SlideShare ist ein Scribd-Unternehmen logo
1 von 56
Downloaden Sie, um offline zu lesen
Lecture # 14
Investment Alternatives
Incremental ROI/IRR Method
1
Dr. A. Alim
1. Incremental ROI Analysis of Multiple
Mutually Exclusive Alternatives
The concept of incremental investment
Suppose a company has $90,000 to invest in a project. Two
mutually exclusive alternatives are proposed; MARR is 16%:
Alternative A requires an investment of $50,000 and has a ROI of 35%
Alternative B requires an investment of $85,000 and has a ROI of 29%
The remaining funds after the selection would naturally be invested at MARR.
One would intuitively think that option A is preferred since it has a higher ROI,
but this would be incorrect .
Material sourced from "Plant Design and Economics for Chem.
Engineers", 5th ed. by Peters et al. and also from " Engineering
Economy", 6th edition,2005, by Blank and Tarquin. 2
© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Since the company can always invest the unused funds at
MARR, the overall ROI is:
With option A, ROI = (50000(0.35) + 40000(0.16))/90000
= 26.6 %
With option B, ROI = (85000(0.29) + 5000(0.16))/90000
= 28.3 %
Option B is recommended.
Material sourced from "Plant Design and Economics for Chem.
Engineers", 5th ed. by Peters et al. and also from " Engineering
Economy", 6th edition,2005, by Blank and Tarquin. 3
© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
COMPARISON OF ALTERNATIVES
The concept of incremental investment
Definition: incremental investment means every
additional dollar invested must result in an
incremental ROI at least equal to MARR.
If investment B is more than investment A, then:
Investment B is recommended ONLY IF :
(Profit ”B” – Profit “A”) / (Investment “B” – Investment “A”) ≥ MARR
i.e. incremental ROI ≥ MARR
Material sourced from "Plant Design and Economics for Chem. Engineers",
5th ed. by Peters et al. and also from " Engineering Economy", 6th
edition,2005, by Blank and Tarquin.
4© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Material sourced from "Plant Design
and Economics for Chem.
Engineers", 5th ed. by Peters et al.
and also from " Engineering
Economy", 6th edition,2005, by
Blank and Tarquin.
© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
5
Profit
$
Investment
$
B
A
Select B and reject A only if :
Incremental ROI =(Profit ”B” – Profit “A”) / (Investment “B” – Investment “A”) ≥ MARR
Profit
Or
Savings
InvestmentMaterial sourced from "Plant Design and Economics for Chem. Engineers",
5th ed. by Peters et al. and also from " Engineering Economy", 6th
edition,2005, by Blank and Tarquin.
6
© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Profit
Or
Savings
Investment
Incremental ROI = delta profit / delta investment
At the limit of delta investment approaches zero, the incremental ROI is the slope to the curve.
Material sourced from "Plant Design and Economics for Chem.
Engineers", 5th ed. by Peters et al. and also from " Engineering
Economy", 6th edition,2005, by Blank and Tarquin. 7© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Profit
Or
Savings
Investment
Incremental ROI = delta profit / delta investment
At the limit of delta investment approaches zero, the incremental ROI is the slope to the curve.
Material sourced from "Plant Design and Economics for
Chem. Engineers", 5th ed. by Peters et al. and also from
" Engineering Economy", 6th edition,2005, by Blank and
Tarquin.
8© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Profit
Or
Savings
Investment
Line of slope = MARR
Recommended investment for
Incremental ROI = MARR
Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank
and Tarquin.
9© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
All investments here have
incremental ROI over “X” less than MARR
X
Material sourced from "Plant Design and Economics for Chem. Engineers",
5th ed. by Peters et al. and also from " Engineering Economy", 6th
edition,2005, by Blank and Tarquin.
10
© 2003 and 2005 by McGraw-Hill, New York, N.Y All
Rights Reserved
Incremental investment analysisIncremental Investment Analysis
ROI (A) is larger than ROI(B)
Yet we reject A and accept B
Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by
Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and
Tarquin.
11
© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Incremental Investment Analysis
COMPARISON OF ALTERNATIVES
Incremental Investment Analysis
Basic concept: We want the return to be higher than MARR for every
dollar invested.
Below the tangent point:
 ROI > MARR , hence, + ve incremental investment
Beyond the tangent point:
 ROI < MARR , hence, - ve incremental investment
Investments beyond the tangent point are therefore not advised when
Compared to alternative investment at the tangent point.
Calculate incremental ROI:
 ROI =  ( profit or savings) /  ( investment)
Accept if  ROI ≥ MARR
Material sourced from "Plant Design and Economics for Chem. Engineers", 5th
ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by
Blank and Tarquin.
12© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
COMPARISON OF ALTERNATIVES
Incremental Investment Analysis
When comparing several investments using the ROI method,
we apply the incremental analysis and follow this principle:
Select the one alternative
• That requires the largest investment, and
• Indicates that the extra investment over another acceptable
alternative is justified, i.e. yielding an incremental ROI ≥
MARR.
Material sourced from "Plant Design and Economics for Chem. Engineers",
5th ed. by Peters et al. and also from " Engineering Economy", 6th
edition,2005, by Blank and Tarquin.
13
© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Example 8-6, Page 344
Plant Design and Economics For chem. Engineers, 5th ed, 2003 by Peters et al.
Material sourced from "Plant Design and Economics for Chem. Engineers",
5th ed. by Peters et al. and also from " Engineering Economy", 6th
edition,2005, by Blank and Tarquin.
14
© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank
and Tarquin.
15
© 2003 and 2005 by McGraw-Hill, New York, N.Y
All Rights Reserved
• We now apply incremental ROI analysis among alternatives 1,2, and 3:
• First step is to arrange the investments from left to right in ascending
order. In this case the order is 1, 2, then 3.
• We then determine Inc. ROI between pairs starting from the left and
moving right.
• Inc. ROI (2-1) = (3,000 – 2,000) / (16,000 – 10,000) = 16.7 %
which is > MARR.
Therefore: Reject alternative 1
• Inc. ROI (3-2) = (3,200 – 3,000) / (20,000 – 16,000) = 5 %
which is < MARR.
Therefore: Reject alternative 3
Conclusion: Accept alternative 2
Material sourced from "Plant Design and Economics for Chem. Engineers", 5th
ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by
Blank and Tarquin.
16
© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Modified example 8-3, page 331
• 3 investments. Need to evaluate profitability of each.
• Use ROI, PBP, NPV, and DCFRR.
• Assume straight line depreciation.
• Tax rate is 35%
• MARR is 15%
• Use MARR as interest rate for time value of money.
• Ignore land value.
Incremental ROI analysis
Material sourced from "Plant Design and Economics for Chem. Engineers", 5th
ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by
Blank and Tarquin.
17
© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Plant Design and Economics For chem. Engineers, 5th ed, 2003 by Peters et al.
Material sourced from "Plant Design and Economics for Chem. Engineers", 5th
ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by
Blank and Tarquin.
18© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Inv. 1 Inv. 2 Inv. 3
Total inv. $ 110,000 180,000 225,000
NPAT, $/y 24,300 27,607 32,562
ROI (MARR) 22.1(15) 15.3(15) 14.5(15)
Accept? YES YES NO
Incremental ROI (2-1) = (27,607 – 24,300) / (180,000 -110,000)
= 4.7 %
Which is less than MARR. Therefore reject 2 and accept 1.
Material sourced from "Plant Design and Economics for Chem. Engineers", 5th
ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by
Blank and Tarquin. 19© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
2. Incremental DCFRR (IRR) Analysis of
Multiple Mutually Exclusive Alternatives
 Given N mutually exclusive alternatives, using
the incremental DCFRR method
 Select the one alternative that
 Requires the largest investment, and at the
same time
 Indicates that the extra investment over
another acceptable investment is justified.
 This means incremental IRR must be equal to
or higher than MARR.
Material sourced from "Plant Design and Economics for Chem. Engineers", 5th
ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by
Blank and Tarquin.
20© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Material sourced from "Plant Design and Economics for Chem. Engineers", 5th
ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by
Blank and Tarquin.
21
© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank
and Tarquin.
22
© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
IRR (B–A) is the incremental IRR or DCFRR
Which project to accept, A or B?
• Depends on the value of MARR !
• Accept B and reject A if:
IRR (B-A) ≥ MARR
• Accept A and reject B if:
IRR (B-A) < MARR
Material sourced from "Plant Design and Economics for Chem. Engineers",
5th ed. by Peters et al. and also from " Engineering Economy", 6th
edition,2005, by Blank and Tarquin.
23© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
24© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
MARR
Reject both A and B
25© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
MARR
Reject B, accept A
26© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
MARR
Reject B, accept A
Since IRR (B-A) < MARR
27© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
MARR
Reject A, accept B
Since IRR (B-A) > MARR
28© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Ranking Rules – Selection Process
Among Mutually Exclusive
Alternatives
1. Order the alternatives from smallest to
largest initial investment. For revenue
projects the DN alternative is the first on
the left (no investment!)
2. Compute the cash flows for each
alternative (DN has zero cash flows)
3. Ensure project lives are equal, apply LCM
if needed.
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin.
29© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
4. Compute the DCFRR value for all
alternatives in the considered set.
 If any alternative has an DCFRR < MARR
drop it from further consideration
 The candidate set will be those
alternatives with computed DCFRR values
> MARR.
 Call this the FEASIBLE set
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed. by
Peters et al. and also from " Engineering
Economy", 6th edition,2005, by Blank and
Tarquin.
30© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
 The first alternative is called the
DEFENDER
 The second (next higher investment cost)
alternative is called the CHALLENGER
 Compute the incremental cash flow as
(Challenger – Defender)
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed. by
Peters et al. and also from " Engineering
Economy", 6th edition,2005, by Blank and
Tarquin.
31© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
5. Compute DCFRR Challenger – Defender
 If DCFRR Challenger – Defender ≥ MARR drop
the defender and the challenger wins the
current round.
 If DCFRR Challenger – Defender < MARR, drop
the challenger and the defender moves on
to the next comparison round
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin.
32© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
 At each round, a winner is determined
 Either the current Defender or the
current Challenger
 The winner of a given round moves to the
next round and becomes the current
DEFENDER and is compared to the next
challenger
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin.
33© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
6. This process continues until there are
no more challengers remaining.
 The alternative that remains after all
alternatives have been evaluated is the
final winner.
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin.
34© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Costs Only (Service) Problems –
DCFRR Approach
Remember
 Cost problems do not have computed
DCFRR’s since there are more cost amounts
that revenue amounts (salvage values may
exist)
 Thus there are no feasible DCFRR’s for
each alternative, but they do exist for the
delta between two alternatives.
Material sourced from "Plant Design and Economics for
Chem. Engineers", 5th ed. by Peters et al. and also from "
Engineering Economy", 6th edition,2005, by Blank and
Tarquin.
8-35 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights
Reserved
Costs Only Problems - Rules
 Rank the alternatives according to their
investment requirements (low to high)
 For the first round compare:
 (Challenger – Defender) Cash Flow
 Compute DCFRR Challenger – Defender
 If DCFRR Challenger – Defender ≥ MARR,
Challenger wins; else Defender wins
Material sourced from "Plant Design and Economics for
Chem. Engineers", 5th ed. by Peters et al. and also from "
Engineering Economy", 6th edition,2005, by Blank and
Tarquin.
8-36 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights
Reserved
Costs Only Problems -continued
 The current winner now becomes the defender
for the next round.
 Compare the current defender to the next
challenger and DCFRR Challenger – Defender
 The winner becomes the current champion and
moves to the next round as the defender
 Repeat until all alternatives have been
compared.
Material sourced from "Plant Design and Economics for
Chem. Engineers", 5th ed. by Peters et al. and also from "
Engineering Economy", 6th edition,2005, by Blank and
Tarquin.
8-37 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights
Reserved
Equal or unequal service lives?
 Remember what we did when using PW
comparison?
 Projects can be compared only if they have
equal service lives.
 For projects with unequal service lives, we
should use the LCM concept.
 Alternatively we could use the AW approach to
find the breakeven IRR.
Material sourced from "Plant Design and Economics for
Chem. Engineers", 5th ed. by Peters et al. and also from "
Engineering Economy", 6th edition,2005, by Blank and
Tarquin.
8-38 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights
Reserved
Example from: Engineering Economy, Sullivan, et. al., 12th
edition, 2003, P 212 - Equal service lives
39© 2003 by Prentice Hall All rights Reserved.
40© 2003 by Prentice Hall All rights Reserved.
Material sourced from "Plant Design and Economics for
Chem. Engineers", 5th ed. by Peters et al. and also from "
Engineering Economy", 6th edition,2005, by Blank and
Tarquin.
© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights
Reserved41
The incremental IRR method resulted in alternative E being selected. Let’s try the PW method
to check this conclusion:
YEAR A B C D E F
0 -900 -1500 -2500 -4000 -5000 -7000
1 150 276 400 925 1125 1425
2 150 276 400 925 1125 1425
3 150 276 400 925 1125 1425
4 150 276 400 925 1125 1425
5 150 276 400 925 1125 1425
6 150 276 400 925 1125 1425
7 150 276 400 925 1125 1425
8 150 276 400 925 1125 1425
9 150 276 400 925 1125 1425
10 150 276 400 925 1125 1425
PW $21.69 $195.90 ($42.17) $1,683.72 $1,912.64 $1,756.01
Justified ? YES YES NO YES YES YES
WINNER !
• 10 year project
• New equipment is required
• Two vendors
• MARR = 15%
• Which vendor should be selected?
• Cost or Service Problem
• Lowest Common Multiplier (LCM) = 10 years
Example 8.3 Blank (7th ed.), p. 208
Example 8.3 Blank (6th ed.), p. 284
Unequal service lives
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin. 42© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin. 43© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Incremental Cash Flow
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin.
44© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
PW analysis
• We could stop because the PW(15%) has
signaled that A is the winner!
• Lowest PW cost
• Proceed with a IRR analysis BUT….
• IRR must be performed on the
incremental investment
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin.
45© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
IRR (B-A) is less
than the MARR of
15%.
Therefore Reject B
and go with A
IRR (B-A) = 12.65 %
Inc. Cash Flow $
0 -5,000
1 1,900
2 1,900
3 1,900
4 1,900
5 -9,100
6 1,900
7 1,900
8 1,900
9 1,900
10 3,900
IRR 12.65%
Inc. Cash Flow Results
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin.
46© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin. 47© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
This is the
breakeven rate
of return
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin.
48© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Determining incremental DCFRR by
using the AW method
• Approach is particularly useful for comparing projects of unequal
service lives.
• Determine AWA and AWB from one cycle only.
• For projects A and B, express AWA and AWB as a function of
interest rate, then set (AWB – AWA = 0)
• The interest rate satisfying (AWB – AWA = 0) is the breakeven
incremental IRR
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin.
49© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Determining incremental DCFRR by
using the AW method
Example: Re-do example 8.3
Determine the incremental IRR using the AW method:
•10 year project (merger)
•New equipment is required
•Two vendors
•MARR = 15%
•Which vendor should be selected
•Cost or Service Problem
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin.
50© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Determining incremental DCFRR by
using the AW method
AWA = -8,000 (A/P, i*, 10) – 3,500
AWB = -13,000(A/P, i*, 5) + 2,000 (A/F, i*, 5) – 1,600
Set AWB - AWA = 0
Solve for breakeven i* (inc. IRR) = 12.65 (using EXCEL Solver)
This is the incremental IRR; being less than MARR
We then choose project A
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin.
51© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin.
52© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin.
53© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
Home Work # 6
Thursday, March 6, 2014
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin.
54© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
CHEE 5369 / 6369
Homework # 6
The following problem from Peters et al., fifth
edition, 2003:
Problem 8.16 page 356
The following solved examples from Blank and
Tarquin, 7th edition, 2012:
Example 5.1 Page 132
Example 6.1 Page 151
Example 8.4 page 211
Example 8.6 page 215
Example 8.7 page 216
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin.
55© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved
8-16
Material sourced from "Plant Design and
Economics for Chem. Engineers", 5th ed.
by Peters et al. and also from "
Engineering Economy", 6th edition,2005,
by Blank and Tarquin.
56© 2003 and 2005 by McGraw-Hill,
New York, N.Y All Rights Reserved

Weitere ähnliche Inhalte

Was ist angesagt?

Lecture # 7 depreciation i
Lecture # 7 depreciation iLecture # 7 depreciation i
Lecture # 7 depreciation i
Bich Lien Pham
 
Lecture # 11 measures of profitability i
Lecture # 11 measures of profitability iLecture # 11 measures of profitability i
Lecture # 11 measures of profitability i
Bich Lien Pham
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimation
Bich Lien Pham
 
Chapter 8 ror analysis for multiple alternatives
Chapter 8   ror analysis for multiple alternativesChapter 8   ror analysis for multiple alternatives
Chapter 8 ror analysis for multiple alternatives
Bich Lien Pham
 
Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation i
Bich Lien Pham
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examples
Abdulaziz AlSuwaidi
 

Was ist angesagt? (20)

CFD analysis of aerofoil
CFD analysis of aerofoilCFD analysis of aerofoil
CFD analysis of aerofoil
 
Carbon Fiber Fuselage Research Report
Carbon Fiber Fuselage Research ReportCarbon Fiber Fuselage Research Report
Carbon Fiber Fuselage Research Report
 
Solutions manual for mechanical vibrations 6th edition by rao ibsn 9780134361307
Solutions manual for mechanical vibrations 6th edition by rao ibsn 9780134361307Solutions manual for mechanical vibrations 6th edition by rao ibsn 9780134361307
Solutions manual for mechanical vibrations 6th edition by rao ibsn 9780134361307
 
Bell shape lift_distribution
Bell shape lift_distributionBell shape lift_distribution
Bell shape lift_distribution
 
Lecture # 7 depreciation i
Lecture # 7 depreciation iLecture # 7 depreciation i
Lecture # 7 depreciation i
 
Steam turbine
Steam turbine Steam turbine
Steam turbine
 
CFD analysis of an Airfoil
CFD analysis of an AirfoilCFD analysis of an Airfoil
CFD analysis of an Airfoil
 
Nozzles - Lecture B
Nozzles - Lecture BNozzles - Lecture B
Nozzles - Lecture B
 
Airfoil
AirfoilAirfoil
Airfoil
 
Lecture # 11 measures of profitability i
Lecture # 11 measures of profitability iLecture # 11 measures of profitability i
Lecture # 11 measures of profitability i
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimation
 
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
Chapter 6&amp;7  annual worth analysis &amp; ror   lo3bChapter 6&amp;7  annual worth analysis &amp; ror   lo3b
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
 
Comparison and selection among alternatives
Comparison and selection among alternativesComparison and selection among alternatives
Comparison and selection among alternatives
 
6. present worth analysis
6. present worth analysis6. present worth analysis
6. present worth analysis
 
lift force
lift forcelift force
lift force
 
Chapter 8 ror analysis for multiple alternatives
Chapter 8   ror analysis for multiple alternativesChapter 8   ror analysis for multiple alternatives
Chapter 8 ror analysis for multiple alternatives
 
Conceptual Design of Blended Wing Body Cargo Aircraft
Conceptual Design of Blended Wing Body Cargo AircraftConceptual Design of Blended Wing Body Cargo Aircraft
Conceptual Design of Blended Wing Body Cargo Aircraft
 
Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation i
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examples
 
Subsonic and supersonic air intakes
Subsonic and supersonic air intakesSubsonic and supersonic air intakes
Subsonic and supersonic air intakes
 

Andere mochten auch

Chapter 10 making choices & marr
Chapter 10   making choices & marrChapter 10   making choices & marr
Chapter 10 making choices & marr
Bich Lien Pham
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
Izah Asmadi
 

Andere mochten auch (12)

Low Cost Floor Maintenance
Low Cost Floor MaintenanceLow Cost Floor Maintenance
Low Cost Floor Maintenance
 
Chapter 10 making choices & marr
Chapter 10   making choices & marrChapter 10   making choices & marr
Chapter 10 making choices & marr
 
2008 Percent Maintenance Cost per year as a percent of Replacement Asset Value
2008 Percent Maintenance Cost per year as a percent of Replacement Asset Value2008 Percent Maintenance Cost per year as a percent of Replacement Asset Value
2008 Percent Maintenance Cost per year as a percent of Replacement Asset Value
 
Second FAQ on Maintenance of Cost Accounting Records and Cost Report
Second FAQ on Maintenance of Cost Accounting Records and Cost Report Second FAQ on Maintenance of Cost Accounting Records and Cost Report
Second FAQ on Maintenance of Cost Accounting Records and Cost Report
 
maintenance cost,approximate estimation,unit bay method
maintenance cost,approximate estimation,unit bay methodmaintenance cost,approximate estimation,unit bay method
maintenance cost,approximate estimation,unit bay method
 
Introduction to Project Finance
Introduction to Project FinanceIntroduction to Project Finance
Introduction to Project Finance
 
Forklift Planned Maintenance and Total Cost By Year
Forklift Planned Maintenance and Total Cost By YearForklift Planned Maintenance and Total Cost By Year
Forklift Planned Maintenance and Total Cost By Year
 
Estimation
EstimationEstimation
Estimation
 
Software Project Cost Estimation
Software Project Cost EstimationSoftware Project Cost Estimation
Software Project Cost Estimation
 
Landed cost definition, calculation & benefits
Landed cost definition, calculation & benefitsLanded cost definition, calculation & benefits
Landed cost definition, calculation & benefits
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
Building maintenance
Building maintenanceBuilding maintenance
Building maintenance
 

Ähnlich wie Lecture # 14 investment alternatives ii

Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation i
Bich Lien Pham
 
Lecture # 6 cost estimation ii
Lecture # 6 cost estimation iiLecture # 6 cost estimation ii
Lecture # 6 cost estimation ii
Bich Lien Pham
 
Lecture # 12 measures of profitability ii
Lecture # 12 measures of profitability iiLecture # 12 measures of profitability ii
Lecture # 12 measures of profitability ii
Bich Lien Pham
 
Kaushik Nath GCET_Plant Design and Project Engineering.ppt
Kaushik Nath GCET_Plant Design and Project Engineering.pptKaushik Nath GCET_Plant Design and Project Engineering.ppt
Kaushik Nath GCET_Plant Design and Project Engineering.ppt
jignabait
 
Us homebuilding industry
Us homebuilding industryUs homebuilding industry
Us homebuilding industry
bigsmilecho
 
ContentsI.List of tables1II.List of figures1Intr.docx
ContentsI.List of tables1II.List of figures1Intr.docxContentsI.List of tables1II.List of figures1Intr.docx
ContentsI.List of tables1II.List of figures1Intr.docx
maxinesmith73660
 
Chapter 18 sensitivity analysis
Chapter 18   sensitivity analysisChapter 18   sensitivity analysis
Chapter 18 sensitivity analysis
Bich Lien Pham
 
Chapter 18 sensitivity analysis
Chapter 18   sensitivity analysisChapter 18   sensitivity analysis
Chapter 18 sensitivity analysis
Bich Lien Pham
 

Ähnlich wie Lecture # 14 investment alternatives ii (10)

Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation i
 
Lecture # 6 cost estimation ii
Lecture # 6 cost estimation iiLecture # 6 cost estimation ii
Lecture # 6 cost estimation ii
 
Lecture # 12 measures of profitability ii
Lecture # 12 measures of profitability iiLecture # 12 measures of profitability ii
Lecture # 12 measures of profitability ii
 
Kaushik Nath GCET_Plant Design and Project Engineering.ppt
Kaushik Nath GCET_Plant Design and Project Engineering.pptKaushik Nath GCET_Plant Design and Project Engineering.ppt
Kaushik Nath GCET_Plant Design and Project Engineering.ppt
 
Decision & Risk Analysis for Industrial Biotechnology
Decision & Risk Analysis for Industrial BiotechnologyDecision & Risk Analysis for Industrial Biotechnology
Decision & Risk Analysis for Industrial Biotechnology
 
Aviation Aerospace & Defense industry TRIZ Case Studies - An Overview
Aviation Aerospace & Defense industry TRIZ Case Studies - An Overview Aviation Aerospace & Defense industry TRIZ Case Studies - An Overview
Aviation Aerospace & Defense industry TRIZ Case Studies - An Overview
 
Us homebuilding industry
Us homebuilding industryUs homebuilding industry
Us homebuilding industry
 
ContentsI.List of tables1II.List of figures1Intr.docx
ContentsI.List of tables1II.List of figures1Intr.docxContentsI.List of tables1II.List of figures1Intr.docx
ContentsI.List of tables1II.List of figures1Intr.docx
 
Chapter 18 sensitivity analysis
Chapter 18   sensitivity analysisChapter 18   sensitivity analysis
Chapter 18 sensitivity analysis
 
Chapter 18 sensitivity analysis
Chapter 18   sensitivity analysisChapter 18   sensitivity analysis
Chapter 18 sensitivity analysis
 

Mehr von Bich Lien Pham

Lecture # 10 eva and disposal of assets
Lecture # 10 eva and disposal of assetsLecture # 10 eva and disposal of assets
Lecture # 10 eva and disposal of assets
Bich Lien Pham
 
Lecture # 9 taxes and eva
Lecture # 9 taxes and evaLecture # 9 taxes and eva
Lecture # 9 taxes and eva
Bich Lien Pham
 
Lecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesLecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest rates
Bich Lien Pham
 
Lecture # 3 compounding factors effects of inflation
Lecture # 3 compounding factors   effects of inflationLecture # 3 compounding factors   effects of inflation
Lecture # 3 compounding factors effects of inflation
Bich Lien Pham
 
Lecture # 2 time value of money
Lecture # 2 time value of moneyLecture # 2 time value of money
Lecture # 2 time value of money
Bich Lien Pham
 
Lecture # 1 foundation
Lecture # 1 foundationLecture # 1 foundation
Lecture # 1 foundation
Bich Lien Pham
 
Chapter 19 decision-making under risk
Chapter 19   decision-making under riskChapter 19   decision-making under risk
Chapter 19 decision-making under risk
Bich Lien Pham
 
Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysis
Bich Lien Pham
 
Chapter 16 depreciation methods
Chapter 16   depreciation methodsChapter 16   depreciation methods
Chapter 16 depreciation methods
Bich Lien Pham
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysis
Bich Lien Pham
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitation
Bich Lien Pham
 
Chapter 11 replacement & retention decisions
Chapter 11   replacement & retention decisionsChapter 11   replacement & retention decisions
Chapter 11 replacement & retention decisions
Bich Lien Pham
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysis
Bich Lien Pham
 
Chapter 8 ror analysis for multiple alternatives
Chapter 8   ror analysis for multiple alternativesChapter 8   ror analysis for multiple alternatives
Chapter 8 ror analysis for multiple alternatives
Bich Lien Pham
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternative
Bich Lien Pham
 
Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysis
Bich Lien Pham
 
Chapter 5 present worth analysis
Chapter 5   present worth analysisChapter 5   present worth analysis
Chapter 5 present worth analysis
Bich Lien Pham
 
Chapter 4 nominal & effective interest rates
Chapter 4   nominal & effective interest ratesChapter 4   nominal & effective interest rates
Chapter 4 nominal & effective interest rates
Bich Lien Pham
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factors
Bich Lien Pham
 

Mehr von Bich Lien Pham (19)

Lecture # 10 eva and disposal of assets
Lecture # 10 eva and disposal of assetsLecture # 10 eva and disposal of assets
Lecture # 10 eva and disposal of assets
 
Lecture # 9 taxes and eva
Lecture # 9 taxes and evaLecture # 9 taxes and eva
Lecture # 9 taxes and eva
 
Lecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesLecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest rates
 
Lecture # 3 compounding factors effects of inflation
Lecture # 3 compounding factors   effects of inflationLecture # 3 compounding factors   effects of inflation
Lecture # 3 compounding factors effects of inflation
 
Lecture # 2 time value of money
Lecture # 2 time value of moneyLecture # 2 time value of money
Lecture # 2 time value of money
 
Lecture # 1 foundation
Lecture # 1 foundationLecture # 1 foundation
Lecture # 1 foundation
 
Chapter 19 decision-making under risk
Chapter 19   decision-making under riskChapter 19   decision-making under risk
Chapter 19 decision-making under risk
 
Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysis
 
Chapter 16 depreciation methods
Chapter 16   depreciation methodsChapter 16   depreciation methods
Chapter 16 depreciation methods
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysis
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitation
 
Chapter 11 replacement & retention decisions
Chapter 11   replacement & retention decisionsChapter 11   replacement & retention decisions
Chapter 11 replacement & retention decisions
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysis
 
Chapter 8 ror analysis for multiple alternatives
Chapter 8   ror analysis for multiple alternativesChapter 8   ror analysis for multiple alternatives
Chapter 8 ror analysis for multiple alternatives
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternative
 
Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysis
 
Chapter 5 present worth analysis
Chapter 5   present worth analysisChapter 5   present worth analysis
Chapter 5 present worth analysis
 
Chapter 4 nominal & effective interest rates
Chapter 4   nominal & effective interest ratesChapter 4   nominal & effective interest rates
Chapter 4 nominal & effective interest rates
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factors
 

Kürzlich hochgeladen

Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
dlhescort
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
amitlee9823
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
Abortion pills in Kuwait Cytotec pills in Kuwait
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
Matteo Carbone
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
amitlee9823
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Dipal Arora
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
dlhescort
 

Kürzlich hochgeladen (20)

It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 

Lecture # 14 investment alternatives ii

  • 1. Lecture # 14 Investment Alternatives Incremental ROI/IRR Method 1 Dr. A. Alim
  • 2. 1. Incremental ROI Analysis of Multiple Mutually Exclusive Alternatives The concept of incremental investment Suppose a company has $90,000 to invest in a project. Two mutually exclusive alternatives are proposed; MARR is 16%: Alternative A requires an investment of $50,000 and has a ROI of 35% Alternative B requires an investment of $85,000 and has a ROI of 29% The remaining funds after the selection would naturally be invested at MARR. One would intuitively think that option A is preferred since it has a higher ROI, but this would be incorrect . Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 2 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 3. Since the company can always invest the unused funds at MARR, the overall ROI is: With option A, ROI = (50000(0.35) + 40000(0.16))/90000 = 26.6 % With option B, ROI = (85000(0.29) + 5000(0.16))/90000 = 28.3 % Option B is recommended. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 3 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 4. COMPARISON OF ALTERNATIVES The concept of incremental investment Definition: incremental investment means every additional dollar invested must result in an incremental ROI at least equal to MARR. If investment B is more than investment A, then: Investment B is recommended ONLY IF : (Profit ”B” – Profit “A”) / (Investment “B” – Investment “A”) ≥ MARR i.e. incremental ROI ≥ MARR Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 4© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 5. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved 5 Profit $ Investment $ B A Select B and reject A only if : Incremental ROI =(Profit ”B” – Profit “A”) / (Investment “B” – Investment “A”) ≥ MARR
  • 6. Profit Or Savings InvestmentMaterial sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 6 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 7. Profit Or Savings Investment Incremental ROI = delta profit / delta investment At the limit of delta investment approaches zero, the incremental ROI is the slope to the curve. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 7© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 8. Profit Or Savings Investment Incremental ROI = delta profit / delta investment At the limit of delta investment approaches zero, the incremental ROI is the slope to the curve. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 8© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 9. Profit Or Savings Investment Line of slope = MARR Recommended investment for Incremental ROI = MARR Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 9© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved All investments here have incremental ROI over “X” less than MARR X
  • 10. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 10 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved Incremental investment analysisIncremental Investment Analysis
  • 11. ROI (A) is larger than ROI(B) Yet we reject A and accept B Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 11 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved Incremental Investment Analysis
  • 12. COMPARISON OF ALTERNATIVES Incremental Investment Analysis Basic concept: We want the return to be higher than MARR for every dollar invested. Below the tangent point:  ROI > MARR , hence, + ve incremental investment Beyond the tangent point:  ROI < MARR , hence, - ve incremental investment Investments beyond the tangent point are therefore not advised when Compared to alternative investment at the tangent point. Calculate incremental ROI:  ROI =  ( profit or savings) /  ( investment) Accept if  ROI ≥ MARR Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 12© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 13. COMPARISON OF ALTERNATIVES Incremental Investment Analysis When comparing several investments using the ROI method, we apply the incremental analysis and follow this principle: Select the one alternative • That requires the largest investment, and • Indicates that the extra investment over another acceptable alternative is justified, i.e. yielding an incremental ROI ≥ MARR. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 13 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 14. Example 8-6, Page 344 Plant Design and Economics For chem. Engineers, 5th ed, 2003 by Peters et al. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 14 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 15. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 15 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 16. • We now apply incremental ROI analysis among alternatives 1,2, and 3: • First step is to arrange the investments from left to right in ascending order. In this case the order is 1, 2, then 3. • We then determine Inc. ROI between pairs starting from the left and moving right. • Inc. ROI (2-1) = (3,000 – 2,000) / (16,000 – 10,000) = 16.7 % which is > MARR. Therefore: Reject alternative 1 • Inc. ROI (3-2) = (3,200 – 3,000) / (20,000 – 16,000) = 5 % which is < MARR. Therefore: Reject alternative 3 Conclusion: Accept alternative 2 Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 16 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 17. Modified example 8-3, page 331 • 3 investments. Need to evaluate profitability of each. • Use ROI, PBP, NPV, and DCFRR. • Assume straight line depreciation. • Tax rate is 35% • MARR is 15% • Use MARR as interest rate for time value of money. • Ignore land value. Incremental ROI analysis Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 17 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved Plant Design and Economics For chem. Engineers, 5th ed, 2003 by Peters et al.
  • 18. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 18© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 19. Inv. 1 Inv. 2 Inv. 3 Total inv. $ 110,000 180,000 225,000 NPAT, $/y 24,300 27,607 32,562 ROI (MARR) 22.1(15) 15.3(15) 14.5(15) Accept? YES YES NO Incremental ROI (2-1) = (27,607 – 24,300) / (180,000 -110,000) = 4.7 % Which is less than MARR. Therefore reject 2 and accept 1. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 19© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 20. 2. Incremental DCFRR (IRR) Analysis of Multiple Mutually Exclusive Alternatives  Given N mutually exclusive alternatives, using the incremental DCFRR method  Select the one alternative that  Requires the largest investment, and at the same time  Indicates that the extra investment over another acceptable investment is justified.  This means incremental IRR must be equal to or higher than MARR. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 20© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 21. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 21 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 22. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 22 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved IRR (B–A) is the incremental IRR or DCFRR
  • 23. Which project to accept, A or B? • Depends on the value of MARR ! • Accept B and reject A if: IRR (B-A) ≥ MARR • Accept A and reject B if: IRR (B-A) < MARR Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 23© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 24. 24© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 25. MARR Reject both A and B 25© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 26. MARR Reject B, accept A 26© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 27. MARR Reject B, accept A Since IRR (B-A) < MARR 27© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 28. MARR Reject A, accept B Since IRR (B-A) > MARR 28© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 29. Ranking Rules – Selection Process Among Mutually Exclusive Alternatives 1. Order the alternatives from smallest to largest initial investment. For revenue projects the DN alternative is the first on the left (no investment!) 2. Compute the cash flows for each alternative (DN has zero cash flows) 3. Ensure project lives are equal, apply LCM if needed. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 29© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 30. 4. Compute the DCFRR value for all alternatives in the considered set.  If any alternative has an DCFRR < MARR drop it from further consideration  The candidate set will be those alternatives with computed DCFRR values > MARR.  Call this the FEASIBLE set Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 30© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 31.  The first alternative is called the DEFENDER  The second (next higher investment cost) alternative is called the CHALLENGER  Compute the incremental cash flow as (Challenger – Defender) Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 31© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 32. 5. Compute DCFRR Challenger – Defender  If DCFRR Challenger – Defender ≥ MARR drop the defender and the challenger wins the current round.  If DCFRR Challenger – Defender < MARR, drop the challenger and the defender moves on to the next comparison round Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 32© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 33.  At each round, a winner is determined  Either the current Defender or the current Challenger  The winner of a given round moves to the next round and becomes the current DEFENDER and is compared to the next challenger Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 33© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 34. 6. This process continues until there are no more challengers remaining.  The alternative that remains after all alternatives have been evaluated is the final winner. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 34© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 35. Costs Only (Service) Problems – DCFRR Approach Remember  Cost problems do not have computed DCFRR’s since there are more cost amounts that revenue amounts (salvage values may exist)  Thus there are no feasible DCFRR’s for each alternative, but they do exist for the delta between two alternatives. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 8-35 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 36. Costs Only Problems - Rules  Rank the alternatives according to their investment requirements (low to high)  For the first round compare:  (Challenger – Defender) Cash Flow  Compute DCFRR Challenger – Defender  If DCFRR Challenger – Defender ≥ MARR, Challenger wins; else Defender wins Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 8-36 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 37. Costs Only Problems -continued  The current winner now becomes the defender for the next round.  Compare the current defender to the next challenger and DCFRR Challenger – Defender  The winner becomes the current champion and moves to the next round as the defender  Repeat until all alternatives have been compared. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 8-37 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 38. Equal or unequal service lives?  Remember what we did when using PW comparison?  Projects can be compared only if they have equal service lives.  For projects with unequal service lives, we should use the LCM concept.  Alternatively we could use the AW approach to find the breakeven IRR. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 8-38 © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 39. Example from: Engineering Economy, Sullivan, et. al., 12th edition, 2003, P 212 - Equal service lives 39© 2003 by Prentice Hall All rights Reserved.
  • 40. 40© 2003 by Prentice Hall All rights Reserved.
  • 41. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. © 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved41 The incremental IRR method resulted in alternative E being selected. Let’s try the PW method to check this conclusion: YEAR A B C D E F 0 -900 -1500 -2500 -4000 -5000 -7000 1 150 276 400 925 1125 1425 2 150 276 400 925 1125 1425 3 150 276 400 925 1125 1425 4 150 276 400 925 1125 1425 5 150 276 400 925 1125 1425 6 150 276 400 925 1125 1425 7 150 276 400 925 1125 1425 8 150 276 400 925 1125 1425 9 150 276 400 925 1125 1425 10 150 276 400 925 1125 1425 PW $21.69 $195.90 ($42.17) $1,683.72 $1,912.64 $1,756.01 Justified ? YES YES NO YES YES YES WINNER !
  • 42. • 10 year project • New equipment is required • Two vendors • MARR = 15% • Which vendor should be selected? • Cost or Service Problem • Lowest Common Multiplier (LCM) = 10 years Example 8.3 Blank (7th ed.), p. 208 Example 8.3 Blank (6th ed.), p. 284 Unequal service lives Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 42© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 43. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 43© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 44. Incremental Cash Flow Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 44© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 45. PW analysis • We could stop because the PW(15%) has signaled that A is the winner! • Lowest PW cost • Proceed with a IRR analysis BUT…. • IRR must be performed on the incremental investment Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 45© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 46. IRR (B-A) is less than the MARR of 15%. Therefore Reject B and go with A IRR (B-A) = 12.65 % Inc. Cash Flow $ 0 -5,000 1 1,900 2 1,900 3 1,900 4 1,900 5 -9,100 6 1,900 7 1,900 8 1,900 9 1,900 10 3,900 IRR 12.65% Inc. Cash Flow Results Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 46© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 47. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 47© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 48. This is the breakeven rate of return Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 48© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 49. Determining incremental DCFRR by using the AW method • Approach is particularly useful for comparing projects of unequal service lives. • Determine AWA and AWB from one cycle only. • For projects A and B, express AWA and AWB as a function of interest rate, then set (AWB – AWA = 0) • The interest rate satisfying (AWB – AWA = 0) is the breakeven incremental IRR Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 49© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 50. Determining incremental DCFRR by using the AW method Example: Re-do example 8.3 Determine the incremental IRR using the AW method: •10 year project (merger) •New equipment is required •Two vendors •MARR = 15% •Which vendor should be selected •Cost or Service Problem Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 50© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 51. Determining incremental DCFRR by using the AW method AWA = -8,000 (A/P, i*, 10) – 3,500 AWB = -13,000(A/P, i*, 5) + 2,000 (A/F, i*, 5) – 1,600 Set AWB - AWA = 0 Solve for breakeven i* (inc. IRR) = 12.65 (using EXCEL Solver) This is the incremental IRR; being less than MARR We then choose project A Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 51© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 52. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 52© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 53. Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 53© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 54. Home Work # 6 Thursday, March 6, 2014 Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 54© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 55. CHEE 5369 / 6369 Homework # 6 The following problem from Peters et al., fifth edition, 2003: Problem 8.16 page 356 The following solved examples from Blank and Tarquin, 7th edition, 2012: Example 5.1 Page 132 Example 6.1 Page 151 Example 8.4 page 211 Example 8.6 page 215 Example 8.7 page 216 Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 55© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved
  • 56. 8-16 Material sourced from "Plant Design and Economics for Chem. Engineers", 5th ed. by Peters et al. and also from " Engineering Economy", 6th edition,2005, by Blank and Tarquin. 56© 2003 and 2005 by McGraw-Hill, New York, N.Y All Rights Reserved