SlideShare ist ein Scribd-Unternehmen logo
1 von 17
1
ACKNOWLEDGEMENT
Today as a student,I am in high spiritand stepping forward into the
challenging future.Any technicalcourseis incompletewithoutsome type of
training.The course of B.Tech also requirestechnicaltraining.
I convey my thanksto PSPCL Jalandharauthorities for allowing me to do
this at their 66 KV Grid Sub Station at Jalandhar.
I would also like to expressmy gratitudeto my projectleader Er.chatur
singh(S.S.E.),who rendered invaluable helpand guidance during my
project.
My thanks to all staff members of the division who helped directly or in
directly in completing my project.
Last but not the least I thank all the individuals who supported and criticized
me during this period of training.
2
PUNJAB STATE POWER CORPORATION LTD. (PSPCL)
History
PSPCL was incorporated as company on 16-04-2010 and was given the responsibility of operating and
maintenance of State's own generating projects. The business of Generation of power of erstwhile PSEB
was transferred to PSPCL.
4.76 lakh new connections including 61849 No. tubewell connections were released during 2007-09.
24 Hrs. Urban pattern supply made available to 12428 villages and 6158 Deras/ Dhanies with 5 or
more houses. To help SC & BPL consumers, free monthly consumption up to 200 units allowed for
connected load of 1000 watts w.e.f. 12-10-06 instead of earlier 500 watts. Strict measures have
been taken to reduce power theft. Disciplinary action taken against the erring employees and 5
numbers Anti Power Theft Police Stations have been set up. New technologies like electronic
meters, remote control of transformers, remote meter reading and HVDS system for AP/ Industries
introduced. 20.29 lakh meters out of 55.98 lakh General/ Industrial Consumers shifted out of their
premises as on 31.3.09 to curb theft of energy. All these measures have helped in reducing losses
by 4% from 23.92% (2006–07) to 19.91% (2008–09) / which resulted in substantial increase in
revenue. During 2007-09, 62 numbers New Grid substations erected and capacity at 132 number
Grid substations augmented besides addition of 1070 circuit km. Transmission line and 149 MVAR
shunt capacitors to State Grid.
3
4
Achievements Of PSPCL
Record Availability of Machines:
 Being the largest hydroelectric complex in the region, PSPCL plays a vital role in the
day to day operation of the northern grid.
 The PSPL powerhouses provide much needed peaking power to the grid thus
enabling the thermal stations to work on base load.
 The powerhouses help in frequency regulation of the grid by flexing generation
between 1900 MW and 2800 MW in summers and between 500 MW and 1900 MW
during winters.
 The average annual plant availability of PSPCL powerhouses is around 88%. The
transmission line availability is around 99%.
5
66KV Grid Sub-Station Jalandhar
Introduction
66KV grid station Jal is one of the very important power receiving and distribution centre of PSPCL is a
vital link in the northern region powr grid of country. This substation is located on sports and surgical
complex near bawakhel on the in-skirts of Jalandhar city distance of about 7 KM from Bus stand and
about 5Km from railway station of Jal. City. The entire complex is spread over an area of approx 15.
marla, out of which 5 marla have been occupied by the grid substation comprising of switch yard , control
room,pseb carrier communication centre , compressor room, battery room, 11KV switchgear room, stores
and 150/25 Ton crane bay building. The remaining area has been used for residential complex, rest
houses, club cum dispensary building, divinl and other office building, security guard huts and garages
etc.
11 KV Feeders
Sr.no TRANSFORMER (t1) TRANSFORMER (t2) TRANSFORMER (t3)
1 Gazipur Treatment plant 2 Kapurthala road
2 Variyana complex 2 Leather complex Friends
3 Sangal shoal Neel kamal Kanal
4 Basti peer daad Basti bawakhel Sutlej
5 Basti mitthu Jalandhar kunz Treatment plant 1
6 Juneja surgical Videsh sanchar
7 Variyana complex 1 Ganda nala
8 National park
9 3 spare
6
Equipments installed at 66 KV Grid Substation
PSPCL. Jalandhar
Transformer
Transformer is a static device which transform electrical energy one circuit to
another without any direct electrical connection with the help of mutual induction
between two winding
It transform power from one circuit to another circuit without changing the
frequency but may different voltage level
Working principal of Transformer
The working principal of transformer is very simple .it depends on faradays law of
electromagnetic induction
Actually mutual induction between two or more winding is responsible for transformation
action in an electrical transformer
7
Faraday's Laws of Electromagnetic Induction
According to these Faraday's laws,
"Rate of change of flux linkage with respect to time is directly proportional to the induced EMF in a
conductor or coil".
Main Constructional Parts of Transformer
The three main parts of a transformer are,
1. Primary Winding of transformer - which produces magnetic flux when it is connected
to electrical source.
2. Magnetic Core of transformer - the magnetic flux produced by the primary winding,
that will pass through this low reluctance path linked with secondary winding and create
a closed magnetic circuit.
3. Secondary Winding of transformer - the flux, produced by primary winding, passes
through the core, will link with the secondary winding. This winding also wounds on the
same core and gives the desired output of the transformer.
8
Circuit Breakers
A circuit breaker is an automatically
operated electrical switch designed to protect
an electrical circuit from damage caused
by overload or short circuit. Its basic function is
to detect a fault condition and interrupt current
flow. Unlike a fuse, which operates once and
then must be replaced, a circuit breaker can be
reset (either manually or automatically) to
resume normal operation. Circuit breakers are
made in varying sizes, from small devices that
protect an individual household appliance up to
large switchgear designed to protect high-
voltage circuits feeding an entire city.
Operation
All circuit breakers have common features in
their operation, although details vary
substantially depending on the voltage class,
current rating and type of the circuit breaker.The
circuit breaker must detect a fault condition; in
low-voltage circuit breakers this is usually done
within the breaker enclosure. Circuit breakers for
large currents or high voltages are usually
arranged with pilot devices to sense a fault
current and to operate the trip opening mechanism. The trip solenoid that releases the latch is usually
energized by a separate battery, although some high-voltage circuit breakers are self-contained with
current transformers, protection relays, and an internal control power source.
Once a fault is detected, contacts within the circuit breaker must open to interrupt the circuit; some
mechanically-stored energy (using something such as springs or compressed air) contained within the
breaker is used to separate the contacts, although some of the energy required may be obtained from the
fault current itself. Small circuit breakers may be manually operated, larger units have solenoids to trip the
mechanism, and electric motors to restore energy to the springs.
9
The circuit breaker contacts must carry the load current without excessive heating, and must also
withstand the heat of the arc produced when interrupting (opening) the circuit. Contacts are made of
copper or copper alloys, silver alloys, and other highly conductive materials. Service life of the contacts is
limited by the erosion of contact material due to arcing while interrupting the current. Miniature and
molded case circuit breakers are usually discarded when the contacts have worn, but power circuit
breakers and high-voltage circuit breakers have replaceable contacts.
When a current is interrupted, an arc is generated. This arc must be contained, cooled, and extinguished
in a controlled way, so that the gap between the contacts can again withstand the voltage in the circuit.
Different circuit breakers use vacuum, air, insulating gas, or oil as the medium the arc forms in.
Different techniques are used to extinguish the arc including:
 Lengthening / deflection of the arc
 Intensive cooling (in jet chambers)
 Division into partial arcs
 Zero point quenching (Contacts open at the zero current time crossing of the AC waveform,
effectively breaking no load current at the time of opening. The zero crossing occurs at twice the
line frequency i.e. 100 times per second for 50 Hz and 120 times per second for 60 Hz AC)
 Connecting capacitors in parallel with contacts in DC circuits.
Finally, once the fault condition has been cleared, the contacts must again be closed to restore power to
the interrupted circuit..
Sulphur Hexafluoride Circuit Breaker (SF6)
High-voltage circuit breakers have greatly changed since they were first introduced in the mid-1950s, and
several interrupting principles have been developed that have contributed successively to a large
reduction of the operating energy. These breakers are available for indoor or outdoor applications, the
latter being in the form of breaker poles housed in ceramic insulators mounted on a structure.
Current interruption in a high-voltage circuit-breaker is obtained by separating two contacts in a medium,
such as sulfur hexafluoride (SF6), having excellent dielectric and arc-quenching properties. After contact
separation, current is carried through an arc and is interrupted when this arc is cooled by a gas blast of
sufficient intensity.
10
Isolators
n electrical engineering,
a disconnector or isolator switch or disconnect
switch is used to make sure that an electrical
circuit can be completely de-energised for
service or maintenance. Such switches are
often found in electrical
distribution and industrial applications where
machinery must have its source of driving
power removed for adjustment or repair. High-
voltage isolation switches are used in electrical
substations to allow isolation of apparatus such
as circuit breakers and transformers and
transmission lines, for maintenance. Often the
isolation switch is not intended for normal
control of the circuit and is used only for
solation; in such a case, it functions as a
second, usually physically distant master
switch (wired in series with the primary one)
that can independently disable the circuit even if the master switch used in everyday operation is turned
on.
Current Transformer (C.T’s)
A current transformer (CT) is used for measurement of alternating electric currents. Current transformers,
together with voltage transformers (VT) (potential transformers (PT)), are known as instrument
transformers. When current in a circuit is too high to directly apply to measuring instruments, a current
transformer produces a reduced current accurately proportional to the current in the circuit, which can be
conveniently connected to measuring and recording instruments. A current transformer also isolates the
11
measuring instruments from what may be very high voltage in the monitored circuit. Current transformers
are commonly used in metering and protective relays in the electrical power industry.
Design
Like any other transformer, a current transformer has a primary winding, a magnetic core, and a
secondary winding. The alternating current flowing in the primary produces an alternating magnetic field
in the core, which then induces an alternating current in the secondary winding circuit. An essential
objective of current transformer design is to ensure that the primary and secondary circuits are efficiently
coupled, so that the secondary current bears an accurate relationship to the primary current.
Usage
Current transformers are used extensively for measuring current and monitoring the operation of
the power grid. Along with voltage leads, revenue-grade CTs drive the electrical utility's watt-hour meter
on virtually every building with three-phase service and single-phase services greater than 200 amps.
The CT is typically described by its current ratio from primary to secondary. Often, multiple CTs are
installed as a "stack" for various uses. For example, protection devices and revenue metering may use
separate CTs to provide isolation between metering and protection circuits, and allows current
transformers and different characteristics (accuracy, overload performance) to be used for the devices.
The accuracy of a CT is directly related to a number of factors including:
 Burden
 Burden class/saturation class
 Rating factor
 Load
 External electromagnetic fields
 Temperature and
 Physical configuration.
 The selected tap, for multi-ratio CTs
12
Lightening Arrestor
A surge arrester is a product installed near the end of any conductor of sufficient length prior to the
conductor landing on its intended electrical component. The purpose is to divert
damaging lightning induced transients safely to ground through property changes to its varistor in parallel
arrangement to the conductor inside the unit. Also called a surge protection device (SPD) or transient
voltage surge suppressor (TVSS), they are only designed to protect against electrical transients resulting
from the lightning flash, not a direct lightning termination to the conductors themselves.
Lightning termination to earth results in ground currents which pass over buried conductors and induce a
transient that propagates outward towards the ends of the conductor. The same induction happens in
overhead and above ground conductors which experience the passing energy of an atmospheric EMP
caused by the flash.
Types
 Low-voltage surge arrester Apply in Low-voltage distribution system, exchange of electrical
appliances protector, low-voltage distribution transformer windings
 Distribution arrester Apply in 3KV, 6KV, 10KV AC power distribution system to protect distribution
transformers, cables and power station equipment
 Protection of rotating machine using magnetic blow valve arrester Used to protect the AC
generator and motor insulation
 Line Magnetic blow valve arrester Used to protect 330KV and above communication system circuit
equipment insulation
 DC or blowing valve-type arrester Use to protect the DC system’s insulation of electrical equipment
 Neutral protection arrester Apply in motor or the transformer’s neutral protection
 Fiber-tube arrester Apply in the power station’s wires and the weaknesses protection in the
insulated
 High-frequency feeder arrester Used to protect the microwave, mobile base stations satellite
receiver, etc.
 Receptacle-type surge arrester Use to Protect the terminal Electronic equipment
 Network arrester Apply in servers, workstations, interfaces etc.
 Coaxial cable lightning arrester Used to the coaxial cable in order to protect the wireless
transmission and receiving system
13
Potential Transformer(P.T’s)
Potential transformers (PT) (also called voltage transformers (VT) are a parallel connected type of
instrument transformer. They are designed to present negligible load to the supply being measured and
have an accurate voltage ratio and phase relationship to enable accurate secondary connected metering.
Ratio
The PT is typically described by its voltage ratio from primary to secondary. A 600:120 PT would provide
an output voltage of 120 volts when 600 volts are impressed across its primary winding. Standard
secondary voltage ratings are 120 volts and 70 volts, compatible with standard measuring instruments.
Main applications of CVTs in HV Networks
 Voltage Measuring: They accurately transform transmission voltages down to useable levels for
revenue metering, protection and control purposes
 Insulation: They guarantee the insulation between HV network and LV circuits ensuring safety
condition to control room operators
 HF Transmissions: They can be used for Power Line Carrier (PLC) coupling
 Transient Recovery Voltage: When installed in close proximity to HV/EHV Circuit Breakers, CVT’s
own High Capacitance enhance C/B short line fault / TRV performance
Mechanical Features
 Available with standard/heavy/very heavy creepage distance
 All external components are made by aluminum
 Inox steel bellows
 High earthquake strength capability
 Suitable for ambient temperature -60 / +70 °C (extended range upon request)
 Available for Line Traps mounting on the top
Electrical Features
 Best capacitance/accuracy stabilities in all service conditions
 Design solutions allow to reach High Rated Capacitance in reduced CVTs dimensions
 Passive ferroresonance suppression circuit provides superior damping while not degrading
transient response
 Best accuracy as transient performance – suitable for ultra-rapid line protection devices
14
Wave trap
Wave Traps are used at sub-stations using Power Line Carrier Communication (PLCC). PLCC
is used to transmit communication and control information at a high frequency over the power
lines. This reduces need for a separate infra for communication between sub-stations.
The Wave Traps extract the high frequency information from the power lines and route it to the
telecomm panels. They also block any surges from passing through.
Wave Traps are simply resonant circuits that produce a high impedance against PLCC carrier
frequencies (24kHz - 500kHz) while allowing power frequency (50Hz - 60Hz).
15
66 KV SYSTEM
Specifications of Equipments installed at 66 KV
system
Specification of transformers
TRANSFORMER
(T1)
TRANSFORMER(T2) TRANSFORMER
(T3)
Company name Apex Technical association ltd. Technical association
ltd.
Kva 16000/20000 31500/25000 31500/25000
Volts at no load HV :66000
LV:11000
HV :66000
LV:11000
HV :66000
LV:11000
Ampere HV :140.0/175.0
LV:839.8/1049.7
HV:275/218.7
LV:1653/1312.1
HV:275/218.7
LV:1653/1312.1
Phase HV:3
LV:3
HV:3
LV:3
HV:3
LV:3
HV ball line end 325kvp 325kvp
LV ball line and
neautral end
95kvp 95kvp
Guranted max. temp.
rise of winding/oil
40/50 c 45 / 35 c 45 / 35
Temperature gradient c° 11.54 c° 11.54
Max. ambient temp. c° 50 c° 50 c° 50
16
Type of cooling ONAF/ONAN ONAF/ONAN
Impedence voltage 10% 10%
Wt. of bare copper 5200 kg 9270 kg. 9270 kg.
Core wt. 19000 kg 17900 kg 17900 kg
Wdg with insulator 9500 kg 9500 kg
Wt. of oil 8900 kg 12300 kg 12300 kg
Total mass 37400 kg 53300 kg 53300 kg
Oil litre 1000 litre 15000 litre 15000 litre
Transport mass(oil
filled)
49000 kg 49000 kg
Year of manufacture 2012 2012
Max. short circuit
duration
3 sec 5 sec. 5 sec.
17

Weitere ähnliche Inhalte

Was ist angesagt?

Transformer protection
Transformer protectionTransformer protection
Transformer protectionjawaharramaya
 
Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)Sourabh sharma
 
Substations
SubstationsSubstations
Substationsitfakash
 
Design of substation
Design of substationDesign of substation
Design of substationSayanSarkar55
 
Numerical Relaying.pptx
Numerical Relaying.pptxNumerical Relaying.pptx
Numerical Relaying.pptxrohith650557
 
Ppt of current transformer
Ppt of current transformerPpt of current transformer
Ppt of current transformerROOPAL PANCHOLI
 
Electrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirElectrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirSheikh Shakir
 
final year project report
final year project reportfinal year project report
final year project reportAnuj Kumar
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & MaintenanceHimansu Pradhan
 
Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-StationTowfiqur Rahman
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substationsvishalgohel12195
 
Switchyard design overview
Switchyard design overviewSwitchyard design overview
Switchyard design overviewMilind Punj
 
Capacitive voltage transformer (1)
Capacitive voltage transformer (1)Capacitive voltage transformer (1)
Capacitive voltage transformer (1)kaushal boghani
 
Line to Line & Double Line to Ground Fault On Power System
Line to Line & Double Line to Ground Fault On Power SystemLine to Line & Double Line to Ground Fault On Power System
Line to Line & Double Line to Ground Fault On Power SystemSmit Shah
 
Protection and control of Microgrid
Protection and control of MicrogridProtection and control of Microgrid
Protection and control of MicrogridAmarjeet S Pandey
 
Selection Of Circuit Breaker
Selection Of Circuit BreakerSelection Of Circuit Breaker
Selection Of Circuit BreakerRaviraj solanki
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.Hemendra Kumar Rajput
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level CalculationDinesh Sarda
 

Was ist angesagt? (20)

Transformer protection
Transformer protectionTransformer protection
Transformer protection
 
Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)Electrical substation (one and half breaker scheme)
Electrical substation (one and half breaker scheme)
 
Substations
SubstationsSubstations
Substations
 
Design of substation
Design of substationDesign of substation
Design of substation
 
132 kv
132 kv132 kv
132 kv
 
Numerical Relaying.pptx
Numerical Relaying.pptxNumerical Relaying.pptx
Numerical Relaying.pptx
 
Ppt of current transformer
Ppt of current transformerPpt of current transformer
Ppt of current transformer
 
Electrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirElectrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakir
 
final year project report
final year project reportfinal year project report
final year project report
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
 
Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-Station
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
 
Switchyard design overview
Switchyard design overviewSwitchyard design overview
Switchyard design overview
 
Capacitive voltage transformer (1)
Capacitive voltage transformer (1)Capacitive voltage transformer (1)
Capacitive voltage transformer (1)
 
Line to Line & Double Line to Ground Fault On Power System
Line to Line & Double Line to Ground Fault On Power SystemLine to Line & Double Line to Ground Fault On Power System
Line to Line & Double Line to Ground Fault On Power System
 
Electrical SUBSTATION ppt
Electrical SUBSTATION pptElectrical SUBSTATION ppt
Electrical SUBSTATION ppt
 
Protection and control of Microgrid
Protection and control of MicrogridProtection and control of Microgrid
Protection and control of Microgrid
 
Selection Of Circuit Breaker
Selection Of Circuit BreakerSelection Of Circuit Breaker
Selection Of Circuit Breaker
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 

Andere mochten auch

33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)Prateek Agarwal
 
Benefits in moving the intra-array voltage from 33 kV to 66 kV AC for large o...
Benefits in moving the intra-array voltage from 33 kV to 66 kV AC for large o...Benefits in moving the intra-array voltage from 33 kV to 66 kV AC for large o...
Benefits in moving the intra-array voltage from 33 kV to 66 kV AC for large o...Torben Haagh
 
Blackall 66-22kV Substation Package for Ergon Energy
Blackall 66-22kV Substation Package for Ergon EnergyBlackall 66-22kV Substation Package for Ergon Energy
Blackall 66-22kV Substation Package for Ergon EnergyGary Hayes
 
66kV Offshore Wind Farm - Wet Design for Higher Voltage Wind Farm Applications
66kV Offshore Wind Farm - Wet Design for Higher Voltage Wind Farm Applications66kV Offshore Wind Farm - Wet Design for Higher Voltage Wind Farm Applications
66kV Offshore Wind Farm - Wet Design for Higher Voltage Wind Farm ApplicationsTorben Haagh
 
Training report of 33/11kv substation Mohamdabad, Tundla
Training report of 33/11kv substation Mohamdabad, TundlaTraining report of 33/11kv substation Mohamdabad, Tundla
Training report of 33/11kv substation Mohamdabad, Tundlashashanksltor
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentationKamal Mittal
 
132kv Substation
132kv Substation132kv Substation
132kv Substationguestecdd58
 

Andere mochten auch (10)

220 66 kv nrs sub report
220 66 kv nrs sub report220 66 kv nrs sub report
220 66 kv nrs sub report
 
33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)
 
Benefits in moving the intra-array voltage from 33 kV to 66 kV AC for large o...
Benefits in moving the intra-array voltage from 33 kV to 66 kV AC for large o...Benefits in moving the intra-array voltage from 33 kV to 66 kV AC for large o...
Benefits in moving the intra-array voltage from 33 kV to 66 kV AC for large o...
 
Blackall 66-22kV Substation Package for Ergon Energy
Blackall 66-22kV Substation Package for Ergon EnergyBlackall 66-22kV Substation Package for Ergon Energy
Blackall 66-22kV Substation Package for Ergon Energy
 
66kV Offshore Wind Farm - Wet Design for Higher Voltage Wind Farm Applications
66kV Offshore Wind Farm - Wet Design for Higher Voltage Wind Farm Applications66kV Offshore Wind Farm - Wet Design for Higher Voltage Wind Farm Applications
66kV Offshore Wind Farm - Wet Design for Higher Voltage Wind Farm Applications
 
Training report of 33/11kv substation Mohamdabad, Tundla
Training report of 33/11kv substation Mohamdabad, TundlaTraining report of 33/11kv substation Mohamdabad, Tundla
Training report of 33/11kv substation Mohamdabad, Tundla
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
A 220kV Substation
A 220kV SubstationA 220kV Substation
A 220kV Substation
 
132kv Substation
132kv Substation132kv Substation
132kv Substation
 
Substation overview
Substation overviewSubstation overview
Substation overview
 

Ähnlich wie 66 kv substation

Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Mohit Kothari
 
Gssherap 110901224655-phpapp0
Gssherap 110901224655-phpapp0Gssherap 110901224655-phpapp0
Gssherap 110901224655-phpapp0Mohit Kothari
 
Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Mohit Kothari
 
132 kv sub-station, power transmission
132 kv sub-station, power transmission132 kv sub-station, power transmission
132 kv sub-station, power transmissionprasantakcs
 
Bses powerpoint presentation
Bses powerpoint presentationBses powerpoint presentation
Bses powerpoint presentationAnuj Gupta
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at JassureShuvam Pathania
 
INTERNSHhjjhuhjjkhhjhjjhhjhhIP ppt-1.pptx
INTERNSHhjjhuhjjkhhjhjjhhjhhIP ppt-1.pptxINTERNSHhjjhuhjjkhhjhjjhhjhhIP ppt-1.pptx
INTERNSHhjjhuhjjkhhjhjjhhjhhIP ppt-1.pptxSrujan99
 
protection scheme of a grid substation prsentation
protection scheme of a grid substation prsentationprotection scheme of a grid substation prsentation
protection scheme of a grid substation prsentationabu jubayer
 
132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training reportMuntazir Mehdi
 
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOWSatya Prakash Chaurasia
 
Anurag Attri.pptx
Anurag Attri.pptxAnurag Attri.pptx
Anurag Attri.pptxAsif682330
 
Amanppt 140826070457-phpapp02
Amanppt 140826070457-phpapp02Amanppt 140826070457-phpapp02
Amanppt 140826070457-phpapp02Md Hasan
 
132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCLAman Rajput
 
132 kv substation
132 kv substation132 kv substation
132 kv substationWipro
 
Report On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-StationReport On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-StationEkram Bin Mamun
 
Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7Sachin Airan
 
132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptxAsif682330
 
Presentation on BSPTCL Grid Sub-Station
Presentation on BSPTCL Grid Sub-StationPresentation on BSPTCL Grid Sub-Station
Presentation on BSPTCL Grid Sub-StationRahul Prajapati
 

Ähnlich wie 66 kv substation (20)

Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02
 
Gssherap 110901224655-phpapp0
Gssherap 110901224655-phpapp0Gssherap 110901224655-phpapp0
Gssherap 110901224655-phpapp0
 
Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02
 
132 kv sub-station, power transmission
132 kv sub-station, power transmission132 kv sub-station, power transmission
132 kv sub-station, power transmission
 
DPL Training .doc file
DPL Training .doc file DPL Training .doc file
DPL Training .doc file
 
Bses powerpoint presentation
Bses powerpoint presentationBses powerpoint presentation
Bses powerpoint presentation
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
 
INTERNSHhjjhuhjjkhhjhjjhhjhhIP ppt-1.pptx
INTERNSHhjjhuhjjkhhjhjjhhjhhIP ppt-1.pptxINTERNSHhjjhuhjjkhhjhjjhhjhhIP ppt-1.pptx
INTERNSHhjjhuhjjkhhjhjjhhjhhIP ppt-1.pptx
 
protection scheme of a grid substation prsentation
protection scheme of a grid substation prsentationprotection scheme of a grid substation prsentation
protection scheme of a grid substation prsentation
 
132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report
 
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI  NAGAR, LUCKNOW
33/11 KV SUB-STATION, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW
 
Anurag Attri.pptx
Anurag Attri.pptxAnurag Attri.pptx
Anurag Attri.pptx
 
Amanppt 140826070457-phpapp02
Amanppt 140826070457-phpapp02Amanppt 140826070457-phpapp02
Amanppt 140826070457-phpapp02
 
132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL
 
ms ppt.ppt
ms ppt.pptms ppt.ppt
ms ppt.ppt
 
132 kv substation
132 kv substation132 kv substation
132 kv substation
 
Report On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-StationReport On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-Station
 
Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7
 
132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx132 KV Substation Gajraula.pptx
132 KV Substation Gajraula.pptx
 
Presentation on BSPTCL Grid Sub-Station
Presentation on BSPTCL Grid Sub-StationPresentation on BSPTCL Grid Sub-Station
Presentation on BSPTCL Grid Sub-Station
 

Kürzlich hochgeladen

DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesMayuraD1
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersMairaAshraf6
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadhamedmustafa094
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEselvakumar948
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 

Kürzlich hochgeladen (20)

DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 

66 kv substation

  • 1. 1 ACKNOWLEDGEMENT Today as a student,I am in high spiritand stepping forward into the challenging future.Any technicalcourseis incompletewithoutsome type of training.The course of B.Tech also requirestechnicaltraining. I convey my thanksto PSPCL Jalandharauthorities for allowing me to do this at their 66 KV Grid Sub Station at Jalandhar. I would also like to expressmy gratitudeto my projectleader Er.chatur singh(S.S.E.),who rendered invaluable helpand guidance during my project. My thanks to all staff members of the division who helped directly or in directly in completing my project. Last but not the least I thank all the individuals who supported and criticized me during this period of training.
  • 2. 2 PUNJAB STATE POWER CORPORATION LTD. (PSPCL) History PSPCL was incorporated as company on 16-04-2010 and was given the responsibility of operating and maintenance of State's own generating projects. The business of Generation of power of erstwhile PSEB was transferred to PSPCL. 4.76 lakh new connections including 61849 No. tubewell connections were released during 2007-09. 24 Hrs. Urban pattern supply made available to 12428 villages and 6158 Deras/ Dhanies with 5 or more houses. To help SC & BPL consumers, free monthly consumption up to 200 units allowed for connected load of 1000 watts w.e.f. 12-10-06 instead of earlier 500 watts. Strict measures have been taken to reduce power theft. Disciplinary action taken against the erring employees and 5 numbers Anti Power Theft Police Stations have been set up. New technologies like electronic meters, remote control of transformers, remote meter reading and HVDS system for AP/ Industries introduced. 20.29 lakh meters out of 55.98 lakh General/ Industrial Consumers shifted out of their premises as on 31.3.09 to curb theft of energy. All these measures have helped in reducing losses by 4% from 23.92% (2006–07) to 19.91% (2008–09) / which resulted in substantial increase in revenue. During 2007-09, 62 numbers New Grid substations erected and capacity at 132 number Grid substations augmented besides addition of 1070 circuit km. Transmission line and 149 MVAR shunt capacitors to State Grid.
  • 3. 3
  • 4. 4 Achievements Of PSPCL Record Availability of Machines:  Being the largest hydroelectric complex in the region, PSPCL plays a vital role in the day to day operation of the northern grid.  The PSPL powerhouses provide much needed peaking power to the grid thus enabling the thermal stations to work on base load.  The powerhouses help in frequency regulation of the grid by flexing generation between 1900 MW and 2800 MW in summers and between 500 MW and 1900 MW during winters.  The average annual plant availability of PSPCL powerhouses is around 88%. The transmission line availability is around 99%.
  • 5. 5 66KV Grid Sub-Station Jalandhar Introduction 66KV grid station Jal is one of the very important power receiving and distribution centre of PSPCL is a vital link in the northern region powr grid of country. This substation is located on sports and surgical complex near bawakhel on the in-skirts of Jalandhar city distance of about 7 KM from Bus stand and about 5Km from railway station of Jal. City. The entire complex is spread over an area of approx 15. marla, out of which 5 marla have been occupied by the grid substation comprising of switch yard , control room,pseb carrier communication centre , compressor room, battery room, 11KV switchgear room, stores and 150/25 Ton crane bay building. The remaining area has been used for residential complex, rest houses, club cum dispensary building, divinl and other office building, security guard huts and garages etc. 11 KV Feeders Sr.no TRANSFORMER (t1) TRANSFORMER (t2) TRANSFORMER (t3) 1 Gazipur Treatment plant 2 Kapurthala road 2 Variyana complex 2 Leather complex Friends 3 Sangal shoal Neel kamal Kanal 4 Basti peer daad Basti bawakhel Sutlej 5 Basti mitthu Jalandhar kunz Treatment plant 1 6 Juneja surgical Videsh sanchar 7 Variyana complex 1 Ganda nala 8 National park 9 3 spare
  • 6. 6 Equipments installed at 66 KV Grid Substation PSPCL. Jalandhar Transformer Transformer is a static device which transform electrical energy one circuit to another without any direct electrical connection with the help of mutual induction between two winding It transform power from one circuit to another circuit without changing the frequency but may different voltage level Working principal of Transformer The working principal of transformer is very simple .it depends on faradays law of electromagnetic induction Actually mutual induction between two or more winding is responsible for transformation action in an electrical transformer
  • 7. 7 Faraday's Laws of Electromagnetic Induction According to these Faraday's laws, "Rate of change of flux linkage with respect to time is directly proportional to the induced EMF in a conductor or coil". Main Constructional Parts of Transformer The three main parts of a transformer are, 1. Primary Winding of transformer - which produces magnetic flux when it is connected to electrical source. 2. Magnetic Core of transformer - the magnetic flux produced by the primary winding, that will pass through this low reluctance path linked with secondary winding and create a closed magnetic circuit. 3. Secondary Winding of transformer - the flux, produced by primary winding, passes through the core, will link with the secondary winding. This winding also wounds on the same core and gives the desired output of the transformer.
  • 8. 8 Circuit Breakers A circuit breaker is an automatically operated electrical switch designed to protect an electrical circuit from damage caused by overload or short circuit. Its basic function is to detect a fault condition and interrupt current flow. Unlike a fuse, which operates once and then must be replaced, a circuit breaker can be reset (either manually or automatically) to resume normal operation. Circuit breakers are made in varying sizes, from small devices that protect an individual household appliance up to large switchgear designed to protect high- voltage circuits feeding an entire city. Operation All circuit breakers have common features in their operation, although details vary substantially depending on the voltage class, current rating and type of the circuit breaker.The circuit breaker must detect a fault condition; in low-voltage circuit breakers this is usually done within the breaker enclosure. Circuit breakers for large currents or high voltages are usually arranged with pilot devices to sense a fault current and to operate the trip opening mechanism. The trip solenoid that releases the latch is usually energized by a separate battery, although some high-voltage circuit breakers are self-contained with current transformers, protection relays, and an internal control power source. Once a fault is detected, contacts within the circuit breaker must open to interrupt the circuit; some mechanically-stored energy (using something such as springs or compressed air) contained within the breaker is used to separate the contacts, although some of the energy required may be obtained from the fault current itself. Small circuit breakers may be manually operated, larger units have solenoids to trip the mechanism, and electric motors to restore energy to the springs.
  • 9. 9 The circuit breaker contacts must carry the load current without excessive heating, and must also withstand the heat of the arc produced when interrupting (opening) the circuit. Contacts are made of copper or copper alloys, silver alloys, and other highly conductive materials. Service life of the contacts is limited by the erosion of contact material due to arcing while interrupting the current. Miniature and molded case circuit breakers are usually discarded when the contacts have worn, but power circuit breakers and high-voltage circuit breakers have replaceable contacts. When a current is interrupted, an arc is generated. This arc must be contained, cooled, and extinguished in a controlled way, so that the gap between the contacts can again withstand the voltage in the circuit. Different circuit breakers use vacuum, air, insulating gas, or oil as the medium the arc forms in. Different techniques are used to extinguish the arc including:  Lengthening / deflection of the arc  Intensive cooling (in jet chambers)  Division into partial arcs  Zero point quenching (Contacts open at the zero current time crossing of the AC waveform, effectively breaking no load current at the time of opening. The zero crossing occurs at twice the line frequency i.e. 100 times per second for 50 Hz and 120 times per second for 60 Hz AC)  Connecting capacitors in parallel with contacts in DC circuits. Finally, once the fault condition has been cleared, the contacts must again be closed to restore power to the interrupted circuit.. Sulphur Hexafluoride Circuit Breaker (SF6) High-voltage circuit breakers have greatly changed since they were first introduced in the mid-1950s, and several interrupting principles have been developed that have contributed successively to a large reduction of the operating energy. These breakers are available for indoor or outdoor applications, the latter being in the form of breaker poles housed in ceramic insulators mounted on a structure. Current interruption in a high-voltage circuit-breaker is obtained by separating two contacts in a medium, such as sulfur hexafluoride (SF6), having excellent dielectric and arc-quenching properties. After contact separation, current is carried through an arc and is interrupted when this arc is cooled by a gas blast of sufficient intensity.
  • 10. 10 Isolators n electrical engineering, a disconnector or isolator switch or disconnect switch is used to make sure that an electrical circuit can be completely de-energised for service or maintenance. Such switches are often found in electrical distribution and industrial applications where machinery must have its source of driving power removed for adjustment or repair. High- voltage isolation switches are used in electrical substations to allow isolation of apparatus such as circuit breakers and transformers and transmission lines, for maintenance. Often the isolation switch is not intended for normal control of the circuit and is used only for solation; in such a case, it functions as a second, usually physically distant master switch (wired in series with the primary one) that can independently disable the circuit even if the master switch used in everyday operation is turned on. Current Transformer (C.T’s) A current transformer (CT) is used for measurement of alternating electric currents. Current transformers, together with voltage transformers (VT) (potential transformers (PT)), are known as instrument transformers. When current in a circuit is too high to directly apply to measuring instruments, a current transformer produces a reduced current accurately proportional to the current in the circuit, which can be conveniently connected to measuring and recording instruments. A current transformer also isolates the
  • 11. 11 measuring instruments from what may be very high voltage in the monitored circuit. Current transformers are commonly used in metering and protective relays in the electrical power industry. Design Like any other transformer, a current transformer has a primary winding, a magnetic core, and a secondary winding. The alternating current flowing in the primary produces an alternating magnetic field in the core, which then induces an alternating current in the secondary winding circuit. An essential objective of current transformer design is to ensure that the primary and secondary circuits are efficiently coupled, so that the secondary current bears an accurate relationship to the primary current. Usage Current transformers are used extensively for measuring current and monitoring the operation of the power grid. Along with voltage leads, revenue-grade CTs drive the electrical utility's watt-hour meter on virtually every building with three-phase service and single-phase services greater than 200 amps. The CT is typically described by its current ratio from primary to secondary. Often, multiple CTs are installed as a "stack" for various uses. For example, protection devices and revenue metering may use separate CTs to provide isolation between metering and protection circuits, and allows current transformers and different characteristics (accuracy, overload performance) to be used for the devices. The accuracy of a CT is directly related to a number of factors including:  Burden  Burden class/saturation class  Rating factor  Load  External electromagnetic fields  Temperature and  Physical configuration.  The selected tap, for multi-ratio CTs
  • 12. 12 Lightening Arrestor A surge arrester is a product installed near the end of any conductor of sufficient length prior to the conductor landing on its intended electrical component. The purpose is to divert damaging lightning induced transients safely to ground through property changes to its varistor in parallel arrangement to the conductor inside the unit. Also called a surge protection device (SPD) or transient voltage surge suppressor (TVSS), they are only designed to protect against electrical transients resulting from the lightning flash, not a direct lightning termination to the conductors themselves. Lightning termination to earth results in ground currents which pass over buried conductors and induce a transient that propagates outward towards the ends of the conductor. The same induction happens in overhead and above ground conductors which experience the passing energy of an atmospheric EMP caused by the flash. Types  Low-voltage surge arrester Apply in Low-voltage distribution system, exchange of electrical appliances protector, low-voltage distribution transformer windings  Distribution arrester Apply in 3KV, 6KV, 10KV AC power distribution system to protect distribution transformers, cables and power station equipment  Protection of rotating machine using magnetic blow valve arrester Used to protect the AC generator and motor insulation  Line Magnetic blow valve arrester Used to protect 330KV and above communication system circuit equipment insulation  DC or blowing valve-type arrester Use to protect the DC system’s insulation of electrical equipment  Neutral protection arrester Apply in motor or the transformer’s neutral protection  Fiber-tube arrester Apply in the power station’s wires and the weaknesses protection in the insulated  High-frequency feeder arrester Used to protect the microwave, mobile base stations satellite receiver, etc.  Receptacle-type surge arrester Use to Protect the terminal Electronic equipment  Network arrester Apply in servers, workstations, interfaces etc.  Coaxial cable lightning arrester Used to the coaxial cable in order to protect the wireless transmission and receiving system
  • 13. 13 Potential Transformer(P.T’s) Potential transformers (PT) (also called voltage transformers (VT) are a parallel connected type of instrument transformer. They are designed to present negligible load to the supply being measured and have an accurate voltage ratio and phase relationship to enable accurate secondary connected metering. Ratio The PT is typically described by its voltage ratio from primary to secondary. A 600:120 PT would provide an output voltage of 120 volts when 600 volts are impressed across its primary winding. Standard secondary voltage ratings are 120 volts and 70 volts, compatible with standard measuring instruments. Main applications of CVTs in HV Networks  Voltage Measuring: They accurately transform transmission voltages down to useable levels for revenue metering, protection and control purposes  Insulation: They guarantee the insulation between HV network and LV circuits ensuring safety condition to control room operators  HF Transmissions: They can be used for Power Line Carrier (PLC) coupling  Transient Recovery Voltage: When installed in close proximity to HV/EHV Circuit Breakers, CVT’s own High Capacitance enhance C/B short line fault / TRV performance Mechanical Features  Available with standard/heavy/very heavy creepage distance  All external components are made by aluminum  Inox steel bellows  High earthquake strength capability  Suitable for ambient temperature -60 / +70 °C (extended range upon request)  Available for Line Traps mounting on the top Electrical Features  Best capacitance/accuracy stabilities in all service conditions  Design solutions allow to reach High Rated Capacitance in reduced CVTs dimensions  Passive ferroresonance suppression circuit provides superior damping while not degrading transient response  Best accuracy as transient performance – suitable for ultra-rapid line protection devices
  • 14. 14 Wave trap Wave Traps are used at sub-stations using Power Line Carrier Communication (PLCC). PLCC is used to transmit communication and control information at a high frequency over the power lines. This reduces need for a separate infra for communication between sub-stations. The Wave Traps extract the high frequency information from the power lines and route it to the telecomm panels. They also block any surges from passing through. Wave Traps are simply resonant circuits that produce a high impedance against PLCC carrier frequencies (24kHz - 500kHz) while allowing power frequency (50Hz - 60Hz).
  • 15. 15 66 KV SYSTEM Specifications of Equipments installed at 66 KV system Specification of transformers TRANSFORMER (T1) TRANSFORMER(T2) TRANSFORMER (T3) Company name Apex Technical association ltd. Technical association ltd. Kva 16000/20000 31500/25000 31500/25000 Volts at no load HV :66000 LV:11000 HV :66000 LV:11000 HV :66000 LV:11000 Ampere HV :140.0/175.0 LV:839.8/1049.7 HV:275/218.7 LV:1653/1312.1 HV:275/218.7 LV:1653/1312.1 Phase HV:3 LV:3 HV:3 LV:3 HV:3 LV:3 HV ball line end 325kvp 325kvp LV ball line and neautral end 95kvp 95kvp Guranted max. temp. rise of winding/oil 40/50 c 45 / 35 c 45 / 35 Temperature gradient c° 11.54 c° 11.54 Max. ambient temp. c° 50 c° 50 c° 50
  • 16. 16 Type of cooling ONAF/ONAN ONAF/ONAN Impedence voltage 10% 10% Wt. of bare copper 5200 kg 9270 kg. 9270 kg. Core wt. 19000 kg 17900 kg 17900 kg Wdg with insulator 9500 kg 9500 kg Wt. of oil 8900 kg 12300 kg 12300 kg Total mass 37400 kg 53300 kg 53300 kg Oil litre 1000 litre 15000 litre 15000 litre Transport mass(oil filled) 49000 kg 49000 kg Year of manufacture 2012 2012 Max. short circuit duration 3 sec 5 sec. 5 sec.
  • 17. 17