12. Delhi Mumbai Industrial Corridor
MUMBAI
DFC Western corridor at a glance
•Delhi to Mumbai - High axle load 1483 km
•Influence area 150 km on both sides of the corridor
•Covering 6 states with 24 proposed nodes
•Length in Gujarat– 565 km (38%) with 6 nodes
including Ahmedabad - Dholera node
Current status of DFC Western corridor
•Under construction, approved in Rail Budget 2014-15
Project Schedule of DFC Western corridor
• Phase I (Rewari – Vadodara)
• Phase II (Vadodara – JNPT)
• Phase III (Rewari – Dadri)
920kms –
430kms
–
140kms –
2011 – 2017
2012 – 2018
2013 - 2018
DFC western corridor
Area under DMIC
M
I
C
D
C
GICC
13. Development (Master ) Plan is the Basis for DSIR Implementation
N
Total DSIR Area – 920 sqkm
Developable Area – 580 sqkm
D
M
I
C
D
C
GICC
14. Residential &
Mixed Use
14%
Industrial
14%
Infrastructure
5%
Recreational &
Tourism
11%
CRZ & Non
Developable
Land
56%
DSIR Development Plan Sanctioned Land Use Pattern
LANDUSE TYPES TOTAL DP
AREA
Ha
Residential 9,780
High Access Corridor 2,645
City Centre 679
Mixed Use
TOTAL – 13104 Ha
Industrial
11,457
Knowledge and IT 1,230
TOTAL – 12687 Ha
Solar Park 1,346
Strategic Infrastructure
3,554
Public Facilities
250 Mt. Express Road
55 Mt. DP Road
Logistics
TOTAL – 4900 Ha
Recreation, Sports and
Entertainment
4,500
Green Spaces 1,960
Tourism: Resorts 3,889
TOTAL – 10349 Ha
Gamtal 1,772
Village Buffer
Agriculture
15,272
Notified Forest Land
Water Body
River
River Buffer Zone
Coastal Regulation Zone (CRZ)
33,885
TOTAL – 50929 Ha
GRAND TOTAL 91,969
15. Dholera SIR: Key Indicators
Total Area
91,970 Ha
(920 sq km)
Area outside CRZ
58085 Ha
(580 sq. Kms)
Area under CRZ
33,885 Ha
(340 sq.
Kms)
As per Development Plan for
2042
22 Villages of Ahmedabad District
Existing Population 37000 (Census – 2001)
Population of Dholera Village 2637 (Census – 2001)
I
C
D
C
16. Dholera SIR: Development Plan Projections
Resident population in DSIR
2.0 million
Supported Jobs
484,000
Industrial, Tourism
& other Jobs
343,000
Total Jobs
827,000
As per Development Plan for
2042
C
D
C
GICC
17. Phase TP Scheme Area
(Sq.km)
Time line
1 1 51.40
2012 – 2022
2 102.34
2 3 66.60
2023 – 2032
4 60.00
3 5 74.75
2033 – 2042
6 67.33
Total 422. 42 30 years
DSIR Town Planning Schemes are Phased over 3 Decades
TP-1
M
I
C
D
C
GICC
TP-2
TP-3
TP-4
TP-5
TP-6
• All 6 Draft TP Schemes
notified
• Final TP Schemes in process
• 422 sq.km. area will be
developed from 580
sq.km available (158 sq. km.
is agriculture)
18. Electronics, High-tech
Emerging
Technologies
Pharmaceuticals and
Biotechnology
Heavy Engineering
Automobile and Auto
Ancillary Industries
General
Manufacturing
Agro and Food
Processing
Metals and
Metallurgical Products
Tourism IT & ITES Education
M
I
C
D
C
GICC
Only Non polluting industries are allowed in DSIR – as per DP
Source: Development Plan
19. DSIR Phase 1 –
(Town Planning
Scheme 1 & 2)
154 sqkm ,
Cost Breakup
I
C
D
CNo Project
Cost estimate
(in INR
Crores)
Escalation,
Project
Development,
Supervision and
Contingencies
(in INR Crores)
Total Cost
Estimate (in
INR Crores)
Overall Trunk Infrastructure Projects
1 TP1 and 2 urban development
including ABCD site
18,642.06 2,632.09 21,274.15
2 Potable water 768.52 95.01 863.53
3 Industrial water 1,403.74 173.79 1,577.53
4 Wastewater (TP level STP,
CETP and effluent
outfall)
772.00 95.41 867.41
5 Solid waste management 21.06 2.56 23.61
6 ICT 3,528.65 443.21 3,971.86
7 Power infrastructure 2819.87 350.51 3170.38
8 River training and bunding on all
rivers
705.71 87.32 793.03
TOTAL 32,541.51
External Infrastructure Projects
a Ahmedabad – Dholera
Expressway
3599.08*
b Ahmedabad – Dholera MRTS/
RRTS
7685.00*
c Freight rail from DSIR to Bhimnath 496.21**
d Dholera International Airport 1,000.00^
TOTAL 12,780.29
GRAND TOTAL FOR DSIR PHASE I 45,321.80