorecard
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
project management plan.pptx
project management plan.pptxproject management plan.pptx
project management plan.pptx
 
Project Management Plan Templatewww.ProjectManagementDocs.com.docx
Project Management Plan Templatewww.ProjectManagementDocs.com.docxProject Management Plan Templatewww.ProjectManagementDocs.com.docx
Project Management Plan Templatewww.ProjectManagementDocs.com.docx
 
The Business of Projects
The Business of ProjectsThe Business of Projects
The Business of Projects
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
 
Software project management- Software Engineering
Software project management- Software EngineeringSoftware project management- Software Engineering
Software project management- Software Engineering
 
PMO (Project Management Office)
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)
 
Project Management Plan Templatewww.ProjectManagementDocs.com.docx
Project Management Plan Templatewww.ProjectManagementDocs.com.docxProject Management Plan Templatewww.ProjectManagementDocs.com.docx
Project Management Plan Templatewww.ProjectManagementDocs.com.docx
 
unit-vpart-2.ppt
unit-vpart-2.pptunit-vpart-2.ppt
unit-vpart-2.ppt
 
PMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best PracticesPMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best Practices
 
Northern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentNorthern Finishing School: IT Project Managment
Northern Finishing School: IT Project Managment
 
Webinar on PMS
Webinar on PMSWebinar on PMS
Webinar on PMS
 
Ev+agile=success
Ev+agile=successEv+agile=success
Ev+agile=success
 
Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdf
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt
 

Mehr von Michael Gowlett PMP, Prince 2 Practitioner (6)

Graphical CV
Graphical CVGraphical CV
Graphical CV
 
BCBS Information Article By Mike Gowlett
BCBS Information Article By Mike GowlettBCBS Information Article By Mike Gowlett
BCBS Information Article By Mike Gowlett
 
Preparing For A Competency Interview Template
Preparing For A Competency Interview TemplatePreparing For A Competency Interview Template
Preparing For A Competency Interview Template
 
Real World Excel Formulas
Real World Excel FormulasReal World Excel Formulas
Real World Excel Formulas
 
How to setup EVM within a PMO
How to setup EVM within a PMOHow to setup EVM within a PMO
How to setup EVM within a PMO
 
High Level Overview Of Using The Earned Value On A T24 Project
High Level Overview Of Using The Earned Value On A T24 ProjectHigh Level Overview Of Using The Earned Value On A T24 Project
High Level Overview Of Using The Earned Value On A T24 Project
 

T24 Temenos Earned Value Management & Project Planning Presentation

  • 1. Project Planning and Earned Value Management
  • 2. Contents Objective Fact about Earned Value Management Earned Value definitions & descriptions How to Produce Earned Value Introduction to the “Project Planning Approach” utilizing the top level down & bottom level up mechanism for planning a T24 project. - Two screenshots showing how the lower deliverables can be managed more effectively in Microsoft Sharepoint - Microsoft Project and how Earned Value is derived. - Weekly Earned Value analytical graph. - Earned Value trend analysis across the T24 project. Introduction to the planning process and how it was integrated into the T24 project. - Example of a High Level Work Breakdown Structure For a T24 Methodology - The planning process - The control process Overview of Microsoft Sharepoint T24 Project Dashboard
  • 3. Objective The objective of this slideshow is to provide the audience with the following: A high level overview of Earned Value Analysis and the benefits of using this analytical method to measure a projects progress. How Earned Value Management enhances project performance by allowing the project audience to exhume levels of detail from any project and retrieve statistics that can be measured against the baseline under project control. A detailed overview of one specific phase from the project which will define how to approach project planning for this type of project, using combined solutions of both Microsoft Sharepoint Services and Microsoft Project 2007. Define and show how the iterative project planning process works within the Hub T24 project and how the best practice of maintaining and enforcing this process within a project of this magnitude. Review of the project dashboard – Implemented a one stop solution for visual knowledge about the project for senior management.
  • 4. Facts About Earned Value Organisations often want to know some of the following questions when Considering using the Earned Value Technique What is EVM? It’s a metric devised to achieve meaningful comparisons between planned and completed work. Earned Value allows projects to show early indications of cost and schedule overruns within a project by using controlled mechanisms that are enforced before the baseline of the project. The three basic main elements of EVT are PV, EV, and AC. These are the core analytical acronyms that are used to produce the statistics for EVA. Why should we adopt the EVT within our organisation and what are the benefits to using EVA within a project? The EVM technique integrates the triple constraints of scope, time and cost and is becoming a wide spread form of tracking mechanism for projects. It evaluates progress analytically and this been known for its proven and established efficiencies it brings to any project. EVT allows you to have more control and management of the project. Coupled with good planning and effective use of EVM will reduce the impact to a significant number of project issues which are due to schedule and cost overrun. EVM also aids in negotiations with the end customers about scope increase, because cost and schedule increases nearly always occur due to scope creep and this will be quite evident to stakeholders. EVM also provides statistics to stakeholders when reporting on project performance because EVM can show past, current and predicted forecast performance and this shows a greater level of detail.
  • 5. EV Definitions & Descriptions
  • 6.
  • 7. The dependencies are built upon the independency relationships that is scaled out from the WBS and these are done in either the project plan itself or in a integrated solution that has been designed within MSP.
  • 8. You also need a list of assumed or available resources including their costs and the designated tasks they have been delegated to own.
  • 9.
  • 10. Project Planning Approach A combination of a top level down and a bottom level up approach was used to track and measure the deliverables of the project. This provides senior management with the ability to view the project from a high level financially and at the lower level products. Products like MPP and MSP where used to store, maintain and effectively manage the project and to provide advanced dynamic reporting to the stakeholders. The following slides are document outputs from MSP and MPP showing the planning solutions that were used for the T24 project at KBL bank, which includes an example of a T24 WBS methodology.
  • 11. High Level WBS For A T24 Project Including the Methodology START Gap Analysis Functional Design DST based Development System Testing Functional Catalogue Local Code Conversion Migration Testing Migration Design Technical Design Non Functional Testing Architecture Unit Testing Build Team UAT Testing Business Process Testing Dress Rehearsal Implementation Migration Cutover Training END BPT & UAT Testing Team Implementation Team
  • 12. MSP Lower Level Deliverables
  • 13. MSP With Gantt Chart
  • 14. Microsoft Project With Earned Value The below example is a screen shot showing the high level deliverables of the securities areasituated within the design & analysis phase of the project. This report allows seniormanagement to view the project at phase level. The below screenshot shows how we retrievethe Earned Value statistics.
  • 16. Overall T24 Project EV Report
  • 17.
  • 18. The Control ProcessThe Planning Processis a high level overview that provides a detailed analysis and breakdown of each work stream in the T24 program. The goal of the planning phase is to have clear timeframes driven by concrete milestones, by which the project can be measured against. The Control Process is where you should monitor the progress and constantly review the SPI and CPI for the project, so that the tolerance thresholds are controlled. If you exceed a project tolerance then actions are invoked to allow senior management to review the relevant work stream and implement corrective action to reduce or eradicate the issue at an early stage. The breakdown of the high level solutions for the planning and control processes can be seen in the next slides.
  • 19. Plan Tasks Resources Re-Forecast Budget T24 High Level Planning Process High Level Planning Process Solution Earned Value Reporting WBS By Phase Access Reports Financial Reporting
  • 21. T24 MSP Project Dashboard

Hinweis der Redaktion

  1. Glossary Of TermsPV = Planned ValueEV = Earned ValueAC = Actual CostEVA = Earned Value AnalysisEVM = Earned Value ManagementEVT = Earned Value Technique
  2. SME = Subject Matter ExpertMPP = Microsoft Project 2003/2007WIP = Work In ProgressMSP = Microsoft Sharepoint ServicesWBS = Work Breakdown Structure - The WBS is aconsolidated group of chronological deliverables that will be used to understand the fundamental requirements tobuild the tasks within the MPP plan. The best way to produce a WBS is using a grouped consensus of SME’s whounderstand the final product and what it takes to produce it.
  3. Glossary Of TermsMPP = Microsoft Project PlanMSP = Microsoft SharepointT24 = Temenos 24
  4. For each component listed above there is a separate work stream and this is broken down into further products to produce actual deliverables.
  5. Double Click To OpenMSP = Microsoft Sharepoint ServicesThis slide shows you how the lower level deliverables that are depicted and maintained in MSP You can clearly see here the DSF/DST’s and the quality reviews for each of the product deliverables that were assigned to resources who provided updates and progressive comments to each of the lower level deliverables as and when they are actively in progress, completed or just as an update. The owners also have the ability to setup alerts so that this makes it easier for them to track the tasks in project. Coupled with this it is also possible to build Gantt charts in Sharepoint so you can clearly see progress the next slide shows the a real definitive amount of detail to a particular area of the T24 project.
  6. Double click to review in full screen.High level overview showing how a Temonos T24 project effectively making use of the functionality within Microsoft SharePoint to manage the lower level deliverables. This allows for clear visibility to the project and allows work stream leads/owners to take manage their phase of the project at a definitive level. This helps to maintain efficiency and productivity of all deliverables that have been specified.
  7. High Level overview of the Microsoft plan showing Earned Value. The two values below are the main factors that contribute to schedule and cost performance and these are the values that are constantly measured against the tolerance margins and these are the measurements that are used to monitor cost and schedule overrunSPI = Schedule Performance Index CPI = Cost Performance Index
  8. Double Click To OpenExample EV Showing AC =Actual CostEV =Earned ValuePV =Planned ValueThis graph shows that actual cost is over what has been planned and the Earned Value and Planned Value are at equal status.
  9. Glossary Of TermsT24 = Name of the Temenos Product that is being implementedDouble click the slide because its an embedded document for a better view.This is a full analytical overview of Earned Value for the T24 project showing trend analysis over the course of the project.
  10. Glossary Of TermsCPI = Cost Performance IndexSPI = Schedule Performance IndexT24 = Name of the Temenos Product that is being implemented
  11. This is a high level overview defining the preferred solutions used to implement a Temenos T24 project for an example project for KBL bank for a £17.5m projectThis shows how four software solutions where used to successfully integrate Temenos T24 into the business. The following is a small breakdown of the above process:WBS structure segregated into phases and a financial budget proposed to each phase of the project providing distinction to where the budget is being spent When the financials are broken down the tasks can be estimated, planned and forecasted within the WBS of the project. There is a clear interaction and relationship of collaborating financials with Microsoft Project plans, which have an output of Earned Value that is fed into Microsoft Sharepoint for visualisation and project governance, control and reporting.Microsoft Access works interactively with Microsoft Sharepoint Reporting Services to provide clear and concise reporting for senior management.
  12. Glossary Of TermsT24 = Name of the Temenos Product that is being implementedDouble Click To Open: Embedded Document
  13. Glossary Of TermsMSP = Microsoft Sharepoint T24 = Name of the Temenos Product that is being implementedDouble Click To Open: Embedded DocumentProject DashboardThis dashboard has been designed and implemented and shows the following: Links to all Microsoft project plansLinks to all EV trend graphs for each phaseLinks to the lower level deliverables for each phaseOwners to each phaseWBS showed and maintainedPDF documents showing cost analysis to each plan and phase of the project.% complete