7. Hollywood Budget & Schedule
Project Budget
Land / Site Dev $74,884,754
Construction 148,567,886
FF & E 85,532,474
Other 31,014,886
Sub-total $340,000,000
License Fee 25,000,000
TOTAL $365,000,000
Project Schedule
Pre-Construction/Permits 9-01-08 to 12-31-08
Construction Site/Foundations 12-31-08 to 5-04-09
Construction Casino/Hotel 5-05-09 to 11-09-10
CO’s/Pre-Opening 9-09-10 to 12-09-10
Open Facility 12-09-10
8. Hollywood Wellington Site Status
• City Zoning Approval (Wellington) 9-18-07
• City Endorsement 10-16-08
• SUP Approval by Wellington BZA 11-08-07
• Sumner County Endorsement 12-22-07
• Executed Pre-Development Agreement with County 12-22-07
• Phase I Environmental – No adverse effects
Wetlands – manageable on site
Species study – none found
Drainage – no adverse effects
• Utility sourcing and coordination with City and providers has been
established
• Traffic / Off-Sites – have been reviewed and approved by KTA &
KDOT, including dedicated I-35 S exit ramp into property
Only Site with TWO Turnpike exits