Project Management

Delivering the contract
Realisation of the proposal


• The contract has been signed
• Start dates and completion dates are
  agreed
• The whole project now moves into the
  “Realisation” stage


Conception     Development            Realisation
The Guggenheim Museum, Bilbao Frank Gehry




Conception           Development        Realisation
The building design process v. project management




Conception              Development              Realisation



      Design process: tails off on realisation


                                                   Project
 Contractor appointed to organise                management
 the realisation stage of the
 project and is responsible for the
 project management
The “Project”


• There may be two projects running in
  parallel:
  – The entire design project, managed by the
    architect/professional advisor:
    • Completing and delivering the design
  – The realisation project managed by the
    contractor:
    • Completing and delivering the building
  – Sometimes the design project finishes
    completely at the end of the development
    stage
Managing the design project


•   The architect’s responsibility during
    the realisation phase of the design
    project is to ensure two things:
    1. That what the contractor delivers is what
       the employer expects-the contract is met
    2. Where that cannot be done, that the
       employer agrees any changes which
       have to be made
      •   Where the design project is terminated at the
          end of the development stage, there may be
          no professional protection for the employer.
Managing the building project


• This is the contractor’s responsibility.
  He/she has to manage
  – Different trades
  – Delivery and securing of materials and
    prefabricated elements (windows,
    plumbing etc)
  – Site security and safety
  – Payment of suppliers and sub-contractors
  – Testing of materials, as required by the
    contract
  – Agreeing changes with the supervising
    architect
Project management can go wrong…
Project tasks


• Every building project is built up of
  many tasks.
• Some of these tasks may be critical in
  that other tasks cannot be
  started/completed before they are:
  – Walls can’t be plastered until basic
    electrical wiring is installed and completed
  – Brick laying cannot start until foundations
    are finished and cured to full strength
  – Internal decorations can’t start until the
    building fabric is dry.
Defining tasks


• The project is broken into tasks and sub
  tasks
• Dependency of tasks is established
  (task B can’t start until task A is
  finished, task C can happen at any time
  etc. )
• Estimated duration of tasks is calculated
• A bar chart or GANT chart of the tasks
  is drawn up
GANT charting

• Each task is a horizontal bar
• Length of bar = time to complete task
• The beginning and end of the chart are
  the start and finish dates for the building
  project
GANT chart for project planning


• The contractor knows the chart must fit
  into the contract time.
• Different tasks can be tweaked to
  shorten the overall project time
  – If a critical task looks like it might take one
    week too long, the contractor can allocate
    more resources to it to speed it up
  – If a non critical task looks like it is
    consuming resources needed by a critical
    task, it can be moved to a different time
GANT chart for project monitoring


• Once the project is underway a parallel
  chart is drawn showing actual progress
• A comparison between actual and
  planned progress will form the basis of
  all site meetings with the architect. This
  will give early warning of problems.
• The management of the building project
  is entirely the responsibility of the
  contractor but he/she is obliged to
  demonstrate the state of progress of the
  project to the employer.
The architect’s project management role


• The supervising architect carries out
  three fundamental project management
  roles
  – Confirming all works are in accordance
    with the contract documents
  – Authorising modifications from the contract
    documents, with the employer’s agreement
  – Authorising stage payments to the
    contractor
Confirming works


• The architect will visit the site regularly,
  with the contractor’s permission
• During those visits, completed works
  are inspected. If they are not in
  accordance with the contract, the
  architect will condemn them. It is the
  contractor’s responsibility to replace the
  works as necessary
Modifications


• Things always change
  –   Difficult ground conditions are discovered
  –   Goods supplier goes bankrupt
  –   Employer’s requirements change
  –   New technology becomes available
• Changes must only happen:
  – with the employer’s and the contractor’s
    agreement
  – With the changes fully priced, in accordance with
    rules agreed in the contract
• The Architect issues formal instructions
  confirming these agreed changes
Stage payments


• The contractor is paid in stages in
  arrears for completed work
• The architect visits the site to confirm
  that the work is complete, to confirm the
  value of the work, and then issues a
  certificate authorising payment
• The employer is contractually
  committed to pay the value of each
  certificate, less a retention amount
  (usually 10%), the “retention fund”
Practical completion


• On “practical completion” the architect
  confirms the works are substantially complete
  and the building is handed over to the
  employer
• Half the retention fund is paid to the
  contractor and the “defects liability period”
  commences (usually 6 months)
• At the end of this period a “snagging list” of
  outstanding work and discovered defects is
  given to the contractor who must correct them
  before the final certificate of completion is
  issued and the remainder of the retention
  fund is released. The contract is now
  complete.
Management contract: very large projects




  Conception           Development            Realisation




Management                          Project
contractor appointed              management
at development stage
to coordinate
specialist suppliers
and contractors
Management really big projects: Olympics 2012
Many sites, many designers, many builders, many clients,
absolutely fixed deadline




                                                                 July 27, 2012
 Conception              Development              Realisation




                          Project
                        management
Nothing is more complex than the Olympics




Source: London 2012
Summary


• Contracts rarely run as smoothly as in theory
  – Building works are too unpredictable
  – The amount of work on the snagging list is not
    worth 5% to the contractor so he never does it
  – Agreement cannot always be achieved on who is
    responsible for a defect, is it the contractor, the
    designer, a nominated sub-contractor
• However, if you know how a project should
  run, you have a good chance of managing
  the project in reality.

Weitere ähnliche Inhalte

Was ist angesagt?

Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter SummeryDerek Cooksey
 
Construction Management Services
Construction Management ServicesConstruction Management Services
Construction Management ServicesDavid Rosacker
 
Project 1 - Architect
Project 1 - Architect Project 1 - Architect
Project 1 - Architect leejanett3
 
Building Construction 3. responsibilities of participants
Building Construction 3. responsibilities of participantsBuilding Construction 3. responsibilities of participants
Building Construction 3. responsibilities of participantsHamdija Velagic
 
Process of pre construction phase drawbacks
Process of pre construction phase drawbacksProcess of pre construction phase drawbacks
Process of pre construction phase drawbacksglibson rojer
 
Eco friendly electricity generating tiles project
Eco friendly electricity generating tiles projectEco friendly electricity generating tiles project
Eco friendly electricity generating tiles projectHagi Sahib
 
Project management assignment help
Project management assignment helpProject management assignment help
Project management assignment helpassignmenthelpp
 
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptm
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptmDesign Engineer Construct Level 2 Unit 1_1.1-4.4.pptm
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptmSamuel Boone
 
Project report on construction of hotel/hostel
Project report on construction of hotel/hostelProject report on construction of hotel/hostel
Project report on construction of hotel/hostelmuhammed iqbal
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotChris Carson
 
4 storied building superstructure construction proposal
4 storied building superstructure construction proposal4 storied building superstructure construction proposal
4 storied building superstructure construction proposalMkh Nantu
 
Managing The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy ProjectsManaging The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy Projectsmtingle
 
Project Management Assignment 1
Project Management Assignment 1Project Management Assignment 1
Project Management Assignment 1DavidJPCChai
 
Defining and documenting a project
Defining and documenting a projectDefining and documenting a project
Defining and documenting a projectJing Fan Koh
 

Was ist angesagt? (20)

Updated Resume.DOC
Updated Resume.DOCUpdated Resume.DOC
Updated Resume.DOC
 
Michelle Simpson Assignment #2
Michelle Simpson Assignment #2Michelle Simpson Assignment #2
Michelle Simpson Assignment #2
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter Summery
 
Construction Management Services
Construction Management ServicesConstruction Management Services
Construction Management Services
 
Project 1 - Architect
Project 1 - Architect Project 1 - Architect
Project 1 - Architect
 
Managing Project Transitions
Managing Project TransitionsManaging Project Transitions
Managing Project Transitions
 
Building Construction 3. responsibilities of participants
Building Construction 3. responsibilities of participantsBuilding Construction 3. responsibilities of participants
Building Construction 3. responsibilities of participants
 
Process of pre construction phase drawbacks
Process of pre construction phase drawbacksProcess of pre construction phase drawbacks
Process of pre construction phase drawbacks
 
Eco friendly electricity generating tiles project
Eco friendly electricity generating tiles projectEco friendly electricity generating tiles project
Eco friendly electricity generating tiles project
 
Claim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINALClaim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINAL
 
EPC Contracts
EPC Contracts EPC Contracts
EPC Contracts
 
Project management assignment help
Project management assignment helpProject management assignment help
Project management assignment help
 
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptm
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptmDesign Engineer Construct Level 2 Unit 1_1.1-4.4.pptm
Design Engineer Construct Level 2 Unit 1_1.1-4.4.pptm
 
Project report on construction of hotel/hostel
Project report on construction of hotel/hostelProject report on construction of hotel/hostel
Project report on construction of hotel/hostel
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
 
4 storied building superstructure construction proposal
4 storied building superstructure construction proposal4 storied building superstructure construction proposal
4 storied building superstructure construction proposal
 
Managing The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy ProjectsManaging The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy Projects
 
Claims
ClaimsClaims
Claims
 
Project Management Assignment 1
Project Management Assignment 1Project Management Assignment 1
Project Management Assignment 1
 
Defining and documenting a project
Defining and documenting a projectDefining and documenting a project
Defining and documenting a project
 

Andere mochten auch

Blue Group Gant Chart Iii Sr
Blue Group Gant Chart Iii SrBlue Group Gant Chart Iii Sr
Blue Group Gant Chart Iii Srguest224dd2
 
Chuong 4 11-2014
Chuong 4 11-2014Chuong 4 11-2014
Chuong 4 11-2014Phi Phi
 
Research paper
Research paperResearch paper
Research paperwillhulsey
 
Product work log photoshow
Product work log photoshowProduct work log photoshow
Product work log photoshowwillhulsey
 
El poder executiu i les formes de govern
El poder executiu i les formes de governEl poder executiu i les formes de govern
El poder executiu i les formes de governMarina Vallmajor
 
Adéu al cotxe elèctric israelià
Adéu al cotxe elèctric israeliàAdéu al cotxe elèctric israelià
Adéu al cotxe elèctric israeliàmajdaelmourabit
 
Excel Lesson 3
Excel Lesson 3Excel Lesson 3
Excel Lesson 3spirax1681
 
El govern espanyol assegura que l’economia està accelerant
El govern espanyol assegura que l’economia està accelerantEl govern espanyol assegura que l’economia està accelerant
El govern espanyol assegura que l’economia està accelerantclaudiacanet
 
Running Successful Outsourcing Procurement Projects & Delivering Profitab...
Running Successful Outsourcing Procurement Projects & Delivering Profitab...Running Successful Outsourcing Procurement Projects & Delivering Profitab...
Running Successful Outsourcing Procurement Projects & Delivering Profitab...lonas19
 
How to Create a ArcGIS Story Map Final Presentation
How to Create a ArcGIS Story Map Final Presentation How to Create a ArcGIS Story Map Final Presentation
How to Create a ArcGIS Story Map Final Presentation Kathryn Cannon
 
Usos adolescents de les xarxes socials: #oportunitats i #riscos
Usos adolescents de les xarxes socials: #oportunitats i #riscosUsos adolescents de les xarxes socials: #oportunitats i #riscos
Usos adolescents de les xarxes socials: #oportunitats i #riscosJordi Bernabeu Farrús
 
Luyện thi toeic cấp tốc part 7
Luyện thi toeic cấp tốc part 7Luyện thi toeic cấp tốc part 7
Luyện thi toeic cấp tốc part 7TOEIC BOOK STORE
 
Ground Support Equipment for aircraft
Ground Support Equipment for aircraftGround Support Equipment for aircraft
Ground Support Equipment for aircraftangleratrium
 

Andere mochten auch (20)

Gant chart final
Gant chart finalGant chart final
Gant chart final
 
Prakashic
PrakashicPrakashic
Prakashic
 
Blue Group Gant Chart Iii Sr
Blue Group Gant Chart Iii SrBlue Group Gant Chart Iii Sr
Blue Group Gant Chart Iii Sr
 
Chuong 4 11-2014
Chuong 4 11-2014Chuong 4 11-2014
Chuong 4 11-2014
 
Research paper
Research paperResearch paper
Research paper
 
Product work log photoshow
Product work log photoshowProduct work log photoshow
Product work log photoshow
 
K griham chapter 5
K griham chapter 5K griham chapter 5
K griham chapter 5
 
El poder executiu i les formes de govern
El poder executiu i les formes de governEl poder executiu i les formes de govern
El poder executiu i les formes de govern
 
Adéu al cotxe elèctric israelià
Adéu al cotxe elèctric israeliàAdéu al cotxe elèctric israelià
Adéu al cotxe elèctric israelià
 
Gant chart
Gant chartGant chart
Gant chart
 
Question 5
Question 5Question 5
Question 5
 
Excel Lesson 3
Excel Lesson 3Excel Lesson 3
Excel Lesson 3
 
El govern espanyol assegura que l’economia està accelerant
El govern espanyol assegura que l’economia està accelerantEl govern espanyol assegura que l’economia està accelerant
El govern espanyol assegura que l’economia està accelerant
 
Running Successful Outsourcing Procurement Projects & Delivering Profitab...
Running Successful Outsourcing Procurement Projects & Delivering Profitab...Running Successful Outsourcing Procurement Projects & Delivering Profitab...
Running Successful Outsourcing Procurement Projects & Delivering Profitab...
 
The brain
The brainThe brain
The brain
 
How to Create a ArcGIS Story Map Final Presentation
How to Create a ArcGIS Story Map Final Presentation How to Create a ArcGIS Story Map Final Presentation
How to Create a ArcGIS Story Map Final Presentation
 
Usos adolescents de les xarxes socials: #oportunitats i #riscos
Usos adolescents de les xarxes socials: #oportunitats i #riscosUsos adolescents de les xarxes socials: #oportunitats i #riscos
Usos adolescents de les xarxes socials: #oportunitats i #riscos
 
Luyện thi toeic cấp tốc part 7
Luyện thi toeic cấp tốc part 7Luyện thi toeic cấp tốc part 7
Luyện thi toeic cấp tốc part 7
 
Ground Support Equipment for aircraft
Ground Support Equipment for aircraftGround Support Equipment for aircraft
Ground Support Equipment for aircraft
 
Modern_Macramé
Modern_MacraméModern_Macramé
Modern_Macramé
 

Ähnlich wie Project management

Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectNekumi Kida
 
Role of HVAC Engineer
Role of HVAC EngineerRole of HVAC Engineer
Role of HVAC EngineerAshutosh
 
ZAKI Michael_CV 042014
ZAKI Michael_CV 042014ZAKI Michael_CV 042014
ZAKI Michael_CV 042014Michael Khalil
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Managementbrainquisitive
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contractsAnil Kumar(6)
 
Construction Management Lesson - L1.pptx
Construction Management Lesson - L1.pptxConstruction Management Lesson - L1.pptx
Construction Management Lesson - L1.pptxMaxwellAcquah1
 
Project Planning and Excution chapter 6.ppt
Project Planning and Excution chapter 6.pptProject Planning and Excution chapter 6.ppt
Project Planning and Excution chapter 6.pptadabotor7
 
Haytham zidan, civil engineer, 2008
Haytham zidan, civil engineer, 2008Haytham zidan, civil engineer, 2008
Haytham zidan, civil engineer, 2008HaythamZidan1
 
BASICS OF PROJECT MANAGEMENT
BASICS OF PROJECT MANAGEMENTBASICS OF PROJECT MANAGEMENT
BASICS OF PROJECT MANAGEMENTNiruban Projoth
 
project-management.pdf
project-management.pdfproject-management.pdf
project-management.pdfSAMPREET3
 
Curriculum vitae updated as of 01 April,2017
Curriculum vitae updated as of 01 April,2017Curriculum vitae updated as of 01 April,2017
Curriculum vitae updated as of 01 April,2017Renilo Ubusan
 
Curriculum vitae updated as of 01 April,2017
Curriculum vitae updated as of 01 April,2017Curriculum vitae updated as of 01 April,2017
Curriculum vitae updated as of 01 April,2017Renilo Ubusan
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1zerospaces_
 
building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTRiyaVerma238431
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUPKeshav Seewraz
 
CV - Alaa Nour
CV - Alaa Nour CV - Alaa Nour
CV - Alaa Nour Zoy Zoy
 
Guc arct 702 legislations lecture 4 - project delivery process and business...
Guc arct 702 legislations   lecture 4 - project delivery process and business...Guc arct 702 legislations   lecture 4 - project delivery process and business...
Guc arct 702 legislations lecture 4 - project delivery process and business...Galala University
 

Ähnlich wie Project management (20)

Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A Project
 
Role of HVAC Engineer
Role of HVAC EngineerRole of HVAC Engineer
Role of HVAC Engineer
 
Resume
ResumeResume
Resume
 
ZAKI Michael_CV 042014
ZAKI Michael_CV 042014ZAKI Michael_CV 042014
ZAKI Michael_CV 042014
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Management
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
Construction Management Lesson - L1.pptx
Construction Management Lesson - L1.pptxConstruction Management Lesson - L1.pptx
Construction Management Lesson - L1.pptx
 
Project Planning and Excution chapter 6.ppt
Project Planning and Excution chapter 6.pptProject Planning and Excution chapter 6.ppt
Project Planning and Excution chapter 6.ppt
 
Haytham zidan, civil engineer, 2008
Haytham zidan, civil engineer, 2008Haytham zidan, civil engineer, 2008
Haytham zidan, civil engineer, 2008
 
BASICS OF PROJECT MANAGEMENT
BASICS OF PROJECT MANAGEMENTBASICS OF PROJECT MANAGEMENT
BASICS OF PROJECT MANAGEMENT
 
project-management.pdf
project-management.pdfproject-management.pdf
project-management.pdf
 
Curriculum vitae updated as of 01 April,2017
Curriculum vitae updated as of 01 April,2017Curriculum vitae updated as of 01 April,2017
Curriculum vitae updated as of 01 April,2017
 
Curriculum vitae updated as of 01 April,2017
Curriculum vitae updated as of 01 April,2017Curriculum vitae updated as of 01 April,2017
Curriculum vitae updated as of 01 April,2017
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1
 
CEM unit -I ppt.pptx
CEM unit -I ppt.pptxCEM unit -I ppt.pptx
CEM unit -I ppt.pptx
 
Project Files Completion
Project Files CompletionProject Files Completion
Project Files Completion
 
building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENT
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
 
CV - Alaa Nour
CV - Alaa Nour CV - Alaa Nour
CV - Alaa Nour
 
Guc arct 702 legislations lecture 4 - project delivery process and business...
Guc arct 702 legislations   lecture 4 - project delivery process and business...Guc arct 702 legislations   lecture 4 - project delivery process and business...
Guc arct 702 legislations lecture 4 - project delivery process and business...
 

Mehr von Julian Swindell

Juhm farming in north east india
Juhm farming in north east indiaJuhm farming in north east india
Juhm farming in north east indiaJulian Swindell
 
Elements of the rural landscape
Elements of the rural landscapeElements of the rural landscape
Elements of the rural landscapeJulian Swindell
 
Introduction to building technology
Introduction to building technologyIntroduction to building technology
Introduction to building technologyJulian Swindell
 
Servicing large buildings
Servicing large buildingsServicing large buildings
Servicing large buildingsJulian Swindell
 
Options for energy_sustainability
Options for energy_sustainabilityOptions for energy_sustainability
Options for energy_sustainabilityJulian Swindell
 
Conversions of buildings
Conversions of buildingsConversions of buildings
Conversions of buildingsJulian Swindell
 
The Building Regulations and their approved documents
The Building Regulations and their approved documentsThe Building Regulations and their approved documents
The Building Regulations and their approved documentsJulian Swindell
 
Building Contracts and CDM regulations
Building Contracts and CDM regulationsBuilding Contracts and CDM regulations
Building Contracts and CDM regulationsJulian Swindell
 
CVs for work experience in property
CVs for work experience in propertyCVs for work experience in property
CVs for work experience in propertyJulian Swindell
 
The village knowledge_centres_introduction
The village knowledge_centres_introductionThe village knowledge_centres_introduction
The village knowledge_centres_introductionJulian Swindell
 
Module 2006 introduction
Module 2006 introductionModule 2006 introduction
Module 2006 introductionJulian Swindell
 
Selecting features by attributes
Selecting features by attributesSelecting features by attributes
Selecting features by attributesJulian Swindell
 
Basic tools to use in assignment3
Basic tools to use in assignment3Basic tools to use in assignment3
Basic tools to use in assignment3Julian Swindell
 
Assignment 3 second set of videos
Assignment 3  second set of videosAssignment 3  second set of videos
Assignment 3 second set of videosJulian Swindell
 
3012: Assignment 3 Video clip collection 1
3012: Assignment 3 Video clip collection 13012: Assignment 3 Video clip collection 1
3012: Assignment 3 Video clip collection 1Julian Swindell
 

Mehr von Julian Swindell (20)

Juhm farming in north east india
Juhm farming in north east indiaJuhm farming in north east india
Juhm farming in north east india
 
Elements of the rural landscape
Elements of the rural landscapeElements of the rural landscape
Elements of the rural landscape
 
Introduction to building technology
Introduction to building technologyIntroduction to building technology
Introduction to building technology
 
Complex services
Complex servicesComplex services
Complex services
 
Servicing large buildings
Servicing large buildingsServicing large buildings
Servicing large buildings
 
Options for energy_sustainability
Options for energy_sustainabilityOptions for energy_sustainability
Options for energy_sustainability
 
Drawings
DrawingsDrawings
Drawings
 
Conversions of buildings
Conversions of buildingsConversions of buildings
Conversions of buildings
 
The Building Regulations and their approved documents
The Building Regulations and their approved documentsThe Building Regulations and their approved documents
The Building Regulations and their approved documents
 
Building Contracts and CDM regulations
Building Contracts and CDM regulationsBuilding Contracts and CDM regulations
Building Contracts and CDM regulations
 
Remote sensing
Remote sensingRemote sensing
Remote sensing
 
Greenshopsolar photos
Greenshopsolar photosGreenshopsolar photos
Greenshopsolar photos
 
CVs for work experience in property
CVs for work experience in propertyCVs for work experience in property
CVs for work experience in property
 
Efita2007 update2011
Efita2007 update2011Efita2007 update2011
Efita2007 update2011
 
The village knowledge_centres_introduction
The village knowledge_centres_introductionThe village knowledge_centres_introduction
The village knowledge_centres_introduction
 
Module 2006 introduction
Module 2006 introductionModule 2006 introduction
Module 2006 introduction
 
Selecting features by attributes
Selecting features by attributesSelecting features by attributes
Selecting features by attributes
 
Basic tools to use in assignment3
Basic tools to use in assignment3Basic tools to use in assignment3
Basic tools to use in assignment3
 
Assignment 3 second set of videos
Assignment 3  second set of videosAssignment 3  second set of videos
Assignment 3 second set of videos
 
3012: Assignment 3 Video clip collection 1
3012: Assignment 3 Video clip collection 13012: Assignment 3 Video clip collection 1
3012: Assignment 3 Video clip collection 1
 

Kürzlich hochgeladen

Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...Pooja Nehwal
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...anjaliyadav012327
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 

Kürzlich hochgeladen (20)

Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 

Project management

  • 2. Realisation of the proposal • The contract has been signed • Start dates and completion dates are agreed • The whole project now moves into the “Realisation” stage Conception Development Realisation
  • 3. The Guggenheim Museum, Bilbao Frank Gehry Conception Development Realisation
  • 4. The building design process v. project management Conception Development Realisation Design process: tails off on realisation Project Contractor appointed to organise management the realisation stage of the project and is responsible for the project management
  • 5. The “Project” • There may be two projects running in parallel: – The entire design project, managed by the architect/professional advisor: • Completing and delivering the design – The realisation project managed by the contractor: • Completing and delivering the building – Sometimes the design project finishes completely at the end of the development stage
  • 6. Managing the design project • The architect’s responsibility during the realisation phase of the design project is to ensure two things: 1. That what the contractor delivers is what the employer expects-the contract is met 2. Where that cannot be done, that the employer agrees any changes which have to be made • Where the design project is terminated at the end of the development stage, there may be no professional protection for the employer.
  • 7. Managing the building project • This is the contractor’s responsibility. He/she has to manage – Different trades – Delivery and securing of materials and prefabricated elements (windows, plumbing etc) – Site security and safety – Payment of suppliers and sub-contractors – Testing of materials, as required by the contract – Agreeing changes with the supervising architect
  • 9. Project tasks • Every building project is built up of many tasks. • Some of these tasks may be critical in that other tasks cannot be started/completed before they are: – Walls can’t be plastered until basic electrical wiring is installed and completed – Brick laying cannot start until foundations are finished and cured to full strength – Internal decorations can’t start until the building fabric is dry.
  • 10. Defining tasks • The project is broken into tasks and sub tasks • Dependency of tasks is established (task B can’t start until task A is finished, task C can happen at any time etc. ) • Estimated duration of tasks is calculated • A bar chart or GANT chart of the tasks is drawn up
  • 11. GANT charting • Each task is a horizontal bar • Length of bar = time to complete task • The beginning and end of the chart are the start and finish dates for the building project
  • 12. GANT chart for project planning • The contractor knows the chart must fit into the contract time. • Different tasks can be tweaked to shorten the overall project time – If a critical task looks like it might take one week too long, the contractor can allocate more resources to it to speed it up – If a non critical task looks like it is consuming resources needed by a critical task, it can be moved to a different time
  • 13. GANT chart for project monitoring • Once the project is underway a parallel chart is drawn showing actual progress • A comparison between actual and planned progress will form the basis of all site meetings with the architect. This will give early warning of problems. • The management of the building project is entirely the responsibility of the contractor but he/she is obliged to demonstrate the state of progress of the project to the employer.
  • 14. The architect’s project management role • The supervising architect carries out three fundamental project management roles – Confirming all works are in accordance with the contract documents – Authorising modifications from the contract documents, with the employer’s agreement – Authorising stage payments to the contractor
  • 15. Confirming works • The architect will visit the site regularly, with the contractor’s permission • During those visits, completed works are inspected. If they are not in accordance with the contract, the architect will condemn them. It is the contractor’s responsibility to replace the works as necessary
  • 16. Modifications • Things always change – Difficult ground conditions are discovered – Goods supplier goes bankrupt – Employer’s requirements change – New technology becomes available • Changes must only happen: – with the employer’s and the contractor’s agreement – With the changes fully priced, in accordance with rules agreed in the contract • The Architect issues formal instructions confirming these agreed changes
  • 17. Stage payments • The contractor is paid in stages in arrears for completed work • The architect visits the site to confirm that the work is complete, to confirm the value of the work, and then issues a certificate authorising payment • The employer is contractually committed to pay the value of each certificate, less a retention amount (usually 10%), the “retention fund”
  • 18. Practical completion • On “practical completion” the architect confirms the works are substantially complete and the building is handed over to the employer • Half the retention fund is paid to the contractor and the “defects liability period” commences (usually 6 months) • At the end of this period a “snagging list” of outstanding work and discovered defects is given to the contractor who must correct them before the final certificate of completion is issued and the remainder of the retention fund is released. The contract is now complete.
  • 19. Management contract: very large projects Conception Development Realisation Management Project contractor appointed management at development stage to coordinate specialist suppliers and contractors
  • 20. Management really big projects: Olympics 2012 Many sites, many designers, many builders, many clients, absolutely fixed deadline July 27, 2012 Conception Development Realisation Project management
  • 21. Nothing is more complex than the Olympics Source: London 2012
  • 22. Summary • Contracts rarely run as smoothly as in theory – Building works are too unpredictable – The amount of work on the snagging list is not worth 5% to the contractor so he never does it – Agreement cannot always be achieved on who is responsible for a defect, is it the contractor, the designer, a nominated sub-contractor • However, if you know how a project should run, you have a good chance of managing the project in reality.