Sr
No.
What You need: Availability
Require
ment
met?
What I have developed as a
solution:
1
Format of Project budget
which is mapped with the
Proposal
Y/N
Skeleton format of budget is
proposed which will be useful for
Cost control during project life
view
2
Budget Summary format: We
must have predefined formats
of out budget presentation
which should be self
explanantory
(N/A)
Developed Top Summary of Budget
which will be repeatedly used in
Variance Analysis to be reported to
the Management.
view
3
Summarized monthly Project
Report describing
achievement of targets in
terms of major cost elements
comparising the project
(N/A)
Project Cost Report which will
highlight variations from monthly
budget in terms of WBEs and Cost
elements( Material, Labor etc)
view
4
Detailed monthly Project
Report which explains in detail
where variations occurred.
(N/A)
Detailed Cost Report which
explains in detail the above Project
Cost Report i.e Cost Center wise
budget, actual and variations are
provided
view
5
Consolidated Cost Report of
all Projects: A corporate level
report describing status of all
running projects
(N/A)
Summary report on all projects
which portrays Key Performance
Indicators of all running projects.
view
6
Daily Progress Report of
Project with quantities
Report
available
but without
Qty.
Developed Daily Progress Report
showing quantitative data to
measure and evaluate project
performance
view
7
Need to know which project is
over-spending in which type
of costs
Consolidated Cost Report by
elements: shows variances of
Material, Lab etc of each project in
one report
view
8
Need to know which project is
over-spending in which areas
of Project
WBE wise Cost Report: This
explains cost spent in diff kind of
activities like Excavation,
concreting etc. along with
variances
View
9
Need to know which kind of
material was used in which
kind of activities
Material Cost Variance Analysis:
shows WBE wise material
consumption with quantities and
price
view
Cost Control Reporting requirements and Solutions
Sr
No.
What You need: Availability
Require
ment
met?
What I have developed as a
solution:
Cost Control Reporting requirements and Solutions
10
Need to measure labor
utilization on different
activities (WBE)
Labor Utilization Report: It
calculates manpower employed on
each WBE and compares with
standard time required as per
Proposal
view
11
WBE wise Equipment
utilization
Equipment Utilization Report: It
portrays the usage of Equipment in
diff activities of the project
view
12
Shared Costs of Equipment to
be charged to relevant
activities
Shared Equipment Costs allocation
report is designed alongwith the
basis of allocation
view
13
Cost Audit techniques of
Project Expenses should be
provided to ensure integrity of
project data
Simple to use audit techniques are
being formulated. To check
accuracy of Material cost, attached
report is designed
view
14
Subcontractor evaluation
forms should be available to
control cost and payments to
subcontractors.
Subcontractor Evaluation Form is
designed
view
15
Cost of Production reports of
Plants
A Sample of my previous work is
attached for reference only. Actual
report will be created based on
Information systems of IMP
view
16
Weekly Project Performance
Report: Showing all critical
aspects of a Project
Not designed here, however, a
sample is avilable for adoption.
Exact report will be created based
on Information System of IMP
view
17
Expected At Completion: This
is required to be reported as
per company policy but
format is not available
This report can take any format.
For reference, image of one report
is attached.
view
18 Knowledge of your existing systems is required to make these reports successfully operational
DETAIL FORECAST COST CONTROL
Budget
Project#
Project Name:
Location:
Material Labor
Sub-
contract
Equip-
ment
Over-
head Total
1 General Costs
1 00 6 10 Insurance
2 00 6 11 CAR
3 00 6 15 CPM cover
4 00 8 90 Mobilization
5 01 3 21 Demobilization
6 01 3 31 Sign Board
7 01 4 51
2 01 5 01 Design Related Costs
3 01 5 02
4 01 5 03
5 01 5 04 General Requirements- Site Workshops
6 01 5 11 General Requirements- Temporary Water
7 01 5 12 General Requirements - Temporary Electricity
8 01 5 13 General Requirements- Temporary
Telecommunications
3 01 5 14 Architectural
4 01 5 22 General Requirements- Site Transportation
5 01 5 23 General Requirements- Site Offices and
Equipment for Contractor
4 01 5 24 Structural
4.1 Structural Steel and Re inforced
t
Shalow foundations
II. Other Provisional Cost Not Included
- - - - -
Prepared by: Approved by :
S.N
o
Cost code Description
Total Cost (Budget)
T O T A L
Budget Summary(format)
Project Name
Project No.
Employer: Expected Start Date
Expected Finish Date
Sr. BOQ Items Material Labor Subcontract Equipment Overhead Total Cost Profit Margin Total Price
1 General Costs
2 Design Costs
3 Archiectural
4 Structural
5 Geotechnical
6 Mechanical
7 Electrical
8 Utilities
9 Transportation
10 Dewatering
11 Jet Fuel Hydrant Network
TOTAL
Structural
Description RESP. Unit Total Qty.
Planned Qty.
for the
Month
Actual Qty.
for the Month
Earned %Age
This Month
Todate
Qty.
Balance Qty. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Culverts
Precast parapets IMP Cum 44,492 11,934 1,756 15% 34,314 10,178 - - - - - 94 - - 510 376 - - 83 - 232 - 461 - -
Slabs IMP Cum 226,208 1,687 1,687 100% ###### 0 - - - - 507 - - - - 484 - - - - - 696 - - -
Subco Cum 198,504 30,756 10,482 34% ###### 20,274 - - - ### - ### 810 200 362 - - - ### - #### ### ###
Subco Cum 572,669 115,202 - #REF! ###### 115,202 - - - - - - - - - - - - - - - - - - -
Cum - - - - - - - - - - - - - - - - - - -
SUB-TOTAL Cum ####### 159,579 13,925 9% ###### 145,654 - - - - - - ### 507 ### 810 200 872 860 - - ### - #### ### ### - - - - -
Geo Technical
Site Clearing KST Cum 65427 - 60,427 5,000 - - - - - - - - - - - - - - - - - - -
IMP Cum 93675 - 81,592 12,083 - - - - - - - - - - - - - - - - - - -
LBCC Cum 71,000 - 73,945 (2,945) - - - - - - - - - - - - - - - - - - -
HMHAS Cum 42,253 - 39,827 2,426 - - - - - - - - - - - - - - - - - - -
SUB-TOTAL Cum 272,355 - - ###### 16,564 - - - - - - - - - - - - - - - - - - - - - - - -
GRAND TOTAL Cum ####### 159,579 13,925 9% ###### 162,218 - - - - - - ### 507 ### 810 200 872 860 - - ### - #### ### ### - - - - -
Plumbing
Domestic water pumping Subco Cum 40,552 21,092 1,338 6% 20,798 19,754 - - - - - 165 345 - - - - 510 147 171 - - - - -
LBCC Cum 59,186 42,606 4,517 19% 11,476 47,710 - - - - - 951 904 597 - - 831 - 536 - - - 435 263 -
DEL Cum 3,545 10,957 - - - - - - 375 587 - - 366 360 349 - 698 - 585 - 225
HMHAS Cum 12,199 10,840 - 1,359 10,840 - - - - - - - - - - - - - - - - - - -
GRAND TOTAL Cum 111,937 74,538 9,400 13% 44,590 78,304 - - - - - - - - ### ### ### - - ### 870 ### 171 698 - ### 263 225 - - -
EQUIPMENT STATUS
Available
at Site
Available
at Site
Break
down
Break
down
Availab
le
at Site
Break
down
Availab
le
at Site
Break
down
Availab
le
at Site
Break
down
DUMPER 4+ 23 IDLE 10 - - 5 - - - - -
LOADER 1 2 - - 2 - 2 - - -
DOZER - - - - - - 1 - - - 495 582 320
MOTOR GRADER 2 1 - - 5 - 3 - - -
Highlights: Bottlenecks:
PROJECT #
DAILY PROGRESS REPORT
(All data for illustrative purpose only)
Month
NAME OF EQUIPMENT
IMP Subcontractor-1 Subcontractor-1
Subcontractor-
1
Subcontractor-
1
Subcontractor-
1
Break
down
Available
at Site
- -
MANPOWER
- - Impregilo Sub-CO.
- -
I/C PLANNING SITE MANAGER
- - Direct Indirect
Project Name :
Location :
Covered Period Upto the month
SUMMARY BY WBS SUMMARY BY ELEMENTS:
WBS Description
Total
Budgeted
Budget upto the
period
Actual Cost from
ERP
VARIANCE
Expected at
Completion
COMMENT
Budget upto the
period
ACTUAL COST
FROM ERP
VARIANCE COMMENT
1 General Costs Material
2 Design Costs Labor
3 Archiectural Subcontract
4 Structural Equipment
5 Geotechnical Overhead
6 Mechanical Total
7 Electrical
8 Utilities
9 Transportation
10 Dewatering
11 Jet Fuel Hydrant Network
TOTAL
Prepared by: Approved by : Project In-charge Checked by : Controlled by:
REVENUE
Gross Profit
Gross Profit %
DETAIL TO DATE COST COST CONTROL REPORT
Project Name :
Location :
Covered Period : UP TO ----
SNOST CODE DESCRIPTION
Material Labor Subcontract Equipment Overhead TOTAL Material Labor Subcontract Equipment Overhead TOTAL Material Labor
1 00 6 10 Bidding & Contracting Requirements- Bonds - -
2 00 6 11 Bidding & Contracting Requirements- Bank Gaurantees - -
3 00 6 15 Bidding & Contracting Requirements- Insurances - -
4 00 8 90 Bidding & Contracting Requirements- Permit Fees - -
5 01 3 21 The Contractor shall Provide photos & reports to the consult. - -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
TOTAL BUDGET COST PREVIOUS EXPENSES
DETAIL TO DATE COST COST CONTROL REPORT
Subcontract Equipment Overhead TOTAL Material Labor Subcontract Equipment Overhead TOTAL Material Labor Subcontract Equipment Overhead TOTAL
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
EXPENSES THIS MONTH TOTAL EXPENSES TO DATE Variance
Checklist for Cost Control Dept in Contracting Company Page 1 of 1
Projected
Invoice todate
Projected Cost
todate
% Amount
1 IMP001 500,000,000
2.00 IMP002
A TOTAL 500,000,000 - - - - -
CONSOLIDATED COST REPORT
AS OF 31-JANUARY-2011
No.
IMP Project
No.
Total Contract
Amount
Total Budgetted
Cost
Actual Invoice
todate (Certified)
Actual Cost
todate
Actual Margin - To Date
Checklist for Cost Control Dept in Contracting Company Page 1 of 2
COST REPORT BY ELEMENTS
Material Labor Subcontract Equipment Overhead
Total
Material Labor Subcontract Equipment Overhead
1 IMP001
TOTAL - - - - - - - - - - -
AS OF 31-January-2011
No. IMP Project No.
Estimated for the period Actual for the period
Checklist for Cost Control Dept in Contracting Company Page 2 of 2
Provision For
Works
Total
Material Labor
-
-
-
-
-
-
-
-
- - - -
Page: 1
Date: 8/3/2015 at 4:49 PM
Date Job Numbe WBE Item Number Item Description Quantity Unit Cost Ext. Cost
21210 Total 1,973,959 8,916,390
21220 Total 6,250 43,544
21230 Total 5,400 21,435
21250 Total 9,402 125,358
21320 Total 50 504
21340 Total 18,000 1,044,342
21410 Total 146,888 5,415,707
21710 Total 3 (497,061)
21740 Total 224,331 5,836,061
21753 Total 51,218 239,509
21830 Total 51 231,284
21860 Total 70,813 274,999
21885 Total 1,533 55,612
21895 Total 3 2,458,645
Subtotal for Project 2,507,901 ##########
2,507,901 ##########
Grand Total for All Projects 7,523,702 ##########
WBE Total Cost
21210
ADMIXTURE SIKAMENT 520-BA 264,202
CEMENT ORDINARY PORTLAND BSS 12 7,798,754
CRUSH 3/8" 535,183
DIRECT MATERIALS -298
SAND FINE 318,551
8,916,390Rs.
21220 Total
SAND FINE 27,211
CEMENT ORDINARY PORTLAND BSS 12 16,333
43,544Rs.
21230
CEMENT ORDINARY PORTLAND BSS 12 21,435
21,435Rs.
21250
CALCIUM CARBONATE (LIME POWDER) 647
CEMENT ORDINARY PORTLAND BSS 12 13,094
DISC CUTTING CS: 7"x1/8" 477
ELECTRODE WELDING AWS E6013: 3.25 MM 1,115
GAS OXYGEN 1,236
Others 108,789
125,358Rs.
21320
ANGLE EQ. AL: 1/2"X1/2"X1/8" 504
21340 WIRE PRESTRESSING TENDON M.S 12.7MM 1,044,342
21410 REBAR DEFORMED MS 25 MM GR-60 # 8 5,415,707
21710 DIRECT MATERIALS (497,061)
21740 BITUMEN: GRADE 60/70 5,375,199
KEROSENE 411,603
DIRECT MATERIALS 49,260
5,836,062Rs.
21753
CEMENT ORDINARY PORTLAND BSS 12 188,761
CRUSH 3/4" 13,915
DIRECT MATERIALS 32,735
POWDER MARBLE FOR CHIPS 471
SAND FINE 3,628
239509.44
21830
PIPE RCC 48`` X 8` 231,284
21860
CRUSH 3/4" 2,272
SAND FINE 6,803
POWDER MARBLE FOR CHIPS 65
CEMENT ORDINARY PORTLAND BSS 12 265,860
274999.06
21885 CEMENT ORDINARY PORTLAND BSS 12 212
REBAR DEFORMED MS 12 MM GR-60 # 4 55,399
55612
21895
DIRECT MATERIALS 2,458,645
WBE WISE COST REPORT
Page: 1
Date: 8/3/2015 at 4:49 PM
WBE
Work Done
QTY Material Total Cost Quantity Unit Cost
Standard
Material Qty
Standard
Cost Variance
21210
ADMIXTURE SIKAMENT 520-BA 264,202 10,686 25
CEMENT ORDINARY PORTLAND BSS 12 7,798,754 1,898,818 4
CRUSH 3/8" 535,183 36,440 15
DIRECT MATERIALS (298) (2) 149
SAND FINE 318,551 28,017 11
8,916,390
21220
SAND FINE 27,211 2,400 11
CEMENT ORDINARY PORTLAND BSS 12 16,333 3,850 4
43,544
21230
CEMENT ORDINARY PORTLAND BSS 12 21,435 5,400 4
21,435
21250
CALCIUM CARBONATE (LIME POWDER 647 100 6
CEMENT ORDINARY PORTLAND BSS 12 13,094 3,150 4
DISC CUTTING CS: 7"x1/8" 477 10 48
ELECTRODE WELDING AWS E6013: 3.2 1,115 18 62
GAS OXYGEN 1,236 4 309
Others 108,789 6,120 18
125,358
21320
ANGLE EQ. AL: 1/2"X1/2"X1/8" 504 50 10
21340 WIRE PRESTRESSING TENDON M.S 12 1,044,342 18,000 58
21410 REBAR DEFORMED MS 25 MM GR-60 # 5,415,707 146,888 37
21710 DIRECT MATERIALS (497,061) (3) 165,687
21740 BITUMEN: GRADE 60/70 5,375,199 212,730 25
KEROSENE 411,603 11,600 35
DIRECT MATERIALS 49,260 1 49,260
5,836,062
21753
CEMENT ORDINARY PORTLAND BSS 12 188,761 49,700 4
CRUSH 3/4" 13,915 960 14
DIRECT MATERIALS 32,735 1 32,735
POWDER MARBLE FOR CHIPS 471 237 2
SAND FINE 3,628 320 11
239,509
21830
PIPE RCC 48`` X 8` 231,284 51 4,535
21860
CRUSH 3/4" 2,272 160 14
SAND FINE 6,803 600 11
POWDER MARBLE FOR CHIPS 65 53 1
CEMENT ORDINARY PORTLAND BSS 12 265,860 70,000 4
274,999
21885 CEMENT ORDINARY PORTLAND BSS 12 212 50 4
REBAR DEFORMED MS 12 MM GR-60 # 55,399 1,483 37
55612
21895
DIRECT MATERIALS 2,458,645 3 819,548
24,166,330
Material Cost Variance Analysis
WBE WISE MAN-HOURS REPORT
21132- SITE CLEARING
PROJECT : Period
Craft
Description
Normal Time Over time Total
05 AREA INCHARGE(CIVIL) 48.00 12.00 60.00
11 SUPERVISOR(CIVIL) 48.00 12.00 60.00
49 LABOUR 80.00 20.00 100.00
57 HELPER 80.00 20.00 100.00
256.00 64.00 320.00
Labour utilization report
WBE Cost Code
Quantity
Claimed in
Progress
Invoice Craft
Standard
Labour
hours
required
Actual
Labour
Hours
spent
Variance
Hours Over Break DIESEL ENGINE
Eqp. C.C Proj WBE WBE Description Consumed Time Down OIL
71105 CRANE 40 TONN 21110 CLEARING / GRUBBING / STRIPPING / T 10 0 0 0 0
71105 CRANE 40 TONN 21120 GENERAL OPEN SECTION EXCAVATION BY MACHI 9 0 0 100 0
71105 CRANE 40 TONN 21130 BACK FILLING GENERAL/OPEN SECTION WITH C 104 28 0 0 0
71105 CRANE 40 TONN 21135 FILL WITHOUT COMPACTION 130 10 0 0 0
71105 CRANE 40 TONN 21170 DEWATERING 10 4 0 0 0
71105 CRANE 40 TONN 21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 88 26 10 302 0
71105 CRANE 40 TONN 21250 CONCRETE PLACING FOR PRECAST ELEMENTS 40 29 0 30 5
71105 CRANE 40 TONN 21255 ERECTION OF PRE CAST ELEMENTS 24 13 10 0 3
71105 CRANE 40 TONN 21310 FORMWORK IN STRUCTURE 182 31 60 165 2
71105 CRANE 40 TONN 21320 FORM WORK SUPER-STRUCTURE 4 0 0 68 0
71105 CRANE 40 TONN 21340 FORM WORK FOR PRE CAST ELEMENTS 255 86 40 178 0
71105 CRANE 40 TONN 21885 MISC. CIVIL WORKS 247 63 23 343 5
TOTAL 1103 290 143 1186 15
72156 AIR COMPRESSOR 21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 15 0 0 200 0
72156 AIR COMPRESSOR 21740 PRODUCTION OF ASPHALT CONCR. AND SUPPLY 154 20 54 2751 0
72156 AIR COMPRESSOR 21748 ASPHALT TACK/PRIME COAT 10 0 0 0 0
72156 AIR COMPRESSOR 21885 MISC. CIVIL WORKS 78 18 0 680 0
72156
TOTAL 257 38 54 3631 0
73224 POWER GEN.40 K 21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 136 136 0 144 0
21885 MISC. CIVIL WORKS 1006 314 0 2557 6
TOTAL 1142 450 0 2701 6
73322 POWER GEN.100K 21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 50 22 0 421 0
21310 FORMWORK IN STRUCTURE 20 4 0 195 0
21320 FORM WORK SUPER-STRUCTURE 20 17 0 260 0
21410 STEEL REBAR 10 0 0 50 0
21885 MISC. CIVIL WORKS 1296 1111 2 9825 34
TOTAL 1396 1154 2 10751 34
73323 POWER GEN.100 21110 CLEARING / GRUBBING / STRIPPING / T 20 0 0 0 0
21140 HAULAGE OF RIP RAP 0 21 0 160 0
21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 20 2 0 109 0
21280 CONCRETE PLACING FOR PILES 64 24 16 642 0
21310 FORMWORK IN STRUCTURE 108 45 0 1472 0
21320 FORM WORK SUPER-STRUCTURE 60 39 0 864 30
21410 STEEL REBAR 95 62 0 1279 0
21885 MISC. CIVIL WORKS 790 719 0 7121 33.5
TOTAL 1157 912 16 11647 63.5
73324 P.GENERATOR 40 21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 260 125 0 819 0
21250 CONCRETE PLACING FOR PRECAST ELEMENTS 40 6 0 184 0
21310 FORMWORK IN STRUCTURE 82 31 8 406 0
21320 FORM WORK SUPER-STRUCTURE 70 43 0 512 0
21340 FORM WORK FOR PRE CAST ELEMENTS 110 60 0 807 0
21410 STEEL REBAR 0 10 0 57 0
TOTAL 562 275 8 2785 0
73325 POWER GEN.275 21135 FILL WITHOUT COMPACTION 2 12 0 351 0
21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 505 793 2 16262 0
21885 MISC. CIVIL WORKS 671 405 0 8424 0
TOTAL 1178 1210 2 25037 0
73326 POWER GEN.275 1 BRAKE DOWN 10 0 0 84 25
21110 CLEARING / GRUBBING / STRIPPING / T 20 1 0 60 0
21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 158 93 0 2286 0
21250 CONCRETE PLACING FOR PRECAST ELEMENTS 50 12 0 641 0
21310 FORMWORK IN STRUCTURE 278 152 10 3915 0
21320 FORM WORK SUPER-STRUCTURE 582 224.1 21 7587 25
21340 FORM WORK FOR PRE CAST ELEMENTS 110 50 0 1153 0
21410 STEEL REBAR 40 17 0 544 0
21885 MISC. CIVIL WORKS 180 38 0 938 0
TOTAL 1428 587.1 31 17208 50
73327 POWER GEN.275 1 BRAKE DOWN 10 7 0 350 0
21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 637 266 1 9780 0
21885 MISC. CIVIL WORKS 680 337 128 12957 165
TOTAL 1327 610 129 23087 165
73328 P.GEN 15 KVA S 21135 FILL WITHOUT COMPACTION 10 0 0 0 0
21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 110 0 0 86 0
21250 CONCRETE PLACING FOR PRECAST ELEMENTS 0 10 0 0 0
21255 ERECTION OF PRE CAST ELEMENTS 20 20 0 32 0
21310 FORMWORK IN STRUCTURE 231 32 80 332 0
Project WBE Wise Equipment Utilization Report
Project Name
Report period------
WBE Diesel Engine Oil Rent Charged Total
Production
Qty Unit
Cost Per unit
of Production
Clearing of site 335,601 - 573,052 908,653 0
Compaction 158,321 - 271,766 430,087 0
Asphalt 258,413 - 556,726 815,139 0
1,090,676 - 1,455,813 2,546,489 210 Sq M
225,792 - 523,181 748,973 215 Sq M
182,979 - 85,224 268,203 63 Sq M
Rebar 15,635 1,416 8,843 25,894 12 Ton
430,470 - 1,280,129 1,710,598 2963 Cum
2,814,710 - 1,924,984 4,739,693 0 Cum
279,272 5,664 758,671 1,043,607 934 Cum
496,589 - 699,215 1,195,804 1800 Sq M
94,722 - 148,897 243,619
- - - -
1,496,159 - 1,482,135 2,978,294
2,143,142 - 3,757,836 5,900,978 1795 Cum
- - - - 56 Cum
Grand Total 19,709,360 14,160 26,479,890 46,203,410
Rent is allocated to WBEs based on Equipment Utilization Report
Project
WBE wise Equipment Cost
For the period
Store/warehouse Record
For the month of….
Sr Material Item
QTY Value QTY Value QTY
1,000,000
Reconciliaiton with:
Financial Record
Total Purchases for the month 1,000,000
Closing balance in financial ledger
Total Material Issues in financial record
Difference -
Monthly Cost Audit Sheet for Materials
Opening Bal Purchases Iss
Value QTY Value
800,000 200,000
200,000
800,000
- -
sue Closing Bal
Subcontractor evaluation form
Project#
Subcontractor:
Invoice No.
For the period
Quantity Rate Amount Quantity Amount Quantity Amount Quantity Rate Amount
This Period Balance to be done
RemarksWBS WBE Description UOM
Total Contract Invoice Upto last period
Subcontracting Cost
Project #
Subco WBE Bill Inv # Qty(Cum) rate Amount
Subco -1 21132 month 3 102,700.00 138.17 14,189,640
Subco -2 21133 month - 3,351,907
Subco -3 21134 month 6 266,793 110.25 29,413,885
46,955,432
Subcontracting Cost of Culverts
Remarks
Analysis of Culverts costs
Quantity of work done
For the period
QTY Total Cost Per unit Cost QTY Total Cost Per unit Cost
Material
Labour
Equipment
Sub-contractor
Overhead
Total Cost
Cost Elements
Budget Actual
Variance
Material Purchase Evaluation form
Project#
Supplier:
Quantity Rate Amount Quantity Amount Quantity Amount Quantity Rate Amount
Budget Balance Suggested Purchase Budget Balance
after Purchase RemarksWBE Item Code Item Description UOM
Total Budget Spent todate
Check-List for Material Items mostly likely to be chargeable to certain Cost Codes
WBS(s) WBE(s)
Audit of Project Record for correct Cost Codes(Using Excel tools)
Sr. No Item Code Item Description Issue to WBE Correct/Incorrect
1 123 xyz 88-888-99 Y/N
Sr. No. Item Code Item Description
Applicable Cost Codes for:

Weitere ähnliche Inhalte

Was ist angesagt?

Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Arissa Loh
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantitiesBt Lee
 
ECA Presentation
ECA PresentationECA Presentation
ECA PresentationLee Pei Gie
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4Moustafa Ismail Abu Dief
 
Fidic comparison red book yellow book_silver book_en_newsletters
Fidic comparison red book yellow book_silver book_en_newslettersFidic comparison red book yellow book_silver book_en_newsletters
Fidic comparison red book yellow book_silver book_en_newslettersAtul Duggal
 
Implied term in building contracts
Implied term in building contractsImplied term in building contracts
Implied term in building contractsHafizul Mukhlis
 
ECA Presentation slide
ECA Presentation slideECA Presentation slide
ECA Presentation slideseenyeeyong
 
Piping drawing Knowledge.pdf
Piping drawing Knowledge.pdfPiping drawing Knowledge.pdf
Piping drawing Knowledge.pdfewwervq2323452
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1Moustafa Ismail Abu Dief
 
Vm assignment (5)
Vm assignment (5)Vm assignment (5)
Vm assignment (5)Yong Sy
 
QUANTITY SURVEYOR magazine
QUANTITY SURVEYOR magazineQUANTITY SURVEYOR magazine
QUANTITY SURVEYOR magazineChong Chin Pin
 

Was ist angesagt? (20)

Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
 
ECA Presentation
ECA PresentationECA Presentation
ECA Presentation
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
Fidic comparison red book yellow book_silver book_en_newsletters
Fidic comparison red book yellow book_silver book_en_newslettersFidic comparison red book yellow book_silver book_en_newsletters
Fidic comparison red book yellow book_silver book_en_newsletters
 
Implied term in building contracts
Implied term in building contractsImplied term in building contracts
Implied term in building contracts
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
ECA Presentation slide
ECA Presentation slideECA Presentation slide
ECA Presentation slide
 
CCP Technical Paper and Application
CCP Technical Paper and ApplicationCCP Technical Paper and Application
CCP Technical Paper and Application
 
Eot
EotEot
Eot
 
Retention fund
Retention fundRetention fund
Retention fund
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
Piping drawing Knowledge.pdf
Piping drawing Knowledge.pdfPiping drawing Knowledge.pdf
Piping drawing Knowledge.pdf
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
 
Conquas
ConquasConquas
Conquas
 
Vm assignment (5)
Vm assignment (5)Vm assignment (5)
Vm assignment (5)
 
QUANTITY SURVEYOR magazine
QUANTITY SURVEYOR magazineQUANTITY SURVEYOR magazine
QUANTITY SURVEYOR magazine
 
Practice for Quantity Surveyors
Practice for Quantity SurveyorsPractice for Quantity Surveyors
Practice for Quantity Surveyors
 

Ähnlich wie Cost Control Reporting and Budget Formats for Construction Projects

M2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxM2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxKhaled Jomaa
 
M2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxM2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxSIBANJAN MISHRA
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpmKinshook Chaturvedi
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxFaisalGulzar19
 
Formats of Cost and Financial Control Reports
Formats of Cost and Financial Control ReportsFormats of Cost and Financial Control Reports
Formats of Cost and Financial Control Reportskashif khawja
 
IRJET- Design and Analysis of Catalytic Converter of Automobile Engine
IRJET- Design and Analysis of Catalytic Converter of Automobile EngineIRJET- Design and Analysis of Catalytic Converter of Automobile Engine
IRJET- Design and Analysis of Catalytic Converter of Automobile EngineIRJET Journal
 
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISIONREWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISIONIRJET Journal
 
SAP JVA ( Joint Venture Accounting )
SAP JVA ( Joint Venture Accounting )SAP JVA ( Joint Venture Accounting )
SAP JVA ( Joint Venture Accounting )Peter Ezzat
 
Best Business Practice @ Nov 22.pptx
Best Business Practice @ Nov 22.pptxBest Business Practice @ Nov 22.pptx
Best Business Practice @ Nov 22.pptxsonutyagi20
 
M20Lesson070111100Financial0Modeling.pdf
M20Lesson070111100Financial0Modeling.pdfM20Lesson070111100Financial0Modeling.pdf
M20Lesson070111100Financial0Modeling.pdfMohammedYASEEN963424
 
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance ProgressGlen Alleman
 
High Efficiency Motor Systems
High Efficiency Motor SystemsHigh Efficiency Motor Systems
High Efficiency Motor SystemsLeonardo ENERGY
 

Ähnlich wie Cost Control Reporting and Budget Formats for Construction Projects (20)

Session B2 - Project Cost Control
Session B2 - Project Cost ControlSession B2 - Project Cost Control
Session B2 - Project Cost Control
 
004 benchmarking and productivity
004 benchmarking and productivity004 benchmarking and productivity
004 benchmarking and productivity
 
M2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxM2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptx
 
M2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxM2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptx
 
Incurred_Cost_Submissions
Incurred_Cost_SubmissionsIncurred_Cost_Submissions
Incurred_Cost_Submissions
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
 
Procedures
ProceduresProcedures
Procedures
 
Formats of Cost and Financial Control Reports
Formats of Cost and Financial Control ReportsFormats of Cost and Financial Control Reports
Formats of Cost and Financial Control Reports
 
IRJET- Design and Analysis of Catalytic Converter of Automobile Engine
IRJET- Design and Analysis of Catalytic Converter of Automobile EngineIRJET- Design and Analysis of Catalytic Converter of Automobile Engine
IRJET- Design and Analysis of Catalytic Converter of Automobile Engine
 
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISIONREWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
 
SAP JVA ( Joint Venture Accounting )
SAP JVA ( Joint Venture Accounting )SAP JVA ( Joint Venture Accounting )
SAP JVA ( Joint Venture Accounting )
 
Project Controls Overview - R2
Project Controls Overview - R2Project Controls Overview - R2
Project Controls Overview - R2
 
En business plan
En business planEn business plan
En business plan
 
Best Business Practice @ Nov 22.pptx
Best Business Practice @ Nov 22.pptxBest Business Practice @ Nov 22.pptx
Best Business Practice @ Nov 22.pptx
 
CCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost ControlCCP_SEC4_Progress and Cost Control
CCP_SEC4_Progress and Cost Control
 
M20Lesson070111100Financial0Modeling.pdf
M20Lesson070111100Financial0Modeling.pdfM20Lesson070111100Financial0Modeling.pdf
M20Lesson070111100Financial0Modeling.pdf
 
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance Progress
 
SAP Project system.pptx
SAP Project system.pptxSAP Project system.pptx
SAP Project system.pptx
 
High Efficiency Motor Systems
High Efficiency Motor SystemsHigh Efficiency Motor Systems
High Efficiency Motor Systems
 

Cost Control Reporting and Budget Formats for Construction Projects

  • 1. Sr No. What You need: Availability Require ment met? What I have developed as a solution: 1 Format of Project budget which is mapped with the Proposal Y/N Skeleton format of budget is proposed which will be useful for Cost control during project life view 2 Budget Summary format: We must have predefined formats of out budget presentation which should be self explanantory (N/A) Developed Top Summary of Budget which will be repeatedly used in Variance Analysis to be reported to the Management. view 3 Summarized monthly Project Report describing achievement of targets in terms of major cost elements comparising the project (N/A) Project Cost Report which will highlight variations from monthly budget in terms of WBEs and Cost elements( Material, Labor etc) view 4 Detailed monthly Project Report which explains in detail where variations occurred. (N/A) Detailed Cost Report which explains in detail the above Project Cost Report i.e Cost Center wise budget, actual and variations are provided view 5 Consolidated Cost Report of all Projects: A corporate level report describing status of all running projects (N/A) Summary report on all projects which portrays Key Performance Indicators of all running projects. view 6 Daily Progress Report of Project with quantities Report available but without Qty. Developed Daily Progress Report showing quantitative data to measure and evaluate project performance view 7 Need to know which project is over-spending in which type of costs Consolidated Cost Report by elements: shows variances of Material, Lab etc of each project in one report view 8 Need to know which project is over-spending in which areas of Project WBE wise Cost Report: This explains cost spent in diff kind of activities like Excavation, concreting etc. along with variances View 9 Need to know which kind of material was used in which kind of activities Material Cost Variance Analysis: shows WBE wise material consumption with quantities and price view Cost Control Reporting requirements and Solutions
  • 2. Sr No. What You need: Availability Require ment met? What I have developed as a solution: Cost Control Reporting requirements and Solutions 10 Need to measure labor utilization on different activities (WBE) Labor Utilization Report: It calculates manpower employed on each WBE and compares with standard time required as per Proposal view 11 WBE wise Equipment utilization Equipment Utilization Report: It portrays the usage of Equipment in diff activities of the project view 12 Shared Costs of Equipment to be charged to relevant activities Shared Equipment Costs allocation report is designed alongwith the basis of allocation view 13 Cost Audit techniques of Project Expenses should be provided to ensure integrity of project data Simple to use audit techniques are being formulated. To check accuracy of Material cost, attached report is designed view 14 Subcontractor evaluation forms should be available to control cost and payments to subcontractors. Subcontractor Evaluation Form is designed view 15 Cost of Production reports of Plants A Sample of my previous work is attached for reference only. Actual report will be created based on Information systems of IMP view 16 Weekly Project Performance Report: Showing all critical aspects of a Project Not designed here, however, a sample is avilable for adoption. Exact report will be created based on Information System of IMP view 17 Expected At Completion: This is required to be reported as per company policy but format is not available This report can take any format. For reference, image of one report is attached. view 18 Knowledge of your existing systems is required to make these reports successfully operational
  • 3. DETAIL FORECAST COST CONTROL Budget Project# Project Name: Location: Material Labor Sub- contract Equip- ment Over- head Total 1 General Costs 1 00 6 10 Insurance 2 00 6 11 CAR 3 00 6 15 CPM cover 4 00 8 90 Mobilization 5 01 3 21 Demobilization 6 01 3 31 Sign Board 7 01 4 51 2 01 5 01 Design Related Costs 3 01 5 02 4 01 5 03 5 01 5 04 General Requirements- Site Workshops 6 01 5 11 General Requirements- Temporary Water 7 01 5 12 General Requirements - Temporary Electricity 8 01 5 13 General Requirements- Temporary Telecommunications 3 01 5 14 Architectural 4 01 5 22 General Requirements- Site Transportation 5 01 5 23 General Requirements- Site Offices and Equipment for Contractor 4 01 5 24 Structural 4.1 Structural Steel and Re inforced t Shalow foundations II. Other Provisional Cost Not Included - - - - - Prepared by: Approved by : S.N o Cost code Description Total Cost (Budget) T O T A L
  • 4. Budget Summary(format) Project Name Project No. Employer: Expected Start Date Expected Finish Date Sr. BOQ Items Material Labor Subcontract Equipment Overhead Total Cost Profit Margin Total Price 1 General Costs 2 Design Costs 3 Archiectural 4 Structural 5 Geotechnical 6 Mechanical 7 Electrical 8 Utilities 9 Transportation 10 Dewatering 11 Jet Fuel Hydrant Network TOTAL
  • 5. Structural Description RESP. Unit Total Qty. Planned Qty. for the Month Actual Qty. for the Month Earned %Age This Month Todate Qty. Balance Qty. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Culverts Precast parapets IMP Cum 44,492 11,934 1,756 15% 34,314 10,178 - - - - - 94 - - 510 376 - - 83 - 232 - 461 - - Slabs IMP Cum 226,208 1,687 1,687 100% ###### 0 - - - - 507 - - - - 484 - - - - - 696 - - - Subco Cum 198,504 30,756 10,482 34% ###### 20,274 - - - ### - ### 810 200 362 - - - ### - #### ### ### Subco Cum 572,669 115,202 - #REF! ###### 115,202 - - - - - - - - - - - - - - - - - - - Cum - - - - - - - - - - - - - - - - - - - SUB-TOTAL Cum ####### 159,579 13,925 9% ###### 145,654 - - - - - - ### 507 ### 810 200 872 860 - - ### - #### ### ### - - - - - Geo Technical Site Clearing KST Cum 65427 - 60,427 5,000 - - - - - - - - - - - - - - - - - - - IMP Cum 93675 - 81,592 12,083 - - - - - - - - - - - - - - - - - - - LBCC Cum 71,000 - 73,945 (2,945) - - - - - - - - - - - - - - - - - - - HMHAS Cum 42,253 - 39,827 2,426 - - - - - - - - - - - - - - - - - - - SUB-TOTAL Cum 272,355 - - ###### 16,564 - - - - - - - - - - - - - - - - - - - - - - - - GRAND TOTAL Cum ####### 159,579 13,925 9% ###### 162,218 - - - - - - ### 507 ### 810 200 872 860 - - ### - #### ### ### - - - - - Plumbing Domestic water pumping Subco Cum 40,552 21,092 1,338 6% 20,798 19,754 - - - - - 165 345 - - - - 510 147 171 - - - - - LBCC Cum 59,186 42,606 4,517 19% 11,476 47,710 - - - - - 951 904 597 - - 831 - 536 - - - 435 263 - DEL Cum 3,545 10,957 - - - - - - 375 587 - - 366 360 349 - 698 - 585 - 225 HMHAS Cum 12,199 10,840 - 1,359 10,840 - - - - - - - - - - - - - - - - - - - GRAND TOTAL Cum 111,937 74,538 9,400 13% 44,590 78,304 - - - - - - - - ### ### ### - - ### 870 ### 171 698 - ### 263 225 - - - EQUIPMENT STATUS Available at Site Available at Site Break down Break down Availab le at Site Break down Availab le at Site Break down Availab le at Site Break down DUMPER 4+ 23 IDLE 10 - - 5 - - - - - LOADER 1 2 - - 2 - 2 - - - DOZER - - - - - - 1 - - - 495 582 320 MOTOR GRADER 2 1 - - 5 - 3 - - - Highlights: Bottlenecks: PROJECT # DAILY PROGRESS REPORT (All data for illustrative purpose only) Month NAME OF EQUIPMENT IMP Subcontractor-1 Subcontractor-1 Subcontractor- 1 Subcontractor- 1 Subcontractor- 1 Break down Available at Site - - MANPOWER - - Impregilo Sub-CO. - - I/C PLANNING SITE MANAGER - - Direct Indirect
  • 6. Project Name : Location : Covered Period Upto the month SUMMARY BY WBS SUMMARY BY ELEMENTS: WBS Description Total Budgeted Budget upto the period Actual Cost from ERP VARIANCE Expected at Completion COMMENT Budget upto the period ACTUAL COST FROM ERP VARIANCE COMMENT 1 General Costs Material 2 Design Costs Labor 3 Archiectural Subcontract 4 Structural Equipment 5 Geotechnical Overhead 6 Mechanical Total 7 Electrical 8 Utilities 9 Transportation 10 Dewatering 11 Jet Fuel Hydrant Network TOTAL Prepared by: Approved by : Project In-charge Checked by : Controlled by: REVENUE Gross Profit Gross Profit %
  • 7. DETAIL TO DATE COST COST CONTROL REPORT Project Name : Location : Covered Period : UP TO ---- SNOST CODE DESCRIPTION Material Labor Subcontract Equipment Overhead TOTAL Material Labor Subcontract Equipment Overhead TOTAL Material Labor 1 00 6 10 Bidding & Contracting Requirements- Bonds - - 2 00 6 11 Bidding & Contracting Requirements- Bank Gaurantees - - 3 00 6 15 Bidding & Contracting Requirements- Insurances - - 4 00 8 90 Bidding & Contracting Requirements- Permit Fees - - 5 01 3 21 The Contractor shall Provide photos & reports to the consult. - - - - - - - - - - - - - - - - - - - - - - - - TOTAL BUDGET COST PREVIOUS EXPENSES
  • 8. DETAIL TO DATE COST COST CONTROL REPORT Subcontract Equipment Overhead TOTAL Material Labor Subcontract Equipment Overhead TOTAL Material Labor Subcontract Equipment Overhead TOTAL - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - EXPENSES THIS MONTH TOTAL EXPENSES TO DATE Variance
  • 9. Checklist for Cost Control Dept in Contracting Company Page 1 of 1 Projected Invoice todate Projected Cost todate % Amount 1 IMP001 500,000,000 2.00 IMP002 A TOTAL 500,000,000 - - - - - CONSOLIDATED COST REPORT AS OF 31-JANUARY-2011 No. IMP Project No. Total Contract Amount Total Budgetted Cost Actual Invoice todate (Certified) Actual Cost todate Actual Margin - To Date
  • 10. Checklist for Cost Control Dept in Contracting Company Page 1 of 2 COST REPORT BY ELEMENTS Material Labor Subcontract Equipment Overhead Total Material Labor Subcontract Equipment Overhead 1 IMP001 TOTAL - - - - - - - - - - - AS OF 31-January-2011 No. IMP Project No. Estimated for the period Actual for the period
  • 11. Checklist for Cost Control Dept in Contracting Company Page 2 of 2 Provision For Works Total Material Labor - - - - - - - - - - - -
  • 12. Page: 1 Date: 8/3/2015 at 4:49 PM Date Job Numbe WBE Item Number Item Description Quantity Unit Cost Ext. Cost 21210 Total 1,973,959 8,916,390 21220 Total 6,250 43,544 21230 Total 5,400 21,435 21250 Total 9,402 125,358 21320 Total 50 504 21340 Total 18,000 1,044,342 21410 Total 146,888 5,415,707 21710 Total 3 (497,061) 21740 Total 224,331 5,836,061 21753 Total 51,218 239,509 21830 Total 51 231,284 21860 Total 70,813 274,999 21885 Total 1,533 55,612 21895 Total 3 2,458,645 Subtotal for Project 2,507,901 ########## 2,507,901 ########## Grand Total for All Projects 7,523,702 ########## WBE Total Cost 21210 ADMIXTURE SIKAMENT 520-BA 264,202 CEMENT ORDINARY PORTLAND BSS 12 7,798,754 CRUSH 3/8" 535,183 DIRECT MATERIALS -298 SAND FINE 318,551 8,916,390Rs. 21220 Total SAND FINE 27,211 CEMENT ORDINARY PORTLAND BSS 12 16,333 43,544Rs. 21230 CEMENT ORDINARY PORTLAND BSS 12 21,435 21,435Rs. 21250 CALCIUM CARBONATE (LIME POWDER) 647 CEMENT ORDINARY PORTLAND BSS 12 13,094 DISC CUTTING CS: 7"x1/8" 477 ELECTRODE WELDING AWS E6013: 3.25 MM 1,115 GAS OXYGEN 1,236 Others 108,789 125,358Rs. 21320 ANGLE EQ. AL: 1/2"X1/2"X1/8" 504 21340 WIRE PRESTRESSING TENDON M.S 12.7MM 1,044,342 21410 REBAR DEFORMED MS 25 MM GR-60 # 8 5,415,707 21710 DIRECT MATERIALS (497,061) 21740 BITUMEN: GRADE 60/70 5,375,199 KEROSENE 411,603 DIRECT MATERIALS 49,260 5,836,062Rs. 21753 CEMENT ORDINARY PORTLAND BSS 12 188,761 CRUSH 3/4" 13,915 DIRECT MATERIALS 32,735 POWDER MARBLE FOR CHIPS 471 SAND FINE 3,628 239509.44 21830 PIPE RCC 48`` X 8` 231,284 21860 CRUSH 3/4" 2,272 SAND FINE 6,803 POWDER MARBLE FOR CHIPS 65 CEMENT ORDINARY PORTLAND BSS 12 265,860 274999.06 21885 CEMENT ORDINARY PORTLAND BSS 12 212 REBAR DEFORMED MS 12 MM GR-60 # 4 55,399 55612 21895 DIRECT MATERIALS 2,458,645 WBE WISE COST REPORT
  • 13. Page: 1 Date: 8/3/2015 at 4:49 PM WBE Work Done QTY Material Total Cost Quantity Unit Cost Standard Material Qty Standard Cost Variance 21210 ADMIXTURE SIKAMENT 520-BA 264,202 10,686 25 CEMENT ORDINARY PORTLAND BSS 12 7,798,754 1,898,818 4 CRUSH 3/8" 535,183 36,440 15 DIRECT MATERIALS (298) (2) 149 SAND FINE 318,551 28,017 11 8,916,390 21220 SAND FINE 27,211 2,400 11 CEMENT ORDINARY PORTLAND BSS 12 16,333 3,850 4 43,544 21230 CEMENT ORDINARY PORTLAND BSS 12 21,435 5,400 4 21,435 21250 CALCIUM CARBONATE (LIME POWDER 647 100 6 CEMENT ORDINARY PORTLAND BSS 12 13,094 3,150 4 DISC CUTTING CS: 7"x1/8" 477 10 48 ELECTRODE WELDING AWS E6013: 3.2 1,115 18 62 GAS OXYGEN 1,236 4 309 Others 108,789 6,120 18 125,358 21320 ANGLE EQ. AL: 1/2"X1/2"X1/8" 504 50 10 21340 WIRE PRESTRESSING TENDON M.S 12 1,044,342 18,000 58 21410 REBAR DEFORMED MS 25 MM GR-60 # 5,415,707 146,888 37 21710 DIRECT MATERIALS (497,061) (3) 165,687 21740 BITUMEN: GRADE 60/70 5,375,199 212,730 25 KEROSENE 411,603 11,600 35 DIRECT MATERIALS 49,260 1 49,260 5,836,062 21753 CEMENT ORDINARY PORTLAND BSS 12 188,761 49,700 4 CRUSH 3/4" 13,915 960 14 DIRECT MATERIALS 32,735 1 32,735 POWDER MARBLE FOR CHIPS 471 237 2 SAND FINE 3,628 320 11 239,509 21830 PIPE RCC 48`` X 8` 231,284 51 4,535 21860 CRUSH 3/4" 2,272 160 14 SAND FINE 6,803 600 11 POWDER MARBLE FOR CHIPS 65 53 1 CEMENT ORDINARY PORTLAND BSS 12 265,860 70,000 4 274,999 21885 CEMENT ORDINARY PORTLAND BSS 12 212 50 4 REBAR DEFORMED MS 12 MM GR-60 # 55,399 1,483 37 55612 21895 DIRECT MATERIALS 2,458,645 3 819,548 24,166,330 Material Cost Variance Analysis
  • 14. WBE WISE MAN-HOURS REPORT 21132- SITE CLEARING PROJECT : Period Craft Description Normal Time Over time Total 05 AREA INCHARGE(CIVIL) 48.00 12.00 60.00 11 SUPERVISOR(CIVIL) 48.00 12.00 60.00 49 LABOUR 80.00 20.00 100.00 57 HELPER 80.00 20.00 100.00 256.00 64.00 320.00 Labour utilization report WBE Cost Code Quantity Claimed in Progress Invoice Craft Standard Labour hours required Actual Labour Hours spent
  • 16. Hours Over Break DIESEL ENGINE Eqp. C.C Proj WBE WBE Description Consumed Time Down OIL 71105 CRANE 40 TONN 21110 CLEARING / GRUBBING / STRIPPING / T 10 0 0 0 0 71105 CRANE 40 TONN 21120 GENERAL OPEN SECTION EXCAVATION BY MACHI 9 0 0 100 0 71105 CRANE 40 TONN 21130 BACK FILLING GENERAL/OPEN SECTION WITH C 104 28 0 0 0 71105 CRANE 40 TONN 21135 FILL WITHOUT COMPACTION 130 10 0 0 0 71105 CRANE 40 TONN 21170 DEWATERING 10 4 0 0 0 71105 CRANE 40 TONN 21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 88 26 10 302 0 71105 CRANE 40 TONN 21250 CONCRETE PLACING FOR PRECAST ELEMENTS 40 29 0 30 5 71105 CRANE 40 TONN 21255 ERECTION OF PRE CAST ELEMENTS 24 13 10 0 3 71105 CRANE 40 TONN 21310 FORMWORK IN STRUCTURE 182 31 60 165 2 71105 CRANE 40 TONN 21320 FORM WORK SUPER-STRUCTURE 4 0 0 68 0 71105 CRANE 40 TONN 21340 FORM WORK FOR PRE CAST ELEMENTS 255 86 40 178 0 71105 CRANE 40 TONN 21885 MISC. CIVIL WORKS 247 63 23 343 5 TOTAL 1103 290 143 1186 15 72156 AIR COMPRESSOR 21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 15 0 0 200 0 72156 AIR COMPRESSOR 21740 PRODUCTION OF ASPHALT CONCR. AND SUPPLY 154 20 54 2751 0 72156 AIR COMPRESSOR 21748 ASPHALT TACK/PRIME COAT 10 0 0 0 0 72156 AIR COMPRESSOR 21885 MISC. CIVIL WORKS 78 18 0 680 0 72156 TOTAL 257 38 54 3631 0 73224 POWER GEN.40 K 21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 136 136 0 144 0 21885 MISC. CIVIL WORKS 1006 314 0 2557 6 TOTAL 1142 450 0 2701 6 73322 POWER GEN.100K 21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 50 22 0 421 0 21310 FORMWORK IN STRUCTURE 20 4 0 195 0 21320 FORM WORK SUPER-STRUCTURE 20 17 0 260 0 21410 STEEL REBAR 10 0 0 50 0 21885 MISC. CIVIL WORKS 1296 1111 2 9825 34 TOTAL 1396 1154 2 10751 34 73323 POWER GEN.100 21110 CLEARING / GRUBBING / STRIPPING / T 20 0 0 0 0 21140 HAULAGE OF RIP RAP 0 21 0 160 0 21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 20 2 0 109 0 21280 CONCRETE PLACING FOR PILES 64 24 16 642 0 21310 FORMWORK IN STRUCTURE 108 45 0 1472 0 21320 FORM WORK SUPER-STRUCTURE 60 39 0 864 30 21410 STEEL REBAR 95 62 0 1279 0 21885 MISC. CIVIL WORKS 790 719 0 7121 33.5 TOTAL 1157 912 16 11647 63.5 73324 P.GENERATOR 40 21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 260 125 0 819 0 21250 CONCRETE PLACING FOR PRECAST ELEMENTS 40 6 0 184 0 21310 FORMWORK IN STRUCTURE 82 31 8 406 0 21320 FORM WORK SUPER-STRUCTURE 70 43 0 512 0 21340 FORM WORK FOR PRE CAST ELEMENTS 110 60 0 807 0 21410 STEEL REBAR 0 10 0 57 0 TOTAL 562 275 8 2785 0 73325 POWER GEN.275 21135 FILL WITHOUT COMPACTION 2 12 0 351 0 21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 505 793 2 16262 0 21885 MISC. CIVIL WORKS 671 405 0 8424 0 TOTAL 1178 1210 2 25037 0 73326 POWER GEN.275 1 BRAKE DOWN 10 0 0 84 25 21110 CLEARING / GRUBBING / STRIPPING / T 20 1 0 60 0 21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 158 93 0 2286 0 21250 CONCRETE PLACING FOR PRECAST ELEMENTS 50 12 0 641 0 21310 FORMWORK IN STRUCTURE 278 152 10 3915 0 21320 FORM WORK SUPER-STRUCTURE 582 224.1 21 7587 25 21340 FORM WORK FOR PRE CAST ELEMENTS 110 50 0 1153 0 21410 STEEL REBAR 40 17 0 544 0 21885 MISC. CIVIL WORKS 180 38 0 938 0 TOTAL 1428 587.1 31 17208 50 73327 POWER GEN.275 1 BRAKE DOWN 10 7 0 350 0 21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 637 266 1 9780 0 21885 MISC. CIVIL WORKS 680 337 128 12957 165 TOTAL 1327 610 129 23087 165 73328 P.GEN 15 KVA S 21135 FILL WITHOUT COMPACTION 10 0 0 0 0 21210 CEMENT CONCRETE PRODUCTION AND SUPPLY AT 110 0 0 86 0 21250 CONCRETE PLACING FOR PRECAST ELEMENTS 0 10 0 0 0 21255 ERECTION OF PRE CAST ELEMENTS 20 20 0 32 0 21310 FORMWORK IN STRUCTURE 231 32 80 332 0 Project WBE Wise Equipment Utilization Report Project Name Report period------
  • 17. WBE Diesel Engine Oil Rent Charged Total Production Qty Unit Cost Per unit of Production Clearing of site 335,601 - 573,052 908,653 0 Compaction 158,321 - 271,766 430,087 0 Asphalt 258,413 - 556,726 815,139 0 1,090,676 - 1,455,813 2,546,489 210 Sq M 225,792 - 523,181 748,973 215 Sq M 182,979 - 85,224 268,203 63 Sq M Rebar 15,635 1,416 8,843 25,894 12 Ton 430,470 - 1,280,129 1,710,598 2963 Cum 2,814,710 - 1,924,984 4,739,693 0 Cum 279,272 5,664 758,671 1,043,607 934 Cum 496,589 - 699,215 1,195,804 1800 Sq M 94,722 - 148,897 243,619 - - - - 1,496,159 - 1,482,135 2,978,294 2,143,142 - 3,757,836 5,900,978 1795 Cum - - - - 56 Cum Grand Total 19,709,360 14,160 26,479,890 46,203,410 Rent is allocated to WBEs based on Equipment Utilization Report Project WBE wise Equipment Cost For the period
  • 18. Store/warehouse Record For the month of…. Sr Material Item QTY Value QTY Value QTY 1,000,000 Reconciliaiton with: Financial Record Total Purchases for the month 1,000,000 Closing balance in financial ledger Total Material Issues in financial record Difference - Monthly Cost Audit Sheet for Materials Opening Bal Purchases Iss
  • 19. Value QTY Value 800,000 200,000 200,000 800,000 - - sue Closing Bal
  • 20. Subcontractor evaluation form Project# Subcontractor: Invoice No. For the period Quantity Rate Amount Quantity Amount Quantity Amount Quantity Rate Amount This Period Balance to be done RemarksWBS WBE Description UOM Total Contract Invoice Upto last period
  • 21. Subcontracting Cost Project # Subco WBE Bill Inv # Qty(Cum) rate Amount Subco -1 21132 month 3 102,700.00 138.17 14,189,640 Subco -2 21133 month - 3,351,907 Subco -3 21134 month 6 266,793 110.25 29,413,885 46,955,432 Subcontracting Cost of Culverts
  • 23. Analysis of Culverts costs Quantity of work done For the period QTY Total Cost Per unit Cost QTY Total Cost Per unit Cost Material Labour Equipment Sub-contractor Overhead Total Cost Cost Elements Budget Actual Variance
  • 24. Material Purchase Evaluation form Project# Supplier: Quantity Rate Amount Quantity Amount Quantity Amount Quantity Rate Amount Budget Balance Suggested Purchase Budget Balance after Purchase RemarksWBE Item Code Item Description UOM Total Budget Spent todate
  • 25. Check-List for Material Items mostly likely to be chargeable to certain Cost Codes WBS(s) WBE(s) Audit of Project Record for correct Cost Codes(Using Excel tools) Sr. No Item Code Item Description Issue to WBE Correct/Incorrect 1 123 xyz 88-888-99 Y/N Sr. No. Item Code Item Description Applicable Cost Codes for: