This diagram illustrates the scrum process. Planning and estimation is integrated within the process.
During project preparation - Build scope = start of requirements inventory (high-level product and release planning)
During sprint planning (Detailed release planning)
Meeting 1: Stakeholders and product owner put items in the backlog of the next iteration.
Meeting 2 :
During standup meetings (Daily cycle) (Detailed daily planning)
What did I do yesterday --> to evaluate progress, learning opportunities
What will I do today --> To optimize daily efforts
What will keep me from doing my work today --> to obtain help - be more productive.
...
This diagram illustrates the scrum process. Planning and estimation is integrated within the process.
During project preparation - Build scope = start of requirements inventory (high-level product and release planning)
During sprint planning (Detailed release planning)
Meeting 1: Stakeholders and product owner put items in the backlog of the next iteration.
Meeting 2 :
During standup meetings (Daily cycle) (Detailed daily planning)
What did I do yesterday --> to evaluate progress, learning opportunities
What will I do today --> To optimize daily efforts
What will keep me from doing my work today --> to obtain help - be more productive.
...
This diagram illustrates the scrum process. Planning and estimation is integrated within the process.
During project preparation - Build scope = start of requirements inventory (high-level product and release planning)
During sprint planning (Detailed release planning)
Meeting 1: Stakeholders and product owner put items in the backlog of the next iteration.
Meeting 2 :
During standup meetings (Daily cycle) (Detailed daily planning)
What did I do yesterday --> to evaluate progress, learning opportunities
What will I do today --> To optimize daily efforts
What will keep me from doing my work today --> to obtain help - be more productive.
...
Adhere to the XP principles;
+ DTSTTCPW
+ DRY
+ TDD
+ ...
Pull Pair programming:
challenging stories are done in pair, others not.
Works great with mature team; build by people who know their strengths and weaknesses.
In the E4N project the following artefacts are unit tested:
+ Smoke tests for each individual screen
+ Integration tests on the Service level
+ Individual unit tests for the domain, and status automat.
This is the actual burndown of the E4N project.
The team had 225 hours to burn during the sprint (22,5 hours/day or 3 FTE with 1FTE 2 days on holiday)
Estimated accuracy - to be added
This is the actual burndown of the E4N project.
The team had 225 hours to burn during the sprint (22,5 hours/day or 3 FTE with 1FTE 2 days on holiday)
Estimated accuracy - to be added
This is the actual burndown of the E4N project.
The team had 225 hours to burn during the sprint (22,5 hours/day or 3 FTE with 1FTE 2 days on holiday)
Estimated accuracy - to be added
This is the actual burndown of the E4N project.
The team had 225 hours to burn during the sprint (22,5 hours/day or 3 FTE with 1FTE 2 days on holiday)
Estimated accuracy - to be added
This is the actual burndown of the E4N project.
The team had 225 hours to burn during the sprint (22,5 hours/day or 3 FTE with 1FTE 2 days on holiday)
Estimated accuracy - to be added
This is the actual burndown of the E4N project.
The team had 225 hours to burn during the sprint (22,5 hours/day or 3 FTE with 1FTE 2 days on holiday)
Estimated accuracy - to be added
This is the actual burndown of the E4N project.
The team had 225 hours to burn during the sprint (22,5 hours/day or 3 FTE with 1FTE 2 days on holiday)
Estimated accuracy - to be added
This diagram illustrates the scrum process. Planning and estimation is integrated within the process.
During project preparation - Build scope = start of requirements inventory (high-level product and release planning)
During sprint planning (Detailed release planning)
Meeting 1: Stakeholders and product owner put items in the backlog of the next iteration.
Meeting 2 :
During standup meetings (Daily cycle) (Detailed daily planning)
What did I do yesterday --> to evaluate progress, learning opportunities
What will I do today --> To optimize daily efforts
What will keep me from doing my work today --> to obtain help - be more productive.
...
This diagram illustrates the scrum process. Planning and estimation is integrated within the process.
During project preparation - Build scope = start of requirements inventory (high-level product and release planning)
During sprint planning (Detailed release planning)
Meeting 1: Stakeholders and product owner put items in the backlog of the next iteration.
Meeting 2 :
During standup meetings (Daily cycle) (Detailed daily planning)
What did I do yesterday --> to evaluate progress, learning opportunities
What will I do today --> To optimize daily efforts
What will keep me from doing my work today --> to obtain help - be more productive.
...
This diagram illustrates the scrum process. Planning and estimation is integrated within the process.
During project preparation - Build scope = start of requirements inventory (high-level product and release planning)
During sprint planning (Detailed release planning)
Meeting 1: Stakeholders and product owner put items in the backlog of the next iteration.
Meeting 2 :
During standup meetings (Daily cycle) (Detailed daily planning)
What did I do yesterday --> to evaluate progress, learning opportunities
What will I do today --> To optimize daily efforts
What will keep me from doing my work today --> to obtain help - be more productive.
...