2. Purpose of the Cost Management
Budgeting and controlling the costs so that the
project can be completed within the approved
budget
www.projektor.ee/pm/#cost
27. Cost Control System
• Comparing actual costs with baseline costs
• Reflecting schedule and scope changes in the
budget
• Avoiding non-eligible expenses
• Change communication
• Bringing cost overruns within accepted limit
www.projektor.ee/pm/#cost
28. Earned Value Method
Method that measures
performance of the project and
forecast future performance based
on past performance
work completed ratio × budget price
www.projektor.ee/pm/#cost
29. Earned Value Analysis EVA
• Method for measuring project progress
• Project scope, duration and cost integration
• Enables to estimate project final cost and duration in
the middle of the project
www.projektor.ee/pm/#cost
30. Concept of Earned Value
• Planned value (PV) = planned work × budget price
• Earned value (EV) = work completed ratio × budget
price (actual performance % × budgeted total cost)
• Actual cost (AC) = actual work × actual cost
www.projektor.ee/pm/#cost
31. Planned Value - Earned Value - Actual Value
BMBOK Guide 2009 www.projektor.ee/pm/#cost
32. Earned Value Implementation
• Cost variance (CV) = earned value (EV) – actual cost (AC)
• Schedule variance (SV) = earned value (EV) – planned value
(PV)
• Cost estimation (cost performance index CPI) = earned
value(EV) / actual cost (AC)
• Duration estimation (schedule performance index SPI) =
earned value (EV) / planned value (PV)
www.projektor.ee/pm/#cost
33. Planned task duration 4 d
Planned resource cost 30 $/h
Planned task total cost 960 $/h
Completed duration 2 d
Planned percent complete 50%
Remaining duration estimation 3 d
Actual percent complete 40%
Actual resource cost 25 $/h
How big is:
Planned value 480 $
Earned value 384 $
Actual value 400 $
Estimated total cost 1000 $
www.projektor.ee/pm/#cost
34. Planned task duration 4 d
Planned resource cost 30 $/h
Planned task total cost 960 $/h = 4d x 30 x 8h
Completed duration 2 d
Planned percent complete 50% = 2d / 4d
Remaining duration estimation 3 d
Actual percent complete 40% = 2d / 5d
Actual resource cost 25 $/h
How big is:
Planned value 480 $ = 2d x 30 x 8h
Earned value 384 $ = 960 x 40%
Actual value 400 $ = 2d x 25 x 8h
Estimated total cost 1000 $ = 5d x 8d x 25$/h
www.projektor.ee/pm/#cost
36. Cost Forecasting Method
• CPI - Cost Performance Index (CPI= EV/AC)
• ETC - Estimate to Complete - the remaining cost of
the project
• EAC - Estimate at Completion - the total cost of the
project at the end
www.projektor.ee/pm/#cost
Mostly focus on cost of resources needed in order to complete the project.
Project life-cycle costing = project decision effect on project results (e.g. limiting resign review = decreasing production costs, increasing client’s operational costs)
Estimating – approximate costs (currency or work units) – focus on resources
Budgeting – calculating task, WP and project cost
In smaller projects cost estimating and budgeting are integrated together.
+IN:
Resource calendars
Cost management plan
+MET:
Cost aggregation???
Cost of quality???
Reserve analysis???
Funding limit reconciliation
+OUT:
Requested changes???
Market – what resources are available, what prices
Commercial database as a service
Too general
Parameetriline – näiteks elamu hinna arvutamine ruutmeetrite alusel, tarkvara puhul 13 faktorist koosnev hindamismudel (5 parameetrit igas)
Management puudu
SOW - Statement of Work
Total: 5D x 8H x 25$/h = 1000
Eelmine valem ???: 400 / 384 x 960
Exercises based on equations:
- ETC based on new estimate
- ETC based on Atypical variance ETC = BAC - EVC
- ETC based on typical variance ETC = (BAC - EVC)/CPIC
- EAC using a new estimate EAC = ACC + ETC
- EAC using remaining budget: EAC = ACC + BAC - EV
- EAC using CPIC: EAC = ACC + (BAC – EV)/CPIC
BAC: Budget at completion