CRITICAL PATH METHOD
                               (CEE 320 – VDC SEMINAR)


4 February 2009   Jesse Santiago & Desirae Magallon
Overview
 Background & History
 CPM Defined
 The CPM approach
 Definitions
 Class Exercise
Background & History
 Developed in the 1950s by the US Navy
 Originally, the critical path method considered only logical
 dependencies between terminal elements
 Since then, it has been expanded to allow for the inclusion of
 resources related to each activity, through processes called
 activity-based resource assignments and resource leveling.
 Critical Path Method for the construction industry
   Non-computer approach
   John Fondahl
John Fondahl
 Stanford CE Professor Emeritus – 35 years
 Passed away last September 13th, 2008
 US Marine Corps Sergeant in Iwo Jima
   His father was USMC LtCol
 Co-founder of the CEM program
 1961 Paper for the US Navy – "Non-Computer
 Approach to the Critical Path Method for the
 Construction Industry"
What is CPM?
 The Critical Path Method or Critical Path Analysis, is a
 mathematically based algorithm for scheduling a set of project
 activities
 It is an important tool for effective project management
 Commonly used with all forms of projects, including
 construction, software development, research projects, product
 development, engineering, and plant maintenance, among
 others
 Any project with interdependent activities can apply this
 method of scheduling
What is CPM?
 The essential technique for using CPM is to construct
 a model of the project that includes the following:
   A list of all activities required to complete the project
   (also known as Work Breakdown Structure)
   The time (duration) that each activity will take to
   completion
   The dependencies between the activities.
What is CPM?
 CPM calculates
   The longest path of planned activities to the end of the project
   The earliest and latest that each activity can start and finish without
   making the project longer
 Determines “critical” activities (on the longest path)
 Prioritize activities for the effective management and to
 shorten the planned critical path of a project by:
   Pruning critical path activities
   “Fast tracking" (performing more activities in parallel)
   “Crashing the critical path" (shortening the durations of critical path
   activities by adding resources)
The CPM Approach
 Phase I
   Break project into operations necessary for completion
   Determine sequential relationship of operations
     Every operation must have event to mark commencement –
     i.e. completion of preceding operation
     Can operations overlap?
The CPM Approach
 Phase II
   Create time estimates for each operation
   Determine earliest possible start date, earliest possible
   finish date , latest start & finish
     Determine “free float” and “total float”
   Revised after completion of Phase III
The CPM Approach
 Phase III
   Establish time-cost relationship
   Establish scheduling variations
     Determine most favorable balance between time-cost
   Normal Start – normal time, least cost
   All-Crash Start – least time, higher cost
The CPM Approach
Definitions
 Float (slack) - amount of time that a task can be delayed without causing a
 delay to:
    subsequent tasks (free float)
    project completion date (total float)
 Critical path is the sequence of activities which add up to the longest overall
 duration. It is the shortest time possible to complete the project. Any delay of
 an activity on the critical path directly impacts the planned project completion
 date (there is no float on the critical path). A project can have several, parallel,
 near critical paths. An additional parallel path through the network with the
 total durations shorter than the critical path is called a sub-critical or non-critical
 path.
 Critical activity – activity with zero float
 Resource leveling – iterative process of assigning crews to activities in order to
 calculate their duration
Definitions

Activity Identity box

        Early Start                 Early Finish
           (ES)                         (EF)


                      Activity ID

         Late Start                 Late Finish
            (LS)        Duration
                                       (LF)
Class Exercise
                    A              C   G
      STAR                                          H
      T
                    B              D   E


                                   F
      Activity ID       Duration       Dependency
          A                7
          B                3
          C                6               A
          D                3               B
          E                3               D,F
          F                2               B
          G                3               C
          H                2               E,G
Class Exercise

  0       7   7        13   13       16
      A            C             G
  0   7 7     7    6 13     13   3 16
                                          16       18
                                               H
                                          16   2 18
  0       3   3        6    6        9
      B            D             E
  7   3 10    10   3 13     13   3 16



              3        5
                   F
              11   2 13
Class Exercise

Gantt Chart
Summary

 Critical Path Analysis is an effective and powerful method of
 assessing:
    Tasks which must be carried out
    Where parallel activity can be carried out
    The shortest time in which a project can be completed
    Resources needed to achieve a project
    The sequence of activities, scheduling, and timings involved
    Task priorities
References
 Fondahl, John W., “Non-Computer Approach to the Critical Path Method for
 the Construction Industry”, Report #9, Stanford University, 1961
 Fondahl, John W. “The History of Modern Project Management –
 Precedence Diagramming Methods: Origins and Early Development”.
 Project Management Journal. Volume XVIII. No. 2. June 1987.
 Hendrickson, Chris & Au, Tung, Project Management for Construction,
 Prentice Hall, 1989
 Weber, Sandra C., Scheduling Construction Projects: Principles and Practices,
 Prentice Hall, 2005
Questions???

Weitere ähnliche Inhalte

Was ist angesagt?

Critical path method
Critical path methodCritical path method
Critical path method
Nicola2903
 
Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDM
Shaiful Amri Mansur
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)
Mayur Rahangdale
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
Rahul Dubey
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
Debanjan15
 
Construction scheduling
Construction schedulingConstruction scheduling
Construction scheduling
ZTE Nepal
 

Was ist angesagt? (20)

Critical path method
Critical path methodCritical path method
Critical path method
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Project Management - Critical path method
Project Management - Critical path methodProject Management - Critical path method
Project Management - Critical path method
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDM
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Pert+cpm
Pert+cpmPert+cpm
Pert+cpm
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
crashing of project
crashing of project crashing of project
crashing of project
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path method
 
Construction scheduling
Construction schedulingConstruction scheduling
Construction scheduling
 
Applications of pert
Applications of pertApplications of pert
Applications of pert
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPM
 

Andere mochten auch

Advantages of swot analysis
Advantages of swot analysisAdvantages of swot analysis
Advantages of swot analysis
Dhivya S Dhvi
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
Areef Khan
 
Establishing performance standards
Establishing performance standardsEstablishing performance standards
Establishing performance standards
Rajendra Nabar
 
Management and it's functions
Management and it's functionsManagement and it's functions
Management and it's functions
George Cherian
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
tomeh
 

Andere mochten auch (20)

Critical path method
Critical path methodCritical path method
Critical path method
 
Black box and White box examples
Black box and White box examplesBlack box and White box examples
Black box and White box examples
 
Gantt PERT and CPM
Gantt PERT and CPMGantt PERT and CPM
Gantt PERT and CPM
 
Swot analysis , its importance and limitations
Swot analysis , its importance and limitationsSwot analysis , its importance and limitations
Swot analysis , its importance and limitations
 
Advantages of swot analysis
Advantages of swot analysisAdvantages of swot analysis
Advantages of swot analysis
 
Internal Auditing - Performance Standards
Internal Auditing - Performance StandardsInternal Auditing - Performance Standards
Internal Auditing - Performance Standards
 
Eindtermen en leerplannen wo natuur - Walter Dons
Eindtermen en leerplannen wo natuur - Walter DonsEindtermen en leerplannen wo natuur - Walter Dons
Eindtermen en leerplannen wo natuur - Walter Dons
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Critical Path Method presentation.
Critical Path Method presentation.Critical Path Method presentation.
Critical Path Method presentation.
 
Establishing performance standards
Establishing performance standardsEstablishing performance standards
Establishing performance standards
 
P E R T
P E R TP E R T
P E R T
 
Pert and its applications
Pert and its applicationsPert and its applications
Pert and its applications
 
Management and it's functions
Management and it's functionsManagement and it's functions
Management and it's functions
 
Posdcorb
PosdcorbPosdcorb
Posdcorb
 
Posdcorb
PosdcorbPosdcorb
Posdcorb
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
 
CPM-Updating
CPM-UpdatingCPM-Updating
CPM-Updating
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review Technique
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
POSDCORB
POSDCORBPOSDCORB
POSDCORB
 

Ähnlich wie Cpm (critical path method)

Project management activity task
Project management activity taskProject management activity task
Project management activity task
Tadele Asmare
 
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptxLec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
NegeseTeklearegay
 

Ähnlich wie Cpm (critical path method) (20)

Cpm
CpmCpm
Cpm
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Network analysis & cpm
Network analysis & cpmNetwork analysis & cpm
Network analysis & cpm
 
Cm exercise 4
Cm exercise 4Cm exercise 4
Cm exercise 4
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
MGT-Ch07.ppt
MGT-Ch07.pptMGT-Ch07.ppt
MGT-Ch07.ppt
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Project management
Project managementProject management
Project management
 
Project Management
Project Management Project Management
Project Management
 
Project management activity task
Project management activity taskProject management activity task
Project management activity task
 
Introduction to Project Management
Introduction to Project Management Introduction to Project Management
Introduction to Project Management
 
Project management
Project managementProject management
Project management
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptxLec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
 
Chap003
Chap003Chap003
Chap003
 

Mehr von El Moro (8)

Utility panel
Utility panelUtility panel
Utility panel
 
Process & procedure presentation
Process & procedure presentationProcess & procedure presentation
Process & procedure presentation
 
Contoh pelan konsep
Contoh pelan konsepContoh pelan konsep
Contoh pelan konsep
 
Commercial presentation group b
Commercial presentation group bCommercial presentation group b
Commercial presentation group b
 
Mbas piawaian copy
Mbas piawaian   copyMbas piawaian   copy
Mbas piawaian copy
 
Presentation1 adi
Presentation1 adiPresentation1 adi
Presentation1 adi
 
Perumahan edit (2)
Perumahan   edit (2)Perumahan   edit (2)
Perumahan edit (2)
 
Piawaian industri
Piawaian industriPiawaian industri
Piawaian industri
 

Kürzlich hochgeladen

💚😋 Saharanpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
💚😋 Saharanpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋💚😋 Saharanpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
💚😋 Saharanpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
nirzagarg
 
Corporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdfCorporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdf
Probe Gold
 
VIP Call Girls Junagadh 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Junagadh 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Junagadh 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Junagadh 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Call Girls in Panjabi Bagh, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Panjabi Bagh, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Panjabi Bagh, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Panjabi Bagh, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Terna - 1Q 2024 Consolidated Results Presentation
Terna - 1Q 2024 Consolidated Results PresentationTerna - 1Q 2024 Consolidated Results Presentation
Terna - 1Q 2024 Consolidated Results Presentation
Terna SpA
 
Editing progress 20th march.docxxxxxxxxx
Editing progress 20th march.docxxxxxxxxxEditing progress 20th march.docxxxxxxxxx
Editing progress 20th march.docxxxxxxxxx
MollyBrown86
 
VIP Call Girls Kheda 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Kheda 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Kheda 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Kheda 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 

Kürzlich hochgeladen (20)

countries with the highest gold reserves in 2024
countries with the highest gold reserves in 2024countries with the highest gold reserves in 2024
countries with the highest gold reserves in 2024
 
Teck Supplemental Information, May 2, 2024
Teck Supplemental Information, May 2, 2024Teck Supplemental Information, May 2, 2024
Teck Supplemental Information, May 2, 2024
 
Osisko Gold Royalties Ltd - Q1 2024 Results
Osisko Gold Royalties Ltd - Q1 2024 ResultsOsisko Gold Royalties Ltd - Q1 2024 Results
Osisko Gold Royalties Ltd - Q1 2024 Results
 
💚😋 Saharanpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
💚😋 Saharanpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋💚😋 Saharanpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
💚😋 Saharanpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
 
Corporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdfCorporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdf
 
VIP Call Girls Junagadh 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Junagadh 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Junagadh 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Junagadh 7001035870 Whatsapp Number, 24/07 Booking
 
Dubai Call Girls O525547&19 Calls Girls In Dubai (L0w+Charger)
Dubai Call Girls O525547&19 Calls Girls In Dubai (L0w+Charger)Dubai Call Girls O525547&19 Calls Girls In Dubai (L0w+Charger)
Dubai Call Girls O525547&19 Calls Girls In Dubai (L0w+Charger)
 
Call Girls in Panjabi Bagh, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Panjabi Bagh, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Panjabi Bagh, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Panjabi Bagh, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
VVIP Pune Call Girls Sopan Baug WhatSapp Number 8005736733 With Elite Staff A...
VVIP Pune Call Girls Sopan Baug WhatSapp Number 8005736733 With Elite Staff A...VVIP Pune Call Girls Sopan Baug WhatSapp Number 8005736733 With Elite Staff A...
VVIP Pune Call Girls Sopan Baug WhatSapp Number 8005736733 With Elite Staff A...
 
Terna - 1Q 2024 Consolidated Results Presentation
Terna - 1Q 2024 Consolidated Results PresentationTerna - 1Q 2024 Consolidated Results Presentation
Terna - 1Q 2024 Consolidated Results Presentation
 
SME IPO Opportunity and Trends of May 2024
SME IPO Opportunity and Trends of May 2024SME IPO Opportunity and Trends of May 2024
SME IPO Opportunity and Trends of May 2024
 
Editing progress 20th march.docxxxxxxxxx
Editing progress 20th march.docxxxxxxxxxEditing progress 20th march.docxxxxxxxxx
Editing progress 20th march.docxxxxxxxxx
 
Indapur - Virgin Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service...
Indapur - Virgin Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service...Indapur - Virgin Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service...
Indapur - Virgin Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service...
 
VIP Call Girls Kheda 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Kheda 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Kheda 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Kheda 7001035870 Whatsapp Number, 24/07 Booking
 
Osisko Development - Investor Presentation - May 2024
Osisko Development - Investor Presentation - May 2024Osisko Development - Investor Presentation - May 2024
Osisko Development - Investor Presentation - May 2024
 
VVIP Pune Call Girls Handewadi WhatSapp Number 8005736733 With Elite Staff An...
VVIP Pune Call Girls Handewadi WhatSapp Number 8005736733 With Elite Staff An...VVIP Pune Call Girls Handewadi WhatSapp Number 8005736733 With Elite Staff An...
VVIP Pune Call Girls Handewadi WhatSapp Number 8005736733 With Elite Staff An...
 
The Leonardo 1Q 2024 Results Presentation
The Leonardo 1Q 2024 Results PresentationThe Leonardo 1Q 2024 Results Presentation
The Leonardo 1Q 2024 Results Presentation
 
AMG Quarterly Investor Presentation May 2024
AMG Quarterly Investor Presentation May 2024AMG Quarterly Investor Presentation May 2024
AMG Quarterly Investor Presentation May 2024
 
Collective Mining | Corporate Presentation - May 2024
Collective Mining | Corporate Presentation - May 2024Collective Mining | Corporate Presentation - May 2024
Collective Mining | Corporate Presentation - May 2024
 
Dattawadi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready Fo...
Dattawadi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready Fo...Dattawadi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready Fo...
Dattawadi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready Fo...
 

Cpm (critical path method)

  • 1. CRITICAL PATH METHOD (CEE 320 – VDC SEMINAR) 4 February 2009 Jesse Santiago & Desirae Magallon
  • 2. Overview Background & History CPM Defined The CPM approach Definitions Class Exercise
  • 3. Background & History Developed in the 1950s by the US Navy Originally, the critical path method considered only logical dependencies between terminal elements Since then, it has been expanded to allow for the inclusion of resources related to each activity, through processes called activity-based resource assignments and resource leveling. Critical Path Method for the construction industry Non-computer approach John Fondahl
  • 4. John Fondahl Stanford CE Professor Emeritus – 35 years Passed away last September 13th, 2008 US Marine Corps Sergeant in Iwo Jima His father was USMC LtCol Co-founder of the CEM program 1961 Paper for the US Navy – "Non-Computer Approach to the Critical Path Method for the Construction Industry"
  • 5. What is CPM? The Critical Path Method or Critical Path Analysis, is a mathematically based algorithm for scheduling a set of project activities It is an important tool for effective project management Commonly used with all forms of projects, including construction, software development, research projects, product development, engineering, and plant maintenance, among others Any project with interdependent activities can apply this method of scheduling
  • 6. What is CPM? The essential technique for using CPM is to construct a model of the project that includes the following: A list of all activities required to complete the project (also known as Work Breakdown Structure) The time (duration) that each activity will take to completion The dependencies between the activities.
  • 7. What is CPM? CPM calculates The longest path of planned activities to the end of the project The earliest and latest that each activity can start and finish without making the project longer Determines “critical” activities (on the longest path) Prioritize activities for the effective management and to shorten the planned critical path of a project by: Pruning critical path activities “Fast tracking" (performing more activities in parallel) “Crashing the critical path" (shortening the durations of critical path activities by adding resources)
  • 8. The CPM Approach Phase I Break project into operations necessary for completion Determine sequential relationship of operations Every operation must have event to mark commencement – i.e. completion of preceding operation Can operations overlap?
  • 9. The CPM Approach Phase II Create time estimates for each operation Determine earliest possible start date, earliest possible finish date , latest start & finish Determine “free float” and “total float” Revised after completion of Phase III
  • 10. The CPM Approach Phase III Establish time-cost relationship Establish scheduling variations Determine most favorable balance between time-cost Normal Start – normal time, least cost All-Crash Start – least time, higher cost
  • 12. Definitions Float (slack) - amount of time that a task can be delayed without causing a delay to: subsequent tasks (free float) project completion date (total float) Critical path is the sequence of activities which add up to the longest overall duration. It is the shortest time possible to complete the project. Any delay of an activity on the critical path directly impacts the planned project completion date (there is no float on the critical path). A project can have several, parallel, near critical paths. An additional parallel path through the network with the total durations shorter than the critical path is called a sub-critical or non-critical path. Critical activity – activity with zero float Resource leveling – iterative process of assigning crews to activities in order to calculate their duration
  • 13. Definitions Activity Identity box Early Start Early Finish (ES) (EF) Activity ID Late Start Late Finish (LS) Duration (LF)
  • 14. Class Exercise A C G STAR H T B D E F Activity ID Duration Dependency A 7 B 3 C 6 A D 3 B E 3 D,F F 2 B G 3 C H 2 E,G
  • 15. Class Exercise 0 7 7 13 13 16 A C G 0 7 7 7 6 13 13 3 16 16 18 H 16 2 18 0 3 3 6 6 9 B D E 7 3 10 10 3 13 13 3 16 3 5 F 11 2 13
  • 17. Summary Critical Path Analysis is an effective and powerful method of assessing: Tasks which must be carried out Where parallel activity can be carried out The shortest time in which a project can be completed Resources needed to achieve a project The sequence of activities, scheduling, and timings involved Task priorities
  • 18. References Fondahl, John W., “Non-Computer Approach to the Critical Path Method for the Construction Industry”, Report #9, Stanford University, 1961 Fondahl, John W. “The History of Modern Project Management – Precedence Diagramming Methods: Origins and Early Development”. Project Management Journal. Volume XVIII. No. 2. June 1987. Hendrickson, Chris & Au, Tung, Project Management for Construction, Prentice Hall, 1989 Weber, Sandra C., Scheduling Construction Projects: Principles and Practices, Prentice Hall, 2005